Contract
No: HK/2011/07 Wanchai Development Phase II and Central Wanchai
Bypass Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/A and FEP-08/364/2009/A Monthly Environmental
Monitoring & Audit Report
- june 2012 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre
Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
                         Raymond Dai Environmental Team Leader |
|
DATE: |
|
11 July 2012 |
1.1    Scope
of the Report
1.2    Structure
of the Report
2.   Project Background
2.1    Background
2.2    Scope
of the Project and Site Description.
2.3    Division
of the Project Responsibility
2.4    Project
Organization and Contact Personnel
3.   status of regulatory compliance
3.1    Status
of Environmental Licensing and Permitting under the Project
4.   Monitoring
Requirements
4.1    Noise
Monitoring
4.2    Air
Monitoring
5.   Monitoring Results
5.1    Noise
Monitoring Results
5.2    Real Time Noise Monitoring Results
5.3    Air
Monitoring Results
5.4    Waste
Monitoring Results
6.1    Noise
Monitoring
6.2    Real Time Noise Monitoring.
6.3    Air
Monitoring
6.4    Review
of the Reasons for and the Implications of Non-compliance
6.5    Summary
of action taken in the event of and follow-up on non-compliance
7.   Cumulative Construction Impact due to the
Concurrent Projects
8.   Environmental Site
Audit
9.   Complaints, Notification of Summons and Prosecution
lIST
OF TABLES
Table 2.1    Schedule 2 Designated Projects under this
Project
Table 2.2   Details of Individual Contracts under the Project
Table 2.3   Contact Details of Key Personnel
Table 3.3   Summary of submission status under FEP-03/364/2009
Table 3.5   Summary of submission status under FEP-02/364/2009
Table 3.7   Summary of submission status under FEP-01/364/2009
Table 3.9   Summary of submission status under FEP-05/364/2009/A
Table 3.10  Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Table 3.11  Summary of submission status under
FEP-06/364/2009/A
Table 3.12  Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/19
Table 3.13  Summary of submission status under
FEP-07/364/2009/A
Table 3.14  Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2010/06
Table 4.1   Noise Monitoring Stations
Table 4.2   Real Time Noise Monitoring Stations
Table 4.3   Air Monitoring Stations
Table 5.1    Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.2    Noise Monitoring Stations for Contract no. HY/2009/18
Table 5.3    Noise Monitoring Station for Contract no HK/2009/01 and
HK/2009/02
Table 5.4    Noise Monitoring Stations for Contract no. HY/2009/15
Table 5.5    Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.6   Real Time Noise Monitoring Stations for Contract no.
HY/2009/17
Table 5.7   Real Time Noise Monitoring Stations for Contract no.
HY/2009/19
Table 5.8    Air Monitoring Station for Contract no. HY/2009/17
Table 5.9    Air Monitoring Stations for Contract no. HY/2009/18
Table 5.10   Air Monitoring Station for Contract no.
HK/2009/01
Table 5.11   Air Monitoring Station for Contract no.
HK/2009/02
Table 5.12   Air Monitoring Station for Contract no. HY/2009/15
Table 5.13   Air Monitoring Stations for Contract no.
HY/2009/19
Table 5.14  Details of Waste Disposal for Contract no.
HY/2009/17
Table 5.15  Details of Waste Disposal for Contract no.
HK/2009/01
Table 5.16  Details of Waste Disposal for Contract no.
HK/2009/02
Table 5.17  Details of Waste Disposal for Contract no.
HY/2009/18
Table 5.18  Details of Waste Disposal for Contract no.
HY/2009/15
Table 5.19  Details of Waste Disposal for Contract no.
HY/2009/19
Table 5.20  Details of Waste Disposal for Contract no. HK/2010/06
Table 8.1   Summary of Environmental Inspections for Contract no.
HY/2009/15
Table 8.2   Summary of Environmental Inspections for Contract no.
HY/2009/19
Table 8.3   Summary of Environmental Inspections for Contract no.
