Contract No: HK/2009/05 Wanchai Development Phase II and Sampling, Field Measurement and Testing Work (Stage
1) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEp-06/364/2009/a and FEP-07/364/2009/A Monthly Environmental Monitoring
& Audit Report
- november 2011 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
14 December 2011 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring
6.4 Review
of the Reasons for and the Implications of Non-compliance
6.5 Summary
of action taken in the event of and follow-up on non-compliance
7. Cumulative Construction Impact due to the
Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/17
Table 3.3 Summary of submission status under FEP-03/364/2009
Table 3.4 Cumulative Summary of Valid Licences and Permits under Contract no.
HK/2009/01
Table 3.5 Summary of submission status under FEP-02/364/2009
Table 3.6 Cumulative Summary of Valid Licences and Permits under Contract no.
HK/2009/02
Table 3.7 Summary of submission status under FEP-01/364/2009
Table 3.8 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/18
Table 3.9 Summary of submission status under FEP-05/364/2009/A
Table 3.10 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/15
Table 3.11 Summary of submission status under FEP-06/364/2009/A
Table 3.12 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/19
Table 3.13 Summary of submission status under FEP-07/364/2009/A
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring Stations
Table 4.3 Air Monitoring Stations
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.2 Noise Monitoring Stations for Contract no. HY/2009/18
Table 5.3 Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Table 5.4 Noise Monitoring Stations for Contract no. HY/2009/15
Table 5.5 Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.6 Real Time Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Air Monitoring Station for Contract no. HY/2009/17
Table 5.9 Air Monitoring Stations for Contract no. HY/2009/18
Table 5.10 Air Monitoring Station for Contract no. HK/2009/01
Table 5.11 Air Monitoring Station for Contract no. HK/2009/02
Table 5.12 Air Monitoring Station for Contract no. HY/2009/15
Table 5.13 Air Monitoring Stations for Contract no. HY/2009/19
Table 5.14 Details of Waste Disposal for Contract no. HY/2009/17
Table 5.15 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.16 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.17 Details of Waste Disposal for Contract no. HY/2009/18
Table 5.18 Details of Waste Disposal for Contract no. HY/2009/15
Table 5.19 Details of Waste Disposal for Contract no. HY/2009/19
Table 8.1 Summary of Environmental Inspections for Contract no. HY/2009/15
Table 8.2 Summary of Environmental Inspections for Contract no. HY/2009/18
Table 8.3 Summary of Environmental Inspections for Contract no. HY/2009/19
Table 8.4 Summary of Environmental Inspections for Contract no. HK/2009/01
Table 8.5 Summary of Environmental Inspections for Contract no. HK/2009/02
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
lIST OF
FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental
Mitigation Implementation Schedule
Appendix 4.1 Action and
Limit Level
Appendix
4.2 Copies of Calibration
Certificates
Appendix
5.1 Monitoring Schedule for Reporting
Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical
Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical
Presentations
Appendix
5.4 Real-time Noise Monitoring Results and Graphical
Presentations
Appendix 6.1 Event
Action Plans
Appendix 6.2 Notification of Exceedance
Appendix
9.1 Complaint Log
Appendix 10.1 Construction
Programme of Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot
- Advanced piling works under FEP-03/364/2009
·
ELS works
for basement construction for pile cap construction.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
·
Instrumentation
works for Manholes and Intake Culvert Survey
·
Excavation
of trial pit
·
Drainage
work at
·
Site
investigation and pre-drilling works at CR3
·
Diaphragm
wall construction
·
Hoarding
erection
·
Roadworks
at CR3
·
Grout
curtain
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
·
Diaphragm
wall construction works for CWB (Stage 1) and SCL protection works
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Tunnel
bored pile works at WCR1
·
Toe grout
at WCR1 area
·
Shear pin
at WCR1 area
·
Pumping
test at WCR1 area
·
King Post
at WCR area
·
Excavation
and lateral support at western Tunnel portion
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
·
Diaphragm
wall construction preparation works at TS4
·
Diaphragm
wall construction at TS1 and TPCWAE
·
Night
time protection works at CHT
·
Construction
of dewatering well at
·
Precautionary
works at Abutment A
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under
FEP-07/364/2009/A
·
Preparation
works and removal of existing marine
piles
·
Road
works at
·
Fabrication
of bored piling platform
·
Bored
piling
·
Ground
contamination assessment
·
D-wall Construction
·
Sheet
piling for Box Culvert T
Noise Monitoring
Air Monitoring
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/17 –
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works
under FEP-03/364/2009
·
ELS works
for basement construction for pile cap construction.
