Contract No: HK/2015/01 Wanchai Development Phase II and Central Wanchai
Bypass Sampling, Field Measurement and Testing Works (Stage 3) Environmental Permit no. EP-356/2009, Further
Evironmental permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 ,
Fep-06/356/2009, FEP-07/356/2009 and Fep-08/356/2009 Monthly
Environmental Monitoring & Audit Report
-
February 2017 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre
Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
March
2017 |
|
|
2.2 Scope of the Project and Site
Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact
Personnel
3 Status of
Regulatory Compliance
3.1 Status of Environmental Licensing and
Permitting under the Project
5.3 Water quality monitoring Results
6.4 Review of the Reasons for and the
Implications of Non-compliance
6.5 Summary of action taken in the event
of and follow-up on non-compliance
7. Cumulative Construction Impact due to
the Concurrent Projects
9.
Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of Water Quality Monitoring
Exceedances in Reporting Month
Table II Summary of Enhanced Dissolved Oxygen
Monitoring Exceedances in Reporting Month
Table 2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details of Individual Contracts under
the Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/01
Table 3.3 Summary of submission status under
FEP-02/356/2009 Condition
Table 3.4 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/02
Table 3.5 Summary of submission status under
FEP-03/356/2009 Condition
Table 3.6 Cumulative Summary of Valid Licences
and Permits under Contract no. HY/2009/15
Table 3.7 Summary of submission status under
FEP-04/356/2009 Condition
Table 3.8 Cumulative Summary of Valid Licences
and Permits under Contract no. HY/2009/19
Table 3.9 Cumulative Summary of
Valid Licences and Permits under Contract no. HK/2012/08
Table
3.10 Summary of submission
status under EP-356/2009 & FEP-06/356/2009 Condition
Table
3.11 Cumulative Summary of
Valid Licences and Permits under Contract no. HY/2010/08
Table
3.12 Summary of submission
status under EP-356/2009 and FEP-07/356/2009 Condition
Table 4.1 Noise Monitoring Station
Table 4.2 Air Monitoring Station
Table 4.3 Marine Water Quality Stations for Water Quality
Monitoring
Table 4.4 Marine Water Quality Monitoring
Frequency and Parameters
Table 4.5 Marine Water Quality Stations for Enhanced Water Quality
Monitoring
Table 5.1 Noise Monitoring Station for Contract
nos. HK/2009/01, HK/2009/02
Table 5.2 Noise Monitoring Station for Contract
no. HY/2009/15
Table 5.3 Noise Monitoring Station for Contract
no. HY/2009/19
Table 5.4
Noise Monitoring Station for Contract no. HY/2010/08
Table 5.5
Air Monitoring Station for Contract no. HK/2009/01
Table 5.6 Air Monitoring Station for Contract
no. HK/2009/02
Table 5.7 Air Monitoring Station for Contract
no. HY/2009/15
Table 5.8 Air Monitoring Stations for Contract
no. HY/2009/19
Table 5.9 Air Monitoring Stations for Contract no.
HK/2012/08
Table 5.10 Air Monitoring Stations for Contract no. HY/2010/08
Table 5.12 Water quality monitoringStations for
Contract no. HK/2009/01
Table 5.13 Water quality monitoringStations for
Contract no. HK/2009/02
Table 5.14 Water quality monitoringStations for Contract no. HK/2012/08
Table 5.15 Water quality monitoringStations for Contract no.
HY/2009/15
Table 5.16 Enhanced Dissolved Oxygen Monitoring Stations for Contract no.
HY/2009/15
Table 5.17 Water quality monitoring Station for Contract no. HY/2010/08
Table 5.18 Enhance Dissolved Oxygen Monitoring Stations for
Contract no. HY/2010/08
Table 5.19 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.20 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.21 Details of Waste Disposal for Contract
no. HY/2009/15
Table 5.22 Details of Waste Disposal for Contract
no. HY/2009/19
Table 5.23 Details of Waste Disposal for Contract
no. HK/2012/08
Table 5.24 Details of Waste Disposal for Contract
no. HY/2010/08
Table 8.1 Summary of Environmental Inspections
for Contract no. HK/2009/01
Table 8.2 Summary of Environmental Inspections for Contract no.
HK/2009/02
Table 8.3 Summary of
Environmental Inpsections for Contract no. HY/2009/15
Table 8.4 Summary of Environmental Inspections for Contract no.
HY/2009/19
Table 8.5 Summary of
Environmental Inspections for Contract no. HK/2012/08
Table 8.6 Summary of
Environmental Inspections for Contract no. HY/2010/08
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful
Prosecutions
Table 10.1 Construction Activities and
Recommended Mitigation Measures in Coming Reporting Month
lIST OF FIGUREs
Figure 2.2 Project Organization
Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation
Implementation Schedule
Appendix 4.1 Action
and Limit Level
Appendix 4.2 Copies
of Calibration Certificates
Appendix 5.1 Monitoring Schedule for
Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and
Graphical Presentations
Appendix 5.3 Air Quality Monitoring
Results and Graphical Presentations
Appendix 5.4 Water Quality Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Summary for Notification of Exceedance
Appendix 10.1 Construction Programme of
Individual Contracts
EXECUTIVE
SUMMARY
i.
This is the Environmental Monitoring and
Audit (EM&A) Monthly Report – February 2017 for the Project of Wan Chai Development Phase II
and Central-Wanchai Bypass under Environmental Permit no. EP-356/2009 and Further
Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009,
FEP-06/356/2009, FEP-07/356/2009 and FEP-08/356/2009. This report presents the environmental
monitoring findings and information recorded during the period of 27th January
2017 to 26th February 2017. The cut-off date of reporting is at
26th of each reporting month.
Construction
Activities for the Reported Period
ii.
During this reporting period, the major work
activities for Contract no. HK/2009/01 included:
·
Nil
iii.
During this reporting period, the major work
activities for Contract no. HK/2009/02 included:
Nil
iv.
During this reporting period, the major work
activities for Contract no. HY/2009/15 included:
·
Reinstatement of Eastern Breakwater
v.
During this reporting period, the major work
activities for Contract no. HY/2009/19 included:
Nil
vi.
During this reporting period, the major work
activities for Contract no. HK/2012/08 included:
·
Installation of Box 1 unit
·
Construction of culver L Bay 8
vii.
During this reporting period, the major work activities
for Contract no. HY/2010/08.
·
Diversion pipe maintenance
·
Preparation for Diaphragm Wall Removal Works
Noise Monitoring
viii.
With respect to the
shift in major construction site portions at Wan Chai North, the noise
monitoring station M1a – Harbour Sports Centre was finely adjusted from East of
Harbour Road Sports Centre to West of Harbour Road Sports Centre on 21 June
2016.
ix.
School examination
was scheduled to be taken place at Henrietta Secondary School from 6 February
2017 to 21 February 2017, the limit level of noise monitoring at station M6 was
adjusted to 65dB(A) during examination period accordingly.
x.
Three limit level exceedances were recorded
at M6 – HK Baptist Church Henrietta School on 7, 13 and 21 February 2017 in the
reporting month. The exceedances were concluded as non-Project related.
xi.
Noise monitoring during daytime and
restricted hour were conducted at the stations M1a, M2b, M3a, M4b, M5b and M6
on a weekly basis in the reporting month.
Air Quality
Monitoring
xii.
Due to interruption
of electricity supply, the 24hr TSP was rescheduled as follows:
CMA1b were
rescheduled from 01 and 13 February 2017 to 02 and 14 February 2017
respectively
CMA3a were
rescheduled from 13 February 2017 to 14 February 2017.
xiii.
One 1hr TSP action
level exceedance was recorded at CMA5b – Pedestrian Plaza on 2 February 2017 in
the reporting month. The exceedance was concluded to be non-Project related.
xiv.
One 24hr TSP action level exceedance was
recorded at CMA5b – Pedestrian Plaza on 18 February 2017 in the reporting
month. The exceedance was concluded to be non-Project related.
xv.
With respect to the proposed demolition of
eastern podium of Oil Street Site Office, the respective air quality monitoring
station CMA1b – Oil Street Site Office was finely adjusted from East podium of
the Oil Street Site Office to the West podium of the Oil Street Site Office on
21 December 2016.
xvi.
1-hour and 24-hour Total Suspended
Particulates (TSP) monitoring were conducted at CMA1b – Oil Street Site Office;
CMA2a – Causeway Bay Community Center; CMA3a – CWB PRE Site Office Area; CMA4a
– Society for the Prevention of Cruelty to Animals; CMA5b – Pedestrian Plaza;
CMA6a – WDII PRE Site Office in the reporting month.
Water Quality
Monitoring
xviii.
