Contract No: HK/2009/05 Wanchai
Development Phase II and Sampling,
Field Measurement and Testing Work (Stage 1) Environmental Permit no.
EP-356/2009, Further
Evironmental permit nos. fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009
and Fep-05/356/2009 Monthly
Environmental Monitoring & Audit Report
- june 2011 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185
Gloucester Road, Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
7 July 2011 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of
Water Quality Monitoring Exceedances in Reporting Month
Table 2.1 Schedule 2 Designated Projects under this
Project
Table 2.2 Details of
Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/11
Table 3.3 Summary of
submission status under FEP-01/356/2009 Condition
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.5 Summary of
submission status under FEP-02/356/2009 Condition
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.7 Summary of
submission status under FEP-03/356/2009 Condition
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table 3.9 Summary of
submission status under FEP-04/356/2009 Condition
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2010/06
Table 3.11 Summary of submission status under
EP-356/2009 and FEP-05/356/2009 Condition
Table 4.1 Noise
Monitoring Station
Table 4.2 Real Time
Noise Monitoring Station
Table 4.3 Air
Monitoring Station
Table 4.4 Marine Water Quality Stations for Water
Quality Monitoring
Table 4.5 Marine Water
Quality Monitoring Frequency and Parameters
Table 4.6 Marine Water Quality Stations for
Enhanced Water Quality Monitoring
Table 5.1 Noise Monitoring Stations for Contract
no. HY/2009/11
Table 5.2 Noise Monitoring Station for Contract
nos. HK/2009/01, HK/2009/02 and HK/2010/06
Table 5.3 Noise Monitoring Station for Contract
no. HY/2009/15
Table 5.4 Real Time
Noise Monitoring Station for Contract no. HY/2009/11
Table 5.5 Air Monitoring Stations for Contract no.
HY/2009/11
Table 5.6 Air Monitoring Stations for Contract no.
HK/2009/01
Table 5.7 Air Monitoring Station for Contract no.
HK/2009/02
Table 5.8 Air Monitoring Station for Contract no.
HY/2009/15
Table 5.9 Water Monitoring Stations for Contract
no. HY/2009/11
Table 5.10 Water Monitoring Stations for Contract
no. HK/2009/01
Table 5.11 Water Monitoring Stations for Contract
no. HK/2009/02
Table 5.12 Water Monitoring Stations for Contract
no. HK/2009/02
Table 5.14 Summary of Water Quality Monitoring Exceedances
in Reporting Month
Table 5.15 Details of Waste Disposal for Contract
no. HY/2009/11
Table 5.16 Details of Waste Disposal for Contract
no. HK/2009/01
Table 5.17 Details of Waste Disposal for Contract
no. HK/2009/02
Table 5.18 Details of Waste Disposal for Contract
no. HY/2009/15
Table 5.19 Details of Type I Marine Sediment
Disposal for Contract no. HY/2009/15
Table 5.20 Details of Waste Disposal for Contract
no. HK/2010/06
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/11
Table 8.2 Summary of Environmental Inspections for
Contract no. HK/2009/01
Table 8.3 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.4 Summary of Environmental Inspections for
Contract no. HY/2009/15
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2010/06
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended
Mitigation Measures in Coming Reporting Month
lIST
OF FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project
Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST
OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming
month
Appendix 5.2 Noise Monitoring Results and
Graphical Presentations
Appendix 5.3 Air Quality
Monitoring Results and Graphical Presentations
Appendix 5.4 Water Quality
Monitoring Results and Graphical Presentations
Appendix 5.5 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Summary for Notification of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction
Programme of Individual Contracts
Construction Activities for the Reported Period
¡P
Reclamation
works;
¡P
Concreting;
¡P
Slotted panel
fixing;
¡P
Drainage
Construction works;
¡P
Outfall
construction works;
¡P
Construction
& installation of Concrete Block; and
¡P
Installation of
Caisson Seawall
¡P
Reclamation
works of HKCEC water Channel;
¡P
Assembly of
jack-up barge at Tsim Sha Tsui;
¡P
Installation of
sheet pile water channel at Dome Promenade;
¡P
Removal of rock
armours within the HKCEC Water Channel;
¡P
Installation of
cross-harbour water mains nos. B2 & As;
¡P
Thrust block
construction for cross-harbour watermains nos. A1 & B1 was commenced on 7 Jun
2011 when the steel formwork was installed into its working position;
¡P
Trench excavations
for proposed pipe laying works in Convention Avenue, VIP Drop-off Area;
¡P
Mainlaying works
at Zone B1-2 had been completed and the road reinstatement works;
¡P
Mainlaying works
at Zone B1-5;
¡P
Mainlaying works
at Zone A4-3A;
¡P
Backfilling
works for Temporary diversion of 2nos. DN900 cooling water discharge pipes of
Convention Plaza;
¡P
The fenced off
area at Zone B4-2 would be continued as a water tank establishment area for
cross harbour watermains installation until the original seawall had been
reinstated; and
¡P
Utility
diversion works for conflicting utilities at Salisbury Garden of Tsim Sha Tsui
¡P
Tseung Kwan O public fill sorting facility
¡P
Internal and external decoration for new public toilet;
¡P
FEHD pre-inspection of new public toilet;
¡P
Modification works for disable toilet;
¡P
Modification of hoarding and reinstatement works for public toilet opening
was carried out;
¡P
Basement structure and ground floor slab of passenger terminal building;
¡P
Modification of existing finger pier deck and tree pits;
¡P
Stripping interior fixing of existing ferry pier at Expo Drive East;
¡P
Erection of bamboo scaffolding;
¡P
Trench excavation and deck over works along Tonnochy Road;
¡P
Pipe jacking across Harbour Road;
¡P
Approximate
¡P
Excavation and lateral support for WSD Salt Water Pumping Station at Wan
Shing Street;
¡P
Laying blinding layer for WSD Salt Water Pumping Station at Wan Shing
Street;
¡P
Hacking H-pile head for WSD Salt Water Pumping Station at Wan Shing
Street;
¡P
Excavation and lateral support at Wan Shing Street;
¡P
Dredging for submarine outfall pipe;
¡P
Approximate
¡P
Modification of ELS and formwork for top slab of DSD extension chamber;
¡P
Marine piling works for new ferry pier was ongoing. 43 out of 83 nos.
marine piles and
¡P
Excavation and lateral support for WSD & DSD receiving pits
¡P
Dredging of
odorous sediment at TS4;
¡P
Seawall block
construction at TS4;
¡P
Maintenance of
navigation channel;
¡P
Diaphragm wall
preparation work at TS1 and TPCWAE;
¡P
Grouting works
at Abutment A;
¡P
Night time
protection works at CHT; and
¡P
Trial trench
work at Hung Hing Road and POC
¡P
Erection of
Staging Platform; and
¡P
Marine Bored
Piling
Noise Monitoring
Real-time Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
Table
I Summary of Water Quality
Monitoring Exceedances in Reporting Month
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD20 |
0 |
0 |
0 |
1 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C3 |
0 |
0 |
0 |
1 |
1 |
1 |
0 |
0 |
0 |
3 |
1 |
1 |
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 &
HK/2010/06 |
C2 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C5w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
0 |
0 |
0 |
3 |
3 |
2 |
0 |
0 |
0 |
3 |
3 |
1 |
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/11- North Point Reclamation
¡P
Reclamation
works;
¡P
Concreting;
¡P
Slotted panel
fixing;
¡P
Drainage
Construction works;
¡P
Outfall
construction works;
¡P
Sheet Pilling;
and
¡P
Construction
& installation of Seawall Block
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
¡P
Sheet pile
installation for a temporary water channel covering the existing cooling water
intake at Dome Promenade would be completed.
¡P
Removal of rock
armours within the HKCEC Water Channel would be continued.
¡P
Installation of
both silt screen type 1 & 3 at Tsim Sha Tsui would be completed.
Subsequently, installation of sheet piles near the proposed silt screen type 3
at Tsim Sha Tsui would be commenced.
¡P
Installation of
cross-harbour watermains nos. A3 & B3 and A4 & B4 would be completed.
¡P
Platform
erection fir crawler crane mobilization near the existing seawall at Salisbury Garden
would be continued and anticipated to be completed.
¡P
Works would be
continued at Convention Avenue, VIP Drop-off Area would be continued.
¡P
Excavation of
trial pot at Zone B5-1 and Zone b5-3 would be continued in order to determine
the suitable alignments for laying the proposed G1 ducts to and from the
existing HKCEC Phase 2 LV Switch room.
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Operating Tseung
Kwan O Public Fill Sorting Facility;
¡P
Modification
works for disable toilet;
¡P
Construction of
passenger terminal;
¡P
Demolition of
remaining ferry pier;
¡P
Casting seawall
coping for Expo Drive East seawall modification;
¡P
Modification of
hoarding at Expo Drive East for public toilet opening.
¡P
Trench
excavation and pipe laying works for cooling mains;
¡P
Trench
excavation and deck over at Tonnochy Road;
¡P
Lean concrete at
P7, P8 and P9 pump stations;
¡P
Hacking H-pile
head and cast the base slab at -5mPD for WSD Salt Water Pumping Station at Wan
Shing Street;
¡P
Excavation and
lateral support at Wan Shing Street for WSD Salt Water Intake;
¡P
Pre-bored H-pile
at for WSD Salt Water Intake and Box Culvert N1 at WCR1 Area;
¡P
Dredging for
submarine outfall pipe; and
¡P
Connection
chamber at DSD Screening Plant
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section)
¡P
Seawall block
construction at TS4;
¡P
Filling at TS4;
¡P
Maintenance of
navigation channel;
¡P
Diaphragm wall
construction at TS1 and TPCWAE;
¡P
Precautionary
works at Abutment A; and
¡P
Night time
protection works at CHT
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Erection of
Staging Platform; and
¡P
Disposal of Type
1 and Type 2 Marine Sediment for Pilling Works
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009
and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009,
FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring
and auditing work carried out in accordance to the Section 10.3 of EM&A
Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under
Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
for Environmental Permit no. EP-356/2009, Further Environmental Permit no.
FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and
FEP-05/356/2009 and during the period 28th May to 27th June
2011. The cut-off date of reporting is at 27th of each reporting
month.
Section
1 Introduction ¡V
details the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results
obtained in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Site Inspection ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review
of any relevant
follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai
Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨
(hereafter called ¡§the Project¡¨) are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment
(EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link
(Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan
Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001
and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB
to provide relief to the very congested east-west Connaught Road
Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1.
The Project is located mainly in Wan Chai North,
Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria
Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road
Interchange to the east, as shown in Figure 2.1.
2.2.2.
The study area encompasses existing developments
along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses
include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the
Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the
Royal Hong Kong Yacht Club (RHKYC), the Police Officers¡¦ Club, the Causeway Bay
Typhoon Shelter (CBTS) and commercial and residential developments.
2.2.3.
The scope of the Project
comprises:
¡P
Land formation
for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated
slip roads for connection to the Trunk Road and for through traffic from Central to
Wan Chai and Causeway Bay. The land formed for the above transport infrastructure
will provide opportunities for the development of an attractive waterfront
promenade for the enjoyment of the public
¡P
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
¡P
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
¡P
Upgrading of
hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
¡P
Provision of the
ground level roads, flyovers, footbridges, necessary transport facilities and
the associated utility services
¡P
Construction of
the new waterfront promenade, landscape works and the associated utility
services
¡P
The Trunk Road
(i.e. CWB) within the study area and the associated slip roads for connection
to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1
summarises the five individual DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced.
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits (FEP) such that the impact monitoring
stations are sub-divided accordingly to facilitate the implementation of
EM&A programme and to streamline the EM&A reporting for individual FEP
holders correspondingly.
2.3.2.
The details of individual contracts are summarized
in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North
Point Reclamation |
DP3 |
17 March 2010 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the
construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars
are summarized in Table 2.3:
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
China Harbour- CRBC Joint Venture |
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
Simon Tong |
9124 2471 |
2634 1626 |
Site Agent |
Paul Yu |
9456 9819 |
|||
Operation Manager |
Lau Yee Ching |
9466 3918 |
|||
Construction Manager |
David Wong |
9653 8635 |
|||
Construction Manager |
Wilson Lau |
5183 1270 |
|||
Construction Manager |
Chan Mui Sang |
9864 8615 |
|||
Environmental Officer
(Compliance Manager) |
Brian Wan |
9312 2827 |
|||
Environmental Engineer |
Shelton Chan |
5395 5470 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Eric Lam |
3658 3048 |
|||
Deputy Site Agent |
Mr. Anthony Wu |
3658 3004 |
|||
Quality & Environmental Manager |
Mr. C.P. Ho |
3658 3000 |
|||
Environmental Officer |
Ms. Flora Ng |
3658 3064 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2528 5651 |
Site Agent |
Mr. Simon Tang |
3557 6358 |
2566 2192 |
||
|
|
Construction Manager |
Mr. C K Kwok |
9779 2162 |
|
|
|
Assistant Construction Manager (East) |
Mr. Gene Cheung |
6105 4880 |
|
|
|
Assistant Construction Manager (West) |
Mr. Tony Chiu |
9090 0606 |
|
|
|
Section Agent (East) |
Mr. Jason Chan |
9254 1635 |
|
|
|
Section Agent (West) |
Mr. Tang Ka Tung |
9473 4771 |
|
|
|
Environmental Manager |
Mr. Samuel Tsui |
3557 6347 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project Manager |
Mr. Simon Tong |
9124 2471 |
2529 2880 |
Site Agent |
Mr. Book Kin Man |
9193
8680 |
|||
Environmental Officer |
Mr. Lee Wai Man |
9481
6024 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HY/2009/11, the principal work
activities in this reporting month included:
¡P
Reclamation
works;
¡P
Concreting;
¡P
Slotted panel
fixing;
¡P
Drainage
Construction works;
¡P
Outfall
construction works;
¡P
Construction
& installation of Concrete Block; and
¡P
Installation of
Caisson Seawall
2.4.4.
For Contract no. HK/2009/01, the principal work
activities in this reporting month included:
¡P
Reclamation
works of HKCEC water Channel;
¡P
Assembly of
jack-up barge at Tsim Sha Tsui;
¡P
Installation of
sheet pile water channel at Dome Promenade;
¡P
Removal of rock
armours within the HKCEC Water Channel;
¡P
Installation of
cross-harbour water mains nos. B2 & As;
¡P
Thrust block
construction for cross-harbour watermains nos. A1 & B1 was commenced on 7 Jun
2011 when the steel formwork was installed into its working position;
¡P
Trench excavations
for proposed pipe laying works in Convention Avenue, VIP Drop-off Area;
¡P
Mainlaying works
at Zone B1-2 had been completed and the road reinstatement works;
¡P
Mainlaying works
at Zone B1-5;
¡P
Mainlaying works
at Zone A4-3A;
¡P
Backfilling
works for Temporary diversion of 2nos. DN900 cooling water discharge pipes of
Convention Plaza;
¡P
The fenced off
area at Zone B4-2 would be continued as a water tank establishment area for cross
harbour watermains installation until the original seawall had been reinstated;
and
¡P
Utility
diversion works for conflicting utilities at Salisbury Garden of Tsim Sha Tsui
2.4.5.
For Contract no. HK/2009/02, the principal work
activities in this reporting month included:
¡P
Tseung Kwan O
public fill sorting facility
¡P
Internal and
external decoration for new public toilet;
¡P
FEHD
pre-inspection of new public toilet;
¡P
Modification
works for disable toilet;
¡P
Modification of
hoarding and reinstatement works for public toilet opening was carried out;
¡P
Basement
structure and ground floor slab of passenger terminal building;
¡P
Modification of
existing finger pier deck and tree pits;
¡P
Stripping
interior fixing of existing ferry pier at Expo Drive East;
¡P
Erection of
bamboo scaffolding;
¡P
Trench
excavation and deck over works along Tonnochy Road;
¡P
Pipe jacking
across Harbour Road;
¡P
Approximate
¡P
Excavation and
lateral support for WSD Salt Water Pumping Station at Wan Shing Street;
¡P
Laying blinding
layer for WSD Salt Water Pumping Station at Wan Shing Street;
¡P
Hacking H-pile
head for WSD Salt Water Pumping Station at Wan Shing Street;
¡P
Excavation and
lateral support at Wan Shing Street;
¡P
Dredging for submarine
outfall pipe;
¡P
Approximate
¡P
Modification of
ELS and formwork for top slab of DSD extension chamber;
¡P
Marine piling
works for new ferry pier was ongoing. 43 out of 83 nos. marine piles; and
¡P
Excavation and
lateral support for WSD & DSD receiving pits
2.4.6.
For Contract no. HY/2009/15, the principal work
activities in this reporting month included:
¡P
Dredging of odorous sediment at TS4;
¡P
Seawall block construction at TS4;
¡P
Maintenance of navigation channel;
¡P
Diaphragm wall preparation work at TS1 and TPCWAE;
¡P
Grouting works at Abutment A;
¡P
Night time protection works at CHT; and
¡P
Trial trench work at Hung Hing Road and POC
2.4.7.
For Contract no. HK/2010/06, the principal work
activities in this reporting month included:
¡P
Erection of
Staging Platform; and
¡P
Marine Bored
Piling
2.4.8.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. HY/2009/11- North Point Reclamation
¡P
Reclamation
works;
¡P
Concreting;
¡P
Slotted panel
fixing;
¡P
Drainage
Construction works;
¡P
Outfall
construction works;
¡P
Sheet Pilling;
and
¡P
Construction
& installation of Seawall Block
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
¡P
Sheet pile installation
for a temporary water channel covering the existing cooling water intake at
Dome Promenade would be completed.
¡P
Removal of rock
armours within the HKCEC Water Channel would be continued.
¡P
Installation of
both silt screen type 1 & 3 at Tsim Sha Tsui would be completed.
Subsequently, installation of sheet piles near the proposed silt screen type 3
at Tsim Sha Tsui would be commenced.
¡P
Installation of
cross-harbour watermains nos. A3 & B3 and A4 & B4 would be completed.
¡P
Platform
erection fir crawler crane mobilization near the existing seawall at Salisbury Garden
would be continued and anticipated to be completed.
¡P
Works would be
continued at Convention Avenue, VIP Drop-off Area would be continued.
¡P
Excavation of
trial pot at Zone B5-1 and Zone b5-3 would be continued in order to determine
the suitable alignments for laying the proposed G1 ducts to and from the
existing HKCEC Phase 2 LV Switch room.
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Operating Tseung
Kwan O Public Fill Sorting Facility;
¡P
Modification
works for disable toilet;
¡P
Construction of
passenger terminal;
¡P
Demolition of
remaining ferry pier;
¡P
Casting seawall
coping for Expo Drive East seawall modification;
¡P
Modification of
hoarding at Expo Drive East for public toilet opening.
¡P
Trench
excavation and pipe laying works for cooling mains;
¡P
Trench
excavation and deck over at Tonnochy Road;
¡P
Lean concrete at
P7, P8 and P9 pump stations;
¡P
Hacking H-pile
head and cast the base slab at -5mPD for WSD Salt Water Pumping Station at Wan
Shing Street;
¡P
Excavation and
lateral support at Wan Shing Street for WSD Salt Water Intake;
¡P
Pre-bored H-pile
at for WSD Salt Water Intake and Box Culvert N1 at WCR1 Area;
¡P
Dredging for
submarine outfall pipe; and
¡P
Connection chamber
at DSD Screening Plant
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section)
¡P
Seawall block
construction at TS4;
¡P
Filling at TS4;
¡P
Maintenance of
navigation channel;
¡P
Diaphragm wall
construction at TS1 and TPCWAE;
¡P
Precautionary
works at Abutment A; and
¡P
Night time
protection works at CHT
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Marine Bored
Piling;
¡P
Erection of
Staging Platform; and
¡P
Disposal of Type
1 and Type 2 Marine Sediment for Pilling Works
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009/A |
4 Aug
2010 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb
2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
22 Nov
2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Valid |
Further
Environmental Permit |
FEP-01/364/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further
Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Valid |
Further
Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Valid |
Further
Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HY/2009/11 ¡V
Central ¡V Wanchai Bypass, North Point Reclamation
3.1.3.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-01/356/2009 for contract no. HY/2009/11 are shown in Table 3.2 and
Table 3.3.
Table
3.2 Cumulative Summary of Valid Licences
and Permits
under Contract no. HY/2009/11
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
N/A |
Valid |
Notification of Works Under APCO |
314911 |
9 Mar 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0330-11 |
15 Apr 2011 |
1 May 2011 to 31 Oct 2011 |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-151-C3631-02 |
12 Oct 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7010037 |
13 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00007942-2010 |
29 Nov 2010 |
30 Nov 2015 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/11-116 |
29 Dec 2010 |
31 Dec 2010 to 29 Jun 2011 |
Valid until 29 Jun 2011 |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) |
EP/MD/12-008 |
28 Apr 2011 |
30 Apr 2011 to 29 May 2011 |
Expired |
EP/MD/12-025 |
31 May 2011 |
1 Jun 2011 to 29 Jun 2011 |
Valid |
Table
3.3 Summary of submission status under
FEP-01/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
18 Dec 2009 |
Condition 2.7 |
Submission of works schedule
and location plan |
8 Feb 2010 |
Condition 2.8 |
Revised Silt Curtain Deployment
Plan (Rev. 3) |
4 Dec 2010 |
Condition 2.9 |
Silt Screen Deployment Plan
(Rev. 6) |
18 May 2011 |
Condition 2.10 |
Coral Translocation Plan |
20 Nov 2009 |
Condition 2.16 |
Revised Noise Management Plan
(Rev 5) |
19 Feb 2011 |
Condition 2.17 |
Landscape Plan |
12 May 2010 |
|
Revised landscape Plan |
30 Jun 2010 |
|
Submission of Supplementary
Information - Revised Management & Maintenance Schedule for Submitted
Revised Landscape Plan |
25 Aug 2010 |
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
3.1.4.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and
Table 3.5.
Table
3.4 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling equipment |
PP-RS0045-10 |
21 Dec 2010 |
21 Dec 2010 to 20 Jun 2011 |
Expired |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS1074-10 |
3 Dec 2010 |
09 Dec 2010 to 08 Jun 2011 |
Valid |
|
GS-RS0022-11 |
12 Jan 2011 |
23 Jan 2011 to 22 Jul 2011 |
Withdrawn |
|
GW-RS0107-11 |
8 Feb 2011 |
16 Mar 2011 to 15 Sep 2011 |
Valid |
|
GW-RS0111-11 |
11 Feb 2011 |
28 Feb 2011 to 31 Aug 2011 |
Valid |
|
GW-RS0311-11 |
1 Apr 2011 |
7 Apr 2011 to 6 Oct 2011 |
Withdrawn |
|
GW-RS0384-11 |
29 Apr 2011 |
27 May 2011 to 26 Nov 2011 |
Valid |
|
GW-RS0421-11 |
6 May 2011 |
11 May 2011 to 10 Nov 2011 |
Valid |
|
GW-RS0450-11 |
20 May 2010 |
9 Jun 2010 to 8 Dec 2011 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
Billing account under Waste
Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/12-021 |
20 May 2011 |
24 May 2011 to 23 Nov 2011 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) |
EP/MD/11-164 |
6 Apr 2011 |
8 Apr to 7 May 2011 |
Expired |
Table
3.5 Summary of submission status under
FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
13 Apr 2010 |
Condition 2.7 |
Works Schedule and Location
Plan |
8 Apr 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
19 Apr 2010 |
Condition 2.9 |
Silt Screen Deployment Plan |
19 Apr 2010 |
Conditions 2.8 and 2.9 |
Supplementary Document on Silt
Curtain and Silt Screen Deployment Plan |
19 Jul 2010 |
Report on Field Testing for
Silt Curtain |
26 Aug 2010 |
|
Report on Field Testing for
Silt Curtain (Rev. A) |
15 Nov 2010 |
|
Condition 2.12(d) |
Alternative Proposal on
Concurrent Dredging for Sewage Pipeline and Cross Harbour Water Mains |
15 Apr 2011 |
Condition 2.17 |
Noise Management Plan |
23 Apr 2010 |
Condition 2.18 |
Landscape Plan (Erection of
Decorative Screen Hoarding along Construction Site around Hong Kong
Exhibition and Convention Centre) |
15 May 2010 |
Landscape Plan (Night-time
Lighting) |
22 Oct 2010 |
|
|
Landscape Plan (Rev. B) |
15 Nov 2010 |
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
3.1.5.
Summary of the current
status on licences and/or permits on environmental protection pertinent and
submission for contract no. HK/2009/02 under FEP-03/356/2009 are shown in Table
3.6 and Table 3.7.
Table
3.6 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
|
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling equipment |
PP-RS0037 |