Contract no. HY/2009/18 – Central – Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Instrumentation
works for Manholes and Intake Culvert Survey
·
Excavation
of trial pit
·
Drainage
work at
·
Site
investigation and pre-drilling works at CR3
·
Diaphragm
wall construction
·
Hoarding
erection
·
Roadworks
at CR3
·
Grout
curtain
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at
·
Diaphragm
wall construction works for both CWB and SCL Protection Works within HKCEC1
·
Pre-drilling
works for CWB at Stage 2
·
Pilling
works for CWB at Stage 1
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Tunnel
bored pile construction works and ELS at western tunnel portion
·
Toe
grout, Shear pine, and Pumping test at WCR1 area.
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
·
Diaphragm
wall construction preparation works at TS4
·
ELS works
at TS1 and TPCWAE
·
Night
time protection works at CHT
·
Construction
of dewatering well at
·
Precautionary
works at Abutment A
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
·
Remove
existing dolphin
·
Road works
at
·
Fabrication
of bored piling platform
·
Bored
piling
·
Ground
contamination assessment
·
Pre-drilling
works for bored pile and Diaphragm wall
·
D-wall Construction
·
Sheet
piling for Box Culvert T
·
Construction
works for Box Culvert T
·
Marine
Piling
1.1.1.
Lam Geotechnics
Limited (LGL) has been appointed to work as the Environmental Team (ET) under
Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to implement the Environmental Monitoring and Audit
(EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report
presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of EM&A
Manual and “Environmental Monitoring and Audit Requirements” under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/A, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-03/364/2009,
FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A during the period
28th October to 27th
November 2011. The cut-off date of reporting is at 27th of each reporting
month.
Section
1 Introduction
– details the scope and structure of the report.
Section
2 Project Background
– summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section
3 Status of Regulatory
Compliance – summarizes the status of valid
Environmental Permits / Licenses during the reporting period.
Section
4 Monitoring Requirements
– summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section
5 Monitoring Results
– summarizes the monitoring results obtained in the reporting period.
Section
6 Compliance Audit
– summarizes the auditing
of monitoring results, all exceedances environmental parameters.
Section
7 Cumulative Construction
Impact due to the Concurrent Projects –
summarizes the relevant
cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section
8 Site Inspection –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of
summons and Prosecution – summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
“Wan Chai
Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai Bypass
and Island Eastern Corridor Link” (hereafter called “the Project”) are Designed
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose
of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North
and North Point for construction of the Central-Wan Chai Bypass and Island
Eastern Corridor Link (CWB). Land formed under the project will be developed as
a world-class waterfront promenade joining that at the new Central waterfront
for public enjoyment.
2.1.3.
There is a
compelling and present need for the CWB to provide relief to the very congested
2.2.1.
Design and Construction of Central – Wan Chai Bypass and Island Eastern
Corridor Link under the Project involves the construction and operation of a
trunk road and its road tunnel more than 800m in length between portals that is
shown at Figure 2.1.
2.2.2.
The study area encompasses existing
developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
·
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
·
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
·
Tunnel
control buildings and ventilation buildings;
·
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
·
Associated
road lighting, road signing, traffic control and surveillance system; and
·
Other
associated works.
2.2.3.
