Contract No: HK/2011/07

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Works (Stage 2)

 

Environmental Permit no. EP-356/2009,

Further Evironmental permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 ,Fep-05/356/2009,  Fep-06/356/2009 and FEP-07/356/2009

 

Monthly Environmental Monitoring & Audit Report

 

- JUNE 2014 -


CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

14 July 2014

 

 


Table of contents

 

EXECUTIVE SUMMARY. 4

1.     Introduction. 11

1.1        Scope of the Report 13

1.2        Structure of the Report 13

2.     Project Background. 15

2.1        Background. 15

2.2        Scope of the Project and Site Description. 15

2.3        Division of the Project Responsibility. 16

2.4        Project Organization and Contact Personnel 17

3.     Status of Regulatory Compliance. 21

3.1        Status of Environmental Licensing and Permitting under the Project 24

4.     Monitoring Requirements. 34

4.1        Noise Monitoring. 37

4.2        Air Monitoring. 38

4.3        Water Quality Monitoring. 41

5.     Monitoring Results. 46

5.1        Noise Monitoring Results. 46

5.2        Real-time Noise Monitoring. 48

5.3        Air Monitoring Results. 48

5.4        Water Monitoring Results. 50

5.5        Waste Monitoring Results. 56

6.     Compliance Audit. 61

6.1        Noise Monitoring. 63

6.2        Real-time noise Monitoring. 63

6.3        Air Monitoring. 63

6.4        Water Quality Monitoring. 64

6.5        Review of the Reasons for and the Implications of Non-compliance. 65

6.6        Summary of action taken in the event of and follow-up on non-compliance. 65

7.     Cumulative Construction Impact due to the Concurrent Projects. 65

8.     Environmental Site Audit. 66

9.     Complaints, Notification of Summons and Prosecution. 69

10.    Conclusion. 73


lIST OF TABLES

 

Table I         Summary of Water Quality Monitoring Exceedances in Reporting Month

Table II        Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Table 2.1     Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 3.1      Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.4      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.5      Summary of submission status under FEP-02/356/2009 Condition

Table 3.6      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.7      Summary of submission status under FEP-03/356/2009 Condition

Table 3.8      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.9      Summary of submission status under FEP-04/356/2009 Condition

Table 3.10    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2010/06

Table 3.11    Summary of submission status under EP-356/2009 and FEP-05/356/2009 Condition

Table 3.12    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Table 3.12    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Table 3.13    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2012/08

Table 3.14    Summary of submission status under EP-356/2009 and FEP-06/356/2009 Condition

Table 3.15    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2010/08

Table 3.16    Summary of submission status under EP-356/2009 and FEP-07/356/2009 Condition

Table 4.1      Noise Monitoring Station

Table 4.2      Real Time Noise Monitoring Station

Table 4.3      Air Monitoring Station

Table 4.4     Marine Water Quality Stations for Water Quality Monitoring

Table 4.5      Marine Water Quality Monitoring Frequency and Parameters

Table 4.6     Marine Water Quality Stations for Enhanced Water Quality Monitoring

Table 5.2     Noise Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06

Table 5.3     Noise Monitoring Station for Contract no. HY/2009/15

Table 5.4     Noise Monitoring Station for Contract no. HY/2009/19

Table 5.5      Real Time Noise Monitoring Station for Contract no. HY/2009/19

Table 5.7     Air Monitoring Stations for Contract no. HK/2009/01

Table 5.8     Air Monitoring Station for Contract no. HK/2009/02

Table 5.9     Air Monitoring Station for Contract no. HY/2009/15

Table 5.10    Air Monitoring Stations for Contract no. HY/2009/19

Table 5.11  Water Monitoring Stations for contracts with respect to remaining DP3

work areas after the completion of DP5 & DP6 in 2012 and intake diversion in 2013

Table 5.12    Water Monitoring Stations for Contract no. HK/2009/01

Table 5.13    Water Monitoring Stations for Contract no. HK/2009/02

Table 5.14    Water Monitoring Stations for Contract no. HK/2010/06

Table 5.15    Water Monitoring Stations for Contract no. HY/2009/15

Table 5.16    Water Monitoring Stations for Contract no. HY/2009/19

Table 5.17    Summary of Water Quality Monitoring Exceedances in Reporting Month

Table 5.18    Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Table 5.19    Details of Waste Disposal for Contract no. HK/2009/01

Table 5.20    Details of Waste Disposal for Contract no. HK/2009/02

Table 5.21    Details of Waste Disposal for Contract no. HY/2009/15

Table 5.22    Details of Waste Disposal for Contract no. HK/2010/06

Table 5.23    Details of Waste Disposal for Contract no. HY/2009/19

Table 5.24    Details of Waste Disposal for Contract no. HK/2012/08

Table 5.25  Details of Waste Disposal for Contract no. HY/2010/08

Table 8.1     Summary of Environmental Inspections for Contract no. HK/2009/01

Table 8.2     Summary of Environmental Inspections for Contract no. HK/2009/02

Table 8.3     Summary of Environmental Inspections for Contract no. HY/2009/15

Table 8.4     Summary of Environmental Inspections for Contract no. HK/2012/08

Table 8.5      Summary of Environmental Inspections for Contract no. HY/2010/08

Table 9.1      Cumulative Statistics on Complaints

Table 9.2      Cumulative Statistics on Successful Prosecutions

Table 10.1    Construction Activities and Recommended Mitigation Measures in Coming Reporting Month

 

 

lIST OF FIGUREs

 

Figure 2.1       Project Layout

Figure 2.2       Project Organization Chart

Figure 4.1     Locations of Environmental Monitoring Stations

 

 

 

lIST OF APPENDIces

 

Appendix 3.1  Environmental Mitigation Implementation Schedule

Appendix 4.1  Action and Limit Level

Appendix 4.2  Copies of Calibration Certificates

Appendix 5.1  Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2  Noise Monitoring Results and Graphical Presentations

Appendix 5.3  Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4  Water Quality Monitoring Results and Graphical Presentations

Appendix 5.4a  Additional Dissolved Oxygen Monitoring Results

Appendix 5.5  Real-time Noise Monitoring Results and Graphical Presentations

Appendix 6.1  Event Action Plans

Appendix 6.2  Summary for Notification of Exceedance

Appendix 9.1  Complaint Log

Appendix 10.1  Construction Programme of Individual Contracts


EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report ¡VJune 2014 for the Project of Wan Chai Development Phase II and Central-Wanchai Bypass under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-05/356/2009, FEP-06/356/2009 and FEP-07/356/2009. This report presents the environmental monitoring findings and information recorded during the period May 2014 to June 2014. The cut-off date of reporting is at 27th of each reporting month.

 

Construction Activities for the Reported Period

 

  1. During this reporting period, the major work activities for Contract no. HK/2009/01 included:

¡P          Ongoing demolition work of the exiting Expo Drive East Bridge

¡P          Ongoing work on UU diversion at Expo Drive East Bridge

¡P          Ongoing structure works for Stage 1 tunnel

¡P          Ongoing Stage 2 excavation

¡P          Installation of pre-bored H-piles at HKCEC water channel

¡P          Construction of D-wall

¡P          Ongoing mainlaying work on discharge cooling and saltwater

¡P          Ongoing rectification work

¡P          Demolition work of exiting HKCEC pump house

 

  1. During this reporting period, the major work activities for Contract no. HK/2009/02 included:

Ÿ   Road works between Expo Drive and Expo Drive East

Ÿ   Backfilling work

Ÿ   Installation and testing of AVR

Ÿ   Defect rectification works in WSD Salt Water Pumping Station

Ÿ   ABWF Works( Completion of fender system panels installation)

Ÿ   E&M Works for instance fire services ducting and cabling works

Ÿ   VSD installation and testing of movable ramp and life cage

Ÿ   Ongoing capping beam construction

Ÿ   Removal of marine mud at WCR2

Ÿ   Erection of Bridge 3

Ÿ   Modification of D-Wall for Bridge 2

Ÿ   Delivery of fabricated temp bridges

 

  1. During this reporting period, the major work activities for Contract no. HY/2009/15 included:

¡P          EVA construction at Eastern Breakwater

¡P          Reinstatement of Eastern Breakwater      

¡P          Removal of Seawall Blocks at TS2, TPCWAE & TS4

¡P          Demolition of D-Wall at TS2, TPCWAE & TS4

¡P          Maintenance dredging

 

  1. During this reporting period, no major work activities for Contract no. HK/2010/06.

 

  1. During this reporting period, the major work activities for Contract no. HY/2009/19 included:

Ÿ   Road works at Watson Road

Ÿ   Bored piling (Land)

Ÿ   Removal/Installation of strut at ELS

Ÿ   Construction of Dolphin Cap

Ÿ   ELS for Cut &Cover Tunnel and EVB

Ÿ   Laying of 1500f pipe

Ÿ   Launching of segments

Ÿ   Extraction of temporary pile from marine section

Ÿ   Construction of bridge TA1

Ÿ   Pre-bored H-pile for Admin. Building continue

Ÿ   U-beam installation continue

Ÿ   Parapet construction continue

Ÿ   Wing slab extension for segment continue

Ÿ   Construction of TD bridge continue

Ÿ   Construction of Bridge E

Ÿ   Construction of Bride F4 and F5

 

  1. During this reporting period, the major work activities for Contract no. HK/2012/08 included:

¡P          ELS for box culvert La at Lung King Street

¡P          Filling for seawall rock mound formation

¡P          Filling for reclamation

¡P          Dredging

 

  1. During this reporting period, the major work activities for Contract no. HY/2010/08.

¡P          Rock filling works (works cease on 8th Feb. 2014)

¡P          No dredging works carried out in reporting period.

 

Noise Monitoring

  1. No action and four limit level exceedances at M6 ¡V HK Baptist Church Henrietta Secondary School were recorded on 5, 10, 17 and 25 June 2014 in this reporting month. The exceedances were concluded as non-project related.
  2. One limit level exceedance at M2b ¡V Noon Day Gun Area was recorded on 24 June 2014 in this reporting month. The exceedance was concluded as project related.
  3. Noise monitoring during daytime and restricted hour were conducted at the stations M1a, M2b, M3a, M4b, M5b and M6 on a weekly basis in the reporting month.

 

 

Real-time Noise Monitoring

  1. As the land-based piling and filling works- DP3 at Tin Hau had been completed on 3 September 2012 and confirmed by RSS, the real-time noise monitoring results at FEHD Hong Kong Transport Section Whitfield Depot was excluded under EP-356/2009 since 28 November 2012.
  2. The real-time noise monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct 2012, which is a representative of noise sensitive receiver- City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.
  3. 24-hour real time noise monitoring was conducted at RTN2a ¡V Hong Kong Electric Centre. No project related exceedance was recorded in the reporting month.

 

Air Quality Monitoring

  1. Due to extension of site boundary by contractor of HY/2009/19, location of air monitoring station CMA1b ¡V Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.
  2. The location ID of air monitoring station CMA1b was updated as Oil Street Site Office in April 2013.
  3. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b ¡V Oil Street Site Office; CMA2a ¡V Causeway Bay Community Center; CMA3a ¡V CWB PRE Site Office Area; CMA4a ¡V Society for the Prevention of Cruelty to Animals; CMA5a ¡V Children Garden opposite to Pedestrian Plaza.

 

Water Quality Monitoring

  1. Action and Limit level of water quality monitoring was transited from dry season to wet season from 1 April 2014.
  2. As advised by WDII RSS, the water quality monitoring for WSD21 pump station with respect to HK/2009/02 was switched over to the relocated location since 12 March 2014. According to the EM&A Manual, the water quality monitoring station WSD21 was relocated to station RW21-P789 and the water quality monitoring at station WSD21 was temporarily suspended since 12 March 2014.
  3. According to CWB RSS, oil dispersion at the culvert outfall location at SW corner of CBTS was observed on 6, 22, 24 and 28 Feb 2014. An ICC case (ICC ref: 2-92821253) regarding the above issue was lodged by CWB RSS team to request for follow-up action by relevant departments.
  4. Oil dispersion at the culvert outfall location at Ex-Cargo handling area was observed on 28 Feb 2014 by CWB RSS. An ICC case (ICC ref: 2-125779508) regarding the above observation was lodged by CWB RSS team to request for follow-up action by relevant departments.
  5. With respect to the commencement of marine dredging works under contract HY/2010/08. The respective water quality monitoring station C7 were associated with HY/2009/15 and HY/201008
  6. With respect to the commencement of marine dredging works under contract HK/2012/08. The respective water quality monitoring station WSD19, P1, P3, P4, and P5 were associated with Contract HK/2012/08 since September 2013.
  7. With respect to the switching over of cooling water intake location, the water quality monitoring at the relocated intake station RW21-P789 under HK/2009/02 was commenced since 29 July 2013.
  8. Upon confirmation with WDII RSS and the IEC, water quality monitoring at relocated intakes monitoring location P1, P3, P4 and P5 were commenced since 24 April 2013 and WQM events at monitoring stations C2, C3, C4e and C4w were temporarily suspended since 22 April 2013.
  9. WDII/RSS advised that the dredging works for submarine pipeline at Victoria Harbour had been completed in January 2012. Therefore, the concurrent dredging activities at Sewage Pipeline Zone and reclamation shoreline zone TCBR under the EP-356/2009 scenario 2B no longer exist. As such, with reference to Table 5.39 of the EIA Report for Wan Chai Development Phase II and Central-Wan Chai Bypass, the application of silt screen for cooling water intakes for Queensway Government Offices was suspended and the others were remains unchanged.
  10. Based on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no water deterioration with respect to NPR was commenced since 7 Jan 2012 and was completed on 6 Feb 2012 water quality monitoring.
  11. Water quality monitoring at WSD10 and WSD15 will be temporary suspended while water quality monitoring at WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8 Feb 12 onwards;
  12. Water quality monitoring at C8 and C9 have been implemented with respect to HY/2009/19 since the marine bore piling work started on 28 Jan 12.
  13. As confirmed by CWB RSS, the marine pilling works under contract HY/2009/19 was confirmed completed by 4 March 2013. The water quality monitoring at the respective monitoring stations C8 and C9 were temporarily suspended since 30 March 2013.
  14. Due to the marine piling under Contract no. HY/2009/19 was completed on 4 March 2013, the temporary suspension of impact water quality monitoring at C8 and C9 from 4 March 2013 have been monitored for 4-week period after the completion of marine works to confirm no water deterioration.
  15. Based on the safety concern when external façade refurbishment was conducted by contractor employed by Provident Centre (C9) between 9 January 2012 to 30 July 2012 which caused to the inaccessibility of sampling either land and marine since 3 Feb 2012, there is a fine adjustment of the sampling location of water quality monitoring at C9 since 10 March 2012 to the closest accessible point prior to the completion of the external façade refurbishment work.
  16. Due to the access of water monitoring station at WSD19 was blocked by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the inaccessibility of sampling either land and marine, there is a fine adjustment of the sampling point of WSD 19 since 5 April 2012 to the closest accessible point prior to the completion of the construction activities.
  17. Due to the dredging works for Cross Harbour Water Mains from Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April 2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for 4-week period after the completion of DP6 to confirm no water deterioration.
  18. Water quality monitoring at 10 monitoring stations was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table I.
  19. RSS confirmed that all Type III Dredging works under HK/2009/01 have been completed since Oct 2012.

 

 

Table I    Summary of Water Quality Monitoring Exceedances in Reporting Month

 

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HK/2009/01

C1

0

0

0

0

0

0

0

0

0

0

0

0

HK/2012/08

WSD19

0

0

0

0

0

0

0

0

0

0

0

0

P1

0

0

0

0

0

0

1

0

0

0

0

0

P3

0

0

0

0

0

0

1

0

0

0

0

0

P4

0

0

0

0

0

0

0

0

0

0

0

0

P5

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/02

Monitoring started on

8 Feb 2012

WSD9

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD17

0

0

0

0

0

0

0

0

0

0

0

0

Monitoring started on

29 July 2013

RW21-P789

0

0

0

0

0

0

0

0

0

0

0

0

HY/2009/15 & HY/2010/08

C7

0

0

0

0

0

0

0

0

0

0

0

0

Total

0

0

0

0

0

0

2

0

0

0

0

0

Remarks: -     The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

         -   WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.

-   4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.

-   C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.

-       C8 & C9 was temporary suspended on 30 March 2013 due to the marine works for Contract no. HY/2009/19 had been completed on 4 March 2013

-   WSD7 and WSD20 water quality monitoring were temporarily suspended from 27 Apr 2012.

-      C2, C3 C4e and C4w water quality monitoring station was temporarily suspended since 24 Apr 2013

-       C5e and C5w water quality monitoring station was temporarily suspended since 29 July 2013

-       WSD21 water quality monitoring station was temporarily suspended since 12 March 2014

-       Maintenance responsibility of silt screen C1, WSD19, P3, P4 and P5 are under Contract HK/2009/01.

  1. Investigation found that the exceedances were not project-related. The details of the recorded exceedances can be referred to the Section 6.4.
  2. Enhanced DO monitoring at 4 monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table II.

 

Table II   Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

DO

AL

LL

AL

LL

HY/2009/15

C6

0

0

0

0

C7

0

0

0

0

Ex-WPCWA SW

0

4

0

2

Ex-WPCWA SE

0

4

0

2

Total

0

8

0

4

 

  1. There were no action level exceedances and 12 limit level exceedances of enhanced dissolved oxygen recorded in this reporting month. Investigation found that the exceedances are not related to the Project works. The details of the recorded exceedances can be referred to the Section 6.4.
  2. In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be installed to channel water discharge flow from Culvert L to locations outside the embayment area, a proposed replacement of the requirement with additional dissolved oxygen monitoring has been conducted at three monitoring stations, namely A, B and C between the eastern seawall of Central Reclamation Phase III and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level between the eastern seawall of Central Reclamation Phase II and the HKCEC extension could be continuously monitored.
  3. With respect to the commencement of dredging works under HK/2012/08 and the installation of MTR precast protection unit, the enhanced water quality monitoring for Culvert L was temporarily suspended since 24 July 2013.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. There was one environmental complaint received in this reporting month.

 

  1. A public complaint regarding water quality impact referred by WDII RSS team was received by ET on 12 June 2014. Notification letter from EPD on the captioned case was subsequently received by ET on 13 June 2014. The complainant reported that a large piece of muddy water was found on the waterfront outside the Hong Kong Academy for Performing Arts Theatre Block on 12 June 2014 morning.

 

  1. ET confirmed with the Resident Site Staff that neither marine construction works nor barge operation was conducted at the concerned location during the time of complaint. Nevertheless, with the respect to the EPD complaint case and the email notification issued by the Environmental team to contractor on 12 June 2014 morning, muddy dispersion was observe at HKCEC2W works area and the dispersion was observed partly extended beyond the outermost layer silt curtain at 1000hrs and contractor¡¦s immediate follow up action was requested.

 

  1. Mitigation measures implemented by the Contractor for the above construction works include the deployment of double layer of silt curtain for marine filling works area at HKCEC2W, additional silt curtain at marine access between caisson seawall on 12 June 2014, and regular diver checking on the silt curtain deployed at the location. It is considered that Contractor¡¦s mitigation measures for safeguarding the water quality during marine filling works at the concerned location implemented would require further review on the effectiveness to avoid seepage of muddy dispersion.

 

  1. Follow-up inspection was further conducted on 16 June 2014 and in addition, diver inspection check on the silt curtain deployed was conducted by the Contractor on 14 June 2014 to confirm the integrity of silt curtain.

 

  1. The Contractors¡¦ investigation report on the complaint case was submitted to EPD via email on 18 June 2014, and the interim report was submitted to EPD on 20 June 2014.

 

  1. The details of cumulative complaint log and updated summary of complaints are presented in Appendix 9.1

 

 

Site Inspections and Audit

  1. The Environmental Team (ET) conducted weekly site inspections for Contract nos. HK/2009/01, HK/2009/02, HY/2009/15 HK/2010/06, HY/2009/19, HK/2012/08 and HY/2010/08 under EP no. EP-356/2009 in the reporting month. Major observations and recommendations made during the audit sessions were rectified by the Contractors. No non-conformance was identified during the site inspections.

 

 

Future Key Issues

  1. In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

Ÿ   Tunnel structure work

Ÿ   Construction of D-wall

Ÿ   Installation of pre-bored H-piles

Ÿ   Discharge cooling mainlaying works for BI, BG & BF

Ÿ   Sewer works at Fenwick Pier Street

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East

¡P          Completion of Cooling Water Pumping Station (P7, P8, P9)

¡P          Road works on Hung Hing Road

¡P          Completion of ABWF works at WSD Salt Water Pumping Station

¡P          Backfilling works for Tunnel Portion 1

¡P          Completion of all plumbing system

¡P          Completion of ABWF works at Ferry Pier

¡P          Completion of testing and commissioning of movable ramps and disable life

¡P          Installation of seating base plates, steel frames and roof canopy

¡P          Completion of capping beam construction at Tunnel Portion 2

¡P          Completion of reclamation at WCR2

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

¡P          EVA construction at Eastern Breakwater

¡P          Reinstatement of Eastern Breakwater

¡P          Removal of Seawall Blocks at TS2, TPCWAE & TS4

¡P          Demolition of D-Wall at TS2, TPCWAE &TS4

¡P          Maintenance Dredging

 

Contract no. HK/2010/06 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line

¡P          Nil

 

Contract no. HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

¡P            Road works at Watson Road

¡P            Bored piling (Land)

¡P            Removal/ Installation of strut at ELS

¡P            Construction of Dolphin Cap

¡P            ELS for Cut &Cover Tunnel and EVB

¡P            Laying of 1500f pipe

¡P            Launching of segments

¡P            Extraction of temporary pile from marine section

¡P            Construction of bridge TA1

¡P            Pre-bored H-pile for Admin. Building continue

¡P            Parapet construction continue

¡P            Wing slab extension for segment continue

¡P            Construction of TD bridge continue

¡P            Construction of Bridge E

¡P            Construction of Bride F4 and F5

 

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

¡P          ELS for box culvert La at Lung King Street

¡P          Filling for seawall rock mound formation

¡P          Filling for reclamation

 

Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8)

¡P          Dredging works (works commence subject to handover from other Contract)

1      Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-05/356/2009, FEP-06/356/2009 and FEP-07/356/2009 to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works for Environmental Permit no. EP-356/2009, Further Environmental Permit no. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-05/356/2009, FEP-06/356/2009 and FEP-07/356/2009 during the period of May 2014 to June 2014. The cut-off date of reporting is at 27th of each reporting month.

 

1.2          Structure of the Report

 

Section 1        Introduction ¡V details the scope and structure of the report.

 

Section 2        Project Background ¡V summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3        Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4        Monitoring Requirements ¡V summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5        Monitoring Results ¡V summarizes the monitoring results obtained in the reporting period.

 

Section 6        Compliance Audit ¡V summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7        Cumulative Construction Impact due to the Concurrent Projects ¡V summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8        Site Inspection ¡V summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9        Complaints, Notification of summons and Prosecution ¡V summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10       Conclusion

2      Project Background

2.1          Background

2.1.1.     ¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called ¡§the Project¡¨) are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2          Scope of the Project and Site Description

2.2.1.     The Project is located mainly in Wan Chai North, Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road Interchange to the east, as shown in Figure 2.1.

2.2.2.     The study area encompasses existing developments along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police Officers¡¦ Club, the Causeway Bay Typhoon Shelter (CBTS) and commercial and residential developments.

2.2.3.     The scope of the Project comprises:

¡P          Land formation for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for connection to the Trunk Road and for through traffic from Central to Wan Chai and Causeway Bay. The land formed for the above transport infrastructure will provide opportunities for the development of an attractive waterfront promenade for the enjoyment of the public

¡P          Reprovisioning / protection of the existing facilities and structures affected by the land formation works mentioned above

¡P          Extension, modification, reprovisioning or protection of existing storm water drainage outfalls, sewerage outfalls and watermains affected by the revised land use and land formation works mentioned above

¡P          Upgrading of hinterland storm water drainage system and sewerage system, which would be rendered insufficient by the land formation works mentioned above

¡P          Provision of the ground level roads, flyovers, footbridges, necessary transport facilities and the associated utility services

¡P          Construction of the new waterfront promenade, landscape works and the associated utility services

¡P          The Trunk Road (i.e. CWB) within the study area and the associated slip roads for connection to the Trunk Road.

 

2.2.4.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (Eps) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1      Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3          Division of the Project Responsibility

2.3.1.     Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced. Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits (FEP) such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.     The details of individual contracts are summarized in Table 2.2.

 

 

 

Table 2.2 Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HK/2009/01

Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at Hong Kong Convention and Exhibition Centre

DP3, DP6

23 July 2010

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

DP3, DP5

5 July 2010

DP1

26 April 2011

HY/2009/11

Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North Point Reclamation

DP3

17 March 2010

(Completed)

HY/2009/15

Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

DP3

10 November 2010

DP1

13 July 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

(Completed)

HY/2009/17

Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works.

DP1

5 October 2010

(Completed)

HY/2009/18

Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange

DP1

21 April 2011

HY/2009/19

Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

HK/2012/08

Wan Chai Development Phase II Central-

Wan Chai Bypass at Wan Chai

West

DP1,DP2, DP3

5 March 2013

HY/2010/08

Central- Wanchai Bypass Tunnel ¡V Tunnel (Slip Road 8)

DP1, DP2, DP3

21 March 2013

 

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are summarized in Table 2.3:

 

 

 

 

 

Table 2.3 Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer¡¦s Representative for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer¡¦s Representative for CWB

Principal Resident Engineer

Mr. Peter Poon

3912 3388

3912 3010

Chun Wo ¡V Leader Joint Venture

Contractor under Contract no. HK/2009/01

Joint Venture Board Representative

Mr. Simon Liu

9304 8355

2587 1878

Deputy Site Agent

Mr Andy Yu

9648 4896

Construction Manager

Mr Terry Wong

9757 9846

Construction Manager

Mr. Wyman Wong

9627 2467

Construction Manager

Mr Kenneth Chan

9160 3850

Assistant Environmental Engineer

Miss. Connie Chan

6157 7057

Environmental Supervisor

Stanley Chan

9047 6148

Chun Wo ¡V CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Project Manager

Mr. Alfred Leung

3658-3022

2827 9996

Quality & Environmental Manager

Mr. C.P. Ho

9191 8856

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

K C Cheung

3557 6399

2566 2192

 

Site Manager

J H Chen

3557 6368

 

 

Contractor¡¦s Representative

Andrew Wong

3557 6358

 

 

Head of Construction

Manager

Roger Cheung

3557 6371

 

 

Senior Construction Manager

Gene Cheung

3557 6395

 

 

Environmental Officer

Andy Mak

3557 6347

Gammon

-Leader JV

Contractor under Contract no. HK/2010/06

Project Manager

Mr. Paul Lui

9095 7922

2529 2880

Site Agent

Mr. Eric Yip

2529 2068

Environmental Officer

Clement Pang

9735 9200

Environmental Supervisor

Jacky Cheung

9779 2292

Chun Wo ¡V CRGL ¡V MBEC Joint Venture

 

Contractor under Contract no. HY/2009/19

 

Project Manager

Mr. Rayland Lee

3758 8879

 

Site Agent

Mr. Eric Yip

252902068

Environmental Engineer

Mr. Calvin Leung

9286 9208

Environmental Manager /

Environmental Officer

Mr. M.H. Isa

9884 0810

Construction Manager (Marine)

William Luk

9610 1101

Construction Manager

(Land)

Patrick Cheung

9643 3012

Construction Manager

(Land)

Eric Fong

6191 9337

Operation Manager (Land)

Yung Kwok Wah

9834 1010

China State-

Leader JV

Contractor

under Contract

no. HK/2012/08

Project Director

Andrew Tse

9137 1811

2877 1522

Project Manager

Victor Wu

9193 8871

Deputy Project Manager

George Cheung

9268 1918

Site Agent

Paul Lui

9095 7922

Environmental Officer

James Ma

9130 9549

Environmental Supervisor

Ching Man, Chan

6050 4919

China State

 

Contractor

under Contract

no. HY/2010/08

Project Director

Cheung Kit Cheung

3557 6399

2566 8061

 

 

 

Project Manager

Chan Ying Lun

9812 0592

 

 

Deputy Project Manager

Chris Leung

3467 4299

 

 

Site Agent

Dave Chan

3467 4277

 

 

Environmental Officer

C.M. Wong

3557 6464

 

 

Environmental Supervisor

Louis Lam Tsz Kwan

3557 6470

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3465 2888

3465 2899

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

 

 

2.4.3.     For Contract no. HK/2009/01, the principal work activities in this reporting month included:

Ÿ   Ongoing demolition work of the exiting Expo Drive East Bridge

Ÿ   Ongoing work on UU diversion at Expo Drive East Bridge

Ÿ   Ongoing structure works for Stage 1 tunnel

Ÿ   Ongoing Stage 2 excavation

Ÿ   Installation of pre-bored H-piles at HKCEC water channel

Ÿ   Construction of D-wall

Ÿ   Ongoing mainlaying work on discharge cooling and saltwater

Ÿ   Ongoing rectification work

Ÿ   Demolition work of exiting HKCEC pump house

 

2.4.4.     For Contract no. HK/2009/02, the principal work activities in this reporting month included:

¡P          Road works between Expo Drive and Expo Drive East

¡P          Backfilling work

¡P          Installation and testing of AVR

¡P          Defect rectification works in WSD Salt Water Pumping Station

¡P          ABWF Works( Completion of fender system panels installation)

¡P          E&M Works for instance fire services ducting and cabling works

¡P          VSD installation and testing of movable ramp and life cage

¡P          Ongoing capping beam construction

¡P          Removal of marine mud at WCR2

¡P          Erection of Bridge 3

¡P          Modification of D-Wall for Bridge 2

¡P          Delivery of fabricated temp bridges

 

2.4.5.     For Contract no. HY/2009/15, the principal work activities in this reporting month included:

Ÿ   EVA construction at Eastern Breakwater

Ÿ   Reinstatement of Eastern Breakwater     

Ÿ   Removal of Seawall Blocks at TS2, TPCWAE & TS4

Ÿ   Demolition of D-Wall at TS2, TPCWAE & TS4

Ÿ   Maintenance dredging

 

2.4.6.     For Contract no. HK/2010/06, no principal work activities in this reporting month.

2.4.7.     For Contract no. HY/2009/19, the principal work activity in this reporting month included:

Ÿ   Road works at Watson Road

Ÿ   Bored piling (Land)

Ÿ   Removal/Installation of strut at ELS

Ÿ   Construction of Dolphin Cap

Ÿ   ELS for Cut &Cover Tunnel and EVB

Ÿ   Laying of 1500f pipe

Ÿ   Launching of segments

Ÿ   Extraction of temporary pile from marine section

Ÿ   Construction of bridge TA1

Ÿ   Pre-bored H-pile for Admin. Building continue

Ÿ   U-beam installation continue

Ÿ   Parapet construction continue

Ÿ   Wing slab extension for segment continue

Ÿ   Construction of TD bridge continue

Ÿ   Construction of Bridge E

Ÿ   Construction of Bride F4 and F5

2.4.8.         For Contract no. HK/2012/08, the principal work activity in this reporting month included:

¡P          ELS for box culvert La at Lung King Street

¡P          Filling for seawall rock mound formation

¡P          Filling for reclamation

¡P          Dredging

 

2.4.9.     For Contract no. HY/2010/08, no principal work activities this reporting month.

¡P       Rock filling works (works cease on 8th Feb. 2014)

¡P          No dredging works carried out in reporting period.

