Contract No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and Testing Work (Stage
2) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a
and FEP-07/364/2009/A Monthly Environmental Monitoring
& Audit Report
- february 2012 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
                         Raymond Dai Environmental Team
Leader |
|
DATE: |
|
9 March 2012 |
1.1    Scope
of the Report
1.2    Structure
of the Report
2.   Project Background
2.1    Background
2.2    Scope
of the Project and Site Description
2.3    Division
of the Project Responsibility
2.4    Project
Organization and Contact Personnel
3.   status of regulatory compliance
3.1    Status
of Environmental Licensing and Permitting under the Project
4.   Monitoring
Requirements
4.1    Noise
Monitoring
4.2    Air
Monitoring
5.   Monitoring Results
5.1    Noise
Monitoring Results
5.2    Real Time Noise Monitoring Results
5.3    Air
Monitoring Results
5.4    Waste
Monitoring Results
6.1    Noise
Monitoring
6.2    Real Time Noise Monitoring
6.3    Air
Monitoring
6.4    Review
of the Reasons for and the Implications of Non-compliance
6.5    Summary
of action taken in the event of and follow-up on non-compliance
7.   Cumulative Construction Impact due to the
Concurrent Projects
8.   Environmental Site
Audit
9.   Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1    Schedule
2 Designated Projects under this Project
Table 2.2   Details of Individual Contracts under the Project
Table 2.3   Contact Details of Key Personnel
Table 3.3   Summary of submission status under FEP-03/364/2009
Table 3.5   Summary of submission status under FEP-02/364/2009
Table 3.7   Summary of submission status under FEP-01/364/2009
Table 3.9   Summary of submission status under FEP-05/364/2009/A
Table 3.10  Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/15
Table 3.11  Summary of submission status under FEP-06/364/2009/A
Table 3.12  Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/19
Table 3.13  Summary of submission status under FEP-07/364/2009/A
Table 4.1   Noise Monitoring Stations
Table 4.2   Real Time Noise Monitoring Stations
Table 4.3   Air Monitoring Stations
Table 5.1    Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.2    Noise Monitoring Stations for Contract no. HY/2009/18
Table 5.3    Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Table 5.4    Noise Monitoring Stations for Contract no. HY/2009/15
Table 5.5    Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.6   Real Time Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.7   Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8    Air Monitoring Station for Contract no. HY/2009/17
Table 5.9    Air Monitoring Stations for Contract no. HY/2009/18
Table 5.10   Air Monitoring Station for Contract no. HK/2009/01
Table 5.11   Air Monitoring Station for Contract no. HK/2009/02
Table 5.12   Air Monitoring Station for Contract no. HY/2009/15
Table 5.13   Air Monitoring Stations for Contract no. HY/2009/19
Table 5.14  Details of Waste Disposal for Contract no. HY/2009/17
Table 5.15  Details of Waste Disposal for Contract no. HK/2009/01
Table 5.16  Details of Waste Disposal for Contract no. HK/2009/02
Table 5.17  Details of Waste Disposal for Contract no. HY/2009/18
Table 5.18  Details of Waste Disposal for Contract no. HY/2009/15
Table 5.19  Details of Waste Disposal for Contract no. HY/2009/19
Table 8.1   Summary of Environmental Inspections for Contract no. HY/2009/15
Table 8.2   Summary of Environmental Inspections for Contract no. HY/2009/18
Table 8.3   Summary of Environmental Inspections for Contract no. HY/2009/19
Table 8.4   Summary of Environmental Inspections for Contract no. HK/2009/01
Table 8.5   Summary of Environmental Inspections for Contract no. HK/2009/02
Table 9.1   Cumulative Statistics on Complaints
Table 9.2   Cumulative Statistics on Successful Prosecutions
lIST OF
FIGUREs
Figure
2.1       Project
Layout
Figure
2.2       Project Organization Chart