The project also
contains various Schedule 2 DPs that, under the EIAO, require Environmental
Permits (Eps) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the
five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads |
Schedule
2, Part I, A.1 and A.7 |
Trunk
road and road tunnel more than 800 m in length |
DP2 |
Road P2
and other roads which are classified as primary/district distributor roads |
Schedule
2, Part I, A.1 |
Primary
/ district distributor roads |
DP3 |
Reclamation
works including associated dredging works |
Schedule
2, Part I, C.1 and C.12 |
Reclamation
more than 5 ha in size and a dredging operation less than 100 m from a
seawater intake point |
DP5 |
Wan Chai
East Sewage Outfall |
Schedule
2, Part I, F.5 and F.6 |
Submarine
sewage pipelines with a total diameter more than 1,200 mm and include a
submarine sewage outfall |
DP6 |
Dredging
for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui |
Schedule
2, Part I, C.12 |
A
dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the
multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such that the impact monitoring
stations are sub-divided accordingly to facilitate the implementation of
EM&A programme and to streamline the EM&A reporting for individual FEP
holders correspondingly.
2.3.2.
In the reporting
month, Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)
was commenced on 13 July 2011. The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central –
Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central –
Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction
of Bus Terminus near |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai
Development Phase II – Central – Wan Chai Bypass at |
DP1, DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East(CWB Tunnel)
|
DP1 |
26 April
2011 |
HY/2009/15 |
Central-Wanchai
Bypass – Tunnel ( |
DP1 |
13 July
2011 |
HY/2009/19 |
Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link |
DP1 |
24 March
2011 |
2.4.1.
Civil Engineering and Development Department and Highways Department are
the overall project controllers for the Wan Chai Development Phase II and
Central-Wan Chai Bypass respectively. For the construction phase of the
Project, Project Engineer, Contractor(s), Environmental Team and Independent
Environmental Checker are appointed to manage and control environmental issues.
2.4.2.
The proposed
project organization and lines of communication with respect to environmental
protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer
for WDII |
Principal
Resident Engineer |
Mr.
Frankie Fan |
2587
1778 |
2587 1877 |
Engineer
for CWB |
Principal
Resident Engineer |
Mr.
Peter Poon |
3916
1818 |
3529 2829 |
|
Lam Woo &
CO., LTD. |
Contractor
under Contract no. HY/2009/17 |
Project
Manager |
Mr. K.
S. Law |
9090
1378 |
2566 7522 |
Site
Agent |
Mr. Tony
Au |
9725
5874 |
2566 7522 |
||
Sub Agent |
Mr.
Johnny Wong |
9725
5870 |
2566 7522 |
||
Chun Wo
– Leader Joint Venture |
Contractor
under Contract no. HK/2009/01 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
2634 1626 |
Operation Manager |
Mr. Lau Yee Ching |
9466 3918 |
|||
Construction Manager |
Mr Jerry Siu |
9493 3664 |
|||
Construction Manager |
Mr Ricky Lai |
9487 6549 |
|||
Construction Manager |
Mr KK Yuen |
3498 1213 |
|||
Environmental Officer (Compliance
Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Environmental Supervisor |
Ms. Kiwi Chan |
6227 8840 |
|||
Chun Wo
– CRGL Joint Venture |
Contractor
under Contract no. HK/2009/02 |
Project
Manager |
Mr. Chan
Sing Cho |
3658-3002 |
2827 9996 |
Site
Agent |
Mr. Mak
Kam Wing |
3658-3044 |
|||
Deputy
Site Agent |
Mr.
Anthony Wu |
3658-3004 |
|||
Quality
& Environmental Manager |
Mr. C.P.
Ho |
3658-3000 |
|||
Environmental
Officer |
Ms Flora
Ng |
3658-3064 |
|||
Chun Wo
– CRGL Joint Venture |
Contractor
under Contract no. HY/2009/19 |
Project
Manager |
Mr.
Rayland Lee |
3758 8879 |
2570 8013 |
Site
Agent |
Mr. Cheung
Kit Cheung |
6909
1555 |
|||
Environmental
Engineer |
Mr. Simon
Wong |
9281
4346 |
|||
Environmental
Manager / Environmental
Officer |
Mr. M.H.
Isa |
9884
0810 |
|||
Leighton
Contractors ( |
Contractor
under Contract no. HY/2009/18 |
Site
Agent |
Mr.
Brian Gillon |
2214 7700 |
|
Deputy
Site Agent |
Mr.
Desmond Sze |
2214 7703 |
|||
Environmental
Officer |
Mr.
Anfernee Chow |
2214 7721 |
|||
Environmental
Supervisor |
Mr.
