Contract No: HK/2011/07

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Works (Stage 2)

 

Environmental Permit no. EP-356/2009,

Further Evironmental permit nos. fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 and Fep-05/356/2009

 

Monthly Environmental Monitoring & Audit Report

 

- august 2012 -


CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

11 September 2012


Table of contents

 

EXECUTIVE SUMMARY. 4

1.     Introduction. 12

1.1        Scope of the Report 13

1.2        Structure of the Report 13

2.     Project Background. 15

2.1        Background. 15

2.2        Scope of the Project and Site Description. 15

2.3        Division of the Project Responsibility. 16

2.4        Project Organization and Contact Personnel 17

3.     Status of Regulatory Compliance. 25

3.1        Status of Environmental Licensing and Permitting under the Project 25

4.     Monitoring Requirements. 37

4.1        Noise Monitoring. 37

4.2        Air Monitoring. 38

4.3        Water Quality Monitoring. 41

5.     Monitoring Results. 46

5.1        Noise Monitoring Results. 46

5.2        Real-time Noise Monitoring. 48

5.3        Air Monitoring Results. 48

5.4        Water Monitoring Results. 50

5.5        Waste Monitoring Results. 56

6.     Compliance Audit. 60

6.1        Noise Monitoring. 60

6.2        Real-time noise Monitoring. 60

6.3        Air Monitoring. 60

6.4        Water Quality Monitoring. 61

6.5        Review of the Reasons for and the Implications of Non-compliance. 62

6.6        Summary of action taken in the event of and follow-up on non-compliance. 62

7.     Cumulative Construction Impact due to the Concurrent Projects. 64

8.     Environmental Site Audit. 65

9.     Complaints, Notification of Summons and Prosecution. 66

10.    Conclusion. 72


lIST OF TABLES

 

Table I         Summary of Water Quality Monitoring Exceedances in Reporting Month

Table II        Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Table 2.1     Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 3.1      Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.2      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/11

Table 3.3      Summary of submission status under FEP-01/356/2009 Condition

Table 3.4      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.5      Summary of submission status under FEP-02/356/2009 Condition

Table 3.6      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.7      Summary of submission status under FEP-03/356/2009 Condition

Table 3.8      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.9      Summary of submission status under FEP-04/356/2009 Condition

Table 3.10    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2010/06

Table 3.11    Summary of submission status under EP-356/2009 and FEP-05/356/2009 Condition

Table 3.12    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Table 4.1      Noise Monitoring Station

Table 4.2      Real Time Noise Monitoring Station

Table 4.3      Air Monitoring Station

Table 4.4     Marine Water Quality Stations for Water Quality Monitoring

Table 4.5      Marine Water Quality Monitoring Frequency and Parameters

Table 4.6     Marine Water Quality Stations for Enhanced Water Quality Monitoring

Table 4.7     Marine Water Quality Stations for Additional DO Monitoring

Table 5.1     Noise Monitoring Stations for Contract no. HY/2009/11

Table 5.2     Noise Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06

Table 5.3     Noise Monitoring Station for Contract no. HY/2009/15

Table 5.4     Noise Monitoring Station for Contract no. HY/2009/19

Table 5.5      Real Time Noise Monitoring Station for Contract no. HY/2009/11 and HY/2009/19

Table 5.6     Air Monitoring Stations for Contract no. HY/2009/11

Table 5.7     Air Monitoring Stations for Contract no. HK/2009/01

Table 5.8     Air Monitoring Station for Contract no. HK/2009/02

Table 5.9     Air Monitoring Station for Contract no. HY/2009/15

Table 5.10    Air Monitoring Stations for Contract no. HY/2009/19

Table 5.11    Water Monitoring Stations for Contract no. HY/2009/11

Table 5.12    Water Monitoring Stations for Contract no. HK/2009/01

Table 5.13    Water Monitoring Stations for Contract no. HK/2009/02

Table 5.14    Water Monitoring Stations for Contract no. HK/2010/06

Table 5.15    Water Monitoring Stations for Contract no. HY/2009/15

Table 5.16    Water Monitoring Stations for Contract no. HY/2009/19

Table 5.17    Summary of Water Quality Monitoring Exceedances in Reporting Month

Table 5.18    Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Table 5.19    Details of Waste Disposal for Contract no. HK/2009/01

Table 5.20    Details of Waste Disposal for Contract no. HK/2009/02

Table 5.21    Details of Waste Disposal for Contract no. HY/2009/15

Table 5.22    Details of Waste Disposal for Contract no. HK/2010/06

Table 5.23    Details of Waste Disposal for Contract no. HY/2009/19

 

Table 8.1     Summary of Environmental Inspections for Contract no. HK/2009/01

Table 8.2     Summary of Environmental Inspections for Contract no. HK/2009/02

Table 8.3     Summary of Environmental Inspections for Contract no. HY/2009/15

Table 8.4     Summary of Environmental Inspections for Contract no. HK/2010/06

Table 8.5      Summary of Environmental Inspections for Contract no. HY/2009/19

Table 9.1      Cumulative Statistics on Complaints

Table 9.2      Cumulative Statistics on Successful Prosecutions

Table 10.1    Construction Activities and Recommended Mitigation Measures in Coming Reporting Month

