Contract No: HK/2009/05

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 1)

 

Environmental Permit no. EP-356/2009,

Further Evironmental permit nos. fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 and Fep-05/356/2009

 

Monthly Environmental Monitoring & Audit Report

 

- december 2011 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

13 January 2012


Table of contents

 

EXECUTIVE SUMMARY. 4

1.     Introduction. 10

1.1        Scope of the Report 11

1.2        Structure of the Report 11

2.     Project Background. 13

2.1        Background. 13

2.2        Scope of the Project and Site Description. 13

2.3        Division of the Project Responsibility. 14

2.4        Project Organization and Contact Personnel 15

3.     Status of Regulatory Compliance. 22

3.1        Status of Environmental Licensing and Permitting under the Project 22

4.     Monitoring Requirements. 31

4.1        Noise Monitoring. 31

4.2        Air Monitoring. 32

4.3        Water Quality Monitoring. 35

5.     Monitoring Results. 40

5.1        Noise Monitoring Results. 40

5.2        Real-time Noise Monitoring. 41

5.3        Air Monitoring Results. 42

5.4        Water Monitoring Results. 43

5.5        Waste Monitoring Results. 47

6.     Compliance Audit. 51

6.1        Noise Monitoring. 51

6.2        Real-time noise Monitoring. 51

6.3        Air Monitoring. 51

6.4        Water Quality Monitoring. 51

6.5        Review of the Reasons for and the Implications of Non-compliance. 53

6.6        Summary of action taken in the event of and follow-up on non-compliance. 53

7.     Cumulative Construction Impact due to the Concurrent Projects. 54

8.     Environmental Site Audit. 55

9.     Complaints, Notification of Summons and Prosecution. 57

10.    Conclusion. 60


lIST OF TABLES

 

Table I         Summary of Water Quality Monitoring Exceedances in Reporting Month

Table II        Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Table 2.1     Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 3.1      Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.2      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/11

Table 3.3      Summary of submission status under FEP-01/356/2009 Condition

Table 3.4      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.5      Summary of submission status under FEP-02/356/2009 Condition

Table 3.6      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.7      Summary of submission status under FEP-03/356/2009 Condition

Table 3.8      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.9      Summary of submission status under FEP-04/356/2009 Condition

Table 3.10    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2010/06

Table 3.11    Summary of submission status under EP-356/2009 and FEP-05/356/2009 Condition

Table 4.1      Noise Monitoring Station

Table 4.2      Real Time Noise Monitoring Station

Table 4.3      Air Monitoring Station

Table 4.4     Marine Water Quality Stations for Water Quality Monitoring

Table 4.5      Marine Water Quality Monitoring Frequency and Parameters

Table 4.6     Marine Water Quality Stations for Enhanced Water Quality Monitoring

Table 4.7     Marine Water Quality Stations for Additional DO Monitoring

Table 5.1     Noise Monitoring Stations for Contract no. HY/2009/11

Table 5.2     Noise Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06

Table 5.3     Noise Monitoring Station for Contract no. HY/2009/15

Table 5.4      Real Time Noise Monitoring Station for Contract no. HY/2009/11

Table 5.5     Air Monitoring Stations for Contract no. HY/2009/11

Table 5.6     Air Monitoring Stations for Contract no. HK/2009/01

Table 5.7     Air Monitoring Station for Contract no. HK/2009/02

Table 5.8     Air Monitoring Station for Contract no. HY/2009/15

Table 5.9     Water Monitoring Stations for Contract no. HY/2009/11

Table 5.10    Water Monitoring Stations for Contract no. HK/2009/01

Table 5.11    Water Monitoring Stations for Contract no. HK/2009/02

Table 5.12    Water Monitoring Stations for Contract no. HK/2009/02

Table 5.13    Water Monitoring Stations for Contract no. HY/2009/15

Table 5.14    Summary of Water Quality Monitoring Exceedances in Reporting Month

Table 5.15    Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Table 5.16    Details of Waste Disposal for Contract no. HY/2009/11

Table 5.17    Details of Waste Disposal for Contract no. HK/2009/01

Table 5.18    Details of Waste Disposal for Contract no. HK/2009/02

Table 5.19    Details of Waste Disposal for Contract no. HY/2009/15

Table 5.20    Details of Waste Disposal for Contract no. HK/2010/06

Table 8.1      Summary of Environmental Inspections for Contract no. HY/2009/11

Table 8.2     Summary of Environmental Inspections for Contract no. HK/2009/01

Table 8.3     Summary of Environmental Inspections for Contract no. HK/2009/02

Table 8.4     Summary of Environmental Inspections for Contract no. HY/2009/15

Table 8.5     Summary of Environmental Inspections for Contract no. HK/2010/06

Table 9.1      Cumulative Statistics on Complaints

Table 9.2      Cumulative Statistics on Successful Prosecutions

Table 10.1    Construction Activities and Recommended Mitigation Measures in Coming Reporting Month

 

 

lIST OF FIGUREs

 

Figure 2.1          Project Layout

Figure 2.2          Project Organization Chart

Figure 4.1         Locations of Environmental Monitoring Stations

 

 

 

lIST OF APPENDIces

 

Appendix 3.1     Environmental Mitigation Implementation Schedule

Appendix 4.1     Action and Limit Level

Appendix 4.2     Copies of Calibration Certificates

Appendix 5.1     Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2     Noise Monitoring Results and Graphical Presentations

Appendix 5.3     Air Quality Monitoring Results and Graphical Presentations, and Odour Patrol Results

Appendix 5.4     Water Quality Monitoring Results and Graphical Presentations

Appendix 5.4a   Additional Dissolved Oxygen Monitoring Results

Appendix 5.5     Real-time Noise Monitoring Results and Graphical Presentations

Appendix 6.1     Event Action Plans

Appendix 6.2     Summary for Notification of Exceedance

Appendix 9.1     Complaint Log

Appendix 10.1   Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report ¡V December 2011 for the Project of Wan Chai Development Phase II and Central-Wanchai Bypass under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009. This report presents the environmental monitoring findings and information recorded during the period 28th November 2011 to 27th December 2011. The cut-off date of reporting is at 27th of each reporting month.

 

Construction Activities for the Reported Period

  1. During this reporting period, the major work activities for Contract no. HY/2009/11 included:

¡P          Reclamation works;

¡P          Geo-textile laying;

¡P          Slotted panel fixing;

¡P          Drainage Construction works;

¡P          Installation of berm blocks;

¡P          Concreting the slopes of Open Channel U;

¡P          Construction of in-situ mass concrete cooping;

¡P          Construction of granite facing stone; and

¡P          Construction of Seawall Type 8

 

  1. During this reporting period, the major work activities for Contract no. HK/2009/01 included:

¡P          Dredging works within HKCEC Water Channel from CH190 to CH260 for Type 1 & 2 sediment was commences and substantially completed;

¡P          Removal of rock armours from CH150 to CH180 at the North bank of HKCEC Water Channel was commenced and substantially completed;

¡P          A trial for Type 3 sediment disposal was carried out;

¡P          Installation of sheet pile for cooling water intake at Dome Promenade between CH120 and CH170;

¡P          Installation of precast RC outfall at Zone B1-3;

¡P          Trench excavation for the 4 nos. of cooling water discharge pipes at B1-3;

¡P          Reclamation of HKCEC3W (up to CH130) within HKCEC Water Channel;

¡P          Installation of cross -harbour water mains nos. B13, A14/B14 and A15/ B15;

¡P          Thrust block construction for A9/B9 and A11/B11 was commenced;

¡P          Concrete coating at flange joint of cross-harbour water mains nos. A7B7/A8B8, A8B8/A9B9 and A9B9/A10B10;

¡P          Rockfilling and rock protection to cross-harbour watermains;

¡P          Installation of pipe pile at TST (Land Portion) was commenced and substantially completed;

¡P          Grouting works at TST seafront along the pipe piles have been installed;

¡P          Dredging of Type 2 sediment from CH50 to CH250 for subsequent cross-harbour watermains installation off Tsim Sha Tsui;

¡P          Mainlaying works at Zone B1-5B, B1-6, B2-2, B4-2, B4-5, A1-5A, A3-2A, HKCEC Way In/Out, A2-3B and A5-5;

¡P          Mainlaying works at Zone B1-6, B2-2 and B1-5B;

¡P          Coring and Grouting works for external wall of cooling pumping stations Nos. P4 & P5 at Zone B4-5;

¡P          Coring works for external wall of cooling pumping station No P1 at Zone B4-2;

¡P          Mainlaying works at Zone A1-5A1 and A3-5B;

¡P          Heading No. H4, H5, H7 and H13;

¡P          Heading No. H3 was substantially completed.

¡P          GI duct laying works at ZoneA4-3A and Zone A4-3B;

¡P          Trench excavation, pipe laying works and chamber construction for a 1000 dia. watermains (CHF) at Salisbury Garden

 

  1. During this reporting period, the major work activities for Contract no. HK/2009/02 included:

¡P          300mm thick topping slab together with the make up slab below at northern portion commenced on 30 Nov 2011;

¡P          Concreting at Roof Plinth, lift shaft up to +14.15mPD and Fire Service Pump room up to +14.15mPD of Passenger Terminal Building were completed;

¡P          E&M and ABWF of Passenger Terminal Building;

¡P          ELS of Noise Barrier 2 commenced on 29 Nov 2011 and nearly completed.

