Contract No: HK/2011/07 Wanchai
Development Phase II and Central Wanchai Bypass Sampling, Field
Measurement and Testing Works (Stage 2) Environmental Permit no. EP-356/2009, Further Evironmental
permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 ,Fep-05/356/2009,
Fep-06/356/2009 and FEP-07/356/2009 Monthly Environmental Monitoring & Audit Report
- April 2014 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185
Gloucester Road, Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
14 May 2014 |
|
|
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of Water Quality Monitoring Exceedances in
Reporting Month
Table II Summary of Enhanced Dissolved Oxygen Monitoring
Exceedances in Reporting Month
Table 2.1 Schedule 2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.4 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/01
Table 3.5 Summary of submission status under FEP-02/356/2009
Condition
Table 3.6 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/02
Table 3.7 Summary of submission status under FEP-03/356/2009
Condition
Table 3.8 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/15
Table 3.9 Summary of submission status under FEP-04/356/2009
Condition
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2010/06
Table 3.11 Summary of submission status under EP-356/2009 and
FEP-05/356/2009 Condition
Table 3.12 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Table 3.13 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2012/08
Table 3.14 Summary of submission status
under EP-356/2009 and FEP-06/356/2009 Condition
Table 3.15 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2010/08
Table 3.16 Summary of submission status
under EP-356/2009 and FEP-07/356/2009 Condition
Table 4.1 Noise Monitoring Station
Table 4.2 Real Time Noise Monitoring Station
Table 4.3 Air Monitoring Station
Table 4.4 Marine Water Quality Stations for Water Quality
Monitoring
Table 4.5 Marine Water Quality Monitoring Frequency and
Parameters
Table 4.6 Marine Water Quality Stations for Enhanced Water
Quality Monitoring
Table 5.2 Noise Monitoring Station for Contract nos. HK/2009/01,
HK/2009/02 and HK/2010/06
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/15
Table 5.4 Noise Monitoring Station for Contract no. HY/2009/19
Table 5.5 Real Time Noise Monitoring Station for Contract no.
HY/2009/19
Table
5.7 Air Monitoring Station for Contract no.
HK/2009/01
Table 5.8 Air Monitoring Station for Contract no. HK/2009/02
Table 5.9 Air Monitoring Station for Contract no. HY/2009/15
Table 5.10 Air
Monitoring Stations for Contract no. HY/2009/19
Table 5.11 Water Monitoring Stations for contracts
with respect to remaining DP3
work
areas after the completion of DP5 & DP6 in 2012 and intake diversion in
2013
Table 5.12 Water
Monitoring Stations for Contract no. HK/2009/01
Table 5.13 Water
Monitoring Stations for Contract no. HK/2009/02
Table 5.14 Water
Monitoring Stations for Contract no. HK/2010/06
Table 5.15 Water
Monitoring Stations for Contract no. HY/2009/15
Table 5.16 Water
Monitoring Stations for Contract no. HY/2009/19
Table 5.17 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Table 5.18 Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 5.19 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.20 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.21 Details of Waste Disposal for Contract no. HY/2009/15
Table 5.22 Details of Waste Disposal for Contract no. HK/2010/06
Table 5.23 Details
of Waste Disposal for Contract no. HY/2009/19
Table 5.24 Details
of Waste Disposal for Contract no. HK/2012/08
Table 5.25 Details of Waste Disposal for Contract
no. HY/2010/08
Table 8.1 Summary
of Environmental Inspections for Contract no. HK/2009/01
Table 8.2 Summary
of Environmental Inspections for Contract no. HK/2009/02
Table 8.3 Summary
of Environmental Inspections for Contract no. HY/2009/15
Table 8.4 Summary
of Environmental Inspections for Contract no. HK/2010/06
Table 8.5 Summary
of Environmental Inspections for Contract no. HY/2009/19
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended Mitigation
Measures in Coming Reporting Month
lIST OF FIGUREs
Figure 2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix 5.4 Water Quality Monitoring Results and Graphical Presentations
Appendix 5.4a Additional Dissolved Oxygen Monitoring Results
Appendix 5.5 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix
6.2 Summary for Notification of
Exceedance
Appendix 10.1 Construction Programme of Individual Contracts
Construction Activities for the Reported Period
ˇP
New temporary road for diversion of Expo Drive
East.
