Contract No:
HK/2009/05 Wanchai Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing Work
(Stage 1) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEp-06/364/2009/a and FEP-07/364/2009/A Monthly Environmental Monitoring
& Audit Report
- April
2011 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai,
H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
6 May 2011 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise
Monitoring Results
6.2 Real Time Noise
Monitoring
6.4 Review
of the Reasons for and the Implications of Non-compliance
6.5 Summary
of action taken in the event of and follow-up on non-compliance
7. Cumulative Construction Impact due to the
Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF
TABLES
Table 2.1 Schedule 2
Designated Projects under this Project
Table 2.2 Details of
Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/17
Table 3.3 Summary of
submission status under FEP-03/364/2009
Table 3.4 Cumulative Summary
of Valid Licences and Permits under Contract no. 04/HY/2006
Table 3.5 Summary of
submission status under FEP-04/364/2009/A
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.7 Summary of
submission status under FEP-02/364/2009
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.9 Summary of
submission status under FEP-01/364/2009
Table 3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Table 3.11 Summary of
submission status under FEP-05/364/2009/A
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table 3.13 Summary of
submission status under FEP-06/364/2009/A
Table 3.14 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Table 3.15 Summary of
submission status under FEP-07/364/2009/A
Table 4.1 Noise
Monitoring Stations
Table 4.2 Real Time
Noise Monitoring Stations
Table 4.3 Air
Monitoring Stations
Table 5.1 Noise Monitoring
Stations for Contract no. HY/2009/17
Table 5.2 Noise
Monitoring Stations for Contract nos. 04/HY/2006 and HY/2009/18
Table 5.3 Noise
Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Table 5.4 Noise
Monitoring Stations for Contract no. HY/2009/15
Table 5.5 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 5.6 Real Time
Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.7 Real Time
Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Air
Monitoring Station for Contract no. HY/2009/17
Table 5.9 Air
Monitoring Stations for Contract no. 04/HY/2006 and HY/2009/18
Table 5.10 Air
Monitoring Station for Contract no. HK/2009/01
Table 5.11 Air
Monitoring Station for Contract no. HK/2009/02
Table 5.12 Air
Monitoring Station for Contract no. HY/2009/15
Table 5.13 Air
Monitoring Stations for Contract no. HY/2009/19
Table 5.12 Details of
Waste Disposal for Contract no. HY/2009/17
Table 5.13 Details of
Waste Disposal for Contract no. 04/HY/2006
Table 5.14 Details of
Waste Disposal for Contract no. HK/2009/01
Table 5.15 Details of
Waste Disposal for Contract no. HK/2009/02
Table 5.16 Details of
Waste Disposal for Contract no. HY/2009/18
Table 5.17 Details of
Waste Disposal for Contract no. HY/2009/15
Table 5.18 Details of
Waste Disposal for Contract no. HY/2009/19
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/17
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project
Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation
Schedule
Appendix 4.1 Action
and Limit Level
Appendix
4.2 Copies of Calibration
Certificates
Appendix
5.1 Monitoring Schedule for
Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical
Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical
Presentations
Appendix
5.4 Real-time Noise Monitoring Results and
Graphical Presentations
Appendix 6.1 Event
Action Plans
Appendix
9.1 Complaint Log
Appendix 10.1 Construction
Programme of Individual Contracts
Contract no. HY/2009/17
- Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Pile cap construction.
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) - Central Interchange under
FEP-05/364/2009/A
·
Condition survey /
Instrumentation Manholes and Intake Culvert Survey
·
Cable detection and
excavation of trial pit
·
Hoarding and project
signboard erection
·
Tree transplanting
·
Provision of site welfare
facilities
·
Trial installation of
coupler in CR3
·
Temporary drainage
diversion works
·
TTA for Man Po / Man Kwong
diversion
·
Slip road construction
from Man Po Street to Finance Street
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
·
Major construction works were
completed and Engineer’s confirmation for completion of work is under
processing in this reporting month.
