Contract No: Hy/2019/18 Wanchai
Development Phase II and Central Wanchai Bypass Sampling,
Field Measurement and Testing Work (Stage 4) Environmental Permit no. EP-376/2009, Further Environmental Permits No. FEP-01/376/2009 and
FEP-02/376/2009 Quarterly
Environmental Monitoring
and
Audit Report
- FEBRUARY 2020 to APRIL 2020 -
|
CLIENTS: |
|
Civil Engineering
and Development Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
19 May 2020 |
2.2 Scope
of the Project and Site Description
2.3 Project Organization and Contact Personnel
2.4 Principal Work and Activities
4.2. Air Quality Monitoring Results
5.4. Review of the Reasons for and the Implications of
Non-compliance
5.5. Summary of action taken in the event of and follow-up
on non-compliance
6. Complaints,
Notification of Summons and Prosecution
7. Cumulative
Construction Impact due to the Concurrent Projects
lIST
OF TABLES
Table 1 Principal Work Activities in the
reporting period
Table 2.1 Schedule 2 Designated Projects
under this Project
Table 2.2 Contact Details of Key
Personnel
Table 2.3 Principal Work Activities in
the reporting period
Table 3.1 Noise Monitoring Stations
Table 3.2 Air Monitoring Stations
Table 4.1 Noise Monitoring Stations for
Contract no. HK/2012/08
Table 4.2 Air Monitoring Station for
Contract no. HK/2012/08
Table 4.3 Details of Waste Disposal for
Contract no. HK/2012/08
Table 6.1 Cumulative
Statistics on Complaints
Table 6.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure 2.2 Project Organization Chart
Figure 3.1 Locations of Environmental
Monitoring Stations and Sensitive Receivers
lIST OF APPENDIces
Appendix 2.1 Environmental Mitigation
Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 8.1 Construction Programme of
Individual Contracts
Construction
Activities for the Reported Period
Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan
Chai Bypass at Wan Chai West
Table 1
Principal Work Activities in the reporting period
February |
March |
April |
· Landscaping |
· Landscaping |
· Landscaping |
Noise
Monitoring
Air Quality
Monitoring
Complaints,
Notifications of Summons and Successful Prosecutions
1.1.1. Lam Geotechnics Limited (LGL) has been appointed take up the
role as the Environmental Team (ET) under Environmental Permit no. EP-376/2009
and Further Environmental Permits no. FEP-01/376/2009 and FEP-02/376/2009 to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development Phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008).
1.1.2.
This
report documents the finding of EM&A works for Environmental Permit (EP) no.
EP-376/2009 and Further Environmental Permits no. FEP-01/376/2009 and
FEP-02/376/2009, during the period 27th January 2020 to 26th April 2020.
The cut-off date of reporting is the 26th of each reporting period.
Section 1 Introduction – details the scope and structure of the report.
Section 2 Project Background – summarizes background and scope of the project,
site description, project organization and contact details of key personnel
during the reporting period.
Section 3 Monitoring Requirements –
summarizes all monitoring parameters, monitoring locations, monitoring
frequency, duration and action plan.
Section 4 Monitoring Results – summarizes the monitoring results obtained in the
reporting period.
Section 5 Compliance Audit – summarizes the auditing of monitoring results, all exceedances
environmental parameters.
Section 6 Complaints, Notification of
summons and Prosecution –
summarizes the cumulative statistics on complaints, notification of summons and
prosecution
Section 7 Cumulative Construction
Impact due to the Concurrent Projects – summarizes the relevant cumulative construction impact due to the
concurrent activities of the concurrent Projects.
Section 8 Conclusion
2.1.1 Wan Chai Development phase II and
Central-Wan Chai Bypass (hereafter called “the Project”) are Designated Project
(DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) has been approved on
11 December 2008.
2.2.1. The design and construction of Wan
Chai Development Phase II and Central Wanchai Bypass involves the construction
and operation of primary and district distributor roads that is shown at Figure
2.1.
2.2.2.
The
key purpose of the study area encompasses the Wan Chai harbourfront area. The
area starts at the boundary of Central Reclamation Phase III (CRIII) at the
west and connects to the existing Hung Hing Road at the east.
The scope of the project includes:
·
A dual 2-lane primary distributor road, Road P2,
approximately 0.6km in length; and
·
Other new primary and district distributor roads
connecting to the slip roads of the Central-Wan Chai Bypass with a total length
of approximately 0.7km.
2.2.3. The project also contains various Schedule 2 DP that, under
the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or
operated. Table 2.1 summarises the DP under this Project. Figure
2.1 shows the locations of
these Schedule 2 DP.
Table
2.1 Schedule 2 Designated Project under
this Project
Item |
Designated
Project |
EIAO
Reference |
DP2 |
Road P2 and other roads which are classified as
primary/district distributor roads |
Schedule 2, Part I, A.1 |
2.2.4. The designated project work II
(DP2) was awarded to China State-Build King Joint Venture HK/2012/08 – Wan Chai
Development Phase II Central – Wan Chai Bypass at Wan Chai West as part of the
Project works by the Civil Engineering and Development Department (CEDD). The construction work
under EP-376/2009 by Contract no. HK/2012/08 was commenced on 13 May 2015.
2.3.1
Civil Engineering and Development Department and Highway
Department are the
overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai
Bypass respectively. For
the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.3.2
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are
summarized in Table 2.2:
Table 2.2 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer’s Representative for WDII |
Resident Engineer |
Mr. Eliot Liu |
3519 9167 |
2587 1877 |
China State- Build King Joint Venture |
Contractor under Contract no. HK/2012/08 |
Project
Director |
C. N. LAI |
9106
5806 |
2877
1522 |
Site
Agent |
Mr. George Cheung |
9268 1918 |
|||
Environmental
Officer |
Mr. James
Ma |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Y.L. Ho |
9856
5669 |
|||
Ramboll Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882
3939 |
2882 3331 |
2.4.1
During this reporting period, the principle
work activities of the contract is included as follows:
Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai
Bypass at Wan Chai West
Table
2.3 Principal Work Activities in the reporting period
February |
March |
April |
· Landscaping |
· Landscaping |
· Landscaping |
2.4.2
Implementation status of the recommended
mitigation measures during this reporting period is presented in Appendix 2.1.
NOISE
Monitoring Station
3.1.1.
The noise monitoring station
for the Project is listed and shown in Table 3.1 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the monitoring
works.
Table
3.1 Noise Monitoring Station
District |
Station |
Description |
Wan Chai |
M1a |
Footbridge
for Ex-Harbour Road Sports Centre |
Noise
Monitoring Parameters, Frequency and Duration
3.1.2. The construction noise level shall be
measured in terms of the A-weighted equivalent continuous sound pressure level
(Leq). Leq (30 minutes) shall be used as the monitoring
parameter for the time period between 0700 and 1900 hours on normal weekdays.
For all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.3. Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One set of measurements between 0700 and 1900 hours
on normal weekdays.
Monitoring
Equipment
3.1.4.
As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agrees to within 1.0 dB.
3.1.5.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
Air Quality
Monitoring Stations
3.2.1. The air monitoring stations for
the Project are listed and shown in Table 3.2 and Figure 3.1. Appendix 3.1 shows the
established Action/Limit Levels for the monitoring works.
Table 3.2 Air
Quality Monitoring
Stations
Station ID |
Monitoring
Location |
CMA5b |
Pedestrian Plaza |
CMA6a |
WDII PRE Site Office |
Air Monitoring Parameters, Frequency and Duration
3.2.2. One-hour and 24-hour TSP levels
should be measured to indicate the impacts of construction dust on air quality.
The 24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
3.2.3. All relevant data including
temperature, pressure, weather conditions, elapsed-time meter reading for the
start and stop of the sampler, identification and weight of the filter paper,
and any other local atmospheric factors affecting or affected by site
conditions, etc., shall be recorded down in detail.
3.2.4. For regular impact monitoring, the
sampling frequency of at least once in every six-days, shall be strictly
observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour
TSP monitoring, the sampling frequency of at least three times in every
six-days should be undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5.
High volume samplers
(HVSs) in compliance with the following specifications shall be used for
carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6 – 1.7 m3 per minute adjustable flow
range;
·
Equipped with a timing / control device with +/- 5
minutes accuracy for 24 hours operation;
·
Installed with elapsed-time meter with +/- 2
minutes accuracy for 24 hours operation;
·
Capable of providing a minimum exposed area of 406
cm2;
·
Flow control accuracy: +/- 2.5% deviation over
24-hour sampling period;
·
Equipped with a shelter to protect the filter and
sampler;
·
Incorporated with an electronic mass flow rate
controller or other equivalent devices;
·
Equipped with a flow recorder for continuous
monitoring;
·
Provided with a peaked roof inlet;
·
Incorporated with a manometer;
·
Able to hold and seal the filter paper to the
sampler housing at horizontal position;
·
Easily changeable filter; and
·
Capable of operating continuously for a 24-hour
period.
3.2.6. Initial calibration of dust
monitoring equipment shall be conducted upon installation and thereafter at
bi-monthly intervals. The transfer standard shall be traceable to the
internationally recognized primary standard and be calibrated annually. The
concern parties such as IEC shall properly document the calibration data for
future reference. All the data should be converted into standard temperature
and pressure condition.
Laboratory Measurement /
Analysis
3.2.7. A clean laboratory with constant
temperature and humidity control, and equipped with necessary measuring and
conditioning instruments to handle the dust samples collected, shall be
available for sample analysis, and equipment calibration and maintenance. The
laboratory should be HOKLAS accredited.
3.2.8. Filter paper of size 8” x 10”
shall be labelled before sampling. It shall be a clean filter paper with no
pinholes, and shall be conditioned in a humidity-controlled chamber for over
24-hours and be pre-weighed before use for the sampling.
3.2.9. After sampling, the filter paper
loaded with dust shall be kept in a clean and tightly sealed plastic bag. The
filter paper shall then be returned to the laboratory for reconditioning in the
humidity controlled chamber followed by accurate weighing by an electronic
balance with readout down to 0.1 mg. The balance shall be regularly calibrated
against a traceable standard.
3.2.10. All the collected samples shall be
kept in a good condition for 6 months before disposal.
4.0.1.
The
environmental monitoring will be implemented based on the division of works
areas of the designed project managed under the contract with FEP applied by
contractor. Overall layout showing work
areas of various contracts, latest status of work commencement and monitoring
stations is shown in Figure
2.1 and Figure 3.1. The monitoring results are presented
in according to the Individual Contract(s).
4.0.2. In the reporting period, the concurrent
contract is:
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Wan Chai West.
4.1.1 Noise
monitoring for project works under EP-376/2009 was commenced on 19 May 2015.
4.1.2 The
proposed division of noise monitoring station is summarized in Table
4.1 below.
Table 4.1 Noise Monitoring Station for Contract no.
HK/2012/08
Location ID |
District |
Description |
M1a |
Wan Chai |
Footbridge for Ex-Harbour Road Sports Centre |
4.1.3
With respect to WDII RSS confirmed that the
remaining works under HK/2012/08 would be tree planting works at EP-376/2009
area only, considered that no adverse noise impact would be contributed by the
tree planting works, the respective noise monitoring at noise monitoring
station M1a - Footbridge at EX-Wanchai Harbour Road Sports Centre was temporary
suspended from 27 March 2019 onwards.
4.1.4 The noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of continuous noise monitoring results and graphical
presentation can be referred to Appendix
4.1
4.2.1
Air
Quality monitoring for project works under EP-376/2009 was commenced on 16 May
2015.
4.2.2
The
proposed division of air quality monitoring stations are summarized in Table
4.2 below.
Table
4.2 Air Quality Monitoring Station for
Contract no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian
Plaza |
CMA6a |
WDII
PRE Site Office |
4.2.3
With respect to WDII RSS confirmed that the
remaining works under HK/2012/08 would be tree planting works at EP-376/2009
area only, considered that no adverse air quality impact would be contributed
by the tree planting works, the respective air quality monitoring at air
quality monitoring stations CMA5b – Pedestrian Plaza and CMA6a – Contractor
HK/2012/08 Site Office were temporary suspended from 27 March 2019 onwards.
4.3.1 No Inert and Non-inert C&D wastes disposed in
this reporting period. Details of the waste flow table are summarized in Table
4.3.
Table 4.3 Details
of Waste Disposal for Contract no. HK/2012/08
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
NIL |
NIL |
NIL |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Non-inert
C&D materials disposed, m3 |
NIL |
NIL |
NIL |
Non-inert
C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Chemical
waste disposed, kg |
NIL |
NIL |
NIL |
5.0.1. The Event Action Plan for construction
noise and air quality are presented in Appendix 5.1.
5.1.1
With
respect to WDII RSS confirmed that the remaining works under HK/2012/08 would
be tree planting works at EP-376/2009 area only, considered that no adverse
noise impact would be contributed by the tree planting works, the respective
noise monitoring at noise monitoring station M1a - Footbridge at EX-Wanchai
Harbour Road Sports Centre was temporary suspended from 27 March 2019 onwards.
5.2.1 With respect to
WDII RSS confirmed that the remaining works under HK/2012/08 would be tree
planting works at EP-376/2009 area only, considered that no adverse air quality
impact would likely be contributed by the tree planting works, the respective
air quality monitoring at air quality monitoring stations CMA5b – Pedestrian
Plaza and CMA6a – Contractor HK/2012/08 Site Office were temporary suspended
from 27 March 2019 onwards.
5.3.1
There was no non-compliance from the site audits in the reporting period. During
environmental site inspections conducted during the reporting period, minor
deficiencies were noted.
5.3.2
As WDII RSS confirmation of construction
works completion on 1 April 2020 and agreed with IEC on 3 April 2020, the
weekly environmental site inspection for Contract no.HK/2012/08 under
EP-376/2009 was suspended from 3 April 2020 onward.
5.4.1
There was no non-compliance from the site
audits in the reporting period.
5.5.1
There
was no particular action taken since no project-related non-compliance was
recorded from the site audits and environmental monitoring in the reporting
period.
6.0.1.
No
environmental complaint received in this reporting quarter.
6.0.2.
The details of cumulative complaint log and summary of complaints are
presented in Appendix 6.1.
6.0.3. No notification
of summons or prosecution was received in the reporting period. Cumulative statistic on complaints and
successful prosecutions are summarized in Table 6.1 and Table 6.2 respectively.
Table 6.1 Cumulative Statistics on Complaints
Reporting
Period |
No. of
Complaints |
Commencement works (May 2015) to last reporting quarter |
0 |
February 2020 to April 2020 |
0 |
Project-to-Date |
0 |
Table 6.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this
quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1.
According
to the Condition 3.4 of the EP-376/2009, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III (CRIII), Wan Chai
Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern
Corridor Link projects (IECL) and Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel).
7.0.2.
According
to the Final EM&A report of Central Reclamation Phase III (CRIII) for
Contract HK 12/02, the major construction activities were completed by end of
January 2014 and no construction activities were undertaken thereafter and the
water quality monitoring was completed in October 2011. As such, it is considered that there were no
cumulative construction impact due to the concurrent activities of the current
projects with the Central Reclamation Phase III (CRIII) undertaken by contractor
HK12/02 in the reporting period.
7.0.3. According to the construction programme
of Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III
area, no works was conducted in April 2020 reporting period. In view of the above, the cumulative
construction impact due to the Central Reclamation Phase III (CRIII) was not
anticipated.
7.0.4.
According to the construction programme of
Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern
Corridor Link projects, no construction works uner Wan Chai Development Phase
II was conducted at Wan Chai. The major construction activities under
Central-Wan Chai Bypass and Island Eastern Corridor Link Projects were
ventilation building ABWF works at Central; road works, drainage improvement
work, utility diversion works and landscape works at Victoria Park; bridge
noise enclosure installation works, road works, drainage works, soft landscape
works and ventilation building ABWF work at North Point area in the reporting
period. In addition, other non-Wan Chai Development Phase II, Central-Wan Chai
Bypass and Island Eastern Corridor Link projects were observed undertaken at
Wan Chai North and North Point area.
7.0.5.
As
relevant site mitigation measures for air quality and construction noise were
implemented, no significant air quality impact and noise impact from
construction activities was concluded in the reporting period. Besides, no
finding in related to air quality and noise impact was recorded during the
weekly site inspection of EP-376 are in the reporting period. Thus, it is
evaluated that the cumulative construction impact from the concurrent projects
including Central Reclamation Phase III (CRIII), Wan Chai Development Phase II
(WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects
(IECL) was insignificant.
8.0.1. The EM&A programme was carried out
in accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
8.0.2. No non-compliance and no prosecutions were received
during the reporting period.
8.0.3. Mitigation measures according to the environmental
mitigation implementation schedule and the EIA were generally implemented by
the Contractor in this reporting period. Environmental site audit was conducted
by the Environmental Team and the Independent Environmental Checker and no
cumulative environmental impact was identified in the reporting period. Hence,
the EM&A programme was considered effective and shall be maintained.
8.0.4. The
construction programmes of individual contracts are provided in Appendix 8.1.