¡P          Casting of pedestrian pavement above seawall coping Bay 4 to Bay 8 was completed on 13 December 2011;

¡P          Casting of the bus shelter footing at Expo Drive East was completed;

¡P          Precast slab installation at the existing movable ramp was in progress;

¡P          Saw cutting of existing slabs for the construction NB1 footing was completed;

¡P          E&M of P7, P8 & P9

¡P          Approximate 50m cooling water pipe was laid at Harbour Centre, Harbour Road, Tonnochy Road and ex-pet garden;

¡P          Jacking pit at ex-pet garden for the heading construction of cooling mains across Convention Avenue commenced;

¡P          Approximate 50m cable duct was laid at Harbour Road and Tonnochy Road.

¡P          Construction of wash out chamber at Harbour Road and access manhole at Harbour Centre were completed;

¡P          Trench excavation and cooling mains installation along Tonnochy Road;

¡P          Installation of PVC and G.I cable ducts was ongoing at Harbour Road;

¡P          Installation of submarine outfall pipe was completed;

¡P          Dredging for submarine outfall pipe was ongoing;

¡P          Concreting the Base Slab of Wan Shing Street at Bay 24 was completed;

¡P          Concreting the wall shaft and roof slab completed of Wan Shing Street at Bay 21 and Bay 24 were completed;

¡P          Bay 21 to Bay 24 of Wan Shing Street were handover to HEC;

¡P          Slab at +3.10mPD and +3.77 mPD and wall below were completed for the WSD Salt Water Pumping Station;

¡P          Excavation and lateral support for DSD receiving pits were completed;

¡P          D610 pipe pile wall construction at landside cofferdam of salt water intake culvert;

¡P          12 out of 12 nos of pre-bored H-pile for box culverts N1 was casted as of 21 November 2011;

¡P          Temporary working platform was completed and pile cap construction was in progress at Portion 1B for the New Ferry Pier

 

  1. During this reporting period, the major work activities for Contract no. HY/2009/15 included:

¡P          Seawall block construction and reclamation work at TS4;

¡P          Night time protection works at CHT; and

¡P          Precautionary works at Abutment A

 

  1. During this reporting period, the major work activities for Contract no. HK/2010/06 included:

¡P          Installation of bored pile casing;

¡P          Excavation of bored piles; and

¡P          Concreting of bored piles

 

Noise Monitoring

  1. Noise monitoring during daytime and restricted hour were conducted at the stations M1a, M2b, M3a, M4b and M5b on a weekly basis in the reporting month. Two limit level exceedances were recorded at M1a - Harbour Road Sports Centre on 29 November and 6 December 2011 during restricted hour. Investigation found that major traffic noise was contributed in the noise monitoring at M1a and the exceedances were not related to the Project. The construction works conducted were complied with the conditions of CNPs.

 

Real-time Noise Monitoring

  1. Real-time noise monitoring at FEHD Hong Kong Transport Section Whitefield Depot and Oil Street Community Centre have been commenced on 5 October 2010 for the filling works of Contract no. HY/2009/11. No project-related exceedance was recorded in the reporting month.

 

Air Quality Monitoring

  1. Air quality monitoring has been conducted at stations CMA1b, CMA2a, CMA3a, CMA4a, CMA5a and CMA6a. No exceedance was recorded in the reporting month.

 

Water Quality Monitoring

  1. Water quality monitoring at 18 monitoring stations was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table I.

 

Table I    Summary of Water Quality Monitoring Exceedances in Reporting Month

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HY/2009/11

WSD9

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD10

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD15

0

0

0

0

0

1

0

0

0

0

0

0

 

WSD17

0

0

0

0

0

0

0

0

0

0

0

0

 

C8

0

0

2

0

0

0

0

0

0

0

0

0

 

C9

0

0

1

0

0

0

0

0

0

0

0

0

HK/2009/01

WSD19

0

0

0

1

0

0

0

0

0

0

0

0

 

WSD20

0

0

1

2

0

3

0

0

0

0

0

0

 

WSD7

0

0

1

1

0

2

0

0

0

0

0

0

 

C1

0

0

0

0

0

0

0

0

0

0

0

0

 

C3

0

0

0

0

1

0

0

0

0

0

0

0

 

C4e

0

0

0

0

0

0

0

0

0

0

0

1

 

C4w

0

0

0

0

0

0

0

0

0

0

0

1

HK/2009/01

& HK/2010/06

C2

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/02

C5e

0

0

0

0

0

0

0

0

1

0

1

0

 

C5w

0

0

0

0

0

1

0

0

0

0

0

0

 

WSD21

0

0

0

0

0

0

0

0

0

0

0

0

HY/2009/15

C7

0

0

0

0

0

0

0

0

0

0

0

0

Total

0

0

5

4

1

7

0

0

1

0

1

2

Remarks: -    The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

 

  1. Enhanced DO monitoring at 4 monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table II.

 

Table II    Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

DO

AL

LL

AL

LL

HY/2009/15

C6

0

0

0

0

C7

0

0

0

0

Ex-WPCWA SW

0

0

0

0

Ex-WPCWA SE

0

1

0

0

Total

0

1

0

0

 

  1. In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be installed to channel water discharge flow from Culvert L to locations outside the embayment area, a proposed replacement of the requirement with additional dissolved oxygen monitoring has been conducted at three monitoring stations, namely A, B and C between the eastern seawall of Central Reclamation Phase III and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level between the eastern seawall of Central Reclamation Phase II and the HKCEC extension could be continuously monitored.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. There was no complaint received in this reporting month.

 

Site Inspections and Audit

  1. The Environmental Team (ET) conducted weekly site inspections for Contract nos. HY/2009/11, HK/2009/01, HK/2009/02, HY/2009/15 and HK/2010/06 under EP no. EP-356/2009 in the reporting month. Major observations and recommendations made during the audit sessions were rectified by the Contractors. No non-conformance was identified during the site inspections.

 

Future Key Issues

  1. In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HY/2009/11- North Point Reclamation

¡P          The portion of NPR3 are scheduled to be completed and handover in January 2012. No construction work related to DP3 is anticipated to be conduced in coming month.

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

¡P          Reclamation of HKCEC3W at the northern side within the HKCEC Water Channel would be continued;

¡P          Dredging from CH160 to CH260 for subsequent reclamation within HKCEC Water Channel would be resumed right after the consent from EPD for type 3 sediment has been received;

¡P          Rockfilling from CH160 to CH260 for subsequent reclamation within HKCEC Water Channel would be commenced;

¡P          Installation of sheet pile water channel at Dome Promenade (from CH120 to CH170) would be commenced;

¡P          Installation of sheet pile water channel at Dome Promenade (from CH170 to CH260) would be commenced;

¡P          Mainlaying works for 4 nos. of cooling water discharge pipes at WC landfall section (B1-3) would be completed. And subsequent reinstatement works was anticipated to be completed be completed;

¡P          Dredging of type 3 sediment from CH50 to CH250 for subsequent cross-harbour watermains installation off Tsim Sha Tsui would be continued right after the consent from EPD has been received;

¡P          Ground treatment works for the trenches excavation of the proposed cross-harbour watermains nos. A18/b18 would be continued and anticipated to be completed;

¡P          Installation of pipe pile wall at sea portion would be continued and anticipated to be completed;

¡P          Thrust block construction, concrete coating for flange joint and Rockfilling protection works would be continued;

¡P          Works would be continued at Zone A1-5A1, A2-3B, A3-3, A3-2A, A3-5B, A3-5B, A4-3A, A4-3B, HKCEC way in/out, A5-5, B4-2, B4-5, B1-6 and B2-2;

¡P          GI duct laying works at Zone A4-3A and A4-3 B would be completed;

¡P          Heading Nos. H4, H5, H7 and H13 would be continued;

¡P          Heading Nos. H4 and H13 would be completed;

¡P          Heading No. H8 would be commenced after its corresponding jacking pit at Zone A1-5A1 has been excavated;

¡P          After the completion of mainlaying works at Zone B4-2 and B4-5, mainlaying works at Zone B4-4 would be commenced;

¡P          After the completion of mainlaying works at HKCEC way in/out, mainlaying works at Zone B4-2A would be commenced;

¡P          After the completion of mainlaying works at A5-5, mainlaying works at Zone B5-2 would be commenced.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

¡P          Preparation works for temporary diversion intakes of WSD salt water pumping station and Sun Hung Kai pumping station.

¡P          Continue operation of Tseung Kwan O Public Fill Sorting Facility;

¡P          Continue E&M works and ABWF works of passenger terminal;

¡P          Complete 300mm thick slab construction at Northern Portion of Expo Drive East;

¡P          Complete excavation works for noise barrier 2 at Expo Drive East;

¡P          Continue slab modification for NB 1 footing at Expo Drive East;

¡P          Continue construction for bus shelter at Expo Drive East;

¡P          Continue trench excavation and pipe laying works along Harbour Road;

¡P          Continue trench excavation and deck over at Tonnochy Road;

¡P          Continue construction from +3.10mPD to + 5.17mPD for WSD Salt Water Pumping Station;

¡P          Complete pipeline jacking WSD intake A;

¡P          Continue construction of seaside cofferdams for salt water intake culvert, submarine outfall and Box Culvert N1;

¡P          Commence excavation works of landside cofferdam for the construction of Bay 6 ¡V 10 salt water intake culvert;

¡P          Continue backfilling rockfills for the installed submarine outfall pipes;

¡P          Continue installation of the temporary water diversion steel frame;

¡P          Commence the temporary internal propping works for Box Culvert O construction;

¡P          Continue substructure works for the New Ferry Pier

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

¡P          ELS works at TS1;

¡P          Pumping test and ELS preparation works at TPCWAE ;

¡P          Night time protection works at CHT; and

¡P          Precautionary works at Abutment A

 

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line

¡P          Installation of bored pile casing;

¡P          Excavation of bored piles; and

¡P          Bored Pile Concreting

1.         Introduction

1.1               Scope of the Report

1.1.1.        Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.        This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under Particular Specification Section 27.

1.1.3.        This report documents the finding of EM&A works for Environmental Permit no. EP-356/2009, Further Environmental Permit no. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 and during the period 28th November to 27th December 2011. The cut-off date of reporting is at 27th of each reporting month.

 

1.2               Structure of the Report

 

Section 1        Introduction ¡V details the scope and structure of the report.

 

Section 2        Project Background ¡V summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3        Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4        Monitoring Requirements ¡V summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5        Monitoring Results ¡V summarizes the monitoring results obtained in the reporting period.

 

Section 6        Compliance Audit ¡V summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7        Cumulative Construction Impact due to the Concurrent Projects ¡V summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8       Site Inspection ¡V summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9        Complaints, Notification of summons and Prosecution ¡V summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10      Conclusion

2.         Project Background

2.1               Background

2.1.1.        ¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called ¡§the Project¡¨) are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.        The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.        There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2               Scope of the Project and Site Description

2.2.1.        The Project is located mainly in Wan Chai North, Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road Interchange to the east, as shown in Figure 2.1.

2.2.2.        The study area encompasses existing developments along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police Officers¡¦ Club, the Causeway Bay Typhoon Shelter (CBTS) and commercial and residential developments.

2.2.3.        The scope of the Project comprises:

¡P          Land formation for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for connection to the Trunk Road and for through traffic from Central to Wan Chai and Causeway Bay. The land formed for the above transport infrastructure will provide opportunities for the development of an attractive waterfront promenade for the enjoyment of the public

¡P          Reprovisioning / protection of the existing facilities and structures affected by the land formation works mentioned above

¡P          Extension, modification, reprovisioning or protection of existing storm water drainage outfalls, sewerage outfalls and watermains affected by the revised land use and land formation works mentioned above

¡P          Upgrading of hinterland storm water drainage system and sewerage system, which would be rendered insufficient by the land formation works mentioned above

¡P          Provision of the ground level roads, flyovers, footbridges, necessary transport facilities and the associated utility services

¡P          Construction of the new waterfront promenade, landscape works and the associated utility services

¡P          The Trunk Road (i.e. CWB) within the study area and the associated slip roads for connection to the Trunk Road.

 

2.2.4.        The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1      Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3               Division of the Project Responsibility

2.3.1.        Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced. Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits (FEP) such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.        The details of individual contracts are summarized in Table 2.2.

 

 

 

Table 2.2 Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HK/2009/01

Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at Hong Kong Convention and Exhibition Centre

DP3, DP6

23 July 2010

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

DP3, DP5

5 July 2010

DP1

26 April 2011

HY/2009/11

Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North Point Reclamation

DP3

17 March 2010

HY/2009/15

Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

DP3

10 November 2010

DP1

13 July 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

HY/2009/17

Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works.

DP1

5 October 2010

HY/2009/18

Central - Wan Chai Bypass (CWB) ¡V Central Interchange

DP1

21 April 2011

HY/2009/19

Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

 

2.4               Project Organization and Contact Personnel

2.4.1.        Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.        The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3 Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer for CWB

Principal Resident Engineer

Mr. Peter Poon

3916 1818

3529 2829

China Harbour- CRBC Joint Venture

Contractor under Contract no. HY/2009/11

Project Director

Mr. Cho Yu Fun

3157 1086

3157 1085

Project Manager

Mr. Gregory Wong

3157 1086

Site Agent

Mr. Daniel Cheung

3157 1086

Environmental Officer

Mr. C. M. Wong

3157 1086

Chun Wo ¡V Leader Joint Venture

Contractor under Contract no. HK/2009/01

Project Director

Mr. PL Yue

9124 2471

2634 1626

Site Agent

Mr. Paul Yu

9456 9819

Operation Manager

Mr. Lau Yee Ching

9466 3918

Construction Manager

Mr. Wyman Wong

9627 2467

Construction Manager

Mr. Jack Chu

9775 3008

Construction Manager

Mr. KK Yuen

Mr. Andy Yu

9498 1213

96484896

Environmental Officer (Compliance Manager)

Mr. Andy Mak

9103 2370

Chun Wo ¡V CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Project Manager

Mr. Chan Sing Cho

3658 3002

2827 9996

Site Agent

Mr. Mak Kam Wing

3658 3044

Quality & Environmental Manager

Mr. C.P. Ho

3658 3000

Environmental Officer

Ms. Flora Ng

3658 3064

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Manager

Mr. M Y Wong

2823 7879

2528 5651

Site Manager

Mr. P J Fan

3557 6368

2566 2192

 

 

Construction Manager

Mr. C K Kwok

9779 2162

 

 

 

Construction Manager (East)

Gene Cheung

6105 4880

 

 

 

Construction Manager (West)

Tony Chiu

9090 0606

 

 

 

Environmental Officer

Mr. Daniel Sin

3557 6215

 

Gammon

-Leader JV

Contractor under Contract no. HK/2010/06

Project Manager

Mr. Paul Lui

9095 7922

2529 2880

Site Agent

Mr. Keith Tse

2529 2068

Environmental Officer

Mr. Lee Wai Man

9481 6024

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3743 0788

3548 6988

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

2.4.3.        For Contract no. HY/2009/11, the principal work activities in this reporting month included:

¡P          Reclamation works;

¡P          Geo-textile laying;

¡P          Slotted panel fixing;

¡P          Drainage Construction works;

¡P          Installation of berm blocks;

¡P          Concreting the slopes of Open Channel U;

¡P          Construction of in-situ mass concrete cooping;

¡P          Construction of granite facing stone; and

¡P          Construction of Seawall Type 8

 

2.4.4.        For Contract no. HK/2009/01, the principal work activities in this reporting month included:

¡P          Dredging works within HKCEC Water Channel from CH190 to CH260 for Type 1 & 2 sediment was commences and substantially completed;

¡P          Removal of rock armours from CH150 to CH180 at the North bank of HKCEC Water Channel was commenced and substantially completed;

¡P          A trial for Type 3 sediment disposal was carried out;

¡P          Installation of sheet pile for cooling water intake at Dome Promenade between CH120 and CH170;

¡P          Installation of precast RC outfall at Zone B1-3;

¡P          Trench excavation for the 4 nos. of cooling water discharge pipes at B1-3;

¡P          Reclamation of HKCEC3W (up to CH130) within HKCEC Water Channel;

¡P          Installation of cross -harbour water mains nos. B13, A14/B14 and A15/ B15;

¡P          Thrust block construction for A9/B9 and A11/B11 was commenced;

¡P          Concrete coating at flange joint of cross-harbour water mains nos. A7B7/A8B8, A8B8/A9B9 and A9B9/A10B10;

¡P          Rockfilling and rock protection to cross-harbour watermains;

¡P          Installation of pipe pile at TST (Land Portion) was commenced and substantially completed;

¡P          Grouting works at TST seafront along the pipe piles have been installed;

¡P          Dredging of Type 2 sediment from CH50 to CH250 for subsequent cross-harbour watermains installation off Tsim Sha Tsui;

¡P          Mainlaying works at Zone B1-5B, B1-6, B2-2, B4-2, B4-5, A1-5A, A3-2A, HKCEC Way In/Out, A2-3B and A5-5;

¡P          Mainlaying works at Zone B1-6, B2-2 and B1-5B;

¡P          Coring and Grouting works for external wall of cooling pumping stations Nos. P4 & P5 at Zone B4-5;

¡P          Coring works for external wall of cooling pumping station No P1 at Zone B4-2;

¡P          Mainlaying works at Zone A1-5A1 and A3-5B;

¡P          Heading No. H4, H5, H7 and H13;

¡P          Heading No. H3 was substantially completed.

¡P          GI duct laying works at ZoneA4-3A and Zone A4-3B;

¡P          Trench excavation, pipe laying works and chamber construction for a 1000 dia. watermains (CHF) at Salisbury Garden

                                                    

2.4.5.        For Contract no. HK/2009/02, the principal work activities in this reporting month included:

¡P          300mm thick topping slab together with the make up slab below at northern portion commenced on 30 Nov 2011;

¡P          Concreting at Roof Plinth, lift shaft up to +14.15mPD and Fire Service Pump room up to +14.15mPD of Passenger Terminal Building were completed;

¡P          E&M and ABWF of Passenger Terminal Building;

¡P          ELS of Noise Barrier 2 commenced on 29 Nov 2011 and nearly completed.

¡P          Casting of pedestrian pavement above seawall coping Bay 4 to Bay 8 was completed on 13 December 2011;

¡P          Casting of the bus shelter footing at Expo Drive East was completed;

¡P          Precast slab installation at the existing movable ramp was in progress;

¡P          Saw cutting of existing slabs for the construction NB1 footing was completed;

¡P          E&M of P7, P8 & P9

¡P          Approximate 50m cooling water pipe was laid at Harbour Centre, Harbour Road, Tonnochy Road and ex-pet garden;

¡P          Jacking pit at ex-pet garden for the heading construction of cooling mains across Convention Avenue commenced;

¡P          Approximate 50m cable duct was laid at Harbour Road and Tonnochy Road.

¡P          Construction of wash out chamber at Harbour Road and access manhole at Harbour Centre were completed;

¡P          Trench excavation and cooling mains installation along Tonnochy Road;

¡P          Installation of PVC and G.I cable ducts was ongoing at Harbour Road;

¡P          Installation of submarine outfall pipe was completed;

¡P          Dredging for submarine outfall pipe was ongoing;

¡P          Concreting the Base Slab of Wan Shing Street at Bay 24 was completed;

¡P          Concreting the wall shaft and roof slab completed of Wan Shing Street at Bay 21 and Bay 24 were completed;

¡P          Bay 21 to Bay 24 of Wan Shing Street were handover to HEC;

¡P          Slab at +3.10mPD and +3.77 mPD and wall below were completed for the WSD Salt Water Pumping Station;

¡P          Excavation and lateral support for DSD receiving pits were completed;

¡P          D610 pipe pile wall construction at landside cofferdam of salt water intake culvert;

¡P          12 out of 12 nos of pre-bored H-pile for box culverts N1 was casted as of 21 November 2011;

¡P          Temporary working platform was completed and pile cap construction was in progress at Portion 1B for the New Ferry Pier

2.4.6.        For Contract no. HY/2009/15, the principal work activities in this reporting month included:

¡P          Seawall block construction and reclamation work at TS4;

¡P          Night time protection works at CHT; and

¡P          Precautionary works at Abutment A

2.4.7.        For Contract no. HK/2010/06, the principal work activities in this reporting month included:

¡P          Installation of bored pile casing;

¡P          Excavation of bored piles; and

¡P          Concreting of bored piles

2.4.8.        In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

Contract no. HY/2009/11- North Point Reclamation

¡P          The portion of NPR3 are scheduled to be completed and handover in January 2012. No construction work related to DP3 is anticipated to be conduced in coming month.

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

¡P          Reclamation of HKCEC3W at the northern side within the HKCEC Water Channel would be continued;

¡P          Dredging from CH160 to CH260 for subsequent reclamation within HKCEC Water Channel would be resumed right after the consent from EPD for type 3 sediment has been received;

¡P          Rockfilling from CH160 to CH260 for subsequent reclamation within HKCEC Water Channel would be commenced;

¡P          Installation of sheet pile water channel at Dome Promenade (from CH120 to CH170) would be commenced;

¡P          Installation of sheet pile water channel at Dome Promenade (from CH170 to CH260) would be commenced;

¡P          Mainlaying works for 4 nos. of cooling water discharge pipes at WC landfall section (B1-3) would be completed. And subsequent reinstatement works was anticipated to be completed be completed;

¡P          Dredging of type 3 sediment from CH50 to CH250 for subsequent cross-harbour watermains installation off Tsim Sha Tsui would be continued right after the consent from EPD has been received;

¡P          Ground treatment works for the trenches excavation of the proposed cross-harbour watermains nos. A18/b18 would be continued and anticipated to be completed;

¡P          Installation of pipe pile wall at sea portion would be continued and anticipated to be completed;

¡P          Thrust block construction, concrete coating for flange joint and Rockfilling protection works would be continued;

¡P          Works would be continued at Zone A1-5A1, A2-3B, A3-3, A3-2A, A3-5B, A3-5B, A4-3A, A4-3B, HKCEC way in/out, A5-5, B4-2, B4-5, B1-6 and B2-2;

¡P          GI duct laying works at Zone A4-3A and A4-3 B would be completed;

¡P          Heading Nos. H4, H5, H7 and H13 would be continued;

¡P          Heading Nos. H4 and H13 would be completed;

¡P          Heading No. H8 would be commenced after its corresponding jacking pit at Zone A1-5A1 has been excavated;

¡P          After the completion of mainlaying works at Zone B4-2 and B4-5, mainlaying works at Zone B4-4 would be commenced;

¡P          After the completion of mainlaying works at HKCEC way in/out, mainlaying works at Zone B4-2A would be commenced;

¡P          After the completion of mainlaying works at A5-5, mainlaying works at Zone B5-2 would be commenced.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

¡P          Preparation works for temporary diversion intakes of WSD salt water pumping station and Sun Hung Kai pumping station.

¡P          Continue operation of Tseung Kwan O Public Fill Sorting Facility;

¡P          Continue E&M works and ABWF works of passenger terminal;

¡P          Complete 300mm thick slab construction at Northern Portion of Expo Drive East;

¡P          Complete excavation works for noise barrier 2 at Expo Drive East;

¡P          Continue slab modification for NB 1 footing at Expo Drive East;

¡P          Continue construction for bus shelter at Expo Drive East;

¡P          Continue trench excavation and pipe laying works along Harbour Road;

¡P          Continue trench excavation and deck over at Tonnochy Road;

¡P          Continue construction from +3.10mPD to + 5.17mPD for WSD Salt Water Pumping Station;

¡P          Complete pipeline jacking WSD intake A;

¡P          Continue construction of seaside cofferdams for salt water intake culvert, submarine outfall and Box Culvert N1;

¡P          Commence excavation works of landside cofferdam for the construction of Bay 6 ¡V 10 salt water intake culvert;

¡P          Continue backfilling rockfills for the installed submarine outfall pipes;

¡P          Continue installation of the temporary water diversion steel frame;

¡P          Commence the temporary internal propping works for Box Culvert O construction;

¡P          Continue substructure works for the New Ferry Pier

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

¡P          ELS works at TS1;

¡P          Pumping test and ELS preparation works at TPCWAE ;

¡P          Night time protection works at CHT; and

¡P          Precautionary works at Abutment A

 

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line

¡P          Installation of bored pile casing;

¡P          Excavation of bored piles; and

¡P          Bored Pile Concreting

 

3.         Status of Regulatory Compliance

3.1               Status of Environmental Licensing and Permitting under the Project

 

3.1.1.        A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1 Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009/A

4 Aug 2010

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

Superseded

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Valid

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

22 Nov 2010

Valid

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 Jul 2010

Valid

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Surrendered

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

Valid

 

3.1.2.        Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

3.1.3.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-01/356/2009 for contract no. HY/2009/11 are shown in Table 3.2 and Table 3.3.

3.1.4.        Contractor submitted a letter dated 20 July 2011 to confirm that the dredging works and dumping operation were completed.

Table 3.2 Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/11

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

N/A

Valid

Notification of Works Under APCO

331892

4 Jul. 2011

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0922-11

12 Oct 2011

1 Nov 2011 to 30 Apr 2012

Valid

Registration as a Chemical Waste Producer

WPN5213-151-C3631-02

12 Oct 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7010037

13 Jan 2010

N/A

Valid

Discharge Licence

WT00007942-2010

29 Nov 2010

30 Nov 2015

Valid

 

Table 3.3 Summary of submission status under FEP-01/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

18 Dec 2009

Condition 2.7

Submission of works schedule and location plan

8 Feb 2010

Condition 2.8

Revised Silt Curtain Deployment Plan (Rev. 3)

4 Dec 2010

Condition 2.9

Silt Screen Deployment Plan (Rev. 6)

18 May 2011

Condition 2.10

Coral Translocation Plan

20 Nov 2009

Condition 2.16

Revised Noise Management Plan (Rev 5)

19 Feb 2011

Condition 2.17

Landscape Plan

12 May 2010

 

Revised landscape Plan

30 Jun 2010

 

Submission of Supplementary Information - Revised Management & Maintenance Schedule for Submitted Revised Landscape Plan

25 Aug 2010

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

3.1.5.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and Table 3.5.

Table 3.4 Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

N/A

Valid

 

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088                       

6 Jan 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0680-11

22 Jul 2011

29 Jul 2011 to 19 Jan 2012

Valid

 

GW-RS0689-11

28 Jul 2011

29 Jul 2011 to 28 Jan 2012

Cancelled

 

GW-RS0832-11

7 Sep 2011

03 Sep 2011 to 02 Mar 2012

Valid

 

GW-RS0850-11

12 Sept 2011

14 Sept 2011 to 13 Mar 2012

Valid

 

GW-RS0851-11

12 Sept 2011

16 Sept 2011 to 15 Mar 2012

Valid

 

GW-RE0683-11

26 Sept 2011

20 Sept 2011 to 19 Mar 2012

Cancelled

 

GW-RE0716-11

28 Sept 2011

07 Oct 2011 to 29 Mar 2012

Valid

 

GW-RS1094-11