Contract No: HK/2009/05 Wanchai
Development Phase II and Sampling,
Field Measurement and Testing Work (Stage 1) Environmental Permit no.
EP-356/2009, Further
Evironmental permit nos. fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009
and Fep-05/356/2009 Monthly
Environmental Monitoring & Audit Report
- November 2011 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185
Gloucester Road, Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
12 December 2011 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of
Water Quality Monitoring Exceedances in Reporting Month
Table II Summary of
Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details of
Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/11
Table 3.3 Summary of
submission status under FEP-01/356/2009 Condition
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.5 Summary of
submission status under FEP-02/356/2009 Condition
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.7 Summary of
submission status under FEP-03/356/2009 Condition
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table 3.9 Summary of
submission status under FEP-04/356/2009 Condition
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2010/06
Table 3.11 Summary of submission status under
EP-356/2009 and FEP-05/356/2009 Condition
Table 4.1 Noise
Monitoring Station
Table 4.2 Real Time
Noise Monitoring Station
Table 4.3 Air
Monitoring Station
Table 4.4 Marine Water Quality Stations for Water
Quality Monitoring
Table 4.5 Marine Water
Quality Monitoring Frequency and Parameters
Table 4.6 Marine Water Quality Stations for
Enhanced Water Quality Monitoring
Table 5.1 Noise Monitoring Stations for Contract
no. HY/2009/11
Table 5.2 Noise Monitoring Station for Contract
nos. HK/2009/01, HK/2009/02 and HK/2010/06
Table 5.3 Noise Monitoring Station for Contract
no. HY/2009/15
Table 5.4 Real Time
Noise Monitoring Station for Contract no. HY/2009/11
Table 5.5 Air Monitoring Stations for Contract no.
HY/2009/11
Table 5.6 Air Monitoring Stations for Contract no.
HK/2009/01
Table 5.7 Air Monitoring Station for Contract no.
HK/2009/02
Table 5.8 Air Monitoring Station for Contract no.
HY/2009/15
Table 5.9 Water Monitoring Stations for Contract
no. HY/2009/11
Table 5.10 Water Monitoring Stations for Contract
no. HK/2009/01
Table 5.11 Water Monitoring Stations for Contract
no. HK/2009/02
Table 5.12 Water Monitoring Stations for Contract
no. HK/2009/02
Table 5.13 Water Monitoring Stations for Contract
no. HY/2009/15
Table 5.14 Summary of Water Quality Monitoring
Exceedances in Reporting Month
Table 5.15 Summary of Enhanced Dissolved Oxygen
Monitoring Exceedances in Reporting Month
Table 5.16 Details of Waste Disposal for Contract
no. HY/2009/11
Table 5.17 Details of Waste Disposal for Contract
no. HK/2009/01
Table 5.18 Details of Waste Disposal for Contract
no. HK/2009/02
Table 5.19 Details of Waste Disposal for Contract no.
HY/2009/15
Table 5.20 Details of Waste Disposal for Contract
no. HK/2010/06
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/11
Table 8.2 Summary of Environmental Inspections for
Contract no. HK/2009/01
Table 8.3 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.4 Summary of Environmental Inspections for
Contract no. HY/2009/15
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2010/06
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended
Mitigation Measures in Coming Reporting Month
lIST
OF FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project
Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST
OF APPENDIces
Appendix 3.1 Environmental Mitigation
Implementation Schedule
Appendix 4.1 Action
and Limit Level
Appendix
4.2 Copies
of Calibration Certificates
Appendix
5.1 Monitoring
Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring Results and
Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and
Graphical Presentations, and Odour Patrol Results
Appendix
5.4 Water
Quality
Monitoring Results and Graphical Presentations
Appendix
5.5 Real-time
Noise
Monitoring Results and Graphical Presentations
Appendix 6.1 Event
Action Plans
Appendix 6.2 Summary for
Notification of Exceedance
Appendix
9.1 Complaint
Log
Appendix 10.1 Construction
Programme of Individual Contracts
Construction Activities for the Reported Period
·
Geo-textile
laying;
·
Slotted panel
fixing;
·
Reclamation
works;
·
Installation of
Precast Coping;
·
Drainage
Construction works;
·
Installation of
Berm Blocks;
·
Outfall
construction works (Open Channel U);
·
Installation of precast
concrete blocks at seawall type 6 & 7;
·
Construction of
Seawall Type 8; and
·
Placing Granite
Facing Stone
·
Rock-filling for
sheet pile water channel from CH120 to CH160;
·
Dredging works
within HKCEC Water Channel from CH190 to CH260 for Type 1&2 sediment;
·
Removal of rock
armours from CH150 to CH260 at the north bank of HKCEC Water Channel;
·
Installation of
sheet pile for cooling water intake at Dome Promenade between CH120 and CH160;
·
Pre-cast RC
outfall for subsequent seawall reinstatement at Zone B1-3 has been concreted;
·
Reclamation of
HKCEC3W (up to CH110) with in HKCEC Water Channel has been commenced and
substantially completed;
·
Installation of
cross-harbor watermains nos. B10, A11/B11, A12/B12 and A13;
·
Trust block
construction for A5B5 was substantially completed;
·
Dredging of Type
3 sediment from CH50 to Ch250 for subsequent cross-harbor watermains
installation off Tsim Sha Tsui;
·
Installation of
pipe pile wall at TST seafront;
·
Installation of
sheet pile wall for pipe trench dredging at TST was substantially completed;
·
Mainlaying works
at Zone B1-4, B4-2, B4-5, A3-3, A3-2A, HKCEC Way In/Out, A4-3B, A2-23B and
A5-5;
·
Reinstatement
works at Zone B1-4 and A3-3;
·
Mainlaying works
at Zone A1-2 was substantially completed;
·
Mainlaying works
at Zone HKCEC Way In/Out;
·
Headind No. H2
was substantially complete;
·
Heading No. H3,
H4, H5 and H7;
·
Mainlaying works
and the subsequent carriageway reinstatement in Zone A4-3C was substantially
completed;
·
Tree
transplantation and its corresponding planter modification at Expo Drive; and
·
Trench
excavation and pipe laying works for a 1000 dia. Watermains (CHF) at Salisbury
Garden
·
Trial panel of
the 300mm thick topping slab;
·
R/F formwork
erection and steel fixing of Passenger Terminal Building;
·
Formwork for
lift shaft of Passenger Terminal Building;
·
Sheet piling for
Noise Barrier 2 of Helipad;
·
Demolition of
existing ferry pier;
·
Dismantling and
erection of formwork for concrete coping;
·
Casting of Expo
Drive East mass concreting coping formwork erection of Bays 8 and 9 were completed
on 11 November 2011, and Bay 5;
·
Formwork and
rebar fixing for the bus shelter footing at Expo Drive East;
·
Approximate 50m
cooling water pipe was laid at Harbour Centre, Harbour Road, Tonnochy Raod and
ex-pet garden;
·
Approximate
·
Construction of
wash out chamber at Harbour Road and access manhole at Harbour Centre;
·
Trench
excavation and cooling mains installation along Tonnochy Road;
·
Installation of
PVC and G.I cable ducts was ongoing at Harbour Road;
·
Installation of
submarine outfall pipe up to CHA-105 and CHB-130, continue backfilling on the
HDPE pipelines;
·
Dredging for submarine
outfall pipe;
·
Filling up grade
75 to gap between casing sleeves and pile casing of new ferry pier;
·
Installation of
lateral support and excavation for common trench for 132kV cable and manholes
of Wan Shing Street;
·
Rebar fixing of
base slab and formwork completed of Wan Shing Street at Bay 22 was completed;
·
Rock filling and
blinding of Wan Shing Street at Bays 23 and 24 were completed on 11 November
2011, and Bay 21 was completed on 18 November 2011;
·
Base slab of Wan
Shing Street at Bays 24;
·
Excavation and
lateral support for DSD receiving pits;
·
Commence D610
pipe pile wall construction at landside cofferdam of salt water intake culvert;
·
11 out of 12 nos
of pre-bored H-pile for box culverts N1 was casted as of 20 November 2011;
·
Removal of
falsework of P9 was completed on 13 November 2011, and P8 was completed on 19
November 2011;
·
Fabrication of the
steel frames for water diversion and temporary sheet pile walls of WCR2
reclamation commenced; and
·
Installation of
temporary sheet pile seawall of WCR-2
·
Seawall block construction and reclamation work at TS4;
·
Dredging works at ME4;
·
Night time protection works at CHT;
·
Precautionary works at Abutment A
·
Installation of bored pile casing;
·
Excavation of bored piles;
·
Concreting of bored piles; and
·
Pre-drilling works
Noise Monitoring
Real-time Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
Table I Summary
of Water Quality Monitoring Exceedances in Reporting Month
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD15 |
0 |
0 |
1 |
1 |
0 |
4 |
0 |
0 |
1 |
0 |
0 |
1 |
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C8 |
0 |
0 |
3 |
2 |
3 |
0 |
0 |
0 |
2 |
0 |
0 |
0 |
|
C9 |
0 |
0 |
3 |
2 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 |
WSD19 |
0 |
0 |
1 |
1 |
1 |
1 |
0 |
0 |
0 |
1 |
1 |
0 |
|
WSD20 |
0 |
0 |
1 |
2 |
1 |
2 |
0 |
0 |
1 |
0 |
0 |
1 |
|
WSD7 |
0 |
0 |
2 |
1 |
0 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C4w |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C5w |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
|
WSD21 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
1 |
0 |
0 |
0 |
HY/2009/15 |
C7 |
0 |
0 |
0 |
2 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
0 |
0 |
11 |
12 |
11 |
10 |
0 |
0 |
5 |
2 |
2 |
3 |
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
Table
II Summary of Enhanced Dissolved
Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring
Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
AL |
LL |
AL |
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
C7 |
1 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SE |
1 |
0 |
0 |
0 |
|
Total |
2 |
0 |
0 |
0 |
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/11- North Point Reclamation
·
Reclamation
works;
·
Geo-textile
laying;
·
Slotted panel
fixing;
·
Drainage
Construction works;
·
Installation of
berm blocks;
·
Concreting the
slopes of Open Channel U;
·
Construction of
in-situ mass concrete cooping;
·
Construction of
granite facing stone; and
·
Construction of
Seawall Type 8
Contract no. HK/2009/01 - Wan Chai Development
Phase II – Central –Wanchai Bypass at HKCEC
·
Reclamation of
HKCEC3W at the northern side within the HKCEC Water Channel;
·
Dredging from
CH160 to CH260 for subsequent reclamation within HKCEC Water Channel would be
resumed right after the consent from EPD for Type 3 sediment had been received.
·
Removal of rock
armour at North Bank of HKCEC Water Channel between Ch185 and Ch260;
·
Installation of
sheet pile water channel at Dome Promenade (from CH160 to CH260);
·
Rockfilling for
sheet pile water channel at Dome Promenade (from CH160 to CH260);
·
Installation of
Precast RC outfall at WC landfall section ;
·
Dredging of Type
3 sediment from CH50 to CH250 for subsequent cross-harbour watermians installation
off Tsim Sha Tsui would be continues right after the consent from EPD has been
received.
·
Installation of
cross-harbour watermains nos. B13, A14/B14 and A15> B15 ;
·
Installation of
pipe pile wall and the associated ground treatment would for the trenches
excavation of the proposed cross-harbour water mains no. A18/B18;
·
Installation of
pipepile wall at sea portion;
·
Thrust block construction
for A9.B9;
·
Works ; at Zone
A2-3B, A3-2A, A4-3A, HKCEC Way In/Out, A5/B5, B4-2, B4-5 and B5-1.
·
Trench
excavation at Zone A1-5A1;
·
Heading Nos. H3,
H4, H5 and H7;
·
Heading Nos. H13
would be commenced after a gantry have been erected at Fenwick Pier Street;
·
After the
completion of reinstatement works at Zone B1-4, mainlaying works at Zone B2-2,
B1-6 and B1-5B would be commenced; and
·
Reinstatement
works at Zone A3-3- would be completed and the subsequent TTA Zone A3-5B would
be commenced.
Contract no. HK/2009/02 - Wan Chai Development
Phase II – Central – Wan Chai Bypass at WanChai East
·
Operation of
Tseung Kwan O Public Fill Sorting Facility;
·
Construction of
passenger terminal;
·
300mm thick slab
construction at Northern Portion of Expo Drive East;
·
Excavation works
for noise barrier 2 at Expo Drive East;
·
Construction for
bus shelter at Expo Drive East;
·
Construction of
mass seawall coping at Expo Drive East;
·
Trench
excavation and pipe laying works along Harbour Road;
·
Trench
excavation and deck over at Tonnochy Road;
·
Construction
above -0.8mPD at Wan Shing Street for WSD Salt Water Intake;
·
Pipeline jacking
WSD intake A;
·
Pre-bored sheet
pile works for salt water intake culvert Bay1b & Bay 2;
·
Pre-bored H-pile
for Box Culvert N1 at WCR1 Area;
·
Concreting for marine
piles at new ferry pier;
·
Dredging and fabrication
of HDPE pipe diffuser section for submarine outfall pipes;
·
Backfilling of
bagged concrete and rockfills for the installed submarine outfall pipes;
·
Excavation and
lateral support for DSD receiving pits at Hung Hing Road;
·
Installation of
the temporary water diversion steel frame;
·
TTA traffic
diversion on Box Culvert O; and
·
Pre-bored
sheetpiling works at WCR1
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section)
·
ELS works at TS1
and TPCWAE;
·
Dredging works
at ME4;
·
Night time
protection works at CHT; and
·
Precautionary
works at Abutment A
Contract no. HK/2010/06 - Wan Chai Development
Phase II – Central – Wan Chai Bypass over MTR Tsuen Wan Line
·
Installation of
bored pile casing;
·
Excavation of
bored piles; and
·
Bored Pile
Concreting
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009
and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009,
FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring
and auditing work carried out in accordance to the Section 10.3 of EM&A
Manual and “Environmental Monitoring and Audit Requirements” under
Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
for Environmental Permit no. EP-356/2009, Further Environmental Permit no.
FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and
FEP-05/356/2009 and during the period 28th October to 27th
November 2011. The cut-off date of reporting is at 27th of each
reporting month.
Section
1 Introduction –
details the scope and structure of the report.
Section
2 Project
Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance –
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements – summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results – summarizes the monitoring results
obtained in the reporting period.
Section
6 Compliance
Audit – summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects – summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Site Inspection –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review
of any relevant
follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
– summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan Chai
Bypass” and “Central-Wan Chai Bypass and Island Eastern Corridor Link”
(hereafter called “the Project”) are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental
Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern
Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved
on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB
to provide relief to the very congested east-west Connaught Road
Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1.
The Project is located mainly in Wan Chai North,
Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria
Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road
Interchange to the east, as shown in Figure 2.1.
2.2.2.
The study area encompasses existing developments
along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses
include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the
Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the Royal
Hong Kong Yacht Club (RHKYC), the Police Officers’ Club, the Causeway Bay
Typhoon Shelter (CBTS) and commercial and residential developments.
2.2.3.
The scope of the Project
comprises:
·
Land formation
for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated
slip roads for connection to the Trunk Road and for through traffic from Central to
Wan Chai and Causeway Bay. The land formed for the above transport infrastructure
will provide opportunities for the development of an attractive waterfront
promenade for the enjoyment of the public
·
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
·
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
·
Upgrading of
hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
·
Provision of the
ground level roads, flyovers, footbridges, necessary transport facilities and
the associated utility services
·
Construction of
the new waterfront promenade, landscape works and the associated utility services
·
The Trunk Road
(i.e. CWB) within the study area and the associated slip roads for connection
to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1
summarises the five individual DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. Contractors of individual contracts will
be required by the EP holder to apply Further Environmental Permits (FEP) such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized
in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II – Central –Wanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central – Wan Chai Bypass – North
Point Reclamation |
DP3 |
17 March 2010 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the
construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
China Harbour- CRBC Joint Venture |
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
Mr. PL Yue |
9124 2471 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Operation Manager |
Mr. Lau Yee Ching |
9466 3918 |
|||
Construction Manager |
Mr. Jerry Siu |
9493 3664 |
|||
Construction Manager |
Mr. Terence Li |
9487 6549 |
|||
Construction Manager |
Mr. KK Yuen |
3498 1213 |
|||
Environmental Officer
(Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Mak Kam Wing |
3658 3044 |
|||
Quality & Environmental Manager |
Mr. C.P. Ho |
3658 3000 |
|||
Environmental Officer |
Ms. Flora Ng |
3658 3064 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2528 5651 |
Site Manager |
Mr. P J Fan |
3557 6368 |
2566 2192 |
||
|
|
Construction Manager |
Mr. C K Kwok |
9779 2162 |
|
|
|
Assistant Construction Manager (East) |
Mr. Gene Cheung |
6105 4880 |
|
|
|
Assistant Construction Manager (West) |
Mr. Tony Chiu |
9090 0606 |
|
|
|
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental Officer |
Mr. Lee Wai Man |
9481
6024 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HY/2009/11, the principal work
activities in this reporting month included:
·
Geo-textile
laying;
·
Slotted panel
fixing;
·
Reclamation
works;
·
Installation of
Precast Coping;
·
Drainage
Construction works;
·
Installation of
Berm Blocks;
·
Outfall
construction works (Open Channel U);
·
Installation of precast
concrete blocks at seawall type 6 & 7;
·
Construction of
Seawall Type 8; and
·
Placing Granite
Facing Stone
2.4.4.
For Contract no. HK/2009/01, the principal work
activities in this reporting month included:
·
Rock-filling for sheet pile water channel from CH120 to CH160;
·
Dredging works within HKCEC Water Channel from CH190 to CH260 for Type
1&2 sediment;
·
Removal of rock armours from CH150 to CH260 at the north bank of HKCEC
Water Channel;
·
Installation of sheet pile for cooling water intake at Dome Promenade
between CH120 and CH160;
·
Pre-cast RC outfall for subsequent seawall reinstatement at Zone B1-3
has been concreted;
·
Reclamation of HKCEC3W (up to CH110) with in HKCEC Water Channel has
been commenced and substantially completed;
·
Installation of cross-harbor watermains nos. B10, A11/B11, A12/B12 and
A13;
·
Trust block construction for A5B5 was substantially completed;
·
Dredging of Type 3 sediment from CH50 to Ch250 for subsequent
cross-harbor watermains installation off Tsim Sha Tsui;
·
Installation of pipe pile wall at TST seafront;
·
Installation of sheet pile wall for pipe trench dredging at TST was
substantially completed;
·
Mainlaying works at Zone B1-4, B4-2, B4-5, A3-3, A3-2A, HKCEC Way
In/Out, A4-3B, A2-23B and A5-5;
·
Reinstatement works at Zone B1-4 and A3-3;
·
Mainlaying works at Zone A1-2 was substantially completed;
·
Mainlaying works at Zone HKCEC Way In/Out;
·
Headind No. H2 was substantially complete;
·
Heading No. H3, H4, H5 and H7;
·
Mainlaying works and the subsequent carriageway reinstatement in Zone
A4-3C was substantially completed;
·
Tree transplantation and its corresponding planter modification at Expo
Drive; and
·
Trench excavation and pipe laying works for a 1000 dia. Watermains (CHF)
at Salisbury Garden
2.4.5.
For Contract no. HK/2009/02, the principal work
activities in this reporting month included:
·
Trial panel of the 300mm thick topping slab;
·
R/F formwork erection and steel fixing of Passenger Terminal Building;
·
Formwork for lift shaft of Passenger Terminal Building;
·
Sheet piling for Noise Barrier 2 of Helipad;
·
Demolition of existing ferry pier;
·
Dismantling and erection of formwork for concrete coping;
·
Casting of Expo Drive East mass concreting coping formwork erection of
Bays 8 and 9 were completed on 11 November 2011, and Bay 5;
·
Formwork and rebar fixing for the bus shelter footing at Expo Drive
East;
·
Approximate 50m cooling water pipe was laid at Harbour Centre, Harbour
Road, Tonnochy Raod and ex-pet garden;
·
Approximate
·
Construction of wash out chamber at Harbour Road and access manhole at Harbour
Centre;
·
Trench excavation and cooling mains installation along Tonnochy Road;
·
Installation of PVC and G.I cable ducts was ongoing at Harbour Road;
·
Installation of submarine outfall pipe up to CHA-105 and CHB-130, continue
backfilling on the HDPE pipelines;
·
Dredging for submarine outfall pipe;
·
Filling up grade 75 to gap between casing sleeves and pile casing of new
ferry pier;
·
Installation of lateral support and excavation for common trench for
132kV cable and manholes of Wan Shing Street;
·
Rebar fixing of base slab and formwork completed of Wan Shing Street at
Bay 22 was completed;
·
Rock filling and blinding of Wan Shing Street at Bays 23 and 24 were
completed on 11 November 2011, and Bay 21 was completed on 18 November 2011;
·
Base slab of Wan Shing Street at Bays 24;
·
Excavation and lateral support for DSD receiving pits;
·
Commence D610 pipe pile wall construction at landside cofferdam of salt
water intake culvert;
·
11 out of 12 nos of pre-bored H-pile for box culverts N1 was casted as
of 20 November 2011;
·
Removal of falsework of P9 was completed on 13 November 2011, and P8 was
completed on 19 November 2011;
·
Fabrication of the steel frames for water diversion and temporary sheet
pile walls of WCR2 reclamation commenced; and
·
Installation of temporary sheet pile seawall of WCR-2
2.4.6.
For Contract no. HY/2009/15, the principal work
activities in this reporting month included:
·
Seawall block construction and reclamation work at TS4;
·
Dredging works at ME4;
·
Night time protection works at CHT;
·
Precautionary works at Abutment A
2.4.7.
For Contract no. HK/2010/06, the principal work
activities in this reporting month included:
·
Installation of bored pile casing;
·
Excavation of bored piles;
·
Concreting of bored piles; and
·
Pre-drilling works
2.4.8.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. HY/2009/11- North Point Reclamation
·
Reclamation
works;
·
Geo-textile
laying;
·
Slotted panel
fixing;
·
Drainage
Construction works;
·
Installation of
berm blocks;
·
Concreting the
slopes of Open Channel U;
·
Construction of
in-situ mass concrete cooping;
·
Construction of
granite facing stone; and
·
Construction of
Seawall Type 8
Contract no. HK/2009/01 - Wan Chai Development
Phase II – Central –Wanchai Bypass at HKCEC
·
Reclamation of
HKCEC3W at the northern side within the HKCEC Water Channel;
·
Dredging from
CH160 to CH260 for subsequent reclamation within HKCEC Water Channel would be
resumed right after the consent from EPD for Type 3 sediment had been received.
·
Removal of rock
armour at North Bank of HKCEC Water Channel between Ch185 and Ch260;
·
Installation of
sheet pile water channel at Dome Promenade (from CH160 to CH260);
·
Rockfilling for
sheet pile water channel at Dome Promenade (from CH160 to CH260);
·
Installation of
Precast RC outfall at WC landfall section ;
·
Dredging of Type
3 sediment from CH50 to CH250 for subsequent cross-harbour watermians installation
off Tsim Sha Tsui would be continues right after the consent from EPD has been
received.
·
Installation of
cross-harbour watermains nos. B13, A14/B14 and A15> B15 ;
·
Installation of
pipe pile wall and the associated ground treatment would for the trenches
excavation of the proposed cross-harbour water mains no. A18/B18;
·
Installation of
pipepile wall at sea portion;
·
Thrust block
construction for A9.B9;
·
Works ; at Zone
A2-3B, A3-2A, A4-3A, HKCEC Way In/Out, A5/B5, B4-2, B4-5 and B5-1.
·
Trench
excavation at Zone A1-5A1;
·
Heading Nos. H3,
H4, H5 and H7;
·
Heading Nos. H13
would be commenced after a gantry have been erected at Fenwick Pier Street;
·
After the completion
of reinstatement works at Zone B1-4, mainlaying works at Zone B2-2, B1-6 and
B1-5B would be commenced; and
·
Reinstatement
works at Zone A3-3- would be completed and the subsequent TTA Zone A3-5B would
be commenced.
Contract no. HK/2009/02 - Wan Chai Development
Phase II – Central – Wan Chai Bypass at WanChai East
·
Operation of
Tseung Kwan O Public Fill Sorting Facility;
·
Construction of
passenger terminal;
·
300mm thick slab
construction at Northern Portion of Expo Drive East;
·
Excavation works
for noise barrier 2 at Expo Drive East;
·
Construction for
bus shelter at Expo Drive East;
·
Construction of
mass seawall coping at Expo Drive East;
·
Trench
excavation and pipe laying works along Harbour Road;
·
Trench
excavation and deck over at Tonnochy Road;
·
Construction
above -0.8mPD at Wan Shing Street for WSD Salt Water Intake;
·
Pipeline jacking
WSD intake A;
·
Pre-bored sheet
pile works for salt water intake culvert Bay1b & Bay 2;
·
Pre-bored H-pile
for Box Culvert N1 at WCR1 Area;
·
Concreting for
marine piles at new ferry pier;
·
Dredging and fabrication
of HDPE pipe diffuser section for submarine outfall pipes;
·
Backfilling of
bagged concrete and rockfills for the installed submarine outfall pipes;
·
Excavation and
lateral support for DSD receiving pits at Hung Hing Road;
·
Installation of
the temporary water diversion steel frame;
·
TTA traffic
diversion on Box Culvert O; and
·
Pre-bored
sheetpiling works at WCR1
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section)
·
ELS works at TS1
and TPCWAE;
·
Dredging works
at ME4;
·
Night time
protection works at CHT; and
·
Precautionary
works at Abutment A
Contract no. HK/2010/06 - Wan Chai Development
Phase II – Central – Wan Chai Bypass over MTR Tsuen Wan Line
·
Installation of
bored pile casing;
·
Excavation of
bored piles; and
·
Bored Pile
Concreting
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009/A |
4 Aug
2010 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb
2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
22 Nov
2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Valid |
Further
Environmental Permit |
FEP-01/364/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further
Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Valid |
Further
Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Surrendered |
Further
Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HY/2009/11 –
Central – Wanchai Bypass, North Point Reclamation
3.1.3.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-01/356/2009 for contract no. HY/2009/11 are shown in Table 3.2 and
Table 3.3.
3.1.4.
Contractor submitted a letter dated 20 July 2011 to
confirm that the dredging works and dumping operation were completed.
Table 3.2 Cumulative
Summary of Valid Licences and Permits
under Contract no. HY/2009/11
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
N/A |
Valid |
Notification of Works Under APCO |
331892 |
4 Jul. 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0330-11 |
15 Apr 2011 |
1 May 2011 to 31 Oct 2011 |
Expired |
GW-RS0922-11 |
12 Oct 2011 |
1 Nov 2011 to 30 Apr 2012 |
Valid |
|
Registration as a Chemical Waste Producer |
WPN5213-151-C3631-02 |
12 Oct 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7010037 |
13 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00007942-2010 |
29 Nov 2010 |
30 Nov 2015 |
Valid |
Table
3.3 Summary of submission status under
FEP-01/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
18 Dec 2009 |
Condition 2.7 |
Submission of works schedule
and location plan |
8 Feb 2010 |
Condition 2.8 |
Revised Silt Curtain Deployment
Plan (Rev. 3) |
4 Dec 2010 |
Condition 2.9 |
Silt Screen Deployment Plan
(Rev. 6) |
18 May 2011 |
Condition 2.10 |
Coral Translocation Plan |
20 Nov 2009 |
Condition 2.16 |
Revised Noise Management Plan
(Rev 5) |
19 Feb 2011 |
Condition 2.17 |
Landscape Plan |
12 May 2010 |
|
Revised landscape Plan |
30 Jun 2010 |
|
Submission of Supplementary
Information - Revised Management & Maintenance Schedule for Submitted
Revised Landscape Plan |
25 Aug 2010 |
Contract no. HK/2009/01 - Wan Chai Development
Phase II – Central –Wanchai Bypass at HKCEC
3.1.5.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and
Table 3.5.
Table
3.4 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0384-11 |
29 Apr 2011 |
27 May 2011 to 26 Nov 2011 |
Expired |
|
GW-RS0680-11 |
22 Jul 2011 |
29 Jul 2011 to 19 Jan 2012 |
Valid |
|
GW-RS0689-11 |
28 Jul 2011 |
29 Jul 2011 to 28 Jan 2012 |
Valid |
|
GW-RS0832-11 |
7 Sep 2011 |
03 Sep 2011 to 02 Mar 2012 |