Contract
No: HK/2011/07 Wanchai Development Phase
II and Sampling, Field Measurement and
Testing Works
(Stage 2) Environmental Permit no. EP-356/2009, Further Evironmental permit nos.
fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 and Fep-05/356/2009 Monthly Environmental Monitoring & Audit Report
- November 2012 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
13 December 2012 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of Water Quality Monitoring Exceedances in
Reporting Month
Table II Summary of Enhanced Dissolved Oxygen Monitoring
Exceedances in Reporting Month
Table 2.1 Schedule 2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.4 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/01
Table 3.5 Summary of submission status under FEP-02/356/2009
Condition
Table 3.6 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/02
Table 3.7 Summary of submission status under FEP-03/356/2009
Condition
Table 3.8 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/15
Table 3.9 Summary of submission status under FEP-04/356/2009
Condition
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2010/06
Table 3.11 Summary of submission status under EP-356/2009 and
FEP-05/356/2009 Condition
Table 3.12 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Table 4.1 Noise Monitoring Station
Table 4.2 Real Time Noise Monitoring Station
Table 4.3 Air Monitoring Station
Table 4.4 Marine Water Quality Stations for Water Quality
Monitoring
Table 4.5 Marine Water Quality Monitoring Frequency and
Parameters
Table 4.6 Marine Water Quality Stations for Enhanced Water Quality
Monitoring
Table 4.7 Marine Water Quality Stations for Additional DO
Monitoring
Table 5.2 Noise Monitoring Station for Contract nos. HK/2009/01,
HK/2009/02 and HK/2010/06
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/15
Table 5.4 Noise Monitoring Station for Contract no. HY/2009/19
Table 5.5 Real Time Noise Monitoring Station for Contract no.
HY/2009/19
Table 5.8 Air Monitoring Station for Contract no. HK/2009/02
Table 5.9 Air Monitoring Station for Contract no. HY/2009/15
Table 5.10 Air
Monitoring Stations for Contract no. HY/2009/19
Table 5.12 Water
Monitoring Stations for Contract no. HK/2009/01
Table 5.13 Water
Monitoring Stations for Contract no. HK/2009/02
Table 5.14 Water
Monitoring Stations for Contract no. HK/2010/06
Table 5.15 Water
Monitoring Stations for Contract no. HY/2009/15
Table 5.16 Water
Monitoring Stations for Contract no. HY/2009/19
Table 5.17 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Table 5.18 Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 5.19 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.20 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.21 Details of Waste Disposal for Contract no. HY/2009/15
Table 5.22 Details of Waste Disposal for Contract no. HK/2010/06
Table 5.23 Details of Waste Disposal for Contract no. HY/2009/19
Table 8.1 Summary of Environmental Inspections for Contract no.
HK/2009/01
Table 8.2 Summary of Environmental Inspections for Contract no.
HK/2009/02
Table 8.3 Summary of Environmental Inspections for Contract no.
HY/2009/15
Table 8.4 Summary of Environmental Inspections for Contract no.
HK/2010/06
Table 8.5 Summary of Environmental Inspections for Contract no.
HY/2009/19
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended Mitigation
Measures in Coming Reporting Month
lIST
OF FIGUREs
Figure 2.2 Project Organization Chart
Figure 2.3 Locations of Environmental Monitoring Stations
lIST
OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix 5.4 Water Quality Monitoring Results and Graphical Presentations
Appendix 5.4a Additional Dissolved Oxygen Monitoring Results
Appendix 5.5 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Summary for Notification of Exceedance
Appendix 8.1 Construction Programme of Individual Contracts
Construction Activities for the Reported Period
Marine Works (at Wan Chai)
¡P
Rockfilling for HKCEC3E (East of HKCEC) between CH290 and CH385
¡P
Grouting works to pipe pile at
¡P
Removal of existing seawall and rock armour at
¡P
Dredging underneath
¡P
Fabrication of 3 nos. of precast concrete caisson seawall, 1 no. precast
concrete box culvert (namely Bay 10) and 2 nos. precast discharge outfall in
precasting yard at
Cross-Harbour Watermains Installation (CHA & CHB) and Marine Works
(at TST)
¡P
Rockfilling and rock protection to cross-harbour watermains
¡P
Thrust block construction for A18B18
¡P
Connection work between land pipeline and marine pipeline
¡P
Reinstatement works for the TST landfall
Fresh Watermains, Cooling Watermains and Salt Watermains (On Land)
¡P
Mainlaying works at Zone B1-5A, B2-1, B3-1, A1-1, A1-2, A1-4, A1-2A
& A1-3A, A2-3D, A3-2A, A3-4B, A3-3C, C1-6 and run-out of Renaissance Hotel
¡P
Mainlaying works at TTA Zone A2-3D and A1-4
¡P
Pipe laying works at heading No. H1 and Zone A3-4B
¡P
Mainlaying works at Zone A3-3C
¡P
Mainlaying and chamber construction works at the traffic island near
junction of
¡P
Mainlaying works at
¡P
Final cleaning, CCTV inspection and pressure test for the 9 nos. cooling
watermains
E&M
¡P
Electrical works in cooling water pumping stations P5
¡P
Major cabling works from existing LV Switch-board Room to Cooling Water
Pumping Station P5
¡P
Power energization to L.V. switchboard for cooling water pumping
stations P5
¡P
Full commissioning for Cooling Water Pumping Stations P1
¡P
Repairing of door hinges in the New Public Toilet..