HK/2009/01
Table 8.4    Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.5    Summary of Environmental Inspections for
Contract no. HK/2010/06
Table 9.1   Cumulative Statistics on Complaints
Table 9.2   Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure 2.1       Project Layout
Figure
2.2       Project
Organization Chart
Figure 4.1        Locations of
Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
3.1     Environmental Mitigation Implementation Schedule
Appendix 4.1     Action and Limit Level
Appendix 4.2     Copies of Calibration
Certificates
Appendix
5.1     Monitoring Schedule for Reporting Month and Coming month
Appendix
5.2     Noise Monitoring Results and Graphical Presentations
Appendix
5.3     Air Quality Monitoring Results and
Graphical Presentations
Appendix 5.4     Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1     Event Action Plans
Appendix 6.2     Notification of Exceedance
Appendix 9.1     Complaint Log
Appendix 10.1   Construction Programme of
Individual Contracts
i.
This is the
Environmental Monitoring and Audit (EM&A) Monthly Report
 /span> June 2012 specific for Environmental
Permit no. EP-364/2009/A, Further Environmental Permit nos. FEP-01/364/2009,
FEP-02-364/2009, FEP-03-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/A and FEP-08/364/2009/A. The EM&A report is prepared by
the Environmental Team (ET) employed under Contract
No. HK/2011/07  /span> Wan Chai Development Phase II and Central Wanchai Bypass  Sampling, Field Measurement and
Testing Works (Stage 2). This report presents
the environmental monitoring findings and information recorded during the
period May to June 2012. The cut-off
date of reporting is at 27th of each reporting month.
iv.
In the
reporting month, the principal work activities of individual contracts are
included as follows:
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield
Depot - Advanced piling works under FEP-03/364/2009
 -
ELS works for
basement construction for pile cap construction.
Contract no. HY/2009/18 - Central - Wan
Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
 -
Trial Pit
 -
Instrumentation
and monitoring works
 -
Drainage works
 -
Site
investigation and pre-drilling works
 -
D-wall
construction
 -
Sheet piling
 -
Grout curtain
 -
Tree
Transplantation
 -
Earthwork
 -
Preparation
works in existing tunnel
 -
Stitch coring
 -
Approach ramp
structure works
 -
Top down slab
 -
Road works
 -
Tunnel works
 -
Excavation and
Lateral Support
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
 -
Diaphragm wall
construction works for CWB (Stage2)
 -
Pre-drilling
works for CWB (Stage2)
 -
Pre-bored H
piling works for SCL
 -
Excavation for
CWB top slab (Bay1  Bay 4)
 -
Waterproofing
works for CWB top slab (Bay 1  Bay 4)
 -
Excavation and
installation of shoring system for construction of exhaust duct structure
 -
Excavation for
SCL top slab construction works
 -
Construction
of SCL top slab (Bay 3)
 -
Trimming of
SCL Diaphragm wall head
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
 -
Deep
excavation works. The excavation level
has reached -9.0mPD to -9.8mPD on the eastern and western portion of the site respectively.
 -
Tunnel Pre-drill
work of bored pile at tunnel portion 3 & 4 area.
 -
Trench
excavation for guide wall of Diaphragm wall at tunnel portion 3 & 4 area.
 -
Guide wall
construction for Diaphragm wall at tunnel portion 3 & 4 area.
 -
Bored pile
PC34 and PC35.
 -
Pre-drill for
bored pile and diaphragm wall.
 -
Handover of
Government Helipad at Tunnel Portion 3&4 and initial Survey at ex-helipad.
 -
Half bay of
bulkhead wall construction
Contract no. HY/2009/15 -
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
 -
Diaphragm wall
construction works at TS4
 -
ELS works at
TPCWAE
 -
Cut and cover
tunnel construction at TS1
 -
Night time
protection works at CHT
 -
Cut off wall
preparation works at Hung Hing Road and POC
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
 -
Road works at
Watson Road
 -
Fabrication of
bored piling platform
 -
Bored piling
(Land)
 -
Ground
contamination assessment
 -
Pre-drilling
works for bored pile and Diaphragm wall
 -
D-wall Construction
(North & South Section)
 -
Guide wall
construction for D-wall / Barette at North side
 -
Construction
works for Box Culvert T
 -
Construct ion
of socket-H pile for Marine works
 -
Construction
of pre-bored H-pile works for Culvert U
 -
Installation
of sheet pile at D9 location
 -
Construction
of pile cap
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
 -
Construction
of Pre-cast Unit in China
Noise Monitoring
Monitoring
for report of review baseline noise level was performed from 11 April 2011 to 8
June 2011. Then the report was
submitted on the 20 June 2011, verified by IEC on 18 July 2011 and was approved
by ER by January 2012. The new baseline
is used for the noise calculation of this reporting month starting from January
2012.
viii.
24-hour real time noise
monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitefield
Depot for the pilling works in FEHD Whitfield Depot and RTN2  Tunnel (North
Point Section) and Island Eastern Corridor Link. No project related action
and limit level exceedance was recorded in the reporting period.
Air Monitoring
x.
Due to lack of electricity
supply, the 24-hr TSP monitoring at the following stations were rescheduled
CMA1b: from 6 June 2012 to 7
June 2012
CMA5a: from 6 June 2012 to 7
June 2012
CMA2a: from 18 June 2012 to
19 June 2012
xi.
1-hour and 24-hour Total Suspended
Particulates (TSP) monitoring were conducted at CMA1b - Oil Street Community
Liaison Centre; CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site
Office Area; CMA4a  Society for the Prevention of Cruelty to Animals; CMA5a - Children Garden opposite to
Pedestrian Plaza; MA1e and MA1w  International
Finance Centre eastern and western wing on every six days basis. No action and limit level
exceedance were recorded in the reporting period.
Complaints,
Notifications of Summons and Successful Prosecutions
xii.
There was no
environmental complaint received in this
reporting month.
Site Inspections and
Audit
xiii.
The
Environmental Team (ET) conducted weekly site inspections for Contract no.
HY/2009/15, HY/2009/17, HY/2009/18, HY/2009/19, HK/2009/01, HK/2009/02 and
HK/2010/06 in this reporting period. The Contractors rectified major
observations and recommendations made during the audit sessions. No
non-conformance was identified during the site inspections.
xiv.
In the coming
reporting month, the principal work activities of individual contracts are
anticipated as follows:
Contract no. HY/2009/17  Central  Wan
Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under
FEP-03/364/2009
 -
ELS works for
basement construction for pile cap construction.
Contract no. HY/2009/18  Central  Wan
Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
 -
Trial pit
 -
Instrumentation
and monitoring works
 -
Drainage works
 -
Site
investigation and pre-drilling works
 -
D-wall
construction
 -
Sheet piling
 -
Tree
Transplantation
 -
Earthworks
 -
Preparation
works in existing tunnel
 -
Approach ramp
(trough) structure works
 -
Top down slab
 -
Road works
 -
Tunnel works
 -
Excavation and
Lateral Support
 -
Pipe-pile
works
 -
Cooling main
bridge construction
 -
Bridge A
construction
Contract no.
HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009
 -
Diaphragm wall
construction for CWB tunneling works at Stage2
 -
Waterproofing
works for CWB top slab
 -
Excavation and
installation of shoring system for construction of exhaust dust
 -
Construction
of exhaust duct structure (Bay1)
 -
Construction
of exhaust duct structure (Bay2)
 -
Load test on
SCL pre-bored H-piles works
 -
Excavation for
construction of SCL top slab
 -
Construction
of SCL top slab (Bay 3)
 -
Construction
of SCL top slab (Bay1 and Bay 2)
Contract no.
HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
 -
Bored piling,
breaking concrete slab and excavation of trial pit at tunnel portion 3 & 4.
 -
Deep
excavation and strut installation works below -9.8mPD for western tunnel
portion and below +9.0mPD for eastern tunnel portion.
Contract no. HY/2009/15  
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
 -
Diaphragm wall
construction works at TS4
 -
ELS works at
TPCWAE
 -
Cut and cover
tunnel construction at TPCWAE
 -
Mined tunnel
preparation works at TPCWAE and Hung Hing Road
Contract no. HY/2009/19  Central  
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
 -
Road works at
Watson Road
 -
Laying od 1500f drainage pipe
 -
Fabrication of
bored piling platform
 -
Bored piling
(Land)
 -
Ground
contamination assessment
 -
Pre-drilling
works for bored pile and Diaphragm wall
 -
D-wall Construction
(North & South Section)
 -
Guide wall
construction for D-wall / Barette at North side
 -
Construction
works for Box Culvert T
 -
Construct ion
of socket-H pile for Marine works
 -
Construction
of pre-bored H-pile works for Culvert U
 -
Construction
of 1500 drainage along D-wall
 -
Construction
of pile cap
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
 -
Construction
of Pre-cast Unit in China
1.1.1.
Lam Geotechnics Limited (LGL) has been
appointed to work as the Environmental Team (ET) under Environmental Permit no.
EP-364/2009A and Further Environmental permit nos.
FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A and FEP-08/364/2009/A to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This report presents the environmental
monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and  /span>Environmental Monitoring and Audit Requirements /span> under Particular
Specification Section 27.
1.1.3.
This report
documents the finding of EM&A works for Environmental Permit (EP) no.
EP-364/2009/A, Further Environmental Permit (FEP) nos. FEP-01-364/2009,
FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A,
FEP-07/364/2009/A and FEP-08/364/2009/A during the period May to June 2012. The cut-off date of reporting is at 27th of each reporting
month.
Section 1     Introduction  details
the scope and structure of the report.
Section 2     Project
Background  summarizes background and scope of the project, site
description, project organization and contact details of key personnel during
the reporting period.
Section 3     Status of Regulatory Compliance  
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section 4     Monitoring
Requirements  summarizes all monitoring parameters, monitoring
methodology and equipment, monitoring locations, monitoring frequency, criteria
and respective event and action plan and monitoring programmes.
Section 5     Monitoring
Results  summarizes the monitoring results obtained in the
reporting period.
Section 6     Compliance Audit  
summarizes the auditing
of monitoring results, all exceedances environmental parameters.
Section 7     Cumulative Construction Impact due to the Concurrent Projects  summarizes the relevant cumulative construction impact due to the
concurrent activities of the concurrent Projects.
Section 8     Site Inspection  summarizes the findings of
weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9     Complaints, Notification of summons and Prosecution  
summarizes the cumulative statistics on
complaints, notification of summons and prosecution
Section 10    Conclusion
2.1.1.
“Wan Chai Development phase II and
Central-Wan Chai Bypass and “Central-Wan Chai Bypass and Island Eastern
Corridor Link (hereafter called “the Project  are Designated Project (DP) under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development
Phase II (WDII) is to provide land at Wan Chai North and North Point for
construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link
(CWB). Land formed under the project will be developed as a world-class
waterfront promenade joining that at the new Central waterfront for public
enjoyment.
2.1.3.
There is a compelling and present need
for the CWB to provide relief to the very congested east-west Connaught Road
Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1.
Design and
Construction of Central  Wan Chai Bypass and Island Eastern Corridor Link
under the Project involves the construction and operation of a trunk road and
its road tunnel more than 800m in length between portals that is shown at Figure 2.1.
2.2.2.
The study area
encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
 -
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
 -
The Central
Interchange near the Rumsey Street Flyover to provide road connections to the
Central area;
 -
Tunnel control
buildings and ventilation buildings;
 -
Slip roads to
connect the CWB to the local road system in the Wan Chai North and Causeway Bay
area;
 -
Associated
road lighting, road signing, traffic control and surveillance system; and
 -
Other
associated works.
2.2.3.
The project also contains various
Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the
five individual DPs under this Project. Figure 2.1 shows the locations
of these Schedule 2 DPs.
Table
2.1   Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the
Project, there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. 
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits such that the impact
monitoring stations are sub-divided accordingly to facilitate the
implementation of EM&A programme and to streamline the EM&A reporting
for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are
summarized in Table2.2.
Table
2.2  Details of Individual Contracts
under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central  Wan Chai Bypass (CWB)  Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre  Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1 |
13 July 2011 |
HY/2009/19 |
Central  Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
2.4.1.
Civil
Engineering and Development Department and Highways Department are the overall
project controllers for the Wan Chai Development Phase II and Central-Wan Chai
Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and
lines of communication with respect to environmental protection works are shown
in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 8332 |
3529 2829 |
|
Lam Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
Project Manager |
Mr. K. S. Law |
9090 1378 |
2566 7522 |
Site Agent |
Mr. Tony Au |
9725 5874 |
2566 7522 |
||
Sub Agent |
Mr. Johnny Wong |
9725 5870 |
2566 7522 |
||
Chun Wo  Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
Mr. PL Yue |
2162 9909 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Sub Agent |
Mr. Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 2467 |
|||
Construction
Manager |
Mr KK Yuen |
9498 1213 |
|||
Construction
Manager |
Mr. Andy Yu |
9648 4896 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Environmental
Supervisor |
Ms. Kiwi Chan |
6227 8840 |
|||
|
|
Environmental
Supervisor |
Mr. Yeung Sze King |
9047 9952 |
|
Environmental
Supervisor |
Mr. Les Chow |
6692 2423 |
|
||
Chun Wo  CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Quality & Environmental Manager |
Mr. C.P. Ho |
3658-3000 |
|||
Environmental Officer |
Ms Flora Ng |
3658-3064 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Assistant Site Agent |
Mr. Eric Fong |
6191 9337 |
|||
Environmental Engineer |
Mr. Simon Wong |
9281 4346 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
|
Deputy Site Agent |
Mr. Desmond Sze |
2214 7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ray Cheng |
2214 7742 |
|||
Environmental Supervisor |
K. W. Lee |
6461 4623 |
|||
|
|
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|
|
|
Environmental Supervisor |
Bosco Lee |
2214 7711 |
|
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
Mr. P.J. Fan |
3557 6368 |
2566 2192 |
||
Contractor’s Representative |
Mr. David Lau |
3557 6358 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Environmental Supervisor |
Mr. Kelven Yip |
3557 6347 |
|||
Environmental Supervisor |
Mr. Tim Fung |
3557 6349 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee Wai Man |
9481 6024 |
|||
Environmental
Supervisor |
Mr. Clement
Pang |
9735 9200 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team
Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this
reporting month, the principal work activities of individual contracts are
included as follows:
Contract no. HY/2009/17  Central  Wan
Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under
FEP-03/364/2009
 -
ELS works for
basement construction for pile cap construction.
Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central
Interchange under FEP-05/364/2009/A
 -
Trial Pit
 -
Instrumentation
and monitoring works
 -
Drainage works
 -
Site
investigation and pre-drilling works
 -
D-wall
construction
 -
Sheet piling
 -
Grout curtain
 -
Tree
Transplantation
 -
Earthwork
 -
Preparation
works in existing tunnel
 -
Stitch coring
 -
Approach ramp
structure works
 -
Top down slab
 -
Road works
 -
Tunnel works
 -
Excavation and
Lateral Support
Contract no. HK/2009/01  Wan Chai Development
Phase II  Central  Wan Chai Bypass at Hong Kong Convention and Exhibition Centre
 Tunnel Works under FEP-02/364/2009
 -
Diaphragm wall
construction works for CWB (Stage2)
 -
Pre-drilling
works for CWB (Stage2)
 -
Pre-bored H
piling works for SCL
 -
Excavation for
CWB top slab (Bay1  Bay 4)
 -
Waterproofing
works for CWB top slab (Bay 1  Bay 4)
 -
Excavation and
installation of shoring system for construction of exhaust duct structure
 -
Excavation for
SCL top slab construction works
 -
Construction
of SCL top slab (Bay 3)
 -
Trimming of
SCL Diaphragm wall head
Contract no. HK/2009/02  Wan Chai Development
Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
 -
Deep
excavation works. The excavation level
has reached -9.0mPD to -9.8mPD on the eastern and western portion of the site respectively.
 -
Tunnel Pre-drill
work of bored pile at tunnel portion 3 & 4 area.
 -
Trench
excavation for guide wall of Diaphragm wall at tunnel portion 3 & 4 area.
 -
Guide wall
construction for Diaphragm wall at tunnel portion 3 & 4 area.
 -
Bored pile
PC34 and PC35.
 -
Pre-drill for
bored pile and diaphragm wall.
 -
Handover of
Government Helipad at Tunnel Portion 3&4 and initial Survey at ex-helipad.
 -
Half bay of
bulkhead wall construction
Contract no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
 -
Diaphragm wall
construction works at TS4
 -
ELS works at
TPCWAE
 -
Cut and cover
tunnel construction at TS1
 -
Night time
protection works at CHT
 -
Cut off wall
preparation works at Hung Hing Road and POC
Contract no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
 -
Road works at
Watson Road
 -
Fabrication of
bored piling platform
 -
Bored piling
(Land)
 -
Ground
contamination assessment
 -
Pre-drilling
works for bored pile and Diaphragm wall
 -
D-wall Construction
(North & South Section)
 -
Guide wall
construction for D-wall / Barette at North side
 -
Construction
works for Box Culvert T
 -
Construct ion
of socket-H pile for Marine works
 -
Construction
of pre-bored H-pile works for Culvert U
 -
Installation
of sheet pile at D9 location
 -
Construction
of pile cap
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
 -
Construction
of Pre-cast Unit in China
2.4.4.
In coming reporting month, the principal
work activities of individual contracts are anticipated as follows:
Contract no.
HY/2009/17  Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced
piling works under FEP-03/364/2009
 -
ELS works for
basement construction for pile cap construction.
Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central
Interchange under FEP-05/364/2009/A
 -
Trial pit
 -
Instrumentation
and monitoring works
 -
Drainage works
 -
Site
investigation and pre-drilling works
 -
D-wall
construction
 -
Sheet piling
 -
Tree
Transplantation
 -
Earthworks
 -
Preparation
works in existing tunnel
 -
Approach ramp
(trough) structure works
 -
Top down slab
 -
Road works
 -
Tunnel works
 -
Excavation and
Lateral Support
 -
Pipe-pile
works
 -
Cooling main
bridge construction
 -
Bridge A
construction
Contract no.
HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009
 -
Diaphragm wall
construction for CWB tunneling works at Stage2
 -
Waterproofing
works for CWB top slab
 -
Excavation and
installation of shoring system for construction of exhaust dust
 -
Construction
of exhaust duct structure (Bay1)
 -
Construction
of exhaust duct structure (Bay2)
 -
Load test on
SCL pre-bored H-piles works
 -
Excavation for
construction of SCL top slab
 -
Construction
of SCL top slab (Bay 3)
 -
Construction
of SCL top slab (Bay1 and Bay 2)
Contract no.
HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
 -
Bored piling,
breaking concrete slab and excavation of trial pit at tunnel portion 3 & 4.
 -
Deep
excavation and strut installation works below -9.8mPD for western tunnel
portion and below +9.0mPD for eastern tunnel portion.
Contract no. HY/2009/15  
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
 -
Diaphragm wall
construction works at TS4
 -
ELS works at
TPCWAE
 -
Cut and cover
tunnel construction at TPCWAE
 -
Mined tunnel
preparation works at TPCWAE and Hung Hing Road
Contract no. HY/2009/19  Central  
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
 -
Road works at
Watson Road
 -
Laying od 1500f drainage pipe
 -
Fabrication of
bored piling platform
 -
Bored piling
(Land)
 -
Ground
contamination assessment
 -
Pre-drilling
works for bored pile and Diaphragm wall
 -
D-wall Construction
(North & South Section)
 -
Guide wall
construction for D-wall / Barette at North side
 -
Construction
works for Box Culvert T
 -
Construct ion
of socket-H pile for Marine works
 -
Construction
of pre-bored H-pile works for Culvert U
 -
Construction
of 1500 drainage along D-wall
 -
Construction
of pile cap
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
 -
Construction
of Pre-cast Unit in China
3.1.1.
A summary of the current status on
licences and/or permits on environmental protection pertinent to the Project is
shown in Table 3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
 4 Aug 2010 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental
Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Valid |
3.1.2.
Contract no.
HK/2010/06, Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR
Tsuen Wan Line, has submitted an application for Further Environmental Permit
under EP-364/2009/A on 21 May 2012 and received Further Environmental Permit  
FEP-08/364/2009/A on 15 June 2012.
3.1.3.
Due to the multi-contract nature of the
Project, the status of permits and/or licences under the individual contract(s)
are presented as below:
Contract no. HY/2009/17  Central  Wan
Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under
FEP-03/364/2009
3.1.4.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table
3.2 and Table 3.3.
Table 3.2  Cumulative
Summary of Valid Licences and Permits under Contract no.
HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010  31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 July 2010 |
N/A |
Valid |
Billing Account
under Waste Disposal Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Table 3.3  Summary of submission status under FEP-03/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
18 September 2010 |
Conditions 2.7 and
2.8 |
Submission of works schedule and location plan |
1 September 2010 |
Condition 2.9 |
Noise Management Plan |
1 September 2010 |
Contract no. 04/HY/2006  /span> Reconstruction of Bus Terminus near
Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
3.1.5.
The
construction works was completed, and the FEP was surrendered by the Contractor
on 11 February 2011.
Contract no.
HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009
3.1.6.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table
3.4 and Table 3.5
Table 3.4  Cumulative Summary of
Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of
Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS1221-11 |
30 Dec 2011 |
20 Jan 2012 to 19 Jul 2012 |
Valid |
|
GW-RS1227-11 |
30 Dec 2011 |
30 Dec 2011 to 26 Jul 2012 |
Cancelled |
|
GW-RS0038-12 |
16 Jan 2012 |
15 Jan 2012 to 12 Jul 2012 |
Cancelled |
|
GW-RS0158-12 |
24 Feb 2012 |
24 Feb 2012 to 23 Aug 2012 |
Valid |
|
GW-RS0181-12 |
24 Feb 2012 |
27 Feb 2012 to 23 Aug 2012 |
Valid |
|
GW-RS0213-12 |
28 Feb 2012 |
29 Feb 2012 to 27 Aug 2012 |
Valid |
|
GW-RS0225-12 |
02 Mar 2012 |
14 Mar 2011 to 13 Sep 2012 |
Valid |
|
GW-RS0227-12 |
02 Mar 2012 |
16 Mar 2011 to 15 Sep 2012 |
Valid |
|
GW-RE0174-12 |
05 Mar 2012 |
30 Mar 2012 to  /span>29 Sep
2012 |
Valid |
|
GW-RS0312-12 |
28 Mar 2012 |
30 Mar 2012 to  /span>29 Sep 2012 |
Valid |
|
GW-RS0314-12 |
29 Mar 2012 |
30 Mar 2012 to 25
Sep 2012 |
Cancelled |
|
GW-RS0356-12 |
03 Apr 2012 |
11 Apr 2012  to 29 Sep 2012 |
Valid |
|
GW-RS0394-12 |
16 Apr 2012 |
19 Apr 2012  to 12 Oct 2012 |
Valid |
|
GW-RS0459-12 |
3 May 2012 |
7 May 2012 to  /span>6 Nov 2012 |
Cancelled |
|
GW-RS0460-12 |
10 May 2012 |
13 May 2012 to 6
Nov 2012 |
Valid |
|
GW-RS0492-12 |
14 May 2012 |
15 May 2012 to 3
June 2012 |
Valid |
|
GW-RS0514-12 |
14 May 2012 |
27 May 2012 to 26
Nov 2012 |
Valid |
|
GW-RS0545-12 |
24 May 2012 |
26 May 2012 to 25
Nov 2012 |
Valid |
|
GW-RS0546-12 |
25 May 2012 |
26 May 2012 to 25
Nov 2012 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
Billing account under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.5  Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
25 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
10 Jun 2011 |
Contract no.
HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
3.1.7.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table
3.6 and Table 3.7.
Table 3.6  Cumulative Summary of
Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS1028-11 |
3 Nov 2011 |
7 Dec 2011 to 6 June 2012 |
Valid (Expired on 6 June 2012) |
|
GW-RS1111-11 |
28 Nov 2011 |
29 Nov 2011 to 28 May 2012 |
Expired |
|
GW-RS1116-11 |
28 Nov 2011 |
13 Dec 2011 to 12 June 2012 |
Valid (Expired on 12 June 2012) |
|
GW-RS1209-11 |
3 Jan 2012 |
17 Jan 2012 to 16 July 2012 |
Valid |
|
GW-RS0037-12 |
19 Jan 2012 |
1 Feb 2012 to 31 July 2012 |
Valid |
|
GW-RS0051-12 |
19 Jan 2012 |
1 Feb 2012 to 31 July 2012 |
Valid |
|
GW-RS0086-12 |
30 Jan 2012 |
3 Feb 2012 to 2 Aug 2012 |
Cancelled |
|
GW-RS0105-12 |
3 Feb 2012 |
10 Feb 2012 to 9 Aug 2012 |
Valid |
|
GW-RS0153-12 |
17 Feb 2012 |
21 Feb 2012 to 20 Aug 2012 |
Valid |
|
GW-RS0233-12 |
6 Mar 2012 |
9 Mar 2012 to 8 Sept 2012 |
Cancelled |
|
GW-RS0255-12 |
14 Mar 2012 |
17 Mar 2012 to 15 Sept 2012 |
Valid |
|
GW-RE0283-12 |
5 Apr 2012 |
1 May 2012 to 30 Nov 2012 |
Valid |
|
GW-RS0298-12 |
22 Mar 2012 |
26 Mar 2012 to 25 June 2012 |
Valid (Expired on 25 June 2012) |
|
GW-RS0301-12 |
20 Mar 2012 |
21 Mar 2012 to 20 Sept 2012 |
Valid |
|
GW-RS0303-12 |
26 Mar 2012 |
27 Mar 2012 to 27 Sept 2012 |
Valid |
|
GW-RS0341-12 |
3 Apr 2012 |
28 Apr 2012 to 27 Oct 2012 |
Valid |
|
GW-RS0348-12 |
3 Apr 2012 |
10 Apr 2012 to 9 Oct 2012 |
Valid |
|
GW-RS0380-12 |
12 Apr 2012 |
1 May 2012 to 31 Oct 2012 |
Valid |
|
GW-RS0388-12 |
13 Apr 2012 |
1 May 2012 to 31 Oct 2012 |
Valid |
|
GW-RS0418-12 |
30 Apr 2012 |
23 May 2012 to 22 Nov 2012 |
Valid |
|
GW-RS0420-12 |
30 Apr 2012 |
18 May 2012 to 17 Nov 2012 |
Valid |
|
GW-RS0423-12 |
30 Apr 2012 |
19 May 2012 to 18 Nov 2012 |
Valid |
|
GW-RS0427-12 |
30 Apr 2012 |
23 May 2012 to 22 Nov 2012 |
Valid |
|
GW-RS0445-12 |
30 Apr 2012 |
1 May 2012 to 25 Sept 2012 |
Valid |
|
GW-RS0467-12 |
10 May 2012 |
14 May 2012 to 10 Nov 2012 |
Valid |
|
GW-RS0533-12 |
21 May 2012 |
21 May 2012 to 10 Nov 2012 |
Valid |
|
GW-RS0550-12 |
25 May 2012 |
7 June 2012 to 6 Dec 2012 |
Valid |
|
GW-RS0611-12 |
14 June 2012 |
15 Jun 2012 to 28 Nov 2012 |
Valid |
|
GW-RS0633-12 |
13 June 2012 |
16 Jun 2012 to 14 Dec 2012 |
Valid |
Construction Noise Permit (CNP) for piling equipment |
PP-RS0007-12 |
27 Mar 2012 |
28 Mar 2012 to 27 Sept 2012 |
Valid |
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |