Contract No: HK/2011/07 Wanchai
Development Phase II and Sampling,
Field Measurement and Testing Works (Stage 2) Environmental Permit no.
EP-356/2009, Further
Evironmental permit nos. fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009
and Fep-05/356/2009 Monthly
Environmental Monitoring & Audit Report
- January 2012 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
13 February 2012 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of
Water Quality Monitoring Exceedances in Reporting Month
Table II Summary of
Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details of
Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/11
Table 3.3 Summary of
submission status under FEP-01/356/2009 Condition
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.5 Summary of
submission status under FEP-02/356/2009 Condition
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.7 Summary of
submission status under FEP-03/356/2009 Condition
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table 3.9 Summary of
submission status under FEP-04/356/2009 Condition
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2010/06
Table 3.11 Summary of submission status under
EP-356/2009 and FEP-05/356/2009 Condition
Table 4.1 Noise
Monitoring Station
Table 4.2 Real Time
Noise Monitoring Station
Table 4.3 Air
Monitoring Station
Table 4.4 Marine Water Quality Stations for Water
Quality Monitoring
Table 4.5 Marine Water
Quality Monitoring Frequency and Parameters
Table 4.6 Marine Water Quality Stations for
Enhanced Water Quality Monitoring
Table 4.7 Marine Water Quality Stations for
Additional DO Monitoring
Table 5.1 Noise Monitoring Stations for Contract
no. HY/2009/11
Table 5.2 Noise Monitoring Station for Contract
nos. HK/2009/01, HK/2009/02 and HK/2010/06
Table 5.3 Noise Monitoring Station for Contract
no. HY/2009/15
Table 5.4 Real Time
Noise Monitoring Station for Contract no. HY/2009/11
Table 5.5 Air Monitoring Stations for Contract no.
HY/2009/11
Table 5.6 Air Monitoring Stations for Contract no.
HK/2009/01
Table 5.7 Air Monitoring Station for Contract no.
HK/2009/02
Table 5.8 Air Monitoring Station for Contract no.
HY/2009/15
Table 5.9 Water Monitoring Stations for Contract
no. HY/2009/11
Table 5.10 Water Monitoring Stations for Contract
no. HK/2009/01
Table 5.11 Water Monitoring Stations for Contract
no. HK/2009/02
Table 5.12 Water Monitoring Stations for Contract
no. HK/2009/02
Table 5.13 Water Monitoring Stations for Contract
no. HY/2009/15
Table 5.14 Summary of Water Quality Monitoring
Exceedances in Reporting Month
Table 5.15 Summary of Enhanced Dissolved Oxygen
Monitoring Exceedances in Reporting Month
Table 5.16 Details of Waste Disposal for Contract
no. HY/2009/11
Table 5.17 Details of Waste Disposal for Contract
no. HK/2009/01
Table 5.18 Details of Waste Disposal for Contract
no. HK/2009/02
Table 5.19 Details of Waste Disposal for Contract
no. HY/2009/15
Table 5.20 Details of Waste Disposal for Contract
no. HK/2010/06
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/11
Table 8.2 Summary of Environmental Inspections for
Contract no. HK/2009/01
Table 8.3 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.4 Summary of Environmental Inspections for
Contract no. HY/2009/15
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2010/06
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended Mitigation
Measures in Coming Reporting Month
lIST OF
FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project
Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST OF
APPENDIces
Appendix 3.1 Environmental
Mitigation Implementation Schedule
Appendix 4.1 Action
and Limit Level
Appendix
4.2 Copies of
Calibration Certificates
Appendix
5.1 Monitoring
Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring Results and Graphical
Presentations
Appendix 5.3 Air
Quality Monitoring
Results and Graphical Presentations, and Odour Patrol Results
Appendix
5.4 Water
Quality Monitoring
Results and Graphical Presentations
Appendix 5.4a Additional
Dissolved Oxygen
Monitoring Results
Appendix
5.5 Real-time
Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event
Action Plans
Appendix 6.2 Summary
for Notification of Exceedance
Appendix
9.1 Complaint
Log
Appendix 10.1 Construction
Programme of Individual Contracts
Construction
Activities for the Reported Period
¡P
The major work activities for
Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January
2012. The construction site was handed over to contractor HY/2009/19 and the FEP-01/356/2009
was under application of surrender in this reporting
period.
¡P
Dredging works within HKCEC Water
Channel from CH190 to CH260 for Type 3 sediment was commended.
¡P
Removal of rock armours from
CH160 to CH260 at the north bank of HKCEC Water Channel was substantially
completed.
¡P
Installation of sheet pile for
cooling water intake at Dome Promenade between CH120 and CH170 was in progress.
¡P
Reclamation of HKCEC3W (up to
CH130) within HKCEC Water Channel has been substantially completed.
¡P
Installation of 4 nos. of
submersible cooling water discharge pipes at B1-3 was substantially completed.
¡P
Thrust block construction for
A9B9, A11B11, A12B12 and A13B13 were completed.
¡P
Concrete coating at flange at
joint of cross-harbour watermains nos. A10B10/A11B11, A11B11/A12B12 and
A12B12/A12B13 were completed.
¡P
Rockfilling and rock protection
to cross-harbour watermains was currently in progress.
¡P
Grouting works at TST seafront
along the pipe pile wall was commenced.
¡P
Installation of pipe pile at TST
(Sea Protection) was substantially completed.
¡P
Dredging of Type 3 sediment at
designated disposal site was carried out.
¡P
Mainlaying works at Zone B1-5B,
B1-6, B2-2, A3-2A, A3-5B and were in progress.
¡P
Cable ducting works at Zone B5-2
was commenced.
¡P
Mainlaying works and subsequent
reinstatement in Zone B4-5 was completed.
¡P
Mainlaying works and subsequent carriageway
reinstatement in Zone A1-5A1, A4-3A,
¡P
A4-3B and HKCEC Way In/Out had
been completed.
¡P
Mainlaying works and subsequent
carriageway reinstatement in Zone A2-3B and A2-4A was completed.
¡P
Coring and grouting works for
external wall of cooling pumping station No. P1 at Zone B4-2 was completed.
¡P
Pipe laying works at Zone B4-2
was completed and GI ducting works was in progress.
¡P
Jacking pit establishment for
pipe laying works by heading method at Zone A1-5A1 has been completed.
¡P
Mainlaying and chamber
construction works at the traffic island neat junction of
¡P
Trench excavation, pipe laying
works and chamber construction for a 1000 dis. Warermains (CHF) at
¡P
Trench excavation and pipe laying
works for a 1000 dia. Watermains (CHE) at
¡P
¡P
Concreting of structural slab at
existing movable ramp was completed on 18 January 2012.
¡P
ABWFs and E&M works of
¡P
Installation of glass wall
bearing at G/F and 1/F commenced on 22 December 2012 and completed on 5 January
2012.
¡P
ELS of Noise Barrier NB2 was
completed on 15 January 2012.
¡P
Blinding of Noise Barrier NB2
footing was completed on 29 December 2012.
¡P
Steel fixing of Noise Barrier NB2
was in progress.
¡P
Pedestrian diversion above
seawall coping Bay 4 to Bay 8 was implemented on 6 January 2011.
¡P
Bladder Tank steel fixing and
formwork erection are in progress.
¡P
E&M of P7, P8 & P9 were
in progress.
¡P
Sheet piling works of the Jacking
pit at ex-pet garden commenced on 19 December 2011for the heading construction
of cooling mains across
¡P
Approximate
¡P
Approximate
¡P
Trench excavation and cooling
mains installation along
¡P
Installation of PVC and G.I cable
ducts was ongoing at
¡P
+5.17 mPD and wall below were
completed on 12 Jan 2012 for the WSD Salt Water Pumping Station.
¡P
D610 pipe pile wall construction
at landside cofferdam of salt water intake culvert was in progress.
¡P
Setting-up of pile load test at
WSD Seaside Cofferdam was completed on 17 January 2012.
¡P
Formwork removal for remaining
pile caps at Portion 1B for the New Ferry Pier was commenced on 20 January
2012.
¡P
Tower Crane operation commenced
on 16 January 2012 for the Ferry Pier construction.
¡P
Steel Mould installation at
Portion
¡P
Backfilling on the HDPE pipelines
of Portion 2 between CH0 to CH150 was in progress.
¡P
Steel deck support for cooling
main was completed on 30 December 2011 and cooling mains installation was
ongoing across WCR1.
¡P
Construction of Temporary Decking
Platform A for Vehicle Access of the New Wan Chai Ferry Pier was completed on
30 December 2011.
¡P
Quad shore & steel beam
support installation commenced on 19 Jan
¡P
Preparation works for WCR2 diversion
¡P
Seawall block construction and reclamation work at TS4;
¡P
Night time protection works at CHT; and
¡P
Precautionary works at Abutment A
¡P
Installation of bored pile casing
¡P
Excavation of bored piles
¡P
Concreting of bored piles
¡P
Coring works
Noise Monitoring
Real-time Noise
Monitoring
Air Quality
Monitoring
CMA1b: from 4 January 2012 to 5 January 2012
CMA3a: from 16 January 2012 to 17 January 2012
Water Quality
Monitoring
Table I Summary
of Water Quality Monitoring Exceedances in Reporting Month
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
||
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD20 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C5w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
0 |
1 |
0 |
2 |
0 |
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
Table
II Summary of Enhanced Dissolved
Oxygen Monitoring Exceedances in Reporting Month
Contract
no. |
Water
Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
C7 |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SE |
0 |
0 |
0 |
0 |
|
Total |
0 |
0 |
0 |
0 |
Complaints,
Notifications of Summons and Successful Prosecutions
Site Inspections
and Audit
Contract no. HY/2009/11- North Point Reclamation
¡P
The major work activities for
Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January
2012. The construction site was handed over to contractor HY/2009/19 and the FEP-01/356/2009
was under application of surrender in this reporting period.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
¡P
Dredging from CH160 to Ch260 for
subsequent reclamation within HKCEC Water Channel would be resumed upon
completion of dredging of Type 3 sediment at TST.
¡P
Installation of sheet pile water
channel at Dome Promenade (from CH120 to CH170) works be completed.
¡P
Reclamation works and
installation of sheet pile water channel (from CH170 to CH260) would be
commenced upon completion of dredging from CH160 to CH260 within HKCEC water
Channel.
¡P
Seawall reinstatement at WC
landfill section (B1-3) would be commenced and was anticipated to be completed.
¡P
Dredging of Type 3 sediment from CH50
to CH250 for subsequent cross-harbour watermains installation off TST would be
continued and anticipated to be completed.
¡P
Dredging works underneath the
Avenue of Stars by telescopic excavator would be continued and anticipated to
be completed.
¡P
Grout treatment works along the
pipe pile wall at TST seafront would be continued and anticipated to be
completed. Subsequent trench excavator for the proposed cross-harbour
watermains installation nos. A18/B18 would be commenced accordingly.
¡P
Installation of pipe pile for splitting
concrete seawall at TST seashore would be continued and anticipated to be
completed.
¡P
Works would be continued at Zone
A1-5A1 (Jacking Pit), A3-3, A3-2A, A3-5A, A3-5B, A5-5, B4-2, B1-3, B1-6, B1-5B,
B2-2 and B5-2.
¡P
Mainlaying works at Zone B4-2
would be completed.
¡P
Trench excavation at Zone B4-4
would be commenced.
¡P
Mainlaying works at Zone B2-2
would be completed and mainlaying works at Zone B2-1 would be commenced
accordingly.
