Contract No: HK/2011/07 Wanchai Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing Work
(Stage 2) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a
and FEP-07/364/2009/A Monthly Environmental Monitoring
& Audit Report
- January
2012 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai,
H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
                         Raymond Dai Environmental Team Leader |
|
DATE: |
|
14 February 2012 |
1.1    Scope
of the Report
1.2    Structure
of the Report
2.   Project Background
2.1    Background
2.2    Scope
of the Project and Site Description
2.3    Division
of the Project Responsibility
2.4    Project
Organization and Contact Personnel
3.   status of regulatory compliance
3.1    Status
of Environmental Licensing and Permitting under the Project
4.   Monitoring
Requirements
4.1    Noise
Monitoring
4.2    Air
Monitoring
5.   Monitoring Results
5.1    Noise
Monitoring Results
5.2    Real Time Noise
Monitoring Results
5.3    Air
Monitoring Results
5.4    Waste
Monitoring Results
6.1    Noise
Monitoring
6.2    Real Time Noise
Monitoring
6.3    Air
Monitoring
6.4    Review
of the Reasons for and the Implications of Non-compliance
6.5    Summary
of action taken in the event of and follow-up on non-compliance
7.   Cumulative Construction Impact due to the
Concurrent Projects
8.   Environmental Site
Audit
9.   Complaints,
Notification of Summons and Prosecution
lIST OF
TABLES
Table 2.1    Schedule 2 Designated Projects under
this Project
Table 2.2   Details of Individual Contracts under the Project
Table 2.3   Contact Details of Key Personnel
Table 3.3   Summary of submission status under FEP-03/364/2009
Table 3.5   Summary of submission status under FEP-02/364/2009
Table 3.7   Summary of submission status under FEP-01/364/2009
Table 3.9   Summary of submission status under FEP-05/364/2009/A
Table 3.10  Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/15
Table 3.11  Summary of submission status under FEP-06/364/2009/A
Table 3.12  Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Table 3.13  Summary of submission status under FEP-07/364/2009/A
Table 4.1   Noise Monitoring Stations
Table 4.2   Real Time Noise Monitoring Stations
Table 4.3   Air Monitoring Stations
Table 5.1    Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.2    Noise Monitoring Stations for Contract no. HY/2009/18
Table 5.3    Noise Monitoring Station for Contract no HK/2009/01
and HK/2009/02
Table 5.4    Noise Monitoring Stations for Contract no. HY/2009/15
Table 5.5    Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.6   Real Time Noise Monitoring Stations for Contract no.
HY/2009/17
Table 5.7   Real Time Noise Monitoring Stations for Contract no.
HY/2009/19
Table 5.8    Air Monitoring Station for Contract no. HY/2009/17
Table 5.9    Air Monitoring Stations for Contract no. HY/2009/18
Table 5.10   Air Monitoring Station for Contract no. HK/2009/01
Table 5.11   Air Monitoring Station for Contract no. HK/2009/02
Table 5.12   Air Monitoring Station for Contract no. HY/2009/15
Table 5.13   Air Monitoring Stations for Contract no. HY/2009/19
Table 5.14  Details of Waste Disposal for Contract no. HY/2009/17
Table 5.15  Details of Waste Disposal for Contract no. HK/2009/01
Table 5.16  Details of Waste Disposal for Contract no. HK/2009/02
Table 5.17  Details of Waste Disposal for Contract no. HY/2009/18
Table 5.18  Details of Waste Disposal for Contract no. HY/2009/15
Table 5.19  Details of Waste Disposal for Contract no. HY/2009/19
Table 8.1   Summary of Environmental Inspections for Contract no.
HY/2009/15
Table 8.2   Summary of Environmental Inspections for Contract no.
HY/2009/18
Table 8.3   Summary of Environmental Inspections for Contract no.
HY/2009/19
Table 8.4   Summary of Environmental Inspections for Contract no.
HK/2009/01
Table 8.5   Summary of Environmental Inspections for Contract no.