With respect to the reinstatement of the silt
screen system for Cooling Water Intakes P7, P8, P9 and WSD Water Intake RW21,
the respective water quality monitoring was reverted to the previous monitoring
location for Water Quality Monitoring Station RW21-P789 from water quality
stations RW21-P789 East (RW21-P789E) and RW21-P789 West (RW21-P789W) from 25
January 2017 onwards.
xix.
With respect to the removal of silt screen at
WQM station RW21-P789 on 26 November 2016, the respective water quality
monitoring at RW21-P789 was adjusted to RW21-P789E and RW21-P789W since 28
November 2016 ebb-tide.
xx.
With respect to the temporarily suspension of
marine construction works at WCR3 Area by Contract HK/2009/02, the installed
silt screen for intake group (P7, P8, P9 and WSD21) was removed on 26 November
2016.
xxi.
As advised by the Contractor of HK/2009/01,
all silt screen remains removal works at P1, P3, P4, P5 and C1 water quality
monitoring stations were completed on 8 May 2016.
xxii.
With respect to the marine works undertaken
at WCR3 by Contract HK/2009/02, the respective water quality monitoring station
C1 associated with Contract HK/2009/01 was updated as in association with
Contract HK/2009/01 and Contract HK/2009/02.
xxiii.
With respect to the marine works undertaken
at CBTS by Contract HY/2010/08, the respective water quality monitoring station
C7 associated with Contract HY/2009/15 was updated as in association with
Contract HY/2009/15 and Contract HY/2010/08.
xxiv.
With respect to the marine works undertaken
at HKCEC2 by Contract HK/2012/08, the respective water quality monitoring
station WSD19, P1, P3, P4, and P5 were associated with Contract HK/2012/08.
Table I Summary of Water Quality Monitoring
Exceedances in Reporting Month
Water quality monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2012/08 |
WSD19 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
P1 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P5 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
RW21-P789 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 & HY/2010/08 |
C7 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
0 |
0 |
2 |
1 |
1 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
- 4-week post construction water quality
monitoring at WSD9, WSD10, WSD15 and WSD17 were completed on 6 Feb 2012 and the
water quality monitoring at WSD 10 and WSD15 were temporary suspended since 8
Feb 2012, and WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8
Feb 2012 onwards.
- C8 and C9 were implemented with
respect to HY/2009/19 from 28 Jan 2012.
- C8 & C9
were temporary suspended since 4 March 2013.
- WSD7 and WSD20 water quality
monitoring were temporarily suspended from 27 Apr 2012.
-
C2, C3 C4e and
C4w water quality monitoring station was temporarily suspended since 22 Apr
2013
-
P1, P3, P4 and P5
were commenced since 24 Apr 2013
- C5e and C5w
water quality monitoring station was temporarily suspended since 29 Jul 2013.
- WSD21 water
quality monitoring station was temporarily suspended since 12 Mar 2014
- WSD9 and
WSD17 water quality monitoring station was temporarily suspended since 8 Sep
2014 flood tide.
- The water quality monitoring station C1 shall be
associated with Contract No. HK/2009/02 upon commencement of marine works under
DP3 at WCR3 area.
- The water quality monitoring station
RW21-P789 was adjusted to RW21-P789E and RW21-P789W since 28 November 2016 ebb-tide.
- The water quality monitoring was
reverted to previous monitoring station RW21-P789 from PW21-P789E and
RW21-P789W from 25 January 2017 onwards.
xxv.
There were 3 action level and 2 limit level of
turbidity exceedances and 1 action level of suspended solid exceedances recorded
in the reporting month.
xxvi.
Investigation found that the turbidity and
suspended solid exceedances recorded in this reporting month were not related
to Project works. The details of the recorded exceedance can be referred to the
Section
6.4.
xxvii.
Enhanced DO monitoring at 3 monitoring
stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was
conducted three days per week during the reporting period. The action and limit
level exceedances of water quality monitoring are summarized in Table
II.
Table II Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
|
|
Water
quality monitoring Station |
Mid-flood |
Mid-ebb |
||
|
Contract
no. |
DO |
DO |
|||
|
|
AL |
LL |
AL |
LL |
|
|
C6 |
0 |
0 |
0 |
0 |
|
|
HY/2009/15 |
Ex-WPCWA SW |
0 |
0 |
0 |
0 |
|
|
Ex-WPCWA SE |
1 |
0 |
0 |
0 |
|
Total |
1 |
0 |
0 |
0 |
|
Remarks:
1.