Dennis Yu |
2214 7738 |
|||
Environmental
Supervisor |
Ryan
Tsui |
2214 7705 |
|||
|
Contractor
under Contract no. HY/2009/15 |
Project
Manager |
Mr. M Y
Wong |
2823
7879 |
2566 2192 |
Site
Agent |
Mr. P J
Fan |
3557
6368 |
|||
Head of
construction |
Mr. Roger
Cheung |
3557
6371 |
|||
Environmental
Officer |
Mr. Daniel
Sin |
3557
6215 |
|||
Environmental
Supervisor |
Mr. Kelven
Yip |
3557
6347 |
|||
Environmental
Supervisor |
Mr. Tim
Fung |
3557
6349 |
|||
|
|
Environmental
Supervisor |
Mr. Hilda
Lau |
3557
6378 |
|
ENVIRON
Hong Kong Limited |
Independent Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr.
David Yeung |
3743
0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work activities of individual
contracts are included as follows:
Contract no. HY/2009/17 –
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works
under FEP-03/364/2009
·
ELS works
for basement construction for pile cap construction.
Contract no. HY/2009/18 – Central
– Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
·
Instrumentation
works for Manholes and Intake Culvert Survey
·
Excavation
of trial pit
·
Drainage
work at
·
Site
investigation and pre-drilling works at CR3
·
Diaphragm
wall construction
·
Hoarding
erection
·
Roadworks
at CR3
·
Grout
curtain
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at
·
Diaphragm
wall construction works for CWB (Stage 1) and SCL protection works
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
·
Tunnel
bored pile works at WCR1
·
Toe grout
at WCR1 area
·
Shear pin
at WCR1 area
·
Pumping
test at WCR1 area
·
King Post
at WCR area
·
Excavation
and lateral support at western Tunnel portion
Contract no. HY/2009/15 –
Central-Wanchai Bypass – Tunnel (
·
Seawall
block construction, reclamation work and diaphragm wall construction
preparation works at TS4
·
Diaphragm
wall construction at TS1 and TPCWAE
·
Night
time protection works at CHT
·
Construction
of dewatering well at
·
Precautionary
works at Abutment A
Contract no. HY/2009/19 – Central
– Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor
Link under FEP-07/364/2009/A
·
Preparation
works and removal of existing marine
piles
·
Road
works at
·
Fabrication
of bored piling platform
·
Bored
piling
·
Ground
contamination assessment
·
D-wall Construction
·
Sheet
piling for Box Culvert T
2.4.4.
In coming
reporting month, the principal work activities of individual contracts are
anticipated as follows:
Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD
Whitfield Depot – Advanced piling works under FEP-03/364/2009
·
ELS works
for basement construction for pile cap construction.
Contract no. HY/2009/18 – Central – Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Instrumentation
works for Manholes and Intake Culvert Survey
·
Excavation
of trial pit
·
Drainage
work at
·
Site
investigation and pre-drilling works at CR3
·
Diaphragm
wall construction
·
Hoarding
erection
·
Roadworks
at CR3
·
Grout
curtain
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at
·
Diaphragm
wall construction works for both CWB and SCL Protection Works within HKCEC1
·
Pre-drilling
works for CWB at Stage 2
·
Pilling
works for CWB at Stage 1
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Tunnel
bored pile construction works and ELS at western tunnel portion
·
Toe
grout, Shear pine, and Pumping test at WCR1 area.
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
·
Diaphragm
wall construction preparation works at TS4
·
Diaphragm
wall construction at TS1 and TPCWAE
·
Night
time protection works at CHT
·
Construction
of dewatering well at
·
Precautionary
works at Abutment A
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under
FEP-07/364/2009/A
·
Remove
existing dolphin
·
Road
works at
·
Fabrication
of bored piling platform
·
Bored
piling
·
Ground
contamination assessment
·
Pre-drilling
works for bored pile and Diaphragm wall
·
D-wall Construction
·
Sheet
piling for Box Culvert T
·
Construction
works for Box Culvert T
·
Marine
Piling
3.1.1.
A summary of the
current status on licences and/or permits on environmental protection pertinent
to the Project is shown in Table 3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
3.1.2.
Due to the
multi-contract nature of the Project, the status of permits and/or licences
under the individual contract(s) are presented as below:
Contract no. HY/2009/17 – Central
– Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under
FEP-03/364/2009
3.1.3.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table
3.2 and Table 3.3.
Table
3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 – 31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 July 2010 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Table 3.3 Summary
of submission status under FEP-03/364/2009
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization
of Main Construction Companies |
18 September 2010 |
Conditions 2.7 and 2.8 |
Submission of works
schedule and location plan |
1 September 2010 |
Condition 2.9 |
Noise Management Plan |
1 September 2010 |
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus
near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
3.1.4.
The construction works was completed, and the FEP was surrendered by the
Contractor on 11 February 2011.
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
3.1.5.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0384-11 |
29 Apr 2011 |
27 May 2011 to 26 Nov 2011 |
Expired |
|
GW-RS0680-11 |
22 Jul 2011 |
24 Jul 2011
to 19 Jan 2012 |
Valid |
|
GW-RS0689-11 |
28 Jul 2011 |
29 Jul 2011 to 28 Jan 2012 |
Valid |
|
GW-RS0832-11 |
7 Sep 2011 |
03 Sep 2011 to 02 Mar 2012 |
Valid |
|
GW-RS0850-11 |
12 Sept 2011 |
14 Sept 2011 to 13 Mar 2012 |
Valid |
|
GW-RS0851-11 |
12 Sept 2011 |
16 Sept 2011 to 15 Mar 2012 |
Valid |
|
GW-RE0683-11 |
16 Sept
2011 |
20 Sept 2011 to 19 Oct 2012 |
Valid |
|
GW-RE0716-11 |
28 Sept 2011 |
07 Oct 2011 to 29 Mar 2012 |
Valid |
|
GW-RS1094-11 |
23 Nov
2011 |
27 Nov
2011 to 26 May 2012 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar
2015 |
Valid |
|
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
Billing account
under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan
2010 |
N/A |
Valid |
Table 3.5 Summary
of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of
Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May
2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
25 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
10 Jun 2011 |
Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
3.1.6.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb
2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for piling equipment |
PP-RS0011-11 |
27 April
2011 |
1 June
2011 to 30 Nov
2011 |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0369-11 |
21 April
2011 |
1 May
2011 to 31 Oct
2011 |
Expire |
|
GW-RS0377-11 |
27 April
2011 |
1 May
2011 to 31 Oct
2011 |
Expire |
|
GW-RE0311-11 |
4 May
2011 |
5 May
2011 to 31 Oct 2011 |
Expire |
|
GW-RS0401-11 |
3 May
2011 |
18 May
2011 to 17 Nov 2011 |
Expire |
|
GW-RS0414-11 |
3 May
2011 |
9 May
2011 to 8 Nov 2011 |
Cancel |
|
GW-RS0423-11 |
9 May
2011 |
22 May
2011 to 21 Nov 2011 |
Expire |
|
GW-RS0430-11 |
9 May
2011 |
16 May
2011 to 15 Nov 2011 |
Cancel |
|
GW-RS0453-11 |
19 May
2011 |
23 May
2011 to 22 Nov 2011 |
Expire |
|
GW-RS0458-11 |
17 May
2011 |
21 May
2011 to 20 Nov 2011 |
Cancel |
|
GW-RS0461-11 |
19 May
2011 |
23 May
2011 to 22 Nov 2011 |
Expire |
|
GW-RS0473-11 |
27 May
2011 |
01 May
2011 to 30 Nov 2011 |
Cancel |
|
GW-RS0496-11 |
31 May
2011 |
07 Jun
2011 to 06 Dec 2011 |
Valid |
|
GW-RS0502-11 |
8 Jun
2011 |
13 Jun
2011 to 12 Dec 2011 |
Valid |
