Contract No: HK/2011/07 Wanchai
Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing Work (Stage 2) Environmental Permit
no. EP-122/2002/D Quarterly Environmental Monitoring
and Audit Report
- NOVEMBER 2013 to JANUARY
2014 -
|
CLIENTS: |
|
Civil
Engineering and Development Department |
Lam Geotechnics
Limited 11/F Centre
Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
17 February
2014 |
2.2 Scope of the Project and Site
Description
2.3 Project
Organization and Contact Personnel
2.4 Principal
Work and Activities
5.4. Review
of the Reasons for and the Implications of Non-compliance
5.5. Summary
of action taken in the event of and follow-up on non-compliance
6. Complaints, Notification of Summons
and Prosecution
7. Cumulative Construction Impact due to
the Concurrent Projects
lIST
OF TABLES
Table I
Principal Work Activities in the reporting period
Table 2.1 Schedule 2 Designated Projects under this Project
Table 2.2 Contact Details of Key Personnel
Table 2.3 Principal Work Activities in the reporting period
Table 3.1 Continuous Noise Monitoring Stations
Table 3.2 Air Monitoring Stations
Table 4.1 Continuous Noise Monitoring Stations for Contract no. HK/2012/08
Table 4.2 Air Monitoring Station for Contract no. HK/2012/08
Table 4.3 Details of Waste Disposal for Contract no. HK/2012/08
Table 6.1 Cumulative Statistics
on Complaints
Table 6.2 Cumulative Statistics
on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 3.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 2.1 Environmental Mitigation Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix 4.1 Noise Monitoring Graphical Presentations
Appendix 4.2 Air Quality Monitoring Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix
6.1 Complaint Log
Appendix 8.1 Construction
Programme of Individual Contracts
Construction Activities for the
Reported Period
Contract no.
HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West
Table
I Principal Work Activities in the reporting
period
November 2013 |
December 2013 |
January 2014 |
· Site preparation works · Site survey · Temporary works · Concrete breaking · Stockpiling of fill materials · Culvert K diversion |
· Site preparation works · Site survey · Temporary works · Concrete breaking · Stockpiling of fill materials · Culvert K diversion |
· Site preparation works · Site survey · Temporary works · Stockpiling of fill materials · Culvert K diversion · Diaphragm wall preparation works |
Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of Summons
and Successful Prosecutions
1.1.1.
Lam Geotechnics
Limited (LGL) has been appointed to work as the Environmental Team (ET) under
Environmental Permit no. EP-122/2002/D to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report Central Reclamation Phase III - Studies, Site Investigation, Design and
Construction (Register No.: AEIAR-040/2001) since 1 May 2013.
1.1.2.
This report documents the finding of EM&A works for
Environmental Permit (EP) no. EP-122/2002/D, during
the period from 1st November 2013 to
31st January 2014.
Section 1 Introduction –
details the scope and structure of the report.
Section 2 Project
Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements –
summarizes all monitoring parameters, monitoring locations, monitoring
frequency, duration and action
plan.
Section 4 Monitoring Results –
summarizes the monitoring results obtained in the reporting period.
Section 5 Compliance
Audit – summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution –
summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section 8 Conclusion
2.1.1 Central
Reclamation Phase III - Studies, Site Investigation, Design and Construction
(hereafter called “the Project”) are Designated Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental
Impact Assessment (EIA) Reports for Central Reclamation Phase III - Studies,
Site Investigation, Design and Construction (Register No. AEIAR-040/2001) has
been approved on 31 August 2001.
2.2.1.
The design and construction of Central
Reclamation Phase III involves the permanent reclamation and construction and
operation of a trunk road and its road tunnel that is shown at Figure 2.1.
2.2.2.
The key purpose of the study area encompasses the area of Victoria Harbour to the southeast of
the new Outlying Islands Ferry Piers and north of Edinburgh Place and Lung Wui
Road. The area extends eastward to Fenwick Pier Street and the Fleet Arcade,
and includes the existing GPO, Star Ferry Piers, Queens Pier, City Hall, PLA
Headquarters, Hong Kong Red Cross Headquarters building and the Tamar Site. The scope of the Central Reclamation, Phase III includes:
·
Reclamation
and seawalls, roads and associated services, North Island Line Protection Works
and Advance Trunk Road Tunnel (ATRT) for the CWB;
·
Reprovisioning
of Star Ferry Pier, public landing steps, wallah wallah moorings, and motor
boat/launch operators' kiosks;
·
External
cooling water systems which consist of the cooling water pumping shells for
future developments, and the reprovisioning of existing cooling water pumping
stations and associated pipework systems and E&M works;
·
Reprovisioning
of existing Leisure and Cultural Services Department (LCSD)'s facilities;
·
Provision
of a flood relief path, stormwater culvert extensions, upgrading of hinterland
stormwater drainage resulting from the reclamation, demolition of the existing
waterfront structures and necessary landscaping;
·
The
Hong Kong Station Extended Overrun Tunnel (EOT) and associated ventilation
structures entrusted for construction within the CRIII works;
·
Reprovisioning
of the Government Heliport at the Wan Chai PCWA and reprovisioning of the Wan
Chai PCWA at Chai Wan Basin.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be
either constructed or operated. Table 2.1 summarises the four
individual DPs under this Project. Figure 2.1 shows the locations of these
Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects under
this Project
Item |
Designated Project |
EIAO Reference |
DP1
|
Central-Wanchai
Bypass (CWB) |
Schedule
2, Part I, A.7 |
DP2
|
Road
P2 and other roads which are classified as primary/district distributor roads
|
Schedule
2, Part I, A.1 |
DP3
|
Reclamation
works |
Schedule
2, Part I, C.1 |
DP4 |
The
North Island Line (NIL) Protection Works within CRIII |
Schedule
2, Part I, A.7 |
2.2.4.
The designated project work I (DP1) was
awarded to China State-Leader Joint Venture HK/2012/08 as part of the Project
works by the Civil Engineering and Development Department (CEDD). The construction work under Contract no. HK/2012/08 was commenced on 27
May 2013.
2.3.1 Civil Engineering and Development Department is the overall project controllers for the Central Reclamation Phase III Project. For
the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.3.2
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.2:
Table 2.2 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912 3010 |
|
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. Andrew TSE |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Victor WU |
9193
8871 |
|||
Deputy
Project Manager |
Mr. George CHEUNG |
9268
1918 |
|||
Site
Agent |
Mr. Paul LUI |
9095
7922 |
|||
Environmental
Officer |
Mr. James MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Ching Man, CHAN |
6050
4919 |
|||
ENVIRON Hong Kong
Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics
Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882
3939 |
2882 3331 |
2.4.1 During this reporting period, the principle work
activities of the contract is included as follows:
Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai
Bypass at Wan Chai West
Table
2.3 Principal Work Activities in the
reporting period
November 2013 |
December 2013 |
January 2014 |
· Site preparation works · Site survey · Temporary works · Concrete breaking · Stockpiling of fill materials · Culvert K diversion |
· Site preparation works · Site survey · Temporary works · Concrete breaking · Stockpiling of fill materials · Culvert K diversion |
· Site preparation works · Site survey · Temporary works · Stockpiling of fill materials · Culvert K diversion · Diaphragm wall preparation works |
2.4.2 Implementation status of the recommended mitigation
measures during this reporting period is presented in Appendix 2.1.
NOISE Monitoring Stations
3.1.1.
The continuous noise monitoring station for the Project is listed and
shown in Table 3.1 and Figure 3.1. Appendix 3.1 shows the established Action/Limit
Levels for the monitoring works.
Table 3.1 Continuous Noise
Monitoring Stations
District |
Station |
Description |
Central |
ACL3 |
City Hall |
Noise Monitoring
Parameters, Frequency and Duration
3.1.2. Continuous
24-hour noise monitoring shall be carried out at the
designated monitoring stations. The following is an initial guide on the
regular monitoring frequency for each station on a 24 hours daily basis when
noise generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
3.1.3. If
construction works are extended to include works during the hours of 1900 –
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
3.1.4. As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agrees to within 1.0 dB.
3.1.5. Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
3.1.6. The sound
level meter shall be checked using an acoustic calibrator generating a known
sound pressure level at a known frequency before deployment to the site and
during each site visit. Measurements will be accepted as valid only if the
calibration level from before and after the noise measurement agrees to within
1.0 dB.
Air Quality Monitoring Stations
3.2.1.
The air monitoring stations for the Project
are listed and shown in Table 3.2 and Figure 3.1.
Appendix 3.1 shows the
established Action/Limit Levels for the monitoring works.
Table 3.2 Air Monitoring Stations
Station ID |
Monitoring Location |
ACL1 |
City Hall |
ACL2 |
PLA
Barracks1 |
ACL2a |
Contractor HK/2012/08 Site Office |
1Remarks: Monitoring at ACL2 was temporarily suspended from 14th November 2013 and
subsequently relocated to monitoring station ACL2a on 7 December 2013 due to safety
considerations with respect to the large scale renovation undertaking at PLA
Headquarter.
Air Monitoring Parameters, Frequency and Duration
3.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
3.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
3.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring Equipment
3.2.5.
High
volume samplers (HVSs) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6
– 1.7 m3 per minute adjustable flow range;
·
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable
of providing a minimum exposed area of 406 cm2;
·
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped
with a shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped
with a flow recorder for continuous monitoring;
·
Provided
with a peaked roof inlet;
·
Incorporated
with a manometer;
·
Able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
Easily
changeable filter; and
·
Capable
of operating continuously for a 24-hour period.
3.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
Laboratory Measurement / Analysis
3.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
3.2.8.
Filter paper of size 8” x 10” shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
3.2.9.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
3.2.10.
All the collected samples shall be kept in a
good condition for 6 months before disposal.
4.0.1.
The environmental monitoring will be implemented based on the division
of works areas of each designed project managed under different contracts with
separate FEP applied by individual contractors.
Overall layout showing work areas of various contracts, latest status of
work commencement and monitoring stations is shown in Figure
2.1 and Figure 3.1. The monitoring results are
presented in according to the Individual Contract(s).
4.0.2. In the reporting period, the concurrent
contract is:
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Wan Chai West.
4.1.1
Due to safety concerned, the location of the continuous noise monitoring
station at City Hall was finely adjusted to the roof of the City Hall, Low
Block on 1 May 2013.
4.1.2
The proposed division of noise monitoring stations is summarized in
Table 4.1 below.
Table
4.1 Continuous Noise Monitoring
Stations for Contract no. HK/2012/08
Location ID |
District |
Description |
ACL3 |
Central |
City Hall |
Remarks: Continuous
noise monitoring results and graphical presentation for ACL3 during restricted
hours and night time period are for information only.
4.1.3 There were
seven limit level exceedances recorded on 10, 23 and 27 December 2013 and 13
and 28 January 2014 during daytime in the reporting period. The exceedances
were concluded as not project-related.
4.1.4 On 10 Dec
2013, after checking work activities of contractor HK/2012/08, it was found
that no major noisy activities were performed during the recorded period. As
the exceedance was not continuous, it was considered as non-project related and
contributed by nearby traffic noise from Lung Wo Road.
4.1.5 On 23 and
27 Dec 2013, after checking work activities of contractor HK/2012/08, it was
found that no major noisy activities were performed during the recorded period.
In addition, on-going repairing works of the air conditioning system on the
roof of lower block of City Hall adjacent to monitoring station were noted. The
exceedances were not continuous and were considered as non-project related and
contributed by adjacent repairing works and nearby traffic.
4.1.6 On 13 Jan
2014, after checking work activities of contractor HK/2012/08, it was found
that no major noisy activities were performed during the recorded period. Flag
raising ceremony near the lower block of City Hall was observed on 13 Jan 2014.
As the exceedances were non-continuous, they were considered as non-project
related and contributed by the ceremony and nearby traffic.
4.1.7 On 28 Jan
2014, after checking work activities of contractor HK/2012/08, it was found
that no major noisy activities were performed during the recorded period.
Lifting works for City Hall's renovation were observed during the monitoring
period and the exceedance was not continuous. As such, the exceedance was not
contributed by Project works and considered as non-project related.
4.1.8
Continuous noise monitoring results measured in this reporting period
are reviewed and summarized. Details of continuous noise monitoring results and
graphical presentation can be referred to Appendix 4.1 .
4.2.1 The
proposed division of air monitoring stations are summarized in Table 4.2 below.
Table 4.2
Air
Monitoring Station for Contract no. HK/2012/08
Station |
Description |
ACL1 |
City Hall |
ACL2 |
PLA Barracks1 |
ACL2a |
Contractor HK/2012/08 Site Office |
1Remarks:
Monitoring at ACL2 was
temporarily suspended from 14th November 2013 and subsequently relocated to
monitoring station ACL2a on 7 December 2013 due to safety considerations with
respect to the large scale renovation undertaking at PLA Headquarter.
4.2.2
1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were
conducted at ACL1 – City Hall and ACL2 – PLA Barracks (ACL2a Contractor
HK/2012/08 Site Office since 7 December 2013) on every six days basis.
4.2.3
No action or limit level exceedance was recorded at ACL1 – City Hall, ACL2
PLA Barracks and ACL2a Contractor HK/2012/08 Site Office in the reporting
period.
4.2.4
Due to the large scale renovation works at People’s Liberation Army
Headquarter, a Proposal for Relocation of Air Quality Monitoring Station at
People’s Liberation Army Headquarter (ACL2) was formally submitted to EPD on
4th November, 2013.
4.2.5
Air Quality Monitoring at ACL2 was temporarily suspended during the
period from 14th November, 2013 to 3rd December, 2013.
4.2.6
The Proposal for Relocation of Air Quality Monitoring Station at
People’s Liberation Army Headquarter (ACL2) was approved by EPD on 27 November
2013.
4.2.7
According to the approved proposal for relocation of Air Quality
Monitoring station, the action and limit levels of ACL2a shall adopt the reference
monitoring result from the baseline air monitoring report for EP/364/2009 in 22
April 2010 in which approved by EPD.
4.2.8
The air quality monitoring at ACL2a – Contractor HK/2012/08 Site Office was
commenced on 7 December 2013.
4.2.9
Due to lack of electricity supply, the 24hr TSP at ACL2a was rescheduled
from 20 Jan 2014 to 21 Jan 2014 and from 24 Jan 2014 to 25 Jan 2014.
4.2.10
The air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.2.
4.3.1 Only
Non-inert C&D wastes were disposed in this reporting period. Details of the
waste flow table are summarized in Table 4.3.
Table 4.3 Details of Waste Disposal for Contract no. HK/2012/08
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
288 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Non-inert C&D materials disposed, m3 |
35 |
110 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Chemical waste disposed, kg |
NIL |
NIL |
NIL |
5.0.1. The Event Action Plan for construction
noise and air quality are presented in Appendix 5.1.
5.1.1
There were seven limit level exceedances recorded
at ACL3 – City Hall in this reporting period. The
exceedances were concluded as not project-related.
5.2.1
No action or limit level exceedance was recorded at ACL1 – City Hall, ACL2
– PLA Barracks and ACL2a Contractor HK/2012/08 Site Office in this reporting
period.
5.3.1
There was no non-compliance from the site audits in the reporting period. During
environmental site inspections conducted during the reporting period, minor
deficiencies were noted.
5.4.1
There was no non-compliance from the site audits in the reporting period.
5.5.1
There was no particular action taken since no
project-related non-compliance was recorded from the site audits and
environmental monitoring in the reporting period.
6.0.1. There was no environmental complaint
received in this reporting period.
6.0.2.
The details of cumulative complaint log
and summary of complaints are presented in Appendix
6.1.
6.0.3. No notification
of summons or prosecution was received in the reporting period. Cumulative statistic on complaints and
successful prosecutions are summarized in Table 6.1 and Table 6.2 respectively.
Table 6.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
May 2013 – July 2013 |
0 |
August 2013 – October 2013 |
0 |
November 2013 – January 2014 |
0 |
Project-to-Date |
0 |
Table 6.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1. This
section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation
Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass
(CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel).
7.0.2.
According to the Monthly EM&A reports (October,
November and December 2013) of Central Reclamation Phase III
(CRIII) for Contract HK 12/02, remaining soft landscaping work behind GPO
boundary wall, remaining footpath construction at Edinburgh Place, installation
of directional sign at Road P2, removal of two existing E&M drawpits at
East Bound Road P2 near Road D8 and additional surface drain at ACL CER office
compound were performed in the reporting period. The water
quality monitoring was completed in October 2011 and no Project-related exceedance
was recorded for air and noise monitoring.
It can be concluded that cumulative construction impact due to the
concurrent activities of the current projects with the Central Reclamation
Phase III (CRIII) undertaken by contractor HK12/02 was insignificant.
7.0.3. According
to the construction programme of Wan Chai Development Phase II, Central-Wan
Chai Bypass and Island Eastern Corridor Link projects, the major construction
activity under Wan Chai Development Phase II were marine works at HKCEC areas,
cross-harbour Watermains, Fresh Watermains and Cooling Watermains Installations,
tunnel works at Wan Chai East. The major construction activities under
Central-Wan Chai Bypass and Island Eastern Corridor Link Projects were ELS work, tunnel
water proofing works and tunnel construction at TS4 and cut and cover
tunnel construction and dismantling of struts at TPCWAE. Bridge construction and
tunnel works at Central Interchange, ELS segment launching works and IEC
parapet demolition at North Point area. The major
environmental impact was water quality impact at Causeway Bay and Wan Chai.
Land-based construction activities were excavation, tunnel
works at TS2, ELS work and water proofing works, tunnel construction at TS4 and cut
and cover tunnel construction and dismantling of struts at TPCWAE, tunnel
works at Central and ELS work at North Point and tunnel works at Wan Chai East
in the reporting period.
7.0.4. The major
environmental impacts generated from tunnel works at Central and tunnel works
at Wan Chai East, IECL and Causeway Bay Typhoon Shelter were undertaken in the
reporting period. No significant air impact from construction activities was anticipated
in the reporting period. Besides, no project-related exceedances were recorded
during the air and noise environmental monitoring events in the reporting
period. Thus, it is evaluated that the cumulative construction impact from the
concurrent projects including Wan Chai Development Phase II was insignificant.
8.0.1. The EM&A programme was carried out
in accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
8.0.2. No non-compliances were noted and no
prosecutions were received during the reporting period.
8.0.3. The
construction programmes of individual contracts are provided in Appendix 8.1.