 

 

2.4.10.   In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

Ÿ   Tunnel structure work

Ÿ   Construction of D-wall

Ÿ   Installation of pre-bored H-piles

Ÿ   Discharge cooling mainlaying works for BI, BG & BF

Ÿ   Sewer works at Fenwick Pier Street

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East

¡P          Completion of Cooling Water Pumping Station (P7, P8, P9)

¡P          Road works on Hung Hing Road

¡P          Completion of ABWF works at WSD Salt Water Pumping Station

¡P          Backfilling works for Tunnel Portion 1

¡P          Completion of all plumbing system

¡P          Completion of ABWF works at Ferry Pier

¡P          Completion of testing and commissioning of movable ramps and disable life

¡P          Installation of seating base plates, steel frames and roof canopy

¡P          Completion of capping beam construction at Tunnel Portion 2

¡P          Completion of reclamation at WCR2

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

¡P          EVA construction at Eastern Breakwater

¡P          Reinstatement of Eastern Breakwater

¡P          Removal of Seawall Blocks at TS2, TPCWAE & TS4

¡P          Demolition of D-Wall at TS2, TPCWAE &TS4

¡P          Maintenance dredging

 

Contract no. HK/2010/06 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line

¡P          Nil

 

Contract no. HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

¡P            Road works at Watson Road

¡P            Bored piling (Land)

¡P            Removal/ Installation of strut at ELS

¡P            Construction of Dolphin Cap

¡P            ELS for Cut &Cover Tunnel and EVB

¡P            Laying of 1500f pipe

¡P            Launching of segments

¡P            Extraction of temporary pile from marine section

¡P            Construction of bridge TA1

¡P            Pre-bored H-pile for Admin. Building continue

¡P            Parapet construction continue

¡P            Wing slab extension for segment continue

¡P            Construction of TD bridge continue

¡P            Construction of Bridge E

¡P            Construction of Bride F4 and F5

 

 

 

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

¡P          ELS for box culvert La at Lung King Street

¡P          Filling for seawall rock mound formation

¡P          Filling for reclamation

 

Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8)

¡P          Dredging works (works commence subject to handover from other Contract)

3      Status of Regulatory Compliance

3.1          Status of Environmental Licensing and Permitting under the Project

3.1.1.     A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1 Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009/A

4 Aug 2010

Superseded

Environmental Permit

EP-364/2009/B

20 Sep 2012

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

Superseded

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Surrendered

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

22 Nov 2010

Valid

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 Jul 2010

Surrendered

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Surrendered

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/B

20 Sep 2012

Valid

Further Environmental Permit

FEP-08/364/2009/A

15 Jun 2012

Valid

Further Environmental Permit

FEP-06/356/2009

5 Mar 2013

Valid

Further Environmental Permit

FEP-07/356/2009

26 July 2013

Valid

Further Environmental Permit

FEP-10/364/2009/B

26 July 2013

Valid

 

3.1.2.     Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

3.1.3.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and Table 3.5.

Table 3.4 Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

N/A

Valid

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088      

06 Jan 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS1374-13

2 Dec 2013

3 Dec 2013 to   2 Jun 2014

Cancelled

 

GW-RS1433-13

20 Dec 2013

21 Dec 2013 to 20 Jun 2014

Expired

 

GW-RS1450-13

20 Dec 2013

22 Dec 2013 to 19 June 2014

Expired

 

GW-RS0111-14

11 Feb 2013

15 Feb 2014 to 14 August 2014

Valid

 

GW-RS0200-14

18 Mar 2014

21 Mar 2014 to

15 Sept 2014

Valid

 

GW-RS0317-14

7 Apr 2014

8 Apr 2014 to

7 Oct 2014

Valid

 

GW-RS0362-14

17 Apr 2014

20 Apr 2014 to 8 Oct 2014

Valid

 

GW-RS0381-14

8 Apr 2014

9 May 2014 to 11 Nov 2014

Valid

 

GW-RS0435-14

30 Apr 2014

13 May 2014 to 12 Nov 2014

 

Valid

 

GW-RS0437-14

7 May 2014

8 May 2014 to

7 Nov 2014

 

Valid

 

GW-RS0451-14

5 May 2014

12 May 2014 to 11 Nov 2014

 

Valid

 

GW-RS0462-14

17 Apr 2014

18 Apr 2014 to 17 Oct 2014

 

Valid

 

GW-RS0498-14

22 May 2014

24 May 2014 to 22 Nov 2014

 

Valid

Discharge Licence

 

WT00018110-2014

6 Jan 2014

31 Mar 2015

Valid

WT00006220-2010

18 Mar 2010

31 Mar 2015

Valid

 

WT00009641-2011

24 Jul 2011

31 Jul 2016

Valid

Billing account under Waste Disposal Ordinance

7010069

21 Jan 2010

N/A

 

Valid

Registration as a Chemical Waste Producer

WPN5213-134-C3585-01

21 Jan 2010

N/A

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal)

EP/MD/14-010

24 Apr 2014

01 Jun 2014 to

30 June 2014

Valid

 

Table 3.5 Summary of submission status under FEP-02/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

13 Apr 2010

Condition 2.7

Works Schedule and Location Plan

8 Apr 2010

Condition 2.8

Silt Curtain Deployment Plan (Rev. 5)

24 Aug 2012

Silt Curtain Deployment Plan (Rev. 4)

12 July 2012

Silt Curtain Deployment Plan (Rev. 3)

27 June 2012              

Silt Curtain Deployment Plan

19 Apr 2010

Condition 2.9

Silt Screen Deployment Plan (Rev.5)

24 Jul 2013

Silt Screen Deployment Plan (Rev.4)

15 Nov 2012

Silt Screen Deployment Plan

19 Apr 2010

Conditions 2.8 and 2.9

Supplementary Document on Silt Curtain and Silt Screen Deployment Plan

19 Jul 2010

Report on Field Testing for Silt Curtain

26 Aug 2010

Report on Field Testing for Silt Curtain (Rev. A)

15 Nov 2010

Condition 2.12(d)

Alternative Proposal on Concurrent Dredging for Sewage Pipeline and Cross Harbour Water Mains

15 Apr 2011

Condition 2.17

Noise Management Plan

23 Apr 2010

Condition 2.18

Landscape Plan (Erection of Decorative Screen Hoarding along Construction Site around Hong Kong Exhibition and Convention Centre)

15 May 2010

 

Landscape Plan (Night-time Lighting)

22 Oct 2010

 

Landscape Plan (Rev. B)

15 Nov 2010

Condition 1.12

Notification of Commencement Date

20 Jun 2011

Condition 2.6 to 2.8

Management Organization, Works Schedule and Location Plan

18 May 2011

Condition 2.9

Silt Screen Deployment Plan

10 Jun 2011

Condition 2.18

Landscape Plan

31 Oct 2013

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

3.1.4.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HK/2009/02 under FEP-03/356/2009 are shown in Table 3.6 and Table 3.7.

Table 3.6 Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

N/A

Valid

 

FEP-01/364/2009

24 Mar 2010

N/A

Valid

Notification of Works Under APCO

313962

2 Feb 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS1466-13

24 Dec 2013

17 Jan 2014 to 16 July 2014

Valid

GW-RS1458-13

24 Dec 2013

2 Jan 2014 to 1 July 2014

Valid

GW-RS0067-14

29 Jan 2014

15 Feb 2014 to 14 Aug 2014

Valid

GW-RS0112-14

13 Jan 2014

16 Feb 2014 to 13 Aug 2014

Valid

GW-RS0161-14

7/3/2014

11 Mar 2014 to 10 Sep 2014

Valid

GW-RS0162-14

7/3/2014

20 Mar 2014 to 19 Sep 2014

Valid

GW-RS0233-14

21/3/2014

25 Mar 2014 to 24 Sep 2014

Valid

GW-RS0269-14

28/3/2014

7 Apr 2014 to 6 Oct 2014

Valid

GW-RS0319-14

7/4/2014

18 Apr 2014 to 17 Oct 2014

Valid

 

 

 

 

 

 

 

 

 

 

 

 

GW-RS0407-14

25/4/2014

28 Apr 2014 to 16 Oct 2014

Valid

GW-RS0421-14

30/4/2014

30 Apr 2014 to 15 Oct 2014

Valid

GW-RS0460-14

9/5/2014

10 May 2014 to 9 Nov 2014

Valid

GW-RS0491-14

16/5/2014

17 May 2014 to 16 Nov 2014

Valid

GW-RS0494-14

16/5/2014

22 May 2014 to 21 Nov 2014

Valid

GW-RS0482-14

13/5/2014

14 May 2014 to 6 Nov 2014

Valid

GW-RS0461-14

9/5/2014

10 May 2014 to 9 Nov 2014

Valid

GW-RS0422-14

30/4/2014

2 May 2014 to 16 Oct 2014

Valid

GW-RS0515-14

26/5/2014

29 May 2014 to 25 Nov 2014

Valid

GW-RE0565-14

30/5/2014

30/5/2014 to 29/11/2014

Valid

GW-RS0637-14

26/6/2014

2/7/2014 to 25/11/2014

Valid

Discharge Licence

WT00006249-2010

22 Mar 2010

31 Mar 2015

Valid

WT00006436-2010

15 Apr 2010

30 Apr 2015

Valid

WT00006673-2010

14 May 2010

31 Mar 2015

Cancelled

WT00006757-2010

28 May 2010

31 May 2015

Valid

WT00007129-2010

28 July 2010

31 Jul 2015

Valid

WT00008982-2011

26 Apr 2011

30 April 2016

Valid

WT00009691-2011

1 Aug 2011

31 July 2016

Valid

Billing Account under Waste Disposal Ordinance (Land)

7010255

10 Feb 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance (Marine)

7011496

6 Oct 2010

N/A

Valid

Registration as Chemical Waste Producer (Wan Chai)

WPN5213-135-C3593-01

10 Mar 2010

N/A

Valid

Registration as Chemical Waste Producer (TKO 137)

WPN5213-839-C3593-02

22 Sep 2010

N/A

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal)

EP/MD/14-098

26 Nov 2013

29 Nov 2013 to 28 May 2014

Expired

 

EP/MD/15-027

21 May 2014

29 May 2014 to 30 Jun 2014

Valid

Dumping Permit (Type 2 ¡V Confined Marine Disposal)

EP/MD/15-023

15 May 2014

20 May 2014 to 19 Jun 2014

Expired

 

 

 

 

 

Table 3.7 Summary of submission status under FEP-03/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 1.12

Commencement Date of Construction of Marine Works

8 April 2010

Condition 2.6

Management Organization of Main Construction Companies

10 April 2010

Condition 2.7

Works Schedule and Location Plans

8 April 2010

Condition 2.8

Silt Curtain Deployment Plan (Revision A)

20 April 2010

Silt Curtain Deployment Plan (Revision B)

25 May 2010

Silt Curtain Deployment Plan (Revision C)

14 Jun 2010

Silt Curtain Deployment Plan (Revision H)

15 Feb 2011

Silt Curtain Deployment Plan (Revision I)

17 Nov 2011

Silt Curtain Deployment Plan (Revision J)

15 Feb 2012

Silt Curtain Deployment Plan (Revision K)

3 May 2012

Silt Curtain Deployment Plan (Revision L)

25 Oct 2012

Silt Curtain Deployment Plan (Revision M)

30 Nov 2012

 Condition 2.9

Silt Screen Deployment Plan

21 April 2010

Supplementary Information for Existing WSD Salt Water Intakes at Quarry Bay and Sai Wan Ho

5 Oct 2010

Silt Screen Deployment Plan (Revision B)

15 Feb 2012

Silt Screen Deployment Plan (Revision C)

3 May 2012

Silt Screen Deployment Plan (Revision D)

10 Dec 2012

Condition 2.17

Noise Management Plan

6 May 2010

Condition 2.18

Landscape Plan (Decorative Screen Hoarding)

11 May 2010

Landscape Plan (Control of Night Time Lighting)

2 June 2010

Landscape Plan (Combined Version)

20 July 2011

Landscape Plan (Combined Version)

5 Aug 2011

-----

Acknowledge of Submission

22 Aug 2011

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

3.1.5.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HY/2009/15 under EP-356/2009 are shown in Table 3.8 and Table 3.9.

