Contract
No: HK/2009/05 Wanchai Development Phase II and Sampling, Field Measurement and
Testing Work (Stage 1) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A,
FEP-05/364/2009/A,
FEp-06/364/2009/a and FEP-07/364/2009/A Monthly
Environmental Monitoring & Audit Report
- July 2011 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
12 August
2011 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring
6.4 Review
of the Reasons for and the Implications of Non-compliance
6.5 Summary
of action taken in the event of and follow-up on non-compliance
7. Cumulative Construction Impact due to the
Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST
OF TABLES
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/17
Table 3.3 Summary of submission status under FEP-03/364/2009
Table 3.4 Cumulative Summary of Valid Licences and Permits under Contract no.
04/HY/2006
Table 3.5 Summary of submission status under FEP-04/364/2009/A
Table 3.6 Cumulative Summary of Valid Licences and Permits under Contract no.
HK/2009/01
Table 3.7 Summary of submission status under FEP-02/364/2009
Table 3.8 Cumulative Summary of Valid Licences and Permits under Contract no.
HK/2009/02
Table 3.9 Summary of submission status under FEP-01/364/2009
Table 3.10 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/18
Table 3.11 Summary of submission status under FEP-05/364/2009/A
Table 3.12 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/15
Table 3.13 Summary of submission status under FEP-06/364/2009/A
Table 3.14 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/19
Table 3.15 Summary of submission status under FEP-07/364/2009/A
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring Stations
Table 4.3 Air Monitoring Stations
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.2 Noise Monitoring Stations for Contract no. HY/2009/18 and 04/HY/2006
Table 5.3 Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Table 5.4 Noise Monitoring Stations for Contract no. HY/2009/15
Table 5.5 Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.6 Real Time Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Air Monitoring Station for Contract no. HY/2009/17
Table 5.9 Air Monitoring Stations for Contract no. HY/2009/18
Table 5.10 Air Monitoring Station for Contract no. HK/2009/01
Table 5.11 Air Monitoring Station for Contract no. HK/2009/02
Table 5.12 Air Monitoring Station for Contract no. HY/2009/15
Table 5.13 Air Monitoring Stations for Contract no. HY/2009/19
Table 5.14 Details of Waste Disposal for Contract no. HY/2009/17
Table 5.15 Details of Waste Disposal for Contract no. 04/HY/2006
Table 5.16 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.17 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.18 Details of Waste Disposal for Contract no. HY/2009/18
Table 5.19 Details of Waste Disposal for Contract no. HY/2009/15
Table 5.20 Details of Waste Disposal for Contract no. HY/2009/19
Table 8.2 Summary of Environmental Inspections for Contract no. HY/2009/18
Table 8.3 Summary of Environmental Inspections for Contract no. HY/2009/19
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix
3.1 Environmental
Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix
5.1 Monitoring
Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring
Results and Graphical Presentations
Appendix
5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix 5.4 Real-time Noise Monitoring Results and
Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling
works under FEP-03/364/2009
·
Pile cap construction.
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) - Central Interchange under
FEP-05/364/2009/A
·
Instrumentation Manholes and Intake Culvert Survey
·
Excavation of trial pit
·
Hoarding erection
·
Tree transplanting
·
Installation of coupler in CR3
·
Drainage diversion works
·
Site investigation and pre-drilling works
·
Excavation in Trough B
·
Man Kwong Street Gate 1 & 2 setup
·
Sheet piling
·
Guide wall construction near PTI
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under FEP-04/364/2009/A
·
Major construction works were completed and Engineer’s
confirmation for completion of work is under processing in this reporting
month.
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at
·
Commencement date of Tunnel Works under
FEP-02/364/2009 is pending on 25 August 2011. No major construction activity
was but preparation works were commenced in this reporting month
·
Pre-drilling works for SCL Protection Works and
CWB.
·
Site investigation works for the proposed jet
grouting at HKCEC foundation.
·
Pre-bored H piling works for the proposed CWB.
·
Grout treatment works for proposed diaphragm wall
·
Demolition of existing promenade deck
.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
·
Guide wall construction for diaphragm wall
construction.
·
Pre-drilling for diaphragm wall construction at
WCR1 area.
·
Tunnel bored pile works at WCR1 area.
·
Diaphragm wall construction at WCR1 area.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
·
Diaphragm wall construction at TS1 and TPCWAE
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Steel fabrication of temporary platform
·
Erection of platform to enable marine pre-drilling
·
Marine Pre-drilling
·
Trial pitting at Portion XI
Noise Monitoring
Air Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Pile cap construction.