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
No major construction activity
was undertaken in reporting month.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
·
No major construction activity
was undertaken in reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
·
No major construction activity
was undertaken in reporting month.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Steel fabrication of
temporary working platform
Noise Monitoring
Air Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/17 - Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Pile cap construction.
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
·
Condition survey /
Instrumentation Manholes and Intake Culvert Survey
·
Cable detection and
excavation of trial pit
·
Hoarding and project signboard
erection
·
Tree transplanting
·
Provision of site welfare
facilities
·
Installation of couplers
in CR3 site
·
Drainage diversion works
·
Sheet piling
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
·
Major construction works
were completed and Engineer’s confirmation for completion of work is under
processing.
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
No major construction activities are anticipated in coming reporting month.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
·
No major construction activities are anticipated in coming reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
·
No major construction activity was undertaken in coming reporting month.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Steel fabrication of temporary working platform
·
Erection of working platform to enable pre-drilling
works (Pier F3-14)
·
Marine pre-drilling (Pier F3-14)
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit
nos. FEP-01/364/2009,
FEP-02/364/2009, FEP-03/364/2009,
FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to implement the Environmental
Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual
of the approved Environmental Impact Assessment (EIA) Report for Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
and in the EM&A Manual of the approved EIA Report for Central-Wan Chai
Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring and
auditing work carried out in accordance to the Section
10.3 of EM&A Manual
and “Environmental Monitoring and Audit
Requirements”
under Particular Specification Section 27.
1.1.3.
This report documents the
finding of EM&A works for
Environmental Permit (EP) no. EP-364/2009/A, Further Environmental Permit (FEP)
nos. FEP-01-364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A,
FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A during the period 28th March to 27th April 2011. The
cut-off date of reporting is at 27th of each reporting month.
Section 1 Introduction
– details the scope and structure of the report.
Section 2 Project
Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Status of Regulatory Compliance
– summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section 4 Monitoring
Requirements
– summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section 5 Monitoring
Results – summarizes the monitoring results
obtained in the reporting period.
Section 6 Compliance
Audit – summarizes the auditing of
monitoring results, all exceedances environmental parameters.
Section 7 Cumulative Construction Impact due to the
Concurrent Projects – summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section 8 Site Inspection –
summarizes the findings of weekly site inspections undertaken within the reporting
period, with a
review of any relevant follow-up actions within the
reporting period.
Section 9 Complaints, Notification of summons and Prosecution
– summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 10 Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan Chai
Bypass” and “Central-Wan Chai Bypass and Island Eastern Corridor Link”
(hereafter called “the Project”) are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA)
Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register
No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and
11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to
provide relief to the very congested east-west Connaught Road Central/Harcourt
Road / Gloucester Road Corridor (the Corridor) which is currently operating
beyond its capacity. The CWB will provide relief to the existing congestion
along the Corridor and cater for the anticipated growth of traffic on Hong Kong
Island. Without the CWB and its access roads, there will not be sufficient
capacity to serve the heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of
Central – Wan Chai Bypass and Island Eastern Corridor Link under the Project
involves the construction and operation of a trunk road and its road tunnel
more than 800m in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses
existing developments from Central to North Point. The
scope of the Central-Wanchai
Bypass (CWB) and Island Eastern Corridor Link (IECL)
includes:
·
A dual three-lane trunk
road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length
defined from the connection with the existing Rumsey Street Flyover in Central,
through to a connection with the existing Island Eastern Corridor to the east
of the Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange
near the Rumsey Street Flyover to provide road connections to the Central area;
·
Tunnel control buildings
and ventilation buildings;
·
Slip roads to connect the
CWB to the local road system in the Wan Chai North and Causeway Bay area;
·
Associated road lighting,
road signing, traffic control and surveillance system; and
·
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1 summarises the
five individual DPs under this Project. Figure 2.1 shows the locations of these
Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced.
