Contract No: HK/2011/07 Wanchai
Development Phase II and Sampling, Field
Measurement and Testing Works (Stage 2) Environmental Permit no. EP-356/2009, Further Evironmental
permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 ,Fep-05/356/2009,
Fep-06/356/2009 and FEP-07/356/2009 Monthly Environmental Monitoring & Audit Report
- July 2013 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
August 2013 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of Water Quality Monitoring Exceedances in
Reporting Month
Table II Summary of Enhanced Dissolved Oxygen Monitoring
Exceedances in Reporting Month
Table 2.1 Schedule 2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.4 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/01
Table 3.5 Summary of submission status under FEP-02/356/2009
Condition
Table 3.6 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/02
Table 3.7 Summary of submission status under FEP-03/356/2009
Condition
Table 3.8 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/15
Table 3.9 Summary of submission status under FEP-04/356/2009
Condition
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2010/06
Table 3.11 Summary of submission status under EP-356/2009 and
FEP-05/356/2009 Condition
Table 3.12 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Table 3.13 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2012/08
Table 3.14 Summary of submission status
under EP-356/2009 and FEP-06/356/2009 Condition
Table 3.15 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2010/08
Table 3.16 Summary of submission status under EP-356/2009 and FEP-07/356/2009 Condition
Table 4.1 Noise Monitoring Station
Table 4.2 Real Time Noise Monitoring Station
Table 4.3 Air Monitoring Station
Table 4.4 Marine Water Quality Stations for Water Quality
Monitoring
Table 4.5 Marine Water Quality Monitoring Frequency and
Parameters
Table 4.6 Marine Water Quality Stations for Enhanced Water
Quality Monitoring
Table 4.7 Marine Water Quality Stations for Additional DO
Monitoring
Table 5.2 Noise Monitoring Station for Contract nos. HK/2009/01,
HK/2009/02 and HK/2010/06
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/15
Table 5.4 Noise Monitoring Station for Contract no. HY/2009/19
Table 5.5 Real Time Noise Monitoring Station for Contract no.
HY/2009/19
Table
5.7 Air Monitoring Station for Contract no.
HK/2009/01
Table 5.8 Air Monitoring Station for Contract no. HK/2009/02
Table 5.9 Air Monitoring Station for Contract no. HY/2009/15
Table 5.10 Air
Monitoring Stations for Contract no. HY/2009/19
Table 5.11 Water Monitoring Stations for contracts
with respect to remaining DP3
work areas after the completion of
DP5 & DP6 in 2012 and intake diversion in 2013
Table 5.12 Water
Monitoring Stations for Contract no. HK/2009/01
Table 5.13 Water
Monitoring Stations for Contract no. HK/2009/02
Table 5.14 Water
Monitoring Stations for Contract no. HK/2010/06
Table 5.15 Water
Monitoring Stations for Contract no. HY/2009/15
Table 5.16 Water
Monitoring Stations for Contract no. HY/2009/19
Table 5.17 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Table 5.18 Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 5.19 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.20 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.21 Details of Waste Disposal for Contract no. HY/2009/15
Table 5.22 Details of Waste Disposal for Contract no. HK/2010/06
Table 5.23 Details
of Waste Disposal for Contract no. HY/2009/19
Table 5.24 Details
of Waste Disposal for Contract no. HK/2012/08
Table 5.25 Details of Waste Disposal for Contract
no. HY/2010/08
Table 8.1 Summary
of Environmental Inspections for Contract no. HK/2009/01
Table 8.2 Summary
of Environmental Inspections for Contract no. HK/2009/02
Table 8.3 Summary
of Environmental Inspections for Contract no. HY/2009/15
Table 8.4 Summary
of Environmental Inspections for Contract no. HK/2010/06
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended Mitigation
Measures in Coming Reporting Month
lIST OF FIGUREs
Figure 2.2 Project Organization Chart
Figure 2.3 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix 5.4 Water Quality Monitoring Results and Graphical Presentations
Appendix 5.4a Additional Dissolved Oxygen Monitoring Results
Appendix 5.5 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix
6.2 Summary for Notification of
Exceedance
Appendix 8.1 Construction Programme of Individual Contracts
Construction Activities for the Reported Period
Marine Works (at Wan Chai)
ˇP
Rockfilling at the northern
part of HKCEC3E (East of HKCEC) between CH290 and CH385.
ˇP
Structural blinding for construction of proposed
box
ˇP
Pre-drilling work for steel bridge on the top of
temporary open channel along
ˇP
4 nos. of drill holes for D-wall and pre-bored
H-piles in stage 3.
ˇP
Mitigation measures such as widening the waterway
at reclamation area ˇ§HKCEC3Eˇ¨, installation of pumps and water pipe for pumping
seawater from
ˇP
Dumping of ice blocks into temporary water channel
to cool down the seawater at the temporary water channel.
Cross-Harbour Watermains
Installation (CHA & CHB) and Marine Works (at TST)
ˇP
Minor defect rectification works for submarine
pipeline A and B (removal of silt). WSD accepted the rectification work.
ˇP
Testing of ICCP monitoring system and SCADA for new
provided cross harbour watermain was carried out with WSD. Damaged isolation
joints would be delivered to HK in mid Aug 2013.
XHWM, Cooling Watermains,
Salt Watermains and Sewer (On Land)
ˇP
XHWM-Stage 1 connection. Stage 2 and 3 would be
connected.
ˇP
Pipework for Additional Washout Chamber at VIP
drop-off and the excavation and shoring for the structure.
ˇP
Reinstatement works at B6-2B at Northwest of HKCEC.
ˇP
Planter reinstatement, kerbworks, hard paving at
West Foyer of HKCEC.
ˇP
Sewer laying works in Zone B6-2A, B6-4, B6-6 B6-5C
& B6-6 at west of HKCEC area.
ˇP
Cooling main works in Zone C1-2.
ˇP
Salt watermain laying works in Zone A1-5C.
ˇP
Salt watermain laying works in Zone A3-5C.
ˇP
Salt watermain laying works in Zone A3-1, A5-2 and
A1-5C.
ˇP
Salt watermain laying works in A4-1B, 2B.
ˇP
Temporary ducting and cabling works at junction
between
Tunnel Works
ˇP
Installation of pre-bored H-pile in CWB Stage 1
underneath Atrium Link (from CH80 to CH120).
ˇP
Installation of pre-bored H-pile in CWB Stage 2
Atrium Link (from CH120 to CH220).
ˇP
Construction of bulkhead wall at CH3129 (18
panels).
ˇP
Filling of the existing open water channel at
CH260.
ˇP
Construction of the Common D-wall.
ˇP
Demolition of the Promenade Deck.
ˇP
Installation of dewatering wells, observation wells
and piezometers at CWB Stage 1.
E & M
ˇP
Operation attendance of 60 day.
ˇP
Switchover for cooling system P5.
ˇP
The old pumping house for EMSD and CP.
ˇP
Modification work of PTI at
ˇP
Modification of existing covered walkway along
ˇP
The first and second attempt of full commissioning
of P9 cooling water system.
ˇP
Minor remedial works for commissioning for both P7
and P8 cooling water system.-
ˇP
The wall and top slab at
ˇP
Installation of guide rails for preliminary screens
of Salt Water Intake Chamber No.1 at Bay 2A.
ˇP
The leakage test of stoplogs..
ˇP
The base slab of proposed wash out chamber near CHS8A160.
ˇP
The pipe laying work near the proposed connection
point.
ˇP
The remaining ABWF works in WSD Salt Water Pumping
Station, including maintenance platform and external finishes.
ˇP
Dry tests at WSD Salt Water Pumping Station. Wet
test after completion of the proposed intake culvert.
ˇP
Sheet pile cutting works at Bay5 / Bay 6 interface and
excavation down to the formation level for subsequent construction of water plug.
ˇP
The diver works between Bay 5 and the installed
precast unit (Bay 6).
ˇP
The modification work for both east and west wings
of staircase ST-01 landing.
ˇP
Counterweight installation for movable ramp.
ˇP
Installation of landing door for the disabled lift and
glass installation.
ˇP
Last panel (BHC12) of Eastern Bulkhead Wall.
ˇP
Interface coring and shear pin installation for the
Eastern Bulkhead Wall.
ˇP
The road modification works along
ˇP
Placing wearing course along in fount of Gammon
Entrance No. 1 and road making.
ˇP
Breaking up the existing pavement and disposal for
extract sheetpile next to ECO gas filling station.