HK/2009/02
Table 9.1   Cumulative Statistics on Complaints
Table 9.2   Cumulative Statistics on Successful Prosecutions
lIST
OF FIGUREs
Figure
2.1       Project
Layout
Figure
2.2       Project
Organization Chart
Figure 4.1        Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1     Environmental Mitigation Implementation
Schedule
Appendix 4.1     Action
and Limit Level
Appendix
4.2     Copies of
Calibration Certificates
Appendix
5.1     Monitoring
Schedule for Reporting Month and Coming month
Appendix 5.2     Noise Monitoring Results and Graphical
Presentations
Appendix 5.3     Air Quality Monitoring Results and Graphical
Presentations
Appendix
5.4     Real-time
Noise Monitoring
Results and Graphical Presentations
Appendix 6.1     Event
Action Plans
Appendix 6.2     Notification of Exceedance
Appendix
9.1     Complaint
Log
Appendix 10.1   Construction
Programme of Individual Contracts
Contract no. HY/2009/17
- Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
 -
ELS works for basement
construction for pile cap construction.
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) - Central Interchange under
FEP-05/364/2009/A
 -
Instrumentation works for
Manholes and Intake Culvert Survey
 -
Excavation of trial pit
 -
Drainage work
 -
Site investigation and
pre-drilling works
 -
Diaphragm wall
construction
 -
Hoarding erection
 -
Roadwork
 -
Sheet-piling
 -
Grout curtain
 -
Tree pruning
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre - Tunnel Works under FEP-02/364/2009
 -
Diaphragm wall
construction works for CWB
 -
Pre-drilling works for CWB
(stage 2)
 -
Pre-bored H pilling works
for CWB
 -
Grouting works along the southern
side of HKCEC water channel
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
 -
Toe grout at WCR1 area
 -
Shear pin at WCR1 area
 -
Pumping test at WCR1 area
 -
King Post at WCR1 area
 -
Deep excavation of CWB at
the eastern area of working deck B
Contract no. HY/2009/15 - Central-Wanchai Bypass  
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
 -
Seawall block
construction, reclamation work and diaphragm wall construction preparation
works at TS4
 -
ELS works at TS1 and
TPCWAE
 -
Night time protection
works at CHT
 -
Construction of dewatering
well at Hung Hing Road and POC
 -
Precautionary works at Abutment
A
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
 -
Preparation works and concreting of marine piles
 -
Fabrication of bored
piling platform
 -
Bored piling
 -
Ground contamination  /span>assessment
 -
D-wall Construction
 -
Construction works for Box
Culvert T
Noise Monitoring
Air Monitoring
CMA1b:
from 4, 10, 20 and 26 Jan 2012 to 5, 11, 21 and 27 Jan 2012
CMA3a:
form 16 Jan 2012 to 17 Jan 2012
MA1w:
form 16 Jan 2012 to 17 Jan 2012
Complaints, Notifications of
Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/17  Central  Wan Chai Bypass
(CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009
 -
ELS works for basement
construction for pile cap construction.
Contract no. HY/2009/18  Central  Wan Chai Bypass
(CWB)  Central Interchange under FEP-05/364/2009/A
 -
Instrumentation works for
Manholes and Intake Culvert Survey
 -
Excavation of trial pit
 -
Drainage work
 -
Site investigation and
pre-drilling works
 -
Diaphragm wall
construction
 -
Hoarding erection
 -
Roadwork
 -
Grout curtain
 -
Sheet-piling
 -
Tree pruning
Contract no. HK/2009/01  Wan
Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre  Tunnel Works under FEP-02/364/2009
 -
Diaphragm wall
construction works for both CWB and SCL Protection Works within HKCEC 1
 -
Pre-drilling and
pre-treatment works for CWB at stage2
 -
Pilling works for CWB at Stage
1
 -
Excavation and
Installation of shoring system for CWB top slab
 -
Installation of sheet pile
for SCL top slab construction and exhaust duct construction
Contract no. HK/2009/02  Wan
Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
 -
Deep excavation works
below +0.3mPD for western tunnel portion and below +4mPD for eastern tunnel
portion.
