Contract No: HK/2009/05

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 1)

 

Environmental Permit no. EP-356/2009,

Further Evironmental permit nos. fep-01/356/2009, fep-02/356/2009 and FEP-03/356/2009

 

Monthly Environmental Monitoring & Audit Report

 

- < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:21">August< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:21"> September 2010 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

CHECKED by:



 

 

 

 

 

                        

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

11< cite="mailto:Lam20100204" datetime="2010-10-07T16:58">8< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:21">9 < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:21">September October 2010


Table of contents

 

EXECUTIVE SUMMARY.. iv< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">iv< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">iv< cite="mailto:Lam20100204" datetime="2010-09-08T19:01">iv

1.   Introduction.. 1

1.1    Scope of the Report 1

1.2    Structure of the Report 1

2.   Project Background.. 3< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">3< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">3< cite="mailto:Lam20100204" datetime="2010-09-08T19:01">3

2.1    Background. 3< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">3< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">3< cite="mailto:Lam20100204" datetime="2010-09-08T19:01">3

2.2    Scope of the Project and Site Description. 3< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">3< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">3< cite="mailto:Lam20100204" datetime="2010-09-08T19:01">3

2.3    Division of the Project Responsibility. 4< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">4< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">4< cite="mailto:Lam20100204" datetime="2010-09-08T19:01">4

2.4    Project Organization and Contact Personnel 5< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">5< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">5< cite="mailto:Lam20100204" datetime="2010-09-08T19:01">5

3.   status of regulatory compliance. 9< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">9< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">9< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">10< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">9

3.1    Status of Environmental Licensing and Permitting under the Project 9< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">9< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">9< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">10< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">9

4.   Monitoring Requirements. 15< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">15< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">14< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">15< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">14

4.1    Noise Monitoring. 15< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">15< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">14< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">15< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">14

4.2    Air Monitoring. 16< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">16< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">15< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">16< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">15

4.3    Water Quality Monitoring. 18< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">18< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">17< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">18< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">17

5.   Monitoring Results. 22< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">22< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">21< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">22< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">21

5.1    Noise Monitoring Results. 22< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">22< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">21< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">22< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">21

5.2    Air Monitoring Results. 23< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">23< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">22< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">23< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">22

5.3    Water Monitoring Results. 24< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">24< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">23< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">24< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">23

5.4    Waste Monitoring Results. 26< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">26< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">25< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">27< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">26

6.   Compliance Audit. 29< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">29< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">28< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">30< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">29

6.1    Noise Monitoring. 29< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">29< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">28< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">30< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">29

6.2    Air Monitoring. 29< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">29< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">28< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">30< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">29

6.3    Water Quality Monitoring. 29< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">29< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">28< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">30< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">29

6.4    Review of the Reasons for and the Implications of Non-compliance. 31< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">30< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">29< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">31< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">30

6.5    Summary of action taken in the event of and follow-up on non-compliance. 31< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">31< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">30< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">31< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">30

7.   Cumulative Construction Impact due to the Concurrent Projects. 32< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">32< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">31< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">32< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">31

8.   Site Inspection.. 33< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">33< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">32< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">33< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">32

9.   Complaints, Notification of Summons and Prosecution.. 36< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">36< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">35< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">36< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">35

10.  Conclusion.. 37< cite="mailto:Lam20100204" datetime="2010-10-08T11:55">37< cite="mailto:mansonyeung" datetime="2010-10-07T21:24">36< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">37< cite="mailto:mansonyeung" datetime="2010-09-04T13:05">36


lIST OF TABLES

 

Table I      Summary of Water Quality Monitoring Exceedances in Reporting Month

Table 2.1    Schedule 2 Designated Projects under this Project

Table 2.2   Details of Individual Contracts under the Project

Table 2.3   Contact Details of Key Personnel

Table 3.1   Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.2   Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/11

Table 3.3   Summary of submission status under FEP-01/356/2009 Condition

Table 3.4   Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.5   Summary of submission status under FEP-02/356/2009 Condition

Table 3.6   Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.7   Summary of submission status under FEP-03/356/2009 Condition

Table 4.1   Noise Monitoring Station

Table 4.2   Air Monitoring Station

Table 4.3    Marine Water Quality Stations for Water Quality Monitoring

Table 4.4   Marine Water Quality Monitoring Frequency and Parameters

Table 5.1    Noise Monitoring Stations for Contract no. HY/2009/11

Table 5.2    Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02

Table 5.3    Air Monitoring Stations for Contract no. HY/2009/11

Table 5.4    Air Monitoring Stations for Contract no. HK/2009/01

Table 5.5    Air Monitoring Station for Contract no. HK/2009/02

Table 5.6    Water Monitoring Stations for Contract no. HY/2009/11

Table 5.7    Water Monitoring Stations for Contract no. HK/2009/01

Table 5.8    Water Monitoring Stations for Contract no. HK/2009/02

Table 5.9    Summary of Water Quality Monitoring Exceedances in Reporting Month

Table 5.10  Details of Waste Disposal for Contract no. HY/2009/11

Table 5.11  Details of Waste Disposal for Contract no. HK/2009/01

Table 5.12  Details of Waste Disposal for Contract no. HK/2009/02

Table 8.1   Summary of Environmental Inspections for Contract no. HY/2009/11

Table 8.2    Summary of Environmental Inspections for Contract no. HK/2009/01

Table 8.3    Summary of Environmental Inspections for Contract no. HK/2009/02

Table 9.1   Cumulative Statistics on Complaints

Table 9.2   Cumulative Statistics on Successful Prosecutions

Table 10.1  Construction Activities and Recommended Mitigation Measures in Coming Reporting Month

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table I < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of Water Quality Monitoring Exceedances in Reporting Month< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 2.1 < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Schedule 2 Designated Projects under this Project< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 2.2< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Details of Individual Contracts under the Project< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 2.3< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Contact Details of Key Personnel< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 3.1< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of the current status on licences and/or permits on environmental protection pertinent to the Project< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 3.2< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/11< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 3.3< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of submission status under FEP-01/356/2009 Condition< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 3.4< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 3.5< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of submission status under FEP-02/356/2009 Condition< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 3.6< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 3.7< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of submission status under FEP-03/356/2009 Condition< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 4.1< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Noise Monitoring Station< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 4.2< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Air Monitoring Station< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 4.3 < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Marine Water Quality Stations for Water Quality Monitoring< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 4.4< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Marine Water Quality Monitoring Frequency and Parameters< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.1 < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Noise Monitoring Stations for Contract no. HY/2009/11< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.2 < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.3 < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Air Monitoring Stations for Contract no. HY/2009/11< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.4 < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Air Monitoring Stations for Contract no. HK/2009/01< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.5 < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Air Monitoring Station for Contract no. HK/2009/02< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.6 < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Water Monitoring Stations for Contract no. HY/2009/11< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.7 < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Water Monitoring Stations for Contract no. HK/2009/01< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.8 < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Water Monitoring Stations for Contract no. HK/2009/02< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.9 < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of Water Quality Monitoring Exceedances in Reporting Month< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.10< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Details of Waste Disposal for Contract no. HY/2009/11< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.11< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Details of Waste Disposal for Contract no. HK/2009/01< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.12< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Details of Waste Disposal for Contract no. HK/2009/02< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 8.1< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of Environmental Inspections for Contract no. HY/2009/11< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 8.2 < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of Environmental Inspections for Contract no. HK/2009/01< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 8.3 < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of Environmental Inspections for Contract no. HK/2009/02< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 9.1< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Cumulative Statistics on Complaints< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 9.2< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Cumulative Statistics on Successful Prosecutions< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 10.1< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Construction Activities and Recommended Mitigation Measures in Coming Reporting Month< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 10.2< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  < cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">

 

 

lIST OF FIGUREs

 

Figure 2.1     Project Layout

Figure 2.2     Project Organization Chart

Figure 4.1      Locations of Environmental Monitoring Stations

 

 

lIST OF APPENDIces

 

Appendix 3.1   Environmental Mitigation Implementation Schedule

Appendix 4.1   Action and Limit Level

Appendix 4.2   Copies of Calibration Certificates

Appendix 5.1   Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2   Noise Monitoring Results and Graphical Presentations

Appendix 5.3   Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4   Water Quality Monitoring Results and Graphical Presentations

Appendix 6.1   Event Action Plans

Appendix 6.2   Summary for Notification of Exceedance< cite="mailto:Lam20100204" datetime="2010-09-07T20:05"> 

Appendix 9.1   Complaint Log

Appendix 10.1  Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

         i.            This is the Environmental Monitoring and Audit (EM&A) Monthly Report  /span>< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:21">  /span>September < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:21">August 2010 for the Project of < cite="mailto:Lam20100204" datetime="2010-10-12T17:39">Contract No. HK/2009/05 –Wanchai Development Phase II and Central Wanchai Bypass< cite="mailto:Lam20100204" datetime="2010-10-12T17:39"> - < cite="mailto:Lam20100204" datetime="2010-10-12T17:39">Sampling, Field Measurement and Testing Work (Stage 1)Wan Chai Development Phase II and Central-Wanchai Bypass under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009 and FEP-03/356/2009< cite="mailto:Lam20100204" datetime="2010-10-12T17:50">.. < cite="mailto:Lam20100204" datetime="2010-10-12T17:50"> /span>This report presents the environmental monitoring findings and information recorded during the period 28th < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:22">July August 2010 to 27th < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:22">August September 2010. The cut-off date of reporting is at 27th of each reporting month.

 

Construction Activities for the Reported Period

       ii.            During this reporting period, the major work activities for Contract no. HY/2009/11 included:

< cite="mailto:Lam20100204" datetime="2010-09-03T15:01"> -           < cite="mailto:Lam20100204" datetime="2010-09-03T15:01"> < cite="mailto:Lam20100204" datetime="2010-09-03T15:01">

 -           Floating Out of Caisson Seawall,

 -           Installation of Caisson Seawall,

 -           Dredging works,

 -           Reclamation works,

 -           Construction & installation of Seawall Block,

 -           Works for Fenders and rubber steps and

< cite="mailto:Lam20100204" datetime="2010-10-07T17:00"> -           Pre-casting works for coping< cite="mailto:Lam20100204" datetime="2010-10-07T17:00">Construction of Rock Mound,

< cite="mailto:Lam20100204" datetime="2010-10-07T17:00"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:00">Floating Out of Caisson Seawall,

< cite="mailto:Lam20100204" datetime="2010-10-07T17:00"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:00">Installation of Caisson Seawall,

< cite="mailto:Lam20100204" datetime="2010-10-07T17:00"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:00">Dredging works,

< cite="mailto:Lam20100204" datetime="2010-10-07T17:00"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:00">Laying of geo-textile,

< cite="mailto:Lam20100204" datetime="2010-09-07T14:14"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:00">Drainage Works and< cite="mailto:Lam20100204" datetime="2010-10-07T17:00"> < cite="mailto:Lam20100204" datetime="2010-10-07T17:00">Seawall Block Installation< cite="mailto:Lam20100204" datetime="2010-09-07T14:14">

< cite="mailto:mansonyeung" datetime="2010-09-04T12:14">Construction of Rock Mound,

< cite="mailto:mansonyeung" datetime="2010-09-04T12:14"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T12:14">Floating Out of Caisson Seawall,

< cite="mailto:mansonyeung" datetime="2010-09-04T12:14"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T12:14">Installation of Caisson Seawall,

< cite="mailto:mansonyeung" datetime="2010-09-04T12:14"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T12:14">Dredging works,< cite="mailto:mansonyeung" datetime="2010-09-04T12:14">

< cite="mailto:mansonyeung" datetime="2010-09-04T12:14"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T12:14">Filling works< cite="mailto:mansonyeung" datetime="2010-09-04T12:14">

< cite="mailto:mansonyeung" datetime="2010-09-04T12:14"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T12:14">Laying of geo-textile,

< cite="mailto:mansonyeung" datetime="2010-09-04T12:14"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T12:14">Drainage Works and

 -           < cite="mailto:mansonyeung" datetime="2010-09-04T12:14">Seawall Block Installation

 

      iii.            During this reporting period, the major work activities for Contract no. HK/2009/01 included:

< cite="mailto:Lam20100204" datetime="2010-09-03T14:58"> -           < cite="mailto:Lam20100204" datetime="2010-09-03T14:58"> < cite="mailto:Lam20100204" datetime="2010-09-03T14:58">

< cite="mailto:Lam20100204" datetime="2010-09-07T14:18"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:18">Erection of interim Engineer’s Principal Office at Works areas WA2 was completed for moving-in on 5 Aug 10.

 -           Modification of CATV combine service inspection chamber. In addition, trial pit at HKCEC VIP Drop-Off area is ongoing;

 -           Construction of trial bored pile construction;

 -           Dredging works for cross harbour watermains at Central Fairway;

 -           Trial dredging at south side of HKCEC water channel was commenced on 7 Sept 10;

 -           Cutting of abandoned piles at HKCEC water channel was completed on 20 Sept 10;

 -           Dismantling of existing sloping seawall and removal of armor rocks at north-west side of water channel;

 -           Trial pits construction for determination of pipeline alignment at Convention Avenue;

 -           Preparation and excavation works for pipe laying of salt water main at Harbour Road;

 -           Trial pits construction for determination of pipeline alignment and connection for cross harbour water mains at Tsim Sha Tsui and Wan Chai Fenwick Pier Street;

 -           The fabrication of elbow sections of cross harbour submarine pipes;

 -           The assembling of tailor made dredging crane barge.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:17">Modification of CATV combine service inspection chamber is ongoing.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:17"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:17">Installation of staging piles for trial bored pile was completed and bored pile construction is in progress.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:17"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:17">Marine site investigation was completed.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:17"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:17">Dredging works for cross harbour watermains is on going.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:17"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:17">Dismantling of existing sloping seawall and removal of armor rock at north-west side of water channel is stopped and reinstating the rock slope at seawall is in progress.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:17"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:17">Hoarding erection at Tsim Sha Tsui Salisbury Garden area is completed on 18/08/10. However, only 18m of artwork panel is installed as design for other location has yet been finalized from the Engineer.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:17"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:17">Trial pits construction for determination of pipeline alignment at Convention Avenue is ongoing.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:17"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:17">Fabrication of straight sections of cross harbour submarine pipes and land water pipes was completed.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:17"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:17">Elbow sections of cross harbour submarine pipes are being fabricated.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:17"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:17">The assemble of 6 nos. of tailor made flat top barge was commenced on 14 Aug 10. The fabrication of dredging crane was completed and will be installed on the tailor make flat top barge on 21 Aug 10 and ready for dredging by 15 Sept 10 tentatively. < cite="mailto:Lam20100204" datetime="2010-09-07T14:17">

< cite="mailto:Lam20100204" datetime="2010-09-07T14:18"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:17">The registration of 3 mud barges had been fully licensed. Demonstration to EPD for operation is on going.< cite="mailto:Lam20100204" datetime="2010-09-07T14:18">

< cite="mailto:mansonyeung" datetime="2010-09-04T12:16">Erection of interim Engineer’s Principal Office at Works areas WA2

< cite="mailto:mansonyeung" datetime="2010-09-04T12:16"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:16">Modification of CATV combine service inspection chamber

< cite="mailto:mansonyeung" datetime="2010-09-04T12:16"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:16">Installation of staging piles for trial bored pile was completed and bored pile construction

< cite="mailto:mansonyeung" datetime="2010-09-04T12:16"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:16">Marine site investigation

< cite="mailto:mansonyeung" datetime="2010-09-04T12:16"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:16">Dredging works for cross harbour watermains

< cite="mailto:mansonyeung" datetime="2010-09-04T12:16"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:16">Dismantling of existing sloping seawall and removal of armor rock at north-west side of water channel is stopped and reinstating the rock slope at seawall

< cite="mailto:mansonyeung" datetime="2010-09-04T12:16"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:16">Hoarding erection at Tsim Sha Tsui Salisbury Garden area

< cite="mailto:mansonyeung" datetime="2010-09-04T12:16"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:16">18m of artwork panel is installed as design for other location

< cite="mailto:mansonyeung" datetime="2010-09-04T12:16"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:16">Trial pits construction for determination of pipeline alignment at Convention Avenue

< cite="mailto:mansonyeung" datetime="2010-09-04T12:16"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:16">Fabrication of straight sections of cross harbour submarine pipes and land water pipes

< cite="mailto:mansonyeung" datetime="2010-09-04T12:16"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:16">Elbow sections of cross harbour submarine pipes are being fabricated.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:18"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:16">The assemble of 6 nos. of tailor made flat top barge was commenced on 14 Aug 10. The fabrication of dredging crane was completed and will be installed on the tailor make flat top barge on 21 Aug 10 and ready for dredging by 15 Sept 10 tentatively.< cite="mailto:Lam20100204" datetime="2010-09-07T14:18">

 

      iv.            During this reporting period, the major work activities for Contract no. HK/2009/02 included:

< cite="mailto:Lam20100204" datetime="2010-10-07T17:04"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:04">Site Clearance

 -           Site Cleaning and Tidying;

 -           Temporary Hoarding Erection;

 -           Pre-bored H-piles, ELS and excavation at WSD Pumping Station;

 -           Construction of Salt Water Intake Culvert at Pet Garden;

 -           Road Modification and Improvement Works;

 -           Construction of Cooling Mains Along Public Road;

 -           Demolition of Finger Pier;

 -           Construction of Temporary Seawall;

 -           Dredging of WCR 1;

 -           Tree Transplanting; and

< cite="mailto:Lam20100204" datetime="2010-10-07T17:04"> -           Plant Trial of TKO 137 Sorting Facility< cite="mailto:Lam20100204" datetime="2010-10-07T17:04">Hoarding Erection

< cite="mailto:Lam20100204" datetime="2010-10-07T17:04"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:04">Pre-bored H-piles, ELS and excavation at WSD Pumping Station

< cite="mailto:Lam20100204" datetime="2010-10-07T17:04"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:04">Construction of Salt Water Intake Culvert at Pet Garden

< cite="mailto:Lam20100204" datetime="2010-10-07T17:04"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:04">Road Modification Works

< cite="mailto:Lam20100204" datetime="2010-10-07T17:04"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:04">Construction of Cooling Mains Along Public Road

< cite="mailto:Lam20100204" datetime="2010-10-07T17:04"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:04">Construction of Temporary Seawall

< cite="mailto:Lam20100204" datetime="2010-10-07T17:04"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:04">Dredging for WCR 1

< cite="mailto:Lam20100204" datetime="2010-10-07T17:04"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:04">Tree Transplanting

 -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:04">Equipments Procurement for TKO 137

            < cite="mailto:mansonyeung" datetime="2010-09-04T12:20">S< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">ite < cite="mailto:mansonyeung" datetime="2010-09-04T12:20">C< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">learance< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">

< cite="mailto:mansonyeung" datetime="2010-09-04T12:20"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Hoarding < cite="mailto:mansonyeung" datetime="2010-09-04T12:20">E< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">rection< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">

< cite="mailto:mansonyeung" datetime="2010-09-04T12:20"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Pre-bored H-piles, ELS and excavation at WSD Pumping Station< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">

< cite="mailto:mansonyeung" datetime="2010-09-04T12:20"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Construction of < cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Salt Water Intake Culvert at Pet Garden< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">

< cite="mailto:mansonyeung" datetime="2010-09-04T12:20"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Road < cite="mailto:mansonyeung" datetime="2010-09-04T12:20">M< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">odification Works< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">

< cite="mailto:mansonyeung" datetime="2010-09-04T12:20"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Construction of Cooling Mains Along Public Road< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">

< cite="mailto:mansonyeung" datetime="2010-09-04T12:20"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Construction of < cite="mailto:mansonyeung" datetime="2010-09-04T12:20">T< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">emporary < cite="mailto:mansonyeung" datetime="2010-09-04T12:20">S< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">eawall< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">

< cite="mailto:mansonyeung" datetime="2010-09-04T12:20"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">D< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">redging< cite="mailto:mansonyeung" datetime="2010-09-04T12:20"> for WCR 1< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">

< cite="mailto:mansonyeung" datetime="2010-09-04T12:20"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Tree Transplanting< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">

< cite="mailto:Lam20100204" datetime="2010-09-07T14:19"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Equipments < cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Procurement< cite="mailto:mansonyeung" datetime="2010-09-04T12:20"> for TKO 137< cite="mailto:Lam20100204" datetime="2010-09-07T14:19">

 

Noise Monitoring

        v.            Noise monitoring during day time and evening time were conducted at the City Garden, Victoria Centre and Harbour Road Sports Center on a weekly basis in the reporting month. Five limit level exceedances were recorded at Victoria Centre on 31 August and 21 September 2010 during daytime period and at Harbour Road Sports Centre on 31 August, 7 and 14 September 2010 during the evening time period. Investigation found that exceedances were not related to the Project. < cite="mailto:mansonyeung" datetime="2010-09-02T19:18">Noise monitoring during < cite="mailto:mansonyeung" datetime="2010-09-02T19:18">day time and evening time< cite="mailto:mansonyeung" datetime="2010-09-02T19:18"> were conducted at the City Garden on a weekly basis in the reporting period. < cite="mailto:mansonyeung" datetime="2010-09-02T19:18">Two limit level exceedances were recorded at M4a on 20 and 27 July 2010 during restricted hours. Investigation found that is not project related exceedances. < cite="mailto:mansonyeung" datetime="2010-09-02T19:18">Reviewed the past monitoring results and observation at Station M4a, Victoria Centre (Station ID: M4b) is proposed as alternative noise monitoring < cite="mailto:mansonyeung" datetime="2010-09-02T19:18">station< cite="mailto:mansonyeung" datetime="2010-09-02T19:18"> from August 2010.

< cite="mailto:Lam20100204" datetime="2010-09-07T20:10"> < cite="mailto:Lam20100204" datetime="2010-09-07T20:10">

< cite="mailto:Lam20100204" datetime="2010-09-07T14:23">Noise monitoring during daytime< cite="mailto:Lam20100204" datetime="2010-09-07T14:23"> < cite="mailto:Lam20100204" datetime="2010-09-07T14:23">w< cite="mailto:Lam20100204" datetime="2010-09-07T14:23">as< cite="mailto:Lam20100204" datetime="2010-09-07T14:23"> conducted at the < cite="mailto:Lam20100204" datetime="2010-09-07T14:23">M1a < cite="mailto:Lam20100204" datetime="2010-09-07T14:23"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:23"> Harbour Road Sports Centre in this reporting month. < cite="mailto:mansonyeung" datetime="2010-09-02T19:21">Due to the marine works undertaken in evening time from 12 July 2010, noise monitoring during evening time was conducted from 13 July 2010. < cite="mailto:Lam20100204" datetime="2010-09-07T14:23">Three limit level exceedances were recorded < cite="mailto:Lam20100204" datetime="2010-09-07T14:23">at 3, 10 and 17 during restricted hour< cite="mailto:mansonyeung" datetime="2010-09-02T19:22">in reporting month. It is concluded as not related to the Project works. However, baseline noise level at M1 needs to be reviewed in next < cite="mailto:mansonyeung" datetime="2010-09-02T19:22">reporting< cite="mailto:mansonyeung" datetime="2010-09-02T19:22"> month.< cite="mailto:Lam20100204" datetime="2010-09-07T14:23">Investigation found that is not project related exceedances. < cite="mailto:Lam20100204" datetime="2010-09-07T14:23">