Enhanced DO monitoring at Windsor House Cooling (Station Ref: C7) was
temporarily suspended since 22 October 2014 with respect to the formation of temporary
reclamation zone TS3 and to be resumed upon removal of the respective temporary
reclamation zone.
2. Enhanced
DO monitoring at Monitoring station Ex-WPCWA SE was temporarily suspended from
31 August 2015 with respect to seawall reinstatement works and formation of
active works area. The Enhance DO monitoring at Ex-WPCWA SE was resumed on 11
May 2016 due to completed section of seawall reinstatement works at Ex-PCWA.
xxviii.
There was 1 action level exceedance recorded
for enhanced dissolved oxygen monitoring in this reporting month. Investigation
found that the exceedances recorded in this reporting month were not related to
Project works. The details of the recorded exceedances can be referred to the Section
6.4.
Complaints,
Notifications of Summons and Successful Prosecutions
xxix.
There was no environmental complaint received
in this reporting month.
Site Inspections
and Audit
xxx.
The Environmental Team (ET) conducted weekly
site inspections for Contract nos. HK/2009/01, HK/2009/02, HY/2009/15, HY/2009/19,
HK/2012/08 and HY/2010/08 under EP no. EP-356/2009 in the reporting month.
Major observations and recommendations made during the audit sessions were
rectified by the Contractors. No non-conformance was identified during the site
inspections.
Future Key Issues
xxxi.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC
Nil
Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East
·
Nil
Contract no.
HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section)
·
Nil
Contract no.
HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
Contract no. HK/2012/08 – Wan Chai Development
Phase II – Central- Wan Chai Bypass at Wan Chai West
·
Construction of Box 1 unit
·
Construction of culvert L Bay 8
Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip
Road 8)
·
Diversion pipe maintenance
·
Preparation for Diaphragm Wall Removal works
1.1.1.
Lam Geotechnics Limited (LGL) has been
appointed to work as the Environmental Team (ET) under Environmental Permit no.
EP-356/2009 and Further Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009,
FEP-04/356/2009, FEP-06/356/2009, FEP-07/356/2009 and FEP-08/356/2009 to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental
monitoring and auditing work carried out in accordance to the Section 10.3 of
EM&A Manual and “Environmental Monitoring and Audit Requirements”
under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit no. EP-356/2009, Further Environmental Permit
no. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-06/356/2009, FEP-07/356/2009
and FEP-08/356/2009 during the period of 27th January 2017 to 26th February 2017. The
cut-off date of reporting is at 26th of each reporting month.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project
Background – summarizes
background and scope of the project, site description, project organization and
contact details of key personnel during the reporting period.
Section 3 Status of
Regulatory Compliance – summarizes the status of valid Environmental Permits / Licenses
during the reporting period.
Section 4 Monitoring
Requirements – summarizes
all monitoring parameters, monitoring methodology and equipment, monitoring
locations, monitoring frequency, criteria and respective event and action plan
and monitoring programmes.
Section 5 Monitoring
Results – summarizes
the monitoring results obtained in the reporting period.
Section 6 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Environmental
Site Audit – summarizes
the findings of weekly site inspections undertaken within the reporting period,
with a review of any relevant
follow-up actions within the
reporting period.
Section 9 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1.
“Wan Chai Development phase II and
Central-Wan Chai Bypass” and “Central-Wan Chai Bypass and Island Eastern
Corridor Link” (hereafter called “the Project”) are Designed Project (DP) under
the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase
II (WDII) is to provide land at Wan Chai North and North Point for construction
of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land
formed under the project will be developed as a world-class waterfront
promenade joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for
the CWB to provide relief to the very congested east-west Connaught Road
Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1.
The Project is located mainly in Wan Chai
North, Causeway Bay and North Point, and is demarcated by Gloucester Road and
Victoria Park Road to the south, Fenwick Pier Street to the west and Tong Shui
Road Interchange to the east, as shown in Figure 2.1.
2.2.2.
The study area encompasses existing
developments along the Wan Chai, Causeway Bay and North Point shorelines. Major
land uses include the Hong Kong Convention & Exhibition Centre (HKCEC)
Extension, the Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area
(ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police Officers’ Club,
the Causeway Bay Typhoon Shelter (CBTS) and commercial and residential
developments.
2.2.3.
