Contract No: HK/2011/07 Wanchai
Development Phase II and Sampling, Field Measurement and Testing Work (Stage 2) Environmental Permit
no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009,
FEP-03/364/2009, FEP-05/364/2009/A,
FEp-06/364/2009/a, FEP-07/364/2009/A and FEP-08/364/2009/A Monthly
Environmental Monitoring & Audit Report
- august 2012 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
11 September 2012 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status of Environmental Licensing and Permitting under the
Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring.
6.4 Review of the Reasons for and the Implications of
Non-compliance
6.5 Summary of action taken in the event of and follow-up on
non-compliance
7. Cumulative Construction Impact
due to the Concurrent Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects under this Project
Table
2.2 Details of Individual Contracts under the Project
Table
2.3 Contact Details of Key Personnel
Table
3.2 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/17
Table
3.3 Summary of submission status under FEP-03/364/2009
Table
3.4 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/01
Table
3.5 Summary of submission status under FEP-02/364/2009
Table
3.6 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/02
Table
3.7 Summary of submission status under FEP-01/364/2009
Table
3.8 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/18
Table
3.9 Summary of submission status under FEP-05/364/2009/A
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/15
Table 3.11 Summary of submission status under FEP-06/364/2009/A
Table 3.12 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Table 3.13 Summary of submission status under FEP-07/364/2009/A
Table 3.14 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2010/06
Table
4.1 Noise Monitoring Stations
Table
4.2 Real Time Noise Monitoring Stations
Table
4.3 Air Monitoring Stations
Table
5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Table
5.2 Noise Monitoring Stations for Contract no. HY/2009/18
Table
5.3 Noise Monitoring Station for Contract no HK/2009/01 and
HK/2009/02
Table
5.4 Noise Monitoring Stations for Contract no. HY/2009/15
Table
5.5 Noise Monitoring Stations for Contract no. HY/2009/19
Table
5.6 Real Time Noise Monitoring Stations for Contract no.
HY/2009/17
Table
5.7 Real Time Noise Monitoring Stations for Contract no.
HY/2009/19
Table
5.8 Air Monitoring Station for Contract no. HY/2009/17
Table
5.9 Air Monitoring Stations for Contract no. HY/2009/18
Table 5.10 Air Monitoring Station for Contract no. HK/2009/01
Table 5.11 Air Monitoring Station for Contract no. HK/2009/02
Table 5.12 Air Monitoring Station for Contract no. HY/2009/15
Table 5.13 Air Monitoring Stations for Contract no. HY/2009/19
Table 5.14 Details of Waste Disposal for Contract no. HY/2009/17
Table 5.15 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.16 Details of Waste Disposal for Contract no. HK/2009/02
Table
5.17 Details of Waste Disposal for Contract no. HY/2009/18
Table
5.18 Details of Waste Disposal for Contract no. HY/2009/15
Table
5.19 Details of Waste Disposal for Contract no. HY/2009/19
Table
5.20 Details of Waste Disposal for Contract no. HK/2010/06
Table
8.1 Summary of Environmental Inspections for Contract no.
HY/2009/15
Table
8.2 Summary of Environmental Inspections for Contract no. HY/2009/18
Table
8.3 Summary of Environmental Inspections for Contract no.
HY/2009/19
Table
8.4 Summary of Environmental Inspections for Contract no.
HK/2009/01
Table
8.5 Summary of Environmental Inspections for Contract no.
HK/2009/02
Table
8.6 Summary of Environmental Inspections for Contract no.
HK/2010/06
Table
9.1 Cumulative Statistics on Complaints
Table
9.2 Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix
5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring Results and Graphical Presentations
Appendix
5.3 Air Quality Monitoring Results and
Graphical Presentations
Appendix 5.4 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification
of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction
Programme of Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works under FEP-03/364/2009
¡P
ELS
works for basement construction for pile cap construction.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
¡P
Excavation
of trial pit
¡P
Transplanting
of trees
¡P
Hoarding
erection and modification
¡P
Installation
of couplers, UU detection, trial trench, pre-drilling
¡P
Site
investigation and pre-drill works
¡P
Excavation
¡P
Diaphragm
wall construction
¡P
Sheet
Piling
¡P
Drainage
works
¡P
Tunnel
works
¡P
Top
down slab construction
¡P
Trough
structure construction and associated drilling and grouting
¡P
Road
works
¡P
OHVD
installation
¡P
Site
access set up at Portion 6
¡P
TTA
near Gate 3
¡P
Pumping
test
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre - Tunnel Works under FEP-02/364/2009
¡P
Diaphragm
wall construction works for CWB (Stage2) at the northern side
¡P
Pre-drilling
works for CWB (Stage 2)
¡P
Construction
of exhaust duct structure (Bay 1 and Bay 2) including waterproofing and protective
screeding
¡P
Trimming
of SCL Diaphragm wall head
¡P
Construction
of SCL top slab (Bay 2 & Bay 3)
¡P
Remedial
works for SCL Diaphragm Wall
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Deep
excavation works reached -19mPD to -18mPD on the eastern and western portion of
the site respectively
¡P
Pre-drill
holes
¡P
Guide
wall construction for Eastern Bulkhead Diaphragm wall at tunnel portion 3 &
4 area
¡P
Silo
tank, desander and bar bending yard setup for diaphragm wall construction at
existing helipad
¡P
Diaphragm
wall construction of panel P110
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Diaphragm
wall construction works at TS4
¡P
Rock
breaking works at TPCWAE
¡P
Removal
of temporary reclamation at TS1
¡P
Dismantling
of scaffold in tunnel box at TS1
¡P
Preparation
works for bored piling at eastern breakwater
¡P
Mined
tunnel preparation works at TPCWAE
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road
works at Watson Road
¡P
Bored
piling (Land)
¡P
Ground
contamination assessment
¡P
Pre-drilling
works for bored pile and Diaphragm wall
¡P
D-wall
Construction (North & South Section)
¡P
Guide
wall construction for D-wall / Barette at North side
¡P
Construction
works for Box Culvert T
¡P
Marine
Piling
¡P
Construct
ion of socket-H pile
¡P
Construction
of pre-bored H-pile works for Culvert U
¡P
Construction
of 1500f drainage pipe
¡P
Construction
of Pile cap & column (Land)
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P
Construction
of Pre-cast Unit in China
Noise Monitoring
Air Monitoring
CMA1b: from 27 Jul and 20 August 2012 to 31 Jul and
21 August 2012
CMA2a: from 27 Jul and 8 August 2012 to 28 Jul and 10
August 2012
CMA5a: from 20 August 2012 to 21 August 2012
MA1w: from 27 Jul 2012 to 28 Jul 2012
CMA2a: 9 August 2012 to 11 August 2012
Complaints, Notifications of Summons and Successful
Prosecutions
Site Inspections and Audit
Contract no.
HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works under FEP-03/364/2009
¡P
ELS
works for basement construction for pile cap construction.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Excavation
of trial pit
¡P
Transplanting
of trees
¡P
Hoarding
erection and modification
¡P
Installation
of couplers, UU detection, trial trench, pre-drilling
¡P
Site
investigation and pre-drill works
¡P
Excavation
¡P
Diaphragm
wall construction
¡P
Sheet
Piling
¡P
Drainage
works
¡P
Tunnel
works
¡P
Top
down slab construction
¡P
Trough
structure construction and associated drilling and grouting
¡P
Road
works
¡P
OHVD
installation
¡P
Pipe-piling
works
¡P
Cooling
main bridge construction
¡P
Bridge
A construction
¡P
Pre-bored
H-pile
¡P
Pumping
test
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre ¡V Tunnel Works under FEP-02/364/2009
¡P
Preparation
works for pre-bored H-pile installation including excavation to +2mPD at
northern side between Ch120 and Ch190
¡P
Backfilling
for the extent of exhaust duct section for pipe laying works for cross harbour
watermains
¡P
Construction
of SCL top slab (Bay 1 and Bay 2)
¡P
Remedial
works for SCL Diaphragm Wall
¡P
Installation
of dewatering system and equipment at SCL
¡P
Backfilling
works of the Area 3 to the required level for subsequent handover of site area
Contract no. HK/2009/02 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Deep
excavation and strut installation works below -18mPD for western tunnel portion
and below -19mPD for eastern tunnel portion
¡P
Diaphragm
wall construction for Panel C107, P108, C109, C111, P112, C113, P114 and C115
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Diaphragm
wall construction works at TS4
¡P
ELS
preparation works at TS4
¡P
Rock
breaking works at TPCWAE
¡P
Tunnel
works at TS1
¡P
Bored
piling at eastern breakwater
¡P
Horizontal
drilling along west portal of mined tunnel
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road
works at Watson Road
¡P
Bored
piling (Land)
¡P
Ground
contamination assessment
¡P
Pre-drilling
works for bored pile and Diaphragm wall
¡P
D-wall
Construction (North & South Section)
¡P
Guide
wall construction for D-wall / Barette at North side
¡P
Construction
works for Box Culvert T
¡P
Marine
Piling
¡P
Construct
ion of socket-H pile
¡P
Construction
of pre-bored H-pile works for Culvert U
¡P
Construction
of 1500f drainage pipe
¡P
Construction
of Pile cap & column (Land)
¡P
Dismantling
of marine platform
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P
Construction
of Pre-cast Unit in China
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos.
FEP-01/364/2009,
FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A and FEP-08/364/2009/A to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section
10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit
Requirements¡¨ under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/A,
Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009,
FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A and
FEP-08/364/2009/A during the period July to Aug 2012. The cut-off date of reporting is at 27th of each reporting
month.
Section 1 Introduction ¡V details the
scope and structure of the report.
Section 2 Project
Background ¡V summarizes background and scope of the project, site
description, project organization and contact details of key personnel during
the reporting period.
Section 3 Status of Regulatory Compliance ¡V summarizes the
status of valid Environmental Permits / Licenses during the reporting period.
Section 4 Monitoring
Requirements ¡V summarizes all monitoring parameters, monitoring
methodology and equipment, monitoring locations, monitoring frequency, criteria
and respective event and action plan and monitoring programmes.
Section 5 Monitoring
Results ¡V summarizes the monitoring results obtained in the
reporting period.
Section 6 Compliance Audit ¡V summarizes the auditing of monitoring results, all exceedances
environmental parameters.
Section 7 Cumulative Construction Impact due to the Concurrent Projects ¡V summarizes the relevant cumulative construction impact due to the
concurrent activities of the concurrent Projects.
Section 8 Site Inspection ¡V summarizes the findings of weekly site
inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of summons and Prosecution ¡V summarizes the cumulative statistics on complaints, notification of summons and
prosecution
Section 10 Conclusion
2.1.1.
¡§Wan
Chai Development phase II and Central-Wan Chai Bypass¡¨ and ¡§Central-Wan Chai
Bypass and Island Eastern Corridor Link¡¨ (hereafter called ¡§the Project¡¨) are
Designated
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern
Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved
on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key
purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai
North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested east-west Connaught Road Central/Harcourt Road / Gloucester Road
Corridor (the Corridor) which is currently operating beyond its capacity. The
CWB will provide relief to the existing congestion along the Corridor and cater
for the anticipated growth of traffic on Hong Kong Island. Without the CWB and
its access roads, there will not be sufficient capacity to serve the heavy
traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central ¡V Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure
2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and
Island Eastern Corridor Link (IECL) includes:
¡P
A
dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
¡P
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
¡P
Tunnel
control buildings and ventilation buildings;
¡P
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
Causeway Bay area;
¡P
Associated
road lighting, road signing, traffic control and surveillance system; and
¡P
Other
associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to
be granted by the DEP before they may be
either constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2
DPs.
Table 2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to
the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
The
details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual
Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre ¡V Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1 |
13 July 2011 |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For
the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact
Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 8332 |
3529 2829 |
|
Lam Woo & CO.,
LTD. |
Contractor under Contract no. HY/2009/17 |
Project Manager |
Mr. K. S. Law |
9090 1378 |
2566 7522 |
Site Agent |
Mr. Tony Au |
9725 5874 |
2566 7522 |
||
Sub Agent |
Mr. Johnny Wong |
9725 5870 |
2566 7522 |
||
Chun Wo ¡V Leader
Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
Mr. PL Yue |
2162 9909 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Sub Agent |
Mr. Terry Wong |
9757 9846 |
|||
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 2467 |
|||
Construction
Manager |
Mr KK Yuen |
9498 1213 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Environmental
Supervisor |
Ms. Kiwi Chan |
6227 8840 |
|||
|
|
Environmental
Supervisor |
Mr. Yeung Sze King |
9047 9952 |
|
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Calvin Leung |
9286 9208 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
|
Deputy Site Agent |
Mr. Desmond Sze |
2214 7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Engineer Graduate |
Phil Mak |
2214 7738 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ray Cheng |
2214 7742 |
|||
Environmental Supervisor |
K. W. Lee |
6461 4623 |
|||
|
|
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|
|
|
Environmental Supervisor |
Bosco Lee |
2214 7711 |
|
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
Mr. P.J. Fan |
3557 6368 |
2566 2192 |
||
Contractor¡¦s
Representative |
Mr. David Lau |
3557 6358 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Environmental Supervisor |
Mr. Kelven Yip |
3557 6347 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee Wai Man |
9481 6024 |
|||
Environmental
Supervisor |
Mr. Clement
Pang |
9735 9200 |
|||
ENVIRON Hong Kong Limited |
Independent Environmental
Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no.
HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works under FEP-03/364/2009
¡P
ELS
works for basement construction for pile cap construction.
Contract
no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under
FEP-05/364/2009/A
¡P
Excavation
of trial pit
¡P
Transplanting
of trees
¡P
Hoarding
erection and modification
¡P
Installation
of couplers, UU detection, trial trench, pre-drilling
¡P
Site
investigation and pre-drill works
¡P
Excavation
¡P
Diaphragm
wall construction
¡P
Sheet
Piling
¡P
Drainage
works
¡P
Tunnel
works
¡P
Top
down slab construction
¡P
Trough
structure construction and associated drilling and grouting
¡P
Road
works
¡P
OHVD
installation
¡P
Site
access set up at Portion 6
¡P
TTA
near Gate 3
¡P
Pumping
test
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
¡P
Diaphragm
wall construction works for CWB (Stage2) at the northern side
¡P
Pre-drilling
works for CWB (Stage 2)
¡P
Construction
of exhaust duct structure (Bay 1 and Bay 2) including waterproofing and protective
screeding
¡P
Trimming
of SCL Diaphragm wall head
¡P
Construction
of SCL top slab (Bay 2 & Bay 3)
¡P
Remedial
works for SCL Diaphragm Wall
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P
Deep
excavation works reached -19mPD to -18mPD on the eastern and western portion of
the site respectively
¡P
Pre-drill
holes
¡P
Guide
wall construction for Eastern Bulkhead Diaphragm wall at tunnel portion 3 &
4 area
¡P
Silo
tank, desander and bar bending yard setup for diaphragm wall construction at
existing helipad
¡P
Diaphragm
wall construction of panel P110
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
¡P
Diaphragm
wall construction works at TS4
¡P
Rock
breaking works at TPCWAE
¡P
Removal
of temporary reclamation at TS1
¡P
Dismantling
of scaffold in tunnel box at TS1
¡P
Preparation
works for bored piling at eastern breakwater
¡P
Mined
tunnel preparation works at TPCWAE
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
¡P
Road
works at Watson Road
¡P
Bored
piling (Land)
¡P
Ground
contamination assessment
¡P
Pre-drilling
works for bored pile and Diaphragm wall
¡P
D-wall
Construction (North & South Section)
¡P
Guide
wall construction for D-wall / Barette at North side
¡P
Construction
works for Box Culvert T
¡P
Marine
Piling
¡P
Construct
ion of socket-H pile
¡P
Construction
of pre-bored H-pile works for Culvert U
¡P
Construction
of 1500f
drainage pipe
¡P
Construction
of Pile cap & column (Land)
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
¡P
Construction
of Pre-cast Unit in China
2.4.4.
In
coming reporting month, the principal work activities of individual contracts
are anticipated as follows:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD
Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009
¡P
ELS
works for basement construction for pile cap construction.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Excavation
of trial pit
¡P
Transplanting
of trees
¡P
Hoarding
erection and modification
¡P
Installation
of couplers, UU detection, trial trench, pre-drilling
¡P
Site
investigation and pre-drill works
¡P
Excavation
¡P
Diaphragm
wall construction
¡P
Sheet
Piling
¡P
Drainage
works
¡P
Tunnel
works
¡P
Top
down slab construction
¡P
Trough
structure construction and associated drilling and grouting
¡P
Road
works
¡P
OHVD
installation
¡P
Pipe-piling
works
¡P
Cooling
main bridge construction
¡P
Bridge
A construction
¡P
Pre-bored
H-pile
¡P
Pumping
test
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre ¡V Tunnel Works under FEP-02/364/2009
¡P
Preparation
works for pre-bored H-pile installation including excavation to +2mPD at
northern side between Ch120 and Ch190
¡P
Backfilling
for the extent of exhaust duct section for pipe laying works for cross harbour
watermains
¡P
Construction
of SCL top slab (Bay 1 and Bay 2)
¡P
Remedial
works for SCL Diaphragm Wall
¡P
Installation
of dewatering system and equipment at SCL
¡P
Backfilling
works of the Area 3 to the required level for subsequent handover of site area
Contract no. HK/2009/02 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Deep
excavation and strut installation works below -18mPD for western tunnel portion
and below -19mPD for eastern tunnel portion
¡P
Diaphragm
wall construction for Panel C107, P108, C109, C111, P112, C113, P114 and C115
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Diaphragm
wall construction works at TS4
¡P
ELS
preparation works at TS4
¡P
Rock
breaking works at TPCWAE
¡P
Tunnel
works at TS1
¡P
Bored
piling at eastern breakwater
¡P
Horizontal
drilling along west portal of mined tunnel
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road
works at Watson Road
¡P
Bored
piling (Land)
¡P
Ground
contamination assessment
¡P
Pre-drilling
works for bored pile and Diaphragm wall
¡P
D-wall
Construction (North & South Section)
¡P
Guide
wall construction for D-wall / Barette at North side
¡P
Construction
works for Box Culvert T
¡P
Marine
Piling
¡P
Construct
ion of socket-H pile
¡P
Construction
of pre-bored H-pile works for Culvert U
¡P
Construction
of 1500f drainage pipe
¡P
Construction
of Pile cap & column (Land)
¡P
Dismantling
of marine platform
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P
Construction
of Pre-cast Unit in China
3.1.1.
A
summary of the current status on licences and/or permits on environmental
protection pertinent to the Project is shown in Table 3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental
Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Valid |
3.1.2.
Due to
the multi-contract nature of the Project, the status of permits and/or licences
under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass
(CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009
3.1.3.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission
under FEP-03/364/2009 for
contract no. HY/2009/17 showed in Table 3.2 and Table 3.3.
Table 3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 ¡V 31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 July 2010 |
N/A |
Valid |
Billing Account
under Waste Disposal Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Table 3.3 Summary
of submission status under FEP-03/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management
Organization of Main Construction Companies |
18 September 2010 |
Conditions 2.7 and
2.8 |
Submission of works
schedule and location plan |
1 September 2010 |
Condition 2.9 |
Noise Management
Plan |
1 September 2010 |
Contract no. 04/HY/2006 ¡V Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4.
The construction works was
completed, and the FEP was surrendered by the Contractor on 11 February 2011.
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre ¡V Tunnel Works under FEP-02/364/2009
3.1.5.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission
under FEP-02/364/2009 for
contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of
Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling
equipment |
GW-RS0158-12 |
24 Feb 2012 |
24 Feb 2012 to 23 Aug 2012 |
Valid (Expired on 23 Aug
2012) |
|
GW-RS0181-12 |
24 Feb 2012 |
27 Feb 2012 to 23 Aug 2012 |
Valid (Expired on 23 Aug
2012) |
|
GW-RS0213-12 |
28 Feb 2012 |
29 Feb 2012 to 27 Aug 2012 |
Valid (Expired on 27 Aug
2012) |
|
GW-RS0225-12 |
02 Mar 2012 |
14 Mar 2011 to
13 Sep 2012 |
Valid |
|
GW-RS0227-12 |
02 Mar 2012 |
16 Mar 2011 to 15 Sep 2012 |
Valid |
|
GW-RE0174-12 |
05 Mar 2012 |
30 Mar 2012 to 29 Sep 2012 |
Valid |
|
GW-RS0312-12 |
28 Mar 2012 |
30 Mar 2012 to 29 Sep 2012 |
Valid |
|
GW-RS0314-12 |
29 Mar 2012 |
30 Mar 2012 to 25
Sep 2012 |
Cancelled |
|
GW-RS0356-12 |
03 Apr 2012 |
11 Apr 2012 to 29 Sep 2012 |
Valid |
|
GW-RS0394-12 |
16 Apr 2012 |
19 Apr 2012 to 12 Oct 2012 |
Valid |
|
GW-RS0459-12 |
3 May 2012 |
7 May 2012 to 6 Nov 2012 |
Cancelled |
|
GW-RS0460-12 |
10 May 2012 |
13 May 2012 to 6
Nov 2012 |
Valid |
|
GW-RS0514-12 |
14 May 2012 |
27 May 2012 to 26
Nov 2012 |
Valid |
|
GW-RS0545-12 |
24 May 2012 |
26 May 2012 to 25
Nov 2012 |
Valid |
|
GW-RS0546-12 |
25 May 2012 |
26 May 2012 to 25
Nov 2012 |
Valid |
|
GW-RS0731-12 |
5 Jul 2012 |
05 Jul 2012 to 01 Jan 2013 |
Cancelled |
|
GW-RS0760-12 |
18 Jul 2012 |
20 Jul 2012 to 19 Jan 2013 |
Valid |
|
GW-RS0771-12 |
23 Jul 2012 |
23 Jul 2012 to 31 Aug 2012 |
Valid |
|
GW-RS0806-12 |
3 Aug 2012 |
4 Aug 2012 to 3 Feb
2012 |
Valid |
|
GW-RS0823-12 |
3 Aug 2012 |
3 Aug 2012 to 2 Feb 2012 |
Valid |
|
GW-RS0852-12 |
16 Aug 2012 |
16 Aug 2012 to 1 Feb
2012 |
Valid |
|
GW-RS0855-12 |
16 Aug 2012 |
17 Aug 2012 to 9 Feb 2012 |
Valid |
|
GW-RS0862-12 |
20 Aug 2012 |
28 Aug 2012 to 27 Feb
2012 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00009641-2011 |
24 Jul
2011 |
31 Jul
2016 |
Valid |
Billing account
under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.5 Summary
of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
25 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
10 Jun 2011 |
Contract no. HK/2009/02 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
3.1.6.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission
under FEP-01/364/2009 for
contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of
Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS0037-12 |
19 Jan 2012 |
1 Feb 2012 to 31 July 2012 |
Valid (Expired on 31 July 2012) |
|
GW-RS0051-12 |
19 Jan 2012 |
1 Feb 2012 to 31 July 2012 |
Valid (Expired on 31 July 2012) |
|
GW-RS0086-12 |
30 Jan 2012 |
3 Feb 2012 to 2 Aug 2012 |
Cancelled |
|
GW-RS0105-12 |
3 Feb 2012 |
10 Feb 2012 to 9 Aug 2012 |
Cancelled |
|
GW-RS0153-12 |
17 Feb 2012 |
21 Feb 2012 to 20 Aug 2012 |
Cancelled |
|
GW-RS0233-12 |
6 Mar 2012 |
9 Mar 2012 to 8 Sept 2012 |
Cancelled |
|
GW-RS0255-12 |
14 Mar 2012 |
17 Mar 2012 to 15 Sept 2012 |
Valid |
|
GW-RE0283-12 |
5 Apr 2012 |
1 May 2012 to 30 Nov 2012 |
Valid |
|
GW-RS0301-12 |
20 Mar 2012 |
21 Mar 2012 to 20 Sept 2012 |
Cancelled |
|
GW-RS0303-12 |
26 Mar 2012 |
27 Mar 2012 to 27 Sept 2012 |
Valid |
|
GW-RS0341-12 |
3 Apr 2012 |
28 Apr 2012 to 27 Oct 2012 |
Valid |
|
GW-RS0348-12 |
3 Apr 2012 |
10 Apr 2012 to 9 Oct 2012 |
Valid |
|
GW-RS0380-12 |
12 Apr 2012 |
1 May 2012 to 31 Oct 2012 |
Valid |
|
GW-RS0388-12 |
13 Apr 2012 |
1 May 2012 to 31 Oct 2012 |
Valid |
|
GW-RS0418-12 |
30 Apr 2012 |
23 May 2012 to 22 Nov 2012 |
Valid |
|
GW-RS0420-12 |
30 Apr 2012 |
18 May 2012 to 17 Nov 2012 |
Cancelled |