Figure 4.1        Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1     Environmental
Mitigation Implementation Schedule
Appendix 4.1     Action and
Limit Level
Appendix
4.2     Copies of Calibration
Certificates
Appendix
5.1     Monitoring Schedule for Reporting
Month and Coming month
Appendix 5.2     Noise Monitoring Results and Graphical
Presentations
Appendix 5.3     Air Quality Monitoring Results and Graphical
Presentations
Appendix
5.4     Real-time Noise Monitoring Results and Graphical
Presentations
Appendix 6.1     Event
Action Plans
Appendix
6.2     Notification
of Exceedance
Appendix
9.1     Complaint Log
Appendix 10.1   Construction
Programme of Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot
- Advanced piling works under FEP-03/364/2009
 -
ELS works
for basement construction for pile cap construction.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under
FEP-05/364/2009/A
 -
Instrumentation works for Manholes and Intake Culvert Survey
 -
Excavation of trial pit
 -
Drainage work
 -
Site investigation and pre-drilling works
 -
Diaphragm wall construction
 -
Hoarding erection
 -
Roadwork
 -
Grout curtain
 -
Sheet-piling
 -
Tree pruning
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under
FEP-02/364/2009
 -
Diaphragm wall construction works for CWB (stage 1) and SCL protection
Works
 -
Diaphragm wall construction works for CWB (stage2)
 -
Pre-drill works for CWB (stage 2).
 -
Pre-bored H pilling works for CWB (stage 1)
 -
Pre-bored H pilling for exhaust duct
 -
Installation of shoring system for construction of CWB Diaphragm wall
(stage 1)
 -
Installation of shoring system for construction of exhaust duct
structure at stage 1
 -
Pre-treatment works for construction of CWB Diaphragm wall (stage 2)
 -
Guide wall construction for construction of CWB Diaphragm wall (stage 2)
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
 -
Shear pin
and Pumping test at WCR1 area.
Contract
no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
 -
Diaphragm
wall construction preparation works at TS4
 -
ELS works
at TS1 and TPCWAE
 -
Night
time protection works at CHT
 -
Cut off
wall preparation works at Hung Hing Road and POC
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under
FEP-07/364/2009/A
 -
Preparation
works and concreting of marine piles
 -
Fabrication
of bored piling platform
 -
Bored
piling (Land)
 -
Ground
contamination assessment
 -
D-wall Construction
(North & South Section)
 -
Guide
wall construction for D-wall / Barette at North side
 -
Construction
works for Box Culvert T
 -
Marine
Piling
 -
Preparing
for fabrication of temporary steel bridge for Culvert U
 -
Construction
of Jetty
Noise Monitoring
iii. ix.Monitoring
for report of review baseline noise level was performed from 11 April 2011 to 8
June 2011. Then the report was submitted
on the 20 June 2011, verified by IEC on 18 July 2011 and was approved by ER by
January 2012. The new baseline is used
for the noise calculation of this reporting month starting from January 2012.
iv.iii.
Noise monitoring
during daytime was conducted at M1a - Harbour Road Sports Center; M2b -
Noon-day gun area; M3a - Tung Lo Wan Fire Station; M4b - Victoria Center; M5b -
City Garden, M6 - HK Baptist Church Henrietta Secondary School,
M7e and M7w  International Finance Centre Eastern and Western End
of Podium on a weekly basis.  /span>No action or limit level exceedance was
recorded during the reporting month.
v. iv.
24-hour real
time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section
Whitefield Depot for the pilling works in FEHD Whitfield Depot and RTN2  
Tunnel (North Point Section) and Island Eastern Corridor Link. No project
related action and limit level exceedance was recorded in the
reporting period.
Air Monitoring
vi. v.
Due
to lack of electricity supply, the 24 TSP monitoring at the following stations
were rescheduled
CMA1b: from 13 Feb 2012 to 16 Feb 2012
CMA3a: from 13 Feb 2012 to 14 Feb 2012
CMA5a:
from 18 Feb 2012 to 20 Feb 2012
vii.vi.
