Contract No: HK/2015/01

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Works (Stage 3)

 

Environmental Permit no. EP-356/2009,

Further Evironmental permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 , Fep-06/356/2009, FEP-07/356/2009 and Fep-08/356/2009

 

Monthly Environmental Monitoring & Audit Report

 

-       January 2018 -


CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

   February 2018

 

 


Table of contents

 

1      Introduction.. 10

1.1          Scope of the Report 10

1.2          Structure of the Report 11

2      Project Background.. 12

2.1          Background. 12

2.2          Scope of the Project and Site Description.. 12

2.3          Division of the Project Responsibility. 14

2.4          Project Organization and Contact Personnel 16

3      Status of Regulatory Compliance.. 20

3.1          Status of Environmental Licensing and Permitting under the Project 20

4      Monitoring Requirements. 33

4.1          Noise Monitoring. 33

4.2          Air Monitoring. 34

4.3          Water Quality Monitoring. 37

5.       Monitoring Results. 44

5.1          Air Monitoring Results. 47

5.2          Water quality monitoring Results. 49

5.4          Waste Monitoring Results. 54

6.       Compliance Audit.. 61

6.1        Noise Monitoring. 61

6.2        Air Monitoring. 61

6.3        Water Quality Monitoring. 62

6.4        Review of the Reasons for and the Implications of Non-compliance. 62

6.5        Summary of action taken in the event of and follow-up on non-compliance  62

7.       Cumulative Construction Impact due to the Concurrent Projects  63

8.       Environmental Site Audit.. 64

9. Complaints, Notification of Summons and Prosecution.. 66

10.    Conclusion.. 67


lIST OF TABLES

 

Table I        Summary of Water Quality Monitoring Exceedances in Reporting Month

Table II       Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Table 2.1    Schedule 2 Designated Projects under this Project

Table 2.2     Details of Individual Contracts under the Project

Table 2.3     Contact Details of Key Personnel

Table 3.1     Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.2     Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.3     Summary of submission status under FEP-02/356/2009 Condition

Table 3.4     Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.5     Summary of submission status under FEP-03/356/2009 Condition

Table 3.6     Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.7     Summary of submission status under FEP-04/356/2009 Condition

Table 3.8     Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Table 3.9     Cumulative Summary of Valid Licences and Permits under Contract no. HK/2012/08

Table 3.10   Summary of submission status under EP-356/2009 & FEP-06/356/2009 Condition

Table 3.11   Cumulative Summary of Valid Licences and Permits under Contract no. HY/2010/08

Table 3.12   Summary of submission status under EP-356/2009 and FEP-07/356/2009 Condition

Table 4.1     Noise Monitoring Station

Table 4.2     Air Monitoring Station

Table 4.3    Marine Water Quality Stations for Water Quality Monitoring

Table 4.4     Marine Water Quality Monitoring Frequency and Parameters

Table 4.5    Marine Water Quality Stations for Enhanced Water Quality Monitoring

Table 5.1    Noise Monitoring Station for Contract nos. HK/2009/01, HK/2009/02

Table 5.2    Noise Monitoring Station for Contract no. HY/2009/15

Table 5.3    Noise Monitoring Station for Contract no. HY/2009/19

Table 5.4    Noise Monitoring Station for Contract no. HY/2010/08

Table 5.5    Air Monitoring Station for Contract no. HK/2009/01

Table 5.6    Air Monitoring Station for Contract no. HK/2009/02

Table 5.7    Air Monitoring Station for Contract no. HY/2009/15

Table 5.8    Air Monitoring Stations for Contract no. HY/2009/19

Table 5.9     Air Monitoring Stations for Contract no. HK/2012/08

Table 5.10   Air Monitoring Stations for Contract no. HY/2010/08

Table 5.11   Water quality monitoringStations for contracts with respect to remaining DP3 work areas after the completion of DP5 & DP6 in 2012 and intake diversion in 2013

Table 5.12   Water quality monitoringStations for Contract no. HK/2009/01

Table 5.13   Water quality monitoringStations for Contract no. HK/2009/02

Table 5.14   Water quality monitoringStations for Contract no. HK/2012/08

Table 5.15   Water quality monitoring Station for Contract no. HY/2010/08

Table 5.16   Enhance Dissolved Oxygen Monitoring Stations for Contract no. HY/2010/08