 

 

lIST OF FIGUREs

 

Figure 2.1       Project Layout

Figure 2.2       Project Organization Chart

Figure 2.3    Locations of Environmental Monitoring Stations

 

 

 

lIST OF APPENDIces

 

Appendix 3.1  Environmental Mitigation Implementation Schedule

Appendix 4.1  Action and Limit Level

Appendix 4.2  Copies of Calibration Certificates

Appendix 5.1  Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2  Noise Monitoring Results and Graphical Presentations

Appendix 5.3  Air Quality Monitoring Results and Graphical Presentations, and Odour Patrol Results

Appendix 5.4  Water Quality Monitoring Results and Graphical Presentations

Appendix 5.4a  Additional Dissolved Oxygen Monitoring Results

Appendix 5.5  Real-time Noise Monitoring Results and Graphical Presentations

Appendix 6.1  Event Action Plans

Appendix 6.2  Summary for Notification of Exceedance

Appendix 7.1  Complaint Log

Appendix 8.1  Construction Programme of Individual Contracts


 

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report ¡V August 2012 for the Project of Wan Chai Development Phase II and Central-Wanchai Bypass under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009. This report presents the environmental monitoring findings and information recorded during the period July 2012 to August 2012. The cut-off date of reporting is at 27th of each reporting month.

 

Construction Activities for the Reported Period

  1. Contract no. HY/2009/11- North Point Reclamation

¡P          The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19.

 

  1. During this reporting period, the major work activities for Contract no. HK/2009/01 included:

 

Marine Works (at Wan Chai)

¡P          Rockfilling for rock bund across HKCEC Water Channel from Ch220 to Ch230

¡P          Reclamation of HKCEC3W within HKCEC Water Channel

¡P          Installation of pipe pile wall for demolition of existing seawall at Expo Drive East

¡P           Demolition of Wan Chai West Ferry Pier

 

Cross-Harbour Watermains Installation (CHA & CHB) and Marine Works (at TST)

¡P          Rockfilling and rock protection to cross-harbour watermains

¡P          Installation of cross-harbour watermains No. A18 & B18

 

Fresh Watermains, Cooling Watermains and Salt Watermains (On Land)

¡P          Mainlaying works at Zone B1-5A, B2-1, B3-1, B4-3, B4-1A, B5-1(Switch Room), B5-3(Switch Room), A1-1, A1-2, A1-3B, A2-2, A3-2A, A3-4B, A3-5B and A4-2A

¡P          The reinstatement of one carriageway at Zone B2-1 Mainlaying Works at Zone B3-1 of Expo Drive Central

¡P          Breakup of concrete surround and trimming of 1 no. existing intake and 2 no. existing discharge pipe at Zone A1-1 and A1-2

¡P          Pipe laying works at Heading No. H7

¡P          Heading No. H6c (Mainlaying works by trenchless method)

¡P          Mainlaying and chamber construction works at the traffic island near junction of Convention Avenue and Fenwick Pier Street

¡P          Mainlaying works at Zone A3-2A of Fenwick Pier Street

¡P          Mainlaying works at Expo Drive East in Zone C1-10

¡P          Mainlaying Works for a 1000 dia. Watermains (CHE) at Salisbury Garden

¡P          Reinstatement Works at Salisbury Garden

¡P          Pipe Laying works including 9 nos. cooling mains across E/D section within HKCEC Water Channel

¡P          Pipe Laying works including 9 nos. cooling mains across SCL section within HKCEC Water Channel

¡P          Pipe Laying works including 9 nos. cooling mains and 2no. cross harbour watermains at North Bank of HKCEC Water Channel

 

  1. During this reporting period, the major work activities for Contract no. HK/2009/02 included:

¡P      Modification work of PTI and bus station at Expo Drive East

¡P      Self-testing of the individual pumping systems for cooling mains work

¡P      Wet well was handed over to E & M for penstock leakage testing

¡P      Reinstatement at Tonnochy Road - Harbour Road junction

¡P      Cooling mains installation at west of Gate 1 inside ex-pet garden and the steel fixing  and casting of the damaged thrust box

¡P      Cabling works along Harbour Road and Great Eagle Centre / Harbour Centre area

¡P      Waterproofing membrane at roof level at WSD Salt Water Pumping Station.

¡P      E&M works at WSD Salt Water Pumping Station

¡P      Wall shaft and roof slab casting of salt water intake culvert at Wan Shing Street Bay 20 and steel fixing of 19B

¡P      Removing the strut & waling for road reinstatement near Bay 24 and backfilling of salt water intake culvert at Wan Shing Street

¡P      Sheetpiling at Bay 11 and the grouting work

¡P      Pile cap steel fixing of Bay 6 in salt water intake landside cofferdam

¡P      Concreting the salt water intake culvert of Bay 4 and Bay 7 at WCR1 and concreting the base slab of Bay 8

¡P      Concreting pile cap of IC1 and the construction of pile cap IC2 in salt water intake seaside cofferdam.