ˇP
Rockfilling by Grade 400 at WCR4 and Grade 200 rockfilling
works..
ˇP
Placing geotextile at TWCR4.
ˇP
Seawall blocks installation at WCR4 & TWCR4.
ˇP
Construction of EVA
ˇP
Sheet piling works
ˇP
Utility diversion works
ˇP
Road resurfacing works
ˇP
D-wall and Barrette Construction
ˇP
Construction works for Box Culvert T1
ˇP
Construction works for Culvert U1
ˇP
Demolition of parapet at IEC Link
ˇP
Construction of dewatering well for Cut & Cover
Tunnel
ˇP
Removal of marine platform
ˇP
Construction of pile cap, column & cross head
(Marine)
ˇP
ELS for Cut & Cover Tunnel
ˇP
Laying of 1500f pipe
ˇP
Launching of segments
ˇP
Unloading segments from derrick
ˇP
Extraction of temporary pile from marine section
ˇP
Site preparation works
ˇP
Site survey
ˇP
Marine ground investigation
ˇP
ELS for box culvert La at
ˇP
Dredging
ˇP
Demolition of the existing
Noise
Monitoring
Real-time
Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
Table I Summary
of Water Quality Monitoring Exceedances in Reporting Month
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
||
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
P5 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C5w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Monitoring started
on 8 Feb 2012 |
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
HY/2009/15 |
C7 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
1 |
0 |
0 |
Total |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
1 |
0 |
1 |
- WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
- 4-week water quality monitoring at
WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.
- C8 and C9 were implemented with
respect to HY/2009/19 from 28 Jan 2012.
- C8 & C9 was temporary
suspended on 30 March 2013 due to the marine works for Contract no. HY/2009/19
had been completed on 4 March 2013
- WSD7 and WSD20 water quality
monitoring were temporarily suspended from 27 Apr 2012.
Table
II Summary of Enhanced Dissolved
Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
C6 |
0 |
0 |
0 |
0 |
|
C7 |
1 |
0 |
1 |
0 |
|
Ex-WPCWA SW |
0 |
4 |
0 |
2 |
|
Ex-WPCWA SE |
5 |
4 |
2 |
0 |
|
Total |
6 |
8 |
3 |
2 |
Complaints, Notifications of Summons and Successful
Prosecutions
Site Inspections and Audit
Contract no. HK/2009/01 ˇV Wan Chai Development
Phase II ˇV Central ˇVWanchai Bypass at HKCEC
Marine Works
ˇP
Filling works up to +4.0mPD between CH290 to CH370.
ˇP
Pre-bored H-pile footing at north side for
construction of steel bridge over temporary open channel between CH220 and
CH260.
ˇP
Reinstatement of existing seawall at
ˇP
Construction of RC structure proposed box culvert
Bay 8 and Bay 9.
ˇP
Backfilling to temporary water channel for
subsequent demolition of promenade deck and pumping station at HKCEC Water
Channel.
Cross-Harbour Watermains
Installation (CHA & CHB) and Marine Works at TST
ˇP
Connection of pipeline D to existing mains at Wan
Chai .
ˇP
Connection of Pipeline C to exiting mains at Wan
Chai.
ˇP
Connection of Pipeline F to exiting mains at TST.
ˇP
Disconnection and capping to existing mains at TST.
Cooling Watermains, Salt
Watermains and Sewer (On Land)
ˇP
XHWM-Stage 4.
ˇP
Additional Washout Chamber at VIP drop-off.
ˇP
Reinstatement works at B6-2A and B6-3 at Northwest
of HKCEC.
ˇP
Reinstatement of roadworks at B6-4 West Foyer of
HKCEC.
ˇP
Works at Zone A1-5C, A1-5A2 and A3-5C.
ˇP
Mainlaying works at A1-5C.
ˇP
Mainlaying works at Zone A5-5, A5-2, A4-2B, A1-5A2.
ˇP
Advance works for mainlaying works in Zone C1-2.
ˇP
Mainlaying works at Zone X2-1 when instruction from
the Engineer had been received.
ˇP
Temporary ducting and cabling works at junction
between
ˇP
Temporary ducting and cabling works at junction
between
Tunnel Works
ˇP
Installation of pre-bored H-pile in CWB Stage 2 Atrium,
Link.
ˇP
Filling of the existing open water channel and
Dome.
ˇP
Construction of the south Common D-wall.
ˇP
Demolition of the Promenade Deck.
ˇP
Installation of dewatering wells, observation wells
and piezometers at CWB stage 1.
ˇP
ELS for Stage 1 CWB.
E&M Works
ˇP
Operation attendance of 60 day for P5.
Contract no. HK/2009/02 ˇV Wan Chai Development
Phase II ˇV Central ˇV Wan Chai Bypass at Wan Chai East
ˇP
Full commissioning for P7 cooling water system.
ˇP
Full commissioning for P9 cooling water system.
ˇP
Remedial works for P8 discharge pipe at WCR1 area.
ˇP
Remaining DN800 salt watermins (CHS
ˇP
All mainlaying works and prepare for connection
with the existing DN600 salt watermains at
ˇP
All civil works of SWIC and commence wet test of
the Pumping Station.
ˇP
Facade works for the external wall of WSD Salt
Water Pumping Station.
ˇP
Construction of Bay 5 Box Culvert N1.
ˇP
ABWF works in Ferry Pier.
ˇP
Installation of moveable ramp system and disabled
lift installation.
ˇP
Canopy installation and waterproofing works on
Observation Deck.
ˇP
Curtain wall (glass) installation.
ˇP
Site delivery of critical E&M equipment
especially the switchboard.
ˇP
ˇP
Rockfilling and evelling stone installation for
seawall construction at both WCR4 & TWCR4.
ˇP
Geotextile installation for temporary reclamation
at TWCR4 and commence filing works.
ˇP
Precast concrete seawall installation at WCR4 &
TWCR4.
ˇP
Backfilling and road reinstatement works at Hung
Hing Road & Wan Shing Street for successful implementation of HHR Flyover
Diversion (Stage 1) .
Contract no. HY/2009/15 ˇV Central-Wanchai Bypass ˇV
Tunnel (
Contract no. HK/2010/06 ˇV Wan Chai Development
Phase II ˇV Central ˇV Wan Chai Bypass over MTR Tsuen Wan Line
ˇP
Sheet piling works
ˇP
Utility diversion works
Contract no. HY/2009/19- Wan Chai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link
ˇP
D-wall and Barrette Construction
ˇP
Construction works for Box Culvert T1
ˇP
Demolition of parapet at IEC Link
ˇP
Construction of dewatering well for Cut & Cover
Tunnel
ˇP
Removal of marine platform
ˇP
Construction of pile cap, column & cross head
(Marine)
ˇP
ELS for Cut & Cover Tunnel
ˇP
Installation of dewatering well
ˇP
Laying of 1500f pipe
ˇP
Launching of segments
ˇP
Unloading segments from derrick
ˇP
Extraction of temporary pile from marine section
Contract
no. HK/2012/08 ˇV Wan Chai Development Phase II ˇV Central- Wan Chai Bypass at Wan
Chai West
ˇP
Site survey
ˇP
Marine ground investigation
ˇP
Dredging
ˇP
Demolition of the existing
ˇP
ELS for box culvert La at
Contract
no. HY/2010/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel (Slip Road 8)
ˇP
Nil
1.1.1. Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-356/2009 and Further Environmental
permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-05/356/2009,
FEP-06/356/2009 and FEP-07/356/2009 to implement the Environmental Monitoring and Audit
(EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2. This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of EM&A Manual and ˇ§Environmental
Monitoring and Audit Requirementsˇ¨ under Particular Specification Section
27.
1.1.3. This
report documents the finding of EM&A works for Environmental Permit no.
EP-356/2009, Further Environmental Permit no. FEP-02/356/2009, FEP-03/356/2009,
FEP-04/356/2009, FEP-05/356/2009, FEP-06/356/2009 and FEP-07/356/2009 during the
period of June 2013 to July 2013. The cut-off date of reporting is at 27th
of each reporting month.
Section 1 Introduction ˇV details the scope and structure of the report.
Section 2 Project
Background ˇV summarizes background and
scope of the project, site description, project organization and contact
details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance ˇV summarizes the status of valid Environmental Permits /
Licenses during the reporting period.
Section 4 Monitoring
Requirements ˇV summarizes all monitoring
parameters, monitoring methodology and equipment, monitoring locations,
monitoring frequency, criteria and respective event and action plan and
monitoring programmes.
Section 5 Monitoring
Results ˇV summarizes the monitoring
results obtained in the reporting period.
Section 6 Compliance Audit ˇV summarizes
the auditing of monitoring results, all exceedances environmental
parameters.
Section 7 Cumulative Construction Impact due
to the Concurrent Projects ˇV summarizes the relevant cumulative
construction impact due to the concurrent activities of the concurrent Projects.
Section 8 Site Inspection ˇV summarizes the findings of weekly site inspections
undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of
summons and Prosecution ˇV summarizes the cumulative statistics on
complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1. ˇ§Wan Chai
Development phase II and Central-Wan Chai Bypassˇ¨ and ˇ§Central-Wan Chai Bypass
and Island Eastern Corridor Linkˇ¨ (hereafter called ˇ§the Projectˇ¨) are Designed
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai
Bypass and
2.1.2. The key
purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai
North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3. There is a
compelling and present need for the CWB to provide relief to the very congested
2.2.1. The
Project is located mainly in Wan Chai North, Causeway Bay and North Point, and
is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick
Pier Street to the west and Tong Shui Road Interchange to the east, as shown in
Figure 2.1.
2.2.2. The study
area encompasses existing developments along the Wan Chai,
2.2.3. The scope of the Project comprises:
ˇP
Land
formation for key transport infrastructure and facilities, including the Trunk
Road (i.e.
CWB) and the associated slip roads for connection to the Trunk Road and for through
traffic from Central to Wan Chai and Causeway Bay. The land formed for the above
transport infrastructure will provide opportunities for the development of an
attractive waterfront promenade for the enjoyment of the public
ˇP
Reprovisioning
/ protection of the existing facilities and structures affected by the land
formation works mentioned above
ˇP
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
ˇP
Upgrading
of hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
ˇP
Provision
of the ground level roads, flyovers, footbridges, necessary transport
facilities and the associated utility services
ˇP
Construction
of the new waterfront promenade, landscape works and the associated utility
services
ˇP
The
Trunk Road (i.e. CWB) within the study area and the associated slip roads for
connection to the Trunk Road.
2.2.4. The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (Eps) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1. Due to the
multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be commenced.
Contractors of individual contracts will be required by the EP holder to apply
Further Environmental Permits (FEP) such that the impact monitoring stations
are sub-divided accordingly to facilitate the implementation of EM&A
programme and to streamline the EM&A reporting for individual FEP holders
correspondingly.
2.3.2. The
details of individual contracts are summarized in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ˇV Central ˇVWanchai Bypass at |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central ˇV Wan Chai Bypass ˇV North
Point Reclamation |
DP3 |
17 March 2010 |
HY/2009/15 |
Central-Wanchai Bypass ˇV Tunnel ( |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HY/2009/17 |
Central ˇV Wan Chai Bypass (CWB) at FEHD Whitfield Depot ˇV Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central ˇV Wan Chai Bypass (CWB) ˇV Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central ˇV Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2012/08 |
Wan Chai
Development Phase II Central- Wan Chai Bypass at
Wan Chai West |
DP1,DP2,
DP3 |
March 2013 |
2.4.1. Civil
Engineering and Development Department and Highways Department are the overall
project controllers for the Wan Chai Development Phase II and Central-Wan Chai
Bypass respectively. For the construction phase of the Project, Project
Engineer, Contractor(s), Environmental Team and Independent Environmental
Checker are appointed to manage and control environmental issues.
2.4.2. The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineerˇ¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineerˇ¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun Wo ˇV Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint
Venture Board Representative |
|
2162 9909 |
2587 1878 |
Deputy Site
Agent |
Mr Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr Terry
Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 3008 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy
Mak |
9103 2370 |
|||
Environmental
Supervisor |
Kwong Weng
Kit |
6253 3356 |
|||
Chun Wo ˇV CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Deputy
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Quality & Environmental Manager |
Mr. C.P. Ho |
9191 8856 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
K C Cheung |
3557 6399 |
2566 2192 |
Site Manager |
J H Chen |
3557 6368 |
|||
|
|
Contractorˇ¦s Representative |
Andrew Wong |
3557 6358 |
|
|
|
Head of Construction Manager |
Roger Cheung |
3557 6371 |
|
|
|
Senior Construction Manager |
Gene Cheung |
3557 6395 |
|
|
|
Environmental Officer |
|