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits such that the impact monitoring
stations are sub-divided accordingly to facilitate the implementation of
EM&A programme and to streamline the EM&A reporting for individual FEP
holders correspondingly.
2.3.2.
In the reporting month, advance
piling work at FEHD Whitfield Depot under Contract no. HY/2009/17 was commenced
on 5 October 2010 and pending to construct one pile cap. In addition, Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link
under HY2009/19 was commenced on 24 April 2011 .The details of individual contracts
are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre - Tunnel Works |
DP1, DP2 |
Pending |
HK/2009/02 |
Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai
East(CWB Tunnel) (CWB Tunnel) |
DP1 |
Pending |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1 |
Pending |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and
Development Department and Highways Department are the overall project
controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass
respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Lam
Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
Project Manager |
Mr. K. S. Law |
9090 1378 |
2566 7522 |
Construction Manager / Sub Agent |
Mr. Joe Tsang |
9725-5874 |
|||
Site
Agent |
Mr. Daniel Chan |
9372 0495 |
|||
Environmental Officer |
Mr. Andy Mak |
6461 3065 |
|||
Chiu Hing Construction & Transportation Co. Ltd. |
Contractor under Contract no. 04/HY/2006 |
Contract Manager |
Mr. Frederick Tsui |
2967 6363 |
2967 6366 |
Senior Site Agent |
Mr. Alvin Ma |
2967 6363 |
2967 6366 |
||
Environmental Consultant |
Mr. Jimmy Cheng |
2965 0898 |
2556 9172 |
||
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
2634 1626 |
Operation Manager |
Mr. Ho Wing Tai |
9306 1356 |
|||
Construction Manager |
Mr. David Wong |
9653 8635 |
|||
Construction Manager |
Mr. Wilson Lau |
5183 1270 |
|||
Construction Manager |
Mr. Alex Tsang |
9194 9383 |
|||
Environmental Officer
(Compliance Manager) |
Mr.Ho Wing Tai |
9306 1356 |
|||
Environmental Engineer |
Mr. Ken Yang |
9262 6791 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Eric Lam |
3658-3048 |
|||
Deputy Site Agent |
Mr. Anthony Wu |
3658-3004 |
|||
Environmental Officer (Compliance Manager) |
Mr. Barry Leung |
3658 3031 |
|||
Environmental Engineer |
Ms. Flora Ng |
3658-3064 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Construction Manager |
Mr. William Luk |
9610 1101 |
|||
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Officer |
Mr. Simon Wong |
9281 4346 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
2140 6799 |
Deputy Site Agent |
Mr. Desmond Sze |
2214 7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|
||
Environmental Supervisor |
Mr. Dennis Yu |
2214 7738 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2566 2192 |
Site Agent |
Mr. Leung Kwok Yiu |
9026 8808 |
|||
Head of construction |
Mr. Simon Tang |
9022 6060 |
|||
Construction Manager |
Mr. C K Kwok |
9779 2162 |
|||
Assistant Construction Manager (East) |
Mr. Gene Cheung |
6105 4880 |
|||
Assistant Construction Manager (West) |
Mr. Tony Chiu |
9090 0606 |
|||
Section Agent (East) |
Mr. Jason Chan |
9254 1635 |
|||
Section Agent (West) |
Mr. Tang Ka Tung |
9473 4771 |
|||
Environmental Manager |
Ms. Anna Yu |
9473 1945 |
|||
Environmental Officer |
Mr Kelven Yip |
9669 5447 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month, the
principal work activities of individual contracts are included as follows:
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under FEP-04/364/2009/A
·
Major construction work
was completed and Engineer’s confirmation for completion
of work is under processing.