¡P      Excavation and breaking up the rock down to 3rd layer of strut and waling installation of the outfall launching shaft and then the 2nd layer waling

¡P      Cutting the opening of sheetpiles and coring of thrust wall between Launching Pit and Jacking Pit

¡P      Excavation the fill material to expose HDPE pipe end by divers inside the outfall seaside cofferdam

¡P      Cutting casing of pre-bored H-pile to cut-off level for pile cap at Bay 4 and Bay 5 of Box Culvert N1 northern cofferdam

¡P      Excavation to formation level and making good of blinding layer for pile cap at Bay 4 and Bay 5 of Box Culvert N1 northern cofferdam

¡P      Concreting the base slab of Box Culvert N1 Bay 2 and Bay 3 on UU bridge

¡P      Dismantling of steel panel & H-beam of water tank at zone 2B and the dismantling work of water tank in zone 3B and 3C at Ferry Pier.

¡P      Concreting the columns at New Ferry Pier GL 6-7 / B-F level 1 to level 2 and erection formwork and falsework at GL 8-15 / B-F

¡P      Steel fixing the slab at New Ferry Pier GL 1-8 level 1 and GL 9 -15 level 2

¡P      Rockfilling and placing bagged concrete for the seawall block area at WCR2

¡P      Reclamation of WCR2

¡P      TDMP for Box Culvert ¡§O¡¨ Diversion at Bay 12-13

¡P      Bulkhead wall at Box Culvert ¡§O¡¨ Bay 17

¡P      Water pressure test and sterilization test for 150MS freshwater pipe at Box Culvert ¡§O¡¨ prior to the diversion of captioned water pipe.

¡P      Trial pit excavation and preparation works for Hung Hing Road Diversion

 

  1. During this reporting period, the major work activities for Contract no. HY/2009/15 included:

¡P      Removal of temporary reclamation at TS1

¡P      Underwater cutting of temporary diaphragm walls at TS1

¡P      Dredging for seawall foundation at TS2

¡P      Seawall trench works at TS2

 

  1. During this reporting period, the major work activities for Contract no. HK/2010/06 included:

¡P      Pile head breaking

¡P      Sonic tube trimming

 

  1. During this reporting period, the major work activities for Contract no. HY/2009/19 included:

¡P          Marine bored piling

¡P          Construction works for Box Culvert T

 

Noise Monitoring

  1. Noise monitoring during daytime and restricted hour were conducted at the stations M1a, M2b, M3a, M4b, M5b and M6 on a weekly basis in the reporting month.
  2. Due to the equipment repair, the noise monitoring at M4b and M6 were rescheduled from 23 August 2012 to 24 August 2012
  3. One limit level exceedance was recorded at M6 on 24 August 2012. The limit level exceedance was considered as non-project related.

Real-time Noise Monitoring

  1. Real-time noise monitoring at FEHD Hong Kong Transport Section Whitefield Depot and Oil Street Community Centre have been commenced on 5 October 2010 for the filling works of Contract no. HY/2009/11.
  2. Real-time noise monitoring at FEHD Hong Kong Transport Section Whitefield Depot commenced external wall renovation since 1 June 2012
  3. Exceedances were recorded at RTN2- Oil Street Community Liaison Centre, between 0700 and 1900 hours throughout the reporting month.  Investigations found that no major noisy activities by the Contractor HY/2009/19 were being performed. The major noise impact was arising from the demolition works near Oil Street Community Liaison Center. As such, the exceedances were concluded as not project related.

 

Air Quality Monitoring

  1. Due to extension of site boundary by contractor of HY/2009/19, location of air monitoring station CMA1b ¡V Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.
  2. Due to lack of electricity supply, the 24-hr TSP monitoring at the following stations were rescheduled:

CMA1b: from 27 Jul and 20 August 2012 to 31 Jul and 21 August 2012

CMA2a: from 27 Jul and 8 August 2012 to 28 Jul and 10 August 2012

CMA5a: from 20 August 2012 to 21 August 2012

CMA6a: from 8 August 2012 to 9 August 2012

 

  1. Due to adverse weather condition, the 1-hr TSP monitoring at the following stations were rescheduled:

CMA2a: from 9 August 2012 to 11 August 2012

 

  1. Air quality monitoring has been conducted at stations CMA1b, CMA2a, CMA3a, CMA4a, CMA5a and CMA6a. No exceedance was recorded in the reporting month.
  2. The odour patrol along the odour route with 7 sniffing locations was conducted by a qualified odour patrol member on 13 and 23 August 2012 at the concerned hours (afternoon for higher daily temperature). No exceedance was recorded in this reporting period.

Water Quality Monitoring

  1. Due to the adverse weather condition (e.g. Amber Rainstorm signal or Strong wind signal No.3 or above) were hoisted on 11 and 17 August 2012, water quality monitoring at ebb tide were cancelled.
  2. WDII/RSS advised that the dredging works for submarine pipeline at Victoria Harbour had been completed in January 2012. Therefore, the concurrent dredging activities at Sewage Pipeline Zone and reclamation shoreline zone TCBR under the EP-356/2009 scenario 2B no longer exist. As such, with reference to Table 5.39 of the EIA Report for Wan Chai Development Phase II and Central-Wan Chai Bypass, the application of silt screen for cooling water intakes for Queensway Government Offices was suspended and the others were remains unchanged.
  3. Based on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no water deterioration with respect to NPR was commenced since 7 Jan 2012 and was completed on 6 Feb 2012 water quality monitoring.
  4. Water quality monitoring at WSD10 and WSD15 will be temporary suspended while water quality monitoring at WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8 Feb 12 onwards;
  5. Water quality monitoring at C8 and C9 have been implemented with respect to HY/2009/19 since the marine bore piling work started on 28 Jan 12.
  6. Based on the safety concern when external façade refurbishment was conducted by contractor employed by Provident Centre (C9) between 9 January 2012 to 30 July 2012 which caused to the inaccessibility of sampling either land and marine since 3 Feb 2012, there is a fine adjustment of the sampling location of water quality monitoring at C9 since 10 March 2012 to the closest accessible point prior to the completion of the external façade refurbishment work.
  7. Due to the access of water monitoring station at WSD19 was blocked by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the inaccessibility of sampling either land and marine, there is a fine adjustment of the sampling point of WSD 19 since 5 April 2012 to the closest accessible point prior to the completion of the construction activities.
  8. Due to the dredging works for Cross Harbour Water Mains from Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April 2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for 4-week period after the completion of DP6 to confirm no water deterioration.
  9. During the weekly site inspection for HY/2009/15 on 10 July 2012 and further inspection on 11 July 2012, it was found that the seawall blocks on the south side of TCBR1E (TS1) have been removed before all dredging works have been completed.  The contractor has immediately surrounded the seawall gap with silt curtains and stopped the relevant dredging works on 12 July 2012.  No action or limit level exceedance was found during the water quality monitoring on 9 or 11 July 2012.  The contractor has promised to provide double layer silt curtains and geotextile to act as temporary seawall and covered the sloping seawall with geotextile, and would provide a full incident report.  A self water quality monitoring was conducted on 15 July 2012 to indicate the effectiveness of the double silt curtain layers and would perform each time during dredging operations.  The results from the self water quality monitoring showed that the suspended solids, turbidity and dissolved oxygen level outside the double silt curtain layers were not affected by the dredging activities inside the silt curtain layers.
  10. Water quality monitoring at 14 monitoring stations was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table I.

Table I    Summary of Water Quality Monitoring Exceedances in Reporting Month

 

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HY/2009/11

WSD9

0

0

0

0

0

0

0

0

0

0

0

0

Monitoring finished on

6 Feb 2012

WSD10

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD15

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD17

0

0

0

0

0

0

0

0

0

0

0

0

 

C8

0

0

0

0

0

0

0

0

0

0

0

0

 

C9

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/01

WSD19

0

0

0

0

1

0

0

0

0

0

0

0

 

C1

0

0

0

0

0

0

0

0

0

0

0

0

 

C3

0

0

0

0

1

0

0

0

0

0

0

0

 

C4e

0

0

0

0

0

0

0

0

0

0

0

0

 

C4w

1

0

0

0

0

0

0

0

0

0

0

0

Monitoring finished on 27 April 2012

WSD20

0

0

0

0

0

0

0

0

0

0

0

0

WSD7

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/01

& HK/2010/06

C2

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/02

C5e

0

0

0

0

0

0

0

0

0

0

0

0

 

C5w

0

0

0

0

0

0

0

0

0

1

0

1

Monitoring started on

8 Feb 2012

WSD21

0

0

0

0

2

0

1

0

0

0

0

0

WSD9

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD17

0

0

0

0

0

0

0

0

0

0

0

0

HY/2009/15

C7

1

0

0

0

0

0

0

0

0

0

0

0

HY/2009/19

Monitoring started on 28 Jan 2012

C8

0

0

0

0

0

0

0

0

0

1

1

1

C9

0

0

0

0

0

0

0

0

0

0

0

0

Total

2

0

0

0

4

0

1

0

0

2

2

2

 

Remarks: -     The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

         -   WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.

-   4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.

-   C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.

-   WSD7 and WSD20 water quality monitoring were temporarily suspended from 27 Apr 2012.

 

  1. Investigations were found that the exceedances were not related to the Project works. The details of the recorded exceedances can be referred to the Section 6.4.

 

  1. Enhanced DO monitoring at 4 monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table II.

      

Table II   Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

DO

AL

LL

AL

LL

HY/2009/15

C6

0

0

0

0

C7

2

0

0

0

Ex-WPCWA SW

0

0

0

4

Ex-WPCWA SE

5

0

4

3

Total

7

0

4

7

 

  1. There were 11 action level exceedances and 7 limit level exceedances of enhanced dissolved oxygen recorded in this reporting month. Investigation found that the exceedances are not related to the Project works. The details of the recorded exceedances can be referred to the Section 6.4.
  2. In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be installed to channel water discharge flow from Culvert L to locations outside the embayment area, a proposed replacement of the requirement with additional dissolved oxygen monitoring has been conducted at three monitoring stations, namely A, B and C between the eastern seawall of Central Reclamation Phase III and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level between the eastern seawall of Central Reclamation Phase II and the HKCEC extension could be continuously monitored.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. There was one complaint received in this reporting month.

 

Site Inspections and Audit

  1. The Environmental Team (ET) conducted weekly site inspections for Contract nos. HK/2009/01, HK/2009/02, HY/2009/15 HK/2010/06 and HY/2009/19 under EP no. EP-356/2009 in the reporting month. Major observations and recommendations made during the audit sessions were rectified by the Contractors. No non-conformance was identified during the site inspections.
  2. During the monitoring stations inspection for HK/2009/02 in July 2012, turbid appearance was occasionally observed the well for WSD intake pumping station as a result of the silty water seepage during reclamation work at WCR2. The contractor was reminded that the water quality inside the well should be ensured with adequate freshwater circulation and sufficient inspection to avoid any gaps and leakage into well.

 

Future Key Issues

  1. In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HY/2009/11- North Point Reclamation

¡P          The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011.

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

Marine Works

¡P          Reclamation works within HKCEC Water Channel (from CH170 to CH220)

¡P          Rockfilling for formation of rock bund within HKCEC Water Channel (from CH220 to CH230)

¡P          Installation pipe pile wall for modification of vertical seawall near Expo Drive East

¡P          Rockfilling at northeast of Area 9 and Area7 near Expo Drive East Bridge

¡P          Demolition of Wan Chai West Ferry Pier

¡P          Cross-Harbour Watermains Installation (CHA & CHB) Trust block construction, concrete coating for flange joint and rockfilling protection works for cross-harbour watermains in Victoria Harbour

¡P          Reinstatement works at TST seashore including removal of silt screen and dismantling of jack-up barge

 

Fresh Watermains, Cooling Watermains and Salt Watermains (On Land)

¡P          Zone B1-5A, B2-1, B4-1A, B4-3, B5-1, B5- 3, A1-1, A1-2, A1-3B, A2-2, A3-2A, A3-4B, A3-5B, A4-2A

¡P          Mainlaying works and G.I. ducting works at Zone B1-5A, B4-1A and B4-3

¡P          Mainlaying works at Zone B3-1

¡P          Mainlaying works across the run-out of Renaissance Harbour View Hotel by open-cut method

¡P          Mainlaying works at Convention Avenue in Zone A1-1, A1-2 and Zone A2-2 and the next TTA workfront for cross harbour watermains at Zone A1-2 CHWM)

¡P          Mainlaying works at traffic island near junction between Convention Avenue and Fenwick Pier Street

¡P          Pipe laying works at Zone A3-2A would be completed and heading no. H1

¡P          Mainlaying works at Zone A3-5B of Fenwick Pier Street and A3-4B

¡P          No. H6C excavation works.

¡P          Pipe laying works for cross harbour watermains within HKCEC water channel

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

¡P          Complete PTI modification works after completion of New Public Toilet in East Island at Expo Drive East.

¡P          Complete the initial testing of P7, P8 and P9 pumping station.

¡P          Complete all cooling mains and cabling works for P7, P8 & P9 Pumping Stations permanent power-on and signal control.

¡P          800MS pipe installation inside Ex-pet Garden.

¡P          ABWFs & E&M works of WSD Salt Water Pumping Station.

¡P          Conduct Fire Service Inspection of  WSD Salt Water Pumping Station

¡P          Complete the finishing works of WSD Salt Water Pumping Station.

¡P          Complete WSD intake A and Intake B in-situ concrete work.

¡P          Construction of Bay 1b ¡V 2, Bay 6 ¡V 8 salt water intake culverts at WCR1 area.

¡P          Continue construction salt water intake culverts Bay 9 ¡V 11 to formation level at WCR1 area.

¡P          Commence salt water intake culvert at transition bays inside jacking pit and receiving pit.

¡P          Continue remaining drainage works and reinstatement works along Wan Shing Street.

¡P          Commence HDPE piping on UU Bridge and inside launching pit.

¡P          Construction for Box Culvert N1 at WCR1 area.

¡P          Complete concreting works for the Level 2 at the New Ferry Pier.

¡P          Reclamation works at WCR2 area.

¡P          Commence drainage work to suit TWCR4 construction.

¡P          Diversion of uncharted drainage works at Box culvert ¡§O¡¨.

¡P          Continue trial excavation and preparation works for Hung Hing Road Diversion

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

¡P          TZ1 reclamation works

¡P          Seawall trench works at TS2

¡P          Formation of temporary seawall at TS2

¡P          Dredging at TS2

 

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line

¡P          Pile head breaking

¡P          Sonic tube trimming

 

Contract no. HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

¡P          Construction works for Box Culvert T

¡P          Marine Piling

1.         Introduction

1.1               Scope of the Report

1.1.1.        Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.        This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under Particular Specification Section 27.

1.1.3.        This report documents the finding of EM&A works for Environmental Permit no. EP-356/2009, Further Environmental Permit no. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 and during the period of July to August. The cut-off date of reporting is at 27th of each reporting month.

 

1.2               Structure of the Report

 

Section 1        Introduction ¡V details the scope and structure of the report.

 

Section 2        Project Background ¡V summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3        Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4        Monitoring Requirements ¡V summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5        Monitoring Results ¡V summarizes the monitoring results obtained in the reporting period.

 

Section 6        Compliance Audit ¡V summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7        Cumulative Construction Impact due to the Concurrent Projects ¡V summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8        Site Inspection ¡V summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9        Complaints, Notification of summons and Prosecution ¡V summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10       Conclusion

2.         Project Background

2.1               Background

2.1.1.        ¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called ¡§the Project¡¨) are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.        The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.        There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2               Scope of the Project and Site Description

2.2.1.        The Project is located mainly in Wan Chai North, Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road Interchange to the east, as shown in Figure 2.1.

2.2.2.        The study area encompasses existing developments along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police Officers¡¦ Club, the Causeway Bay Typhoon Shelter (CBTS) and commercial and residential developments.

2.2.3.        The scope of the Project comprises:

¡P          Land formation for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for connection to the Trunk Road and for through traffic from Central to Wan Chai and Causeway Bay. The land formed for the above transport infrastructure will provide opportunities for the development of an attractive waterfront promenade for the enjoyment of the public

¡P          Reprovisioning / protection of the existing facilities and structures affected by the land formation works mentioned above

¡P          Extension, modification, reprovisioning or protection of existing storm water drainage outfalls, sewerage outfalls and watermains affected by the revised land use and land formation works mentioned above

¡P          Upgrading of hinterland storm water drainage system and sewerage system, which would be rendered insufficient by the land formation works mentioned above

¡P          Provision of the ground level roads, flyovers, footbridges, necessary transport facilities and the associated utility services

¡P          Construction of the new waterfront promenade, landscape works and the associated utility services

¡P          The Trunk Road (i.e. CWB) within the study area and the associated slip roads for connection to the Trunk Road.

 

2.2.4.        The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1      Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3               Division of the Project Responsibility

2.3.1.        Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced. Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits (FEP) such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.        The details of individual contracts are summarized in Table 2.2.

 

 

 

Table 2.2 Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HK/2009/01

Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at Hong Kong Convention and Exhibition Centre

DP3, DP6

23 July 2010

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

DP3, DP5

5 July 2010

DP1

26 April 2011

HY/2009/11

Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North Point Reclamation

DP3

17 March 2010 (Under application

of surrender)

HY/2009/15

Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

DP3

10 November 2010

DP1

13 July 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

HY/2009/17

Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works.

DP1

5 October 2010

HY/2009/18

Central - Wan Chai Bypass (CWB) ¡V Central Interchange

DP1

21 April 2011

HY/2009/19

Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

 

2.4               Project Organization and Contact Personnel

2.4.1.        Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.        The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3 Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer¡¦s Representative for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer¡¦s Representative for CWB

Principal Resident Engineer

Mr. Peter Poon

3922 8332

3529 2829

China Harbour- CRBC Joint Venture

Contractor under Contract no. HY/2009/11

Project Director

Mr. Cho Yu Fun

3157 1086

3157 1085

Project Manager

Mr. Gregory Wong

3157 1086

Site Agent

Mr. Daniel Cheung

3157 1086

Environmental Officer

Mr. C. M. Wong

3157 1086

Chun Wo ¡V Leader Joint Venture

Contractor under Contract no. HK/2009/01

Project Director

Mr. PL Yue

2162 9909

2587 1878

Site Agent

Mr. Paul Yu

9456 9819

Sub-Agent

Mr Terry Wong

9757 9846

Construction Manager

Mr. Wyman Wong

9627 2467

Construction Manager

Mr. Jack Chu

9775 3008

Construction Manager

Mr. KK Yuen

 

9498 1213

 

Environmental Officer (Compliance Manager)

Mr. Andy Mak

9103 2370

Chun Wo ¡V CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Site Agent

Mr. Chan Sing Cho

3658 3002

2827 9996

Quality & Environmental Manager

(Environmental Officer)

Mr. C.P. Ho

3658 3000

 

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Chan Wai Hung

2823 7813

2865 5229

Site Manager

P J Fan

3557 6368

2566 2192

 

 

Contractor¡¦s Representative

Mr. David Lau

3557 6358

 

 

Head of Construction

Manager

Roger Cheung

3557 6371

 

 

Senior Construction Manager

Gene Cheung

3557 6395

 

 

Environmental Officer

Mr. Daniel Sin

3557 6347

Gammon

-Leader JV

Contractor under Contract no. HK/2010/06

Project Manager

Mr. Paul Lui

9095 7922

2529 2880

Site Agent

Mr. Keith Tse

2529 2068

Environmental Officer

Mr. Lee Wai Man

9481 6024

Chun Wo - CRGL - MBEC Joint Venture

 

Contractor under Contract no. HY/2009/19

 

Project Manager

    Mr. Rayland Lee

3758 8879

2570 8013

 

Site Agent

Mr. Cheung Kit Cheung

6909 1555

Environmental Engineer

Mr. Calvin Leung

9286 9208

Environmental Manager /

Environmental Officer

Mr. M.H. Isa

9884 0810

Construction Manager

(Land)

Patrick Cheung

9643 3012

Construction Manager

(Land)

Eric Fong

6191 9337

Operation Manager (Land)

Yung Kwok Wah

9834 1010

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3743 0788

3548 6988

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

 

2.4.3.        For Contract no. HY/2009/11, the principal work activities in this reporting month included:

¡P          The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011.

 

2.4.4.        For Contract no. HK/2009/01, the principal work activities in this reporting month included:

Marine Works (at Wan Chai)

 

¡P          Rockfilling for rock bund across HKCEC Water Channel from Ch220 to Ch230

¡P          Reclamation of HKCEC3W within HKCEC Water Channel

¡P          Installation of pipe pile wall for demolition of existing seawall at Expo Drive East

¡P          Demolition of Wan Chai West Ferry Pier

Cross-Harbour Watermains Installation (CHA & CHB) and Marine Works (at TST)

¡P          Rockfilling and rock protection to cross-harbour watermains

¡P          Installation of cross-harbour watermains No. A18 & B18

Fresh Watermains, Cooling Watermains and Salt Watermains (On Land)

¡P          Mainlaying works at Zone B1-5A, B2-1, B3-1, B4-3, B4-1A, B5-1(Switch Room), B5-3(Switch Room), A1-1, A1-2, A1-3B, A2-2, A3-2A, A3-4B, A3-5B and A4-2A

¡P          The reinstatement of one carriageway at Zone B2-1 Mainlaying Works at Zone B3-1 of Expo Drive Central

¡P          Breakup of concrete surround and trimming of 1 no. existing intake and 2 no. existing discharge pipe at Zone A1-1 and A1-2

¡P          Pipe laying works at Heading No. H7

¡P          Heading No. H6c (Mainlaying works by trenchless method)

¡P          Mainlaying and chamber construction works at the traffic island near junction of Convention Avenue and Fenwick Pier Street

¡P          Mainlaying works at Zone A3-2A of Fenwick Pier Street

¡P          Mainlaying works at Expo Drive East in Zone C1-10

¡P          Mainlaying Works for a 1000 dia. Watermains (CHE) at Salisbury Garden

¡P          Reinstatement Works at Salisbury Garden

¡P          Pipe Laying works including 9 nos. cooling mains across E/D section within HKCEC Water Channel

¡P          Pipe Laying works including 9 nos. cooling mains across SCL section within HKCEC Water Channel

¡P          Pipe Laying works including 9 nos. cooling mains and 2no. cross harbour watermains at North Bank of HKCEC Water Channel

 

2.4.5.        For Contract no. HK/2009/02, the principal work activities in this reporting month included:

¡P          Modification work of PTI and bus station at Expo Drive East

¡P          Self-testing of the individual pumping systems for cooling mains work

¡P          Wet well was handed over to E & M for penstock leakage testing

¡P          Reinstatement at Tonnochy Road - Harbour Road junction

¡P          Cooling mains installation at west of Gate 1 inside ex-pet garden and the steel fixing  and casting of the damaged thrust box

¡P          Cabling works along Harbour Road and Great Eagle Centre / Harbour Centre area

¡P          Waterproofing membrane at roof level at WSD Salt Water Pumping Station.

¡P          E&M works at WSD Salt Water Pumping Station

¡P          Wall shaft and roof slab casting of salt water intake culvert at Wan Shing Street Bay 20 and steel fixing of 19B

¡P          Removing the strut & waling for road reinstatement near Bay 24 and backfilling of salt water intake culvert at Wan Shing Street

¡P          Sheetpiling at Bay 11 and the grouting work

¡P          Pile cap steel fixing of Bay 6 in salt water intake landside cofferdam

¡P          Concreting the salt water intake culvert of Bay 4 and Bay 7 at WCR1 and concreting the base slab of Bay 8

¡P          Concreting pile cap of IC1 and the construction of pile cap IC2 in salt water intake seaside cofferdam.

¡P          Excavation and breaking up the rock down to 3rd layer of strut and waling installation of the outfall launching shaft and then the 2nd layer waling

¡P          Cutting the opening of sheetpiles and coring of thrust wall between Launching Pit and Jacking Pit

¡P          Excavation the fill material to expose HDPE pipe end by divers inside the outfall seaside cofferdam

¡P          Cutting casing of pre-bored H-pile to cut-off level for pile cap at Bay 4 and Bay 5 of Box Culvert N1 northern cofferdam

¡P          Excavation to formation level and making good of blinding layer for pile cap at Bay 4 and Bay 5 of Box Culvert N1 northern cofferdam

¡P          Concreting the base slab of Box Culvert N1 Bay 2 and Bay 3 on UU bridge

¡P          Dismantling of steel panel & H-beam of water tank at zone 2B and the dismantling work of water tank in zone 3B and 3C at Ferry Pier.

¡P          Concreting the columns at New Ferry Pier GL 6-7 / B-F level 1 to level 2 and erection formwork and falsework at GL 8-15 / B-F

¡P          Steel fixing the slab at New Ferry Pier GL 1-8 level 1 and GL 9 -15 level 2

¡P          Rockfilling and placing bagged concrete for the seawall block area at WCR2

¡P          Reclamation of WCR2

¡P          TDMP for Box Culvert ¡§O¡¨ Diversion at Bay 12-13

¡P          Bulkhead wall at Box Culvert ¡§O¡¨ Bay 17

¡P          Water pressure test and sterilization test for 150MS freshwater pipe at Box Culvert ¡§O¡¨ prior to the diversion of captioned water pipe.

¡P          Trial pit excavation and preparation works for Hung Hing Road Diversion

2.4.6.        For Contract no. HY/2009/15, the principal work activities in this reporting month included:

¡P          Removal of temporary reclamation at TS1

¡P          Underwater cutting of temporary diaphragm walls at TS1

¡P          Dredging for seawall foundation at TS2

¡P          Seawall trench works at TS2

2.4.7.        For Contract no. HK/2010/06, the principal work activities in this reporting month included:

¡P          Pile head breaking

¡P          Sonic tube trimming

2.4.8.        For Contract no. HY/2009/19, the principal work activity in this reporting month included:

¡P          Construction works for Box Culvert T

¡P          Marine Piling

2.4.9.        In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

Contract no. HY/2009/11- North Point Reclamation

¡P          The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011.

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

Marine Works

¡P          Reclamation works within HKCEC Water Channel (from CH170 to CH220)

¡P          Rockfilling for formation of rock bund within HKCEC Water Channel (from CH220 to CH230)

¡P          Installation pipe pile wall for modification of vertical seawall near Expo Drive East

¡P          Rockfilling at northeast of Area 9 and Area7 near Expo Drive East Bridge

¡P          Demolition of Wan Chai West Ferry Pier

¡P          Cross-Harbour Watermains Installation (CHA & CHB) Trust block construction, concrete coating for flange joint and rockfilling protection works for cross-harbour watermains in Victoria Harbour

¡P          Reinstatement works at TST seashore including removal of silt screen and dismantling of jack-up barge

 

Fresh Watermains, Cooling Watermains and Salt Watermains (On Land)

 

¡P          Zone B1-5A, B2-1, B4-1A, B4-3, B5-1, B5- 3, A1-1, A1-2, A1-3B, A2-2, A3-2A, A3-4B, A3-5B, A4-2A

¡P          Mainlaying works and G.I. ducting works at Zone B1-5A, B4-1A and B4-3

¡P          Mainlaying works at Zone B3-1

¡P          Mainlaying works across the run-out of Renaissance Harbour View Hotel by open-cut method

¡P          Mainlaying works at Convention Avenue in Zone A1-1, A1-2 and Zone A2-2 and the next TTA workfront for cross harbour watermains at Zone A1-2 CHWM)

¡P          Mainlaying works at traffic island near junction between Convention Avenue and Fenwick Pier Street

¡P          Pipe laying works at Zone A3-2A would be completed and heading no. H1

¡P          Mainlaying works at Zone A3-5B of Fenwick Pier Street and A3-4B

¡P          No. H6C excavation works.

¡P          Pipe laying works for cross harbour watermains within HKCEC water channel

 

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

 

¡P          Complete PTI modification works after completion of New Public Toilet in East Island at Expo Drive East.

¡P          Complete the initial testing of P7, P8 and P9 pumping station.

¡P          Complete all cooling mains and cabling works for P7, P8 & P9 Pumping Stations permanent power-on and signal control.

¡P          800MS pipe installation inside Ex-pet Garden.

¡P          ABWFs & E&M works of WSD Salt Water Pumping Station.

¡P          Conduct Fire Service Inspection of  WSD Salt Water Pumping Station

¡P          Complete the finishing works of WSD Salt Water Pumping Station.

¡P          Complete WSD intake A and Intake B in-situ concrete work.

¡P          Construction of Bay 1b ¡V 2, Bay 6 ¡V 8 salt water intake culverts at WCR1 area.

¡P          Continue construction salt water intake culverts Bay 9 ¡V 11 to formation level at WCR1 area.

¡P          Commence salt water intake culvert at transition bays inside jacking pit and receiving pit.

¡P          Continue remaining drainage works and reinstatement works along Wan Shing Street.

¡P          Commence HDPE piping on UU Bridge and inside launching pit.

¡P          Construction for Box Culvert N1 at WCR1 area.

¡P          Complete concreting works for the Level 2 at the New Ferry Pier.

¡P          Reclamation works at WCR2 area.

¡P          Commence drainage work to suit TWCR4 construction.

¡P          Diversion of uncharted drainage works at Box culvert ¡§O¡¨.

¡P          Continue trial excavation and preparation works for Hung Hing Road Diversion

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

¡P          TZ1 reclamation works

¡P          Seawall trench works at TS2

¡P          Formation of temporary seawall at TS2

¡P          Dredging at TS2

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line

¡P          Pile head breaking

¡P          Sonic tube trimming

 

Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

¡P          Construction works for Box Culvert T

¡P          Marine Piling

 

 

3.         Status of Regulatory Compliance

3.1               Status of Environmental Licensing and Permitting under the Project

 

3.1.1.        A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1 Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009/A

4 Aug 2010

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

Superseded

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Under application of surrender

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

22 Nov 2010

Valid

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 Jul 2010

Valid

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Surrendered

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

Valid

Further Environmental Permit

FEP-08/364/2009/A

15 Jun 2012

Valid

 

3.1.2.        Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

3.1.3.        The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011.

3.1.4.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-01/356/2009 for contract no. HY/2009/11 are shown in Table 3.2 and Table 3.3.

3.1.5.        Contractor submitted a letter dated 20 July 2011 to confirm that the dredging works and dumping operation were completed.

Table 3.2 Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/11

Permits and/or Licences