Contract No: HK/2015/01 Wanchai
Development Phase II and Central Wanchai Bypass Sampling,
Field Measurement and Testing Work (Stage 3) Environmental Permit
no. EP-376/2009, Further Environmental
Permits No. FEP-01/376/2009 and FEP-02/376/2009 Quarterly Environmental Monitoring
and Audit Report
- AUG 2018 to OCT 2018 -
|
CLIENTS: |
|
Civil Engineering
and Development Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
23 November 2018 |
2.2 Scope of the Project and Site Description
2.3 Project
Organization and Contact Personnel
2.4 Principal
Work and Activities
4.2. Air Quality Monitoring Results
5.4. Review of the Reasons for and the Implications of
Non-compliance
5.5. Summary of action taken in the event of and follow-up
on non-compliance
6. Complaints,
Notification of Summons and Prosecution
7. Cumulative
Construction Impact due to the Concurrent Projects
lIST
OF TABLES
Table 1 Principal Work Activities in the reporting
period
Table 2.1 Schedule 2 Designated Projects
under this Project
Table 2.2 Contact Details of Key
Personnel
Table 2.3 Principal Work Activities in
the reporting period
Table 3.1 Noise Monitoring Stations
Table 3.2 Air Monitoring Stations
Table 4.1 Noise Monitoring
Stations for Contract no. HK/2012/08
Table 4.2 Air Monitoring Station for
Contract no. HK/2012/08
Table 4.3 Details of Waste
Disposal for Contract no. HK/2012/08
Table 6.1 Cumulative
Statistics on Complaints
Table 6.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure 2.1 Project
Layout
Figure 2.2 Project Organization Chart
Figure 3.1 Locations of
Environmental Monitoring Stations and Sensitive Receivers
lIST OF APPENDIces
Appendix 2.1 Environmental Mitigation
Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix 4.1 Noise
Monitoring Graphical Presentations
Appendix 4.2 Air Quality
Monitoring Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix
6.1 Complaint Log
Appendix 8.1 Construction
Programme of Individual Contracts
Construction Activities for the Reported Period
Contract no. HK/2012/08 – Wan Chai Development
Phase II – Central- Wan Chai Bypass at Wan Chai West
Table 1
Principal Work Activities in the reporting period
August 2018 |
September 2018 |
October 2018 |
· Drainage · Roadworks |
· Drainage · Roadworks |
· Drainage · Roadworks |
Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of Summons and Successful Prosecutions
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed take up the role as the
Environmental Team (ET) under Environmental Permit no. EP-376/2009 and Further
Environmental Permits no. FEP-01/376/2009 and FEP-02/376/2009 to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development Phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-458/2008).
1.1.2.
This report documents the finding of EM&A
works for Environmental Permit (EP) no.
EP-376/2009 and Further Environmental Permits no. FEP-01/376/2009 and
FEP-02/376/2009, during the period 27th July 2018
to 26th October 2018. The cut-off date of reporting is the 26th
of each reporting period.
Section 1 Introduction – details the scope
and structure of the report.
Section 2 Project
Background
– summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section 3 Monitoring
Requirements – summarizes all
monitoring parameters, monitoring locations, monitoring frequency, duration and action
plan.
Section 4 Monitoring
Results
– summarizes the monitoring results obtained in the reporting period.
Section 5 Compliance
Audit
– summarizes the auditing of monitoring results, all exceedances
environmental parameters.
Section 6 Complaints, Notification of summons and Prosecution
–
summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 7 Cumulative Construction Impact due to the
Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1 Wan Chai
Development phase II and Central-Wan Chai Bypass (hereafter called “the
Project”) are Designated Project (DP) under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) has been approved on 11 December 2008.
2.2.1.
The design and construction of Wan Chai
Development Phase II and Central Wanchai Bypass involves the construction and
operation of primary and district distributor roads that is shown at Figure 2.1.
2.2.2. The key
purpose of the study area encompasses the Wan Chai
harbourfront area. The area starts at the boundary of Central Reclamation Phase
III (CRIII) at the west and connects to the existing Hung Hing Road at the
east. The scope of the project includes:
·
A dual 2-lane
primary distributor road, Road P2, approximately 0.6km in length; and
·
Other new
primary and district distributor roads connecting to the slip roads of the
Central-Wan Chai Bypass with a total length of approximately 0.7km.
2.2.3.
The project also contains various Schedule 2 DP that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be
either constructed or operated. Table 2.1 summarises the DP under
this Project. Figure 2.1 shows the locations of these Schedule 2 DP.
Table
2.1 Schedule 2 Designated Project
under this Project
Item |
Designated Project |
EIAO Reference |
DP2 |
Road P2 and
other roads which are classified as primary/district distributor roads |
Schedule 2,
Part I, A.1 |
2.2.4.
The designated project work II (DP2) was
awarded to China State-Build King Joint Venture HK/2012/08 – Wan Chai
Development Phase II Central – Wan Chai Bypass at Wan Chai West as part of the
Project works by the Civil Engineering and Development Department (CEDD). The construction work under EP-376/2009 by Contract no. HK/2012/08 was
commenced on 13 May 2015.
2.3.1 Civil Engineering and Development Department and Highway Department are the
overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For
the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.3.2
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.2:
Table 2.2 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for
WDII |
Principal Resident Engineer |
Ms. Gloria Tang |
2587 1778 |
2587 1877 |
Engineer’s Representative for
CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912 3010 |
|
China State- Build King Joint
Venture |
Contractor under Contract no.
HK/2012/08 |
Project Director |
C. N. LAI |
9106 5806 |
2877 1522 |
Project Manager |
Mr. Eddie Chung |
9189 8118 |
|||
Site Agent |
Mr. George Cheung |
9268 1918 |
|||
Environmental Officer |
Mr. James Ma |
9130 9549 |
|||
Ramboll Hong Kong Limited |
Independent Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited (For Enquiry) |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.1 During this reporting period, the principle work
activities of the contract is included as follows:
Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai
Bypass at Wan Chai West
Table
2.3 Principal Work Activities in the reporting period
August 2018 |
September 2018 |
October 2018 |
· Drainage · Roadworks |
· Drainage · Roadworks |
· Drainage · Roadworks |
2.4.2 Implementation status of the recommended mitigation
measures during this reporting period is presented in Appendix
2.1.
NOISE Monitoring Station
3.1.1.
The noise monitoring station for the Project is listed and shown in Table
3.1 and Figure 3.1. Appendix 3.1 shows the established Action/Limit
Levels for the monitoring works.
Table
3.1 Noise Monitoring Station
District |
Station |
Description |
Wan Chai |
M1a |
Footbridge for Ex-Harbour Road Sports Centre |
Noise Monitoring Parameters, Frequency and Duration
3.1.2.
The construction noise level shall
be measured in terms of the A-weighted equivalent continuous sound pressure
level (Leq). Leq (30 minutes) shall be used as the
monitoring parameter for the time period between 0700 and 1900 hours on normal
weekdays. For all other time periods, Leq (5 minutes) shall be
employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for
data auditing, statistical results such as L10 and L90 shall also be obtained
for reference.
3.1.3.
Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One set of
measurements between 0700 and 1900 hours on normal weekdays.
Monitoring Equipment
3.1.4. As referred
to in the Technical Memorandum ™ issued under the NCO, sound level meters in
compliance with the International Electrotechnical Commission Publications 651:
1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying
out the noise monitoring. Immediately prior to and following each noise
measurement the accuracy of the sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agrees to within 1.0 dB.
3.1.5. Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
Air Quality Monitoring Stations
3.2.1.
The air monitoring stations for the Project
are listed and shown in Table 3.2 and Figure 3.1. Appendix 3.1 shows the
established Action/Limit Levels for the monitoring works.
