Contract No: HK/2009/05 Wanchai
Development Phase II and Central Wanchai Bypass Sampling,
Field Measurement and Testing Work (Stage 1) Environmental Permit no.
EP-356/2009, Further
Evironmental permit nos. fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009
and Fep-05/356/2009 Monthly
Environmental Monitoring & Audit Report
- September 2011 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185
Gloucester Road, Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
11 October 2011 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of
Water Quality Monitoring Exceedances in Reporting Month
Table II Summary of
Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details of
Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/11
Table 3.3 Summary of
submission status under FEP-01/356/2009 Condition
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.5 Summary of
submission status under FEP-02/356/2009 Condition
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.7 Summary of
submission status under FEP-03/356/2009 Condition
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table 3.9 Summary of
submission status under FEP-04/356/2009 Condition
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2010/06
Table 3.11 Summary of submission status under
EP-356/2009 and FEP-05/356/2009 Condition
Table 4.1 Noise
Monitoring Station
Table 4.2 Real Time
Noise Monitoring Station
Table 4.3 Air
Monitoring Station
Table 4.4 Marine Water Quality Stations for Water
Quality Monitoring
Table 4.5 Marine Water
Quality Monitoring Frequency and Parameters
Table 4.6 Marine Water Quality Stations for
Enhanced Water Quality Monitoring
Table 5.1 Noise Monitoring Stations for Contract
no. HY/2009/11
Table 5.2 Noise Monitoring Station for Contract
nos. HK/2009/01, HK/2009/02 and HK/2010/06
Table 5.3 Noise Monitoring Station for Contract
no. HY/2009/15
Table 5.4 Real Time
Noise Monitoring Station for Contract no. HY/2009/11
Table 5.5 Air Monitoring Stations for Contract no.
HY/2009/11
Table 5.6 Air Monitoring Stations for Contract no.
HK/2009/01
Table 5.7 Air Monitoring Station for Contract no.
HK/2009/02
Table 5.8 Air Monitoring Station for Contract no.
HY/2009/15
Table 5.9 Water Monitoring Stations for Contract
no. HY/2009/11
Table 5.10 Water Monitoring Stations for Contract
no. HK/2009/01
Table 5.11 Water Monitoring Stations for Contract
no. HK/2009/02
Table 5.12 Water Monitoring Stations for Contract
no. HK/2009/02
Table 5.13 Water Monitoring Stations for Contract
no. HY/2009/15
Table 5.14 Summary of Water Quality Monitoring
Exceedances in Reporting Month
Table 5.15 Summary of Enhanced Dissolved Oxygen
Monitoring Exceedances in Reporting Month
Table 5.16 Details of Waste Disposal for Contract
no. HY/2009/11
Table 5.17 Details of Waste Disposal for Contract
no. HK/2009/01
Table 5.18 Details of Waste Disposal for Contract
no. HK/2009/02
Table 5.19 Details of Waste Disposal for Contract
no. HY/2009/15
Table 5.20 Details of Waste Disposal for Contract
no. HK/2010/06
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/11
Table 8.2 Summary of Environmental Inspections for
Contract no. HK/2009/01
Table 8.3 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.4 Summary of Environmental Inspections for
Contract no. HY/2009/15
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2010/06
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended
Mitigation Measures in Coming Reporting Month
lIST
OF FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project
Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST
OF APPENDIces
Appendix 3.1 Environmental Mitigation
Implementation Schedule
Appendix 4.1 Action
and Limit Level
Appendix
4.2 Copies
of Calibration Certificates
Appendix
5.1 Monitoring
Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring Results and
Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and
Graphical Presentations, and Odour Patrol Results
Appendix
5.4 Water
Quality
Monitoring Results and Graphical Presentations
Appendix
5.5 Real-time
Noise
Monitoring Results and Graphical Presentations
Appendix 6.1 Event
Action Plans
Appendix 6.2 Summary for
Notification of Exceedance
Appendix
9.1 Complaint
Log
Appendix 10.1 Construction
Programme of Individual Contracts
Construction Activities for the Reported Period
¡P
Reclamation
works;
¡P
Geo-textile
laying;
¡P
Drainage
Construction works;
¡P
Outfall construction
works (Open Channel U);
¡P
Sheet Pilling;
¡P
Pre-casting of Coping;
and
¡P
Construction
& installation of Seawall Concrete Block
¡P
Installation of
silt screen (type 1) at TST;
¡P
Seawall toe
block installation for reinstating seawall at Zone B1-3;
¡P
Dredging within
HKCEC Water Channel from CH160 to CH190 for Type 1 & 2 sediment;
¡P
Trench
backfilling and seawall reinstatement for both the completed cross-harbour
watermains and the seawall near Expo Promenade (Zone B1-3);
¡P
Installation of
cross-harbour watermains nos. A8 & B8;
¡P
Final trimming
within Principle Fairway for cross-harbour watermains installation;
¡P
Platform
erection for crawler crane mobilization near the existing seawall at Salisbury
Garden had been completed and WSD¡¦s consent had been given for mobilization of
crawler crane to the jack-up barge. Mobilization;
¡P
The trench
excavation works at Zone B1-4, B4-2, A1-2, A2-4A, A3-3, A4-3B, A4-3B, A4-3C and
A5-5;
¡P
Trench
excavation works at Zone A3-2A;
¡P
Excavation for
jacking pits for pipe laying works by heading method along Convention Avenue at
Zone A1-2A, A1-4A and A2-4A;
¡P
Heading No. H2,
H5 and H6 (Mainlaying works by trenchless method); and
¡P
Trench
excavation for a 1000 dia. Watermains at Salisbury Garden
¡P
Tseung Kwan O public fill sorting facility
¡P
Steel fixing of Passenger Terminal Building was completed on 8 September
2011;
¡P
Demolition of existing ferry pier;
¡P
Racking piles and dredging work of Ferry Pier;
¡P
Formwork for lift shaft of Passenger Terminal Building;
¡P
Fixing G/F to 1/F R.C wall waling on Passenger Terminal Building;
¡P
Construction of wash out chamber at Harbour Road and access manhole at
Harbour Centre;
¡P
Reinstatement work for footpath and existing inspection chamber at Great
Eagle Centre;
¡P
Trench excavation and deck over works along Tonnochy Road;
¡P
Approximate
¡P
Grouting for the cross road pipeline of Harbour Road;
¡P
Installation of PVC and G.I cable ducts was ongoing at Harbour Road;
¡P
Wall and column construction below -0.8 mPD;
¡P
Installation of submarine outfall pipe up to CHA-105 and CHB-130, continue
backfill on the HDPE pipelines;
¡P
Dredging for submarine outfall pipe;
¡P
3 out of 12 nos of pre-bored H-pile for box culverts N1 was reached to
founding levels;
¡P
1st and 2nd loading test of New Ferry Pier;
¡P
Marine piling works for new ferry pier was ongoing. 83 out of 83 nos. marine
piles;
¡P
Dredging inside the piles was ongoing. 45 out of 83 piles;
¡P
Wall and column construction below -0.8 mPD;
¡P
Casting of the base slab of WSD Receiving Pit;
¡P
Excavation and lateral support for DSD receiving pits;
¡P
Half landing slab for P7, P8 & P9 Pumping Stations was completed,
top slab false work & formwork erection;
¡P
Expo Drive East mass concreting coping formwork erection;
¡P
Levelling for proposed bream blocks in progress at Vertical Seawall T4
to T6; and
¡P
Commenced fabricating the steel frames for water diversion and temporary
sheet piles walls for WCR2 reclamation.
¡P
Seawall block construction, reclamation work at TS4;
¡P
Maintenance dredging of navigation channel and mooring area;
¡P
Night time protection works at CHT;
¡P
Construction of dewatering well at Hung Hing Road and POC; and
¡P
Precautionary works at Abutment A
¡P
Installation of bored pile casing;
¡P
Excavation of bored piles;
¡P
Pre-drilling works; and
¡P
Installation of temporary staging platforms
Noise Monitoring
Real-time Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
Table I Summary
of Water Quality Monitoring Exceedances in Reporting Month
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C5w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 |
C7 |
2 |
0 |
0 |
0 |
0 |
0 |
4 |
0 |
0 |
0 |
0 |
0 |
Total |
2 |
0 |
0 |
1 |
0 |
0 |
4 |
0 |
1 |
1 |
0 |
0 |
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
Table
II Summary of Enhanced Dissolved
Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring
Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
AL |
LL |
AL |
LL |
||
HY/2009/15 |
C6 |
2 |
2 |
4 |
1 |
C7 |
3 |
0 |
4 |
2 |
|
Ex-WPCWA SW |
0 |
3 |
0 |
9 |
|
Ex-WPCWA SE |
1 |
5 |
5 |
8 |
|
Total |
6 |
10 |
13 |
20 |
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/11- North Point Reclamation
¡P
Reclamation
works;
¡P
Slotted panel
fixing;
¡P
Geo-textile
laying;
¡P
Drainage
Construction works;
¡P
Outfall
construction works (Open Channel U);
¡P
Sheet Pilling;
¡P
Pre-casting and
Installation of Coping; and
¡P
Construction
& installation of Seawall Concrete Block
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
¡P
Dredging works
from CH190to CH260 for the reclamation of HKCEC3W would be commenced upon giving
7-day advance notice to EPD;
¡P
Reclamation of
HKCEC3W (up to CH120) within the HKCEC Water Channel;
¡P
Installation of
sheet pile water channel at Dome Promenade (from CH120 to CH160);
¡P
Installation of
silt screen (type 3) at TST;
¡P
Dredging woks
from CH50 to Ch250 for subsequent cross-harbour watermains installation off TST
would be commenced. A trial dredging operation near the Avenue of Stars would
be demonstrated to the representatives of LCSD on 22 September.
¡P
Installation of
cross harbour watermains nos. A9 &B9 and A10 & B10;
¡P
Sheet pipe pile
wall and the associated ground treatment works for the trenches of the proposed
cross harbour watermaines nos. A18 & B18 works be commenced after the
subsequent removal of the temporary steel platform;
¡P
Trench excavation
works at Zone A1-2;
¡P
Works would be continued
out at Zone A2-3B, A3-3, A3-2A, A4-3B, A4-3B, A4-3C, A5-5, B1-4, B4-2 and B4-5;
¡P
Heading Nos. H2,
H5 and H6 (Mainlaying works by trenchless method); and
¡P
Heading Nos. H3,
H4 and H9 (Mainlaying works by trenchless method) would be commenced after
their corresponding jacking pits had been excavated in Convention Avenue.
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Operating Tseung
Kwan O Public Fill Sorting Facility;
¡P
Construction of
passenger terminal;
¡P
Demolition of
remaining finger pier;
¡P
Construction of
mass seawall coping at Expo Drive East;
¡P
Trench
excavation and pipe laying works along Harbour Road;
¡P
Trench
excavation and deck over at Tonnochy Road;
¡P
Top soffit slab
at P7, P8 & P9 pump stations;
¡P
Construction
above -0.8mPDat Wan Shing Street for WSD Salt Water Intake;
¡P
Pipeline jacking
WSD intake A.
¡P
Pre-bored sheet
pile works for salt water intake culvert Bay1b & Bay 2;
¡P
Pre-bored H-pile
for Box Culvert N1 at WCR1 Area;
¡P
The 3rd and 4th
loading test of New Ferry Pier;
¡P
All piles
excavation at new ferry pier;
¡P
Grouting plug in
piles of New Ferry Pier;
¡P
Concreting for
marine piles at new ferry pier;
¡P
Dredging and fabrication
of HDPE pipe diffuser section for submarine outfall pipes;
¡P
Backfilling of
bagged concrete and rockfills for the installed submarine outfall pipes;
¡P
Excavation and
lateral support for receiving pits at Hung Hing Road;
¡P
Installation of
temporary sheet piles wall at WCR2; and
¡P
Installation of
the temporary water diversion steel frame
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section)
¡P
Mooring
rearrangement and dredging at ME4;
¡P
Night time
protection works at CHT;
¡P
Construction of
dewatering well at Hung Hing Road and POC; and
¡P
Precautionary
works at Abutment A
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Installation of
bored pile casing;
¡P
Excavation of
bored piles;
¡P
Bored Pile
Concreting;
¡P
Pre-drilling works;
and
¡P
Installation of
temporary staging platforms
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009
and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009,
FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring
and auditing work carried out in accordance to the Section 10.3 of EM&A
Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under
Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
for Environmental Permit no. EP-356/2009, Further Environmental Permit no.
FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and
FEP-05/356/2009 and during the period 28th August to 27th
September 2011. The cut-off date of reporting is at 27th of each
reporting month.
Section
1 Introduction ¡V
details the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results
obtained in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the relevant cumulative construction impact
due to the concurrent activities of the concurrent Projects.
Section
8 Site Inspection ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review
of any relevant
follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai
Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨
(hereafter called ¡§the Project¡¨) are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental
Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern
Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved
on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB
to provide relief to the very congested east-west Connaught Road
Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1.
The Project is located mainly in Wan Chai North,
Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria
Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road
Interchange to the east, as shown in Figure 2.1.
2.2.2.
The study area encompasses existing developments
along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses
include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the
Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the
Royal Hong Kong Yacht Club (RHKYC), the Police Officers¡¦ Club, the Causeway Bay
Typhoon Shelter (CBTS) and commercial and residential developments.
2.2.3.
The scope of the Project
comprises:
¡P
Land formation
for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated
slip roads for connection to the Trunk Road and for through traffic from Central to
Wan Chai and Causeway Bay. The land formed for the above transport infrastructure
will provide opportunities for the development of an attractive waterfront
promenade for the enjoyment of the public
¡P
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
¡P
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
¡P
Upgrading of
hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
¡P
Provision of the
ground level roads, flyovers, footbridges, necessary transport facilities and
the associated utility services
¡P
Construction of
the new waterfront promenade, landscape works and the associated utility
services
¡P
The Trunk Road
(i.e. CWB) within the study area and the associated slip roads for connection
to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1
summarises the five individual DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. Contractors of individual contracts will
be required by the EP holder to apply Further Environmental Permits (FEP) such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized
in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North
Point Reclamation |
DP3 |
17 March 2010 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and Highways
Department are the overall project controllers for the Wan Chai Development
Phase II and Central-Wan Chai Bypass respectively. For the construction phase
of the Project, Project Engineer, Contractor(s), Environmental Team and
Independent Environmental Checker are appointed to manage and control
environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
China Harbour- CRBC Joint Venture |
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
Mr. Simon Tong |
9124 2471 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Operation Manager |
Mr. Lau Yee Ching |
9466 3918 |
|||
Construction Manager |
Mr. Jerry Siu |
9493 3664 |
|||
Construction Manager |
Mr. Ricky Lai |
9487 6549 |
|||
Construction Manager |
Mr. KK Yuen |
3498 1213 |
|||
Environmental Officer
(Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Mak Kam Wing |
3658 3044 |
|||
Quality & Environmental Manager |
Mr. C.P. Ho |
3658 3000 |
|||
Environmental Officer |
Ms. Flora Ng |
3658 3064 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2528 5651 |
Site Agent |
Mr. Simon Tang |
3557 6358 |
2566 2192 |
||
|
|
Construction Manager |
Mr. C K Kwok |
9779 2162 |
|
|
|
Assistant Construction Manager (East) |
Mr. Gene Cheung |
6105 4880 |
|
|
|
Assistant Construction Manager (West) |
Mr. Tony Chiu |
9090 0606 |
|
|
|
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project Manager |
Mr. Simon Tong |
9124 2471 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental Officer |
Mr. Lee Wai Man |
9481
6024 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HY/2009/11, the principal work
activities in this reporting month included:
¡P
Reclamation works;
¡P
Geo-textile laying;
¡P
Drainage Construction works;
¡P
Outfall construction works (Open Channel U);
¡P
Sheet Pilling;
¡P
Pre-casting of Coping; and
¡P
Construction & installation of Seawall Concrete Block
2.4.4.
For Contract no. HK/2009/01, the principal work
activities in this reporting month included:
¡P
Installation of silt screen (type 1) at TST;
¡P
Seawall toe block installation for reinstating seawall at Zone B1-3;
¡P
Dredging within HKCEC Water Channel from CH160 to CH190 for Type 1 &
2 sediment;
¡P
Trench backfilling and seawall reinstatement for both the completed
cross-harbour watermains and the seawall near Expo Promenade (Zone B1-3);
¡P
Installation of cross-harbour watermains nos. A8 & B8;
¡P
Final trimming within Principle Fairway for cross-harbour watermains
installation;
¡P
Platform erection for crawler crane mobilization near the existing
seawall at Salisbury Garden had been completed and WSD¡¦s consent had been given
for mobilization of crawler crane to the jack-up barge. Mobilization;
¡P
The trench excavation works at Zone B1-4, B4-2, A1-2, A2-4A, A3-3,
A4-3B, A4-3B, A4-3C and A5-5;
¡P
Trench excavation works at Zone A3-2A;
¡P
Excavation for jacking pits for pipe laying works by heading method
along Convention Avenue at Zone A1-2A, A1-4A and A2-4A;
¡P
Heading No. H2, H5 and H6 (Mainlaying works by trenchless method); and
¡P
Trench excavation for a 1000 dia. Watermains at Salisbury Garden
2.4.5.
For Contract no. HK/2009/02, the principal work
activities in this reporting month included:
¡P
Tseung Kwan O public fill sorting facility
¡P
Steel fixing of Passenger Terminal Building was completed on 8 September
2011;
¡P
Demolition of existing ferry pier;
¡P
Racking piles and dredging work of Ferry Pier;
¡P
Formwork for lift shaft of Passenger Terminal Building;
¡P
Fixing G/F to 1/F R.C wall waling on Passenger Terminal Building;
¡P
Construction of wash out chamber at Harbour Road and access manhole at
Harbour Centre;
¡P
Reinstatement work for footpath and existing inspection chamber at Great
Eagle Centre;
¡P
Trench excavation and deck over works along Tonnochy Road;
¡P
Approximate
¡P
Grouting for the cross road pipeline of Harbour Road;
¡P
Installation of PVC and G.I cable ducts was ongoing at Harbour Road;
¡P
Wall and column construction below -0.8 mPD;
¡P
Installation of submarine outfall pipe up to CHA-105 and CHB-130, continue
backfill on the HDPE pipelines;
¡P
Dredging for submarine outfall pipe;
¡P
3 out of 12 nos of pre-bored H-pile for box culverts N1 was reached to
founding levels;
¡P
1st and 2nd loading test of New Ferry Pier;
¡P
Marine piling works for new ferry pier was ongoing. 83 out of 83 nos.
marine piles;
¡P
Dredging inside the piles was ongoing. 45 out of 83 piles;
¡P
Wall and column construction below -0.8 mPD;
¡P
Casting of the base slab of WSD Receiving Pit;
¡P
Excavation and lateral support for DSD receiving pits;
¡P
Half landing slab for P7, P8 & P9 Pumping Stations was completed,
top slab falsework & formwork erection;
¡P
Expo Drive East mass concreting coping formwork erection;
¡P
Levelling for proposed bream blocks in progress at Vertical Seawall T4
to T6; and
¡P
Commenced fabricating the steel frames for water diversion and temporary
sheet piles walls for WCR2 reclamation.
2.4.6.
For Contract no. HY/2009/15, the principal work
activities in this reporting month included:
¡P
Seawall block construction, reclamation work at TS4;
¡P
Maintenance dredging of navigation channel and mooring area;
¡P
Night time protection works at CHT;
¡P
Construction of dewatering well at Hung Hing Road and POC; and
¡P
Precautionary works at Abutment A
2.4.7.
For Contract no. HK/2010/06, the principal work
activities in this reporting month included:
¡P
Installation of bored pile casing;
¡P
Excavation of bored piles;
¡P
Pre-drilling works; and
¡P
Installation of temporary staging platforms
2.4.8.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. HY/2009/11- North Point Reclamation
¡P
Reclamation
works;
¡P
Slotted panel
fixing;
¡P
Geo-textile
laying;
¡P
Drainage
Construction works;
¡P
Outfall
construction works (Open Channel U);
¡P
Sheet Pilling;
¡P
Pre-casting and
Installation of Coping; and
¡P
Construction
& installation of Seawall Concrete Block
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
¡P
Dredging works
from CH190to CH260 for the reclamation of HKCEC3W would be commenced upon giving
7-day advance notice to EPD;
¡P
Reclamation of
HKCEC3W (up to CH120) within the HKCEC Water Channel;
¡P
Installation of
sheet pile water channel at Dome Promenade (from CH120 to CH160);
¡P
Installation of
silt screen (type 3) at TST;
¡P
Dredging woks
from CH50 to Ch250 for subsequent cross-harbour watermains installation off TST
would be commenced. A trial dredging operation near the Avenue of Stars would
be demonstrated to the representatives of LCSD on 22 September.
¡P
Installation of
cross harbour watermains nos. A9 &B9 and A10 & B10;
¡P
Sheet pipe pile
wall and the associated ground treatment works for the trenches of the proposed
cross harbour watermaines nos. A18 & B18 works be commenced after the
subsequent removal of the temporary steel platform;
¡P
Trench
excavation works at Zone A1-2;
¡P
Works would be continued
out at Zone A2-3B, A3-3, A3-2A, A4-3B, A4-3B, A4-3C, A5-5, B1-4, B4-2 and B4-5;
¡P
Heading Nos. H2,
H5 and H6 (Mainlaying works by trenchless method); and
¡P
Heading Nos. H3,
H4 and H9 (Mainlaying works by trenchless method) would be commenced after
their corresponding jacking pits had been excavated in Convention Avenue.
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Operating Tseung
Kwan O Public Fill Sorting Facility;
¡P
Construction of
passenger terminal;
¡P
Demolition of
remaining finger pier;
¡P
Construction of
mass seawall coping at Expo Drive East;
¡P
Trench
excavation and pipe laying works along Harbour Road;
¡P
Trench
excavation and deck over at Tonnochy Road;
¡P
Top soffit slab
at P7, P8 & P9 pump stations;
¡P
Construction
above -0.8mPDat Wan Shing Street for WSD Salt Water Intake;
¡P
Pipeline jacking
WSD intake A.
¡P
Pre-bored sheet
pile works for salt water intake culvert Bay1b & Bay 2;
¡P
Pre-bored H-pile
for Box Culvert N1 at WCR1 Area;
¡P
The 3rd and 4th
loading test of New Ferry Pier;
¡P
All piles
excavation at new ferry pier;
¡P
Grouting plug in
piles of New Ferry Pier;
¡P
Concreting for
marine piles at new ferry pier;
¡P
Dredging and fabrication
of HDPE pipe diffuser section for submarine outfall pipes;
¡P
Backfilling of
bagged concrete and rockfills for the installed submarine outfall pipes;
¡P
Excavation and
lateral support for receiving pits at Hung Hing Road;
¡P
Installation of
temporary sheet piles wall at WCR2; and
¡P
Installation of
the temporary water diversion steel frame
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section)
¡P
Mooring
rearrangement and dredging at ME4;
¡P
Night time
protection works at CHT;
¡P
Construction of
dewatering well at Hung Hing Road and POC; and
¡P
Precautionary
works at Abutment A
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Installation of
bored pile casing;
¡P
Excavation of
bored piles;
¡P
Bored Pile
Concreting;
¡P
Pre-drilling
works; and
¡P
Installation of
temporary staging platforms
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009/A |
4 Aug
2010 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb
2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
22 Nov
2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Valid |
Further
Environmental Permit |
FEP-01/364/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further
Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Valid |
Further
Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Valid |
Further
Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HY/2009/11 ¡V
Central ¡V Wanchai Bypass, North Point Reclamation
3.1.3.
Summary of the current status on licences and/or permits
on environmental protection pertinent and submission under FEP-01/356/2009 for
contract no. HY/2009/11 are shown in Table 3.2 and Table
3.3.
3.1.4.
Contractor submitted a letter dated 20 July 2011 to
confirm that the dredging works and dumping operation were completed.
Table 3.2 Cumulative
Summary of Valid Licences and Permits
under Contract no. HY/2009/11
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
N/A |
Valid |
Notification of Works Under APCO |
314911 |
9 Mar 2010 |
N/A |
Valid |
|
331892 |
4 Jul. 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0330-11 |
15 Apr 2011 |
1 May 2011 to 31 Oct 2011 |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-151-C3631-02 |
12 Oct 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7010037 |
13 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00007942-2010 |
29 Nov 2010 |
30 Nov 2015 |
Valid |
Table
3.3 Summary of submission status under
FEP-01/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
18 Dec 2009 |
Condition 2.7 |
Submission of works schedule
and location plan |
8 Feb 2010 |
Condition 2.8 |
Revised Silt Curtain Deployment
Plan (Rev. 3) |
4 Dec 2010 |
Condition 2.9 |
Silt Screen Deployment Plan
(Rev. 6) |
18 May 2011 |
Condition 2.10 |
Coral Translocation Plan |
20 Nov 2009 |
Condition 2.16 |
Revised Noise Management Plan
(Rev 5) |
19 Feb 2011 |
Condition 2.17 |
Landscape Plan |
12 May 2010 |
|
Revised landscape Plan |
30 Jun 2010 |
|
Submission of Supplementary
Information - Revised Management & Maintenance Schedule for Submitted
Revised Landscape Plan |
25 Aug 2010 |
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
3.1.5.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and
Table 3.5.
Table
3.4 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0107-11 |
8 Feb 2011 |
16 Mar 2011 to 15 Sep 2011 |
Expired |
|
GW-RS0384-11 |
29 Apr 2011 |
27 May 2011 to 26 Nov 2011 |
Valid |
|
GW-RS0680-11 |
22 Jul 2011 |
29 Jul 2011 to 19 Jan 2012 |
Valid |
|
GW-RS0689-11 |
28 Jul 2011 |
29 Jul 2011 to 28 Jan 2012 |
Valid |
|
GW-RS0832-11 |
7 Sep 2011 |
03 Sep 2011 to 02 Mar 2012 |
Valid |
|
GW-RS0850-11 |
12 Sept 2011 |
14 Sept 2011 to 13 Mar 2012 |
Valid |
|
GW-RS0851-11 |
12 Sept 2011 |
16 Sept 2011 to 15 Mar 2012 |
Valid |
|
GW-RE0683-11 |
16 Sept 2011 |
20 Sept 2011 to 19 Oct 2011 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
|