¡P
Modification work of PTI at
¡P
Modification work of bus station at
¡P
Pre-inspection for P9 (SHK) Pumping Station.Reinstatement at
¡P
Cooling mains installation at west of Gate 1 inside ex-pet garden
¡P
Cooling main remedial works for the bending pipes
¡P
Installation of optic fiber and power cable
¡P
E&M works and ABWFs installation at WSD Salt Water Pumping Station
¡P
Concreting of boundary wall of EVA at WSD Pumping Station
¡P
Concreting of Inspection Manhole and Access Chamber of Salt Water Intake
Culvert at Bay 19B & 20
¡P
Concreting of the wall and top slab at salt water intake culvert Bay
¡P
Concreting of the blinding layer at salt water intake culvert Bay 9 -
Bay 11 at WCR1
¡P
Concreting of the wall and top slab at salt water intake culvert Bay 9
at WCR1 and steel fixing of base slab at Bay 10
¡P
Cutting the sheetpile wall at salt water intake culvert Bay 11 to
jacking pit
¡P
Concreting of wall and top slab of Bay
¡P
TZ1 and TS2 reclamation works
¡P
Formation of temporary seawall at TS2
¡P
Pile head breaking
¡P
Platform Disassembly
¡P
Bored Pile cutting
¡P
Marine bored piling
¡P
Construction works for Box Culvert T
¡P
Construction of 1500f drainage pipe
Real-time Noise
Monitoring
Air Quality Monitoring
CMA2a: from 8 and 14 November 2012 to 9 and 15 November 2012
CMA5a: from 8 November 2012 to 9 November 2012
Water Quality Monitoring
3 Nov 2012
Mid-Ebb tide
5 Nov 2012
Mid-Flood tide
6 Nov 2012
Mid-Ebb tide
Table
I Summary of Water Quality
Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring
Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HK/2009/01 |
WSD19 |
0 |
0 |
2 |
1 |
0 |
1 |
0 |
0 |
3 |
2 |
0 |
1 |
|
|
C1 |
0 |
0 |
0 |
0 |
0 |
0
|
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4e |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4w |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
|
Monitoring finished on 27 April 2012 |
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
|
|
C5w |
0 |
0 |
1 |
1 |
0 |
1 |
0 |
0 |
0 |
1 |
1 |
0 |
|
Monitoring started on 8 Feb 2012 |
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
1 |
1 |
|
WSD9 |
0 |
0 |
1 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
||
|
WSD17
|
0 |
0 |
4 |
2 |
0 |
3 |
0 |
0 |
2 |
0 |
0 |
1 |
|
HY/2009/15 |
C7 |
1 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/19 Monitoring started on 28 Jan 2012 |
C8 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
|
C9 |
0 |
0 |
3 |
4 |
2 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
||
Total |
3 |
0 |
12 |
10 |
3 |
6 |
0 |
0 |
9 |
6 |
4 |
3 |
||
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
- WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
-
4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9
were completed on 6 Feb 2012.
-
C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.