The scope of the
Project comprises:
·
Land formation for key transport
infrastructure and facilities, including the Trunk Road (i.e. CWB) and the
associated slip roads for connection to the Trunk Road and for through traffic
from Central to Wan Chai and Causeway Bay. The land formed for the above transport
infrastructure will provide opportunities for the development of an attractive
waterfront promenade for the enjoyment of the public
·
Reprovisioning / protection of the existing
facilities and structures affected by the land formation works mentioned above
·
Extension, modification, reprovisioning or
protection of existing storm water drainage outfalls, sewerage outfalls and
watermains affected by the revised land use and land formation works mentioned
above
·
Upgrading of hinterland storm water drainage
system and sewerage system, which would be rendered insufficient by the land
formation works mentioned above
·
Provision of the ground level roads,
flyovers, footbridges, necessary transport facilities and the associated
utility services
·
Construction of the new waterfront promenade,
landscape works and the associated utility services
·
The Trunk Road (i.e. CWB) within the study
area and the associated slip roads for connection to the Trunk Road.
2.2.4.
The project also contains various Schedule 2
DPs that, under the EIAO, require Environmental Permits (Eps) to be granted by
the DEP before they may be either constructed or operated. Table 2.1
summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB)
including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and
A.7 |
Trunk road and road tunnel
more than 800 m in length |
DP2 |
Road P2 and other roads
which are classified as primary/district distributor roads |
Schedule 2, Part I, A.1 |
Primary / district
distributor roads |
DP3 |
Reclamation works including
associated dredging works |
Schedule 2, Part I, C.1 and
C.12 |
Reclamation more than 5 ha
in size and a dredging operation less than 100 m from a seawater intake point
|
DP5 |
Wan Chai East Sewage Outfall
|
Schedule 2, Part I, F.5 and
F.6 |
Submarine sewage pipelines
with a total diameter more than 1,200 mm and include a submarine sewage
outfall |
DP6 |
Dredging for the
Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less
than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the
Project, there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. Contractors of individual contracts will
be required by the EP holder to apply Further Environmental Permits (FEP) such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are
summarized in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HK/2009/01 |
Wan Chai Development Phase
II – Central –Wanchai Bypass at Hong Kong Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase
II – Central – Wan Chai Bypass at WanChai East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase
II and Central – Wan Chai Bypass – North Point Reclamation |
DP3 |
17 March 2010 (Completed) |
HY/2009/15 |
Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase
II-Central-Wan Chai Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 (Completed) |
04/HY/2006 |
Reconstruction of Bus
Terminus near Man Yiu Street and Man Kwong Street |
DP1 |
September
2010 (Completed) |
HY/2009/17 |
Central – Wan Chai Bypass
(CWB) at FEHD Whitfield Depot – Advanced piling works. |
DP1 |
5
October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass
(CWB) – Central Interchange |
DP1 |
21
April 2011 |
HY/2009/19 |
Central – Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2012/08 |
Wan Chai Development Phase II Central- Wan Chai Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass
Tunnel – Tunnel (Slip Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central-Wan Chai Bypass
(CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with
Tunnel Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the
construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines
of communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and
contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative
for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative
for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun Wo – Leader Joint
Venture |
Contractor under Contract
no. HK/2009/01 |
Project Manager |
Mr. Simon Liu |
9304 8355 |
2587 1878 |
Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Environmental Officer |
Mr. Terry Tsang |
6683 9394 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract
no. HK/2009/02 |
Project Manager |
Mr. Paul Yu |
3658-3085 |
2827 9996 |
Quality & Environmental
Manager |
Mr. C.P. Ho |
9191 8856 |
|||
China State Construction
Engineering (HK) Ltd. |
Contractor under Contract
no. HY/2009/15 |
Project Director |
Chris Leung |
3557 6393 |
2566 2192 |
Senior Site Manager |
Y Huo |
3557 6368 |
|||
Contractor’s Representative |
Rex Lau |
3557 6405 |
|||
Environmental Officer |
Andy Mak |
3557 6347 |
|
||
Chun Wo – CRGL – MBEC Joint Venture |
Contractor under Contract
no. HY/2009/19 |
Project Manager |
Rayland Lee |
3758 6788 |
2570 8013 |
Site
Agent |
David Lau |
3758 8879 |
|||
Deputy Site Agent |
Eric Fong |
6191 9337 |
|||
Environmental Manager / Environmental Officer |
M.H. Isa |
9884 0810 |
|||
|
|
Construction Manager (Marine) |
Andy Chan |
9879 4325 |
|
Construction
Manager (Land) |
Bear Ding |
6483 6198 |
|||
Operation
Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
China State- Build King Joint Venture |
Contractor under Contract no. HK/2012/08 |
Project
Director |
C. N. Lai |
9106 5806 |
2877 1522 |
Project
Manager |
Eddie Chung |
9189 8118 |
|||
Site
Agent |
Keith Tse |
9037 1839 |
|||
Environmental
Officer |
James
Ma |
9130 9549 |
|||
Environmental
Supervisor |
Y.
L. Ho |
9856 5669 |
|||
China State |
Contractor under Contract no. HY/2010/08 |
Project
Director |
Chris
Leung |
3467 4299 |
2566 8061 |
|
|
Project
Manager |
Chan
Ying Lun |
3418 3001 |
|
|
|
Site Agent |
Francis Suen |
6672 0311 |
|
|
|
Environmental
Officer |
Gabriel
Wong |
35576466 |
|
|
|
Environmental
Supervisor |
Desmond
Ho Tsz Ho |
3557 6466 |
|
Ramboll
Environ Hong Kong Limited |
Independent Environmental Checker (IEC) |
Independent Environmental
Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader
(ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HK/2009/01, the principal
work activities in this reporting month included:
Nil
2.4.4.
For Contract no. HK/2009/02, the principal
work activities in this reporting month included:
Nil
2.4.5.
For Contract no. HY/2009/15, the principal
work activities in this reporting month included:
·
Reinstatement of Eastern Breakwater
2.4.6.
For Contract no. HY/2009/19, the principal
work activity in this reporting month included:
Nil
2.4.7.
For Contract no. HK/2012/08, the principal
work activity in this reporting month included:
·
Installation for Box 1 unit
·
Construction of culvert L Bay 8
2.4.8.
For Contract no. HY/2010/08, no principal
work activities this reporting month.
·
Diversion pipe maintenance
·
Preparation for Diaphragm Wall Removal Works
2.4.9.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC
Nil
Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai East
·
Nil
Contract no.
HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section)
·
Nil
Contract no.
HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
Nil
Contract no.
HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West
·
Construction of Box 1 unit
·
Construction of culvert L Bay 8
Contract no.
HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)
·
Diversion pipe maintenance
·
Preparation for Diaphragm Wall Removal Works
3.1.1.
A summary of the current status on licences
and/or permits on environmental protection pertinent to the Project is shown in
Table 3.1.
Table 3.1 Summary
of the current status on licences and/or permits on environmental protection
pertinent to the Project
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Superseded |
Environmental Permit |
EP-364/2009/C |
11 Jul 2014 |
Superseded |
Environmental Permit |
EP-364/2009/D |
24 Nov 2016 |
Superseded |
Environmental Permit |
EP-364/2009/E |
22 Dec 2016 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Surrendered |
Further Environmental Permit |
FEP-01/364/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
21 Apr
2010 |
Valid |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul
2010 |
Surrendered |
Further Environmental Permit |
FEP-04/364/2009/A |
14 Oct
2010 |
Surrendered |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-06/364/2009/A |
22 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-07/364/2009/B |
20 Sep
2012 |
Surrendered |
Further Environmental Permit |
FEP-07/364/2009/D |
24 Nov
2015 |
Valid |
Further Environmental Permit |
FEP-08/364/2009/A |
15 Jun
2012 |
Surrendered |
Further Environmental Permit |
FEP-06/356/2009 |
5 Mar 2013 |
Valid |
Further Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
Superseded |
Further Environmental Permit |
FEP-08/356/2009 |
1 Aug 2016 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/E |
22 Dec 2016 |
Valid |
3.1.2.
Due to the multi-contract nature of the
Project, the status of permits and/or licences under the individual contract(s)
are presented as below:
Contract no. HK/2010/06 – Wan Chai
Development Phase II – Central – Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-05/356/2009
3.1.3.
The construction works were completed and the
FEP-05/356/2009 was surrendered by the Contractor on 3 October 2014.
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC
3.1.4.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission for
contract no. HK/2009/01 under FEP-02/356/2009 are shown in Table 3.2 and
Table 3.3.
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits
and/or Licences |
Reference
No. |
Issued Date
|
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |