Contract No: HK/2009/05 Wanchai
Development Phase II and Sampling,
Field Measurement and Testing Work (Stage 1) Environmental Permit no.
EP-356/2009, Further
Evironmental permit nos. fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009
and Fep-05/356/2009 Monthly
Environmental Monitoring & Audit Report
- May 2011 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185
Gloucester Road, Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
14 June 2011 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of Water Quality Monitoring Exceedances in
Reporting Month
Table 2.1 Schedule 2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/11
Table 3.3 Summary of submission status under FEP-01/356/2009
Condition
Table 3.4 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/01
Table 3.5 Summary of submission status under FEP-02/356/2009
Condition
Table 3.6 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/02
Table 3.7 Summary of submission status under FEP-03/356/2009
Condition
Table 3.8 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/15
Table 3.9 Summary of submission status under FEP-04/356/2009
Condition
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2010/06
Table 3.11 Summary of submission status under EP-356/2009 and
FEP-05/356/2009 Condition
Table 4.1 Noise Monitoring Station
Table 4.2 Real Time Noise Monitoring Station
Table 4.3 Air Monitoring Station
Table 4.4 Marine Water Quality Stations for Water Quality
Monitoring
Table 4.5 Marine Water Quality Monitoring Frequency and
Parameters
Table 4.6 Marine Water Quality Stations for Enhanced Water
Quality Monitoring
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/11
Table 5.2 Noise Monitoring Station for Contract nos. HK/2009/01,
HK/2009/02 and HK/2010/06
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/15
Table 5.4 Real Time Noise Monitoring Station for Contract no.
HY/2009/11
Table 5.5 Air Monitoring Stations for Contract no. HY/2009/11
Table 5.6 Air Monitoring Stations for Contract no. HK/2009/01
Table 5.7 Air Monitoring Station for Contract no. HK/2009/02
Table 5.8 Air Monitoring Station for Contract no. HY/2009/15
Table 5.9 Water Monitoring Stations for Contract no. HY/2009/11
Table 5.10 Water Monitoring Stations for Contract no. HK/2009/01
Table 5.11 Water Monitoring Stations for Contract no. HK/2009/02
Table 5.12 Water Monitoring Stations for Contract no. HK/2009/02
Table 5.14 Summary of Water Quality Monitoring Exceedances in
Reporting Month
Table 5.15 Details of Waste Disposal for Contract no. HY/2009/11
Table 5.16 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.17 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.18 Details of Waste Disposal for Contract no. HY/2009/15
Table 5.19 Details of Waste Disposal for Contract no. HK/2010/06
Table 8.1 Summary of Environmental Inspections for Contract no.
HY/2009/11
Table 8.2 Summary of Environmental Inspections for Contract no.
HK/2009/01
Table 8.3 Summary of Environmental Inspections for Contract no.
HK/2009/02
Table 8.4 Summary of Environmental Inspections for Contract no.
HY/2009/15
Table 8.5 Summary of Environmental Inspections for Contract no.
HK/2010/06
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended Mitigation
Measures in Coming Reporting Month
lIST
OF FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project
Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST
OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming
month
Appendix 5.2 Noise Monitoring Results and
Graphical Presentations
Appendix 5.3 Air Quality
Monitoring Results and Graphical Presentations
Appendix 5.4 Water Quality
Monitoring Results and Graphical Presentations
Appendix 5.5 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Summary for Notification of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction
Programme of Individual Contracts
Construction Activities for the Reported Period
¡P
Reclamation
works;
¡P
Concreting;
¡P
Slotted panel
fixing;
¡P
Drainage
Construction works;
¡P
Construction
& installation of Seawall Block;
¡P
Construction of
coping and outfall construction works; and
¡P
Installation of
Caisson Seawall.
¡P
All dredging
works for HKCEC1 reclamation;
¡P
HKCEC Water
Channel for the reclamation of HKCEC1;
¡P
Demolition of
the existing seawall at VIP Drop-off Area for Cross-Harbour Watermains
installation;
¡P
Installation of
Cross-Harbour Water Mains nos. A1 & B1;
¡P
Dredging within
the MTR Protection Boundary for the installation of Cross-Harbor Watermains
nos. A2 & B2;
¡P
Platform
erection for crawler crane mobilization near the existing seawall at Salisbury
Garden;
¡P
Tee-off
connection between cooling mains intake pipe of Government Towers and the
existing system at Convention Avenue;
¡P
Trench
excavation for proposed pipe laying works in Convention Avenue was in progress;
¡P
Proposed
drainage works at VIP Drop-off Area near HKCEC West;
¡P
Temporary
diversion of 2 nos. DN900 cooling water discharge pipes of Convention Plaza;
¡P
Trench
excavation for a 1000 dia. watermains at Salisbury Garden;
¡P
Demolition of
the existing Promenade Deck at the junction between Convention Avenue and Expo
Drive;
¡P
Pre-drilling
works for the proposed SCL D-Wall;
¡P
Infilling concrete
wall between the return wall (replacing the original PQ31 to PQ34) and the
existing seawall at North Bank of HKCEC Channel; and
¡P
Infilling
concrete wall between PQ1 and the existing seawall at the junction between
Convention Avenue and Expo Drive
¡P
Tseung Kwan O public fill sorting facility
¡P
Internal decoration, external decoration, E&M works and power on for
new public toilet;
¡P
Laying and connecting water and drainage pipe;
¡P
Disable ramp for new public toilet
¡P
Foam concrete for new passenger terminal building
¡P
Ground floor slab for new passenger terminal building
¡P
Modification of existing finger pier deck and tree pits
¡P
Installation of precast manholes and pillar boxes
¡P
The relocated tour ferry pontoon was reinstated;
¡P
Modification of existing seawall;
¡P
A thrust block was cast at Harbour Road;
¡P
Approximate
¡P
Trench excavation at Tonnochy Road;
¡P
Excavation and lateral support for WSD Salt Water Pumping Station at Wan
Shing Street was continued. 4th layer of struts;
¡P
Temporary Traffic Deck at Wan Shing Street for WSD Intake Culvert;
¡P
Dredging for submarine outfall pipe;
¡P
Approximate
¡P
Connection chamber at DSD Screening Plant, modification of strutting and
wall pour ;
¡P
Excavation and lateral support for jacking pit at ex-pet garden;
¡P
Blinding layer for jacking pit at ex-pet garden was cast;
¡P
Excavation and lateral support for WSD & DSD receiving pits;
¡P
Marine piling works for new ferry pier was ongoing. 21 out of 83 nos
marine piles was completed as of 20 May 2011;
¡P
Remedial works for Eastern Temporary Seawall;
¡P
Tunnel bored pile works in WCR1;
¡P
Diaphragm wall construction; and
¡P
Guide wall construction and pre-treatment for diaphragm wall in WCR1
Area
¡P
Seawall block
construction at TS4;
¡P
Filling work at
TS1 and TPCWAE;
¡P
Access formation
at TS1;
¡P
Grouting works
at Abutment A;
¡P
Night time
protection works at CHT; and
¡P
Trial trench
work at Hung Hing Road and POC
¡P
Dredging over
the MTR Tsuen Wan Line;
¡P
Disposal of Type
1 and Type 2 Sediment;
¡P
Mobilization of
Piling and Staging Works; and
¡P
Erection of
Staging Platform
Noise Monitoring
Real-time Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
Table
I Summary of Water Quality
Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring
Station |
Mid-flood |
Mid-ebb |
||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
|
WSD17 |
0 |
0 |
1 |
1 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C8 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
|
C9 |
0 |
0 |
0 |
1 |
3 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
|
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
|
C3 |
0 |
0 |
1 |
3 |
1 |
1 |
0 |
0 |
1 |
7 |
3 |
3 |
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C5w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
0 |
0 |
2 |
6 |
6 |
2 |
0 |
0 |
5 |
7 |
6 |
3 |
- The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
- It was not included the exceedances recorded at C3 in the daily monitoring from 17 May to 27 May 2011.
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
-
Contract no. HY/2009/11- North Point Reclamation
¡P
Reclamation works;
¡P
Concreting;
¡P
Slotted panel
fixing;
¡P
Drainage
Construction works;
¡P
Outfall
construction works;
¡P
Construction
& installation of Seawall Block; and
¡P
Installation of
Caisson Seawall.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
¡P
Reclamation
within HKCEC Water Channel;
¡P
Sheet pile installation
for a temporary water channel covering the existing cooling water intake at
Dome Promenade;
¡P
Dredging within
MTRCL protection boundary would be continued prior to the commencement of
preparation works for installation of Cross-Harbour Watermains nos. A2 &
B2;
¡P
Installation of
Cross-Harbour Watermains nos. A2 & B2 and A3 and B3 would be carried out;
¡P
Platform
erection for crawler crane mobilization near the existing seawall at Salisbury
Garden;
¡P
Works would be continued
at VIP Drop-off Area, Convention Avenue and Fleming Road;
¡P
Main laying
works at VIP Drop-off area;
¡P
Thrust block
construction and trench backfilling works would be carried out;
¡P
Infilling of
mass concrete between PQ1 and existing seawall at South Bank of HKCEC Water
Channel;
¡P
Pre-drilling
works would be continued along SCL D-Wall aliment (South Side) and be extent to
the whole CWB area;
¡P
Pre-bored
H-pilling works for CWB Mainline;
¡P
Plant mobilization,
ground treatment works and guide wall construction for proposed CWB & SCL
D-Wall; and
¡P
All outstanding geotechnical
instrumentation for construction of CWB & SCL Protection Works would be
installed
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Continue
operating Tseung Kwan O Public Fill Sorting Facility;
¡P
Complete
internal and external decoration for new public toilet at Expo Drive East;
¡P
Complete E&M
works for new public toilet at Expo Drive East;
¡P
Commence and
complete modification existing hoarding for new public toilet opening;
¡P
Continue
construction of passenger terminal at Expo Drive East;
¡P
Complete
modification of existing finger pier decking;
¡P
Commence
remaining demolition of existing pier at Expo Drive East;
¡P
Continue trench
excavation and pipe laying works for cooling mains;
¡P
Continue trench
excavation at Tonnochy Road;
¡P
Commence and
complete lean concrete at P7, P8 and P9 pump station;
¡P
Complete
excavation and lateral support for WSD Salt Water Pumping Station at Wan Shing
Street;
¡P
Commence the
construction of WSD Salt Water Pumping Station at Wan Shing Street;
¡P
Commence
excavation and lateral support for construction of salt water intake culvert at
Wan Shing Street;
¡P
Commence
pre-bored H-pile for WSD Salt Water Intake Culvert at WCR1 Area;
¡P
Continue
dredging, pipe welding and pipe laying works for submarine outfall pipe;
¡P
Complete
connection chamber at DSD Screening Plant;
¡P
Commence the
horizontal directional drill for pipe jacking across Hung Hing Road;
¡P
Commence
pre-grouting along pipe jacking alignment across Hung Hing Road.
¡P
Continue
excavation and lateral support for receiving pits;
¡P
Continue marine
piling works for new ferry pier;
¡P
Continue tunnel
bored pile works;
¡P
Continue guide
wall construction for diaphragm wall construction; and
¡P
Continue
pre-treatment for diaphragm wall construction.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section)
¡P
Seawall block
construction at TS4;
¡P
Dredging of
odorous sediment at TS4;
¡P
Filling at TS4;
¡P
Site investigation
at TS1 and TPCWAE;
¡P
Excavation for
diaphragm wall construction at TS1 and TPCWAE; and
¡P
Grouting works
at Abutment A
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Disposal of Type
1 and Type 2 Sediment; and
¡P
Erection of
Staging Platform
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009
and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009,
FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring
and auditing work carried out in accordance to the Section 10.3 of EM&A
Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under
Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
for Environmental Permit no. EP-356/2009, Further Environmental Permit no.
FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and
FEP-05/356/2009 and during the period 28th April to 27th May
2011. The cut-off date of reporting is at 27th of each reporting
month.
Section
1 Introduction ¡V
details the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results
obtained in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Site Inspection ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review
of any relevant
follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai
Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨
(hereafter called ¡§the Project¡¨) are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment
(EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link
(Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan
Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001
and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB
to provide relief to the very congested east-west Connaught Road
Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1.
The Project is located mainly in Wan Chai North,
Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria
Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road
Interchange to the east, as shown in Figure 2.1.
2.2.2.
The study area encompasses existing developments
along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses
include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the
Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the
Royal Hong Kong Yacht Club (RHKYC), the Police Officers¡¦ Club, the Causeway Bay
Typhoon Shelter (CBTS) and commercial and residential developments.
2.2.3.
The scope of the Project
comprises:
¡P
Land formation
for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated
slip roads for connection to the Trunk Road and for through traffic from Central to
Wan Chai and Causeway Bay. The land formed for the above transport infrastructure
will provide opportunities for the development of an attractive waterfront
promenade for the enjoyment of the public
¡P
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
¡P
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
¡P
Upgrading of
hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
¡P
Provision of the
ground level roads, flyovers, footbridges, necessary transport facilities and
the associated utility services
¡P
Construction of
the new waterfront promenade, landscape works and the associated utility
services
¡P
The Trunk Road
(i.e. CWB) within the study area and the associated slip roads for connection
to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1
summarises the five individual DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced.
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits (FEP) such that the impact monitoring
stations are sub-divided accordingly to facilitate the implementation of
EM&A programme and to streamline the EM&A reporting for individual FEP
holders correspondingly.
2.3.2.
The details of individual contracts are summarized
in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
Pending |
||
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North
Point Reclamation |
DP3 |
17 March 2010 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November 2010 |
DP1 |
Pending |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and Highways
Department are the overall project controllers for the Wan Chai Development
Phase II and Central-Wan Chai Bypass respectively. For the construction phase
of the Project, Project Engineer, Contractor(s), Environmental Team and
Independent Environmental Checker are appointed to manage and control
environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars
are summarized in Table 2.3:
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
China Harbour- CRBC Joint Venture |
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
Simon Tong |
9124 2471 |
2634 1626 |
Site Agent |
Paul Yu |
9456 9819 |
|||
Operation Manager |
Lau Yee Ching |
9466 3918 |
|||
Construction Manager |
David Wong |
9653 8635 |
|||
Construction Manager |
Wilson Lau |
5183 1270 |
|||
Construction Manager |
Chan Mui Sang |
9864 8615 |
|||
Environmental Officer
(Compliance Manager) |
Brian Wan |
9312 2827 |
|||
Environmental Engineer |
Shelton Chan |
5395 5470 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Eric Lam |
3658 3048 |
|||
Deputy Site Agent |
Mr. Anthony Wu |
3658 3004 |
|||
Quality & Environmental Manager |
Mr. C.P. Ho |
3658 3000 |
|||
Environmental Officer |
Ms. Flora Ng |
3658 3064 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2528 5651 |
Site Agent |
Mr. Simon Tang |
3557 6358 |
2566 2192 |
||
|
|
Construction Manager |
Mr. C K Kwok |
9779 2162 |
|
|
|
Assistant Construction Manager (East) |
Mr. Gene Cheung |
6105 4880 |
|
|
|
Assistant Construction Manager (West) |
Mr. Tony Chiu |
9090 0606 |
|
|
|
Section Agent (East) |
Mr. Jason Chan |
9254 1635 |
|
|
|
Section Agent (West) |
Mr. Tang Ka Tung |
9473 4771 |
|
|
|
Environmental Manager |
Mr. Samuel Tsui |
3557 6347 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project Manager |
Mr. Simon Tong |
9124 2471 |
2529 2880 |
Site Agent |
Mr. Book Kin Man |
9193
8680 |
|||
Environmental Officer |
Mr. Lee Wai Man |
9481
6024 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HY/2009/11, the principal work
activities in this reporting month included:
¡P
Reclamation
works;
¡P
Concreting;
¡P
Slotted panel
fixing;
¡P
Drainage
Construction works;
¡P
Construction
& installation of Seawall Block;
¡P
Construction of
coping and outfall construction works; and
¡P
Installation of
Caisson Seawall.
2.4.4.
For Contract no. HK/2009/01, the principal work
activities in this reporting month included:
¡P
All dredging
works for HKCEC1 reclamation;
¡P
HKCEC Water
Channel for the reclamation of HKCEC1;
¡P
Demolition of
the existing seawall at VIP Drop-off Area for Cross-Harbour Watermains
installation;
¡P
Installation of
Cross-Harbour Water Mains nos. A1 & B1;
¡P
Dredging within
the MTR Protection Boundary for the installation of Cross-Harbor Watermains
nos, A2 & B2;
¡P
Platform
erection for crawler crane mobilization near the existing seawall at Salisbury
Garden;
¡P
Tee-off
connection between cooling mains intake pipe of Government Towers and the
existing system at Convention Avenue;
¡P
Trench
excavation for proposed pipe laying works in Convention Avenue was in progress;
¡P
Proposed
drainage works at VIP Drop-off Area near HKCEC West;
¡P
Temporary
diversion of 2 nos. DN900 cooling water discharge pipes of Convention Plaza;
¡P
Trench
excavation for a 1000 dia. watermains at Salisbury Garden;
¡P
Demolition of
the existing Promenade Deck at the junction between Convention Avenue and Expo
Drive;
¡P
Pre-drilling
works for the proposed SCL D-Wall;
¡P
Infilling
concrete wall between the return wall (replacing the original PQ31 to PQ34) and
the existing seawall at North Bank of HKCEC Channel; and
¡P
Infilling
concrete wall between PQ1 and the existing seawall at the junction between
Convention Avenue and Expo Drive
2.4.5.
For Contract no. HK/2009/02, the principal work
activities in this reporting month included:
¡P
Tseung Kwan O
public fill sorting facility
¡P
Internal
decoration, external decoration, E&M works and power on for new public
toilet;
¡P
Laying and
connecting water and drainage pipe;
¡P
Disable ramp for
new public toilet
¡P
Foam concrete
for new passenger terminal building
¡P
Ground floor
slab for new passenger terminal building
¡P
Modification of
existing finger pier deck and tree pits
¡P
Installation of
precast manholes and pillar boxes
¡P
The relocated
tour ferry pontoon was reinstated;
¡P
Modification of
existing seawall;
¡P
A thrust block
was cast at Harbour Road;
¡P
Approximate
¡P
Trench
excavation at Tonnochy Road;
¡P
Excavation and
lateral support for WSD Salt Water Pumping Station at Wan Shing Street was
continued. 4th layer of struts;
¡P
Temporary
Traffic Deck at Wan Shing Street for WSD Intake Culvert;
¡P
Dredging for
submarine outfall pipe;
¡P
Approximate
¡P
Connection
chamber at DSD Screening Plant, modification of strutting and wall pour ;
¡P
Excavation and
lateral support for jacking pit at ex-pet garden;
¡P
Blinding layer
for jacking pit at ex-pet garden was cast;
¡P
Excavation and
lateral support for WSD & DSD receiving pits;
¡P
Marine piling
works for new ferry pier was ongoing. 21 out of 83 nos marine piles was
completed as of 20 May 2011;
¡P
Remedial works
for Eastern Temporary Seawall;
¡P
Tunnel bored
pile works in WCR1 area;
¡P
Diaphragm wall construction; and
¡P
Guide wall construction and pre-treatment for diaphragm wall in WCR1
Area
2.4.6.
For Contract no. HY/2009/15, the principal work
activities in this reporting month included:
¡P
Seawall block construction at TS4
¡P
Filling work at TS1 and TPCWAE
¡P
Access formation at TS1
¡P
Grouting works at Abutment A
¡P
Night time protection works at CHT
¡P
Trial trench work at Hung Hing Road and POC
2.4.7.
For Contract no. HK/2010/06, the principal work
activities in this reporting month included:
¡P
Dredging over
the MTR Tsuen Wan Line;
¡P
Disposal of Type
1 and Type 2 Sediment;
¡P
Mobilization of
Piling and Staging Works; and
¡P
Erection of
Staging Platform
2.4.8.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. HY/2009/11- North Point Reclamation
¡P
Reclamation
works;
¡P
Concreting;
¡P
Slotted panel
fixing;
¡P
Drainage
Construction works;
¡P
Outfall
construction works;
¡P
Construction
& installation of Seawall Block; and
¡P
Installation of
Caisson Seawall.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
¡P
Reclamation
within HKCEC Water Channel;
¡P
Sheet pile installation
for a temporary water channel covering the existing cooling water intake at
Dome Promenade;
¡P
Dredging within
MTRCL protection boundary would be continued prior to the commencement of
preparation works for installation of Cross-Harbour Watermains nos. A2 &
B2;
¡P
Installation of
Cross-Harbour Watermains nos. A2 & B2 and A3 and B3 would be carried out;
¡P
Platform
erection for crawler crane mobilization near the existing seawall at Salisbury
Garden;
¡P
Works would be continued
at VIP Drop-off Area, Convention Avenue and Fleming Road;
¡P
Main laying
works at VIP Drop-off area;
¡P
Thrust block
construction and trench backfilling works would be carried out;
¡P
Infilling of
mass concrete between PQ1 and existing seawall at South Bank of HKCEC Water
Channel;
¡P
Pre-drilling
works would be continued along SCL D-Wall aliment (South Side) and be extent to
the whole CWB area;
¡P
Pre-bored
H-pilling works for CWB Mainline;
¡P
Plant mobilization,
ground treatment works and guide wall construction for proposed CWB & SCL
D-Wall; and
¡P
All outstanding geotechnical
instrumentation for construction of CWB & SCL Protection Works would be
installed
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Continue
operating Tseung Kwan O Public Fill Sorting Facility;
¡P
Complete
internal and external decoration for new public toilet at Expo Drive East;
¡P
Complete E&M
works for new public toilet at Expo Drive East;
¡P
Commence and
complete modification existing hoarding for new public toilet opening;
¡P
Continue
construction of passenger terminal at Expo Drive East;
¡P
Complete
modification of existing finger pier decking;
¡P
Commence
remaining demolition of existing pier at Expo Drive East;
¡P
Continue trench
excavation and pipe laying works for cooling mains;
¡P
Continue trench
excavation at Tonnochy Road;
¡P
Commence and
complete lean concrete at P7, P8 and P9 pump station;
¡P
Complete
excavation and lateral support for WSD Salt Water Pumping Station at Wan Shing
Street;
¡P
Commence the
construction of WSD Salt Water Pumping Station at Wan Shing Street;
¡P
Commence
excavation and lateral support for construction of salt water intake culvert at
Wan Shing Street;
¡P
Commence
pre-bored H-pile for WSD Salt Water Intake Culvert at WCR1 Area;
¡P
Continue
dredging, pipe welding and pipe laying works for submarine outfall pipe;
¡P
Complete
connection chamber at DSD Screening Plant;
¡P
Commence the
horizontal directional drill for pipe jacking across Hung Hing Road;
¡P
Commence pre-grouting
along pipe jacking alignment across Hung Hing Road.
¡P
Continue
excavation and lateral support for receiving pits;
¡P
Continue marine
piling works for new ferry pier;
¡P
Continue tunnel
bored pile works;
¡P
Continue guide
wall construction for diaphragm wall construction; and
¡P
Continue
pre-treatment for diaphragm wall construction.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section)
¡P
Seawall block
construction at TS4;
¡P
Dredging of
odorous sediment at TS4;
¡P
Filling at TS4;
¡P
Site
investigation at TS1 and TPCWAE;
¡P
Excavation for
diaphragm wall construction at TS1 and TPCWAE; and
¡P
Grouting works
at Abutment A
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Marine Bored
Piling;
¡P
Disposal of Type
1 and Type 2 Sediment; and
¡P
Erection of
Staging Platform
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009/A |
4 Aug
2010 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb
2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
22 Nov
2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Valid |
Further
Environmental Permit |
FEP-01/364/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further
Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Valid |
Further
Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Valid |
Further
Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HY/2009/11 ¡V
Central ¡V Wanchai Bypass, North Point Reclamation
3.1.3.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-01/356/2009 for contract no. HY/2009/11 are shown in Table 3.2 and
Table 3.3.
-
-
Table
3.2 Cumulative Summary of Valid Licences
and Permits
under Contract no. HY/2009/11
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
N/A |
Valid |
Notification of Works Under APCO |
314911 |
9 Mar 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0870-10 |
6 Oct 2010 |
1 Nov 2010 to 30 Apr 2011 |
Expired |
|
GW-RS0330-11 |
15 Apr 2011 |
1 May 2011 to 31 Oct 2011 |
Valid |
Registration as a Chemical Waste Producer |
WPN: 5213-151-C3631-02 |
12 Oct 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7010037 |
13 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00007942-2010 |
29 Nov 2010 |
30 Nov 2015 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/11-116 |
29 Dec 2010 |
31 Dec 2010 to 28 Jun 2011 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) |
EP/MD/11-162 |
23 Mar 2011 |
31 Mar 2011 to 29 Apr 2011 |
Expired |
EP/MD/12-008 |
28 Apr 2011 |
30 Apr 2011 to 29 May 2011 |
Valid until 29 May 2011 |
Table
3.3 Summary of submission status under
FEP-01/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
18 Dec 2009 |
Condition 2.7 |
Submission of works schedule
and location plan |
8 Feb 2010 |
Condition 2.8 |
Revised Silt Curtain Deployment
Plan (Rev. 3) |
4 Dec 2010 |
Condition 2.9 |
Silt Screen Deployment Plan
(Rev. 6) |
19 May 2011 |
Condition 2.10 |
Coral Translocation Plan |
20 Nov 2009 |
Condition 2.16 |
Revised Noise Management Plan
(Rev 5) |
19 Feb 2011 |
Condition 2.17 |
Landscape Plan |
12 May 2010 |
|
Revised landscape Plan |
30 Jun 2010 |
|
Submission of Supplementary
Information - Revised Management & Maintenance Schedule for Submitted
Revised Landscape Plan |
25 Aug 2010 |
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
3.1.4.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and
Table 3.5.
Table
3.4 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling equipment |
PP-RS0045-10 |
21 Dec 2010 |
21 Dec 2010 to 20 Jun 2011 |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0965-10 |
8 Nov 2010 |
22 Nov 2010 to 21 May 2011 |
Expired |
|
GW-RS1034-10 |
26 Nov 2010 |
27 Nov 2010 to 26 May 2011 |
Expired |
|
GW-RS1074-10 |
3 Dec 2010 |
09 Dec 2010 to 08 Jun 2011 |
Valid |
|
GS-RS0022-11 |
12 Jan 2011 |
23 Jan 2011 to 22 Jul 2011 |
Withdrawn |
|
GW-RS0107-11 |
8 Feb 2011 |
16 Mar 2011 to 15 Sep 2011 |
Valid |
|
GW-RS0111-11 |
11 Feb 2011 |
28 Feb 2011 to 31 Aug 2011 |
Valid |
|
GW-RS0311-11 |
1 Apr 2011 |
7 Apr 2011 to 6 Oct 2011 |
Withdrawn |
|
GW-RS0384-11 |
29 Apr 2011 |
27 May 2011 to 26 Nov 2011 |
Valid |
|
GW-RS0421-11 |
6 May 2011 |
11 May 2011 to 10 Nov 2011 |
Valid |
|
GW-RS0450-11 |
20 May 2010 |
9 Jun 2010 to 8 Dec 2011 |
To be valid on 9 Jun 2011 |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
Billing account under Waste
Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/11-083 |
23 Nov 2010 |
24 Nov 2010 to 23 May 2011 |
Expired |
|
EP/MD/12-021 |
20 May 2011 |
24 May 2011 to 23 Nov 2011 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) |
EP/MD/11-164 |
6 Apr 2011 |
8 Apr to 7 May 2011 |
Expired |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) for trial dump using Geo-synthetic container |
EP/MD/11-138 |
8 Apr 2011 |
15 Apr to 14 May 2011 |
Table
3.5 Summary of submission status under
FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
13 Apr 2010 |
Condition 2.7 |
Works Schedule and Location
Plan |
8 Apr 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
19 Apr 2010 |
Condition 2.9 |
Silt Screen Deployment Plan |
19 Apr 2010 |
Conditions 2.8 and 2.9 |