ˇP
Stage 1 tunnel excavation work down to -10 mPD.
Further trimming for C3 interface. Bay 6 base slab of 950 m3 concrete, and the
side wall and mid wall construction. The concrete pouring for Bay 5.
ˇP
Installation of pre-bored H-piles. In Stage 2,
there were 2 nos. of piles at exhaust duct area (P10 & P24) and 3 nos. of
piles at tunnel (P242, P244 & P246). In Stage 3, there were 5 nos. of pile
casings (P252, P254, P348, P421 and P422).
ˇP
Construction of D-wall for the remaining south
D-wall panels at Stage 2. Panel WS05 and WS02. The target production rate of 1
panel per week.
ˇP
Discharge cooling mainlaying works for BI, BG &
BF. Junction areas with concerns that might in conflict to the route of new
temporary road for Zone C1-7 and X1-4A before the temporary road opening.
ˇP
Saltwater mainlaying works for S8B. Zone A5-4 and
A5-6 at Harbour Road. Zone A1-5A3 and A1-5A2 at Convention Avenue near Grand
Hyatt hotel.
ˇP
Tree transplanting at the planter areas near Hong
Kong Culture Centre at Tsim Sha Tsui.
ˇP
Trimming works at Fairway.
Section III
ˇP
Installation of steel post for the proposed covered
walkway.
ˇP
Modification of road junction between Expo Drive
and Expo Drive East.
Sections IVA, IVB & IVC
ˇP
The shaft of 8x8 pit and the backfilling work.
ˇP
The cable relocation for cooling water pumping
station. The backfilling works.
ˇP
Equipment removal of existing P8 Cooling Water
Pumping Station.
Section V
ˇP
Temp DN600 discharge pipe at inspection chamber.
ˇP
The reprovisioned WSD Salt Water Pumping Station,
the Salt Water Intake Culvert and DN800 salt water delivery main were started
their permanent function after capping the existing pipe.
ˇP
WSD handed over the abandoned Wan Chai Salt Water
Pumping Station at Hung Hing Road to CWCRGLJV.
ˇP
Defect rectification works and other outstanding
ABWF Works in WSD Salt Water Pumping Station.
Section VII:
ˇP
Removal of the temporary bulkhead at FRP-N drain.
ˇP
Pre-inspection for the FRP-N drain and the
reinstated existing manhole of SMH7007315 was done with DSD. DSD had no adverse comment.
Section VIIIA:
ˇP
At 1/F of Reprovisioned Wan Chai Ferry Pier, Gridline
10 -14 was handed over to Star Ferry.
ˇP
T&C of Movable Ramp.
Work related to HHR Flyover Diversion (Stage 2):
ˇP
Steel fixing for the pile cap.
ˇP
The backfilling works.
ˇP
Fabrication of temp bridges in fabrication yard in
the Mainland China.
ˇP
Construction of EVA
ˇP
Removal of marine platform
ˇP
Construction of Dolphin Cap
ˇP
ELS, EVB and Cut & Cover Tunnel
ˇP
Installation of dewatering well
ˇP
Laying of 1500f pipe
ˇP
Launching of segments
ˇP
Extraction of temporary pile from marine section
ˇP
Construction of bridge TA1
ˇP
Pre-bored H-pile for Admin. Building
ˇP
U-beam installation
ˇP
Parapet construction
ˇP
Wing slab extension for segment
ˇP
Construction of TD bridge
ˇP
ELS for box culvert La at Lung King Street
ˇP
Filling for seawall rock mound formation
ˇP
Filling for reclamation
ˇP
Works for abandoning submarine sewerage outfall
Noise
Monitoring
Real-time
Noise Monitoring
Air Quality Monitoring
24hr TSP monitoring at CMA1b was rescheduled from 3
April 2014 to 4 April 2014;
24hr TSP monitoring at CMA3a was rescheduled from 9
April 2014 to 10 April 2014;
24hr TSP monitoring at CMA4a was rescheduled from
21 April 2014 to 22 April 2014;
Water Quality Monitoring
Table I Summary
of Water Quality Monitoring Exceedances in Reporting Month
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2012/08 |
WSD19 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
0 |
0 |
P1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P5 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 Monitoring started
on 8 Feb 2012 |
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Monitoring started
on 29 July 2013 |
RW21-P789 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 &
HY/2010/08 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
0 |
0 |
- WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
- 4-week water quality monitoring at
WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.
- C8 and C9 were implemented with
respect to HY/2009/19 from 28 Jan 2012.
- C8 & C9 was temporary
suspended on 30 March 2013 due to the marine works for Contract no. HY/2009/19
had been completed on 4 March 2013
- WSD7 and WSD20 water quality monitoring
were temporarily suspended from 27 Apr 2012.
- C2, C3 C4e and C4w water quality monitoring
station was temporarily suspended since 24 Apr 2013
- C5e and C5w water quality
monitoring station was temporarily suspended since 29 July 2013
Table
II Summary of Enhanced Dissolved
Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
AL |
LL |
AL |
LL |
||
C6 |
0 |
0 |
0 |
0 |
|
C7 |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
0 |
3 |
0 |
4 |
|
Ex-WPCWA SE |
0 |
3 |
0 |
4 |
|
Total |
0 |
6 |
0 |
8 |
Complaints, Notifications of Summons and Successful
Prosecutions
Site Inspections and Audit
Contract no. HK/2009/01 ˇV Wan Chai Development
Phase II ˇV Central ˇVWanchai Bypass at HKCEC
ˇP
A series of construction works would be carried out
after the diversion of temporary road at Expo Drive East. i.e. Tree transplanting
works, demolition of the existing Expo Drive East Bridge at southern bound,
installation of pre-bored H-piles at the southern bound for box culvert Bay 1
and at the rockfilled area at west of temporary road for CWB. The overall
project would be mainly focus on Stage 2 and Stage 3 tunnel foundation works.
ˇP
Stage 1 tunnel structure works.
ˇP
Remaining cooling mainlaying works (other than Zone
C4 that lay on the East Bridge) after the confirmation of re-alignment.
ˇP
Sewer works at Fenwick Pier Street after confirmation
of re-alignment.
ˇP
Remaining Saltwater mainlaying works would be night
zones A4-2B and A4-2C near Renaissance Harbour View hotel.
Contract no. HK/2009/02 ˇV Wan Chai Development
Phase II ˇV Central ˇV Wan Chai Bypass at Wan Chai East
Sections IVA, IVB & IVC:
ˇP
All outstanding works for P7, P8 and P9 Cooling Water
Pumping Stations and trench backfilling adjacent to 8x8 pit.
Section V:
ˇP
Replace the installed DN600 mild steel coupling for
connection to the existing salt watermains at Hung Hing Road and subsequently
cast the bend block prior to permanent road reinstatement.
ˇP
All outstanding ABWF works at WSD Salt Water
Pumping Station.
Section VII:
ˇP
Backfilling to Tunnel
Portion 1 for completing the Works at Area 7.
Section VIIIA & VIIIB:
ˇP
All plumbing system including the connection with
the existing water supplies system in order to secure the Water Certificate
(WWO46) from WSD.
ˇP
ABWF works at 1/F G.L.1-9 and 2/F of Ferry Pier and
ready for handing over it to Star Ferry for commencing their fitting-out works.
ˇP
Installation of fender system.
ˇP
Testing & commissioning of both movable ramps and
disabled lift for subsequent handing over to Star Ferry.
ˇP
Installation of seating base plates and steel
frames and roof canopy cladding installation.
ˇP
Excavation and D-Wall trimming for capping beam
construction along the bulkhead wall at Tunnel Portion 2
Section XI:
ˇP
Removal of existing E&M equipment at the
abandoned SHK Cooling Water Pump House.
ˇP
Advanced dredging works of WCR3 by night work
ˇP
Remaining reclamation at WCR2 along the existing
seawall.
Contract no. HY/2009/15 ˇV Central-Wanchai Bypass ˇV
Tunnel (Causeway Bay Typhoon Shelter Section)
ˇP
EVA construction at Eastern Breakwater
ˇP
Reinstatement of Eastern Breakwater
Contract no. HK/2010/06 ˇV Wan Chai Development
Phase II ˇV Central ˇV Wan Chai Bypass over MTR Tsuen Wan Line
ˇP
Nil
Contract no. HY/2009/19- Wan Chai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link
ˇP
Removal of marine platform
ˇP
Construction of Dolphin Cap
ˇP
ELS, EVB and Cut & Cover Tunnel
ˇP
Laying of 1500f pipe
ˇP
Launching of segments
ˇP
Extraction of temporary pile from marine section
ˇP
Construction of bridge TA1
ˇP
Pre-bored H-pile for Admin. Building
ˇP
U-beam installation
ˇP
Parapet construction
ˇP
Wing slab extension for segment
ˇP
Construction of TD bridge
Contract
no. HK/2012/08 ˇV Wan Chai Development Phase II ˇV Central- Wan Chai Bypass at Wan
Chai West
ˇP
ELS for box culvert La at Lung King Street
ˇP
Filling for seawall rock mound formation
ˇP
Filling for reclamation
Contract no.
HY/2010/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel (Slip Road 8)
ˇP
Dredging works (works commence subject to handover
from other Contract)
1.1.1. Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-356/2009 and Further Environmental permit
nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-05/356/2009,
FEP-06/356/2009 and FEP-07/356/2009 to implement the Environmental Monitoring and Audit
(EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2. This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of EM&A Manual and ˇ§Environmental
Monitoring and Audit Requirementsˇ¨ under Particular Specification Section
27.
1.1.3. This
report documents the finding of EM&A works for Environmental Permit no.
EP-356/2009, Further Environmental Permit no. FEP-02/356/2009, FEP-03/356/2009,
FEP-04/356/2009, FEP-05/356/2009, FEP-06/356/2009 and FEP-07/356/2009 during the
period of March 2014 to April 2014. The cut-off date of reporting is at 27th
of each reporting month.
Section 1 Introduction ˇV details the scope and structure of the report.
Section 2 Project
Background ˇV summarizes background and
scope of the project, site description, project organization and contact
details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance ˇV summarizes the status of valid Environmental Permits /
Licenses during the reporting period.
Section 4 Monitoring
Requirements ˇV summarizes all monitoring
parameters, monitoring methodology and equipment, monitoring locations,
monitoring frequency, criteria and respective event and action plan and
monitoring programmes.
Section 5 Monitoring
Results ˇV summarizes the monitoring
results obtained in the reporting period.
Section 6 Compliance Audit ˇV summarizes
the auditing of monitoring results, all exceedances environmental
parameters.
Section 7 Cumulative Construction Impact due
to the Concurrent Projects ˇV summarizes the relevant cumulative
construction impact due to the concurrent activities of the concurrent Projects.
Section 8 Site Inspection ˇV summarizes the findings of weekly site inspections
undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of
summons and Prosecution ˇV summarizes the cumulative statistics on
complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1. ˇ§Wan Chai
Development phase II and Central-Wan Chai Bypassˇ¨ and ˇ§Central-Wan Chai Bypass
and Island Eastern Corridor Linkˇ¨ (hereafter called ˇ§the Projectˇ¨) are Designed
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai
Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan
Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008
respectively.
2.1.2. The key
purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai
North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3. There is a
compelling and present need for the CWB to provide relief to the very congested
east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the
Corridor) which is currently operating beyond its capacity. The CWB will
provide relief to the existing congestion along the Corridor and cater for the
anticipated growth of traffic on Hong Kong Island. Without the CWB and its
access roads, there will not be sufficient capacity to serve the heavy traffic
demands at both strategic and local levels.
2.2.1. The
Project is located mainly in Wan Chai North, Causeway Bay and North Point, and
is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick
Pier Street to the west and Tong Shui Road Interchange to the east, as shown in
Figure 2.1.
2.2.2. The study
area encompasses existing developments along the Wan Chai, Causeway Bay and
North Point shorelines. Major land uses include the Hong Kong Convention &
Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan Chai
Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC),
the Police Officersˇ¦ Club, the Causeway Bay Typhoon Shelter (CBTS) and
commercial and residential developments.