Table 3.2 Air Quality Monitoring
Stations
Station ID |
Monitoring
Location |
CMA5b |
Pedestrian Plaza |
CMA6a |
WDII PRE Site Office |
Air Monitoring Parameters, Frequency and Duration
3.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
3.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
3.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring Equipment
3.2.5.
High
volume samplers (HVSs) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6 – 1.7 m3
per minute adjustable flow range;
·
Equipped with a
timing / control device with +/- 5 minutes accuracy for 24 hours operation;
·
Installed with
elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable of providing
a minimum exposed area of 406 cm2;
·
Flow control
accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped with a
shelter to protect the filter and sampler;
·
Incorporated with an
electronic mass flow rate controller or other equivalent devices;
·
Equipped with a flow
recorder for continuous monitoring;
·
Provided with a
peaked roof inlet;
·
Incorporated with a
manometer;
·
Able to hold and
seal the filter paper to the sampler housing at horizontal position;
·
Easily changeable
filter; and
·
Capable of operating
continuously for a 24-hour period.
3.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
Laboratory Measurement / Analysis
3.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS
accredited.
3.2.8.
Filter paper of size 8” x 10” shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
3.2.9.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
3.2.10.
All the collected samples shall be kept in a
good condition for 6 months before disposal.
4.0.1.
The environmental monitoring will be implemented based on the division
of works areas of the designed project managed under the contract with FEP
applied by contractor. Overall layout
showing work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure
2.1 and Figure 3.1. The monitoring results are
presented in according to the Individual Contract(s).
4.0.2. In the reporting period, the concurrent
contract is:
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Wan Chai West.
4.1.1 Noise monitoring for project works
under EP-376/2009 was commenced on 19 May 2015.
4.1.2 The proposed division of noise
monitoring station is summarized in Table 4.1 below.
Table
4.1 Noise Monitoring Station for Contract no. HK/2012/08
Location ID |
District |
Description |
M1a |
Wan Chai |
Footbridge for Ex-Harbour Road Sports Centre |
4.1.3 No action or limit level exceedance was
recorded in this reporting quarter.
4.1.4 The noise monitoring results
measured in this reporting period are reviewed and summarized. Details of
continuous noise monitoring results and graphical presentation can be referred
to Appendix 4.1
4.2.1 Air
Quality monitoring for project works under EP-376/2009 was commenced on 16 May
2015.
4.2.2 The
proposed division of air quality monitoring stations are summarized in Table
4.2 below.
Table 4.2
Air
Quality Monitoring Station for Contract no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian Plaza |
CMA6a |
WDII PRE Site Office |
4.2.3
Due to
interruption of electricity, the 24hr TSP was rescheduled from 19 September, 6
October 2018 to 20 September, 8 October 2018 at CMA5b – Pedestrian Plaza.
4.2.4
Due to
interruption of electricity, the 24hr TSP was rescheduled from 19 September
2018 to 20 September 2018 at CMA6a – Contractor HK/2012/08 Site Office.
4.2.5
No action
or limit level exceedance was recorded at CMA5b – Pedestrian Plaza and CMA6a –
WDII PRE Site Office in this reporting quarter.
4.2.6
The air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix 4.2.
4.3.1
No Inert and Non-inert C&D wastes disposed in
this reporting period. Details of the waste flow table are summarized in Table
4.3.
Table 4.3 Details
of Waste Disposal for Contract no. HK/2012/08
Waste Type |
Quantity this quarter |
Cumulative
Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
NIL |
NIL |
NIL |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Non-inert
C&D materials disposed, m3 |
NIL |
NIL |
NIL |
Non-inert
C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Chemical
waste disposed, kg |
NIL |
NIL |
NIL |
5.0.1. The Event Action Plan for construction
noise and air quality are presented in Appendix 5.1.
5.1.1 No action or limit level exceedance was
recorded in this reporting quarter.