Table 3.8 Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-04/356/2009

22 Nov 2010

N/A

Valid

Notification of Works Under APCO

321822

24 Sep 2010

N/A

Valid

Construction Noise Permit (CNP) for concreting works at Eastern Breakwater of CBTS

GW-RS0095-14

10 Feb 2014

19 Feb 2014 to 18 Aug 2014

Valid

Construction Noise Permit (CNP) for Pre-treatment, ELS and rock breaking works at TS4/ME4

GW-RS1437-13

17 Dec 2013

31 Dec 2013 to 30 Jun 2014

Valid

Construction Noise Permit (CNP) for maintenance dredging

GW-RS0368-14

22 Apr 2014

1 May 2014 to 31 Oct 2014

Valid

Construction Noise Permit (CNP) for P3 Mooring

GW-RS0191-14

12 Mar 2014

12 Mar 2014 to 11 Sep 2014

Valid

Registration as a Chemical Waste Producer

WPN5213-147-C1169-35

15 Nov 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7011553

30 Sep 2010

27 Sep 2010 to 27 Jan 2016

Valid

Billing Account under Waste Disposal Ordinance (Dumping by Vessel)

7011761

27 Dec 2013

17 Apr 2014 to 16 Jul 2014

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal)

EP/MD/14-122

23 Jan 2014

24 Jan 2014 to 23 Jul 2014

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal) P3 Mooring

EP/MD/14-123

21 Jan 2014

23 Jan 2014 to 22 Jul 2014

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal(Dedicated Site) and Type 2 ¡V Confined Marine Disposal)

EP/MD/15-018

8 May 2014

11 May 2014 to 10 Jun 2014

Expired

 

EP/MD/15-032

11 Jun 2014

13 Jun 2014 to 12 Jul 2014

Valid

Dumping Permit (Type 3 ¡V Special Treatment/Disposal contained in Geosynthetic Containers)

EP/MD/15-019

14 May 2014

15 May 2014 to 14 Jun 2014

Expired

 

EP/MD/15-031

11 Jun 2014

15 Jun 2014 to 14 Jul 2014

Valid

 

Table 3.9 Summary of submission status under FEP-04/356/2009 Condition

 

FEP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

30 Sep 2010

Amendment for Management Organization of Main Construction Companies

16 May 2011

Condition 2.7

Works Schedule and Location Plans

27 Oct 2010

 

Amendment for Works Schedule and Location Plans

12 Nov 2010

Condition 2.8

Silt Curtain Deployment Plan

30 Nov 2010

 

Amendment for Silt Curtain Deployment Plan

24 Feb 2011

Amendment for Silt Curtain Deployment Plan

11 May 2011

Amendment for Silt Curtain Deployment Plan

11 Sep 2012

Amendment for Silt Curtain Deployment Plan

30 Oct 2012

Condition 2.9

Silt Screen Deployment Plan

19 Oct 2010

Amendment for Silt Screen Deployment Plan

18 Feb 2011

Amendment for Silt Screen Deployment Plan

15 Jun 2011

Condition 2.18

Proposal for the Removal of Odorous Sediment and Slime

13 Jan 2011

Amendment for Proposal for the Removal of Odorous Sediment and Slime

8 Mar 2011

 

Amendment for Proposal for the Removal of Odorous Sediment and Slime

2 Aug 2011

Condition 2.21

Landscape Plan

18 Feb 2011

Condition 2.20

Noise Management Plan

20 Oct 2010

Amendment for Noise Management Plan

27 Jan 2011

 

3.1.6.     Implementation status of the recommended mitigation measures during this reporting period is presented in Appendix 3.1.

 

Contract no. HK/2010/06 ¡V Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line

3.1.7.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HK/2010/06 under EP-356/2009 is shown in Table 3.10 and Table 3.11.

Table 3.10     Cumulative Summary of Valid Licences and Permits under Contract no. HK/2010/06

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

N/A

Valid

FEP-08/364//2009/A

15 June 2012

N/A

Valid

Notification of Works Under APCO

326344

18 Jan 2011

N/A

Valid

Construction Noise Permit (CNP) for piling equipment

PP-RS0030-13

19 Dec 2013

6 Jan 14 ¡V 5 Jul 14

Valid

Billing Account under Waste Disposal Ordinance

7012338

16 Feb 2011

N/A

Valid

 

Table 3.11     Summary of submission status under EP-356/2009 and FEP-05/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 2.23

Noise Management Plan

11 March 2011

Condition 2.6

Management Organization of Main Construction Companies

29 April 2013

Condition 2.7

Works Schedule and Location Plans

11 March 2011

Condition 2.8

Revised Silt Curtain Deployment Plan

31 August 2011

Revised Silt Curtain Deployment Plan

22 October 2012

Revised Silt Curtain Deployment Plan

26 November 2012

Revised Silt Curtain Deployment Plan

28 January 2013

Condition 2.9

Silt Screen Deployment Plan

11 April 2011

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

3.1.8.     Summary of the current status on licences and/or permits on environmental protection pertinent for contract no. HY/2009/19 is shown in Table 3.12.

Table 3.12     Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Permit / Licence / Notification / Approval

Reference No.

Issued Date

Valid Period / Expiry date

Status

Further Environmental Permit

FEP-07/364/2009/B

20 Sep 2012

Granted

Valid

Notification of Works Under APCO

326160

24 Jan 2011

Notified

Valid

Construction Noise Permit (CNP) (For D-wall construction) (Portion I, VII, VIII & IX)

GW-RS1473-13

29-Dec-13

23-Jun-14

Cancelled

 

GW-RS0152-14

06-Mar-14

27-Aug-14

Valid

Construction Noise Permit (CNP) (For Segment Launching at Portion III)

GW-RS1474-13

29-Dec-13

23-Jun-13

Cancelled

 

GW-RS0072-14

06-Feb-14

02-Aug-14

Cancelled

 

GW-RS0506-14

23-May-14

14-Nov-14

Valid

Construction Noise Permit (CNP) (For Portion Vi Marine)

GW-RS10073-14

06-Feb-14

02-Aug-14

Cancelled

 

GW-RS0507-14

23-May-14

14-Nov-14

Valid

Discharge Licence (Land)

WT00010093-2011

17 Aug 2012

30-Sept-16

Valid

Discharge Licence (Sea)

WT00010865-2011

03 Nov 2011

30-Nov-16

Valid

C&D Waste Disposal

7012306

10 Feb 2011

Registered

-

Vessel Disposal

7013285

21 July 2011

Registered

-

Registration as Chemical Waste Producer

5213-151-C3654-01

24 Mar 2011

Registered

-

Dumping Permit (Tunnel) (Type 1 ¡V Open Sea Disposal)

EP/MD/14-104

10 Dec 2013

09 Jun 2013

Expired

 

EP/MD/14-128

30 Jan 2014

30 Jun 2014

Valid

 

EP/MD/15-035

18 Jun 2014

17 Dec 2014

Valid

Dumping Permit (Tunnel) (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal)

EP/MD/15-022

20 May 2014

19 Jun 2014

Expired

 

EP/MD/15-036

20 Jun 2014

19 Jul 2014

Valid

 

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

3.1.9.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HK/2012/08 under EP-356/2009 are shown in Table 3.13 and Table 3.14.

Table 3.13     Cumulative Summary of Valid Licences and Permits under Contract no. HK/2012/08

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-06/356/2009

5 Mar 2013

N/A

Valid

Notification of Works Under APCO

355439

4 Feb 2013

N/A

Valid

Registration as a Chemical Waste Producer

5213-134-C3790-01

8 Mar 2013

N/A

Valid

Billing Account under Waste Disposal Ordinance

7016883

18 Feb 2013

18 Jul 2017

Valid

Water Discharge Licence

WT00018223-2014

28 Jan 2014

31 Jan 2019

Valid

Construction Noise Permit

GW-RS1477-13

2 Jan 2014

3 Jan 2014 to 2 Jul 2014

Cancelled

 

GW-RS0232-14

21 Mar 2014

23 Mar 2014 to 20 Sep 2014

Valid

 

GW-RS1357-13

2 Dec 2013

4 Dec 2013 to 1 Jun 2014

Cancelled

 

GW-RS0257-14

26 Mar 2014

28 Mar 2014 to 25 Sep 2014

Valid

 

GW-RS0193-14

13 Mar 2014

27 Mar 2014 to 26 Sep 2014

Valid

 

GW-RS0293-14

1 Apr 2014

1 Apr 2014 to 30 Sep 2014

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal)

EP/MD/14-111

1 Jan 2014

30 Jun 2014

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine disposal)

EP/MD/15-025

20 May 2014

24 Jun 2014

Expired

 

EP/MD/15-040

20 Jun 2014

24 Jul 2014

Valid

 

Table 3.14     Summary of submission status under EP-356/2009 and FEP-06/356/2009 Condition

FEP Condition

Submission

Date of Submission

Condition 2.8

Silt Curtain Deployment Plan (Rev. 3)

Submitted on 25 Nov 2013 was returned to CSLJV by EPD.

Condition 2.9

Silt Screen Deployment Plan (Rev. 2)

Generally in order as commented by EPD on 19 Sep 2013

Condition 2.23

Noise Management Plan (Rev. 2)

Generally in order as commented by EPD on 15 Aug 2013

Condition 2.24

Landscape Plan (Rev. 3)

Generally in order as commented by EPD on 31 Oct 2013

 

Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8)

3.1.10.   Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HY/2010/08 under EP-356/2009 are shown in Table 3.15 and Table 3.16.

Table 3.15     Cumulative Summary of Valid Licences and Permits under Contract no. HY/2010/08

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-07/356/2009

26 Jul 2013

NA

Valid

 

FEP-10/364/2009/B

26 Jul 2013

NA

Valid

Notification of Works Under APCO

357176

2 Apr 2013

NIL

Valid

Registration as a Chemical Waste Producer

WPN5213-147-C1169-44

27 Mar 2013

NIL

Valid

Billing Account under Waste Disposal Ordinance

7017170

27 Mar 2013

NIL

Valid

Water Discharge Licence

WT00016561-2013

9 Jul 2013

31 Jul 2018

Valid*

Dumping Permit (Type 1 ¡V Open Sea Disposal)

EP/MD/14-095

29 Nov 2013

1 Jun 2014

Expired

 

EP/MD/15-033

9 Jun 2014

9 Dec 2014

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine disposal)

EP/MD/15-020

13 May 2014

16 Jun 2014

Expired

 

EP/MD/15-034

11 June 2014

14 Jul 2014

Valid

 

Table 3.16     Summary of submission status under EP-356/2009 and FEP-07/356/2009 Condition

FEP Condition

Submission

Date of Submission

Condition 2.8

Silt Curtain Deployment Plan

28 Nov 2013

Condition 2.9

Silt Screen Deployment Plan

29 Nov 2013

Condition 2.23

Noise Management Plan (rev02)

25 Mar 2014

Condition 2.24

Landscape Plan (rev02)

25 Mar 2014

Monitoring Requirements

4.1          Noise Monitoring

Noise Monitoring Stations

4.1.1.     The noise monitoring stations for the Project are listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.1 Noise Monitoring Station

Station

Description

M1a

Harbour Road Sports Centre

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

 

Real-time Noise Monitoring Stations

4.1.2.     The real-time noise monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

4.1.3.     The real-time noise monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct 2012, which is a representative of noise sensitive receiver- City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.

4.1.4.     As the land-based piling and filling works- DP3 at Tin Hau had been completed on 3 September 2012 and confirmed by RSS, the real-time noise monitoring results at FEHD Hong Kong Transport Section Whitfield Depot was excluded under EP-356/2009 since 28 November 2012.

Table 4.2 Real Time Noise Monitoring Station

District

Station

Description

Tin Hau

RTN1

FEHD Hong Kong Transport Section Whitfield Depot

North Point

RTN2

Oil Street Community Liaison Centre

North Point

RTN2a

Electric Centre

l   Real time noise monitoring results and graphical presentation during night time period are for information only.

l   RTN2 had been relocated to RTN2a since 5 Oct 2012

l   RTN1 monitoring had been finished on 28 Nov 2012

 

Noise Monitoring Parameters, Frequency and Duration

4.1.5.     The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

4.1.6.     Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

¡P          One set of measurements between 0700 and 1900 hours on normal weekdays.

4.1.7.     If construction works are extended to include works during the hours of 1900 ¡V 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

Monitoring Equipment

4.1.8.     As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

4.1.9.     Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

 

4.2          Air Monitoring

Air Quality Monitoring Stations

4.2.1.     The air monitoring stations for the Project are listed and shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.3 Air Monitoring Station

Station ID

Monitoring Location

Description

CMA1b

Oil Street Community Liaison Centre

North Point

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

CWB PRE Site Office *

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5a

Children Playgrounds opposite to Pedestrian Plaza

Wan Chai

CMA6a

WDII PRE Site Office *

Wan Chai

Remarks: As per the ENPC meeting in January 2011, the monitoring stations CMA3a ¡V Future CWB site office at Wanchai Waterfront Promenade and CMA6a ¡V Future AECOM site office at Work Area were renamed as remark.

 

Air Monitoring Parameters, Frequency and Duration

4.2.2.     One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

4.2.3.     All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

4.2.4.     For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.

Sampling Procedure and Monitoring Equipment

4.2.5.     High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

¡P          0.6 ¡V 1.7 m3 per minute adjustable flow range;

¡P          equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

¡P          installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

¡P          capable of providing a minimum exposed area of 406 cm2;

¡P          flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

¡P          equipped with a shelter to protect the filter and sampler;

¡P          incorporated with an electronic mass flow rate controller or other equivalent devices;

¡P          equipped with a flow recorder for continuous monitoring;

¡P          provided with a peaked roof inlet;

¡P          incorporated with a manometer;

¡P          able to hold and seal the filter paper to the sampler housing at horizontal position;

¡P          easily changeable filter; and

¡P          capable of operating continuously for a 24-hour period.

 

4.2.6.     Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

 

 

Laboratory Measurement / Analysis

4.2.7.     A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

4.2.8.     An alternative non-HOKLAS accredited laboratory was set-up for carrying out the laboratory analysis, the laboratory equipment was approved by the ER on 8 February 2011 and the measurement procedures were witnessed by the IEC. Any measurement performed by the laboratory was be demonstrated to the satisfaction of the ER and IEC. IEC shall regularly audit to the measurement performed by the laboratory to ensure the accuracy of measurement results.

4.2.9.     Filter paper of size 8¡¨ x 10¡¨ shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

4.2.10.   After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

4.2.11.   All the collected samples shall be kept in a good condition for 6 months before disposal.

impact monitoring for odour patrol

4.2.12.   Odour patrols along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai Public Cargo Working Area when there is temporary reclamation in Causeway Bay Typhoon Shelter and/or in the ex-Wan Chai Public Cargo Working Area, or when there is dredging of the odorous sediment and slime at the south-western corner of the Causeway Bay Typhoon Shelter. Odour patrols will be carried out at bi-weekly intervals during July, August and September by a qualified person of the ET who shall:

¡P          be at least 16 years of age;

¡P          be free from any respiratory illnesses; and

¡P          not be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30 min

¡P          before and during odour patrol

4.2.13.   Odour patrol shall be conducted by independent trained personnel / competent persons patrolling and sniffing around the shore as shown in Figure 4.1 to detect any odour at the concerned hours (afternoon is preferred for higher daily temperature).

4.2.14.   The qualified person will use the nose (olfactory sensor) to sniff odours at different locations. The main odour emission sources and the areas to be affected by the odour nuisance will be identified.

4.2.15.   The perceived odour intensity is to be divided into 5 levels which are ranked in the descending order as follows:

¡P          0 ¡V Not detected. No odour perceived or an odour so weak that it cannot be easily characterized or described;

¡P          1 ¡V Slight Identifiable odour, and slight chance to have odour nuisance;

¡P          2 ¡V Moderate Identifiable odour, and moderate chance to have odour nuisance;

¡P          3 ¡V Strong Identifiable, likely to have odour nuisance;

¡P          4 ¡V Extreme Severe odour, and unacceptable odour level.

 

4.2.16.   The findings including odour intensity, odour nature and possible odour sources, and also the local wind speed and direction at each location will be recorded. In addition, some relevant meteorological and tidal data such as daily average temperature, and daily average humidity, on that surveyed day will be obtained from the Hong Kong Observatory Station for reference. The Action and Limit levels for odour patrol are shown in Appendix 6.1.

4.2.17.   The qualified odour patrol member has individual n-butanol thresholds complied with the requirement of European Standard Method of Air Quality ¡V Determination of Odour Concentration by Dynamic Olfactometry (EN13725) in the range of 20 to 80 ppb.

4.3          Water Quality Monitoring

4.3.1.     The EIA Report has identified that the key water quality impact would be associated with the dredging works during the construction phase. Marine water quality monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is therefore recommended to be carried out at selected WSD flushing water intakes. The impact monitoring should be carried out during the proposed dredging works to ensure the compliance with the water quality standards.

4.3.2.     The updated EM&A Manual for EP-356/2009 (Version in March 2011) is approval by EPD on 29 April 2011. As such, the Action Level and Limit Level for the wet season (April ¡V September) will be effected and applied to the water quality monitoring data from 30 April 2011.

Water Quality Monitoring Stations

4.3.3.     It is proposed to monitor the water quality at 4 WSD salt water intakes and 8 cooling water intakes along the seafront of the Victoria Harbour. The proposed water quality monitoring stations of the Project are shown in Table 4.4 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.4      Marine Water Quality Stations for Water Quality Monitoring

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD9

Tai Wan

837921.0

818330.0

WSD17

Quarry Bay

839790.3

817032.2

WSD19

Sheung Wan

833415.0

816771.0

WSD21

Wan Chai

836220.8

815940.1

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

C7

Windsor House

837193.7

816150.0

P1

HKCEC Phase I

835774.7

816179.4

P3

The Academy of performing Arts

835824.6

816212.0

P4

Shui on Centre

835865.6

816220.0

P5

Government Buildings

(Wanchai Tower / Revenue Tower / Immigration Tower)

835895.2

816215.2

RW21-P789

Great Eagle Centre/ Sun Hung Kai Centre/CWB

836268.0

816020.0

 

Water Quality Parameters

4.3.4.     Monitoring of dissolved oxygen (DO), turbidity and suspended solids (SS) shall be carried out at WSD flushing water intakes and cooling water intakes. DO and Turbidity are measured in-situ while SS is determined in laboratory.

4.3.5.     In association with the water quality parameters, other relevant data shall also be measured, such as monitoring location/position, time, sampling depth, water temperature, pH, salinity, dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal stage, and any special phenomena and work underway at the construction site etc.

Sampling Procedures and Monitoring Equipment

4.3.6.     The interval between two sets of monitoring should not be less than 36 hours except where there are exceedances of Action and/or Limit Levels, in which case the monitoring frequency will be increased. Table 4.5 shows the proposed monitoring frequency and water quality parameters. Duplicate in-situ measurements and water sampling should be carried out in each sampling event. For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5m.

Table 4.5 Marine Water Quality Monitoring Frequency and Parameters

Activities

Monitoring Frequency1

Parameters2

During the 4-week baseline monitoring period

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

During marine construction works

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

After completion of marine construction works

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

Notes:

1.     For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5m.

2.     Turbidity should be measured in situ whereas SS should be determined by laboratory.

 

Dissolved Oxygen and Temperature Measuring Equipment

4.3.7.     The instrument should be a portable, weatherproof dissolved oxygen measuring instrument complete with cable, sensor, comprehensive operation manuals, and use a DC power source. It should be capable of measuring:

¡P          a dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation

¡P          a temperature of 0-45 degree Celsius

4.3.8.     It should have a membrane electrode with automatic temperature compensation complete with a cable. Sufficient stocks of spare electrodes and cables should be available for replacement where necessary. (e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).

4.3.9.     Should salinity compensation not be build-in in the DO equipment, in-situ salinity shall be measured to calibrate the DO equipment prior to each DO measurement.

Turbidity Measurement Instrument

4.3.10.   The instrument should be a portable, weatherproof turbidity-measuring instrument complete with comprehensive operation manual. The equipment should use a DC power source. It should have a photoelectric sensor capable of measuring turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model 2100P or an approved similar instrument).

Sampler

4.3.11.   A water sampler comprises a transparent PVC cylinder, with a capacity of not less than 2 litres, and can be effectively sealed with latex cups at both ends. The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (e.g. Kahlsico Water Sampler or an approved similar instrument).

Sample Container and Storage

4.3.12.   Water samples for suspended solids measurement should be collected in high-density polythene bottles, packed in ice (cooled to 4¢XC without being frozen), and delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection for analysis.

Water Depth Detector

4.3.13.   A portable, battery-operated echo sounder shall be used for the determination of water depth at each designated monitoring station. This unit can either be handheld or affixed to the bottom of the workboat, if the same vessel is to be used throughout the monitoring programme.

Salinity

4.3.14.   A portable salinometer capable of measuring salinity in the range of 0-40 ppt shall be provided for measuring salinity of the water at each of monitoring location.

Monitoring Position Equipment

4.3.15.   A hand-held or boat-fixed type digital Global Positioning System (GPS) with waypoint bearing indication or other equivalent instrument of similar accuracy shall be provided and used during monitoring to ensure the monitoring vessel is at the correct location before taking measurements.

Calibration of In-situ Instruments

4.3.16.   All in-situ monitoring instrument shall be checked, calibrated and certified by a laboratory accredited under HOKLAS or equivalent before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring. Responses of sensors and electrodes should be checked with certified standard solutions before each use. Wet bulb calibration for a DO meter shall be carried out before measurement at each monitoring location.

4.3.17.   For the on site calibration of field equipment by the ET, the BS 127:1993, "Guide to Field and on-site test methods for the analysis of waters" should be observed.

4.3.18.   Sufficient stocks of spare parts should be maintained for replacements when necessary. Backup monitoring equipment shall also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, etc.

4.3.19.   Current calibration certificates of equipments are presented in Appendix 4.2.

Laboratory Measurement / Analysis

4.3.20.   Analysis of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the monitoring stations for carrying out the laboratory SS determination. The SS determination work shall start within 24 hours after collection of the water samples. The SS determination shall follow APHA 19ed or equivalent methods subject to the approval of IEC and EPD.

Enhanced Water Quality Monitoring in the ex-Wan Chai Public Cargo

Working Area and the Causeway Bay Typhoon Shelter

4.3.21.   The enhanced water quality monitoring and audit programme is to avoid aggravation of odour nuisance from seawater arising from temporary reclamation in the ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.

4.3.22.   Dissolved oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when there is temporary reclamation in Causeway Bay Typhoon Shelter and at the south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working Area. The proposed water quality monitoring stations of the Project are shown in Table 4.6 and Figure 4.1.

Table 4.6      Marine Water Quality Stations for Enhanced Water Quality Monitoring

Station

Location

C6

Excelsior Hotel

C7

Windsor House

Ex-WPCWA-SW

South-western of the ex-Wan Chai Public Cargo Working Area

Ex-WPCWA-SE

South-eastern of the ex-Wan Chai Public Cargo Working Area

 

4.3.23.   The monitoring of dissolved oxygen are to be carried out 3 days per week, at mid-flood and mid-ebb tides for 3 water depths (1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth may be omitted. If the water depth be equal to or less than 3m, only the mid-depth will be monitored).

 

 

 

 

Daily SS Monitoring and 24 hours Turbidity Monitoring System

4.3.24.   During dredging of the sediment at the south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of suspended solids and 24 hour monitoring of turbidity at the cooling water intakes (C6 and C7) shall be conducted.

4.3.25.   The 24 hours monitoring of turbidty at the cooling water intakes (C6 and C7) shall be established by setting up a continuous water quality monitoring station in front of the intakes during the dredging activities. The monitoring system include the turbidity sensor and data logger which is capable of data capturing at every 5 minutes. The data sahll be downloaded daily and compared with the Action and Limit level determined during the baseline water qualtiy monitoring at the cooling water intake locations.

Additional Dissovled oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW

4.3.26.   In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be installed to channel water discharge flow from Culvert L to locations outside the embayment area, a proposed replacement of the requirement with additional dissolved oxygen monitoring has been conducted at three monitoring stations, namely A, B and C between the eastern seawall of Central Reclamation Phase III and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level between the eastern seawall of Central Reclamation Phase II and the HKCEC extension could be continuously monitored.

4.3.27.   With respect to the commencement of dredging works under HK/2012/08 and the installation of MTR precast protection unit, the enhanced water quality monitoring for Culvert L was temporarily suspended since 24 July 2013

4.3.28.   The monitoring of dissolved oxygen are to be carried out once per week, at mid-flood and mid-ebb tides for 3 water depths (1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth may be omitted. If the water depth be equal to or less than 3m, only the mid-depth will be monitored).  

 

 

5.         Monitoring Results

5.0.1.     The environmental monitoring will be implemented based on the division of works areas of each designed project managed under different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 4.1. The monitoring results are presented in according to the Individual Contract(s).

5.0.2.     In the reporting month, the concurrent contracts are as follows:

Ÿ  Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central-Wan Chai Bypass at Hong Kong Convention and Exhibition Centre; and

Ÿ  Contract no. HK/2009/02 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass at Wan Chai East

Ÿ  Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

Ÿ  Contract no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR Tsuen Wan Line

Ÿ  Contract no. HY/2009/19- Cental- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

Ÿ  Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

Ÿ  Contract no. HY/2010/08 ¡V Central- Wanchai Bypass Tunnel (Slip Road 8 Section)

 

5.0.3.     The environment monitoring schedules for reporting month and coming month are presented in Appendix 5.1.

5.1          Noise Monitoring Results

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC, Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East and Contract no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR Tsuen Wan Line

5.1.1.     The proposed division of noise monitoring stations are summarized in Table 5.2 below.

Table 5.2  Noise Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06

Station

Description

M1a

Harbour Road Sports Centre

 

5.1.2.     Daytime and evening period noise monitoring was conducted at the Harbour Road Sport Centre in the reporting month.

5.1.3.     No exceedance was recorded in this reporting period. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2

 

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

5.1.4.     The noise monitoring for HY/2009/15 was commenced on 10 November 2010. The proposed division of noise monitoring stations are summarized in Table 5.3 below.

Table 5.3      Noise Monitoring Station for Contract no. HY/2009/15

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

 

5.1.5.     One limit level exceedance was recorded on 24 June 2014 at M2b ¡V Noon Day Gun Area in the reporting month.  

5.1.6.     Concrete breaking works at TS4 under HY/2009/15 were observed during monitoring on 24 June 2014. It was considered that the concrete breaking works was the major noise contribution. As such, the limit level exceedance was concluded as project related. Rectification measures including provision of noise blanket for breakers was implemented by the contractor. Additional monitoring was conducted and no exceedance was identified.

5.1.7.     Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

Contract no. HY/2009/19- Wan Chai Bypass Tunnal (North Point Section) and Island Eastern Corridor Link

5.1.8.     The proposed division of noise monitoring stations are summarized in Table 5.4 below.

Table 5.4      Noise Monitoring Station for Contract no. HY/2009/19

Station

Description

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

 

 

 

 

 

 

5.1.9.     Four limit level exceedances were recorded on 5, 10, 17 and 25 June 2014 at M6 ¡V HK Baptist Church Henrietta Secondary School in the reporting month.   

5.1.10.   Major traffic noise observed during monitoring on 5, 10, 17 and 25 June 2014 and it was considered as the major noise contribution. As such, the limit level exceedances were concluded as non-project related.

5.1.11.   Noise monitoring results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

5.2          Real-time Noise Monitoring

Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

5.2.1       As the land-based piling and filling works- DP3 at Tin Hau had been completed on 3 September 2012 and confirmed by RSS, the real-time noise monitoring results at FEHD Hong Kong Transport Section Whitfield Depot was excluded under EP-356/2009 since 28 November 2012.

 

5.2.2       The real-time noise monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct 2012, which is a representative of noise sensitive receiver- City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.

 

5.2.3       The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011 and the FEP-01/356/2009 was surrendered on 22 Oct 2012.

 

5.2.4       Real-time noise monitoring at FEHD Hong Kong Transport Section Whitfield Depot commenced external wall renovation since 1 June 2012

Table 5.5 Real Time Noise Monitoring Station for Contract no. HY/2009/19

District

Station

Description

North Point

RTN2a

Electric Centre

l   Real time noise monitoring results and graphical presentation during night time period are for information only.

l   RTN2 had been relocated to RTN2a since 5 Oct 2012

l   RTN1 monitoring had been finished on 28 Nov 2012

5.2.5       Limit level exceedances were recorded at RTN2a-Electric Centre during restricted hours on 8 June 2014 and during daytime on 20 June 2014 in the reporting month. After checking with Contractor, no construction activity was conducted at the concerned location on 8 June 2014 during the recorded period and the exceedances were considered to be contributed by the adverse weather condition during the hoisting period of rainstorm signal. On 20 June 2014, despite socket H-piling and bored piling activities were conducted at the concerned location on the monitoring day, contractor mitigation measures including erection of temporary noise barrier was in place. Also, piling works was also observed at nearby non-CWB Projects. In view of the exceedance was non-continuous, it was considered that the exceedance was considered as non-project related.

5.2.6       Details of real time noise monitoring results and graphical presentation can be referred to Appendix 5.5.

5.3          Air Monitoring Results

  

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

5.3.1.     Air monitoring was commenced on 1 April 2011 in response to the commencement of the land-filling work for Contract no. HK/2009/01. The proposed divisions of air monitoring stations are summarized in Table 5.7 below. No exceedance was recorded in the reporting month.

Table 5.7      Air Monitoring Stations for Contract no. HK/2009/01

Station

Description

CMA5a

Children Playgrounds opposite to Pedestrian Plaza

CMA6a

WDII PRE Site Office

5.3.1       No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3.  

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

5.3.2.     Air monitoring was commenced in mid-January 2011 for the land-filling work for Contract no. HK/2009/02. The proposed division of air monitoring stations are summarized in Table 5.8 below. No exceedance was recorded in the reporting month.

Table 5.8      Air Monitoring Station for Contract no. HK/2009/02

Station

Description

CMA4a

Society for the Prevention of Cruelty to Animals

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

5.3.3.     Air monitoring was commenced on 15 March 2011 for the land filling work for Contract no. HY/2009/15. The proposed division of air monitoring stations are summarized in Table 5.9 below.