2.2.3. The scope of the Project comprises:
ˇP
Land
formation for key transport infrastructure and facilities, including the Trunk
Road (i.e.
CWB) and the associated slip roads for connection to the Trunk Road and for through
traffic from Central to Wan Chai and Causeway Bay. The land formed for the above
transport infrastructure will provide opportunities for the development of an
attractive waterfront promenade for the enjoyment of the public
ˇP
Reprovisioning
/ protection of the existing facilities and structures affected by the land
formation works mentioned above
ˇP
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
ˇP
Upgrading
of hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
ˇP
Provision
of the ground level roads, flyovers, footbridges, necessary transport
facilities and the associated utility services
ˇP
Construction
of the new waterfront promenade, landscape works and the associated utility
services
ˇP
The
Trunk Road (i.e. CWB) within the study area and the associated slip roads for
connection to the Trunk Road.
2.2.4. The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (Eps) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1. Due to the
multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be commenced.
Contractors of individual contracts will be required by the EP holder to apply
Further Environmental Permits (FEP) such that the impact monitoring stations
are sub-divided accordingly to facilitate the implementation of EM&A
programme and to streamline the EM&A reporting for individual FEP holders
correspondingly.
2.3.2. The
details of individual contracts are summarized in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ˇV Central ˇVWanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central ˇV Wan Chai Bypass ˇV North
Point Reclamation |
DP3 |
17 March 2010 (Completed) |
HY/2009/15 |
Central-Wanchai Bypass ˇV Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 (Completed) |
HY/2009/17 |
Central ˇV Wan Chai Bypass (CWB) at FEHD Whitfield Depot ˇV Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central ˇV Wan Chai Bypass (CWB) ˇV Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central ˇV Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2012/08 |
Wan Chai Development
Phase II Central- Wan Chai Bypass at
Wan Chai West |
DP1,DP2,
DP3 |
5 March 2013 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel ˇV Tunnel (Slip Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
2.4.1. Civil
Engineering and Development Department and Highways Department are the overall
project controllers for the Wan Chai Development Phase II and Central-Wan Chai
Bypass respectively. For the construction phase of the Project, Project
Engineer, Contractor(s), Environmental Team and Independent Environmental
Checker are appointed to manage and control environmental issues.
2.4.2. The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineerˇ¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineerˇ¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun Wo ˇV Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint
Venture Board Representative |
Mr. Simon Liu |
9304 8355 |
2587 1878 |
Deputy Site
Agent |
Mr Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr Terry
Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr Kenneth
Chan |
9160 3850 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Frank So |
9863 6587 |
|||
Assistant
Environmental Engineer |
Miss.
Connie Chan |
6157 7057 |
|||
Environmental
Supervisor |
Stanley
Chan |
9047 6148 |
|||
Chun Wo ˇV CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project
Manager |
Mr. Alfred Leung |
3658-3022 |
2827 9996 |
Quality & Environmental Manager |
Mr. C.P. Ho |
9191 8856 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
K C Cheung |
3557 6399 |
2566 2192 |
Site Manager |
J H Chen |
3557 6368 |
|||
|
|
Contractorˇ¦s Representative |
Andrew Wong |
3557 6358 |
|
|
|
Head of Construction Manager |
Roger Cheung |
3557 6371 |
|
|
|
Senior Construction Manager |
Gene Cheung |
3557 6395 |
|
|
|
Environmental Officer |
Andy Mak |
3557 6347 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Eric
Yip |
2529 2068 |
|||
Environmental
Officer |
Clement
Pang |
9735 9200 |
|||
Environmental
Supervisor |
Jacky
Cheung |
9779 2292 |
|||
Chun Wo ˇV CRGL ˇV MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
|
Site Agent |
Mr. Eric Yip |
252902068 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project Director |
Andrew Tse |
9137 1811 |
2877 1522 |
Project Manager |
Victor Wu |
9193 8871 |
|||
Deputy Project Manager |
George Cheung |
9268 1918 |
|||
Site Agent |
Paul Lui |
9095 7922 |
|||
Environmental Officer |
James Ma |
9130 9549 |
|||
Environmental Supervisor |
Ching Man, Chan |
6050 4919 |
|||
China State |
Contractor under
Contract |