1-hour and
24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b -
Oil Street Community Liaison Centre; CMA2a - Causeway Bay Community Center;
CMA3a - CWB PRE Site Office Area; CMA4a  Society for the Prevention of Cruelty
to Animals; CMA5a -
Children Garden opposite to Pedestrian Plaza; MA1e and
MA1w  International Finance Centre eastern and western wing on every six days basis. No action and limit
level exceedance were recorded in the reporting period.
Complaints, Notifications of Summons and Successful
Prosecutions
viii.vii.
There
was no environmental complaint in this reporting month.
Site Inspections and Audit
ix.viii.
The Environmental Team (ET) conducted weekly site inspections for
Contract no. HY/2009/15, HY/2009/17, HY/2009/18, HY/2009/19, HK/2009/01 and HK/2009/02
in this reporting period. The Contractors rectified major observations and
recommendations made during the audit sessions. No non-conformance was
identified during the site inspections.
x.ix.
In coming reporting month, the principal work activities of individual
contracts are anticipated as follows:
Contract no. HY/2009/17  
Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works
under FEP-03/364/2009
 -
ELS works
for basement construction for pile cap construction.
Contract no. HY/2009/18  Central  Wan Chai
Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
 -
Instrumentation works for Manholes and Intake Culvert Survey
 -
Excavation of trial pit
 -
Drainage work
 -
Site investigation and pre-drilling works
 -
Diaphragm wall construction
 -
Hoarding erection
 -
Roadwork
 -
Grout curtain
 -
Sheet-piling
 -
Tree pruning
Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under
FEP-02/364/2009
 -
Diaphragm wall construction works for both CWB and SCL Protection Works
 -
Guide wall for construction of CWB Diaphragm wall at Stage 2
 -
Pilling works for CWB and exhaust duct at Stage 1
 -
Pilling works for SCL Protection Works
 -
Installation of sheet pile for construction of exhaust duct
 -
Excavation woks
 -
Installation
of sheet pile for construction exhaust duct
 -
Installation
of sheet pile for construction of SCL top slab
Contract no. HK/2009/02  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
 -
Deep excavation works below
-0.9mPD for western tunnel portion and below +1.5mPD for eastern tunnel
portion.
 -
Shear pin
and Pumping test at WCR1 area.
Contract
no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
 -
Diaphragm wall construction at
TS4
 -
ELS works at TS1 and TPCWAE
 -
Night time protection works at
CHT
 -
Cut off wall preparation works at
Hung Hing Road and POC
Contract
no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
 -
Road
works at Watson Road
 -
Fabrication
of bored piling platform
 -
Bored
piling (Land)
 -
Ground
contamination assessment
 -
Pre-drilling
works for bored pile and Diaphragm wall
 -
D-wall Construction
(North & South Section)
 -
Guide
wall construction for D-wall / Barette at North side
 -
Construction
works for Box Culvert T
 -
Marine
Piling
 -
Installation
of temporary steel bridge at Culvert U
1.1.1.
Lam Geotechnics
Limited (LGL) has been appointed to work as the Environmental Team (ET) under
Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to implement the Environmental Monitoring and Audit
(EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report
presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of EM&A
Manual and  /span>Environmental Monitoring and Audit Requirements /span> under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/A, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-03/364/2009,
FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A during the period
28th January 2012 to 27th
February 2012. The cut-off date of reporting is at 27th of each reporting
month.
Section
1     Introduction
 details the scope and structure of the report.
Section
2     Project Background
 summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section
3     Status of Regulatory
Compliance  summarizes the status of valid
Environmental Permits / Licenses during the reporting period.
Section
4     Monitoring Requirements
 summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section
5     Monitoring Results
 summarizes the monitoring results obtained in the reporting period.
Section
6     Compliance Audit
 summarizes the auditing
of monitoring results, all exceedances environmental parameters.
Section
7     Cumulative Construction
Impact due to the Concurrent Projects  
summarizes the relevant
cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section
8     Site Inspection  
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9     Complaints, Notification of
summons and Prosecution  summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10    Conclusion
2.1.1.
“Wan Chai
Development phase II and Central-Wan Chai Bypass and “Central-Wan Chai Bypass
and Island Eastern Corridor Link (hereafter called “the Project  are Designed
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern
Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved
on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose
of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North
and North Point for construction of the Central-Wan Chai Bypass and Island
Eastern Corridor Link (CWB). Land formed under the project will be developed as
a world-class waterfront promenade joining that at the new Central waterfront
for public enjoyment.
2.1.3.
There is a
compelling and present need for the CWB to provide relief to the very congested
east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the
Corridor) which is currently operating beyond its capacity. The CWB will
provide relief to the existing congestion along the Corridor and cater for the
anticipated growth of traffic on Hong Kong Island. Without the CWB and its
access roads, there will not be sufficient capacity to serve the heavy traffic
demands at both strategic and local levels.
2.2.1.
Design and Construction of Central  Wan Chai Bypass and Island Eastern
Corridor Link under the Project involves the construction and operation of a
trunk road and its road tunnel more than 800m in length between portals that is
shown at Figure 2.1.
2.2.2.
The study area encompasses existing
developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
 -
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
 -
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
 -
Tunnel
control buildings and ventilation buildings;
 -
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
Causeway Bay area;
 -
Associated
road lighting, road signing, traffic control and surveillance system; and
 -
Other
associated works.
2.2.3.
The project also
contains various Schedule 2 DPs that, under the EIAO, require Environmental
Permits (Eps) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the
five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1   Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads |
Schedule
2, Part I, A.1 and A.7 |
Trunk
road and road tunnel more than 800 m in length |
DP2 |
Road P2
and other roads which are classified as primary/district distributor roads |
Schedule
2, Part I, A.1 |
Primary
/ district distributor roads |
DP3 |
Reclamation
works including associated dredging works |
Schedule
2, Part I, C.1 and C.12 |
Reclamation
more than 5 ha in size and a dredging operation less than 100 m from a
seawater intake point |
DP5 |
Wan Chai
East Sewage Outfall |
Schedule
2, Part I, F.5 and F.6 |
Submarine
sewage pipelines with a total diameter more than 1,200 mm and include a
submarine sewage outfall |
DP6 |
Dredging
for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui |
Schedule
2, Part I, C.12 |
A dredging
operation less than 100 m from a seawater intake point |
2.3.1.
Due to the
multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be commenced. Contractors of individual contracts will be
required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided
accordingly to facilitate the implementation of EM&A programme and to
streamline the EM&A reporting for individual FEP holders correspondingly.
2.3.2.
In the reporting
month, Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section)
was commenced on 13 July 2011. The details of individual contracts are summarized in Table2.2.
Table 2.2  Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central
 Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central
 Wan Chai Bypass (CWB)  Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai
Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre  Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai
Development Phase II  Central  Wan Chai Bypass at Wan Chai East(CWB Tunnel)
|
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai
Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1 |
13 July 2011 |
HY/2009/19 |
Central
 Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor
Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and Highways Department are
the overall project controllers for the Wan Chai Development Phase II and
Central-Wan Chai Bypass respectively. For the construction phase of the
Project, Project Engineer, Contractor(s), Environmental Team and Independent
Environmental Checker are appointed to manage and control environmental issues.
2.4.2.
The proposed
project organization and lines of communication with respect to environmental
protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer
for WDII |
Principal
Resident Engineer |
Mr.
Frankie Fan |
2587
1778 |
2587 1877 |
Engineer
for CWB |
Principal
Resident Engineer |
Mr.
Peter Poon |
3916
1818 |
3529 2829 |
|
Lam Woo &
CO., LTD. |
Contractor
under Contract no. HY/2009/17 |
Project
Manager |
Mr. K.
S. Law |
9090
1378 |
2566 7522 |
Site
Agent |
Mr. Tony
Au |
9725
5874 |
2566 7522 |
||
Sub Agent |
Mr.
