Contract No: HK/2009/05 Wanchai
Development Phase II and Central Wanchai Bypass Sampling,
Field Measurement and Testing Work (Stage 1) Environmental Permit no.
EP-356/2009, Further
Evironmental permit nos. fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009,
Fep-04/356/2009 and Fep-05/356/2009 Monthly
Environmental Monitoring & Audit Report
- March 2011 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185
Gloucester Road, Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
11 April 2011 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of Water Quality Monitoring Exceedances in
Reporting Month
Table 2.1 Schedule 2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/11
Table 3.3 Summary of submission status under FEP-01/356/2009
Condition
Table 3.4 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/01
Table 3.5 Summary of submission status under FEP-02/356/2009
Condition
Table 3.6 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/02
Table 3.7 Summary of submission status under FEP-03/356/2009
Condition
Table 3.8 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/15
Table 3.9 Summary of submission status under FEP-04/356/2009
Condition
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2010/06
Table 3.11 Summary of submission status under EP-356/2009
Condition
Table 4.1 Noise Monitoring Station
Table 4.2 Real Time Noise Monitoring Station
Table 4.3 Air Monitoring Station
Table 4.4 Marine Water Quality Stations for Water Quality
Monitoring
Table 4.5 Marine Water Quality Monitoring Frequency and
Parameters
Table 4.6 Marine Water Quality Stations for Enhanced Water
Quality Monitoring
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/11
Table 5.2 Noise Monitoring Station for Contract nos. HK/2009/01,
HK/2009/02 and HK/2010/06
Table 5.3 Noise Monitoring Station for Contract nos. HY/2009/15
Table 5.4 Real Time Noise Monitoring Station for Contract no.
HY/2009/15
Table 5.5 Air Monitoring Stations for Contract no. HY/2009/11
Table 5.6 Air Monitoring Stations for Contract no. HK/2009/01
Table 5.7 Air Monitoring Station for Contract no. HK/2009/02
Table 5.8 Air Monitoring Station for Contract no. HY/2009/15
Table 5.9 Water Monitoring Stations for Contract no. HY/2009/11
Table 5.10 Water Monitoring Stations for Contract no. HK/2009/01
Table 5.11 Water Monitoring Stations for Contract no. HK/2009/02
Table 5.12 Water Monitoring Stations for Contract no. HK/2009/02
Table 5.14 Summary of Water Quality Monitoring Exceedances in
Reporting Month
Table 5.15 Details of Waste Disposal for Contract no. HY/2009/11
Table 5.16 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.17 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.18 Details of Waste Disposal for Contract no. HY/2009/15
Table 8.1 Summary of Environmental Inspections for Contract no.
HY/2009/11
Table 8.2 Summary of Environmental Inspections for Contract no.
HK/2009/01
Table 8.3 Summary of Environmental Inspections for Contract no.
HK/2009/02
Table 8.4 Summary of Environmental Inspections for Contract no.
HY/2009/15
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended Mitigation
Measures in Coming Reporting Month
lIST
OF FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project
Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST
OF APPENDIces
Appendix 3.1 Environmental Mitigation
Implementation Schedule
Appendix 4.1 Action
and Limit Level
Appendix
4.2 Copies
of Calibration Certificates
Appendix
5.1 Monitoring
Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring Results and
Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and
Graphical Presentations
Appendix
5.4 Water
Quality
Monitoring Results and Graphical Presentations
Appendix
5.5 Real-time
Noise
Monitoring Results and Graphical Presentations
Appendix 6.1 Event
Action Plans
Appendix 6.2 Summary for
Notification of Exceedance
Appendix
9.1 Complaint
Log
Appendix 10.1 Construction
Programme of Individual Contracts
Construction Activities for the Reported Period
¡P
Dredging works,
¡P
Reclamation
works,
¡P
Construction &
installation of Seawall Block; and
¡P
Drainage
Construction works
¡P
Dredging of
marine sediments for the open cut trench of cross harbour water mains and final
trimming for pipe trench (From CHA 450 to 970);
¡P
Removal of
existing rock-fill material at west side sloping seawall of HKCEC extension for
trench dredging of cross harbour water mains;
¡P
Excavation and
installation of shoring system for pipe laying work at Wan Chai (Zone A2-2);
¡P
For
transplanting 29 nos. of trees at Tsim Sha Tsui Salisbury Garden (South
Portion) and 7 nos. of trees at along Expo Drive (for jetty access
construction), transplanting of 11 more tress at Tsim Sha Tsui Salisbury (North
Portion) shall either be transplanted or felled prior to the pipe laying work
as per the updated pipe layout;
¡P
Pipe laying at
TST was commenced on early February and trench excavation;
¡P
After receiving
the latest as-built information from WSD, trial pit excavation for Wan Chai
connection points at Fenwick Pier Street footpath;
¡P
Routine
maintenance and clearance works for silt screens;
¡P
Coring works
(Stage 1: 42 nos. under 350mm diameter openings) at Pump House P1, P3, P4, and
P5;
¡P
Installation of
cooling main pipelines at HKCEC VIP Drop-Off Area (Zone B1-1) and reinstatement
works;
¡P
Installation of
cooling main pipelines at HKCEC Golden Bauhinia Garden (Zone B4-1), area were
backfilled and reinstatement to be commenced;
¡P
Installation of
cooling main pipelines at HKCEC West Wing (Zone B1-2) is on-going (approx. 140m
pipe length completed). Portion of area A were reinstated and cleared on 18
Mar. 2011;
¡P
Due to
construction of SCL works, trial trench construction for temporary diversion of
Convention Plaza discharge mains;
¡P
Excavation for
connection points for Shui On (AE & BE) at Convention Avenue (Zone A2-2)
have to be enlarged for tentative pipe connection work;
¡P
Installation of
another 6 pipe piles;
¡P
Demolition of
staging platform; and
¡P
Removal of rock
armour along north shore of HKCEC water channel
¡P
No sorted fill produce
at Tseung
Kwan O public fill sorting facility;
¡P
Finishing works and remedial works
for new public toilet was completed;
¡P
Internal decoration for new
public toilet was commenced;
¡P
External decoration for new
public toilet was commenced;
¡P
Partial
demolition of existing ferry pier at Expo Drive East was completed;
¡P
Existing jetty pier at Expo
Drive East was relocated;
¡P
Preparation
works for seawall modification at Expo Drive East was completed;
¡P
Modification
of existing seawall at Expo Drive East was commenced;
¡P
Excavation at
Harbour Road and Harbour Centre for cooling mains;
¡P
24m cooling
water mains was laid at Harbour Road;
¡P
Sun Hung Kai tee
connection was carried out;
¡P
China Resource
Building tee connection was carried out;
¡P
Driving
remaining sheet-piles for excavation and lateral support at WSD Salt Water
Pumping Station was completed;
¡P
Curtain grout
works at WSD Salt Water Pumping Station was carried
out;
¡P
Excavation and
lateral support;
¡P
Driving
sheet-piles at Wan Shing Street for WSD Intake Culvert;
¡P
Dredging for
submarine outfall pipe was ongoing;
¡P
Installation
of T6 & T7 seawall blocks was commenced;
¡P
Curtain grout
for jacking pit at ex-pet garden was carried out;
¡P
Excavation and
lateral support for jacking pit at ex-pet garden was commenced
¡P
Tunnel bored
pile works;
¡P
Guide wall for
diaphragm wall construction;
¡P
Establishment
of desander and silo for diaphragm wall construction was commenced;
¡P
Pre-drilling
of bored pile and diaphragm wall;
¡P
1800 diameter
drainage diversion was completed; and
¡P
Road work for
Hung Hing Road traffic diversion was completed.