-
WSD7 and WSD20 water quality monitoring were temporarily suspended from
27 Apr 2012.
Table
II Summary of Enhanced Dissolved
Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
1 |
0 |
C7 |
0 |
1 |
1 |
0 |
|
Ex-WPCWA SW |
0 |
6 |
1 |
1 |
|
Ex-WPCWA SE |
4 |
5 |
5 |
3 |
|
Total |
4 |
12 |
8 |
4 |
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
Marine Works
¡P
Fabrication of precast concrete caisson seawalls, precast box culvert
(Bay 10) and precast discharge outfall in precasting yard at
¡P
Dredging works for Type 2 sediment underneath
¡P
Dredging works between CH290 and CH370 at east of HKCEC near Wan Chai
west ferry pier would be commenced after completion of removal of high spot of
Grade 75 rock fill along the submarine pipeline of cross-harbour watermains.
¡P
Excavation work and tie back system for construction of pipe pile wall
near expo drive East
¡P
Removal of seawall and rock armour at
¡P
Rockfilling at east of HKCEC near
¡P
Trust block construction at TST landfall
¡P
Rockfilling and rock armour protection works to cross-harbour watermains
¡P
Reinstatement works at TST seashore including removal of silt screen
¡P
Fresh water flushing, final cleaning and sterilizatioin for
cross-harbour watermains CHA, CHB, CHE & CHF
¡P
Installation of Impressed Current Cathodic Protection (ICCP) system to
CHA and CHB
Fresh Watermains, Cooling
Watermains and Salt Watermains (On Land)
¡P
Works would be continued at Zone B1-5A, B2-1, B3-1, A1-1, A1-2, A2-2,
A1-4(CHWM), A2-3D, A3-2A, A3-4B, A3-3C, run-out of Renaissance Hotel and C1-6
¡P
Mainlaying works at Zone C1-6
¡P
Reinstatement works at Zone B1-5A and B2-1
¡P
Mainlaying works at Zone B3-1
¡P
Mainlaying works at
¡P
Mainlaying works and grouting works at jacking pit in Zone A1-2A &
A1-3A of
¡P
Mainlaying works at traffic island near junction between
¡P
Pipe laying works for Heading no. H1 would be continued .The remaining
pipe works at Zone A3-2A
¡P
Mainlaying works at Zone A3-4B would be continued and the works at Zone
A3-4A & A3-5A would be subsequently commenced concurrently after the Zone
A3-4B had been completed reinstated and reopened to public.
¡P
Pressure test for the 1 no. cooling watermains (AF)
E&M Works
¡P
Electrical works in Cooling Water Pumping Stations P5
¡P
Power supply to cooling water pumping station P5 from L.V. switchboard
¡P
Initial commissioning for Cooling Water Pumping Stations P5
¡P
Power energization for Cooling Water Pumping Stations P5
¡P
Full commissioning for Cooling Water Pumping Stations P3, P4 & P5
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Complete rectification works of cooling mains
and pressure test.
¡P
Continue 800MS pipe installation inside
¡P
Continue entrance area works at WSD Pumping
Station
¡P
Continue the finishing and E&M works of
WSD Salt Water Pumping Station.
¡P
Continue construction of Bay 1b ¡V 2 Salt
water intake culverts at WCR1 area.
¡P
Complete salt water intake
¡P
Continue salt water intake culvert at
transition bays inside jacking pit.
¡P
Continue remaining drainage works and reinstatement
works along
¡P
Complete Outfall Pipe B connection inside
outfall seaside cofferdam and Dye Tests
¡P
Continue construction of 1800 connection of Box
Culvert N1, Bay 4 & Bay 5 and
FRP installation at WCR1 area.
¡P
Commence concreting works for the Observation
Deck Level at the New Ferry Pier.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
¡P
Formation of temporary seawall at TS2
¡P
TZ1 and TS2 reclamation works
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Pile head breaking
¡P
Platform Disassembly
¡P
Dredging
¡P
Bored Pile cutting
Contract no. HY/2009/19- Wan Chai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link
¡P
Construction works for Box Culvert T
¡P
Marine Piling
¡P
Construction of 1500f drainage pipe
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009
and Further Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009,
FEP-04/356/2009 and FEP-05/356/2009 to implement the Environmental Monitoring
and Audit (EM&A) programme as stipulated in the EM&A Manual of the
approved Environmental Impact Assessment (EIA) Report for Wan Chai Development
phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the
EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring
and auditing work carried out in accordance to the Section 10.3 of EM&A Manual
and ¡§Environmental Monitoring and Audit Requirements¡¨ under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
for Environmental Permit no. EP-356/2009, Further Environmental Permit no.
FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 and during
the period of October to November. The cut-off date of reporting is at 27th
of each reporting month.
Section
1 Introduction ¡V
details the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results
obtained in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Site Inspection ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review
of any relevant
follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints, notification
of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai
Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨
(hereafter called ¡§the Project¡¨) are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental
Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB
to provide relief to the very congested
2.2.1.
The Project is located mainly in Wan Chai North,
2.2.2.
The study area encompasses existing developments
along the Wan Chai,
2.2.3.
The scope of the Project
comprises:
¡P
Land formation
for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated
slip roads for connection to the Trunk Road and for through traffic from Central to
Wan Chai and Causeway Bay. The land formed for the above transport infrastructure
will provide opportunities for the development of an attractive waterfront
promenade for the enjoyment of the public
¡P
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
¡P
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
¡P
Upgrading of
hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
¡P
Provision of the
ground level roads, flyovers, footbridges, necessary transport facilities and
the associated utility services
¡P
Construction of
the new waterfront promenade, landscape works and the associated utility
services
¡P
The Trunk Road
(i.e. CWB) within the study area and the associated slip roads for connection
to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1
summarises the five individual DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. Contractors of individual contracts will
be required by the EP holder to apply Further Environmental Permits (FEP) such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A reporting
for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized
in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North
Point Reclamation |
DP3 |
17 March 2010 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel ( |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the
construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
|
2162 9909 |
2587 1878 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Deputy Site Agent |
Mr Andy Yu |
96484896 |
|||
Construction Manager |
Mr Terry Wong |
9757 9846 |
|||
Construction Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction Manager |
Mr. Jack Chu |
9775 3008 |
|||
Environmental Officer
(Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Quality & Environmental Manager |
Mr. C.P. Ho |
9191 8856 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
P J Fan |
3557 6368 |
2566 2192 |
||
|
|
Contractor¡¦s Representative |
Mr. David Lau |
3557 6358 |
|
|
|
Head of Construction Manager |
Roger Cheung |
3557 6371 |
|
|
|
Senior Construction Manager |
Gene Cheung |
3557 6395 |
|
|
|
Environmental Officer |
Mr. Daniel Sin |
3557 6347 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental Officer |
Mr. Lee Wai Man |
9481
6024 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HK/2009/01, the principal work
activities in this reporting month included:
Marine Works (at Wan Chai)
¡P
Rockfilling for HKCEC3E (East of HKCEC) between CH290 and CH385
¡P
Grouting works to pipe pile at
¡P
Removal of existing seawall and rock armour at
¡P
Dredging underneath
¡P
Fabrication of 3 nos. of precast concrete caisson seawall, 1 no. precast
concrete box culvert (namely Bay 10) and 2 nos. precast discharge outfall in
precasting yard at
Cross-Harbour Watermains
Installation (CHA & CHB) and Marine Works (at TST)
¡P
Rockfilling and rock protection to cross-harbour watermains
¡P
Thrust block construction for A18B18
¡P
Connection work between land pipeline and marine pipeline
¡P
Reinstatement works for the TST landfall
Fresh Watermains, Cooling
Watermains and Salt Watermains (On Land)
¡P
Mainlaying works at Zone B1-5A, B2-1, B3-1, A1-1, A1-2, A1-4, A1-2A
& A1-3A, A2-3D, A3-2A, A3-4B, A3-3C, C1-6 and run-out of Renaissance Hotel
¡P
Mainlaying works at TTA Zone A2-3D and A1-4
¡P
Pipe laying works at heading No. H1 and Zone A3-4B
¡P
Mainlaying works at Zone A3-3C
¡P
Mainlaying and chamber construction works at the traffic island near
junction of
¡P
Mainlaying works at
¡P
Final cleaning, CCTV inspection and pressure test for the 9 nos. cooling
watermains
E&M
¡P
Electrical works in cooling water pumping stations P5
¡P
Major cabling works from existing LV Switch-board Room to Cooling Water
Pumping Station P5
¡P
Power energization to L.V. switchboard for cooling water pumping
stations P5
¡P
Full commissioning for Cooling Water Pumping Stations P1
2.4.4.
For Contract no. HK/2009/02, the principal work
activities in this reporting month included:
¡P
Repairing of door hinges in the New Public Toilet..
¡P
Modification work of PTI at
¡P
Modification work of bus station at
¡P
Pre-inspection for P9 (SHK) Pumping Station.Reinstatement at
¡P
Cooling mains installation at west of Gate 1 inside ex-pet garden
¡P
Cooling main remedial works for the bending pipes
¡P
Installation of optic fiber and power cable
¡P
E&M works and ABWFs installation at WSD Salt Water Pumping Station
¡P
Concreting of boundary wall of EVA at WSD Pumping Station
¡P
Concreting of Inspection Manhole and Access Chamber of Salt Water Intake
Culvert at Bay 19B & 20
¡P
Concreting of the wall and top slab at salt water intake culvert Bay
¡P
Concreting of the blinding layer at salt water intake culvert Bay 9 -
Bay 11 at WCR1
¡P
Concreting of the wall and top slab at salt water intake culvert Bay 9
at WCR1 and steel fixing of base slab at Bay 10
¡P
Cutting the sheetpile wall at salt water intake culvert Bay 11 to
jacking pit
¡P
Concreting of wall and top slab of Bay
2.4.5.
For Contract no. HY/2009/15, the principal work
activities in this reporting month included:
¡P
TZ1 and TS2 reclamation works
¡P
Formation of temporary seawall at TS2
2.4.6.
For Contract no. HK/2010/06, the principal work
activities in this reporting month included:
¡P
Pile head breaking
¡P
Platform Disassembly
¡P
Bored Pile cutting
2.4.7.
For Contract no. HY/2009/19, the principal work
activity in this reporting month included:
¡P
Marine bored piling
¡P
Construction works for Box Culvert T
¡P
Construction of 1500f drainage pipe
2.4.8.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
Marine Works
¡P
Fabrication of precast concrete caisson seawalls, precast box culvert
(Bay 10) and precast discharge outfall in precasting yard at
¡P
Dredging works for Type 2 sediment underneath
¡P
Dredging works between CH290 and CH370 at east of HKCEC near Wan Chai
west ferry pier would be commenced after completion of removal of high spot of
Grade 75 rock fill along the submarine pipeline of cross-harbour watermains.
¡P
Excavation work and tie back system for construction of pipe pile wall
near expo drive East
¡P
Removal of seawall and rock armour at
¡P
Rockfilling at east of HKCEC near
¡P
Trust block construction at TST landfall
¡P
Rockfilling and rock armour protection works to cross-harbour watermains
¡P
Reinstatement works at TST seashore including removal of silt screen
¡P
Fresh water flushing, final cleaning and sterilizatioin for
cross-harbour watermains CHA, CHB, CHE & CHF
¡P
Installation of Impressed Current Cathodic Protection (ICCP) system to
CHA and CHB
Fresh Watermains, Cooling
Watermains and Salt Watermains (On Land)
¡P
Works would be continued at Zone B1-5A, B2-1, B3-1, A1-1, A1-2, A2-2,
A1-4(CHWM), A2-3D, A3-2A, A3-4B, A3-3C, run-out of Renaissance Hotel and C1-6
¡P
Mainlaying works at Zone C1-6
¡P
Reinstatement works at Zone B1-5A and B2-1
¡P
Mainlaying works at Zone B3-1
¡P
Mainlaying works at
¡P
Mainlaying works and grouting works at jacking pit in Zone A1-2A &
A1-3A of
¡P
Mainlaying works at traffic island near junction between
¡P
Pipe laying works for Heading no. H1 would be continued .The remaining
pipe works at Zone A3-2A
¡P
Mainlaying works at Zone A3-4B would be continued and the works at Zone
A3-4A & A3-5A would be subsequently commenced concurrently after the Zone
A3-4B had been completed reinstated and reopened to public.
¡P
Pressure test for the 1 no. cooling watermains (AF)
E&M Works
¡P
Electrical works in Cooling Water Pumping Stations P5
¡P
Power supply to cooling water pumping station P5 from L.V. switchboard
¡P
Initial commissioning for Cooling Water Pumping Stations P5
¡P
Power energization for Cooling Water Pumping Stations P5
¡P
Full commissioning for Cooling Water Pumping Stations P3, P4 & P5
Contract no. HK/2009/02 - Wan
Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
PTI modification works after completion of
New Public Toilet in
¡P
Complete all cooling mains and cabling works
for P7, P8 & P9 Pumping Stations permanent power-on and signal control.
¡P
800MS pipe installation inside
¡P
Modification work of EVA & Vehicle access
at WSD Pumping Station
¡P
Finishing works of WSD Salt Water Pumping
Station.
¡P
Construction of Bay 1b ¡V 2, Bay 6 ¡V 8 salt
water intake culverts at WCR1 area.
¡P
ELS of the salt water intake
¡P
Salt water intake culvert at transition bays
inside jacking pit and receiving pit.
¡P
Remaining drainage works and reinstatement works
along
¡P
HDPE piping inside outfall seaside cofferdam.
¡P
Construction for Box Culvert N1 at WCR1 area.
¡P
Concreting works for the Mezzanine Level at
the New Ferry Pier.
¡P
Seawall strengthening works at WCR2 area.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (
¡P
Formation of temporary seawall at TS2
¡P
TZ1 and TS2 reclamation works
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Pile head breaking
¡P
Platform Disassembly
¡P
Dredging
¡P
Bored Pile cutting
Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
¡P
Construction
works for Box Culvert T
¡P
Marine Piling
¡P
Construction of
1500f drainage pipe
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009/A |
4 Aug
2010 |
Superseded |
Environmental
Permit |
EP-364/2009/B |
17 Aug
2009 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb
2010 |
Surrendered |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
22 Nov
2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Valid |
Further
Environmental Permit |
FEP-01/364/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further
Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Valid |
Further
Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Surrendered |
Further
Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Valid |
Further
Environmental Permit |
FEP-08/364/2009/A |
15 Jun 2012 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
3.1.3.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and
Table 3.5.
Table
3.4 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0460-12 |
10 May 2012 |
13 May 2012 to 6 Nov 2012 |
Expired |
|
GW-RS0514-12 |
14 May 2012 |
27 May 2012 to 26 Nov 2012 |
Expired |
|
GW-RS0855-12 |
16 Aug 2012 |
17 Aug 2012 to 9 Feb 2013 |
Cancelled |
|
GW-RS0862-12 |
20 Aug 2012 |
28 Aug 2012 to 27 Feb 2013 |
Cancelled |
|
GW-RS0949-12 |
12 Sep 2012 |
16 Sep 2012 to 15 Mar 2013 |
Cancelled |
|
GW-RS0545-12 |
24 May 2012 |
26 May 2012 to 25 Nov 2012 |
Expired |
|
GW-RS0546-12 |
25 May 2012 |
26 May 2012 to 25 Nov 2012 |
Expired |
|
GW-RS0760-12 |
18 Jul 2012 |
20 Jul 2012 to 19 Jan 2013 |
Valid |
|
GW-RS0806-12 |
3 Aug 2012 |
4 Aug 2012 to 03 Feb 2013 |
Cancelled |
GW-RS0823-12 |
3 Aug 2012 |
3 Aug 2012 to 02 Feb 2013 |
Cancelled |
|
GW-RS0852-12 |
16 Aug 2012 |
16 Aug 2012 to 01 Feb 2013 |
Cancelled |
|
GW-RS0994-12 |
25 Sep 2012 |
25 Sep 2012 to 19 Nov 2012 |
Expired |
|
GW-RS1011-12 |
26 Sep 2012 |
30 Sep 2012 to 29 Mar 2013 |
Cancelled |
|
GW-RS1017-12 |
27 Sep 2012 |
30 Sep 2012 to 24 Mar 2013 |
Valid |
|
GW-RE0793-12 |
21 Sep 2012 |
30 Sep 2012 to 29 Mar 2013 |
Valid |
|
|
GW-RS1040-12 |
8 Oct 2012 |
13 Oct 2012 to 12 Apr 2013 |
Valid |
GW-RS1177-12 |
15 Nov 2012 |
17 Nov 2012 to 10 May 2013 |
Valid |
|
GW-RS1184-12 |
15 Nov 2012 |
17 Nov 2012 to 8 May 2013 |
Valid |
|
GW-RS1185-12 |
19 Nov 2012 |
21 Nov 2012 to 8 May 2013 |
Valid |
|
GW-RS1179-12 |
20 Nov 2012 |
22 Nov 2012 to 21 May 2013 |
Valid |
|
GW-RS1187-12 |
20 Nov 2012 |
27 Nov 2012 to 26 May 2013 |
Valid |
|
|
GW-RS1199-12 |
20 Nov 2012 |
26 Nov 2012 to 25 May 2013 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
|
Billing account under Waste Disposal Ordinance |
7010069 |