 

Air Quality Monitoring

      vi.            Air quality monitoring has been conducted at stations CMA1a  Oil Street Community Liaison Centre and CMA2a  Causeway Bay Community Centre. < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">As no filling works < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">for Contract no. < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">HY/2009/11 < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">was carried< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">commenced < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24"> /span>out in < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">mid-< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">reporting month< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">August 2010< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">, n< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">o air quality monitoring < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">at stations CMA1b < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24"> />< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24"> Oil < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">Street Community Liaison Centre < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">and CMA2a  Causeway Bay Community Centre < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">was < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">were < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">undertaken< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">commenced< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24"> during < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">on 11 August 2010< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">the reporting month.< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24"> One No < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">action level exceedance < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">of 1hour TSP was recorded < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">at CMA1b< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24"> < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">on 24 August 2010. Investigation found th< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">at < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">exceedance was< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24"> not related to the Project.in the reporting month.

 

Water Quality Monitoring

     vii.            Water quality monitoring at 17 monitoring stations < cite="mailto:Lam20100204" datetime="2010-09-07T14:44">werewas conducted three days per week during the reporting period.  /span>The action and limit level exceedances of water quality monitoring are summarized in Table I. Investigations were found that the exceedances are not related to the Project works. The details of the exceedances can be referred to Section 5.3 and 6.3 of the report.

 

Table I     Summary of Water Quality Monitoring Exceedances in Reporting Month

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HY/2009/11

WSD9

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">3

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

 

WSD10

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">5

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

 

WSD15

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">3

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">4

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

 

WSD17

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

3 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">5

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

 

C8

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">4

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

2 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

3 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">5

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">3

 

C9

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

2 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">4

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

2 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

5 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">3

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

HK/2009/01

WSD19

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

 

WSD20

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

 

WSD7

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">3

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

 

C1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

 

C2

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">3

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

 

C3

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">3

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

2 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

 

C4e

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

 

C4w

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

HK/2009/02

C5e

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

 

C5w

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

2 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

 

WSD21

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1

Total

2 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">11

0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">11

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

2 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0

4 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">18

1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">16

10 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">22

3 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">24

6 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">3

5 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2

15 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">15

5 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">8

 

   viii.            Turbidity and SS exceedances at stations C3 and C4e were recorded on 8 September 2010 at mid-ebb during the undertaken of trial dredging at south side of HKCEC. Silt screen and silt curtain were inspected in proper condition during the trial dredging. No further dredging works was carried out after this monitoring date. It cannot be concluded the exceedances were not related to the Project. Since the dredging works was carried out in close proximity of the intakes, Contractor was reminded to ensure all mitigation measures be properly implemented.

 

Complaints, Notifications of Summons and Successful Prosecutions

     ix.            < cite="mailto:mansonyeung" datetime="2010-09-02T19:30">No complaint< cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">Two< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24"> noiseNo environmental complaint< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">s w< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">ereas re< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:30">cordedceived < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">on 30< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">1< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24"> July and 12 August 2010< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24"> regarding noise nuisance < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">generated < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">from the dredging works between 1900 and 0800 in North Point district.< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24"> Investigation found that < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">the complaints were< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24"> considered not valid from the < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:24">Environmental Permit and Construction Noise Permit point of view.in the reporting month.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:47">i.< cite="mailto:Lam20100204" datetime="2010-09-07T14:46">, < cite="mailto:mansonyeung" datetime="2010-09-02T19:31">notification of summons and prosecution was recorded in < cite="mailto:mansonyeung" datetime="2010-09-02T19:31">reporting< cite="mailto:mansonyeung" datetime="2010-09-02T19:31"> month.< cite="mailto:Lam20100204" datetime="2010-09-07T14:47">

 

Site Inspections and Audit

       x.            The Environmental Team (ET) conducted weekly site inspections for Contract nos. HY/2009/11, HK/2009/01 and HK/2009/02 under EP no. EP-356/2009 in the< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:31">is reporting < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:31">periodmonth. Major observations and recommendations made during the audit sessions were rectified by the Contractors. No non-conformance was identified during the site inspections.

 

Future Key Issues

     xi.            In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HY/2009/11- North Point Reclamation

< cite="mailto:Lam20100204" datetime="2010-10-07T17:05"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:05">Floating Out of Caisson Seawall,

 -           Floating Out of Caisson Seawall,

 -           Installation of Caisson Seawall,

 -           Dredging works,

 -           Reclamation works,

 -           Construction & installation of Seawall Block and

< cite="mailto:Lam20100204" datetime="2010-10-07T17:05"> -           Pre-casting works for coping.< cite="mailto:Lam20100204" datetime="2010-10-07T17:05">Installation of Caisson Seawall,

< cite="mailto:Lam20100204" datetime="2010-10-07T17:05"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:05">Dredging works,

< cite="mailto:Lam20100204" datetime="2010-10-07T17:05"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:05">Construction of Seawall Block,< cite="mailto:Lam20100204" datetime="2010-10-07T17:05">

 -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:05">Works for Fenders and rubber steps and Drainage works

< cite="mailto:mansonyeung" datetime="2010-09-04T12:23">Floating< cite="mailto:mansonyeung" datetime="2010-09-04T12:23"> Out of Caisson Seawall,

< cite="mailto:mansonyeung" datetime="2010-09-04T12:23"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:23">Installation of Caisson Seawall,

< cite="mailto:mansonyeung" datetime="2010-09-04T12:23"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:23">Dredging works,< cite="mailto:mansonyeung" datetime="2010-09-04T12:23">

< cite="mailto:mansonyeung" datetime="2010-09-04T12:23"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:23">Filling works< cite="mailto:mansonyeung" datetime="2010-09-04T12:23">

< cite="mailto:mansonyeung" datetime="2010-09-04T12:23"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:23">Construction of Seawall Block,

< cite="mailto:mansonyeung" datetime="2010-09-04T12:23"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:23">Works for Fenders and rubber steps and

< cite="mailto:Lam20100204" datetime="2010-09-03T15:02"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:23">Drainage works< cite="mailto:Lam20100204" datetime="2010-09-03T15:02">

< cite="mailto:Lam20100204" datetime="2010-09-03T15:02"> />< cite="mailto:Lam20100204" datetime="2010-09-03T15:02"> < cite="mailto:Lam20100204" datetime="2010-09-03T15:02">

 

Contract no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at HKCEC

< cite="mailto:Lam20100204" datetime="2010-10-07T17:07"> 

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:49">Installation of pipe pile wall at West Bridge

 -           Installation of pipe pile wall at West Bridge and trial bored pile for tunnel and excavation;

 -           Dredging works and removal of rock armour for existing sloping seawall at HKCEC water channel;

 -           Dredging works for cross harbour watermains;

 -           Commencement of temporary jetty construction;

 -           Implementation of TTM scheme for trial pit at Convention Avenue (Area A1);

 -           Implementation of TTM scheme for pipe laying at Convention Avenue (Area A1) for cooling water main and Harbour Road (Area A5) for salt water main and optic fibre;

 -           Implementation of TTM scheme for Stage 1 pipe laying for cooling mains and cross harbour water main at Expo Drive near HKCEC (Area B1);

 -           Tree transplantation at Wan Chai and Tsim Sha Tsui;

 -           Builder’s work and structural modification for Sea water pump houses / Transformer room of HKCEC;

 -           Additional coring for pipe sleeve and puddle flange opening at Pump Station Nos. 1, 3, 4 & 5; and

 -           Preparation work for E&M first fixing at high level of Pump Station Nos. 1, 3, 4 & 5

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:49">Installation of trial bored pile

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:49">Assembly of crane to the custom made dredger

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:49">Dredging works for cross harbour watermains

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:49">Construction of wheel washing facilities

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:49">Commencement of temporary jetty construction

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:49">Implementation of TTM scheme for trial pit at Convention Avenue (Area A1) and Harbour Road (Area A5)

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:49">Implementation of TTM scheme for Stage 1 pipe laying for cooling mains and cross harbour water main at Convention Avenue (Area A1)

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:49">Implementation of TTM scheme for Stage 1 pipe laying for salt water main and optic fibre at Harbour Road (Area A5)

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:49">Implementation of TTM scheme for Stage 1 pipe laying for cooling mains and cross harbour water main at Expo Drive near HKCEC (Area B1)

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:49">Tree transplantation at Wan Chai and Tsim Sha Tsui

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:49">Builder’s work and structural modification for Sea water  pump houses / Transformer room of HKCEC

< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:31"> 

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> 

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> 

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> 

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> < cite="mailto:Lam20100204" datetime="2010-09-07T14:49">

< cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Installation of pipe pile wall at West Bridge

< cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Installation of trial bored pile

< cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Assembly of crane to the custom made dredger

< cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Dredging works for cross harbour watermains

< cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Construction of wheel washing facilities

< cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Commencement of temporary jetty construction

< cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Implementation of TTM scheme for trial pit at Convention Avenue (Area A1) and Harbour Road (Area A5)

< cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Implementation of TTM scheme for Stage 1 pipe laying for cooling mains and cross harbour water main at Convention Avenue (Area A1)

< cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Implementation of TTM scheme for Stage 1 pipe laying for salt water main and optic fibre at Harbour Road (Area A5)

< cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Implementation of TTM scheme for Stage 1 pipe laying for cooling mains and cross harbour water main at Expo Drive near HKCEC (Area B1)

< cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Tree transplantation at Wan Chai and Tsim Sha Tsui

< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Builder’s work and structural modification for Sea water pump houses / Transformer room of HKC< cite="mailto:Lam20100204" datetime="2010-09-07T14:49">

 

Contract no. HK/2009/02 - Wan Chai Development Phase II  Central  Wan Chai Bypass at WanChai East

< cite="mailto:Lam20100204" datetime="2010-10-07T17:08"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T17:08">Site Clearance

 -           Site Cleaning and Tidying;

 -           Temporary Hoarding Erection;

 -           Pre-bored H-piles, ELS and excavation at WSD Pumping Station;

 -           Construction of Salt Water Intake Culvert at Pet Garden;

 -           Road Modification and Improvement Works;

 -           Construction of Cooling Mains Along Public Road;

 -           Demolition of Finger Pier;

 -           Construction of Temporary Seawall;

 -           Dredging and Backfilling of WCR 1;

 -           Tree Transplanting; and

 -           Plant Trial of TKO 137 Sorting Facility

< cite="mailto:Lam20100204" datetime="2010-10-07T17:08"> />< cite="mailto:Lam20100204" datetime="2010-10-07T17:08">Hoarding Erection

< cite="mailto:Lam20100204" datetime="2010-10-07T17:08"> />< cite="mailto:Lam20100204" datetime="2010-10-07T17:08">Pre-bored H-piles, ELS and excavation at WSD Pumping Station

< cite="mailto:Lam20100204" datetime="2010-10-07T17:08"> />< cite="mailto:Lam20100204" datetime="2010-10-07T17:08">Construction of Salt Water Intake Culvert at Pet Garden

< cite="mailto:Lam20100204" datetime="2010-10-07T17:08"> />< cite="mailto:Lam20100204" datetime="2010-10-07T17:08">Road Modification Works

< cite="mailto:Lam20100204" datetime="2010-10-07T17:08"> />< cite="mailto:Lam20100204" datetime="2010-10-07T17:08">Construction of Cooling Mains Along Public Road

< cite="mailto:Lam20100204" datetime="2010-10-07T17:08"> />< cite="mailto:Lam20100204" datetime="2010-10-07T17:08">Construction of Temporary Seawall

< cite="mailto:Lam20100204" datetime="2010-10-07T17:08"> />< cite="mailto:Lam20100204" datetime="2010-10-07T17:08">Dredging for WCR 1

< cite="mailto:Lam20100204" datetime="2010-10-07T17:08"> />< cite="mailto:Lam20100204" datetime="2010-10-07T17:08">Tree Transplanting

< cite="mailto:Lam20100204" datetime="2010-10-07T17:08"> />< cite="mailto:Lam20100204" datetime="2010-10-07T17:08">Equipments Procurement for TKO 137< cite="mailto:Lam20100204" datetime="2010-10-07T17:08">

 

 

 


1.     Introduction

1.1               Scope of the Report

1.1.1.        Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009 and FEP-03/356/2009 < cite="mailto:Lam20100204" datetime="2010-10-12T17:45">for Contract< cite="mailto:Lam20100204" datetime="2010-10-12T17:45">or< cite="mailto:Lam20100204" datetime="2010-10-12T17:45"> No. HK/2009/05 Wan Chai Development Phase II and Central –Wan Chai Bypass   Sampling,< cite="mailto:Lam20100204" datetime="2010-10-12T17:45"> Field Measurement and Testing Work (Stage 1) to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.        This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and  i style='mso-bidi-font-style: normal'>Environmental Monitoring and Audit Requirements /i> under Particular Specification Section 27.

1.1.3.        This report documents the finding of EM&A works for Environmental Permit no. EP-356/2009, Further Environmental Permit no. FEP-01/356/2009, FEP-02/356/2009 and FEP-03/356/2009 during the period 28th < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:31">July August to 27th < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:31">August September 2010. The cut-off date of reporting is at 27th of each reporting month.

 

1.2               Structure of the Report

 

Section 1     Introduction  details the scope and structure of the report.

 

Section 2     Project Background  summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3     Status of Regulatory Compliance  summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4     Monitoring Requirements  summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5     Monitoring Results  summarizes the monitoring results obtained in the reporting period.

 

Section 6     Compliance Audit  summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7     Cumulative Construction Impact due to the Concurrent Projects  summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8     Site Inspection   summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9     Complaints, Notification of summons and Prosecution  summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10    Conclusion

2.     Project Background

2.1               Background

2.1.1.        “Wan Chai Development phase II and Central-Wan Chai Bypass and “Central-Wan Chai Bypass and Island Eastern Corridor Link (hereafter called “the Project  are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.        The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.        There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2               Scope of the Project and Site Description

2.2.1.        The Project is located mainly in Wan Chai North, Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road Interchange to the east, as shown in Figure 2.1.

2.2.2.        The study area encompasses existing developments along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police Officers' Club, the Causeway Bay Typhoon Shelter (CBTS) and commercial and residential developments.

2.2.3.        The scope of the Project comprises:

 -           Land formation for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for connection to the Trunk Road and for through traffic from Central to Wan Chai and Causeway Bay. The land formed for the above transport infrastructure will provide opportunities for the development of an attractive waterfront promenade for the enjoyment of the public

 -           Reprovisioning / protection of the existing facilities and structures affected by the land formation works mentioned above

 -           Extension, modification, reprovisioning or protection of existing storm water drainage outfalls, sewerage outfalls and watermains affected by the revised land use and land formation works mentioned above

 -           Upgrading of hinterland storm water drainage system and sewerage system, which would be rendered insufficient by the land formation works mentioned above

 -           Provision of the ground level roads, flyovers, footbridges, necessary transport facilities and the associated utility services

 -           Construction of the new waterfront promenade, landscape works and the associated utility services

 -           The Trunk Road (i.e. CWB) within the study area and the associated slip roads for connection to the Trunk Road.

 

2.2.4.        The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1   Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

 

2.3               Division of the Project Responsibility

2.3.1.        Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced. Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits (FEP) such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.        < cite="mailto:Lam20100204" datetime="2010-09-07T14:52">In the reporting month, < cite="mailto:Lam20100204" datetime="2010-09-07T14:52">the dredging works for Contracts no. HK/2009/01 and HK/2009/02 were commenced on 23 July and 5 July 2010 respectively. The details of individual contracts are summarized in Table 2.2.

Table 2.2  Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HK/2009/01

Wan Chai Development Phase II  Central –Wanchai Bypass at Hong Kong Convention and Exhibition Centre

DP3, DP6

23 July 2010

DP1, DP2

Pending

HK/2009/02

Wan Chai Development Phase II  Central  Wan Chai Bypass at WanChai East

DP3, DP5

5 July 2010

DP1

Pending

HY/2009/11

Wan Chai Development Phase II and Central - Wan Chai Bypass - North Point Reclamation

DP3

17 March 2010

 

2.4               Project Organization and Contact Personnel

2.4.1.        Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.        The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are summarized in Table 2.3:

< cite="mailto:Lam20100204" datetime="2010-09-07T14:53">

Table 2.3  Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer for WDII

Principle Resident Engineer

Mr. Frankie Fan

2607 7801

2687 2322

Engineer for CWB

Principle < cite="mailto:Lam20100204" datetime="2010-10-12T17:35">Chief Resident Engineer

Mr. < cite="mailto:Lam20100204" datetime="2010-10-12T17:35">David KwanPeter Poon

3916 1818

3529 2829

China Harbour- CRBC Joint Venture

Contractor under Contract no. HY/2009/11

Project Director

Mr. Cho Yu Fun

3157 1086

3157 1085

Project Manager

Mr. Gregory Wong

3157 1086

Site Agent

Mr. Daniel Cheung

3157 1086

Environmental Officer

Mr. C. M. Wong

3157 1086

Chun Wo  Leader Joint Venture

Contractor under Contract no. HK/2009/01

Site Agent

Paul Yu

9456 9819

2634 1626

Operation Manager

Lau Yee Ching< cite="mailto:mansonyeung" datetime="2010-09-04T13:03">Ho Wing Tai

9466 3918< cite="mailto:mansonyeung" datetime="2010-09-04T13:03">9306 1356

Construction Manager

David Wong

9653 8635

Construction Manager

Wilson Lau

5183 1270

Construction Manager

Chan Mui Sang< cite="mailto:mansonyeung" datetime="2010-09-04T13:03">Alex Tsang

9864 8615< cite="mailto:mansonyeung" datetime="2010-09-04T13:03">9194 9383

Environmental Officer (Compliance Manager)

Brian Wan< cite="mailto:mansonyeung" datetime="2010-09-04T13:04">Ho Wing Tai

9312 2827< cite="mailto:mansonyeung" datetime="2010-09-04T13:04">9306 1356

Environmental Engineer

Shelton Chan< cite="mailto:mansonyeung" datetime="2010-09-04T13:04">Ken Yang

5395 5470< cite="mailto:mansonyeung" datetime="2010-09-04T13:04">9262 6791

Chun Wo  CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Project Manager

Mr. Chan Sing Cho

3658 3002

2827 9996

Site Agent

Mr. Eric Lam< cite="mailto:mansonyeung" datetime="2010-09-04T13:04">Mr. Anthony Wu

3658-3048< cite="mailto:mansonyeung" datetime="2010-09-04T13:04">3658 3004

Environmental Officer (Compliance Manager)

Mr. Barry Leung

3658 3031

Environmental Engineer

Ms. Flora Ng

3658-3064

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3743 0788

3548 6988

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:33"> < cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:33">

2.4.3.        For Contract no. HY/2009/11, the principal work activities in this reporting month included:

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Construction of Rock Mound,

 -           Floating Out of Caisson Seawall;

 -           Installation of Caisson Seawall;

 -           Dredging works;

 -           Reclamation works;

 -           Construction & installation of Seawall Block;

 -           Works for Fenders and rubber steps; and

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           Pre-casting works for coping< cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Floating Out of Caisson Seawall,

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Installation of Caisson Seawall,

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Dredging works,

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Laying of geo-textile,

 -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Drainage Works and Seawall Block Installation

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Construction of Rock Mound,

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Floating Out of Caisson Seawall,

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Installation of Caisson Seawall,

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Dredging works,

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Filling works;

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Laying of geo-textile,

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Drainage Works and

< cite="mailto:Lam20100204" datetime="2010-09-07T14:53"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Seawall Block Installation< cite="mailto:Lam20100204" datetime="2010-09-07T14:53">

< cite="mailto:Lam20100204" datetime="2010-09-03T16:56"> < cite="mailto:Lam20100204" datetime="2010-09-03T16:56">

< cite="mailto:Lam20100204" datetime="2010-09-07T14:53"> < cite="mailto:Lam20100204" datetime="2010-09-07T14:53">

 

2.4.4.        For Contract no. HK/2009/01, the principal work activities in this reporting month included:

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Erection of interim Engineer’s Principal Office at Works areas WA2 was completed for moving-in on 5 Aug 10.

 -           Modification of CATV combine service inspection chamber. In addition, trial pit at HKCEC VIP Drop-Off area is ongoing;

 -           Construction of trial bored pile construction;

 -           Dredging works for cross harbour watermains at Central Fairway;

 -           Trial dredging at south side of HKCEC water channel was commenced on 7 Sept 10;

 -           Cutting of abandoned piles at HKCEC water channel was completed on 20 Sept 10;

 -           Dismantling of existing sloping seawall and removal of armor rocks at north-west side of water channel;

 -           Trial pits construction for determination of pipeline alignment at Convention Avenue;

 -           Preparation and excavation works for pipe laying of salt water main at Harbour Road;

 -           Trial pits construction for determination of pipeline alignment and connection for cross harbour water mains at Tsim Sha Tsui and Wan Chai Fenwick Pier Street;

 -           The fabrication of elbow sections of cross harbour submarine pipes;

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           The assembling of tailor made dredging crane barge.< cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Modification of CATV combine service inspection chamber is ongoing.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Installation of staging piles for trial bored pile was completed and bored pile construction is in progress.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Marine site investigation was completed.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Dredging works for cross harbour watermains is on going.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Dismantling of existing sloping seawall and removal of armor rock at north-west side of water channel is stopped and reinstating the rock slope at seawall is in progress.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Hoarding erection at Tsim Sha Tsui Salisbury Garden area is completed on 18/08/10. However, only 18m of artwork panel is installed as design for other location has yet been finalized from the Engineer.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Trial pits construction for determination of pipeline alignment at Convention Avenue is ongoing.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Fabrication of straight sections of cross harbour submarine pipes and land water pipes was completed.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Elbow sections of cross harbour submarine pipes are being fabricated.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">The assemble of 6 nos. of tailor made flat top barge was commenced on 14 Aug 10. The fabrication of dredging crane was completed and will be installed on the tailor make flat top barge on 21 Aug 10 and ready for dredging by 15 Sept 10 tentatively.

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">The registration of 3 mud barges had been fully licensed. Demonstration to EPD for operation is on going.

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Erection of interim Engineer’s Principal Office at Works areas WA2

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Modification of CATV combine service inspection chamber

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Installation of staging piles for trial bored pile was completed and bored pile construction

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Marine site investigation

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Dredging works for cross harbour watermains

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Dismantling of existing sloping seawall and removal of armor rock at north-west side of water channel is stopped and reinstating the rock slope at seawall

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Hoarding erection at Tsim Sha Tsui Salisbury Garden area

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:06">18m of artwork panel is installed as design for other location

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Trial pits construction for determination of pipeline alignment at Convention Avenue

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Fabrication of straight sections of cross harbour submarine pipes and land water pipes

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Elbow sections of cross harbour submarine pipes are being fabricated.

< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:06">The assemble of 6 nos. of tailor made flat top barge was commenced on 14 Aug 10. The fabrication of dredging crane was completed and will be installed on the tailor make flat top barge on 21 Aug 10 and ready for dredging by 15 Sept 10 tentatively.< cite="mailto:mansonyeung" datetime="2010-09-04T13:06">

< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> -           < cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> < cite="mailto:Lam20100204" datetime="2010-09-07T14:54">

 -            

2.4.5.        For Contract no. HK/2009/02, the principal work activities in this reporting month included:

< cite="mailto:Lam20100204" datetime="2010-10-07T18:00"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:00">Site Clearance

 -           Site Cleaning and Tidying;

 -           Temporary Hoarding Erection;

 -           Pre-bored H-piles, ELS and excavation at WSD Pumping Station;

 -           Construction of Salt Water Intake Culvert at Pet Garden;

 -           Road Modification and Improvement Works;

 -           Construction of Cooling Mains Along Public Road;

 -           Demolition of Finger Pier;

 -           Construction of Temporary Seawall;

 -           Dredging of WCR 1;

 -           Tree Transplanting; and

< cite="mailto:Lam20100204" datetime="2010-10-07T18:00"> -           Plant Trial of TKO 137 Sorting Facility< cite="mailto:Lam20100204" datetime="2010-10-07T18:00">Hoarding Erection

< cite="mailto:Lam20100204" datetime="2010-10-07T18:00"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:00">Pre-bored H-piles, ELS and excavation at WSD Pumping Station

< cite="mailto:Lam20100204" datetime="2010-10-07T18:00"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:00">Construction of Salt Water Intake Culvert at Pet Garden

< cite="mailto:Lam20100204" datetime="2010-10-07T18:00"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:00">Road Modification Works

< cite="mailto:Lam20100204" datetime="2010-10-07T18:00"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:00">Construction of Cooling Mains Along Public Road

< cite="mailto:Lam20100204" datetime="2010-10-07T18:00"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:00">Construction of Temporary Seawall

< cite="mailto:Lam20100204" datetime="2010-10-07T18:00"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:00">Dredging for WCR 1

< cite="mailto:Lam20100204" datetime="2010-10-07T18:00"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:00">Tree Transplanting

 -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:00">Equipments Procurement for TKO 137

< cite="mailto:Lam20100204" datetime="2010-09-07T14:55"> < cite="mailto:Lam20100204" datetime="2010-09-07T14:55">

 

2.4.6.        In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

Contract no. HY/2009/11- North Point Reclamation

< cite="mailto:Lam20100204" datetime="2010-10-07T18:11"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:11">Floating Out of Caisson Seawall,

 -           Floating Out of Caisson Seawall;

 -           Installation of Caisson Seawall;

 -           Dredging works;

 -           Reclamation works;

 -           Construction & installation of Seawall Block; and

< cite="mailto:Lam20100204" datetime="2010-10-07T18:10"> -           Pre-casting works for coping.< cite="mailto:Lam20100204" datetime="2010-10-07T18:10">Installation of Caisson Seawall,

< cite="mailto:Lam20100204" datetime="2010-10-07T18:10"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:10">Dredging works,

< cite="mailto:Lam20100204" datetime="2010-10-07T18:10"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:10">Construction of Seawall Block,< cite="mailto:Lam20100204" datetime="2010-10-07T18:10">

< cite="mailto:Lam20100204" datetime="2010-09-07T14:55"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:10">Works for Fenders and rubber steps and Drainage works< cite="mailto:Lam20100204" datetime="2010-09-07T14:55">

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Floating Out of Caisson Seawall,

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Installation of Caisson Seawall,

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Dredging works,

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Filling works

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Construction of Seawall Block,

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Works for Fenders and rubber steps and

< cite="mailto:Lam20100204" datetime="2010-09-07T14:55"> -           < cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Drainage works< cite="mailto:Lam20100204" datetime="2010-09-07T14:55">

< cite="mailto:Lam20100204" datetime="2010-09-03T16:56"> < cite="mailto:Lam20100204" datetime="2010-09-03T16:56">

 -            

 

Contract no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at HKCEC

< cite="mailto:Lam20100204" datetime="2010-10-07T18:11"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:11">Installation of pipe pile wall at West Bridge

 -           Installation of pipe pile wall at West Bridge and trial bored pile for tunnel and excavation;

 -           Dredging works and removal of rock armour for existing sloping seawall at HKCEC water channel;

 -           Dredging works for cross harbour watermains;

 -           Commencement of temporary jetty construction;

 -           Implementation of TTM scheme for trial pit at Convention Avenue (Area A1);

 -           Implementation of TTM scheme for pipe laying at Convention Avenue (Area A1) for cooling water main and Harbour Road (Area A5) for salt water main and optic fibre;

 -           Implementation of TTM scheme for Stage 1 pipe laying for cooling mains and cross harbour water main at Expo Drive near HKCEC (Area B1);

 -           Tree transplantation at Wan Chai and Tsim Sha Tsui;

 -           Builder’s work and structural modification for Sea water pump houses / Transformer room of HKCEC;

 -           Additional coring for pipe sleeve and puddle flange opening at Pump Station Nos. 1, 3, 4 & 5; and

 -           Preparation work for E&M first fixing at high level of Pump Station Nos. 1, 3, 4 & 5

< cite="mailto:Lam20100204" datetime="2010-10-07T18:11"> />< cite="mailto:Lam20100204" datetime="2010-10-07T18:11">Installation of trial bored pile

< cite="mailto:Lam20100204" datetime="2010-10-07T18:11"> />< cite="mailto:Lam20100204" datetime="2010-10-07T18:11">Assembly of crane to the custom made dredger

< cite="mailto:Lam20100204" datetime="2010-10-07T18:11"> />< cite="mailto:Lam20100204" datetime="2010-10-07T18:11">Dredging works for cross harbour watermains

< cite="mailto:Lam20100204" datetime="2010-10-07T18:11"> />< cite="mailto:Lam20100204" datetime="2010-10-07T18:11">Construction of wheel washing facilities

< cite="mailto:Lam20100204" datetime="2010-10-07T18:11"> />< cite="mailto:Lam20100204" datetime="2010-10-07T18:11">Commencement of temporary jetty construction

< cite="mailto:Lam20100204" datetime="2010-10-07T18:11"> />< cite="mailto:Lam20100204" datetime="2010-10-07T18:11">Implementation of TTM scheme for trial pit at Convention Avenue (Area A1) and Harbour Road (Area A5)

< cite="mailto:Lam20100204" datetime="2010-10-07T18:11"> />< cite="mailto:Lam20100204" datetime="2010-10-07T18:11">Implementation of TTM scheme for Stage 1 pipe laying for cooling mains and cross harbour water main at Convention Avenue (Area A1)

< cite="mailto:Lam20100204" datetime="2010-10-07T18:11"> />< cite="mailto:Lam20100204" datetime="2010-10-07T18:11">Implementation of TTM scheme for Stage 1 pipe laying for salt water main and optic fibre at Harbour Road (Area A5)

< cite="mailto:Lam20100204" datetime="2010-10-07T18:11"> />< cite="mailto:Lam20100204" datetime="2010-10-07T18:11">Implementation of TTM scheme for Stage 1 pipe laying for cooling mains and cross harbour water main at Expo Drive near HKCEC (Area B1)

< cite="mailto:Lam20100204" datetime="2010-10-07T18:11"> />< cite="mailto:Lam20100204" datetime="2010-10-07T18:11">Tree transplantation at Wan Chai and Tsim Sha Tsui

< cite="mailto:Lam20100204" datetime="2010-10-07T18:11"> />< cite="mailto:Lam20100204" datetime="2010-10-07T18:11">Builder’s work and structural modification for Sea water  pump houses / Transformer room of HKCEC< cite="mailto:Lam20100204" datetime="2010-10-07T18:11">

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Installation of pipe pile wall at West Bridge

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Installation of trial bored pile

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Assembly of crane to the custom made dredger

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Dredging works for cross harbour watermains

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Construction of wheel washing facilities

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Commencement of temporary jetty construction

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Implementation of TTM scheme for trial pit at Convention Avenue (Area A1) and Harbour Road (Area A5)

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Implementation of TTM scheme for Stage 1 pipe laying for cooling mains and cross harbour water main at Convention Avenue (Area A1)

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Implementation of TTM scheme for Stage 1 pipe laying for salt water main and optic fibre at Harbour Road (Area A5)

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Implementation of TTM scheme for Stage 1 pipe laying for cooling mains and cross harbour water main at Expo Drive near HKCEC (Area B1)

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Tree transplantation at Wan Chai and Tsim Sha Tsui

< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> />< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Builder’s work and structural modification for Sea water pump houses / Transformer room of HKCEC< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">

< cite="mailto:Lam20100204" datetime="2010-09-03T16:56"> />< cite="mailto:Lam20100204" datetime="2010-09-03T16:56"> < cite="mailto:Lam20100204" datetime="2010-09-03T16:56">

< cite="mailto:Lam20100204" datetime="2010-09-03T16:56"> />< cite="mailto:Lam20100204" datetime="2010-09-03T16:56"> < cite="mailto:Lam20100204" datetime="2010-09-03T16:56">

< cite="mailto:Lam20100204" datetime="2010-09-03T16:56"> />< cite="mailto:Lam20100204" datetime="2010-09-03T16:56"> < cite="mailto:Lam20100204" datetime="2010-09-03T16:56">

 

Contract no. HK/2009/02 - Wan Chai Development Phase II  Central  Wan Chai Bypass at WanChai East

< cite="mailto:Lam20100204" datetime="2010-10-07T18:12"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:12">Site Clearance

 -           Site Cleaning and Tidying;

 -           Temporary Hoarding Erection;

 -           Pre-bored H-piles, ELS and excavation at WSD Pumping Station;

 -           Construction of Salt Water Intake Culvert at Pet Garden;

 -           Road Modification and Improvement Works;

 -           Construction of Cooling Mains Along Public Road;

 -           Demolition of Finger Pier;

 -           Construction of Temporary Seawall;

 -           Dredging and Backfilling of WCR 1;

 -           Tree Transplanting; and

< cite="mailto:Lam20100204" datetime="2010-10-07T18:12"> -           Plant Trial of TKO 137 Sorting Facility< cite="mailto:Lam20100204" datetime="2010-10-07T18:12">Hoarding Erection

< cite="mailto:Lam20100204" datetime="2010-10-07T18:12"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:12">Pre-bored H-piles, ELS and excavation at WSD Pumping Station

< cite="mailto:Lam20100204" datetime="2010-10-07T18:12"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:12">Construction of Salt Water Intake Culvert at Pet Garden

< cite="mailto:Lam20100204" datetime="2010-10-07T18:12"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:12">Road Modification Works

< cite="mailto:Lam20100204" datetime="2010-10-07T18:12"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:12">Construction of Cooling Mains Along Public Road

< cite="mailto:Lam20100204" datetime="2010-10-07T18:12"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:12">Construction of Temporary Seawall

< cite="mailto:Lam20100204" datetime="2010-10-07T18:12"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:12">Dredging for WCR 1

< cite="mailto:Lam20100204" datetime="2010-10-07T18:12"> -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:12">Tree Transplanting

 -           < cite="mailto:Lam20100204" datetime="2010-10-07T18:12">Equipments Procurement for TKO 137

 

< cite="mailto:mansonyeung" datetime="2010-09-02T19:34"> < cite="mailto:mansonyeung" datetime="2010-09-02T19:34">

< cite="mailto:mansonyeung" datetime="2010-09-02T19:34"> />< cite="mailto:mansonyeung" datetime="2010-09-02T19:34"> < cite="mailto:mansonyeung" datetime="2010-09-02T19:34">

 

3.     status of regulatory compliance

3.1               Status of Environmental Licensing and Permitting under the Project

 

3.1.1.        A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1  Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009/A

4 Aug < cite="mailto:Lam20100204" datetime="2010-09-08T19:03">17 Aug 20092010

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:33">SuspersededSuperseded

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Valid

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 July 2010

Valid

 

3.1.2.        Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation

3.1.3.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-01/356/2009 for contract no. HY/2009/11 are shown in Table 3.2 and Table 3.3.

Table 3.2  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/11

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

N/A

Valid

Notification of Works Under APCO

314911

9 Mar 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0371-10< cite="mailto:Lam20100204" datetime="2010-09-07T15:01">GW-RS0119-10

7 May 2010< cite="mailto:Lam20100204" datetime="2010-09-07T15:01">17 Feb 2010

10 May 2010 to 31 Oct 2010< cite="mailto:Lam20100204" datetime="2010-09-07T15:01">22< cite="mailto:Lam20100204" datetime="2010-09-07T15:01"> Feb < cite="mailto:Lam20100204" datetime="2010-09-07T15:01">2010< cite="mailto:Lam20100204" datetime="2010-09-07T15:01"> to< cite="mailto:Lam20100204" datetime="2010-09-07T15:01"> < cite="mailto:Lam20100204" datetime="2010-09-07T15:01">22 Aug 2010

Valid < cite="mailto:Lam20100204" datetime="2010-09-07T15:01">Superseded

GW-RS0534-10

22 Jun 2010

29 Jun 2010 to 28 Dec 2010

Valid < cite="mailto:Lam20100204" datetime="2010-09-07T15:01">(Replaced CNP no. GW-RS0437-10)

Billing Account under Waste Disposal Ordinance

7010037

13 Jan 2010

N/A

Valid

Dumping Permit (Type 1  Open Sea Disposal)

EP/MD/10-067

10 Mar 2010

10 Mar 2010 to 9 Sep 2010

< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:34">ValidExpired

 

EP/MD/10-055

26 Aug 2010

10 Sep 2010 to 30 Dec 2010

Valid

Dumping Permit (Type 1  Open Sea Disposal (Dedicate Sites) & Type 2  Confined Marine Disposal)

EP/MD/11-044< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:34">EP/MD/11-0< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:34">33

2 Aug 2010< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:34">9< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:34"> Ju< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:34">l< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:34"> 2010

10 Aug to 9 Sep 2010< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:34">10 Jul to 9 Aug 2010

Expired< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:34">Expired

EP/MD/11-062< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:34">EP/MD/11-0< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:34">44

2 Sep 2010< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:34">2 Aug 2010

10 Sep 2010 to 9 Oct 2010< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:34">10 Aug to 9 Sep 2010

Valid< cite="mailto:Cherry%20Mak" datetime="2010-10-05T01:34">Valid

 

Table 3.3  Summary of submission status under FEP-01/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

18 Dec 2009

Condition 2.7

Submission of works schedule and location plan

8 Feb 2010

Condition 2.8

Silt Curtain Deployment Plan

25 Feb 2010

Condition 2.9

Silt Screen Deployment Plan

25 Feb 2010

 

Revised Silt Screen Deployment Plan

10 May 2010

Condition 2.10

Coral Translocation Plan

20 Nov 2009

Condition 2.16

Noise Management Plan

1 Mar 2010

<