¡P
Rock removal at
TS4 and TPCWA;
¡P
Seawall block
construction at TS1 and TPCWAE;
¡P
Night time
protection works at CHT;
¡P
Ground
investigation and trial pit excavation; and
¡P
Drainage works
at PRE office
¡P
Installation of
Silt Curtain for Dredging Works;
¡P
Dredging over
the MTR Tsuen Wan Line; and
¡P
Pre-construction
Condition Survey inside MTR tunnel
Noise Monitoring
Real-time Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
Table I Summary of Water Quality Monitoring
Exceedances in Reporting Month
Contract no. |
Water Monitoring
Station |
Mid-flood |
Mid-ebb |
||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C8 |
0 |
0 |
1 |
1 |
1 |
0 |
0 |
0 |
0 |
3 |
2 |
0 |
|
C9 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
2 |
0 |
0 |
1 |
0 |
2 |
0 |
|
WSD20 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C3 |
0 |
0 |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C5w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD21 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
0 |
0 |
3 |
2 |
4 |
3 |
0 |
0 |
1 |
4 |
5 |
0 |
Remarks:
- Station C2 is related to the Contract no. HK/2010/06 which was commenced on
23 March 2011;
-
Considering the absence of intake pump operation at Windsor House intake (C7),
this sensitive receiver was apparently not exist during this period so that no
water quality monitoring at C7 for compliance checking was undertaken in this
reporting month.
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/11- North Point Reclamation
¡P
Dredging works;
¡P
Reclamation
works;
¡P
Construction
& installation of Seawall Block;
¡P
Drainage
Construction works;
¡P
Floating out of
Caisson seawall;
¡P
Construction of
coping; and
¡P
Installation of
Caisson Seawall
Contract no. HK/2009/01 - Wan Chai Development Phase
II ¡V Central ¡VWanchai Bypass at HKCEC
¡P
Dredging for the
cross harbour water mains from Wan Chai side
¡P
Pipe line
installation for the cross harbour water mains from Wan Chai side;
¡P
Removal and
reinstatement of sloping seawall at Wan Chai;
¡P
Implementation
of TTM scheme at Convention Avenue, Harbour Road and Expo Drive (HKCEC area);
¡P
Pipe laying
works for cooling mains, harbour main & fresh water mains at Zone A1, A4,
A5, B1 & B4;
¡P
Tree
transplantation at Wan Chai and Tsim Sha Tsui;
¡P
Additional
wall openings penetration and construction work (over dimension 350mm x350mm)
for pipe sleeves and puddle flanges openings at Pump Station P1, 3, 4
& 5;
¡P
Equipment
concrete plinths construction inside pumping station;
¡P
E & M first
fixing work at HKCEC-II and pumping station P1, 3, 4, 5.
¡P
Removal of
armour rock at north side of HKCEC water channel (CH0 to CH160);
¡P
Laying
geotextile in the seawall slope at north side of HKCEC;
¡P
Reclamation
works at HKCEC water channel (CH0
to CH80);
¡P
Installation of
the sheet piling works for temporary water channel at the promenade pump house;
¡P
Dredging works
at HKCEC water channel(CH160 to CH250);
¡P
Installation of
conveyor belt for filling works at HKCEC water channel(CH0 to CH80);
¡P
Demolition of
promenade deck; and
¡P
Preparation, excavation
and pipe laying works at Convention Avenue and Harbour Road (Zones A2-2, A4-1,
A5-1, A5-5).
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Operating
Tseung Kwan O Public Fill Sorting Facility;
¡P
Internal and
external decoration for new public toilet at Expo Drive East;
¡P
Commence
E&M works for new public toilet at Expo Drive East;
¡P
Construction
of passenger terminal at Expo Drive East;
¡P
Modification of
existing seawall at Expo Drive East;
¡P
Trench
excavation and pipe laying works for cooling mains;
¡P
Excavation and
lateral support for construction of WSD Salt Water Pumping Station;
¡P
Sheet-piling
for construction of salt water intake culvert at Wan Shing Street;
¡P
Construction
of submarine outfall extension chamber;
¡P
Dredging and
pipe welding for submarine outfall pipe;
¡P
Marine piling
works for new ferry pier construction;
¡P
Complete
excavation and lateral support for jacking pit at ex-pet garden;
¡P
Driving
sheet-piles for receiving pit for DSD pipes;
¡P
Reclamation at
WCR1 area;
¡P
Pre-drilling
for bored piles and diaphragm wall at WCR1 area;
¡P
Guide wall
construction for diaphragm wall construction at WCR1 area;
¡P
Bored pile
construction (alternative design); and
¡P
Establish
plants for diaphragm wall construction
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section)
¡P
Filling at TS1
and TPCWAE;
¡P
Utility and
preparation work at CHT;
¡P
Alignment works
at Portion VII; and
¡P
Drainage works
at PRE office
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Dredging over
the MTR Tsuen Wan Line;
¡P
Disposal of Type
1 Marine Sediment; and
¡P
Mobilization for
the Construction of Temp. Platform of Piling Works
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009
and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009,
FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring
and auditing work carried out in accordance to the Section 10.3 of EM&A
Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under
Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
for Environmental Permit no. EP-356/2009, Further Environmental Permit no.
FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009 and FEP-04/356/2009 during
the period 28th February to 27th March 2011. The cut-off
date of reporting is at 27th of each reporting month.
Section 1 Introduction ¡V
details the scope and structure of the report.
Section 2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section 4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section 5 Monitoring
Results ¡V summarizes the monitoring results
obtained in the reporting period.
Section 6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section 7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section 8 Site Inspection ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review
of any relevant
follow-up actions
within the reporting period.
Section 9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai
Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨
(hereafter called ¡§the Project¡¨) are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment
(EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link
(Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan
Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001
and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB
to provide relief to the very congested east-west Connaught Road
Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1.
The Project is located mainly in Wan Chai North,
Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria
Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road
Interchange to the east, as shown in Figure 2.1.
2.2.2.
The study area encompasses existing developments
along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses
include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the
Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the
Royal Hong Kong Yacht Club (RHKYC), the Police Officers¡¦ Club, the Causeway Bay
Typhoon Shelter (CBTS) and commercial and residential developments.
2.2.3.
The scope of the Project
comprises:
¡P Land formation for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for connection to the Trunk Road and for through traffic from Central to Wan Chai and Causeway Bay. The land formed for the above transport infrastructure will provide opportunities for the development of an attractive waterfront promenade for the enjoyment of the public
¡P
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
¡P
Extension, modification,
reprovisioning or protection of existing storm water drainage outfalls,
sewerage outfalls and watermains affected by the revised land use and land
formation works mentioned above
¡P
Upgrading of
hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
¡P
Provision of the
ground level roads, flyovers, footbridges, necessary transport facilities and
the associated utility services
¡P
Construction of
the new waterfront promenade, landscape works and the associated utility
services
¡P
The Trunk Road
(i.e. CWB) within the study area and the associated slip roads for connection
to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (Eps) to be granted by the
DEP before they may be either constructed or operated. Table 2.1
summarises the five individual DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced.
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits (FEP) such that the impact monitoring
stations are sub-divided accordingly to facilitate the implementation of
EM&A programme and to streamline the EM&A reporting for individual FEP
holders correspondingly.
2.3.2.
The details of individual contracts are summarized
in Table 2.2.
Table 2.2 Details of Individual
Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
Pending |
||
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
Pending |
||
HY/2009/11 |
Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North
Point Reclamation |
DP3 |
17 March 2010 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November 2010 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
2.3.3.
Contract
no. HK/2010/06 ¡V Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR
Tsuen Wan Line was commenced on 20 January 2011. The commencement of
construction was on 22 March 2011.
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the
construction phase of the Project, Project Engineer, Contractor(s), Environmental
Team and Independent Environmental Checker are appointed to manage and control
environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact
Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
China Harbour- CRBC Joint Venture |
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
Simon Tong |
9124 2471 |
2634 1626 |
Site Agent |
Paul Yu |
9456 9819 |
|||
Operation Manager |
Lau Yee Ching |
9466 3918 |
|||
Construction Manager |
David Wong |
9653 8635 |
|||
Construction Manager |
Wilson Lau |
5183 1270 |
|||
Construction Manager |
Chan Mui Sang |
9864 8615 |
|||
Environmental Officer
(Compliance Manager) |
Brian Wan |
9312 2827 |
|||
Environmental Engineer |
Shelton Chan |
5395 5470 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Eric Lam |
3658-3048 |
|||
Environmental Officer (Compliance Manager) |
Mr. Barry Leung |
3658 3031 |
|||
Environmental Engineer |
Ms. Flora Ng |
3658-3064 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2528 5651 |
Site Agent |
Mr. K Y Leung |
9026 8808 |
2566 2192 |
||
|
|
Construction Manager |
Mr. C K Kwok |
9779 2162 |
|
|
|
Assistant Construction Manager (East) |
Mr. Gene Cheung |
6105 4880 |
|
|
|
Assistant Construction Manager (West) |
Mr. Tony Chiu |
9090 0606 |
|
|
|
Section Agent (East) |
Mr. Jason Chan |
9254 1635 |
|
|
|
Section Agent (West) |
Mr. Tang Ka Tung |
9473 4771 |
|
|
|
Environmental Manager |
Ms. Anna Yu |
9473 1945 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project Manager |
Mr. Simon Tong |
9124 2471 |
2529 2880 |
Site Agent |
Mr. Book Kin Man |
9193
8680 |
|||
Environmental Officer |
Mr. Lee Wai Man |
9481
6024 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental
Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HY/2009/11, the principal work
activities in this reporting month included:
¡P
Dredging works,
¡P
Reclamation
works,
¡P
Construction
& installation of Seawall Block; and
¡P
Drainage
Construction works.
2.4.4.
For Contract no. HK/2009/01, the principal work
activities in this reporting month included:
¡P
Dredging of
marine sediments for the open cut trench of cross harbour water mains and final
trimming for pipe trench (From CHA 450 to 970);
¡P
Removal of
existing rock-fill material at west side sloping seawall of HKCEC extension for
trench dredging of cross harbour water mains;
¡P
Excavation and
installation of shoring system for pipe laying work at Wan Chai (Zone A2-2);
¡P
For
transplanting 29 nos. of trees at Tsim Sha Tsui Salisbury Garden (South
Portion) and 7 nos. of trees at along Expo Drive (for jetty access
construction), transplanting of 11 more tress at Tsim Sha Tsui Salisbury (North
Portion) shall either be transplanted or felled prior to the pipe laying work
as per the updated pipe layout;
¡P
Pipe laying at
TST was commenced on early February and trench excavation;
¡P
After receiving
the latest as-built information from WSD, trial pit excavation for Wan Chai
connection points at Fenwick Pier Street footpath;
¡P
Routine maintenance
and clearance works for silt screens;
¡P
Coring works
(Stage 1: 42 nos. under 350mm diameter openings) at Pump House P1, P3, P4, and
P5;
¡P
Installation of
cooling main pipelines at HKCEC VIP Drop-Off Area (Zone B1-1) and reinstatement
works;
¡P
Installation of
cooling main pipelines at HKCEC Golden Bauhinia Garden (Zone B4-1), area were
backfilled and reinstatement to be commenced;
¡P
Installation of
cooling main pipelines at HKCEC West Wing (Zone B1-2) is on-going (approx. 140m
pipe length completed). Portion of area A were reinstated and cleared on 18
Mar. 2011;
¡P
Due to
construction of SCL works, trial trench construction for temporary diversion of
Convention Plaza discharge mains;
¡P
Excavation for
connection points for Shui On (AE & BE) at Convention Avenue (Zone A2-2)
have to be enlarged for tentative pipe connection work;
¡P
Installation of
another 6 pipe piles;
¡P
Demolition of
staging platform; and
¡P
Removal of rock
armour along north shore of HKCEC water channel
2.4.5.
For Contract no. HK/2009/02, the principal work
activities in this reporting month included:
¡P
No sorted fill produce at Tseung Kwan O
public fill sorting facility;
¡P
Finishing works and remedial works
for new public toilet was completed;
¡P
Internal decoration for new
public toilet was commenced;
¡P
External decoration for new
public toilet was commenced;
¡P
Partial
demolition of existing ferry pier at Expo Drive East was completed;
¡P
Existing jetty pier at Expo
Drive East was relocated;
¡P
Preparation
works for seawall modification at Expo Drive East was completed;
¡P
Modification
of existing seawall at Expo Drive East was commenced;
¡P
Excavation at
Harbour Road and Harbour Centre for cooling mains;
¡P
24m cooling
water mains was laid at Harbour Road;
¡P
Sun Hung Kai tee
connection was carried out;
¡P
China Resource
Building tee connection was carried out;
¡P
Driving
remaining sheet-piles for excavation and lateral support at WSD Salt Water
Pumping Station was completed;
¡P
Curtain grout
works at WSD Salt Water Pumping Station was carried
out;
¡P
Excavation and
lateral support;
¡P
Driving sheet-piles
at Wan Shing Street for WSD Intake Culvert;
¡P
Dredging for
submarine outfall pipe was ongoing;
¡P
Installation
of T6 & T7 seawall blocks was commenced;
¡P
Curtain grout
for jacking pit at ex-pet garden was carried out;
¡P
Excavation and
lateral support for jacking pit at ex-pet garden was commenced
¡P
Tunnel bored
pile works;
¡P
Guide wall for
diaphragm wall construction;
¡P
Establishment
of desander and silo for diaphragm wall construction was commenced;
¡P
Pre-drilling
of bored pile and diaphragm wall;
¡P
1800 diameter
drainage diversion was completed; and
¡P
Road work for
Hung Hing Road traffic diversion was completed.
2.4.6.
For Contract no. HY/2009/15, the principal work
activities in this reporting month included:
¡P
Rock removal at
TS4 and TPCWA;
¡P
Seawall block
construction at TS1 and TPCWAE;
¡P
Night time
protection works at CHT;
¡P
Ground
investigation and trial pit excavation; and
¡P
Drainage works
at PRE office
2.4.7.
For Contract no. HK/2010/06, the principal work
activities in this reporting month included:
¡P
Installation of
Silt Curtain for Dredging Works;
¡P
Dredging over
the MTR Tsuen Wan Line; and
¡P
Pre-construction
Condition Survey inside MTR tunnel
2.4.8.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. HY/2009/11- North Point Reclamation
¡P
Dredging works;
¡P
Reclamation
works;
¡P
Construction
& installation of Seawall Block;
¡P
Drainage
Construction works;
¡P
Floating out of
Caisson seawall;
¡P
Construction of
coping; and
¡P
Installation of
Caisson Seawall
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
¡P
Fabrication of
the pipe strings in factory;
¡P
Dredging for the
cross harbour water mains from Wan Chai side;
¡P
Pipe line
installation for the cross harbour water mains from Wan Chai side;
¡P
Removal and
reinstatement of sloping seawall at Wan Chai;
¡P
Cooling Water
Pumping Station and Associated Intake and Discharge Pipelines;
¡P
Implementation
of TTM scheme at Convention Avenue, Harbour Road and Expo Drive (HKCEC area);
¡P
Pipe laying
works for cooling mains, harbour main & fresh water mains at Zone A1, A4,
A5, B1 & B4;
¡P
Tree
transplantation at Wan Chai;
¡P
Additional wall
openings penetration snd construction work (over diamension 350mm x350mm )for
pipe sleeves and puddle flanges openings at Pump Station P1,3, 4 & 5;
¡P
Equipment
concrete plinths construction inside pumping station;
¡P
E & M first
fixing work at HKCEC-II and pumping station P1, 3, 4, 5;
¡P
Central-Wan Chai
Bypass (CWB) Tunnel and Associated Slip Roads 2 & 3
¡P
Installation of
pipe pile wall P1;
¡P
Removal of
armour rock at north side (CH0 to CH160) of HKCEC;
¡P
Laying
geotextile in the seawall slope at north side of HKCEC;
¡P
Reclamation
works at HKCEC water channel (CH 0 to CH160);
¡P
Installation of
the sheet piling works for temporary water channel at the promenade pump house;
¡P
Dredging works
at HKCEC water channel (CH160 to CH250);
¡P
Installation of
conveyor belt for filling works at HKCEC water channel;
¡P
Demolition of
promenade deck;
¡P
The WSD DN450mm
& DN800mm Salt Water Mains; and
¡P
Preparation,
excavation and pipe laying works at Convention Avenue and Harbour Road (Zones
A2-2, A4-1, A5-1, A5-5).
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Operating
Tseung Kwan O Public Fill Sorting Facility;
¡P
Internal and
external decoration for new public toilet at Expo Drive East;
¡P
Commence
E&M works for new public toilet at Expo Drive East;
¡P
Construction
of passenger terminal at Expo Drive East;
¡P
Modification of
existing seawall at Expo Drive East;
¡P
Trench
excavation and pipe laying works for cooling mains;
¡P
Excavation and
lateral support for construction of WSD Salt Water Pumping Station;
¡P
Sheet-piling
for construction of salt water intake culvert at Wan Shing Street;
¡P
Construction
of submarine outfall extension chamber;
¡P
Dredging and
pipe welding for submarine outfall pipe;
¡P
Marine piling
works for new ferry pier construction;
¡P
Complete
excavation and lateral support for jacking pit at ex-pet garden;
¡P
Driving
sheet-piles for receiving pit for DSD pipes;
¡P
Reclamation at
WCR1 area;
¡P
Pre-drilling
for bored piles and diaphragm wall at WCR1 area;
¡P
Guide wall
construction for diaphragm wall construction at WCR1 area;
¡P
Bored pile
construction (alternative design); and
¡P
Establish
plants for diaphragm wall construction
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section)
¡P
Rock removal at
TS4;
¡P
Filling at TS1
and TPCWAE;
¡P
Utility and
preparation work at CHT;
¡P
Alignment works
at Portion VII; and
¡P
Drainage works
at PRE office
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Dredging over
the MTR Tsuen Wan Line;
¡P
Disposal of Type
1 Marine Sediment; and
¡P
Mobilization for
the Construction of Temp. Platform of Piling Works
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009/A |
4 Aug
2010 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb
2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
22 Nov
2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Valid |
Further
Environmental Permit |
FEP-01/364/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further
Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Valid |
Further
Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Valid |
Further
Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract
no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation
3.1.3.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-01/356/2009 for contract no. HY/2009/11 are shown in Table 3.2 and
Table 3.3.
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/11
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
N/A |
Valid |
Notification of Works Under APCO |
314911 |
9 Mar 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0870-10 |
6 Oct 2010 |
1 Nov 2010 to 30 Apr 2011 |
Valid |
Registration as a Chemical Waste Producer |
WPN: 5213-151-C3631-02 |
12 Oct 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7010037 |
13 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00007942-2010 |
29 Nov 2010 |
30 Nov 2015 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/10-055 |
26 Aug 2010 |
10 Sep 2010 to 30 Dec 2010 |
Expired |
|
EP/MD/11-116 |
29 Dec 2010 |
31 Dec 2010 to 28 Jun 2011 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) |
EP/MD/11-124 |
24 Jan 2011 |
31 Jan to 27 Feb 2011 |
Expired |
EP/MD/11-137 |
24 Feb 2011 |
28 Feb 2011 to 30 Mar 2011 |
Valid |
Table 3.3 Summary
of submission
status under FEP-01/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
18 Dec 2009 |
Condition 2.7 |
Submission of works schedule
and location plan |
8 Feb 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
25 Feb 2010 |
|
Revised Silt Curtain Deployment
Plan (Rev. 3) |
4 Dec 2010 |
Condition 2.9 |
Silt Screen Deployment Plan |
25 Feb 2010 |
|
Revised Silt Screen Deployment
Plan |
10 May 2010 |
|
Silt Screen Deployment Plan
(Rev. 4) |
1 Nov 2010 |
|
Silt Screen Deployment Plan
(Rev. 5) |
18 Mar 2011 |
Condition 2.10 |
Coral Translocation Plan |
20 Nov 2009 |
Condition 2.16 |
Noise Management Plan |
1 Mar 2010 |
|
Revised Noise Management Plan |
28 Sep 2010 |
|
Revised Noise Management Plan
(Rev 5) |
19 Feb 2011 |
Condition 2.17 |
Landscape Plan |
12 May 2010 |
|
Revised landscape Plan |
30 Jun 2010 |
|
Submission of Supplementary
Information - Revised Management & Maintenance Schedule for Submitted
Revised Landscape Plan |
25 Aug 2010 |
Contract
no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at
HKCEC
3.1.4.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and
Table 3.5.
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling equipment |
PP-RS0045-10 |
21 Dec 2010 |
21 Dec 2010 to 20 Jun 2011 |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0763-10 |
1 Sep 2010 |
14 Sep 2010 to 14 Mar 2011 |
Superseded |
|
GW-RS0771-10 |
1 Sep 2010 |
1 Sep 2010 to 28 Feb 2011 |
Expired |
|
GW-RS0772-10 |
3 Sep 2010 |
15 Sep 2010 to 14 Mar 2011 |
Superseded |
|
GW-RS0819-10 |
15 Sep 2010 |
16 Sep 2010 to 15 Mar 2011 |
Expired |
|
GW-RS0900-10 |
20 Oct 2010 |
27 Oct 2010 to 26 Mar 2011 |
Superseded |
|
GW-RS0965-10 |
8 Nov 2010 |
22 Nov 2010 to 21 May 2011 |
Valid |
|
GW-RS1034-10 |
26 Nov 2010 |
27 Nov 2010 to 26 May 2011 |
Valid |
|
GW-RS1074-10 |
3 Dec 2010 |
09 Dec 2010 to 08 Jun 2011 |
Valid |
|
GW-RS1119-10 |
23 Dec 2010 |
23 Dec 2010 to 22 Jun 2011 |
Superseded |
|
GS-RS0022-11 |
12 Jan 2011 |
23 Jan 2011 to 22 Jul 2011 |
Valid |
|
GW-RS0107-11 |
8 Feb 2011 |
16 Mar 2011 to 15 Sep 2011 |
Valid |
|
GW-RS0111-11 |
11 Feb 2011 |
28 Feb 2011 to 31 Aug 2011 |
Valid |
|
GW-RS0233-11 |
17 Mar 2011 |
25 Mar 2011 to 25 Apr 2011 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
Billing account under Waste
Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/11-083 |
23 Nov 2010 |
24 Nov 2010 to 23 May 2011 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) |
EP/MD/11-131 |
31 Jan 2011 |
8 Feb 2011 to 7 Mar 2011 |
Valid |
EP/MD/11-147 |
1 Mar 2011 |
8 Mar to 7 Apr 2011 |
Valid |
Table 3.5 Summary
of submission
status under FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
13 Apr 2010 |
Condition 2.7 |
Works Schedule and Location
Plan |
8 Apr 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
19 Apr 2010 |
Condition 2.9 |
Silt Screen Deployment Plan |
19 Apr 2010 |
Conditions 2.8 and 2.9 |
Supplementary Document on Silt
Curtain and Silt Screen Deployment Plan |
19 Jul 2010 |
Report on Field Testing for
Silt Curtain |
26 Aug 2010 |
|
Report on Field Testing for
Silt Curtain (Rev. A) |
15 Nov 2010 |
|
Condition 2.17 |
Noise Management Plan |
23 Apr 2010 |
Condition 2.18 |
Landscape Plan (Erection of
Decorative Screen Hoarding along Construction Site around Hong Kong Exhibition
and Convention Centre) |
15 May 2010 |
Landscape Plan (Night-time
Lighting) |
22 Oct 2010 |
|
|
Landscape Plan (Rev. B) |