 -
Toe grout, Shear pin, and
Pumping test at WCR1 area.
Contract no. HY/2009/15  Central-Wanchai Bypass  
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
 -
Diaphragm wall
construction at TS4
 -
ELS works at TS1 and
TPCWAE
 -
Night time protection
works at CHT
 -
Cut off wall preparation
works at Hung Hing Road and POC
Contract no. HY/2009/19  Central  Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
 -
Road works at Watson Road
 -
Fabrication of bored
piling platform
 -
Bored piling
 -
Ground contamination assessment
 -
Pre-drilling works for
bored pile and Diaphragm wall
 -
D-wall Construction
 -
Guide wall construction
for D-wall / Barette at North side
 -
Construction works for Box
Culvert T
 -
Marine Piling
 -
Preparing for fabrication
of temporary steel bridge for Culvert U
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit
nos. FEP-01/364/2009,
FEP-02/364/2009, FEP-03/364/2009,
FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to implement the Environmental
Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual
of the approved Environmental Impact Assessment (EIA) Report for Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
and in the EM&A Manual of the approved EIA Report for Central-Wan Chai
Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring and
auditing work carried out in accordance to the
Section 10.3 of EM&A Manual
and  /span>Environmental Monitoring and Audit
Requirements /span>
under Particular Specification Section 27.
1.1.3.
This report documents the
finding of EM&A works for
Environmental Permit (EP) no. EP-364/2009/A, Further Environmental Permit (FEP)
nos. FEP-01-364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A and FEP-07/364/2009/A during the period 28th December
2011 to 27th
January 2012. The
cut-off date of reporting is at 27th of each reporting month.
Section 1     Introduction
 details the scope and structure of the report.
Section 2     Project
Background  summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3     Status of Regulatory Compliance
 summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section 4     Monitoring
Requirements
 summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section 5     Monitoring
Results  summarizes the monitoring results
obtained in the reporting period.
Section 6     Compliance
Audit  summarizes the auditing of
monitoring results, all exceedances environmental parameters.
Section 7     Cumulative Construction Impact due to the
Concurrent Projects  summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section 8     Site Inspection  
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a
review of any relevant follow-up actions within the
reporting period.
Section 9     Complaints, Notification of summons and Prosecution
 summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 10    Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan Chai
Bypass and “Central-Wan Chai Bypass and Island Eastern Corridor Link 
(hereafter called “the Project  are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Reports
for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass
(Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11
December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade joining
that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to
provide relief to the very congested east-west Connaught Road Central/Harcourt
Road / Gloucester Road Corridor (the Corridor) which is currently operating
beyond its capacity. The CWB will provide relief to the existing congestion
along the Corridor and cater for the anticipated growth of traffic on Hong Kong
Island. Without the CWB and its access roads, there will not be sufficient
capacity to serve the heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of
Central  Wan Chai Bypass and Island Eastern Corridor Link under the Project
involves the construction and operation of a trunk road and its road tunnel
more than 800m in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses
existing developments from Central to North Point. The
scope of the Central-Wanchai
Bypass (CWB) and Island Eastern Corridor Link (IECL)
includes:
 -
A dual three-lane trunk
road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length
defined from the connection with the existing Rumsey Street Flyover in Central,
through to a connection with the existing Island Eastern Corridor to the east
of the Causeway Bay Typhoon Shelter (CBTS);
 -
The Central Interchange
near the Rumsey Street Flyover to provide road connections to the Central area;
 -
Tunnel control buildings
and ventilation buildings;
 -
Slip roads to connect the
CWB to the local road system in the Wan Chai North and Causeway Bay area;
 -
Associated road lighting,
road signing, traffic control and surveillance system; and
 -
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (Eps) to be granted by the
DEP before they may
be either constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these
Schedule 2 DPs.
Table 2.1   Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. 
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits such that the impact monitoring
stations are sub-divided accordingly to facilitate the implementation of
EM&A programme and to streamline the EM&A reporting for individual FEP
holders correspondingly.