Johnny Wong |
9725
5870 |
2566 7522 |
||
Chun Wo  
Leader Joint Venture |
Contractor
under Contract no. HK/2009/01 |
Joint
Venture Board Representative |
Mr. PL
Yue |
2162
9909 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Sub
Agent |
Mr.
Terry Wong |
9757
9846 |
|||
Construction Manager |
Mr. Wyman Wong |
9627
2467 |
|||
Construction Manager |
Mr. Jack Chu |
9775
2467 |
|||
Construction Manager |
Mr KK Yuen |
9498
1213 |
|||
Construction Manager |
Mr. Andy
Yu |
9648
4896 |
|||
Environmental Officer (Compliance
Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Environmental Supervisor |
Ms. Kiwi Chan |
6227 8840 |
|||
|
|
Environmental Supervisor |
Mr.
Yeung Sze King |
9047
9952 |
|
Environmental Supervisor |
Mr. Les
Chow |
6692
2423 |
|
||
Environmental Supervisor |
Mr. Otto
Yau |
9260
4485 |
|
||
Chun Wo
 CRGL Joint Venture |
Contractor
under Contract no. HK/2009/02 |
Project
Manager |
Mr. Chan
Sing Cho |
3658-3002 |
2827 9996 |
Site
Agent |
Mr. Mak
Kam Wing |
3658-3044 |
|||
Quality
& Environmental Manager |
Mr. C.P.
Ho |
3658-3000 |
|||
Environmental
Officer |
Ms Flora
Ng |
3658-3064 |
|||
Chun Wo
- CRGL - MBEC Joint Venture |
Contractor
under Contract no. HY/2009/19 |
Project
Manager |
Mr.
Rayland Lee |
3758 8879 |
2570 8013 |
Site
Agent |
Mr.
Cheung Kit Cheung |
6909
1555 |
|||
Environmental
Engineer |
Mr.
Simon Wong |
9281
4346 |
|||
Environmental
Manager / Environmental
Officer |
Mr. M.H.
Isa |
9884
0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Leighton
Contractors (Asia) Limited |
Contractor
under Contract no. HY/2009/18 |
Site
Agent |
Mr.
Brian Gillon |
2214 7700 |
|
Deputy
Site Agent |
Mr.
Desmond Sze |
2214 7703 |
|||
Environmental
Officer |
Mr.
Anfernee Chow |
2214 7721 |
|||
Environmental
Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental
Supervisor |
Ryan
Tsui |
2214 7705 |
|||
China
State Construction Engineering (HK) Ltd. |
Contractor
under Contract no. HY/2009/15 |
Project
Manager |
Mr. M Y
Wong |
2823
7879 |
2566 2192 |
Site
Agent |
Mr. P J
Fan |
3557
6368 |
|||
Contractor’s
Representative |
David Lau |
3557 6358 |
|||
Head of
construction |
Mr. Roger
Cheung |
3557
6371 |
|||
Environmental
Officer |
Mr. Daniel
Sin |
3557
6215 |
|||
Environmental
Supervisor |
Mr. Kelven
Yip |
3557
6347 |
|||
Environmental
Supervisor |
Mr. Tim
Fung |
3557
6349 |
|||
ENVIRON
Hong Kong Limited |
Independent Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr.
David Yeung |
3743
0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work activities of individual
contracts are included as follows:
Contract no. HY/2009/17  
Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works
under FEP-03/364/2009
 -
ELS works
for basement construction for pile cap construction.
Contract
no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under
FEP-05/364/2009/A
 -
Instrumentation works for Manholes and Intake Culvert Survey
 -
Excavation of trial pit
 -
Drainage work
 -
Site investigation and pre-drilling works
 -
Diaphragm wall construction
 -
Hoarding erection
 -
Roadwork
 -
Grout curtain
 -
Sheet-piling
 -
Tree pruning
Contract no. HK/2009/01  Wan Chai
Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre  Tunnel Works under FEP-02/364/2009
 -
Diaphragm wall construction works for CWB (stage 1) and SCL protection
Works
 -
Diaphragm wall construction works for CWB (stage2)
 -
Pre-drill works for CWB (stage 2)
 -
Pre-bored H pilling works for CWB (stage 1)
 -
Pre-bored H pilling for exhaust duct
 -
Installation of shoring system for construction of CWB Diaphragm wall
(stage 1)
 -
Installation of shoring system for construction of exhaust duct
structure at stage 1
 -
Pre-treatment works for construction of CWB Diaphragm wall (stage 2)
 -
Guide wall construction for construction of CWB Diaphragm wall (stage 2)
Contract no. HK/2009/02  Wan Chai
Development Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
 -
Shear pin
and Pumping test at WCR1 area.
Contract no. HY/2009/15  
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
 -
Diaphragm
wall construction preparation works at TS4
 -
ELS works
at TS1 and TPCWAE
 -
Night
time protection works at CHT
 -
Cut off
wall preparation works at Hung Hing Road and POC
Contract no. HY/2009/19  Central
 Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
 -
Preparation
works and concreting of marine piles
 -
Fabrication
of bored piling platform
 -
Bored
piling (Land)
 -
Ground
contamination assessment
 -
D-wall Construction
(North & South Section)
 -
Guide wall
construction for D-wall / Barette at North side
 -
Construction
works for Box Culvert T
 -
Marine
Piling
 -
Preparing
for fabrication of temporary steel bridge for Culvert U
 -
Construction
of Jetty
2.4.4.
In coming
reporting month, the principal work activities of individual contracts are
anticipated as follows:
Contract no. HY/2009/17  Central  Wan Chai Bypass (CWB) at FEHD
Whitfield Depot  Advanced piling works under FEP-03/364/2009
 -
ELS works
for basement construction for pile cap construction.
Contract no. HY/2009/18  Central  Wan Chai
Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
 -
Instrumentation works for Manholes and Intake Culvert Survey
 -
Excavation of trial pit
 -
Drainage work
 -
Site investigation and pre-drilling works
 -
Diaphragm wall construction
 -
Hoarding erection
 -
Roadwork
 -
Grout curtain
 -
Sheet-piling
 -
Tree pruning
Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under
FEP-02/364/2009
 -
Diaphragm wall construction works for both CWB and SCL Protection Works
 -
Guide wall for construction of CWB Diaphragm wall at Stage 2
 -
Pilling works for CWB and exhaust duct at Stage 1
 -
Pilling works for SCL Protection Works
 -
Installation of sheet pile for construction of exhaust duct
 -
Excavation woks
 -
Installation
of sheet pile for construction exhaust duct
 -
Installation
of sheet pile for construction of SCL top slab
Contract no. HK/2009/02  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
 -
Deep excavation works below
-0.9mPD for western tunnel portion and below +1.5mPD for eastern tunnel
portion.
 -
Shear pin
and Pumping test at WCR1 area.
Contract
no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
 -
Diaphragm
wall construction at TS4
 -
ELS works
at TS1 and TPCWAE
 -
Night
time protection works at CHT
 -
Cut off
wall preparation works at Hung Hing Road and POC
Contract
no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
 -
Road
works at Watson Road
 -
Fabrication
of bored piling platform
 -
Bored
piling (Land)
 -
Ground
contamination assessment
 -
Pre-drilling
works for bored pile and Diaphragm wall
 -
D-wall Construction
(North & South Section)
 -
Guide
wall construction for D-wall / Barette at North side
 -
Construction
works for Box Culvert T
 -
Marine
Piling
 -
Installation
of temporary steel bridge at Culvert U
3.1.1.
A summary of the
current status on licences and/or permits on environmental protection pertinent
to the Project is shown in Table 3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
 4 Aug 2010 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
3.1.2.
Due to the
multi-contract nature of the Project, the status of permits and/or licences
under the individual contract(s) are presented as below:
Contract no. HY/2009/17  Central
 Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under
FEP-03/364/2009
3.1.3.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table
3.2 and Table 3.3.
Table
3.2  Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010  31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 July 2010 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Table 3.3  Summary
of submission status under FEP-03/364/2009
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization
of Main Construction Companies |
18 September 2010 |
Conditions 2.7 and 2.8 |
Submission of works
schedule and location plan |
1 September 2010 |
Condition 2.9 |
Noise Management Plan |
1 September 2010 |
Contract no. 04/HY/2006  /span> Reconstruction of Bus Terminus
near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
3.1.4.
The construction works was completed, and the FEP was surrendered by the
Contractor on 11 February 2011.
Contract no.
HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009
3.1.5.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5
Table 3.4  Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0832-11 |
7 Sep 2011 |
03 Sep 2011 to 02 Mar 2012 |
Cancelled |
|
GW-RS0850-11 |
12 Sept 2011 |
14 Sept 2011 to 13 Mar 2012 |
Valid |
|
GW-RS0851-11 |
12 Sept 2011 |
16 Sept 2011 to 15 Mar 2012 |
Valid |
|
GW-RE0716-11 |
28 Sept 2011 |
07 Oct 2011 to 29 Mar 2012 |
Valid |
|
GW-RS1031-11 |
02 Nov 2011 |
07 Nov 2011 to 05
May 2012 |
Valid |
|
GW-RS1094-11 |
23 Nov 2011 |
27 Nov 2011 to 26
May 2012 |
Valid |
|
GW-RS1227-11 |
30 Dec
2011 |
30 Dec
2011 to 26 Jul 2012 |
Valid |
|
GW-RS0038-12 |
16 Jan
2012 |
15 Jan
2012 to 12 Jul 2012 |
Valid |
|
GW-RS0158-12 |
24 Feb
2012 |
24 Feb
2012 to 23 Aug 2012 |
Valid |
|
GW-RS0181-12 |
24 Feb
2012 |
27 Feb
2012 to 23 Aug 2012 |
Valid |
|
GW-RS0213-12 |
28 Feb
2012 |
29 Feb
2012 to 27 Aug 2012 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar
2015 |
Valid |
|
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
Billing account
under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan
2010 |
N/A |
Valid |
Table 3.5  Summary
of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of
Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May
2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
25 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
10 Jun 2011 |
Contract no.
HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai
East (CWB Tunnel) under FEP-01/364/2009
3.1.6.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.
Table 3.6  Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb
2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0649-11 |
22 July 2011 |
1 Aug 2011 to 31 Jan 2012 |
Expired |
|
GW-RE0710-11 |
30 Sept
2011 |
1 Nov
2011 to 30 Apr 2012 |
Valid |
|
GW-RS0716-11 |
2 Aug 2011 |
12 Aug 2011 to 11 Feb 2012 |
Cancelled |
|
GW-RS0833-11 |
8 Sept
2011 |
10 Sept
2011 to 4 Mar 2012 |
Cancelled |
|
GW-RS0918-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Valid |
|
GW-RS0929-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Cancelled |
|
GW-RS0930-11 |
11 Oct
2011 |
1 Nov
2011 to 30 Apr 2012 |
Valid |
|
GW-RS0931-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Valid |
|
GW-RS0941-11 |
20 Oct
2011 |
23 Nov
2011 to 22 May 2012 |
Valid |
|
GW-RS0955-11 |
14 Oct
2011 |
23 Nov
2011 to 22 May 2012 |
Valid |
|
GW-RS0968-11 |
20 Oct
2011 |
18 Nov
2011 to 17 May 2012 |
Valid |
|
GW-RS0983-11 |
24 Oct
2011 |
26 Oct
2011 to 23 April 2012 |
Cancelled |
|
GW-RS0984-11 |
 /span>25 Oct 2011 |
30 Oct
2011 to 27 April 2012 |
Valid |
|
GW-RS1028-11 |
3 Nov
2011 |
7 Dec
2011 to 6 June 2012 |
Valid |
|
GW-RS1052-11 |
18 Nov
2011 |
21 Nov
2011 to 18 May 2012 |
Valid |
|
GW-RS1111-11 |
28 Nov
2011 |
29 Nov
2011 to 28 May 2012 |
Valid |
|
GW-RS1116-11 |
28 Nov
2011 |
13 Dec
2011 to 12 June 2012 |
Valid |
|
GW-RS1209-11 |
3 Jan
2012 |
17 Jan
2012 to 16 July 2012 |
Valid |
|
GW-RS0037-12 |
19 Jan
2012 |
1 Feb
2012 to 31 July 2012 |
Valid |
|
GW-RS0051-12 |
19 Jan
2012 |
1 Feb
2012 to 31 July 2012 |
Valid |
|
GW-RS0052-12 |
19 Jan
2012 |
1 Feb
2012 to 30 April 2012 |
Valid |
|
GW-RS0723-11 |
12 Aug 2011 |
15 Aug 2011 to 14 Feb 2012 |
Cancelled |
|
GW-RS0086-12 |
30 Jan 2012 |
3 Feb 2012 to 2 Aug 2012 |
Valid |
|
GW-RS0105-12 |
3 Feb 2012 |
10 Feb 2012 to 9 Aug 2012 |
Valid |
|
GW-RS0153-12 |
17 Feb 2012 |
21 Feb 2012 to 20 Aug 2012 |
Valid |
Discharge
Licence |
WT00006249-2010 |
22 Mar
2010 |
31 Mar
2015 |
Valid |
|
WT00006436-2010 |
15 Apr
2010 |
30 Apr
2015 |
Valid |
|
WT00006673-2010 |
14 May
2010 |
31 Mar
2015 |
Valid |
|
WT00006757-2010 |
28 May
2010 |
31 May
2015 |
Valid |
|
WT00007129-2010 |
28 July
2010 |
31 Jul
2015 |
Valid |
|
WT00008982-2011 |
26 April
2011 |
30 April
2016 |
Valid |
|
WT00009691-2011 |
1 Aug
2011 |
31 July
2016 |
Valid |
Billing
Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb
2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep
2010 |
N/A |
Valid |
Table 3.7  Summary
of submission status under FEP-01/364/2009
EP Condition |
Submission |
Date of
Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
21 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
28 Jun 2011 |
Condition 2.11 |
Landscape Plan |
23 Aug 2011 |
Condition 2.9 |
Noise Management Plan (Rev.A) |
28-Sep-11 |
Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central
Interchange under FEP-05/364/2009/A
3.1.7.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-05/364/2009A for contract no.
HY/2009/18 are shown in Table
3.8 and Table 3.9.
Table 3.8  Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Permit / Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Permit issued |
Valid |
Notification of Works Under APCO |
322293 |
07 Oct 2010 |
Notified |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0993-11 |
28 Oct 2011 |
28 Oct 2011  br>
25 Apr 2012 |
Valid |
|
GW-RS0132-12 |
08 Feb 2012 |
21 Feb 2012  br>
25 Feb 2012 |
Expired |
Discharge Licence |
WT00008229-2011 |
13 Jan 2011 |
31 Jan 2016 |
Valid |
Registration as a Waste Producer |
WPN: 8335-121-L1048-04 |
17 Dec 2010 |
N/A |
Registration completed |
Billing Account under Waste Disposal
Ordinance (Land) |
Account No.: 7011587 |
11 Oct 2010 |
Account approved |
Valid |
Table 3.9  Summary
of submission status under FEP-05/364/2009/A
EP Condition |
Submission |
Date of
Submission |
Condition 2.9 |
Noise Management Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan (Rev. 4) |
3 August 2011 |
Contract
no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
3.1.8.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.10 and Table 3.11
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov
2010 |
N/A |
Valid |