|
GW-RS0579-11 |
22 June
2011 |
17 July
2011 to 16 Jan 2012 |
Valid |
|
GW-RS0645-11 |
18 July
2011 |
22 Jul
2011 to 21 Jan 2012 |
Cancel |
|
GW-RS0649-11 |
22 July
2011 |
1 Aug
2011 to 31 Jan 2011 |
Valid |
|
GW-RS0691-11 |
25 July
2011 |
27 July
2011 to 26 Jan 2011 |
Cancel |
|
GW-RS0716-11 |
2 Aug
2011 |
12 Aug
2011 to 11 Feb 2012 |
Valid |
|
GW-RS0722-11 |
2 Aug
2011 |
5 Aug
2011 to 5 Oct 2011 |
Expire |
|
GW-RS0723-11 |
12 Aug
2011 |
15 Aug
2011 to 14 Feb 2012 |
Valid |
|
GW-RS0833-11 |
8 Sept
2011 |
10 Sept
2011 to 4 Mar 2012 |
Valid |
|
GW-RS0857-11 |
16 Sept
2011 |
6 Oct
2011 to 5 Apr 2011 |
Valid |
|
GW-RE0710-11 |
30 Sept
2011 |
1 Nov
2011 to 30 Apr 2012 |
Valid |
|
GW-RS0918-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Valid |
|
GW-RS0929-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Valid |
|
GW-RS0930-11 |
11 Oct
2011 |
1 Nov
2011 to 30 Apr 2012 |
Valid |
|
GW-RS0931-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Valid |
|
GW-RS0941-11 |
20 Oct
2011 |
23 Nov
2011 to 22 May 2012 |
Valid |
|
GW-RS0955-11 |
14 Oct
2011 |
23 Nov
2011 to 22 May 2012 |
Valid |
|
GW-RS0968-11 |
20 Oct
2011 |
18 Nov
2011 to 17 May 2012 |
Valid |
|
GW-RS0983-11 |
24 Oct
2011 |
26 Oct 2011
to 23 April 2012 |
Valid |
|
GW-RS0984-11 |
25 Oct 2011 |
30 Oct
2011 to 27 April 2012 |
Valid |
|
GW-RS1028-11 |
3 Nov
2011 |
7 Dec
2011 to 6 June 2012 |
Valid |
|
GW-RS1052-11 |
18 Nov
2011 |
21 Nov
2011 to 18 May 2012 |
Valid |
Discharge
Licence |
WT00006249-2010 |
22 Mar
2010 |
31 Mar
2015 |
Valid |
|
WT00006436-2010 |
15 Apr
2010 |
30 Apr
2015 |
Valid |
|
WT00006673-2010 |
14 May
2010 |
31 Mar
2015 |
Valid |
|
WT00006757-2010 |
28 May
2010 |
31 May
2015 |
Valid |
|
WT00007129-2010 |
28 July
2010 |
31 Jul
2015 |
Valid |
|
WT00008982-2011 |
26 April
2011 |
30 April
2016 |
Valid |
|
WT00009691-2011 |
1 Aug
2011 |
31 July
2016 |
Valid |
Billing
Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb
2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep
2010 |
N/A |
Valid |
Table 3.7 Summary
of submission status under FEP-01/364/2009
EP Condition |
Submission |
Date of
Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
21 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
28 Jun 2011 |
Condition 2.11 |
Landscape Plan |
23 Aug 2011 |
Condition 2.9 |
Noise Management Plan (Rev.A) |
28-Sep-11 |
Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
3.1.7.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-05/364/2009A for contract no.
HY/2009/18 are shown in
Table 3.8 and Table 3.9.
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Permit / Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Permit issued |
Valid |
Notification of Works Under APCO |
322293 |
07 Oct 2010 |
Notified |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0840-11 |
09 Sept 2011 |
09 Sept 2011 – |
Expired |
|
GW-RS0878-11 |
22 Sept
2011 |
22 Sept
2011 – |
Expired |
|
GW-RS0993-11 |
28 Oct
2011 |
28 Oct
2011 – |
Valid |
Discharge Licence |
WT00008229-2011 |
13 Jan 2011 |
31 Jan 2016 |
Valid |
Registration as a Waste Producer |
WPN: 8335-121-L1048-04 |
17 Dec 2010 |
Registration completed |
|
Application for a Billing Account for Disposal of Construction Waste (
Construction Work Contract with Value of $1 million or Above) under the Waste
Disposal Ordinance (Cap. 354) sections 5 & 9 of the Waste Disposal
(Charges for Disposal of Construction Waste) Regulation. |
Account No.: 7011587 |
11 Oct 2010 |
Account approved |