 

 

 

 

Table 5.9      Air Monitoring Station for Contract no. HY/2009/15

Station

Description

CMA3a

CWB PRE Site Office

5.3.4.     No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

 

Contract no. HY/2009/19- Wan Chai Bypass Tunnal (North Point Section) and Island Eastern Corridor Link

5.3.5.     The proposed division of air monitoring stations are summarized in Table 5.10 below. No exceedance was recorded in the reporting month.

Table 5.10 Air Monitoring Stations for Contract no. HY/2009/19

Station

Description

CMA1b

Oil Street Site Office

CMA2a

Causeway Bay Community Centre

5.3.6.     No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3.

5.4          Water Monitoring Results.

5.4.1.     Action and Limit level of water quality monitoring was transited from dry season to wet season from 1 April 2014.

5.4.2.     According to CWB RSS, oil dispersion at the culvert outfall location at SW corner of CBTS was observed on 6, 22, 24 and 28 Feb 2014. An ICC case (ICC ref: 2-92821253) regarding the above issue was lodged by CWB RSS team to request for follow-up action by relevant departments.

5.4.3.     Another oil dispersion at the culvert outfall location at Ex-Cargo handling area was observed on 28 Feb 2014 by CWB RSS. An ICC case (ICC ref: 2-125779508) regarding the above observation was lodged by CWB RSS team to request for follow-up action by relevant departments.

5.4.4.     With respect to the switching over of cooling water intake location, the water quality monitoring at the relocated intake station RW21-P789 under HK/2009/02 was commenced since 29 July 2013 and monitoring station C5e and C5w were temporarily suspended and switched over to monitoring station RW21-P789 on 29 July 2013 due to suspension of pump house operation.

5.4.5.     As advised by WDII RSS, the water quality monitoring for WSD21 pump station with respect to HK/2009/02 was switched over to the relocated location since 12 March 2014. According to the EM&A Manual, the water quality monitoring station WSD21 was relocated to station RW21-P789 and the water quality monitoring at station WSD21 was temporarily suspended since 12 March 2014.

5.4.6.     WQM events on 22 April 2013 at monitoring stations C2, C3, C4e and C4w were temporarily suspended. Upon confirmation with WDII RSS and the IEC, water quality monitoring at relocated intakes monitoring location P1, P3, P4 and P5 were commenced since 24 April 2013.

5.4.7.     WDII/RSS advised that the dredging works for submarine pipeline at Victoria Harbour had been completed in January 2012. Therefore, the concurrent dredging activities at Sewage Pipeline Zone and reclamation shoreline zone TCBR under the EP-356/2009 scenario 2B no longer exist. As such, with reference to Table 5.39 of the EIA Report for Wan Chai Development Phase II and Central-Wan Chai Bypass, the application of silt screen for cooling water intakes for Queensway Government Offices was suspended and the others remain unchanged.

5.4.8.     Based on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no water deterioration with respect to NPR was commenced since 7 Jan 2012 and it was completed on 6 February 2012.

5.4.9.     Water quality monitoring at WSD10 and WSD15 was temporary suspended while water quality monitoring at WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8 Feb 12 onwards;

5.4.10.   Due to the marine piling under Contract no. HY/2009/19 was completed on 4 March 2013, the temporary suspension of impact water quality monitoring at C8 and C9 from 4 March 2013 have been monitored for 4-week period after the completion of marine works to confirm no water deterioration.

5.4.11.   The water quality monitoring at the respective monitoring station C8 and C9 were temporarily suspended from 30 March 2013. 

5.4.12.   Based on the safety concern when external façade refurbishment was conducted by contractor employed by Provident Centre (C9) since 3 Feb 2012, there is a fine adjustment of the sampling location of water quality monitoring at C9 to the closest accessible point prior to the completion of the external façade refurbishment work.

5.4.13.   With respect to the trial dredging at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3 , 11, 13, 15, 17, 19, 20 Apr and 3 May 2012, on-going water quality monitoring results at WSD21 during this period was checked and indicated that there was no contribution due to the trial dredging operation.  Enhanced review of water quality around WCR2 was also implemented and no deterioration in the water quality was observed.

5.4.14.   Due to the access of water monitoring station at WSD19 was blocked by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the inaccessibility of sampling either land and marine, there is a fine adjustment of the sampling point of WSD 19 since 5 April 2012 to the closest accessible point prior to the completion of the construction activities.

5.4.15.   Due to the dredging works for Cross Harbour Water Mains from Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April 2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for 4-week period after the completion of DP6 to confirm no water deterioration.

5.4.16.   Due to the presence of obstacle within the inner silt curtain frame at sampling point, water quality point at C7 was finely adjusted to the outside of the inner silt curtain frame since 29 Dec 2012.

Table 5.11 Water Monitoring Stations for contracts with respect to remaining DP3
work areas after the completion of DP5 & DP6 in 2012 and intake diversion in 2013

 

Contract No.

Remaining DP3 and work area(s)

Relevant Water Monitoring Stations,

Division of WQM w.r.t tentative works commenced / to be commenced

 

HK/2009/01

WCR3

C11

Apr 2013

HK/2009/02

WCR3, WCR4, TWCR4

RW21-P7891

Apr 2013

HK/2012/08

HKCEC2W, HKCEC2E

WSD19, P13, P33, P43, P53

Aug 2013

HY/2009/15

 

TCBR2, TCBR3, TCBR1W, TPCWAE, TPCWAW

C64, C7, Ex-WPCWA SW, Ex-WPCWA SE (plus enhanced DO monitoring described in 4.6.3)

Nov 2010

HY/2010/08

TCBR3, TCBR4

C64, C7 (plus enhanced DO monitoring described in 4.6.3)

Mar 2014

Remarks:

-The water monitoring stations for WSD19, P1, P3, P4, P5 shall be associated with Contract No. HK/2009/01 prior to their transition to Contract HK/2012/08.

-4 intakes (re-provisioned Wanchai WSD intake, Great Eagle Centre, China Resources Centre & Sun Hung Kai Centre constructed adjacent to each other) taken as a single group for silt screen protection and monitoring.

-Re-provisioned intake reference: P1: HKCEC Phase 1; P3: APA, P4: Shui On; P5: Government Buildings (Wanchai Tower / Revenue Tower / Immigration Tower)

-Enhanced DO Monitoring at C6 since the intake abandon in May 2011.

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

5.4.17.   Water monitoring for Contract no. HK/2009/01 was commenced on 23 July 2010. The proposed division of water monitoring stations are summarized in Table 5.12 below.

Table 5.12    Water Monitoring Stations for Contract no. HK/2009/01

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

Remarks:

-       The water monitoring stations for the dredging works under Contract No. HK/2009/01 should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these locations have not been carried out by others. Similarly, the water monitoring stations for the dredging works under Contract No. HK/2009/02 should also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality monitoring at these locations have not been carried out by others.

-       WSD7 and WSD20 water quality monitoring were temporarily suspended since 27 Apr 2012.

-       C2, C3 C4e and C4w water quality monitoring station was temporarily suspended since 24 Apr 2013

 

Contract no. HK/2009/02 - Wan Chai Development Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

5.4.18.   Water monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010. The proposed division of water monitoring stations are summarized in Table 5.13 below.

Table 5.13    Water Monitoring Stations for Contract no. HK/2009/02

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD9

Tai Wan

837921.0

818330.0

WSD17

Quarry Bay

839790.3

817032.2

Cooling Water Intake

RW21-P789

Great Eagle Centre/ Sun Hung Kai Centre/CWB

836268.0

816020.0

Remarks:

-       The water monitoring stations for the dredging works under Contract No. HK/2009/01 should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these locations have not been carried out by others. Similarly, the water monitoring stations for the dredging works under Contract No. HK/2009/02 should also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality monitoring at these locations has not been carried out by others.

-       Water quality monitoring at WSD9 and WSD 17 was implemented with respect to HK/2009/02 from 8 Feb 2012.

-       C5e and C5w water quality monitoring station was temporarily suspended since 29 July 2013

-       WSD21 water quality monitoring station was temporarily suspended since 12 March 2014

 

Contract no. HK/2012/08 - Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

5.4.19.   Water monitoring for Contract no. HK/2012/08 was commenced on 5 March 2013. The proposed division of water monitoring stations are summarized in Table 5.14 below.

Table 5.14    Water Monitoring Stations for Contract no. HK/2012/08

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD19

Sheung Wan

833415.0

816771.0

Cooling Water Intake

P1

HKCEC Phase I

835774.7

816179.4

P3

The Academy of performing Arts

835824.6

816212.0

P4

Shui on Centre

835865.6

816220.0

P5

Government Buildings

(Wanchai Tower / Revenue Tower / Immigration Tower)

835895.2

816215.2

 

 

 

 

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

5.4.20.   As the removal of reclamation work of TS1 at CBTS has been completed, all procedures have been rectified and complied with the conditions set in EP-356/2009 and FEP-04/356/2009.

5.4.21.   Due to the commencement of the maintenance dredging on 10 November 2010, water quality monitoring for Contract no. HY/2009/15 was commenced on 9 November 2010. The proposed division of water monitoring stations are summarized in Table 5.15 below.

5.4.22.   Due to the presence of obstacle within the inner silt curtain frame at sampling point, water quality point at C7 was finely adjusted to the outside of the inner silt curtain frame since 29 Dec 2012.

Table 5.15    Water Monitoring Stations for Contract no. HY/2009/15

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C7

Windsor House

837193.7

816150.0

Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

 

Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

5.4.23.   Due to the commencement of the marine bored piling on 28 Jan 2012, water quality monitoring for Contract no. HY/2009/19 was commenced on 28 Jan 2012. The proposed division of water monitoring stations are summarized in Table 5.16 below.

5.4.24.   Due to the marine piling under Contract no. HY/2009/19 was completed on 4 March 2013, the temporary suspension of impact water quality monitoring at C8 and C9 from 4 March 2013 have been monitored for 4-week period after the completion of marine works to confirm no water deterioration.

5.4.25.   Based on the safety concern when external façade refurbishment was conducted by contractor employed by Provident Center (C9) between 9 January 2012 to 30 July 2012 which caused to the inaccessibility of sampling either land and marine since 3 Feb 2012, there is a fine adjustment of the sampling location of water quality monitoring at C9 since 10 March 2012 to the closest accessible point prior to the completion of the external façade refurbishment work.

5.4.26.   Due to the access of water monitoring station at WSD19 was blocked by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the inaccessibility of sampling either land and marine, there is a fine adjustment of the sampling point of WSD 19 since 5 April 2012 to the closest accessible point prior to the completion of the construction activities.

5.4.27.   As per the meeting with the representative of Excelsior Hotel and World Trade Centre on 17 May 2011, they confirmed that the seawater intake for The Excelsior was no longer in use and replaced by the connected permanent water supply from WSD pipelines since 11 January 2011. Thus, the impact water quality monitoring for the cooling intake - C6 was terminated effective from 26 May 2011.

5.4.28.   24 hours monitoring of turbidity at the cooling water intakes at C7 was conducted. With respect to the seawall collapsing at TS4 on 17 November 2011, the 24 hours turbidity monitoring and was kept in November 2011. Since the reinstating the seawall was completed on 13 January 2012 and no any water deterioration was performed, 24 hour turbidity monitoring was then suspended on 27 January 2012.

5.4.29.   Water monitoring results measured in this reporting period are reviewed and summarized. Details of water quality monitoring results and graphical presentation can be referred in Appendix 5.4.


Table 5.17    Summary of Water Quality Monitoring Exceedances in Reporting Month

 

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HK/2009/01

C1

0

0

0

0

0

0

0

0

0

0

0

0

HK/2012/08

WSD19

0

0

0

0

0

0

0

0

0

0

0

0

P1

0

0

0

0

0

0

1

0

0

0

0

0

P3

0

0

0

0

0

0

1

0

0

0

0

0

P4

0

0

0

0

0

0

0

0

0

0

0

0

P5

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/02

Monitoring started on

8 Feb 2012

WSD9

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD17

0

0

0

0

0

0

0

0

0

0

0

0

Monitoring started on

29 July 2013

RW21-P789

0

0

0

0

0

0

0

0

0

0

0

0

HY/2009/15 & HY/2010/08

C7

0

0

0

0

0

0

0

0

0

0

0

0

Total

0

0

0

0

0

0

2

0

0

0

0

0

 

Remarks: -     The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

         -   WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.

-   4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 were completed on 6 Feb 2012.

-   C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.

-       C8 & C9 was temporary suspended on 30 March 2013 due to the marine works for Contract no. HY/2009/19 had been completed on 4 March 2013

-   WSD7 and WSD20 were temporarily suspended from 27 Apr 2012

-       C2, C3 C4e and C4w water quality monitoring station was temporarily suspended since 24 Apr 2013

-       C5e and C5w water quality monitoring station was temporarily suspended since 29 July 2013

-       WSD21 water quality monitoring station was temporarily suspended since 12 March 2014

-       Maintenance responsibility of silt screen C1, WSD19, P3, P4 and P5 are under Contract HK/2009/01.

 

 

5.4.30.   Investigation found that the exceedances were not project-related. The details of the recorded exceedances can be referred to the Section 6.4.

5.4.31.   Enhanced DO monitoring at 4 monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table 5.18.

 

 

 

 

 

Table 5.18     Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

 

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

DO

AL

LL

AL

LL

HY/2009/15

C6

0

0

0

0

C7

0

0

0

0

Ex-WPCWA SW

0

4

0

2

Ex-WPCWA SE

0

4

0

2

Total

0

8

0

4

                                                            

5.4.32.   There were no action level exceedances and 12 limit level exceedances of enhanced dissolved oxygen recorded in this reporting month. Investigation found that the exceedances are not related to the Project works. The details of the recorded exceedances can be referred to the Section 6.4.

5.4.33.   In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be installed to channel water discharge flow from Culvert L to locations outside the embayment area, a proposed replacement of the requirement with additional dissolved oxygen monitoring has been conducted at three monitoring stations, namely A, B and C between the eastern seawall of Central Reclamation Phase III and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level between the eastern seawall of Central Reclamation Phase II and the HKCEC extension could be continuously monitored. Details of additional DO monitoring results can be referred in Appendix 5.4a.

5.4.34.   With respect to the commencement of dredging works under HK/2012/08 and the installation of MTR precast protection unit, the enhanced water quality monitoring for Culvert L was temporarily suspended since 24 July 2013

 

\

 

 

 

 

 

 

 

 

 

 

5.5          Waste Monitoring Results

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

5.5.1.     No Inert C&D waste was disposed and non- inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.19.

Table 5.19     Details of Waste Disposal for Contract no. HK/2009/01

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

8923.65

62116.405

TKO137, TM38

Inert C&D materials recycled, m3

752

5856.5

N/A

Non-inert C&D materials disposed, m3

24.22

1671.69

SENT Landfill

Non-inert C&D materials recycled, kg

52850

203993

N/A

Chemical waste disposed, kg

0

10250

N/A

*Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

0

(Bulk Volume)

97428.2

(Bulk Volume)

South of Cheung Chau

* Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

0

(Bulk Volume)

52250

(Bulk Volume)

East of Cha Chau

Dredged Sediment Requiring Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic Containers

0

 (Bulk Volume)

6773

(Bulk Volume)

East of Cha Chau

     

5.5.2.     There were no marine sediment Type 1- Open Sea Disposal and no marine sediments Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal disposed in this reporting month.

 

 

 

 

 

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East

5.5.3.     Inert C&D waste and Non-inert C&D waste were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.20.

Table 5.20     Details of Waste Disposal for Contract no. HK/2009/02

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

2577.845

263703.91

TKO137 / TM 38

Inert C&D materials recycled, m3

NIL

18161

N/A

Non-inert C&D materials disposed, m3

62.31

1515.103

SENT Landfill

Non-inert C&D materials recycled, m3

N/A

N/A

N/A

Chemical waste disposed, kg

1200

13860

SENT Landfill

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

1121

186409

(Bulk volume)

South of Cheung Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

0

129320

 (Bulk volume)

East of Sha Chau

5.5.4.     There was Marine Sediment Type1- Open Sea Disposal disposed of in this reporting month.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

5.5.5.     No Inert C&D waste and no non- inert C&D waste were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.21

Table 5.21     Details of Waste Disposal for Contract no. HY/2009/15

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Remarks

Inert C&D materials disposed, m3

NIL

141579.2

Tuen Mun Area 38

NIL

NIL

65216

TKO137 FB

NIL

Inert C&D materials recycled, m3

NIL

304

ex-PCWA

NIL

NIL

111.9

TS4

NIL

Non-inert C&D materials disposed, m3

NIL

252.2

SENT Landfill

NIL

Non-inert C&D materials recycled, kg

NIL

299361.5

N/A

NIL

Chemical waste disposed, kg

NIL

8,200

N/A

NIL

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

0

(Bulk Volume)

100208

(Bulk Volume)

Cheung Chau South

Dredging from TCBR1E / TCBR1W / TCBR2/ TCBR3 / TCBR4 / Maintenance dredging

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

 3030

(Bulk Volume)

230345

(Bulk Volume)

East of Sha Chau / South of the Brothers

Dredging from TCBR1E / TCBR1W / TCBR2/ TCBR3 / TCBR4 / Maintenance dredging

Marine Sediment (Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic Containers) m3

0

(Bulk Volume)

8780

(Bulk Volume)

East of Sha Chau / South of the Brothers

Dredging from TCBR1W / Maintenance dredging

Marine Sediment (Type 2 ¡V Confined Marine Disposal), m3

0

9350

(Bulk Volume)

East of Sha Chau

Dredging from Eastern Breakwater of CBTS

Marine Sediment (Type 1 ¡V Open Sea Disposal) , m3

0

(Bulk Volume)

600

(Bulk Volume)

East Sha Chau / South of The Brothers

Dredging from Phase 3 Mooring Re-arrangement

Marine Sediment (Type 2¡V Confined Marine Disposal) , m3

0

(Bulk Volume)

14,780

(Bulk Volume)

South of The Brothers

Dredging from Phase 3 Mooring Re-arrangement

Marine Sediment (Type 3 ¡V Special Treatment / Disposal contained in Geosynehetic Containers) , m3

0

(Bulk Volume)

2,760

(Bulk Volume)

South of The Brothers

Dredging from Phase 3 Mooring Re-arrangement

 

5.5.6.     There were no marine sediment Type 2 ¡V Confined Marine Disposal and marine sediment Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic Containers was disposed of in this reporting month.

 

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line

5.5.7.     No inert C&D waste was disposed and no non-Inert C&D waste was recycled in this reporting month. Details of the waste flow table are summarized in Table 5.22.

Table 5.22     Details of Waste Disposal for Contract no. HK/2010/06

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

0

12567.88

TM38

Inert C&D materials recycled, m3

0

267

HK/2009/01

Non-inert C&D materials disposed, m3

0

369.48

SENT/TKO137SF

Non-inert C&D materials recycled, T

0

60.58

Recyclers

Chemical waste disposed, L

0

             2600

N/A

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

0

3,891

(Bulk Volume)

South Cheung Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

0

12,586

(Bulk Volume)

East Sha Chau

 

5.5.8.     There were no marine sediments Type1- Open Sea Disposal and no Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal was deposed of in this reporting month.

 

 

 

Contract no. HY/2009/19 ¡VCentral- WanChai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

5.5.9.     No inert C&D waste was disposed and non-inert C&D waste were disposed in this reporting month. Details of the waste flow table are summarized in Table 5.23.

Table 5.23 Details of Waste Disposal for Contract no. HY/2009/19

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

7383.94

355921.04

TM38

Inert C&D materials recycled, m3

818.71

59367

N/A

Non-inert C&D materials disposed, m3

348.32

1068.6

N/A

Non-inert C&D materials recycled, kg

12.32

333.14

N/A

Chemical waste disposed, L

0.11

2.12

N/A

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

0

162

South Cheung Chau

Marine Sediment (Type 2 ¡V Confined Marine Disposal) , m3

0

681

East Sha Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

0

4976.00

 

 

5.5.10.   There was no marine sediment Type1- Open Sea Disposal and there was no Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal generated were disposed in this reporting month.

 

Contract no. HK/2012/08 ¡VWan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

5.5.11.   No inert C&D waste was disposed and non-inert C&D waste were disposed in this reporting month. Details of the waste flow table are summarized in Table 5.24.

Table 5.24 Details of Waste Disposal for Contract no. HK/2012/08

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

0

1247

TM38

Inert C&D materials recycled, m3

NIL

NIL

N/A

Non-inert C&D materials disposed, m3

15

310

N/A

Non-inert C&D materials recycled, kg

NIL

NIL

N/A

Chemical waste disposed, L

NIL

NIL

N/A

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

639

(Bulk volume)

31426*

(Bulk volume)

South of Cheung Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

330

(Bulk volume)

108485*

(Bulk volume)

South of The Brothers (from 27 Aug 2013 onwards)

*Remarks: Contractor clarified the cumulative quantity of marine sediment in June Reporting month.

 

5.5.12.   There were Marine Sediment Type 1 ¡V Open Sea Disposal and marine sediment Type 1 ¡V Open Sea Disposal (Delicate Sites) & Type 2 ¡V Confined Marine Disposal disposed in this reporting month.

 

Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8)

5.5.13.   No Inert C&D waste and non-inert C&D waste were disposed in this reporting month. Details of the waste flow table are summarized in Table 5.25

       Table 5.25 Details of Waste Disposal for Contract no. HY/2010/08

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

NIL

NIL

N/A

Inert C&D materials recycled, m3

NIL

NIL

N/A

Non-inert C&D materials disposed, m3

NIL

NIL

N/A

Non-inert C&D materials recycled, kg

NIL

NIL

N/A

Chemical waste disposed, L

NIL

NIL

N/A

Dumping Permit (Type 1 ¡V Open Sea Disposal)

NIL

12860

South Cheung Chau

Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine disposal)

NIL

17820

Brothers Island

5.5.14.   There was no marine sediment Type 1 ¡V Open Sea Disposal and no Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal generated were disposed in this reporting month.

 

 

6.         Compliance Audit

6.0.1.     The Event Action Plan for construction noise, air quality and water quality are presented in Appendix 6.1.

 

6.1          Noise Monitoring

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

6.1.1       No exceedance was recorded in the reporting month.

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East 

6.1.2       No exceedance was recorded in the reporting month.

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

6.1.3       One limit level exceedance was recorded on 24 June 2014 at M2b ¡V Noon Day Gun Area in the reporting month.

6.1.4       Concrete breaking works at TS4 under HY/2009/15 were observed during monitoring on 24 April 2014. It was considered that the concrete breaking works was the major noise contribution. As such, the limit level exceedance was concluded as project related. Rectification measures including provision of noise blanket for breakers was implemented by the contractor. Additional monitoring was conducted and no exceedance was identified.

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line

6.1.5       No exceedance was recorded in the reporting month.

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

6.1.6       Four limit level exceedances were recorded on 5, 10, 17 and 25 June 2014 at M6 ¡V HK Baptist Church Henrietta Secondary School in the reporting month.  Investigations found that on 5, 10, 17 and 25 June 2014, traffic noise was major contribution in the noise monitoring and exceedances were not related to the Project.

 

6.2          Real-time noise Monitoring

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

6.2.1.     Limit level exceedances were recorded at RTN2a-Electric Centre during restricted hours on 8 June 2014 and during daytime on 20 June 2014 in the reporting month. After checking with Contractor, no construction activity was conducted at the concerned location on 8 June 2014 during the recorded period and the exceedance was considered to be contributed by the adverse weather condition during the hoisting period of rainstorm signal. On 20 June 2014, despite socket H-piling and bored piling activities were conducted at the concerned location on the monitoring day, contractor mitigation measures including erection of temporary noise barrier was in place. Also, piling works was also observed at nearby non-CWB Projects. In view of the exceedance was non-continuous, it was considered that the exceedance was considered as non-project related.

 

6.3          Air Monitoring

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

6.3.1       No exceedance was recorded in the reporting month.

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

6.3.2       No exceedance was recorded in the reporting month.

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

6.3.3       No exceedance was recorded in the reporting month.

 

6.4          Water Quality Monitoring

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

 

6.4.1       No exceedance was recorded in this reporting month

Contract no. HK/2012/08 ¡VWan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West.

6.4.2       There were two action level exceedances of water monitoring recorded on 9 June 2014 at P1 and P3 during Ebb tide. Despite marine filling at sea area of former Expo Drive West Bridge was conducted by Contractor HK/2012/08 during monitoring, contractor mitigation measures including the deployment of silt curtain for filling works was in place. After checking, the condition of silt screen installed around intake location was considered generally satisfactory. In view of no further exceedance were recorded in P1 and P3, the exceedance was considered not project related.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East 

 

6.4.3       No exceedance was recorded in this reporting month                

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

 

6.4.4       No exceedance was recorded in this reporting month.

 

 

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line

 

6.4.5       No exceedance was recorded in this reporting month.

 

Contract no. HY/2009/19- Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

 

6.4.6       No exceedance was recorded in this reporting month.

 

Contract no. HK/2012/08- Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

 

6.4.7       There were occasionally DO exceedances at Ex-WPCWA SE and Ex-WPCWA SW recorded in this reporting month on 2 June 2014, 13 June 2014, 20 Jun 2014 and 27 June 2014. No odour nuisance was noted during DO monitoring. After checking with Contractor, no marine works was conducted during the time of monitoring on 28, 30 May 2014, 2, 13, 20, 27 June 2013 at Ex-WPCWA. In the view that there was no marine activities at EX-WPCWA, it was considered not related to Project works.

 

Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8)

 

6.4.8       No exceedance was recorded in this reporting month.

 

6.5          Review of the Reasons for and the Implications of Non-compliance

6.5.1       There was no non-compliance from the site audits in the reporting period. The observations and recommendations made in each individual site audit session were presented in Section 8.

6.5.2       One project-related non-compliance from monitoring was recorded in the reporting month.

6.6          Summary of action taken in the event of and follow-up on non-compliance

6.6.1       There was no particular action taken since no non-compliance was recorded from the site audits in the reporting period.

6.6.2       There was one limit level exceedance of noise monitoring recorded on 24 June 2014 at M2b- Noon Day Gun Area that was considered in relation to concrete breaking works conducted during monitoring.

6.6.3       Following the Event and Action Plan, additional noise monitoring was conducted on 03 July 2014 and a proposal for remediation measures was submitted by the contractor after the exceedance was identified.

6.6.4       Rectification measures including provision of noise blanket for breakers was implemented by the contractor and no further exceedances was recorded.

 

7.         Cumulative Construction Impact due to the Concurrent Projects

7.0.1.     According to Condition 3.4 of the EP-356/2009, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III, Central-Wanchai Bypass and Island Eastern Corridor Link projects.

7.0.2.     According to the Final EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK 12/02, the major construction activities were completed by end of January 2014 and no construction activities were undertaken thereafter and the water quality monitoring was completed in October 2011 and no Project-related exceedance was recorded for air and noise monitoring.  It can be concluded that cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) was insignificant.

7.0.3.     According to the construction programme of Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III area, Diaphragm wall construction, Guide wall construction were performed in June 2014 reporting month. As no exceedances were recorded during the reporting period, cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) was considered as insignificant. 

7.0.4.     According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activity under Wan Chai Development Phase II were marine works at HKCEC areas, tunnel works at Wan Chai East and filling works at Wan Chai West. The major construction activities under Central-Wan Chai Bypass and Island Eastern Corridor Link Projects were tunnel construction at TS4, tunnel construction and dismantling of struts at TPCWAE and TS4. Bridge construction and tunnel works at Central Interchange, ELS, segment launching works, tunnel works at North Point area. The major environmental impact was water quality impact at Causeway Bay and Wan Chai. Land-based construction activities were tunnel construction at TS2, TS4 and TPCWAE, tunnel works at Central and ELS and tunnel works at North Point and tunnel works at Wan Chai East in the reporting month.

7.0.5.     The major environmental impacts generated from tunnel works at Central and tunnel works at Wan Chai East, IECL and Causeway Bay Typhoon Shelter were undertaken in the reporting month.. As no project related exceedance was recorded in the Project, it was considered no adverse environmental impact caused by the Project works. Thus, it is evaluated the cumulative construction impact was insignificant.

 

8.         Environmental Site Audit

8.0.1.     During this reporting month, weekly environmental site audits were conducted for Contracts no.  HK/2009/01, HK/2009/02, HY/2009/15, HK/2010/06, HY/2009/19, HK/2012/08 and HY/2010/08. No non-conformance was identified during the site audits.

8.0.2.     Five site inspections for Contract no. HK/2009/01 were conducted on 28 May 2014, 4, 11, 19 and 25 June 2014 in reporting month. Results of these inspections and outcomes are summarized in Table 8.1.

Table 8.1      Summary of Environmental Inspections for Contract no. HK/2009/01

         Item

Date

Observations

Action taken by Contractor

Outcome

140528_01

28-May-14

Plant should be properly maintained as to prevent emission of dark smoke (Expo Drive East)

The plant was removed.

Completion as observed on 4 June 2014

140604_01

4-Jun-14

Bags of cements should be properly stored (Bay 8)

Cements were removed

Completion as observed on 11 June 2014

140604_02

4-Jun-14

Plant should be properly maintained as to prevent emission of dark smoke (Expo Drive East)

The plant was removed.

Completion as observed on 11 June 2014

140604_03

4-Jun-14

Floating debris should be cleaned more frequently

Floating refuse was cleaned

Completion as observed on 11 June 2014

140611_01

11-Jun-14

Trees should be properly protected (Conservation Avenue)

Proper fencing were provided to the trees

Completion as observed on 19 June 2014

140611_02

11-Jun-14

Silt curtain should be properly depolyed (Bay 8)

Deployment of silt curtain was improved

Completion as observed on 19 June 2014

140619_01

19-Jun-14

Clear the muddy water seepage onto public road. ( Area 8)

The muddy seepage was removed.

Completion as observed on 25 June 2014

140625_01

25-Jun-14

Noise mitigation measure should be provided ( Water Channel)

Noise mitigation measure was provided

Completion as observed on 2 July 2014

140625_02

25-Jun-14

Silt curtain was observed damaged and missed contractor was reminded to deploy and maintain the silt curtain properly. (Bay 8&9 )

Additional silt curtain was provided at the concerned area while repair

Completion as observed on 2 July 2014

 

8.0.3.     Five site inspections for Contract no. HK/2009/02 were carried out on 29 May, 5, 12, 18, 26 June 2014 in reporting month. Results of these inspections and outcomes are summarized in Table 8.2.

 

 

Table 8.2      Summary of Environmental Inspections for Contract no. HK/2009/02

         Item

Date

Observations

Action taken by Contractor

Outcome

140529_01

29-May-14

Cement should be properly covered (WCR2)

Cement were removed

Completed as observed on 5 June 2014

140529_02

29-May-14

Construction water should be prevented from spreading into access road during drilling (WCR2)

Construction effluents was removed at the concern location.

Completed as observed on 5 June 2014

140529_03

29-May-14

Drip tray should be provided to chemical container (WCR2)

Chemical container was removed

Completed as observed on 5 June 2014

140618_01

18-Jun-14

Oil leakage was observed during inspection. Contractor was reminded to prevent from oil leakage and clean the oil leakage as chemical waste (WCR2 )

Oil leakage was cleared

Completion as observed on 26 June 2014

140626_01

26-Jun-14

Stockpile should be properly covered. (WCR1)

Additional covers were placed above the stockpile and barriers were placed between the stockpile and the shore. The size of stockpile was reduced.

Completion as observed on 10 July 2014

140626_01

26-Jun-14

Oil in drip tray should be treated as chemical waste ( portion 3&4)

Oil was removed as chemical waste

Completion as observed on 08 July 2014

 

 

 

 

 

 

 

 

 

 

 

 

8.0.4.     Four site inspections for Contract no. HY/2009/15 were carried out on 3, 10, 17 and 23 June 2014 in reporting month. The results of these inspections and outcomes are summarized in Table 8.3.

Table 8.3      Summary of Environmental Inspections for Contract no. HY/2009/15

Item

Date

Observations

Action taken by Contractor

Outcome

140610_01

10/6/2014

Chemical waste container shall be property collected and stored (TS4)

Chemical waste container was removed

Completion as observed on 17 June 2014.

140617_01

17/6/2014

Review the wastewater process procedure to avoid milky discharge (Ex-PCWA)

No further milky discharge was observed

Completion as observed on 23 June 2014

140623_01

23/6/2014

Provide silt curtain enclose in marine works area to mitigate muddy seepage/ dispersion                                (TS1 Breakwater, TS4)

Silt curtain was provided around marine works area

Completion as observed on 2 July 2014

140623_02

23/6/2014

Clear the mud deposit at the edge of the seawall to prevent drop-off to nearby water

(TS4)

Mud deposit have been removed

Completion as observed on 8 July 2014

140623_03

23/6/2014

Provide proper collection point for chemical waste container (TS2)

Chemical waste container was removed.

Completion as observed on 2 July 2014

 

8.0.5.     Four site inspections for Contract no. HK/2010/06 were carried out on 3, 9, 19 and 23 June 2014 in reporting month. No particular finding was observed in this reporting month.

 

8.0.6.     Five site inspections for Contract no. HY/2009/19 were carried out on 28 May 2014, 4 ,11, 18 and 26 June 2014 in reporting month. No particular finding was observed in this reporting month.

 

8.0.7.     Four site inspections for Contract no. HK/2012/08 were carried out on 3, 10, 17 and 24 June 2014 in this reporting period.  The results of these inspections and outcomes are summarized in Table 8.4.

 

Table 8.4      Summary of Environmental Inspections for Contract no. HK/2012/08

Item

Date

Observations

Action taken by Contractor

Outcome

140617_01

17-Jun-14

Wastewater from construction site should be treated before discharge. (Lung King Street)

No construction wastewater was discharged.

Completion as observed on 24 June 2014

 

 

 

 

8.0.8.     Five site inspections for Contract no. HY/2010/08 were carried out on 29 May 2014, 6, 12, 19 and 26 June 2014 in this reporting period. The results of these inspections and outcomes are summarized in Table 8.5.

 

Table 8.5      Summary of Environmental Inspections for Contract no. HY/2010/08

Item

Date

Observations

Action taken by Contractor

Outcome

140606_01

6-Jun-14

Leaked oil and contaminated soil should be cleared as chemical waste

Leaked oil and contaminated soil was removed

Completion as observed on 12 Jun 2014

140606_02

6-Jun-14

Provide covering to cement bags

Exposed cement bag have been removed

Completion as observed on 12 Jun 2014

140612_01

12-Jun-14

Provide tarpaulin covering to cement bag (Near Gate 1)

Exposed cement bag have been removed

Completion as observed on 19 Jun 2014

140612_02

12-Jun-14

Provide drip tray to oil containers (Victoria Park)

Drip trays have been provide

Completion as observed on 19 Jun 2014

140626_01

26-Jun-14

Provide drip tray to chemical containers and proper collection point for chemical waste

Chemical waste container have been removed

Completion as observed on 2 Jul 2014

140626_02

26-Jun-14

Provide embankment near public road to prevent seepage of muddy water and clear the muddy seepage on public road

Muddy seepage at public area was cleared

Completion as observed on 2 Jul 2014

                                                       

9. Complaints, Notification of Summons and Prosecution

9.0.1.     One environmental complaint under EP-356/2009 was received in the reporting period.

9.0.2.     A public complaint regarding water quality impact referred by WDII RSS team was received by ET on 12 June 2014. Notification letter from EPD on the captioned case was subsequently received by ET on 13 June 2014. The complainant reported that a large piece of muddy water was found on the waterfront outside the Hong Kong Academy for Performing Arts Theatre Block on 12 June 2014 morning.

9.0.3.     ET confirmed with the Resident Site Staff that neither marine construction works nor barge operation was conducted at the concerned location during the time of complaint. Nevertheless, with the respect to the EPD complaint case and the email notification issued by the Environmental team to contractor on 12 June 2014 morning, muddy dispersion was observe at HKCEC2W works area and the dispersion was observed partly extended beyond the outermost layer silt curtain at 1000hrs and contractor¡¦s immediate follow up action was requested.

9.0.4.     Mitigation measures implemented by the Contractor for the above construction works include the deployment of double layer of silt curtain for marine filling works area at HKCEC2W, additional silt curtain at marine access between caisson seawall on 12 June 2014, and regular diver checking on the silt curtain deployed at the location. It is considered that Contractor¡¦s mitigation measures for safeguarding the water quality during marine filling works at the concerned location implemented would require further review on the effectiveness to avoid seepage of muddy dispersion.

9.0.5.     Follow-up inspection was further conducted on 16 June 2014 and in addition, diver inspection check on the silt curtain deployed was conducted by the Contractor on 14 June 2014 to confirm the integrity of silt curtain.

9.0.6.     The Contractors¡¦ investigation report on the complaint case was submitted to EPD via email on 18 June 2014, and the interim report was submitted to EPD on 20 June 2014.

9.0.7.     The details of cumulative complaint log and updated summary of complaints are presented in Appendix 9.1

9.0.8.     Cumulative statistic on complaints and successful prosecutions are summarized in Table 9.1 and Table 9.2 respectively.

 

Table 9.1 Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

Commencement works (Mar 2010) to last reporting month

28

 June 2014

1

Total

29

 

 

 

 

Table 9.2 Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this month (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Water

-

0

0

Waste

-

0

0

Total

-

0

0

 

10.        Conclusion

10.0.1.   The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

10.0.2.   WDII/RSS advised that the dredging works for submarine pipeline at Victoria Harbour had been completed in January 2012. Therefore, the concurrent dredging activities at Sewage Pipeline Zone and reclamation shoreline zone TCBR under the EP-356/2009 scenario 2B no longer exist. As such, with reference to Table 5.39 of the EIA Report for Wan Chai Development Phase II and Central-Wan Chai Bypass, the application of silt screen for cooling water intakes for Queensway Government Offices was suspended and the others were remains unchanged.

10.0.3.   As the land-based piling and filling works- DP3 at Tin Hau had been completed on 3 September 2012 and confirmed by RSS, the real-time noise monitoring results at FEHD Hong Kong Transport Section Whitfield Depot was excluded under EP-356/2009 since 28 November 2012.

10.0.4.   The real-time noise monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct 2012, which is a representative of noise sensitive receiver- City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.

10.0.5.   Water quality monitoring at WSD10 and WSD15 will be temporary suspended while water quality monitoring at WSD9 and WSD17 were implemented with respect to HK/2009/02 for the water quality monitoring scheduled on 8 Feb 12 onwards;

10.0.6.   Due to the marine piling under Contract no. HY/2009/19 was completed on 4 March 2013, the temporary suspension of impact water quality monitoring at C8 and C9 from 4 March 2013 have been monitored for 4-week period after the completion of marine works to confirm no water deterioration.

10.0.7.   Water quality monitoring at C8 & C9 was temporary suspended on 30 March 2013 due to the marine works for Contract no. HY/2009/19 had been completed on 4 March 2013, and conclude if any water deterioration had been identified during the 4-week water quality monitoring.

10.0.8.   Based on the safety concern when external façade refurbishment was conducted by contractor employed by Provident Centre (C9) between 9 January 2012 to 30 July 2012 which caused to the inaccessibility of sampling either land and marine since 3 Feb 2012, there is a fine adjustment of the sampling location of water quality monitoring at C9 since 10 March 2012 to the closest accessible point prior to the completion of the external façade refurbishment work.

10.0.9.   Due to the access of water monitoring station at WSD19 was blocked by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the inaccessibility of sampling either land and marine, there is a fine adjustment of the sampling point of WSD 19 since 5 April 2012 to the closest accessible point prior to the completion of the construction activities.

10.0.10. With respect to the trial dredging at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3,     11, 13, 15, 17, 19, 20 Apr and 3 May 2012, on-going water quality monitoring results at WSD21 during this period was checked and indicated that there was no contribution due to the trial dredging operation.  Enhanced review of water quality around WCR2 was also implemented and no deterioration in the water quality was observed.

10.0.11. Due to the dredging works for Cross Harbour Water Mains from Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April 2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for 4-week period after the completion of DP6 to confirm no water deterioration.

10.0.12. The scheduled construction activities and the recommended mitigation measures for the coming month are listed in Table 10.1.

Table 10.1     Construction Activities and Recommended Mitigation Measures in Coming Reporting Month

Contract No.

Key Construction Works

Recommended Mitigation Measures

HK/2009/01

¡P         Tunnel structure work

¡P         Construction of D-wall

¡P         Installation of pre-bored H-piles

¡P         Discharge cooling mainlaying works for BI, BG & BF

¡P         Sewer works at Fenwick Pier Street

 

¡P         To conform the installation and setting as in the silt screen deployment plan

¡P         Frequency spray water on the dry dusty road and on the surface of concrete breaking

¡P         To cover the dusty material or stockpile by impervious sheet

¡P         To space out noisy equipment and position as far as possible from sensitive receiver.

¡P         To well maintain the mechanical equipments / machineries to avoid abnormal noise nuisance.

¡P         Machines and plant that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum

¡P         Daily visual inspection of silt screen and silt curtain to ensure its operation properly

HK/2009/02

¡P          Completion of Cooling Water Pumping Station (P7, P8, P9)

¡P          Road works on Hung Hing Road

¡P          Completion of ABWF works at WSD Salt Water Pumping Station

¡P          Backfilling works for Tunnel Portion 1

¡P          Completion of all plumbing system

¡P          Completion of ABWF works at Ferry Pier

¡P          Completion of testing and commissioning of movable ramps and disable life

¡P          Installation of seating base plates, steel frames and roof canopy

¡P          Completion of capping beam construction at Tunnel Portion 2

¡P          Completion of reclamation at WCR2

¡P         To cover the dusty material or stockpile by impervious sheet;

¡P         Frequency spray water on the dry dusty road and on the surface of concrete breaking

¡P         To well maintain the mechanical equipments / machineries to avoid abnormal noise nuisance and dark smoke emission

¡P         To conform the installation and setting as in the silt screen and silt curtain deployment plan

¡P         Movable noise barrier shall be deployed for demolition works

¡P         Daily visual inspection of silt screen and silt curtain to ensure its operation properly

¡P         Review silt screen deployment and silt curtain deployment and resubmit associate plans to EPD

¡P         Implement silt screen and silt curtain in accordance with the associated plans submitted to EPD.

 

HY/2009/15

¡P         EVA construction at Eastern Breakwater

¡P         Reinstatement of Eastern Breakwater

¡P         Removal of Seawall Blocks at TS2, TPCWAE & TS4

¡P         Demolition of D-Wall at TS2, TPCWAE &TS4

¡P         Maintenance dredging

¡P         Daily visual inspection of silt screen and silt curtain to ensure its operation properly

¡P         Implement silt curtain in accordance with the associated plans submitted to EPD.

HK/2010/06

¡P         Nil

 

¡P         To conform the installation and setting as in the silt screen and silt curtain deployment plan

¡P         To space out noisy equipment and position as far as possible from sensitive receiver.

¡P         Daily visual inspection of silt screen and silt curtain to ensure its operation properly

HY/2009/19

¡P         Road works at Watson Road

¡P         Bored piling (Land)

¡P         Removal/ Installation of strut at ELS

¡P         Construction of Dolphin Cap

¡P         ELS for Cut &Cover Tunnel and EVB

¡P         Laying of 1500f pipe

¡P         Launching of segments

¡P         Extraction of temporary pile from marine section

¡P         Construction of bridge TA1

¡P         Pre-bored H-pile for Admin. Building continue

¡P         Parapet construction continue

¡P         Wing slab extension for segment continue

¡P         Construction of TD bridge continue

¡P         Construction of Bridge E

¡P         Construction of Bride F4 and F5

¡P         To conform the installation and setting as in the silt screen and silt curtain deployment plan

HK/2012/08

¡P         ELS for box culvert La at Lung King Street

¡P         Filling for seawall rock mound formation

¡P         Filling for reclamation

¡P         To conform the installation and setting as in the silt screen and silt curtain deployment plan

¡P         To space out noisy equipment and position as far as possible from sensitive receiver.

¡P         Daily visual inspection of silt screen and silt curtain to ensure its operation properly

 

HY/2010/08

¡P         Dredging works (works commence subject to handover from other Contract)

¡P         To conform the installation and setting as in the silt screen and silt curtain deployment plan

¡P         Daily visual inspection of silt screen and silt curtain to ensure its operation properly