Table 5.17   Details of Waste Disposal for Contract no. HK/2009/01

Table 5.18   Details of Waste Disposal for Contract no. HK/2009/02

Table 5.19   Details of Waste Disposal for Contract no. HY/2009/15

Table 5.20   Details of Waste Disposal for Contract no. HY/2009/19

Table 5.21  Details of Waste Disposal for Contract no. HK/2012/08

Table 5.22  Details of Waste Disposal for Contract no. HY/2010/08

Table 8.5     Summary of Environmental Inspections for Contract no. HK/2012/08

Table 9.1     Cumulative Statistics on Complaints

Table 9.2     Cumulative Statistics on Successful Prosecutions

Table 10.1   Construction Activities and Recommended Mitigation Measures in Coming Reporting Month

 

 

 

 

lIST OF FIGUREs

 

Figure 2.1     Project Layout

Figure 2.2     Project Organization Chart

Figure 4.1    Locations of Environmental Monitoring Stations

 

 

 

lIST OF APPENDIces

 

Appendix 3.1    Environmental Mitigation Implementation Schedule

Appendix 4.1    Action and Limit Level

Appendix 4.2    Copies of Calibration Certificates

Appendix 5.1    Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2    Noise Monitoring Results and Graphical Presentations

Appendix 5.3    Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4    Water Quality Monitoring Results and Graphical Presentations

Appendix 6.1    Event Action Plans

Appendix 6.2    Summary for Notification of Exceedance

Appendix 9.1    Complaint Log

Appendix 10.1  Construction Programme of Individual Contracts


EXECUTIVE SUMMARY

       i.        This is the Environmental Monitoring and Audit (EM&A) Monthly Report – January 2018 for the Project of Wan Chai Development Phase II and Central-Wanchai Bypass under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-06/356/2009, FEP-07/356/2009 and FEP-08/356/2009. This report presents the environmental monitoring findings and information recorded during the period of 27 December 2017 to 26 January 2018. The cut-off date of reporting is at 26th of each reporting month.

 

      ii.        In the reporting month, the principal work activities of individual contracts conducted are as follow:

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East

·          Nil

Contract no. HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

Ÿ   Nil

Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West

Ÿ   Trimming of rock level

 

Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)

Ÿ   Diversion pipe maintenance

Ÿ   Diaphragm wall removal works

Ÿ   Removal of reclamation at TS3E and TS3W

 

Noise Monitoring

     iii.        With respect to the shift in major construction site portions at Wan Chai North, the noise monitoring station M1a – Harbour Sports Centre was finely adjusted from East of Harbour Road Sports Centre to West of Harbour Road Sports Centre on 21 June 2016.

     iv.        With respect to the demolition of Ex-Harbour Road Sports Centre, the respective noise monitoring station M1a – Harbour Road Sports Centre were finely adjusted on 16 and 25 May 2017 and thereafter to the Footbridge for Harbour Road Sports for noise monitoring.

      v.        Three limit level exceedances were recorded at M1a – Footbridge for Harbour Road Sports Centre on 28 December 2017, 16 and 23 January 2018 in the reporting month. After the investigation, the exceedances were concluded as non-Project related.

     vi.        Noise monitoring during daytime and restricted hour were conducted at the stations M1a, M2b, M3a, M4b, M5b and M6 on a weekly basis in the reporting month.

 

Air Quality Monitoring

    vii.        One 1hr TSP action level exceedances were recorded at CMA5b – Pedestrian Plaza on 29 December 2017 in the reporting month. After the investigation, the exceedance was concluded as non-Project related.

   viii.        With respect to the proposed demolition of the Oil Street Site Office, the respective air quality monitoring station CMA1b – Oil Street Site Office was finely adjusted from the Oil Street Site Office to Harbour Grand Hotel Boundary Wall from 05 June 2017 onwards.

     ix.        With respect to the proposed demolition of eastern podium of Oil Street Site Office, the respective air quality monitoring station CMA1b – Oil Street Site Office was finely adjusted from East podium of the Oil Street Site Office to the West podium of the Oil Street Site Office on 21 December 2016.

      x.        1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b – Oil Street Site Office; CMA2a – Causeway Bay Community Center; CMA3a – CWB PRE Site Office Area; CMA4a – Society for the Prevention of Cruelty to Animals; CMA5b – Pedestrian Plaza; CMA6a – WDII PRE Site Office in the reporting month.

 

Water Quality Monitoring

     xi.        Action and Limit level of water quality monitoring was transited from wet season to dry season from 01 October 2017.

    xii.        Water quality monitoring station C7 and Enhance DO monitoring station C6 shall be associated with Contract HY/2010/08, upon confirmation of marine construction works completion under Contract HY/2009/15 at CBTS area and Ex-PCWA area since 19 June 2017.

   xiii.        Referring to CWB RSS confirmation on the completion of marine construction activities within the Ex-PCWA area and the completion of the post construction water quality monitoring, the respective Enhance DO Monitoring within Ex-PCWA for monitoring station Ex-PCWA SE and Ex-PCWA SW was temporarily suspended since 07 March 2017 ebb tide onwards.

   xiv.        With respect to the reinstatement of the silt screen system for Cooling Water Intakes P7, P8, P9 and WSD Water Intake RW21, the respective water quality monitoring was reverted to the previous monitoring location for Water Quality Monitoring Station RW21-P789 from water quality stations RW21-P789 East (RW21-P789E) and RW21-P789 West (RW21-P789W) from 25 January 2017 onwards.

    xv.        With respect to the removal of silt screen at WQM station RW21-P789 on 26 November 2016, the respective water quality monitoring at RW21-P789 was adjusted to RW21-P789E and RW21-P789W since 28 November 2016 ebb-tide.

   xvi.        With respect to the temporarily suspension of marine construction works at WCR3 Area by Contract HK/2009/02, the installed silt screen for intake group (P7, P8, P9 and WSD21) was removed on 26 November 2016.

  xvii.        As advised by the Contractor of HK/2009/01, all silt screen remains removal works at P1, P3, P4, P5 and C1 water quality monitoring stations were completed on 8 May 2016.

 xviii.        With respect to the marine works undertaken at WCR3 by Contract HK/2009/02, the respective water quality monitoring station C1 associated with Contract HK/2009/01 was updated as in association with Contract HK/2009/01 and Contract HK/2009/02.

   xix.        With respect to the marine works undertaken at CBTS by Contract HY/2010/08, the respective water quality monitoring station C7 associated with Contract HY/2009/15 was updated as in association with Contract HY/2009/15 and Contract HY/2010/08.

    xx.        With respect to the marine works undertaken at HKCEC2 by Contract HK/2012/08, the respective water quality monitoring station WSD19, P1, P3, P4, and P5 were associated with Contract HK/2012/08.

   xxi.        As confirmed by WDII RSS, the marine construction works under Contract HK/2009/01 have been completed since 24 July 2017, the monitoring association with Contract HK/2009/01 and relevant reporting has been ceased in the reporting month.

  xxii.        As confirmed by CWB RSS, the marine construction works under Contract HY/2009/15 and relevant reporting have been completed by 19 June 2017, the monitoring association with Contract HY/2009/15 and relevant reporting has been ceased in the reporting month.

 xxiii.        Based on Contractor confirmed site information on no marine construction activities on 01 January 2018, the respective scheduled water quality monitoring event at all WQM stations and enhanced DO monitoring was temporary suspended on 01 January 2018 during ebb tide and flood tide accordingly.

 

 

 

 

 

 

 

 

 

 

Table I    Summary of Water Quality Monitoring Exceedances in Reporting Month

Contract no.

Water quality monitoring Station

Mid-flood

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HK/2009/02

C1

0

0

0

0

0

0

0

0

0

0

0

0

HK/2012/08

WSD19

0

0

4

0

0

0

0

0

0

0

0

0

P1

0

0

0

0

0

0

0

0

0

0

0

0

P3

0

0

0

0

0

0

0

0

0

0

0

0

P4

0

0

0

0

0

0

0

0

0

0

0

0

P5

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/02

RW21-P789

0

0

1

1

0

0

0

0

0

0

0

0

HY/2010/08

C7

0

0

0

1

0

0

0

0

0

0

0

0

Total

0

0

5

2

0

0

0

0

0

0

0

0

Remarks:

1.     The cessation of seawater intake operation for C6 was confirmed on 17 May 2011 and the water quality monitoring at C6 was then terminated since 17 May 2011.

2.     4-week post construction water quality monitoring at WSD9, WSD10, WSD15 and WSD17 were completed on 6 Feb 2012 and the water quality monitoring at WSD 10 and WSD15 were temporary suspended since 8 Feb 2012, and WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8 Feb 2012 onwards.

3.     C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.

4.     C8 & C9 were temporary suspended since 4 March 2013.

5.     WSD7 and WSD20 water quality monitoring were temporarily suspended from 27 Apr 2012.

6.     C2, C3 C4e and C4w water quality monitoring station was temporarily suspended since 22 Apr 2013

7.     P1, P3, P4 and P5 were commenced since 24 Apr 2013

8.     C5e and C5w water quality monitoring station was temporarily suspended since 29 Jul 2013.

9.     WSD21 water quality monitoring station was temporarily suspended since 12 Mar 2014

10.   WSD9 and WSD17 water quality monitoring station was temporarily suspended since 8 Sep 2014 flood tide.

11.   The water quality monitoring station C1 shall be associated with Contract No. HK/2009/02 upon commencement of marine works under DP3 at WCR3 area.

12.   The water quality monitoring station RW21-P789 was adjusted to RW21-P789E and RW21-P789W since 28 November 2016 ebb-tide.

13.   The water quality monitoring was reverted to previous monitoring station RW21-P789 from PW21-P789E and RW21-P789W from 25 January 2017 onwards.

xxiv.        5 action level and 2 limit level exceedances of Turbidity were recorded in the reporting month.  After investigation, the exceedances were concluded as non-Project related. The details of the recorded exceedances can be referred to Section 6.4.

 

xxv.        Enhanced DO monitoring at 1 monitoring station in Causeway Bay Typhoon Shelter was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table II.

Table II   Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in

Reporting Month

 

 

Enhanced DO monitoring station

Mid-flood

Mid-ebb

 

Contract no.

DO

DO

 

 

AL

LL

AL

LL

 

HY/2010/08

C6

0

0

0

0

 

Total

0

0

0

0

 

Remarks:

1.    Enhanced DO monitoring at Windsor House Cooling (Station Ref: C7) was temporarily suspended since 22 October 2014 with respect to the formation of temporary reclamation zone TS3 and to be resumed upon removal of the respective temporary reclamation zone.

2.    Enhanced DO monitoring at Monitoring station Ex-WPCWA SE was temporarily suspended from 31 August 2015 with respect to seawall reinstatement works and formation of active works area. The Enhance DO monitoring at Ex-WPCWA SE was resumed on 11 May 2016 due to completed section of seawall reinstatement works at Ex-PCWA.

xxvi.        No action or limit level exceedance for Enhanced Dissolved Oxygen monitoring recorded in this reporting month.

 

Complaints, Notifications of Summons and Successful Prosecutions

xxvii.        No environmental complaint received in this reporting month.

 

Site Inspections and Audit

xxviii.        The Environmental Team (ET) conducted weekly site inspections for Contract nos. HK/2009/01, HK/2009/02, HY/2009/19, HK/2012/08 and HY/2010/08 under EP no. EP-356/2009 in the reporting month. Major observations and recommendations made during the audit sessions were rectified by the Contractors. No non-conformance was identified during the site inspections.

 

 

 

 

 

Future Key Issues

xxix.        In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East

·          Nil

Contract no. HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

Ÿ   Nil

Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West

Ÿ   Trimming of rock level

Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)

Ÿ   Diversion pipe maintenance

Ÿ   Diaphragm Wall Removal Works

Ÿ   Removal of reclamation at TS3E and TS3W

1      Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-06/356/2009, FEP-07/356/2009 and FEP-08/356/2009 to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and “Environmental Monitoring and Audit Requirements” under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works for Environmental Permit no. EP-356/2009, Further Environmental Permit no. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-06/356/2009, FEP-07/356/2009 and FEP-08/356/2009 during the period of 27 December 2017 to 26 January 2018. The cut-off date of reporting is at 26th of each reporting month.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.2          Structure of the Report

 

Section 1        Introduction – details the scope and structure of the report.

 

Section 2        Project Background – summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3        Status of Regulatory Compliance – summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4        Monitoring Requirements – summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5        Monitoring Results – summarizes the monitoring results obtained in the reporting period.

 

Section 6        Compliance Audit – summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7        Cumulative Construction Impact due to the Concurrent Projects summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8        Environmental Site Audit – summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9        Complaints, Notification of summons and Prosecution – summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10       Conclusion

2      Project Background

2.1          Background

2.1.1.     “Wan Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

2.2          Scope of the Project and Site Description

2.2.1.     The Project is located mainly in Wan Chai North, Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road Interchange to the east, as shown in Figure 2.1.

2.2.2.     The study area encompasses existing developments along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police Officers’ Club, the Causeway Bay Typhoon Shelter (CBTS) and commercial and residential developments.

2.2.3.     The scope of the Project comprises:

·          Land formation for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for connection to the Trunk Road and for through traffic from Central to Wan Chai and Causeway Bay. The land formed for the above transport infrastructure will provide opportunities for the development of an attractive waterfront promenade for the enjoyment of the public

·          Reprovisioning / protection of the existing facilities and structures affected by the land formation works mentioned above

·          Extension, modification, reprovisioning or protection of existing storm water drainage outfalls, sewerage outfalls and watermains affected by the revised land use and land formation works mentioned above

·          Upgrading of hinterland storm water drainage system and sewerage system, which would be rendered insufficient by the land formation works mentioned above

·          Provision of the ground level roads, flyovers, footbridges, necessary transport facilities and the associated utility services

·          Construction of the new waterfront promenade, landscape works and the associated utility services

·          The Trunk Road (i.e. CWB) within the study area and the associated slip roads for connection to the Trunk Road.

2.2.4.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (Eps) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1      Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3          Division of the Project Responsibility

2.3.1.     Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced. Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits (FEP) such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.     The details of individual contracts are summarized in Table 2.2.

Table 2.2 Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HK/2009/01

Wan Chai Development Phase II – Central –Wanchai Bypass at Hong Kong Convention and Exhibition Centre

DP3, DP6

23 July 2010

DP1, DP2

25 August 2011 (Completed)

HK/2009/02

Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East

DP3, DP5

5 July 2010

DP1

26 April 2011

HY/2009/11

Wan Chai Development Phase II and Central – Wan Chai Bypass – North Point Reclamation

DP3

17 March 2010

(Completed)

HY/2009/15

Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

DP3

10 November 2010

DP1

13 July 2011 (Completed)

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

(Completed)

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

(Completed)

HY/2009/17

Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works.

DP1

5 October 2010

(Completed)

HY/2009/18

Central – Wan Chai Bypass (CWB) – Central Interchange

DP1

21 April 2011

HY/2009/19

Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

HK/2012/08

Wan Chai Development Phase II Central-

Wan Chai Bypass at Wan Chai

West

DP1,DP2, DP3

10 March 2014

HY/2010/08

Central- Wanchai Bypass Tunnel – Tunnel (Slip Road 8)

DP1, DP2, DP3

21 March 2013

HY/2011/08

Central-Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

DP1

8 October 2014

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3 Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer’s Representative for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer’s Representative for CWB

Principal Resident Engineer

Mr. Peter Poon

3912 3388

3912 3328

Chun Wo – Leader Joint Venture

Contractor under Contract no. HK/2009/01

Project Manager

Mr. Simon Liu

9304 8355

2587 1878

Environmental Officer

Mr. Terry Tsang

6683 9394

Chun Wo – CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Project Manager

Mr. Paul Yu

3658 3085

2827 9996

Quality & Environmental Manager

Mr. C.P. Ho

9191 8856

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Mr. Chris Leung

3557 6393

2566 2192

 

Site Agent

Mr. Patrick Ho

3557 6405

Construction Manager

Mr. Tom Tong

3557 6415

Environmental Officer

Mr. Desmond Ho

3557 6347

Environmental Supervisor

Mr. Gordon Lai

6145 6365

Chun Wo – CRGL – MBEC Joint Venture

 

Contractor under Contract no. HY/2009/19

 

Site Agent

Mr. David Lau

3758 8879

3757 8901

Deputy Site Agent

Mr. Andy Chan

9879 4325

Environmental Manager /

Environmental Officer

Mr. M.H. Isa

9884 0810

Construction Manager (Marine)

Mr. Wingo Wong

9300 2625

Construction Manager (Land)

Mr. Ray Ho

9608 6366

Construction Manager (Land)

Mr. Yung Kwok Wah

9834 1010

China State-

Build King Joint Venture

Contractor

under Contract

no. HK/2012/08

Project Director

Mr. C. N. Lai

9106 5806

2877 1522

Site Agent

Mr. George Cheung

9268 1918

Environmental Officer

Mr. James Ma

9130 9549

Environmental Supervisor

Mr. Y. L. Ho

9856 5669

China State

 

Contractor

under Contract

no. HY/2010/08

Project Director

Mr. Chris Leung

3467 4299

2566 8061

 

Project Manager

Mr. Chan Ying Lun

3418 3001

Site Agent

Mr. Thomas Lui

3557 6452

Marine Manager

Mr. Nickael Chan

3557 6333

Construction Manager

Mr. Tom Tong

3557 6367

Environmental Officer

Mr. Gabriel Wong

35576466

Ramboll Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3465 2888

3465 2899

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.4.3.     In the reporting month, the principal work activities of individual contracts conducted are as follow:

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East

·          Nil

Contract no. HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

Ÿ   Nil

Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West

Ÿ   Trimming of rock level

Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)

Ÿ   Diversion pipe maintenance

Ÿ   Diaphragm wall removal works

Ÿ   Removal of reclamation at TS3E and TS3W

 

2.4.4.     In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East

·          Nil

Contract no. HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

Ÿ   Nil

Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West

Ÿ   Trimming of rock level

Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)

·          Diversion pipe maintenance

·          Diaphragm Wall Removal Works

·          Removal of reclamation at TS3E and TS3W

3      Status of Regulatory Compliance

3.1          Status of Environmental Licensing and Permitting under the Project

3.1.1.     A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1 Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009/E

22 Dec 2016

Valid

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Surrendered

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

22 Nov 2010

Valid

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

Surrendered

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 Jul 2010

Surrendered

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Surrendered

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/B

20 Sep 2012

Surrendered

Further Environmental Permit

FEP-07/364/2009/D

24 Nov 2015

Valid

Further Environmental Permit

FEP-08/364/2009/A

15 Jun 2012

Surrendered

Further Environmental Permit

FEP-06/356/2009

5 Mar 2013

Valid

Further Environmental Permit

FEP-07/356/2009

26 July 2013

Valid

Further Environmental Permit

FEP-09/364/2009/B

5 March 2013

Valid

Further Environmental Permit

FEP-10/364/2009/B

26 July 2013

Valid

Further Environmental Permit

FEP-08/356/2009

1 Aug 2016

Valid

Further Environmental Permit

FEP-11/364/2009/E

22 Dec 2016

Valid

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.1.2.     Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HK/2009/01 – Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC

3.1.3.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HK/2009/01 under FEP-02/356/2009 are shown in Table 3.2 and Table 3.3.

Table 3.2 Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

N/A

Valid

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088

06 Jan 2010

N/A

Valid

Discharge Licence

WT00024952-2016

6 Jul 2016

31 Jul 2021

Valid

WT00024844-2016

29 Jun 2016

31 Mar 2020

Valid

Billing account under Waste Disposal Ordinance

7010069

21 Jan 2010

N/A

Valid

Registration as a Chemical Waste Producer

WPN5213-134-C3585-01

21 Jan 2010

N/A

Valid

 

Table 3.3 Summary of submission status under FEP-02/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

13 Apr 2010

Condition 2.7

Works Schedule and Location Plan

8 Apr 2010

Condition 2.8

Silt Curtain Deployment Plan (Rev. 5)

24 Aug 2012

Condition 2.9

Silt Screen Deployment Plan (Rev. 9)

5 Nov 2015

Conditions 2.8 and 2.9

Supplementary Document on Silt Curtain and Silt Screen Deployment Plan

19 Jul 2010

Report on Field Testing for Silt Curtain

26 Aug 2010

Report on Field Testing for Silt Curtain (Rev. A)

15 Nov 2010

Condition 2.12(d)

Alternative Proposal on Concurrent Dredging for Sewage Pipeline and Cross Harbour Water Mains

15 Apr 2011

Condition 2.17

Noise Management Plan

23 Apr 2010

Condition 2.18

Landscape Plan (Erection of Decorative Screen Hoarding along Construction Site around Hong Kong Exhibition and Convention Centre)

15 May 2010

Landscape Plan (Night-time Lighting)

22 Oct 2010

Landscape Plan (Rev. B)