5.2.1
No action
or limit level exceedance was recorded at CMA5b – Pedestrian Plaza and CMA6a –
WDII PRE Site Office in this reporting quarter.
5.3.1
There was no non-compliance from the site audits
in the reporting period. During environmental site inspections conducted during
the reporting period, minor deficiencies were noted.
5.4.1
There
was no non-compliance from the site audits in the reporting period.
5.5.1
There was no particular action taken since no
project-related non-compliance was recorded from the site audits and
environmental monitoring in the reporting period.
6.0.1. No
environmental complaint received in this reporting quarter.
6.0.2.
The details of cumulative complaint log and summary of complaints are
presented in Appendix 6.1.
6.0.3. No notification
of summons or prosecution was received in the reporting period. Cumulative statistic on complaints and
successful prosecutions are summarized in Table 6.1 and Table 6.2 respectively.
Table 6.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works (May 2015) to last
reporting quarter |
0 |
August 2018 to October 2018 |
0 |
Project-to-Date |
0 |
Table 6.2 Cumulative Statistics on Successful Prosecutions
Environmental
Parameters |
Cumulative
No. Brought Forward |
No. of
Successful Prosecutions this quarter (Offence Date) |
Cumulative
No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1. According
to the Condition 3.4 of the EP-376/2009, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III (CRIII), Wan Chai
Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern
Corridor Link projects (IECL) and Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel).
7.0.2. According
to the Final EM&A report of Central Reclamation Phase III (CRIII) for
Contract HK 12/02, the major construction activities were completed by end of
January 2014 and no construction activities were undertaken thereafter and the
water quality monitoring was completed in October 2011. As such, it is considered that there were no
cumulative construction impact due to the concurrent activities of the current
projects with the Central Reclamation Phase III (CRIII) undertaken by
contractor HK12/02 in the reporting period.
7.0.3.
According to the construction programme of
Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III
area include roadworks, drainage and seawall coping were performed in October
2018 reporting period. As
no project related exceedance were recorded during the reporting period,
cumulative construction impact due to the concurrent activities of the current
projects with the Central Reclamation Phase III (CRIII) was considered as insignificant.
7.0.4. According to the
construction programme of Wan Chai Development Phase II, Central-Wan Chai
Bypass and Island Eastern Corridor Link projects, the major construction
activities under Wan Chai Development Phase II were road and drains construction
and removal of temporary reclamation at Wan Chai. The major construction
activities under Central-Wan Chai Bypass and Island Eastern Corridor Link
Projects were ventilation building ABWF works and junction modification at
Central; reinstatement works along Causeway Bay Typhoon Shelter, road works and
landscape works at Victoria Park; bridge construction, approach ramp
construction, landscape deck construction, drainage construction and
ventilation building ABWF work at North Point area in the reporting period. In
addition, other non-Wan Chai Development Phase II, Central-Wan Chai Bypass and
Island Eastern Corridor Link projects were observed undertaken at Wan Chai
North and North Point area.
7.0.5. No significant
air quality impact from construction activities was anticipated in the
reporting period. Besides, no project related exceedance was recorded during air
quality and noise environmental monitoring events in the reporting period. Thus,
it is evaluated that the cumulative construction impact from the concurrent
projects including Central Reclamation Phase III (CRIII), Wan Chai Development
Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link
projects (IECL) was insignificant.
8.0.1. The EM&A programme was carried out
in accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
8.0.2. No non-compliance and no prosecutions were received
during the reporting period.
8.0.3. Mitigation measures according to the environmental mitigation
implementation schedule and the EIA were generally implemented by the
Contractor in this reporting period. Environmental site audit was conducted by
the Environmental Team and the Independent Environmental Checker and no
cumulative environmental impact was identified in the reporting period. Hence,
the EM&A programme was considered effective and shall be maintained.
8.0.4. The
construction programmes of individual contracts are provided in Appendix 8.1.