Contract No: HK/2009/05

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 1)

 

Environmental Permit no. EP-364/2009/A,

Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEp-06/364/2009/a and FEP-07/364/2009/A

 

Monthly Environmental Monitoring & Audit Report

 

- July 2011 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

12 August 2011


Table of contents

 

EXECUTIVE SUMMARY. 4

1.     Introduction. 8

1.1        Scope of the Report 8

1.2        Structure of the Report 8

2.     Project Background. 10

2.1        Background. 10

2.2        Scope of the Project and Site Description. 10

2.3        Division of the Project Responsibility. 11

2.4        Project Organization and Contact Personnel 12

3.     status of regulatory compliance. 17

3.1        Status of Environmental Licensing and Permitting under the Project 17

4.     Monitoring Requirements. 26

4.1        Noise Monitoring. 26

4.2        Air Monitoring. 27

5.     Monitoring Results. 30

5.1        Noise Monitoring Results. 30

5.2        Real Time Noise Monitoring Results. 32

5.3        Air Monitoring Results. 33

5.4        Waste Monitoring Results. 35

6.     Compliance Audit. 39

6.1        Noise Monitoring. 39

6.2        Real Time Noise Monitoring. 39

6.3        Air Monitoring. 40

6.4        Review of the Reasons for and the Implications of Non-compliance. 40

6.5        Summary of action taken in the event of and follow-up on non-compliance. 40

7.     Cumulative Construction Impact due to the Concurrent Projects. 42

8.     Environmental Site Audit. 44

9.     Complaints, Notification of Summons and Prosecution. 47

10.    Conclusion. 49


lIST OF TABLES

 

Table 2.1      Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 3.1      Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.2      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/17

Table 3.3      Summary of submission status under FEP-03/364/2009

Table 3.4      Cumulative Summary of Valid Licences and Permits under Contract no. 04/HY/2006

Table 3.5      Summary of submission status under FEP-04/364/2009/A

Table 3.6      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.7      Summary of submission status under FEP-02/364/2009

Table 3.8      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.9      Summary of submission status under FEP-01/364/2009

Table 3.10    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/18

Table 3.11    Summary of submission status under FEP-05/364/2009/A

Table 3.12    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.13    Summary of submission status under FEP-06/364/2009/A

Table 3.14    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Table 3.15    Summary of submission status under FEP-07/364/2009/A

Table 4.1      Noise Monitoring Stations

Table 4.2      Real Time Noise Monitoring Stations

Table 4.3      Air Monitoring Stations

Table 5.1      Noise Monitoring Stations for Contract no.  HY/2009/17

Table 5.2      Noise Monitoring Stations for Contract no. HY/2009/18 and 04/HY/2006

Table 5.3      Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02

Table 5.4      Noise Monitoring Stations for Contract no. HY/2009/15

Table 5.5      Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.6      Real Time Noise Monitoring Stations for Contract no. HY/2009/17

Table 5.7      Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.8      Air Monitoring Station for Contract no. HY/2009/17

Table 5.9      Air Monitoring Stations for Contract no. HY/2009/18

Table 5.10    Air Monitoring Station for Contract no. HK/2009/01

Table 5.11    Air Monitoring Station for Contract no. HK/2009/02

Table 5.12    Air Monitoring Station for Contract no. HY/2009/15

Table 5.13    Air Monitoring Stations for Contract no. HY/2009/19

Table 5.14    Details of Waste Disposal for Contract no. HY/2009/17

Table 5.15    Details of Waste Disposal for Contract no. 04/HY/2006

Table 5.16    Details of Waste Disposal for Contract no. HK/2009/01

Table 5.17    Details of Waste Disposal for Contract no. HK/2009/02

Table 5.18    Details of Waste Disposal for Contract no. HY/2009/18

Table 5.19    Details of Waste Disposal for Contract no. HY/2009/15

Table 5.20    Details of Waste Disposal for Contract no. HY/2009/19

Table 8.2      Summary of Environmental Inspections for Contract no. HY/2009/18

Table 8.3      Summary of Environmental Inspections for Contract no. HY/2009/19

Table 9.1      Cumulative Statistics on Complaints

Table 9.2      Cumulative Statistics on Successful Prosecutions

Table 10.1    Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

 

 


lIST OF FIGUREs

 

Figure 2.1         Project Layout

Figure 2.2         Project Organization Chart

Figure 4.1         Locations of Environmental Monitoring Stations

 

 

lIST OF APPENDIces

 

Appendix 3.1    Environmental Mitigation Implementation Schedule

Appendix 4.1    Action and Limit Level

Appendix 4.2    Copies of Calibration Certificates

Appendix 5.1    Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2    Noise Monitoring Results and Graphical Presentations

Appendix 5.3    Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4    Real-time Noise Monitoring Results and Graphical Presentations

Appendix 6.1    Event Action Plans

Appendix 6.2    Notification of Exceedance

Appendix 9.1    Complaint Log

Appendix 10.1   Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report – July 2011 specific for Environmental Permit no. EP-364/2009/A, Further Environmental Permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-03-364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HK/2009/05 –Wanchai Development Phase II and Central Wanchai Bypass. This report presents the environmental monitoring findings and information recorded during the period 28th June 2011 to 27th July 2011. The cut-off date of reporting is at 27th of each reporting month.

 

  1. In the reporting month, the principal work activities of individual contracts are included as follows:

 

Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

 

·          Pile cap construction.

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  - Central Interchange under FEP-05/364/2009/A

·          Instrumentation Manholes and Intake Culvert Survey

·          Excavation of trial pit

·          Hoarding erection

·          Tree transplanting

·          Installation of coupler in CR3

·          Drainage diversion works

·          Site investigation and pre-drilling works

·          Excavation in Trough B

·          Man Kwong Street Gate 1 & 2 setup

·          Sheet piling

·          Guide wall construction near PTI

 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

 

·          Major construction works were completed and Engineer’s confirmation for completion of work is under processing in this reporting month.

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

·          Commencement date of Tunnel Works under FEP-02/364/2009 is pending on 25 August 2011. No major construction activity was but preparation works were commenced in this reporting month

·          Pre-drilling works for SCL Protection Works and CWB.

·          Site investigation works for the proposed jet grouting at HKCEC foundation.

·          Pre-bored H piling works for the proposed CWB.

·          Grout treatment works for proposed diaphragm wall

·          Demolition of existing promenade deck

.

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

·          Guide wall construction for diaphragm wall construction.

·          Pre-drilling for diaphragm wall construction at WCR1 area.

·          Tunnel bored pile works at WCR1 area.

·          Diaphragm wall construction at WCR1 area.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

·          Diaphragm wall construction at TS1 and TPCWAE

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link  under FEP-07/364/2009/A

·          Steel fabrication of temporary platform

·          Erection of platform to enable marine pre-drilling

·          Marine Pre-drilling

·          Trial pitting at Portion XI

 

Noise Monitoring

  1. Noise monitoring during daytime was conducted at M1a - Harbour Road Sports Center; M2b - Noon-day gun area; M3a - Tung Lo Wan Fire Station; M4b - Victoria Center; M5b - City Garden, M6 - HK Baptist Church Henrietta Secondary School, M7e and M7w – International Finance Centre Eastern and Western End of Podium on a weekly basis. Five limit level exceedances were recorded at M1a - Harbour Road Sports Centre on 29 June, 5, 13, 19 and 25 July 2011 during restricted hour; a limit level exceedance was recorded at M6 - HK Baptist Church Henrietta Secondary School on 13 July 2011 during day time and a limit level exceedance was recorded at M7w - International Finance Centre Western End of Podium on 19 July 2011. After checking contractor’s work schedules and investigation found that no major construction works were conducted during monitoring and traffic noises as major noise sources contributed in the noise monitoring. It was considered the exceedances were related to the Project at M7w but not related at M1a and M6. Also, four Action levels were recorded due to four recorded noise complaints on 23 and 27 July 2011.

 

  1. 24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitefield Depot for the pilling works in FEHD Whitfield Depot and RTN2 – Tunnel (North Point Section) and Island Eastern Corridor Link. Calibration and maintenance of real time noise meters were conducted at RTN1 on 5 July 2011 from 0900 to 0930 hours and at RTN2 on 7 July 2011 from 1600 to 1630 hours, respectively. No monitoring was conducted during the mentioned periods. Also, no project related action and limit level exceedance was recorded in the reporting period.

 

Air Monitoring

  1. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b - Oil Street Community Liaison Centre; CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site Office Area; CMA4a – Society for the Prevention of Cruelty to Animals; CMA5a - Children Garden opposite to Pedestrian Plaza; MA1e and MA1w – International Finance Centre eastern and western wing on every six days basis. No action and limit level exceedance were recorded in the reporting period.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. There were four environmental complaint recorded in the reporting month regarding noise impact and concern of starting time of nuisance works complaint at Victoria Centre on 23 July 2011 ICC no. 1 –303887687 and 27 July 2011 ICC no. 1 –304616162. No further complaint was received after follow-up action and investigation. There were two noise complaints from the ICC complaint no. 1-304013959 by Ms. Yau on 23 July 2011 and ICC complaint no.1-304615409 by Ms. Chiu on 27 July 2011 referred by RSS to Environmental Team on 28 July 2011. These complaints are under investigation and will be reported in the coming reporting month.

 

Site Inspections and Audit

  1. The Environmental Team (ET) conducted weekly site inspections for Contract no. HY/2009/15, HY/2009/17, HY/2009/18, HY/2009/19 and HK/2009/02 in this reporting period. The Contractors rectified major observations and recommendations made during the audit sessions. No non-conformance was identified during the site inspections.

 

Future Key Issues

  1. In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

 

·          Pile cap construction.

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

 

·          Instrumentation Manholes and Intake Culvert Survey

·          Excavation of trial pit

·          Hoarding erection

·          Tree transplanting

·          Installation of coupler in CR3

·          Drainage diversion works

·          Site investigation and pre-drilling works

·          Excavation in Trough B

·          Sheet piling

·          Diaphragm wall

·          Instrumentation at Man Yiu Street

·          Slip road construction between Man Kwong Street and Finance Street

·          Emergency exit construction at MTR by-law area

·          CCTV for drainage pipes

 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

 

·    Major construction works were completed and Engineer’s confirmation for completion of work is under processing.

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

·    Pre-drilling works for both CWB and SCL Protection Works.

·    Pre-bored H piling works for the proposed CWB

·    Preparatory works such as ground treatment, guide wall construction and plant establishment for the proposed diaphragm wall construction works

·    The proposed diaphragm wall construction works within HKCEC1.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

·    Tunnel bored pile and diaphragm wall construction works.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

·          Diaphragm wall construction at TS1 and TPCWAE

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link  under FEP-07/364/2009/A

·          Steel fabrication of temporary platform

·          Erection of platform to enable marine pre-drilling

·          Marine pre-drilling

·          Remove existing dolphin pier

 

1.         Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and “Environmental Monitoring and Audit Requirements” under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/A, Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A during the period 28th June to 27th July 2011. The cut-off date of reporting is at 27th of each reporting month.

 

1.2          Structure of the Report

 

Section 1          Introduction – details the scope and structure of the report.

 

Section 2          Project Background – summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3          Status of Regulatory Compliance – summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4          Monitoring Requirements – summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5          Monitoring Results – summarizes the monitoring results obtained in the reporting period.

 

Section 6          Compliance Audit – summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7          Cumulative Construction Impact due to the Concurrent Projects summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8          Site Inspection – summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9          Complaints, Notification of summons and Prosecution – summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10        Conclusion

2.         Project Background

2.1          Background

2.1.1.     “Wan Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2          Scope of the Project and Site Description

2.2.1.     Design and Construction of Central – Wan Chai Bypass and Island Eastern Corridor Link under the Project involves the construction and operation of a trunk road and its road tunnel more than 800m in length between portals that is shown at Figure 2.1.

2.2.2.      The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:

·          A dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);

·          The Central Interchange near the Rumsey Street Flyover to provide road connections to the Central area;

·          Tunnel control buildings and ventilation buildings;

·          Slip roads to connect the CWB to the local road system in the Wan Chai North and Causeway Bay area;

·          Associated road lighting, road signing, traffic control and surveillance system; and

·          Other associated works.

 

2.2.3.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3          Division of the Project Responsibility

2.3.1.     Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.     In the reporting month, Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) was commenced on 13 July 2011. The details of individual contracts are summarized in Table2.2.

Table 2.2    Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HY/2009/17

Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works.

DP1

5 October 2010

HY/2009/18

Central - Wan Chai Bypass (CWB) – Central Interchange

DP1

21 April 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

HK/2009/01

Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works

DP1, DP2

Pending on 25 August 2011

HK/2009/02

Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East(CWB Tunnel)

DP1

26 April 2011

HY/2009/15

Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

DP1

13 July 2011

HY/2009/19

Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

 

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer for CWB

Principal Resident Engineer

Mr. Peter Poon

3916 1818

3529 2829

Lam Woo & CO., LTD.

Contractor under Contract no. HY/2009/17

Project Manager

Mr. K. S. Law

9090 1378

2566 7522

Site Agent

Mr. Tony Au

 

9725 5874

Sub Agent

Mr. Johnny Wong

9725 5870

Chiu Hing Construction & Transportation Co. Ltd.

Contractor under Contract no. 04/HY/2006

Contract Manager

Mr. Frederick Tsui

2967 6363

2967 6366

Senior Site Agent

Mr. Alvin Ma

2967 6363

2967 6366

Environmental Consultant

Mr. Jimmy Cheng

2965 0898

2556 9172

Chun Wo – Leader Joint Venture

Contractor under Contract no. HK/2009/01

Site Agent

Mr. Paul Yu

9456 9819

2634 1626

Operation Manager

Mr Lau Yee Ching

9466 3918

Construction Manager

Mr Jerry Siu

9493 3664

Construction Manager

Mr Ricky Lai

9487 6549

Construction Manager

Mr KK Yuen

3498 1213

Environmental Officer (Compliance Manager)

Mr Andy Mak

9103 2370

Environmental Supervisor

Ms Kiwi Chan

6227 8840

Chun Wo – CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Project Manager

Mr. Chan Sing Cho

3658-3002

2827 9996

Site Agent

Mr. Mak Kam Wing

3658-3044

Deputy Site Agent

Mr. Anthony Wu

3658-3004

Quality & Environmental Manager

Mr. C.P. Ho

3658-3000

Environmental Officer

Miss Flora Ng

 

3658-3064

Chun Wo – CRGL Joint Venture

Contractor under Contract no. HY/2009/19

Project Manager

Mr. Rayland Lee

3758 8879

2570 8013

Site Agent

Cheung Kit Cheung

6909 1555

Environmental Engineer

Simon Wong

9281 4346

Environmental Manager /

Environmental Officer

M.H. Isa

9884 0810

Leighton Contractors (Asia) Limited

Contractor under Contract no. HY/2009/18

Site Agent

Mr. Brian Gillon

2214 7700

2140 6799

Deputy Site Agent

Mr. Desmond Sze

2214 7703

Environmental Officer

Mr. Anfernee Chow

2214 7721

Environmental Supervisor

Mr. Dennis Yu

2214 7738

Environmental Supervisor

Ryan Tsui

2214 7705

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Manager

Mr. M Y Wong

2823 7879

2566 2192

Site Agent

Mr. Simon Tang

3557 6358

Head of construction

Andrew Kwan

3557 6396

Environmental Officer

Samuel Tsui

3557 6347

Environmental Officer

Daniel Sin

3557 6215

Environmental Supervisor

Kelven Yip

3557 6347

Environmental Supervisor

Tim Fung

3557 6349

 

 

Environmental Supervisor

Hilda Lau

3557 6378

 

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3743 0788

3548 6988

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

2.4.3.     In this reporting month, the principal work activities of individual contracts are included as follows:

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

·    Major construction work was completed and Engineer’s confirmation for completion of work is under processing.

 

Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

·          Pile cap construction.

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  - Central Interchange under FEP-05/364/2009/A

·          Instrumentation Manholes and Intake Culvert Survey

·          Excavation of trial pit

·          Hoarding erection

·          Tree transplanting

·          Installation of coupler in CR3

·          Drainage diversion works

·          Site investigation and pre-drilling works

·          Excavation in Trough B

·          Man Kwong Street Gate 1 & 2 setup

·          Sheet piling

·          Guide wall construction near PTI

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

·          Commencement date of Tunnel Works under FEP-02/364/2009 pended on 25 August 2011. No major construction activity was but preparation works were commenced in this reporting month

·          Pre-drilling works for SCL Protection Works and CWB.

·          Site investigation works for the proposed jet grouting at HKCEC foundation.

·          Pre-bored H piling works for the proposed CWB.

·          Grout treatment works for proposed diaphragm wall

·          Demolition of existing promenade deck

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

·          Guide wall construction for diaphragm wall construction.

·          Pre-drilling for diaphragm wall construction at WCR1 area.

·          Tunnel bored pile works at WCR1 area.

·          Diaphragm wall construction at WCR1 area.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

·          Diaphragm wall construction at TS1 and TPCWAE

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link  under FEP-07/364/2009/A

·          Steel fabrication of temporary platform

·          Erection of platform to enable marine pre-drilling

·          Marine Pre-drilling

·          Trial pitting at Portion XI

2.4.4.     In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

·          Major construction work was completed and waiting Engineer’s formal confirmation for completion of work.

 

Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

·          Pile cap construction.

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

·          Instrumentation Manholes and Intake Culvert Survey

·          Excavation of trial pit

·          Hoarding erection

·          Tree transplanting

·          Installation of coupler in CR3

·          Drainage diversion works

·          Site investigation and pre-drilling works

·          Excavation in Trough B

·          Sheet piling

·          Diaphragm wall

·          Instrumentation at Man Yiu Street

·          Slip road construction between Man Kwong Street and Finance Street

·          Emergency exit construction at MTR by-law area

·          CCTV for drainage pipes

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

·    Pre-drilling works for both CWB and SCL Protection Works.

·    Pre-bored H piling works for the proposed CWB

·    Preparatory works such as ground treatment, guide wall construction and plant establishment for the proposed diaphragm wall construction works

·    The proposed diaphragm wall construction works within HKCEC1.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

·    Tunnel bored pile and diaphragm wall construction works.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

·          Diaphragm wall construction at TS1 and TPCWAE

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link  under FEP-07/364/2009/A

·          Steel fabrication of temporary platform

·          Erection of platform to enable marine pre-drilling

·          Marine pre-drilling

·          Remove existing dolphin pier

 

3.         status of regulatory compliance

3.1          Status of Environmental Licensing and Permitting under the Project

 

3.1.1.     A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1    Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

Superseded

Environmental Permit

EP-364/2009/A

  4 Aug 2010

Valid

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Valid

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

15 Nov 2010

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 July 2010

Valid

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Valid

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

Valid

 

3.1.2.     Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

3.1.3.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table 3.2 and Table 3.3.

Table 3.2    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/17

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/364/2009

12 Jul 2010

N/A

Valid

Notification of Works Under APCO

319348

13 Jul 2010

N/A

Valid

Discharge Licence

WT00007212-2010

5 Aug 2010

5 Aug 2010 – 31 Aug 2015

Valid

Registration as a Waste Producer

5213-151-L2608-05

13 July 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7010400

16 Mar 2010

N/A

Valid

 

Table 3.3    Summary of submission status under FEP-03/364/2009

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

18 September 2010

Conditions 2.7 and 2.8

Submission of works schedule and location plan

1 September 2010

Condition 2.9

Noise Management Plan

1 September 2010

 

Contract no. 04/HY/2006 Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

3.1.4.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-04/364/2009/A for contract no. 04/HY/2006 are shown in Table 3.4 and Table 3.5.

Table 3.4    Cumulative Summary of Valid Licences and Permits under Contract no. 04/HY/2006

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

N/A

Valid

Notification of Works Under APCO

322225

7 Oct 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7005123

9 Mar 2007

N/A

Valid

 

 

 

 

 

 

Table 3.5       Summary of submission status under FEP-04/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

11 July 2010

Conditions 2.7 and 2.8

Submission of works schedule and location plan

11 July 2010 and

5 August 2010

Condition 2.9

Noise Management Plan

19 October 2010

Condition 2.10

Landscape Plan

26 November 2010

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

3.1.5.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.6 and Table 3.7

Table 3.6    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

N/A

Valid

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088

6 Jan 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0107-11

8 Feb 2011

16 Mar 2011 to 15  Sep 2011

Valid

 

GW-RS0111-11

11 Feb 2011

28 Feb 2011 to 31  Aug 2011

Cancelled

 

GW-RS0384-11

29 Apr 2011

27 May 2011 to 26  Nov 2011

Valid

 

GW-RS0421-11

9 May 2011

11 May 2011 to 10 Nov 2011

Cancelled

 

GW-RS0450-11

20 May 2010

9 Jun 2010 to

8 Dec 2011

Cancelled

 

GW-RS0680-11

22 Jul 2011

29 Jul 2011 to 19 Jan 2012

Valid

 

GW-RS0689-11

28 Jul 2011

29 Jul 2011 to 28 Jan 2012

Valid

Discharge Licence

WT00006220-2010

18 Mar 2010

31 Mar 2015

Valid

 

WT00009641-2011

24 Jul 2011

31 Jul 2016

Valid

Billing account under Waste Disposal Ordinance

7010069

21 Jan 2010

N/A

Valid

Registration as a Chemical Waste Producer

WPN5213-134-C3585-01

21 Jan 2010

N/A

Valid

 

Table 3.7    Summary of submission status under FEP-02/364/2009

EP Condition

Submission

Date of Submission

Special Conditions, Clause 2.7 & 2.8

Works Schedule and Location Plan

18 May 2011

 

Special Conditions, Clause 2.6

Environmental Management Organization Chart

18 May 2011

 

Special Conditions, Clause 2.6

Commencement Date of Works

25 Jun 2011

 

Special Conditions, Clause 2.9

Noise Management Plan

10 Jun 2011

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

3.1.6.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.8 and Table 3.9.

Table 3.8    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

N/A

Valid

FEP-01/364/2009

24 Mar 2010

N/A

Valid

Notification of Works Under APCO

313962

2 Feb 2010

N/A

Valid

Construction Noise Permit (CNP) for piling equipment

PP-RS0011-11

27 April 2011

1 July 2011 to

30 Nov 2011

Valid

Construction Noise Permit (CNP) for non-piling equipment

 

GW-RS0033-11

19 Jan 2011

1 Feb 2011 to

31 Jul 2011

Valid

 

GW-RS0093-11

2 Feb 2011

17 Feb 2011 to

16 Jul 2011

Valid

 

GW-RS0280-11

30 Mar 2011

31 Mar 2011 to 30 Sept 2011

cancelled and superseded by “GW-RW0645-11

 

GW-RS0343-11

11 April 2011

25 Apr 2011 to 10 Oct 2011

Valid

 

GW-RS0369-11

21 April 2011

1 May 2011 to

31 Oct 2011

Valid

 

GW-RS0377-11

27 April 2011

1 May 2011 to

31 Oct 2011

Valid

 

GW-RE0311-11

4 May 2011

5 May 2011 to 31 Oct 2011

Valid

 

GW-RS0401-11

3 May 2011

18 May 2011 to 17 Nov 2011

Valid

 

GW-RS0414-11

3 May 2011

9 May 2011 to 8 Nov 2011

Valid

 

GW-RS0423-11

9 May 2011

22 May 2011 to 21 Nov 2011

Valid

 

GW-RS0430-11

9 May 2011

16 May 2011 to 15 Nov 2011

Valid

 

GW-RS0453-11

19 May 2011

23 May 2011 to 22 Nov 2011

Valid

 

GW-RS0458-11

17 May 2011

21 May 2011 to 20 Nov 2011

Valid

 

GW-RS0461-11

19 May 2011

23 May 2011 to 22 Nov 2011

Valid

 

GW-RS0473-11

27 May 2011

01 May 2011 to 30 Nov 2011

Valid

 

GW-RS0496-11

31 May 2011

07 Jun 2011 to 06 Dec 2011

Valid

 

 

GW-RS0502-11

8 Jun 2011

13 Jun 2011 to 12 Dec 2011

Valid

 

GW-RS0579-11

22 June 2011

17 July 2011 to 16 Jan 2012

Valid

 

GW-RS0645-11

18 July 2011

22 Jul 2011 to 21 Jan 2012

Valid

 

GW-RS0649-11

22 July 2011

1 Aug 2011 to 31 Jan 2012

Valid

 

GW-RS0691-11

25 July 2011

27 July 2011 to 26 Jan 2012

Valid

Discharge Licence

 

WT00006249-2010

22 Mar 2010

31 Mar 2015

Valid

 

WT00006436-2010

15 Apr 2010

30 Apr 2015

Valid

 

WT00006673-2010

14 May 2010

31 Mar 2015

Valid

 

WT00006757-2010

28 May 2010

31 May 2015

Valid

 

WT00007129-2010

28 July 2010

31 Jul 2015

Valid

 

WT00008982-2011

26 April 2011

30 April 2016

Valid

Billing Account under Waste Disposal Ordinance (Land)

 

7010255

10 Feb 2010

N/A

Valid

Registration as Chemical Waste Producer (Wan Chai)

WPN5213-135-C3593-01

10 Mar 2010

N/A

Valid

 

Table 3.9    Summary of submission status under FEP-01/364/2009

EP Condition

Submission

Date of Submission

Special Conditions, Clause 2.7 & 2.8

Works Schedule and Location Plan