¡P
Mainlaying works at traffic
island near junction between
¡P
Heading nos. H5, H7 and h13
(Mainlaying works by trenchless method) would be continued.
¡P
Heading No. H5 and H13 would be
completed.
¡P
Heading No. H8 world be
commenced.
Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at WanChai East
¡P
Operation of Tseung Kwan O Public
Fill Sorting Facility.
¡P
E&M works and ABWF works of
passenger terminal.
¡P
T&C work of passenger
terminal.
¡P
300mm thick slab construction at
passenger terminal area, existing movable Ramp Area, Noise Barrier NB2 at
¡P
Slab modification for NB 1
footing at
¡P
steel platforms installation at
+1.35mPD and -0.85mPD for P7, P8 & P9 Pumping Station
¡P
Trench excavation and pipe laying
works along
¡P
Trench excavation and deck over
at
¡P
Construction from + 5.17mPD to +
10.53mPD or WSD Salt Water Pumping Station.
¡P
Construction of seaside
cofferdams for salt water intake culvert, submarine outfall and Box Culvert N1.
¡P
Pile load test of WSD Seaside
Cofferdam.
¡P
Excavation works of landside
cofferdam for the construction of Bay 6 ¡V 10 salt water intake culverts.
¡P
Backfilling rockfills for the
installed submarine outfall pipes.
¡P
Installation of the temporary
water diversion steel frame at WCR2 area.
¡P
Temporary internal propping works
for Box Culvert O construction and pre-bored H-piles construction.
¡P
Substructure works for the New
Ferry Pier.
¡P
Formwork removal for remaining
pile caps at Portion 1B for the New Ferry Pier;
¡P
Preparation works for WCR2 diversion
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
¡P
Night time protection works at
CHT
Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass over MTR Tsuen Wan Line
¡P
Installation of bored pile casing
¡P
Excavation of bored piles
¡P
Concreting of bored piles
¡P
Coring works
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009
and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009,
FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring
and auditing work carried out in accordance to the Section 10.3 of EM&A
Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under
Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
for Environmental Permit no. EP-356/2009, Further Environmental Permit no.
FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and
FEP-05/356/2009 and during the period 28th December 2011 to 27th
January 2012. The cut-off date of reporting is at 27th of each
reporting month.
Section 1 Introduction ¡V details the
scope and structure of the report.
Section 2 Project
Background ¡V summarizes background and scope of the project, site
description, project organization and contact details of key personnel during
the reporting period.
Section 3 Status of Regulatory Compliance ¡V summarizes the
status of valid Environmental Permits / Licenses during the reporting period.
Section 4 Monitoring
Requirements ¡V summarizes all monitoring parameters, monitoring
methodology and equipment, monitoring locations, monitoring frequency, criteria
and respective event and action plan and monitoring programmes.
Section 5 Monitoring
Results ¡V summarizes the monitoring results obtained in the
reporting period.
Section 6 Compliance
Audit ¡V summarizes the auditing of
monitoring results, all exceedances environmental parameters.
Section 7 Cumulative Construction Impact due to the Concurrent
Projects ¡V summarizes the relevant cumulative
construction impact due to the concurrent activities of the concurrent Projects.
Section 8 Site Inspection ¡V summarizes the
findings of weekly site inspections undertaken within the reporting period,
with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai
Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨
(hereafter called ¡§the Project¡¨) are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental
Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB
to provide relief to the very congested
2.2.1.
The Project is located mainly in Wan Chai North,
2.2.2.
The study area encompasses existing developments
along the Wan Chai,
2.2.3.
The scope of the Project
comprises:
¡P
Land formation for key transport
infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for connection to the Trunk
Road and for through traffic from Central
to Wan Chai and Causeway Bay. The land formed for the above transport infrastructure will provide opportunities for the
development of an attractive waterfront promenade for the enjoyment of the
public
¡P
Reprovisioning / protection of
the existing facilities and structures affected by the land formation works
mentioned above
¡P
Extension, modification,
reprovisioning or protection of existing storm water drainage outfalls,
sewerage outfalls and watermains affected by the revised land use and land
formation works mentioned above
¡P
Upgrading of hinterland storm
water drainage system and sewerage system, which would be rendered insufficient
by the land formation works mentioned above
¡P
Provision of the ground level
roads, flyovers, footbridges, necessary transport facilities and the associated
utility services
¡P
Construction of the new
waterfront promenade, landscape works and the associated utility services
¡P
The Trunk Road (i.e. CWB)
within the study area and the associated slip roads for connection to the Trunk
Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1
summarises the five individual DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads |
Schedule
2, Part I, A.1 and A.7 |
Trunk
road and road tunnel more than 800 m in length |
DP2 |
Road P2
and other roads which are classified as primary/district distributor roads |
Schedule
2, Part I, A.1 |
Primary
/ district distributor roads |
DP3 |
Reclamation
works including associated dredging works |
Schedule
2, Part I, C.1 and C.12 |
Reclamation
more than 5 ha in size and a dredging operation less than 100 m from a
seawater intake point |
DP5 |
Wan Chai
East Sewage Outfall |
Schedule
2, Part I, F.5 and F.6 |
Submarine
sewage pipelines with a total diameter more than 1,200 mm and include a
submarine sewage outfall |
DP6 |
Dredging
for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui |
Schedule
2, Part I, C.12 |
A
dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. Contractors of individual contracts will
be required by the EP holder to apply Further Environmental Permits (FEP) such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized
in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract No. |
Contract
Title |
Associated DP(s) |
Construction Commencement Date |
HK/2009/01 |
Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass at |
DP3, DP6 |
23 July
2010 |
DP1, DP2 |
25
August 2011 |
||
HK/2009/02 |
Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East |
DP3, DP5 |
5 July
2010 |
DP1 |
26 April
2011 |
||
HY/2009/11 |
Wan Chai
Development Phase II and Central ¡V Wan Chai Bypass ¡V North Point Reclamation |
DP3 |
17 March
2010 (Under application of surrender) |
HY/2009/15 |
Central-Wanchai
Bypass ¡V Tunnel ( |
DP3 |
10
November 2010 |
DP1 |
13 July
2011 |
||
HK/2010/06 |
Wan Chai
Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line |
DP3 |
22 March
2011 |
04/HY/2006 |
Reconstruction
of Bus Terminus near |
DP1 |
September 2010 |
HY/2009/17 |
Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central
- Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central
- Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor
Link |
DP1 |
24 March
2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the
construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer
for WDII |
Principal
Resident Engineer |
Mr.
Frankie Fan |
2587
1778 |
2587 1877 |
Engineer
for CWB |
Principal
Resident Engineer |
Mr.
Peter Poon |
3916
1818 |
3529 2829 |
|
|
Contractor
under Contract no. HY/2009/11 |
Project
Director |
Mr. Cho
Yu Fun |
3157
1086 |
3157 1085 |
Project Manager |
Mr.
Gregory Wong |
3157
1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157
1086 |
|||
Environmental Officer |
Mr. C.
M. Wong |
3157
1086 |
|||
Chun Wo
¡V Leader Joint Venture |
Contractor
under Contract no. HK/2009/01 |
Project
Director |
|
9124
2471 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Operation Manager |
Mr. Lau
Yee Ching |
9466
3918 |
|||
Construction Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction Manager |
Mr. Jack Chu |
9775 3008 |
|||
Construction Manager |
Mr. KK Yuen Mr. Andy Yu |
9498 1213 96484896 |
|||
Environmental Officer (Compliance
Manager) |
Mr. Andy Mak |
9103
2370 |
|||
Chun Wo
¡V CRGL Joint Venture |
Contractor
under Contract no. HK/2009/02 |
Project
Manager |
Mr. Chan
Sing Cho |
3658
3002 |
2827 9996 |
Site
Agent |
Mr. Mak
Kam Wing |
3658 3044 |
|||
Quality
& Environmental Manager |
Mr. C.P.
Ho |
3658
3000 |
|||
Environmental
Officer |
Ms.
Flora Ng |
3658 3064 |
|||
|
Contractor
under Contract no. HY/2009/15 |
Project
Manager |
Mr. M Y
Wong |
2823
7879 |
2528
5651 |
Site
Manager |
Mr. P J
Fan |
3557
6368 |
2566
2192 |
||
|
|
Construction
Manager |
Mr. C K
Kwok |
9779
2162 |
|
|
|
Construction
Manager (East) |
Gene
Cheung |
6105
4880 |
|
|
|
Construction
Manager (West) |
Tony
Chiu |
9090
0606 |
|
|
|
Environmental
Officer |
Mr. Daniel
Sin |
3557
6215 |
|
Gammon -Leader
JV |
Contractor
under Contract no. HK/2010/06 |
Project Manager |
Mr. Paul
Lui |
9095
7922 |
2529 2880 |
Site Agent |
Mr. Keith
Tse |
2529 2068 |
|||
Environmental Officer |
Mr. Lee Wai Man |
9481
6024 |
|||
ENVIRON
Hong Kong Limited |
Independent Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr.
David Yeung |
3743
0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 and
the FEP-01/356/2009 was under application of surrender in this reporting
period.
2.4.4.
For Contract no. HK/2009/01, the principal work
activities in this reporting month included:
¡P
Dredging works within HKCEC Water
Channel from CH190 to CH260 for Type 3 sediment was commended.
¡P
Removal of rock armours from
CH160 to CH260 at the north bank of HKCEC Water Channel was substantially
completed.
¡P
Installation of sheet pile for
cooling water intake at Dome Promenade between CH120 and CH170 was in progress.
¡P
Reclamation of HKCEC3W (up to
CH130) within HKCEC Water Channel has been substantially completed.
¡P
Installation of 4 nos. of
submersible cooling water discharge pipes at B1-3 was substantially completed.
¡P
Thrust block construction for
A9B9, A11B11, A12B12 and A13B13 were completed.
¡P
Concrete coating at flange at
joint of cross-harbour watermains nos. A10B10/A11B11, A11B11/A12B12 and
A12B12/A12B13 were completed.
¡P
Rockfilling and rock protection
to cross-harbour watermains was currently in progress.
¡P
Grouting works at TST seafront
along the pipe pile wall was commenced.
¡P
Installation of pipe pile at TST
(Sea Protection) was substantially completed.
¡P
Dredging of Type 3 sediment at
designated disposal site was carried out.
¡P
Mainlaying works at Zone B1-5B,
B1-6, B2-2, A3-2A, A3-5B and were in progress.
¡P
Cable ducting works at Zone B5-2
was commenced.
¡P
Mainlaying works and subsequent
reinstatement in Zone B4-5 was completed.
¡P
Mainlaying works and subsequent carriageway
reinstatement in Zone A1-5A1, A4-3A,
¡P
A4-3B and HKCEC Way In/Out had
been completed.
¡P
Mainlaying works and subsequent
carriageway reinstatement in Zone A2-3B and A2-4A was completed.
¡P
Coring and grouting works for
external wall of cooling pumping station No. P1 at Zone B4-2 was completed.
¡P
Pipe laying works at Zone B4-2
was completed and GI ducting works was in progress.
¡P
Jacking pit establishment for
pipe laying works by heading method at Zone A1-5A1 has been completed.
¡P
Mainlaying and chamber
construction works at the traffic island neat junction of
¡P
Trench excavation, pipe laying
works and chamber construction for a 1000 dis. Warermains (CHF) at
¡P
Trench excavation and pipe laying
works for a 1000 dia. Watermains (CHE) at
2.4.5.
For Contract no. HK/2009/02, the principal work
activities in this reporting month included:
¡P
¡P
Concreting of structural slab at existing movable ramp was completed on
18 January 2012.
¡P
ABWFs and E&M works of
¡P
Installation of glass wall bearing at G/F and 1/F commenced on 22
December 2012 and completed on 5 January 2012.
¡P
ELS of Noise Barrier NB2 was completed on 15 January 2012.
¡P
Blinding of Noise Barrier NB2 footing was completed on 29 December 2012.
¡P
Steel fixing of Noise Barrier NB2 was in progress.
¡P
Pedestrian diversion above seawall coping Bay 4 to Bay 8 was implemented
on 6 January 2011.
¡P
Bladder Tank steel fixing and formwork erection are in progress.
¡P
E&M of P7, P8 & P9 were in progress.
¡P
Sheet piling works of the Jacking pit at ex-pet garden commenced on 19 December
2011for the heading construction of cooling mains across
¡P
Approximate
¡P
Approximate
¡P
Trench excavation and cooling mains installation along
¡P
Installation of PVC and G.I cable ducts was ongoing at
¡P
+5.17 mPD and wall below were completed on 12 January 2012 for the WSD
Salt Water Pumping Station.
¡P
D610 pipe pile wall construction at landside cofferdam of salt water
intake culvert was in progress.
¡P
Setting-up of pile load test at WSD Seaside Cofferdam was completed on
17 January 2012.
¡P
Formwork removal for remaining pile caps at Portion 1B for the New Ferry
Pier was commenced on 20 January 2012.
¡P
Tower Crane operation commenced on 16 January 2012 for the Ferry Pier construction.
¡P
Steel Mould installation at Portion
¡P
Backfilling on the HDPE pipelines of Portion 2 between CH0 to CH150 was
in progress.
¡P
Steel deck support for cooling main was completed on 30 December 2011
and cooling mains installation was ongoing across WCR1.
¡P
Construction of Temporary Decking Platform A for Vehicle Access of the
New Wan Chai Ferry Pier was completed on 30 December 2011.
¡P
Quad shore & steel beam support installation commenced on 19 January
¡P
Preparation works for WCR2 diversion
2.4.6.
For Contract no. HY/2009/15, the principal work
activities in this reporting month included:
¡P
Seawall block construction and reclamation work at TS4;
¡P
Night time protection works at CHT; and
¡P
Precautionary works at Abutment A
2.4.7.
For Contract no. HK/2010/06, the principal work
activities in this reporting month included:
¡P
Installation of bored pile casing
¡P
Excavation of bored piles
¡P
Concreting of bored piles
¡P
Coring works
2.4.8.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. HY/2009/11- North Point Reclamation
¡P
The major work activities for
Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January
2012. The construction site was handed over to
contractor HY/2009/19 and the FEP-01/356/2009 was under application of surrender in this reporting
period.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
¡P
Installation of bored pile casing
¡P
Excavation of bored piles
¡P
Concreting of bored piles
¡P
Coring works
Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at WanChai East
¡P
Operation of Tseung Kwan O Public
Fill Sorting Facility.
¡P
E&M works and ABWF works of
passenger terminal.
¡P
T&C work of passenger
terminal.
¡P
300mm thick slab construction at
passenger terminal area, existing movable Ramp Area, Noise Barrier NB2 at
¡P
Slab modification for NB 1
footing at
¡P
steel platforms installation at
+1.35mPD and -0.85mPD for P7, P8 & P9 Pumping Station
¡P
Trench excavation and pipe laying
works along
¡P
Trench excavation and deck over
at
¡P
Construction from + 5.17mPD to +
10.53mPD or WSD Salt Water Pumping Station.
¡P
Construction of seaside
cofferdams for salt water intake culvert, submarine outfall and Box Culvert N1.
¡P
Pile load test of WSD Seaside
Cofferdam.
¡P
Excavation works of landside
cofferdam for the construction of Bay 6 ¡V 10 salt water intake culverts.
¡P
Backfilling rockfills for the
installed submarine outfall pipes.
¡P
Installation of the temporary
water diversion steel frame at WCR2 area.
¡P
Temporary internal propping works
for Box Culvert O construction and pre-bored H-piles construction.
¡P
Substructure works for the New
Ferry Pier.
¡P
Formwork removal for remaining
pile caps at Portion 1B for the New Ferry Pier.
¡P
Preparation works for WCR2 diversion
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
¡P
Night time protection works at
CHT
Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass over MTR Tsuen Wan Line
¡P
Installation of bored pile casing
¡P
Excavation of bored piles
¡P
Concreting of bored piles
¡P
Coring works
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-376/2009 |
13 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Under application of surrender |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further Environmental Permit |
FEP-01/364/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Valid |
Further Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Surrendered |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HY/2009/11 ¡V
Central ¡V Wanchai Bypass, North Point Reclamation
3.1.3.
The major work activities for Contract no.
HY/2009/11 was completed, confirmed by RSS and handover to Contractor
HY/2009/19 on 4 January 2012 FEP-01/356/2009 was under application of surrender
in this reporting period.
3.1.4.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-01/356/2009 for contract no. HY/2009/11 are shown in Table 3.2 and
Table 3.3.
3.1.5.
Contractor submitted a letter dated 20 July 2011 to
confirm that the dredging works and dumping operation were completed.
Table 3.2 Cumulative
Summary of Valid Licences and Permits
under Contract no. HY/2009/11
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
N/A |
Under application of surrender |
Notification of Works Under APCO |
331892 |
4 Jul. 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0922-11 |
12 Oct 2011 |
1 Nov 2011 to 30 Apr 2012 |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-151-C3631-02 |
12 Oct 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7010037 |
13 Jan
2010 |
N/A |
Valid |
Discharge Licence |
WT00007942-2010 |
29 Nov
2010 |
30 Nov
2015 |
Valid |
Table
3.3 Summary of submission status under
FEP-01/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
18 Dec 2009 |
Condition 2.7 |
Submission of works schedule and location
plan |
8
Feb 2010 |
Condition 2.8 |
Revised Silt Curtain Deployment Plan (Rev.
3) |
4 Dec 2010 |
Condition 2.9 |
Silt Screen Deployment Plan (Rev. 6) |
18 May 2011 |
Condition 2.10 |
Coral Translocation Plan |
20 Nov 2009 |
Condition 2.16 |
Revised Noise Management Plan (Rev 5) |
19 Feb 2011 |
Condition 2.17 |
Landscape Plan |
12 May 2010 |
|
Revised landscape Plan |
30 Jun 2010 |
|
Submission of Supplementary Information -
Revised Management & Maintenance Schedule for Submitted Revised Landscape
Plan |
25 Aug 2010 |
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
3.1.6.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and
Table 3.5.
Table
3.4 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
N/A |
Valid |
|
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan
2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0680-11 |
22 Jul
2011 |
29 Jul
2011 to 19 Jan 2012 |
Expired |
|
GW-RS0832-11 |
7 Sep
2011 |
03 Sep
2011 to 02 Mar 2012 |
Cancelled |
|
GW-RS0850-11 |
12 Sept
2011 |
14 Sept
2011 to 13 Mar 2012 |
Valid |
|
GW-RS0851-11 |
12 Sept
2011 |
16 Sept
2011 to 15 Mar 2012 |
Valid |
|
GW-RE0716-11 |
28 Sept
2011 |
07 Oct
2011 to 29 Mar 2012 |
Valid |
|
GW-RS1094-11 |
23 Nov
2011 |
27 Nov
2011 to 26 May 2012 |
Valid |
|
GW-RS1031-11 |
3 Nov
2011 |
7 Nov
2011 to 6 May 2012 |
Valid |
|
GW-RS1221-11 |
30 Jan
2011 |
20 Jan
2012 to 19 Jul 2012 |
Valid |
|
GW-RS1227-11 |
30 Dec
2011 |
30 Dec
2011 to 26 Jul 2012 |
Valid |
|
|