2.3.2.
In the reporting month, Central-Wanchai Bypass  Tunnel
(Causeway Bay Typhoon Shelter Section) was commenced on 13 July 2011. The details of individual
contracts are summarized in Table2.2.
Table 2.2  Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central  Wan Chai Bypass (CWB)  Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre  Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1 |
13 July 2011 |
HY/2009/19 |
Central  Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and
Development Department and Highways Department are the overall project
controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass
respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Lam
Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
Project Manager |
Mr. K. S. Law |
9090 1378 |
2566 7522 |
Site Agent |
Mr. Tony Au |
9725 5874 |
2566 7522 |
||
Sub Agent |
Mr. Johnny Wong |
9725 5870 |
2566 7522 |
||
Chun
Wo  Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
Mr. PL Yue |
2162 9909 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Sub Agent |
Mr. Terry Wong |
9757 9846 |
|||
Construction Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction Manager |
Mr. Jack Chu |
9775 2467 |
|||
Construction Manager |
Mr KK Yuen |
9498 1213 |
|||
Construction Manager |
Mr. Andy Yu |
9648 4896 |
|||
Environmental Officer
(Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Environmental Supervisor |
Ms. Kiwi Chan |
6227 8840 |
|||
|
|
Environmental Supervisor |
Mr. Yeung Sze King |
9047 9952 |
|
Environmental Supervisor |
Mr. Les Chow |
6692 2423 |
|
||
Environmental Supervisor |
Mr. Otto Yau |
9260 4485 |
|
||
Chun Wo  CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Site Agent |
Mr. Mak Kam Wing |
3658-3044 |
|||
Deputy Site Agent |
Mr. Anthony Wu |
3658-3004 |
|||
Quality & Environmental Manager |
Mr. C.P. Ho |
3658-3000 |
|||
Environmental Officer |
Ms Flora Ng |
3658-3064 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Engineer |
Mr. Simon Wong |
9281 4346 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
|
Deputy Site Agent |
Mr. Desmond Sze |
2214 7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Supervisor |
Mr. Dennis Yu |
2214 7738 |
|||
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2566 2192 |
Site Agent |
Mr. P J Fan |
3557 6368 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Environmental Supervisor |
Mr. Kelven Yip |
3557 6347 |
|||
Environmental Supervisor |
Mr. Tim Fung |
3557 6349 |
|||
|
|
Environmental Supervisor |
Mr. Hilda Lau |
3557 6378 |
|
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month,
the principal work activities of individual contracts are included as follows:
Contract no. HY/2009/17  Central  Wan Chai Bypass
(CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009
 -
ELS works for basement
construction for pile cap construction.
Contract
no. HY/2009/18  Central  Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
 -
Instrumentation works for
Manholes and Intake Culvert Survey
 -
Excavation of trial pit
 -
Drainage work
 -
Site investigation and
pre-drilling works
 -
Diaphragm wall
construction
 -
Hoarding erection
 -
Roadwork
 -
Sheet-piling
 -
Grout curtain
 -
Tree pruning
Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under
FEP-02/364/2009
 -
Diaphragm wall
construction works for CWB
 -
Pre-drilling works for CWB
(stage 2)
 -
Pre-bored H pilling works
for CWB
 -
Grouting works along the southern
side of HKCEC water channel
Contract no. HK/2009/02  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
 -
Toe grout at WCR1 area
 -
Shear pin at WCR1 area
 -
Pumping test at WCR1 area
 -
King Post at WCR1 area
 -
Deep excavation of CWB at
the eastern area of working deck B
 -
Working deck B at WCR1.
Contract
no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
 -
Seawall block
construction, reclamation work and diaphragm wall construction preparation
works at TS4
 -
ELS works at TS1 and
TPCWAE
 -
Night time protection
works at CHT
 -
Construction of dewatering
well at Hung Hing Road and POC
 -
Precautionary works at
Abutment A
Contract
no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
 -
Preparation works and
concreting of marine piles
 -
Fabrication of bored
piling platform
 -
Bored piling
 -
Ground contamination
assessment
 -
D-wall Construction
 -
Construction works for Box
Culvert T
2.4.4.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. HY/2009/17  
Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works
under FEP-03/364/2009
 -
ELS works for basement
construction for pile cap construction.
Contract
no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under
FEP-05/364/2009/A
 -
Instrumentation works for
Manholes and Intake Culvert Survey
 -
Excavation of trial pit
 -
Drainage work
 -
Site investigation and
pre-drilling works
 -
Diaphragm wall
construction
 -
Hoarding erection
 -
Roadwork
 -
Grout curtain
 -
Sheet-piling
 -
Tree pruning
Contract no. HK/2009/01  Wan
Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre  Tunnel Works under FEP-02/364/2009
 -
Diaphragm wall
construction works for both CWB and SCL Protection Works within HKCEC 1
 -
Pre-drilling and
pre-treatment works for CWB at stage2
 -
Pilling works for CWB at
Stage 1
 -
Excavation and
Installation of shoring system for CWB top slab
 -
Installation of sheet pile
for SCL top slab construction and exhaust duct construction
Contract no. HK/2009/02  Wan
Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
 -
Deep excavation works
below +0.3mPD for western tunnel portion and below +4mPD for eastern tunnel
portion.
 -
Toe grout, Shear pin, and
Pumping test at WCR1 area.
Contract no. HY/2009/15  Central-Wanchai Bypass  
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
 -
Diaphragm wall
construction at TS4
 -
ELS works at TS1 and
TPCWAE
 -
Night time protection
works at CHT
 -
Cut off wall preparation
works at Hung Hing Road and POC
Contract no. HY/2009/19  Central  Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
 -
Road works at Watson Road
 -
Fabrication of bored
piling platform
 -
Bored piling
 -
Ground contamination assessment
 -
Pre-drilling works for
bored pile and Diaphragm wall
 -
D-wall Construction
 -
Guide wall construction
for D-wall / Barette at North side
 -
Construction works for Box
Culvert T
 -
Marine Piling
 -
Preparing for fabrication
of temporary steel bridge for Culvert U
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-364/2009/A |
 4 Aug 2010 |
Valid |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov
2010 |
Valid |
Further
Environmental Permit |
24 Mar
2010 |
Valid |
|
Further
Environmental Permit |
21 Apr 2010 |
Valid |
|
Further
Environmental Permit |
12 July 2010 |
Valid |
|
Further
Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further
Environmental Permit |
15 Nov 2010 |
Valid |
|
Further
Environmental Permit |
22 Nov 2010 |
Valid |
|
Further
Environmental Permit |
25 Feb 2011 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the
status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HY/2009/17  Central  Wan Chai Bypass
(CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009
3.1.3.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-03/364/2009 for
contract no. HY/2009/17 showed in Table
3.2 and
Table 3.3.
Table
3.2  Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010  31
Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 July 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Table 3.3  Summary
of submission status under FEP-03/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management
Organization of Main Construction Companies |
18 September 2010 |
Conditions 2.7 and 2.8 |
Submission
of works schedule and location plan |
1 September 2010 |
Condition
2.9 |
Noise
Management Plan |
1 September 2010 |
Contract
no. 04/HY/2006  /span>
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4.
The construction works
was completed, and the FEP was surrendered by the Contractor on 11 February
2011.
Contract no. HK/2009/01  Wan
Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre  Tunnel Works under FEP-02/364/2009
3.1.5.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-02/364/2009 for
contract no.
HK/2009/01 are shown in Table 3.4 and
Table 3.5
Table 3.4  Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under
APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0680-11 |
22 Jul 2011 |
24 Jul 2011 to 19 Jan 2012 |
Expired |
|
GW-RS0689-11 |
28 Jul 2011 |
29 Jul 2011 to 28 Jan 2012 |
Cancelled |
|
GW-RS0832-11 |
7 Sep 2011 |
03 Sep 2011 to 02 Mar 2012 |
Cancelled |
|
GW-RS0850-11 |
12 Sept 2011 |
14 Sept 2011 to 13 Mar 2012 |
Valid |
|
GW-RS0851-11 |
12 Sept 2011 |
16 Sept 2011 to 15 Mar 2012 |
Valid |
|
GW-RE0683-11 |
16 Sept 2011 |
20 Sept 2011 to 19 Oct 2012 |
Valid |
|
GW-RE0716-11 |
28 Sept 2011 |
07 Oct 2011 to 29 Mar 2012 |
Valid |
|
GW-RS1031-11 |
02
Nov 2011 |
07
Nov 2011 to 05 May 2012 |
Valid |
|
GW-RS1094-11 |
23
Nov 2011 |
27
Nov 2011 to 26 May 2011 |
Valid |
|
GW-RS1227-11 |
30 Dec 2011 |
30 Dec 2011 to 26 Jul 2012 |
Valid |
|
GW-RS0038-12 |
16 Jan 2012 |
15 Jan 2012 to 12 Jul 2012 |
Valid |
|
GW-RS0047-12 |
16 Jan 2012 |
15 Jan 2012 to 29 Jan 2012 |
Expired |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
Billing
account under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.5  Summary
of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
25 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
10 Jun 2011 |
Contract no. HK/2009/02  Wan
Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
3.1.6.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-01/364/2009 for
contract no.
HK/2009/02 are shown in Table 3.6 and
Table 3.7.
Table 3.6  Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb
2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0579-11 |
22 June 2011 |
17 July 2011 to 16 Jan 2012 |
Expired |
|
GW-RS0649-11 |
22 July 2011 |
1 Aug 2011 to 31 Jan 2012 |
Expired |
|
GW-RE0710-11 |
30 Sept
2011 |
1 Nov
2011 to 30 Apr 2012 |
Valid |
|
GW-RS0716-11 |
2 Aug 2011 |
12 Aug 2011 to 11 Feb 2012 |
Cancelled |
|
GW-RS0833-11 |
8 Sept
2011 |
10 Sept
2011 to 4 Mar 2012 |
Valid |
|
GW-RS0918-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Valid |
|
GW-RS0929-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Cancelled |
|
GW-RS0930-11 |
11 Oct
2011 |
1 Nov
2011 to 30 Apr 2012 |
Valid |
|
GW-RS0931-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Valid |
|
GW-RS0941-11 |
20 Oct
2011 |
23 Nov
2011 to 22 May 2012 |
Valid |
|
GW-RS0955-11 |
14 Oct
2011 |
23 Nov
2011 to 22 May 2012 |
Valid |
|
GW-RS0968-11 |
20 Oct
2011 |
18 Nov
2011 to 17 May 2012 |
Valid |
|
GW-RS0983-11 |
24 Oct
2011 |
26 Oct
2011 to 23 April 2012 |
Cancelled |
|
GW-RS0984-11 |
 /span>25 Oct 2011 |
30 Oct
2011 to 27 April 2012 |
Valid |
|
GW-RS1028-11 |
3 Nov
2011 |
7 Dec
2011 to 6 June 2012 |
Valid |
|
GW-RS1052-11 |
18 Nov
2011 |
21 Nov
2011 to 18 May 2012 |
Valid |
|
GW-RS1111-11 |
28 Nov
2011 |
29 Nov
2011 to 28 May 2012 |
Valid |
|
GW-RS1116-11 |
28 Nov
2011 |
13 Dec
2011 to 12 June 2012 |
Valid |
|
GW-RS1209-11 |
3 Jan
2012 |
17 Jan
2012 to 16 July 2012 |
Valid |
|
GW-RS0037-12 |
19 Jan
2012 |
1 Feb
2012 to 31 July 2012 |
Valid |
|
GW-RS0051-12 |
19 Jan
2012 |
1 Feb
2012 to 31 July 2012 |
Valid |
|
GW-RS0052-12 |
19 Jan
2012 |
1 Feb
2012 to 30 April 2012 |
Valid |
Discharge
Licence |
WT00006249-2010 |
22 Mar
2010 |
31 Mar
2015 |
Valid |
|
WT00006436-2010 |
15 Apr
2010 |
30 Apr
2015 |
Valid |
|
WT00006673-2010 |
14 May
2010 |
31 Mar
2015 |
Valid |
|
WT00006757-2010 |
28 May
2010 |
31 May
2015 |
Valid |
|
WT00007129-2010 |
28 July
2010 |
31 Jul
2015 |
Valid |
|
WT00008982-2011 |
26 April
2011 |
30 April
2016 |
Valid |
|
WT00009691-2011 |
1 Aug 2011 |
31 July
2016 |
Valid |
Billing
Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table 3.7  Summary
of submission status under FEP-01/364/2009
EP Condition |
Submission |
Date of Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
21 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
28 Jun 2011 |
Condition 2.11 |
Landscape Plan |
23 Aug 2011 |
Condition 2.9 |
Noise Management Plan (Rev.A) |
28-Sep-11 |
Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central
Interchange under FEP-05/364/2009/A
3.1.7.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under FEP-05/364/2009A for
contract no. HY/2009/18
are shown in Table 3.8
and Table 3.9.
Table 3.8  Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Permit / Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Permit issued |
Valid |
Notification of Works Under APCO |
322293 |
07 Oct 2010 |
Notified |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0993-11 |
28 Oct 2011 |
28 Oct 2011  br>
25 Apr 2012 |
Valid |
|
GW-RS1208-11 |
23 Dec 2011 |
18 Jan 2012  br>
21 Jan 2012 |
Expired |
Discharge Licence |
WT00008229-2011 |
13 Jan 2011 |
31 Jan 2016 |
Valid |
Registration as a Waste Producer |
WPN: 8335-121-L1048-04 |
17 Dec 2010 |
N/A |
Registration completed |
Billing Account under Waste
Disposal Ordinance (Land) |
Account No.: 7011587 |
11 Oct 2010 |
Account approved |
Valid |
Table 3.9  Summary
of submission status under FEP-05/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan (Rev. 4) |
3 August 2011 |
Contract no. HY/2009/15  Central-Wanchai Bypass  
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
3.1.8.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-06/364/2009/A for
contract no.
HY/2009/15 are shown in Table 3.10 and
Table 3.11
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0749-11 |
11 Aug 2011 |
15 Aug 2011 to 7 Feb 2012 |
Cancelled |
|
GW-RS1021-11 |
4 Nov 2011 |
10 Nov 2011 to 9 May 2012 |
Valid |
|
GW-RS0847-11 |
14 Sep 2011 |
19 Sep 2011 to 16 Mar 2012 |
Cancelled |
|
GW-RS1153-11 |
9 Dec 2011 |
12 Dec 2011 to 16 Mar 2012 |
Valid |
|
GW-RS0858-11 |
16 Sep 2011 |
18 Sep 2011 to 16 Mar 2012 |
Cancelled |
|
GW-RS1211-11 |
22 Dec 2011 |
24 Dec 2011 to 21 Jun 2012 |
Valid |
|
GW-RS0883-11 |
4 Oct 2011 |
5 Oct 2011to 4 Apr 2012 |
Valid |
|
GW-RS0820-11 |
5 Sep 2011 |
8 
Sep 2011 to 7 Mar 2012 |
Valid |
|
GW-RS1149-11 |
7 Dec 2011 |
8 Dec 2011 to 7 Jun 2012 |
Cancelled |
|
GW-RS1138-11 |
7 Dec 2011 |
8 Dec 2011 to 21 May 2012 |
Valid |
|
GW-RS1190-11 |
30 Dec 2011 |
22 Dec 2011 to 21 Jun
2012 |
Valid |
|
GW-RS0997-11 |
2 Nov 2011 |
2 Nov 2011 to 2 May 2012 |
Valid |
|
GW-RS1021-11 |
4 Nov 2011 |
10 Nov 2011 to 9 May 2012 |
Valid |
Registration as a
Chemical Waste Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010 to 27 Jan 2016 |
Valid |