Contract no. HY/2009/17 - Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Pile cap construction.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
·
Condition survey /
Instrumentation Manholes and Intake Culvert Survey
·
Cable detection and
excavation of trial pit
·
Hoarding and project
signboard erection
·
Tree transplanting
·
Provision of site welfare
facilities
·
Trial installation of
coupler in CR3
·
Temporary drainage
diversion works
·
TTA for Man Po / Man Kwong
diversion
·
Slip road construction
from Man Po Street to Finance Street
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under
FEP-02/364/2009
·
No major construction activity
was undertaken in reporting month.
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
No major construction activity
was undertaken in reporting month.
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
·
No major construction activity
was undertaken in reporting month.
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under
FEP-07/364/2009/A
·
Steel fabrication of
temporary working platform
2.4.4.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under FEP-04/364/2009/A
·
Major construction work
was completed and waiting Engineer’s formal confirmation for completion of work.
Contract no. HY/2009/17 -
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works
under FEP-03/364/2009
·
Pile cap construction.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
·
Condition survey /
Instrumentation Manholes and Intake Culvert Survey
·
Cable detection and
excavation of trial pit
·
Hoarding and project signboard
erection
·
Tree transplanting
·
Provision of site welfare
facilities
·
Installation of couplers
in CR3 site
·
Drainage diversion works
·
Sheet piling
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
No major construction activity is anticipated
in coming reporting month.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
·
No major construction activity is anticipated
in coming reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
·
No major construction activity was undertaken
in coming reporting month.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Steel fabrication of temporary working platform
·
Erection of working platform to enable pre-drilling
works (Pier F3-14)
·
Marine pre-drilling (Pier F3-14)
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-364/2009/A |
4 Aug 2010 |
Valid |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov
2010 |
Valid |
Further
Environmental Permit |
24 Mar
2010 |
Valid |
|
Further
Environmental Permit |
21 Apr 2010 |
Valid |
|
Further
Environmental Permit |
12 July 2010 |
Valid |
|
Further
Environmental Permit |
14 Oct 2010 |
Valid |
|
Further
Environmental Permit |
15 Nov 2010 |
Valid |
|
Further
Environmental Permit |
22 Nov 2010 |
Valid |
|
Further
Environmental Permit |
25 Feb 2011 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the
status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HY/2009/17 - Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
3.1.3.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-03/364/2009 for
contract no. HY/2009/17 showed in Table
3.2 and
Table 3.3.
Table
3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 – 31
Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 May 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Table 3.3 Summary
of submission status under FEP-03/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management
Organization of Main Construction Companies |
18 September 2010 |
Conditions 2.7 and 2.8 |
Submission
of works schedule and location plan |
1 September 2010 |
Condition
2.9 |
Noise
Management Plan |
1 September 2010 |
Contract
no. 04/HY/2006 – Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-04/364/2009/A for
contract no. 04/HY/2006 are shown
in Table
3.4 and
Table 3.5.
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. 04/HY/2006
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
N/A |
Valid |
Notification of Works Under APCO |
322225 |
7 Oct 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7005123 |
9 Mar 2007 |
N/A |
Valid |
Table 3.5 Summary
of submission status under FEP-04/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
11 June 2010 |
Conditions 2.7 and 2.8 |
Submission of works schedule and location
plan |
11 June 2010
and 5 August 2010 |
Condition
2.9 |
Noise Management
Plan |
19
October 2010 |
Condition
2.10 |
Landscape Plan |
26 November 2010 |
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre - Tunnel Works under FEP-02/364/2009
3.1.5.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-02/364/2009 for
contract no.
HK/2009/01 are shown in Table 3.6 and
Table 3.7
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
Billing Account under Waste
Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.7 Summary
of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
NIL |
NIL |
NIL |
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
3.1.6.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-01/364/2009 for
contract no.
HK/2009/02 are shown in Table 3.8 and
Table 3.9.
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31
Mar 2015 |
Valid |
WT00006436-2010 |
15 Apr 2010 |
30
Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31
Mar 2015 |
Valid |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July
2010 |
31 Jul
2015 |
Valid |
|
Billing Account under Waste
Disposal Ordinance |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration as Chemical Waste
Producer |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
WPN5213-839-C3593-02 |
22
Sep 2010 |
N/A |
Valid |
Table 3.9 Summary
of submission status under FEP-01/364/2009
EP Condition |
Submission |
Date of Submission |
NIL |
NIL |
NIL |
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
3.1.7.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under FEP-05/364/2009A for
contract no. HY/2009/18
are shown in Table 3.10
and Table 3.11.
Table 3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
N/A |
Valid |
Notification of Works Under
APCO |
322293 |
07 Oct 2010 |
N/A |
Valid |
Discharge Licence |
WT00008229-2011 |
13 Jan 2011 |
31 Jan 2016 |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011587 |
11-Oct-10 |
N/A |
Valid |
Registration as a Waste
Producer |
WPN: 8335-121-L1048-04 |
17 Dec 2010 |
N/A |
Valid |
Table 3.11 Summary
of submission status under FEP-05/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan |
01-Mar-11 |
Condition 2.10 |
Landscape Plan |
26 Jan 2011 |
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
3.1.8.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-06/364/2009/A for
contract no.
HY/2009/15 are shown in Table 3.12 and
Table 3.13
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
22 Nov 2010 |
N/A |
Valid |
|
22
Nov 2010 |
N/A |
Valid |
||
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Water
Discharge Licence (Discharge at
Portion VII) |
WT00008780-2011 |
22 Mar 2011 |
22 Mar
2011 to 31 Mar 2016 |
Valid |
Water
Discharge Licence (Discharge at Hung
Hing Road) |
WT00008905-2011 |
11 Apr 2011 |
11 Apr
2011 to 30 Apr 2016 |
Valid |
Table 3.13 Summary of submission status under FEP-06/364/2009/A
EP Condition |
Submission |
Date of Submission |
NIL |
NIL |
NIL |
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
3.1.9.
The
current status on licences and/or permits on environmental protection pertinent
and
submission under FEP-07/364/2009/A for
contract no.
HY/2009/19 are shown in Table 3.14 and Table 3.15.
Table 3.14 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
25 Feb 2011 |
N/A |
Valid |
|
Notification of Works Under APCO |
326160 |
24 Jan 2011 |
N/A |
Valid |
Registration as a Waste Producer |
7012306 |
10 Feb 2011 |
N/A |
Valid |
Registration as Chemical Waste
Producer |
5213-151-C3654-01 |
24 Mar 2011 |
N/A |
Valid |
Table 3.15 Summary
of submission status under FEP-07/364/2009/A
EP Condition |
Submission |
Date of Submission |
NIL |
NIL |
NIL |
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are
listed and shown in Table 4.1 and Figure 4.1.
Appendix 4.1 shows the established Action/Limit
Levels for the monitoring works.
Table
4.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour
Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
City
Garden |
M6 |
HK Baptist Church Henrietta
Secondary School |
M7e |
International
Finance Centre (Eastern End of Podium) |
M7w |
International
Finance Centre (Western End of Podium) |
Real time Noise Monitoring Stations
4.1.2.
The noise monitoring stations for the Project are
listed and shown in Table 4.2 and Figure 4.1.. Appendix 4.1
shows the established Action/Limit Levels for the monitoring works.
Table 4.2 Real
Time Noise
Monitoring Stations
District |
Station |
Description |
Tin
Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring Parameters, Frequency
and Duration
4.1.3.
The construction noise level shall
be measured in terms of the A-weighted equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700
and 1900 hours on normal weekdays. For all other time periods, Leq (5
minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria. Supplementary information for
data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
4.1.4.
Noise monitoring shall be carried out at all
the designated monitoring stations. The monitoring frequency shall depend on
the scale of the construction activities. The following is an initial guide on
the regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
·
One set of measurements between 0700 and 1900
hours on normal weekdays.
4.1.5.
Real time noise shall be carried out at the designated
monitoring stations. The following is an initial guide on the regular
monitoring frequency for each station on a 24 hours daily basis when noise
generating activities are underway:
·
One set of measurements between 0700 and 1900
hours on normal weekdays.
·
One set of measurements between 1900 and 2300
hours on normal weekdays and 0700 and 2300 hours on public holidays.
·
One set of measurements between 2300 and 0700
hours on next day on everyday.
4.1.6.
If construction works are extended to include
works during the hours of 1900 – 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.7.
As referred to in the Technical Memorandum ™
issued under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
4.1.8.
Noise measurements shall not be made in fog,
rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10
m/s. The wind speed shall be checked with a portable wind speed meter capable
of measuring the wind speed in m/s.
4.1.9.
The sound level meter shall be checked using
an acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements may be accepted as valid only if the calibration level from before
and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring Stations
4.2.1.
The air monitoring stations for the Project
are listed and shown in Table 4.3 and Figure 4.1..
Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air
Monitoring Stations
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North
Point |
CMA2a |
Causeway Bay Community Centre |
Causeway
Bay |
CMA3a |
CWB PRE
Site Office * |
Causeway
Bay |
CMA4a |
Society for the Prevention of
Cruelty to Animals |
Wan Chai |
CMA5a |
Children
Garden opposite to Pedestrian Plaza |
Wan Chai |
MA1e |
International
Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International
Finance Centre (western End of Podium) |
Central |
* Remarks:
As per the ENPC meeting in March 2011, the monitoring stations CMA3a - Future
CWB site office at Wanchai Waterfront Promenade was renamed as remark.
Air Monitoring Parameters, Frequency and
Duration
4.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring
Equipment
4.2.5.
High volume samplers (HVSs) in compliance
with the following specifications shall be used for carrying out the 1-hour and
24-hour TSP monitoring:
·
0.6 - 1.7 m3 per minute adjustable flow
range;
·
Equipped with a timing / control device with
+/- 5 minutes accuracy for 24 hours operation;
·
Installed with elapsed-time meter with +/- 2
minutes accuracy for 24 hours operation;
·
Capable of providing a minimum exposed area
of 406 cm2;
·
Flow control accuracy: +/- 2.5% deviation
over 24-hour sampling period;
·
Equipped with a shelter to protect the filter
and sampler;
·
Incorporated with an electronic mass flow
rate controller or other equivalent devices;
·
Equipped with a flow recorder for continuous
monitoring;
·
Provided with a peaked roof inlet;
·
Incorporated with a manometer;
·
Able to hold and seal the filter paper to the
sampler housing at horizontal position;
·
Easily changeable filter; and
·
Capable of operating continuously for a
24-hour period.
4.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
Laboratory Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
Filter paper of size 8" x 10" shall
be labeled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
4.2.10. All
the collected samples shall be kept in a good condition for 6 months before
disposal.
4.2.11. Current
calibration certificates of equipments are presented in Appendix
4.2.
5.0.1.
The environmental monitoring will be
implemented based on the division of works areas of each designed project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure
2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent
contracts are as follows:
Contract no. HY/2009/17 - Central - Wan Chai
Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under
FEP-03/364/2009
Contract no. HY/2009/18 - Central - Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009
5.0.3.
The environment monitoring schedules for
reporting month and coming month are presented in Appendix
5.1.
Contract
no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
5.1.1.
The proposed division of noise monitoring
stations for Contract no. HY/2009/17 are summarized in Table 5.1 below:
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Station |
Description |
M4b |
Victoria Centre |
5.1.2.
No action and limit level exceedance was
recorded during day time and restricted hour period in the reporting month. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 5.2.
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and Contract no. HY/2009/18 - Central - Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
5.1.3.
Noise monitoring for the Central Interchange works
under contract no. HY/2009/18 was commenced on 22 April 2011.The proposed
division of noise monitoring stations for Contract no. HY/2009/18 and 04/HY/2006
are summarized in Table 5.2 below:
Table 5.2
Noise Monitoring Stations for Contract no. HY/2009/18 and 04/HY/2006
Station |
Description |
M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
5.1.4. No
action and limit level exceedance was recorded during day time and restricted
hour period on 22 April 2011 in the reporting month. Noise monitoring results
measured in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract
no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
and Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.1.5.
The commencement of construction works for
Contract no. HK/2009/01 and HK/2009/02 under FEP-02/364/2009 and
FEP-01/364/2009 respectively are pending. The proposed division of noise
monitoring stations are summarized in Table 5.3 below.
Table 5.3
Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
5.1.6.
The commencement of construction works for
Contract no. HY/2009/15 under FEP-06/364/2009/A is pending. The proposed
division of noise monitoring stations are summarized in Table 5.4 below.
Table
5.4 Noise
Monitoring Stations for Contract
no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
5.1.7.
Noise monitoring for the tunnel works under
contract no. HY/2009/19 was commenced on 24 April 2011. The proposed division
of noise monitoring stations are summarized in Table 5.5 below.
Table 5.5
Noise Monitoring Stations
for Contract
no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
5.1.8.
No exceedance was recorded in the reporting
month. Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/17 –Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
and Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
Table 5.6 Real Time Noise
Monitoring Stations
for Contract
no. HY/2009/17
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
5.2.2.
No exceedance was recorded in the reporting
month. Real time noise monitoring results measured in this reporting period are
reviewed and summarized. Details of real time noise monitoring results and
graphical presentation can be referred to Appendix 5.4 .
5.2.3.
The proposed division of noise monitoring
stations are summarized in Table 5.7 below. Real time noise
monitoring for major construction works under contract no. HY/2009/19 was
commenced on 24 April 2011.
Table 5.7 Real Time Noise
Monitoring Stations
for Contract
no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
RTN2 |
North
Point |
Oil Street Community Liaison Center |
5.2.4.
No exceedance was recorded in the reporting
month. Real time noise monitoring results measured in this reporting period are
reviewed and summarized. Details of real time noise monitoring results and
graphical presentation can be referred to Appendix 5.4 .
Contract
no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
5.3.1.
The proposed division of air monitoring
stations are summarized in Table 5.8 below. Air monitoring for
the piling works under contract no. HY/2009/17 was commenced on 8 October 2010.
Table 5.8
Air
Monitoring Station for Contract no. HY/2009/17
Station |
Description |
CMA2a |
Causeway Bay Community Centre |
5.3.2.
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and Contract no. HY/2009/18 - Central - Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
5.3.3.
Air monitoring for the Central Interchange
works under contract no. HY/2009/19 was commenced on 21 April 2011.The proposed
division of air monitoring stations are summarized in Table 5.9 below.
Table 5.9
Air
Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
5.3.4.
The commencement of major construction works
for Contract no. HY/2009/18 under FEP-05/364/2009A is pending. Only
preparation works was commenced in the reporting month.
Contract
no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
5.3.5.
Air quality
monitoring will be commenced
depending on the commencement of work for Contract no. HK/2009/01 under
FEP-02/364/2009.
The proposed division of air monitoring stations are summarized in Table
5.10 below.
Table 5.10
Air
Monitoring Station for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
Contract
no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.3.6.
Air quality
monitoring will be commenced
depending on the commencement of work for Contract no. HK/2009/02 under
FEP-01/364/2009.
The proposed division of air monitoring stations are summarized in Table
5.11 below.
Table 5.11
Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
5.3.7.
Air
quality monitoring will be commenced depending on
the commencement of work for Contract no. HY/2009/15 under FEP-06/364/2009/A. The proposed division of air monitoring stations are
summarized in Table 5.12
below.
Table
5.12 Air Monitoring Station for Contract
no. HY/2009/15
Station |
Description |