Contract No: HK/2015/01 Wanchai
Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing Work (Stage 3) Environmental Permit
no. EP-376/2009, Further Environmental
Permits No. FEP-01/376/2009 and FEP-02/376/2009 Quarterly Environmental Monitoring
and Audit Report
- NOV 2017 to JAN 2018 -
|
CLIENTS: |
|
Civil
Engineering and Development Department |
Lam Geotechnics
Limited 11/F Centre
Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
February 2018 |
2.2 Scope of the Project and Site Description
2.3 Project
Organization and Contact Personnel
2.4 Principal
Work and Activities
4.2. Air Quality Monitoring Results
5.4. Review of the Reasons for and the Implications of
Non-compliance
5.5. Summary of action taken in the event of and follow-up
on non-compliance
6. Complaints,
Notification of Summons and Prosecution
7. Cumulative
Construction Impact due to the Concurrent Projects
lIST
OF TABLES
Table 1 Principal Work Activities in the reporting
period
Table
2.1 Schedule 2
Designated Projects under this Project
Table
2.2 Contact Details
of Key Personnel
Table
2.3 Principal Work
Activities in the reporting period
Table 3.1 Noise Monitoring Stations
Table
3.2 Air Monitoring
Stations
Table 4.1 Noise Monitoring
Stations for Contract no. HK/2012/08
Table
4.2 Air Monitoring
Station for Contract no. HK/2012/08
Table 4.3 Details of Waste
Disposal for Contract no. HK/2012/08
Table 6.1 Cumulative
Statistics on Complaints
Table 6.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 3.1 Locations of Environmental Monitoring Stations and
Sensitive Receivers
lIST OF APPENDIces
Appendix 2.1 Environmental Mitigation Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix 4.1 Noise Monitoring Graphical Presentations
Appendix 4.2 Air Quality Monitoring Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix
6.1 Complaint Log
Appendix 8.1 Construction
Programme of Individual Contracts
Construction Activities for the
Reported Period
Contract no.
HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West
Table 1
Principal Work Activities in the reporting period
November 2017 |
December 2017 |
January 2018 |
· Drainage · Roadworks |
· Drainage · Roadworks |
· Drainage · Roadworks |
Noise Monitoring
Air Quality Monitoring
24hr TSP monitoring at CMA5b was
rescheduled from 11 Nov 2017 to 13 Nov 2017.
Complaints, Notifications of Summons
and Successful Prosecutions
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed take up the role as the
Environmental Team (ET) under Environmental Permit no. EP-376/2009 and Further
Environmental Permits no. FEP-01/376/2009 and FEP-02/376/2009 to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development Phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-458/2008).
1.1.2.
This report documents the finding of EM&A
works for Environmental Permit (EP) no.
EP-376/2009 and Further Environmental Permits no. FEP-01/376/2009 and
FEP-02/376/2009, during the period 27th October 2017 to 26th January 2018. The cut-off
date of reporting is the 26th of each reporting period.
Section
1 Introduction –
details the scope and structure of the report.
Section
2 Project
Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Monitoring
Requirements –
summarizes all monitoring parameters, monitoring locations, monitoring
frequency, duration and action
plan.
Section
4 Monitoring
Results – summarizes the monitoring results obtained
in the reporting period.
Section
5 Compliance
Audit – summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
6 Complaints, Notification of summons and Prosecution
– summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
7 Cumulative Construction Impact due to the
Concurrent Projects – summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Conclusion
2.1.1 Wan Chai
Development phase II and Central-Wan Chai Bypass (hereafter called “the
Project”) are Designated Project (DP) under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) has been approved on 11 December 2008.
2.2.1.
The design and construction of Wan Chai
Development Phase II and Central Wanchai Bypass involves the construction and
operation of primary and district distributor roads that is shown at Figure 2.1.
2.2.2. The key
purpose of the study area encompasses the Wan Chai
harbourfront area. The area starts at the boundary of Central Reclamation Phase
III (CRIII) at the west and connects to the existing Hung Hing Road at the
east. The scope of the project includes:
·
A
dual 2-lane primary distributor road, Road P2, approximately 0.6km in length;
and
·
Other
new primary and district distributor roads connecting to the slip roads of the
Central-Wan Chai Bypass with a total length of approximately 0.7km.
2.2.3.
The project also contains various Schedule 2 DP that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be
either constructed or operated. Table 2.1 summarises the DP under
this Project. Figure 2.1 shows the locations of these Schedule 2 DP.
Table
2.1 Schedule 2 Designated Project
under this Project
Item |
Designated Project |
EIAO Reference |
DP2
|
Road
P2 and other roads which are classified as primary/district distributor roads
|
Schedule
2, Part I, A.1 |
2.2.4.
The designated project work II (DP2) was
awarded to China State-Build King Joint Venture HK/2012/08 – Wan Chai
Development Phase II Central – Wan Chai Bypass at Wan Chai West as part of the
Project works by the Civil Engineering and Development Department (CEDD). The construction work under EP-376/2009 by Contract no. HK/2012/08 was
commenced on 13 May 2015.
2.3.1 Civil Engineering and Development Department and Highway Department are the
overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For
the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.3.2
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.2:
Table 2.2 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s
Representative for WDII |
Principal Resident
Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s
Representative for CWB |
Principal Resident
Engineer |
Mr. Peter Poon |
3922 3388 |
3912 3010 |
|
China State- Build
King Joint Venture |
Contractor under
Contract no. HK/2012/08 |
Project Director |
C. N.
LAI |
9106 5806 |
2877 1522 |
Project Manager |
Mr. Eddie Chung |
9189 8118 |
|||
Site Agent |
Mr. George Cheung |
9268 1918 |
|||
Environmental Officer |
Mr. James Ma |
9130 9549 |
|||
Ramboll Hong Kong Limited |
Independent Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics
Limited (For Enquiry) |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.1 During this reporting period, the principle work
activities of the contract is included as follows:
Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai
Bypass at Wan Chai West
Table
2.3 Principal Work Activities in the reporting period
November 2017 |
December 2017 |
January 2018 |
· Drainage · Roadworks |
· Drainage · Roadworks |
· Drainage · Roadworks |
2.4.2 Implementation status of the recommended mitigation
measures during this reporting period is presented in Appendix
2.1.
NOISE Monitoring Station
3.1.1.
The noise monitoring station for the Project is listed and shown in Table
3.1 and Figure 3.1. Appendix 3.1 shows the established Action/Limit
Levels for the monitoring works.
Table
3.1 Noise Monitoring Station
District |
Station |
Description |
Wan Chai |
M1a |
Footbridge for Ex-Harbour Road Sports Centre |
Noise Monitoring
Parameters, Frequency and Duration
3.1.2.
The
construction noise level shall be measured in terms of the A-weighted
equivalent continuous sound pressure level (Leq). Leq (30
minutes) shall be used as the monitoring parameter for the time period
between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq
(5 minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such
as L10 and L90 shall also be obtained for reference.
3.1.3.
Noise monitoring shall be carried out at all the designated monitoring
stations. The monitoring frequency shall depend on the scale of the
construction activities. The following is an initial guide on the regular
monitoring frequency for each station on a weekly basis when noise generating
activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
Monitoring Equipment
3.1.4. As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agrees to within 1.0 dB.
3.1.5. Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
Air Quality Monitoring Stations
3.2.1.
The air monitoring stations for the Project
are listed and shown in Table 3.2 and Figure 3.1. Appendix 3.1 shows the
established Action/Limit Levels for the monitoring works.
Table 3.2 Air Quality Monitoring
Stations
Station ID |
Monitoring Location |
CMA5b |
Pedestrian Plaza |
CMA6a |
WDII PRE Site Office |
Air Monitoring Parameters, Frequency and Duration
3.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
3.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
3.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring Equipment
3.2.5.
High
volume samplers (HVSs) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6
– 1.7 m3 per minute adjustable flow range;
·
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable
of providing a minimum exposed area of 406 cm2;
·
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped
with a shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped
with a flow recorder for continuous monitoring;
·
Provided
with a peaked roof inlet;
·
Incorporated
with a manometer;
·
Able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
Easily
changeable filter; and
·
Capable
of operating continuously for a 24-hour period.
3.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
Laboratory Measurement / Analysis
3.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
3.2.8.
Filter paper of size 8” x 10” shall be labelled
before sampling. It shall be a clean filter paper with no pinholes, and shall
be conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
3.2.9.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
3.2.10.
All the collected samples shall be kept in a
good condition for 6 months before disposal.
4.0.1.
The environmental monitoring will be implemented based on the division
of works areas of the designed project managed under the contract with FEP
applied by contractor. Overall layout
showing work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure
2.1 and Figure 3.1. The monitoring results are
presented in according to the Individual Contract(s).
4.0.2. In the reporting period, the concurrent
contract is:
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Wan Chai West.
4.1.1
Noise monitoring for project works under EP-376/2009 was commenced on 19
May 2015.
4.1.2
The proposed division of noise monitoring station is summarized in Table
4.1 below.
Table
4.1 Noise Monitoring Station for Contract no. HK/2012/08
Location ID |
District |
Description |
M1a |
Wan Chai |
Footbridge for Ex-Harbour Road Sports Centre |
4.1.3
Two limit level exceedances were recorded on 3 and 22 November 2017 in
November 2017 reporting month.
After the investigation, no construction
work under EP-376/2009 was conducted by Contract HK/2012/08 on 3 November 2017 around
the concerned location during the time of measurement while non WDII-CWB
excavation works immediately next to the monitoring station was observed as the
major noise contribution during monitoring. As such, the exceedance was
considered as non-Project related to Contract HK/2012/08.
After the investigation, no construction
work under EP-376/2009 was conducted by Contract HK/2012/08 on 22 November 2017
around the concerned location during the time of measurement while non WDII-CWB
breaking works immediately next to the monitoring station was observed as the
major noise contribution during monitoring. As such, the exceedance was
considered as non-Project related to Contract HK/2012/08.
4.1.4
Two limit level exceedances were recorded on 4 and 11 December 2017 in
December 2017 reporting month.
After the investigation, no construction work under EP-376/2009 was
conducted by Contract HK/2012/08 on 4 December 2017 around the concerned location
during the time of measurement while non WDII-CWB excavation works immediately
next to the monitoring station was observed as the major noise contribution
during monitoring. As such, the exceedance was considered as not related to
Project works under Contract HK/2012/08.
After the investigation, no construction work under EP-376/2009 was
conducted by Contract HK/2012/08 on 11 December 2017 around the concerned location
during the time of measurement while non WDII-CWB breaking works next to the
monitoring station was observed as the major noise contribution during
monitoring. As such, the exceedance was considered as not relate to Project works
under HK/2012/08.
4.1.5
Three limited level exceedances were recorded on 29 December 2017, 16
and 23 January 2018 in January 2018 reporting month.
After the investigation, no construction work under EP-376/2009 was
conducted by Contract HK/2012/08 on 29 December 2017 around the concerned location
during the time of measurement while non WDII-CWB excavation works immediately
next to the monitoring station was observed as the major noise contribution
during monitoring. As such, the exceedance was considered as not related to
Project works under Contract HK/2012/08.
After the investigation, no construction work under EP-376/2009 was
conducted by Contract HK/2012/08 on 16 January 2018 around the concerned location
during the time of measurement while non WDII-CWB breaking works next to the
monitoring station was observed as the major noise contribution during
monitoring. As such, the exceedance was considered as not relate to Project
works under HK/2012/08.
After the investigation, no construction work under EP-376/2009 was
conducted by Contract HK/2012/08 on 23 January 2018 around the concerned location
during the time of measurement while non WDII-CWB breaking works next to the
monitoring station was observed as the major noise contribution during
monitoring. As such, the exceedance was considered as not relate to Project
works under HK/2012/08.
4.1.6
The noise monitoring results measured in this reporting period are
reviewed and summarized. Details of continuous noise monitoring results and
graphical presentation can be referred to Appendix 4.1
4.2.1 Air
Quality monitoring for project works under EP-376/2009 was commenced on 16 May
2015.
4.2.2 The
proposed division of air quality monitoring stations are summarized in Table
4.2 below.
Table 4.2
Air
Quality Monitoring Station for Contract no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian Plaza |
CMA6a |
WDII PRE Site Office |
4.2.3
One 1hr TSP action level exceedance was recorded at CMA5b – Pedestrian
Plaza on 1 November 2017 in November 2017 reporting month.
Road and drains works for P2 road was undertaken by the Contractor of
HK/2012/08 around the monitoring location on the monitoring date and no
particular observation regarding air quality impact was observed during
sampling. Nevertheless, non WDII-CWB Project construction activities was
observed opposite to the monitoring station on the monitoring date. Meanwhile,
it was reported that the ambient air quality was adversely affected by
accumulation of air pollutant influenced by the meteorological condition on the
monitoring date. In view of the above, the exceedance was considered to be
non-project related and potentially contributed by ambient air quality
condition. Nevertheless, the Contractor of HK/2012/08 was reminded to provide
regularly dust suppression measures if any potential dust generating operation around
the concerned location would be required to avoid any potential cumulative air
quality impact.
4.2.4
Two 1hr TSP action level exceedances and one 1hr TSP limit level
exceedances was recorded at CMA5b – Pedestrian Plaza on 24 November 2017 in
November 2017 reporting month.
Road and drains works for P2 road was undertaken by the Contractor of
HK/2012/08 around the monitoring location on the monitoring date and no
particular observation regarding air quality impact was observed during
sampling. Nevertheless, non WDII-CWB Project construction activities was observed
opposite to the monitoring station on the monitoring date. Meanwhile, according
to the EPD monitoring record, highest pollutant concentration was recorded
during the monitoring date at Causeway Bay monitoring station across a seven
days period. In view of the above, the exceedance was considered to be non-project
related and potentially contributed by ambient air quality condition.
Nevertheless, the Contractor of HK/2012/08 was reminded to provide regularly
dust suppression measures if any potential dust generating operation around the
concerned location would be required to avoid any potential cumulative air
quality impact.
Road and drains works for P2 road was
undertaken by the Contractor of HK/2012/08 around the monitoring location on
the monitoring date and no particular observation regarding air quality impact was
observed during sampling. Meanwhile, non WDII-CWB Project construction
activities was observed opposite to the monitoring station on the monitoring
date. According to the EPD monitoring record, AQHI recorded at the Causeway Bay
station was recorded as Lv4 - Lv7 on 11 December 2017 and recorded as Lv6 on 12
December 2017 during the monitoring period indicating the adverse ambient
condition. In addition, similar elevation in TSP level were recorded across the
same period on 11 December 2017 at other Project AQM stations including CMA6a
at Wan Chai and CMA3a at Causeway Bay area suggesting overall air quality
within the district was under influence of ambient pollutant. In view of the
above, the exceedance was considered to be not related to the Project works
under Contract HK/2012/08 and potentially contributed by ambient air quality
condition. Nevertheless, the Contractor of HK/2012/08 was advised to strengthen
the overall dust suppression control measures to ensure all dusty surface are
dampened to avoid potential dust emission.
4.2.6
One 1hr TSP action level exceedances was recorded at CMA5b – Pedestrian
Plaza on 23 December 2017 in December 2017 reporting month.
Road and drains works for P2 road was undertaken by the Contractor of
HK/2012/08 around the monitoring location on the monitoring date and no
particular observation regarding air quality impact was observed during
sampling. Meanwhile, non WDII-CWB Project excavation material handling was
observed opposite to the monitoring station on the monitoring date. In
addition, elevated PM2.5 and PM10 level were recorded at the EPD Causeway Bay
monitoring station across the monitoring period suggesting the meteorological
condition at the time of monitoring may not favor the dispersion of ambient air
pollutant within the district and hence affecting the air quality. In view of
the above, the exceedance was considered to be not related to the Project works
under Contract HK/2012/08 and potentially contributed by ambient air quality
condition. Nevertheless, the Contractor of HK/2012/08 was advised to strengthen
the overall dust suppression control measures to ensure all dusty surface are
dampened to avoid potential dust emission.
4.2.7
One 1hr TSP action level exceedance were recorded at CMA5b – Pedestrian
Plaza on 29 December 2017 in January 2018 reporting month.
Road and drains works for P2 road was undertaken by the Contractor of
HK/2012/08 around the monitoring location on the monitoring date and no
particular observation regarding air quality impact was observed during
sampling. Meanwhile, non WDII-CWB Project construction works was observed
opposite to the monitoring station on the monitoring date. In view of the
above, the exceedance was considered to be not related to the Project works
under Contract HK/2012/08 and potentially contributed by ambient air quality
condition and nearby traffic exhaust. Nevertheless, the Contractor of
HK/2012/08 was advised to strengthen the overall dust suppression control
measures to ensure all dusty surface are dampened to avoid potential dust
emission.
4.2.8
The air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix 4.2.
4.3.1
No Inert and Non-inert C&D wastes disposed in
this reporting period. Details of the waste flow table are summarized in Table
4.3.
Table 4.3 Details
of Waste Disposal for Contract no. HK/2012/08
Waste Type |
Quantity this quarter |
Cumulative
Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
NIL |
NIL |
Inert C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Non-inert C&D materials disposed, m3 |
NIL |
NIL |
NIL |
Non-inert C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Chemical waste disposed, kg |
NIL |
NIL |
NIL |
5.0.1. The Event Action Plan for construction
noise and air quality are presented in Appendix 5.1.
5.1.1 Two limit level exceedances were
recorded on 3 and 22 November 2017 in November 2017 reporting month. After the
investigation, the exceedances were concluded as non-project related.
5.1.2 Two limit level exceedances were
recorded on 4 and 11 December 2017 in December 2017 reporting month. After the
investigation, the exceedances were concluded as non-project related.
5.1.3 Three limit exceedances were recorded on
29 December 2017, 16 and 23 January 2018 in January 2018 reporting month. After
the investigation, the exceedances were concluded as non-project related.
5.2.1
One 1hr TSP action level exceedance was recorded at CMA5b – Pedestrian
Plaza on 1 November 2017 in November 2017 reporting month. After the
investigation, the exceedance was concluded as non-project related.
5.2.2
Two 1hr TSP action level exceedances and one 1hr TSP limit level
exceedances was recorded at CMA5b – Pedestrian Plaza on 24 November 2017 in
November 2017 reporting month. After the investigation, the exceedance was
concluded as non-project related.
5.2.3
One 24hr TSP action level exceedance and two 1hr TSP action level
exceedance were recorded at CMA5b – Pedestrian Plaza on 11, 12 and 23 December
2017 in December 2017 reporting month. After the investigation, the exceedances
were concluded as non-Project related.
5.2.4
One 1-hr TSP action level exceedance was recorded at CMA5b – Pedestrian Plaza
on 29 December 2017 in January 2018 reporting month. After the investigation,
the exceedances were concluded as non-Project related.
5.3.1
There was no non-compliance from the site audits in the reporting period. During
environmental site inspections conducted during the reporting period, minor
deficiencies were noted.
5.4.1
There was no non-compliance from the site audits in the reporting
period.
5.5.1
There was no particular action taken since no
project-related non-compliance was recorded from the site audits and
environmental monitoring in the reporting period.
6.0.1. No
environmental complaint received in this reporting quarter.
6.0.2.
The details of cumulative complaint log
and summary of complaints are presented in Appendix 6.1.
6.0.3. No notification
of summons or prosecution was received in the reporting period. Cumulative statistic on complaints and
successful prosecutions are summarized in Table 6.1 and Table 6.2 respectively.
Table 6.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works (May 2015) to last reporting
quarter |
0 |
November 2017 to January 2018 |
0 |
Project-to-Date |
0 |
Table 6.2 Cumulative Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1. According
to the Condition 3.4 of the EP-376/2009, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III (CRIII), Wan Chai
Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern
Corridor Link projects (IECL) and Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel).
7.0.2. According
to the Final EM&A report of Central Reclamation Phase III (CRIII) for
Contract HK 12/02, the major construction activities were completed by end of
January 2014 and no construction activities were undertaken thereafter and the
water quality monitoring was completed in October 2011. As such, it is considered that there were no
cumulative construction impact due to the concurrent activities of the current
projects with the Central Reclamation Phase III (CRIII) undertaken by
contractor HK12/02 in the reporting period.
7.0.3.
According to the construction programme of
Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III
area roadworks, back-filling, reinstatement of culvert K, drainage, trimming of
rock level and reinstatement of planter at P1 Road were performed in January
2018 reporting month. As no project related exceedance were recorded during the reporting
period, cumulative construction impact due to the concurrent activities of the
current projects with the Central Reclamation Phase III (CRIII) was considered
as insignificant.
7.0.4. According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activities under Wan Chai Development Phase II
were road and drains construction and backfilling works at Wan Chai West and
Wan Chai East. The major construction activities under Central-Wan Chai Bypass
and Island Eastern Corridor Link Projects were drainage works and ventilation
building construction at Central; temporary reclamation removal and
reinstatement works at Causeway Bay, road works at Victoria Park; bridge
construction, approach ramp construction and building construction at North
Point area in the reporting period. In addition, other non-Wan Chai Development
Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects was
observed undertaken at Wan Chai North and North Point area.
7.0.5. No significant
air quality impact from construction activities was anticipated in the
reporting period. Besides, no project related exceedance was recorded during air
quality and noise environmental monitoring events in the reporting period. Thus,
it is evaluated that the cumulative construction impact from the concurrent
projects including Central Reclamation Phase III (CRIII), Wan Chai Development
Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link
projects (IECL) was insignificant.
8.0.1. The EM&A programme was carried out
in accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
8.0.2. No non-compliance and no prosecutions were received
during the reporting period.
8.0.3. Mitigation measures according to the environmental mitigation
implementation schedule and the EIA were generally implemented by the
Contractor in this reporting period. Environmental site audit was conducted by
the Environmental Team and the Independent Environmental Checker and no
cumulative environmental impact was identified in the reporting period. Hence,
the EM&A programme was considered effective and shall be maintained.
8.0.4. The
construction programmes of individual contracts are provided in Appendix 8.1.