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
·
Instrumentation Manholes and Intake Culvert Survey
·
Excavation of trial pit
·
Hoarding erection
·
Tree transplanting
·
Installation of coupler in CR3
·
Drainage diversion works
·
Site investigation and pre-drilling works
·
Excavation in Trough B
·
Sheet piling
·
Diaphragm wall
·
Instrumentation at
·
Slip road construction between
·
Emergency exit construction at MTR by-law area
·
CCTV for drainage pipes
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under FEP-04/364/2009/A
· Major construction
works were completed and Engineer’s confirmation for completion of work is
under processing.
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at
· Pre-drilling works for
both CWB and SCL Protection Works.
· Pre-bored H piling
works for the proposed CWB
· Preparatory works
such as ground treatment, guide wall construction and plant establishment for the
proposed diaphragm wall construction works
· The proposed
diaphragm wall construction works within HKCEC1.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
· Tunnel bored pile
and diaphragm wall construction works.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
·
Diaphragm
wall construction at TS1 and TPCWAE
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Steel
fabrication of temporary platform
·
Erection
of platform to enable marine pre-drilling
·
Marine
pre-drilling
·
Remove
existing dolphin pier
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to
implement the Environmental Monitoring and Audit (EM&A) programme as stipulated
in the EM&A Manual of the approved Environmental Impact Assessment (EIA)
Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register
No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of
EM&A Manual and “Environmental Monitoring and Audit
Requirements” under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/A,
Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009,
FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and
FEP-07/364/2009/A during the period 28th June to 27th July 2011. The cut-off date of reporting is at 27th of
each reporting month.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Status of
Regulatory Compliance – summarizes the status of valid Environmental Permits /
Licenses during the reporting period.
Section 4 Monitoring Requirements – summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section 5 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 6 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Site Inspection
– summarizes
the findings of weekly site inspections undertaken within the reporting period,
with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of
the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km
in length, and tunnel approximately 3.7 km in length defined from the
connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing Island Eastern Corridor to the east of the
Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street
Flyover to provide road connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road
system in the Wan Chai North and
·
Associated road lighting, road signing, traffic
control and surveillance system; and
·
Other associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table
2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
In
the reporting month, Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) was commenced on 13 July 2011. The
details of individual contracts are summarized in Table2.2.
Table
2.2 Details of Individual Contracts
under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai Development Phase II - Central - Wan Chai Bypass at |
DP1, DP2 |
Pending on 25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel ( |
DP1 |
13 July 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Lam
Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
Project Manager |
Mr. K. S. Law |
9090 1378 |
2566 7522 |
Site Agent |
Mr. Tony Au |
9725 5874 |
|||
Sub
Agent |
Mr. Johnny Wong |
9725 5870 |
|||
Chiu Hing Construction & Transportation Co. Ltd. |
Contractor under Contract no. 04/HY/2006 |
Contract Manager |
Mr. Frederick Tsui |
2967 6363 |
2967 6366 |
Senior Site Agent |
Mr. Alvin Ma |
2967 6363 |
2967 6366 |
||
Environmental Consultant |
Mr. Jimmy Cheng |
2965 0898 |
2556 9172 |
||
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
2634 1626 |
Operation
Manager |
Mr Lau Yee
Ching |
9466 3918 |
|||
Construction
Manager |
Mr Jerry
Siu |
9493 3664 |
|||
Construction
Manager |
Mr Ricky
Lai |
9487 6549 |
|||
Construction
Manager |
Mr KK Yuen |
3498 1213 |
|||
Environmental
Officer (Compliance Manager) |
Mr Andy Mak
|
9103 2370 |
|||
Environmental
Supervisor |
Ms Kiwi
Chan |
6227 8840 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Site Agent |
Mr. Mak Kam Wing |
3658-3044 |
|||
Deputy Site Agent |
Mr. Anthony Wu |
3658-3004 |
|||
Quality & Environmental Manager |
Mr. C.P. Ho |
3658-3000 |
|||
Environmental Officer |
Miss Flora Ng |
3658-3064 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Cheung Kit Cheung |
6909 1555 |
|||
Environmental Engineer |
Simon Wong |
9281 4346 |
|||
Environmental Manager / Environmental Officer |
M.H. Isa |
9884 0810 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
|
Deputy Site Agent |
Mr. Desmond Sze |
2214 7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Supervisor |
Mr. Dennis Yu |
2214 7738 |
|||
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2566 2192 |
Site Agent |
Mr. Simon Tang |
3557 6358 |
|||
Head of construction |
Andrew Kwan |
3557 6396 |
|||
Environmental Officer |
Samuel Tsui |
3557 6347 |
|||
Environmental Officer |
Daniel Sin |
3557 6215 |
|||
Environmental Supervisor |
Kelven Yip |
3557 6347 |
|||
Environmental Supervisor |
Tim Fung |
3557 6349 |
|||
|
|
Environmental Supervisor |
Hilda Lau |
3557 6378 |
|
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under FEP-04/364/2009/A
·
Major construction work was completed and Engineer’s
confirmation for completion of work is under processing.
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Pile cap construction.
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB)
- Central Interchange under FEP-05/364/2009/A
·
Instrumentation Manholes and Intake Culvert Survey
·
Excavation of trial pit
·
Hoarding erection
·
Tree transplanting
·
Installation of coupler in CR3
·
Drainage diversion works
·
Site investigation and pre-drilling works
·
Excavation in Trough B
·
Man Kwong Street Gate 1 & 2 setup
·
Sheet piling
·
Guide wall construction near PTI
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
·
Commencement date of Tunnel Works under
FEP-02/364/2009 pended on 25 August 2011. No major construction activity was
but preparation works were commenced in this reporting month
·
Pre-drilling works for SCL Protection Works and
CWB.
·
Site investigation works for the proposed jet
grouting at HKCEC foundation.
·
Pre-bored H piling works for the proposed CWB.
·
Grout treatment works for proposed diaphragm wall
·
Demolition of existing promenade deck
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
·
Guide wall construction for diaphragm wall
construction.
·
Pre-drilling for diaphragm wall construction at
WCR1 area.
·
Tunnel bored pile works at WCR1 area.
·
Diaphragm wall construction at WCR1 area.
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (
·
Diaphragm wall construction at TS1 and TPCWAE
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under
FEP-07/364/2009/A
·
Steel fabrication of temporary platform
·
Erection of platform to enable marine pre-drilling
·
Marine Pre-drilling
·
Trial pitting at Portion XI
2.4.4.
In
coming reporting month, the principal work activities of individual contracts
are anticipated as follows:
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under FEP-04/364/2009/A
·
Major construction work was completed and waiting
Engineer’s formal confirmation for completion of work.
Contract no. HY/2009/17 - Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Pile cap construction.
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
·
Instrumentation Manholes and Intake Culvert Survey
·
Excavation of trial pit
·
Hoarding erection
·
Tree transplanting
·
Installation of coupler in CR3
·
Drainage diversion works
·
Site investigation and pre-drilling works
·
Excavation in Trough B
·
Sheet piling
·
Diaphragm wall
·
Instrumentation at
·
Slip road construction between
·
Emergency exit construction at MTR by-law area
·
CCTV for drainage pipes
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at
· Pre-drilling works for
both CWB and SCL Protection Works.
· Pre-bored H piling
works for the proposed CWB
· Preparatory works
such as ground treatment, guide wall construction and plant establishment for the
proposed diaphragm wall construction works
· The proposed
diaphragm wall construction works within HKCEC1.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
· Tunnel bored pile
and diaphragm wall construction works.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
·
Diaphragm
wall construction at TS1 and TPCWAE
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Steel
fabrication of temporary platform
·
Erection
of platform to enable marine pre-drilling
·
Marine
pre-drilling
·
Remove
existing dolphin pier
3.1.1. A summary of the current status on licences
and/or permits on environmental protection pertinent to the Project is shown in
Table
3.1.
Permits and/or
Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental
Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Valid |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
3.1.2. Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no.
HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works under FEP-03/364/2009
3.1.3. Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-03/364/2009 for
contract no. HY/2009/17 showed in Table 3.2 and Table 3.3.
Table
3.2 Cumulative Summary of Valid
Licences and Permits under Contract no.
HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 – 31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 July
2010 |
N/A |
Valid |
Billing Account
under Waste Disposal Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Table 3.3 Summary of submission status under FEP-03/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
18 September 2010 |
Conditions 2.7 and
2.8 |
Submission of works schedule and location plan |
1 September 2010 |
Condition 2.9 |
Noise Management Plan |
1 September 2010 |
Contract no. 04/HY/2006 – Reconstruction of
Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
3.1.4. Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-04/364/2009/A for
contract no. 04/HY/2006 are shown in Table 3.4 and Table 3.5.
Table 3.4 Cumulative Summary of Valid Licences and
Permits under Contract no. 04/HY/2006
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
N/A |
Valid |
Notification of Works Under APCO |
322225 |
7 Oct 2010 |
N/A |
Valid |
Billing Account
under Waste Disposal Ordinance |
7005123 |
9 Mar 2007 |
N/A |
Valid |
Table 3.5 Summary
of submission status under FEP-04/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management
Organization of Main Construction Companies |
11 July 2010 |
Conditions 2.7 and
2.8 |
Submission of works schedule and location
plan |
11 July 2010 and 5 August 2010 |
Condition 2.9 |
Noise Management
Plan |
19 October 2010 |
Condition 2.10 |
Landscape Plan |
26 November 2010 |
Contract
no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
3.1.5.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under
FEP-02/364/2009 for
contract no. HK/2009/01 are shown in Table 3.6 and Table 3.7
Table 3.6 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental
Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works
Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS0107-11 |
8 Feb 2011 |
16 Mar 2011 to 15 Sep 2011 |
Valid |
|
GW-RS0111-11 |
11 Feb 2011 |
28 Feb 2011 to 31 Aug 2011 |
Cancelled |
|
GW-RS0384-11 |
29 Apr 2011 |
27 May 2011 to 26 Nov 2011 |
Valid |
|
GW-RS0421-11 |
9 May 2011 |
11 May 2011 to 10 Nov 2011 |
Cancelled |
|
GW-RS0450-11 |
20 May 2010 |
9 Jun 2010 to 8 Dec 2011 |
Cancelled |
|
GW-RS0680-11 |
22 Jul 2011 |
29 Jul 2011 to 19 Jan 2012 |
Valid |
|
GW-RS0689-11 |
28 Jul 2011 |
29 Jul 2011 to 28 Jan 2012 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
Billing account under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.7 Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
25 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
10 Jun 2011 |
Contract
no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
3.1.6.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under
FEP-01/364/2009 for
contract no. HK/2009/02 are shown in Table 3.8 and Table 3.9.
Table 3.8 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling
equipment |
PP-RS0011-11 |
27 April 2011 |
1 July 2011
to 30 Nov 2011 |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0033-11 |
19 Jan 2011 |
1 Feb 2011
to 31 Jul 2011 |
Valid |
|
GW-RS0093-11 |
2 Feb 2011 |
17 Feb 2011
to 16 Jul 2011 |
Valid |
|
GW-RS0280-11 |
30 Mar 2011 |
31 Mar 2011
to 30 Sept 2011 |
cancelled
and superseded by “GW-RW0645-11 |
|
GW-RS0343-11 |
11 April
2011 |
25 Apr 2011
to 10 Oct 2011 |
Valid |
|
GW-RS0369-11 |
21 April
2011 |
1 May 2011
to 31 Oct 2011 |
Valid |
|
GW-RS0377-11 |
27 April
2011 |
1 May 2011
to 31 Oct 2011 |
Valid |
|
GW-RE0311-11 |
4 May 2011 |
5 May 2011
to 31 Oct 2011 |
Valid |
|
GW-RS0401-11 |
3 May 2011 |
18 May 2011
to 17 Nov 2011 |
Valid |
|
GW-RS0414-11 |
3 May 2011 |
9 May 2011
to 8 Nov 2011 |
Valid |
|
GW-RS0423-11 |
9 May 2011 |
22 May 2011
to 21 Nov 2011 |
Valid |
|
GW-RS0430-11 |
9 May 2011 |
16 May 2011
to 15 Nov 2011 |
Valid |
|
GW-RS0453-11 |
19 May 2011 |
23 May 2011
to 22 Nov 2011 |
Valid |
|
GW-RS0458-11 |
17 May 2011 |
21 May 2011
to 20 Nov 2011 |
Valid |
|
GW-RS0461-11 |
19 May 2011 |
23 May 2011
to 22 Nov 2011 |
Valid |
|
GW-RS0473-11 |
27 May 2011 |
01 May 2011
to 30 Nov 2011 |
Valid |
|
GW-RS0496-11 |
31 May 2011 |
07 Jun 2011
to 06 Dec 2011 |
Valid |
|
GW-RS0502-11 |
8 Jun 2011 |
13 Jun 2011
to 12 Dec 2011 |
Valid |
|
GW-RS0579-11 |
22 June
2011 |
17 July
2011 to 16 Jan 2012 |
Valid |
|
GW-RS0645-11 |
18 July
2011 |
22 Jul 2011
to 21 Jan 2012 |
Valid |
|
GW-RS0649-11 |
22 July
2011 |
1 Aug 2011
to 31 Jan 2012 |
Valid |
|
GW-RS0691-11 |
25 July
2011 |
27 July
2011 to 26 Jan 2012 |
Valid |
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Valid |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July
2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 April
2011 |
30 April
2016 |
Valid |
Billing Account under Waste Disposal
Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (Wan
Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Table 3.9 Summary of submission status under FEP-01/364/2009
EP Condition |
Submission |
Date of Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |