Contract No: HK/2011/07 Wanchai
Development Phase II and Sampling,
Field Measurement and Testing Work (Stage 2) Environmental Permit no. EP-364/2009/B, Further
Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A,
FEp-06/364/2009/a, FEP-07/364/2009/A and FEP-08/364/2009/A Monthly
Environmental Monitoring & Audit Report
- December 2012 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
11 January 2013 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. status of regulatory
compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring
6.4 Review of the Reasons for and the Implications of
Non-compliance
6.5 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction
Impact due to the Concurrent Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects under this
Project
Table 2.2 Details of Individual Contracts under the
Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/17
Table 3.4 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/01
Table 3.5 Summary of submission status under
FEP-02/364/2009
Table 3.6 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/02
Table 3.7 Summary of submission status under FEP-01/364/2009
Table 3.8 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/18
Table 3.9 Summary of submission status under
FEP-05/364/2009/A
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Table 3.11 Summary of submission status under
FEP-06/364/2009/A
Table 3.14 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2010/06
Table 3.15 Summary of submission status under
FEP-08/364/2009
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring Stations
Table 4.3 Air Monitoring Stations
Table 5.1 Noise Monitoring Stations for Contract no.
HY/2009/17
Table 5.2 Noise Monitoring Stations for Contract no.
HY/2009/18
Table 5.3 Noise Monitoring Station for Contract no
HK/2009/01 and HK/2009/02
Table 5.4 Noise Monitoring Stations for Contract no.
HY/2009/15
Table 5.5 Noise Monitoring Stations for Contract no.
HY/2009/19
Table 5.6 Real Time Noise Monitoring Stations for
Contract no. HY/2009/17
Table 5.7 Real Time Noise Monitoring Stations for
Contract no. HY/2009/19
Table 5.8 Air Monitoring Station for Contract no.
HY/2009/17
Table 5.9 Air Monitoring Stations for Contract no.
HY/2009/18
Table 5.10 Air Monitoring Station for Contract no.
HK/2009/01
Table 5.11 Air Monitoring Station for Contract no.
HK/2009/02
Table 5.12 Air Monitoring Station for Contract no.
HY/2009/15
Table 5.13 Air Monitoring Stations for Contract no.
HY/2009/19
Table 5.15 Details of Waste Disposal for Contract no.
HK/2009/01
Table 5.16 Details of Waste Disposal for Contract no.
HK/2009/02
Table 5.17 Details of Waste Disposal for Contract no.
HY/2009/18
Table 5.18 Details of Waste Disposal for Contract no.
HY/2009/15
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/19
Table 5.20 Details of Waste Disposal for Contract no.
HK/2010/06
Table 8.1 Summary of Environmental Inspections for
Contract no. HY/2009/15
Table 8.2 Summary of Environmental Inspections for
Contract no. HY/2009/19
Table 8.3 Summary of Environmental Inspections for
Contract no. HK/2009/01
Table 8.4 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2010/06
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful
Prosecutions
lIST OF FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project
Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST
OF APPENDIces
Appendix 3.1 Environmental
Mitigation Implementation Schedule
Appendix 4.1 Action
and Limit Level
Appendix
4.2 Copies
of Calibration Certificates
Appendix
5.1 Monitoring
Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring Results and
Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and
Graphical Presentations
Appendix
5.4 Real-time
Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event
Action Plans
Appendix 6.2 Notification
of Exceedance
Appendix
9.1 Complaint
Log
Appendix 10.1 Construction
Programme of Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works under FEP-03/364/2009
·
No
further work under designated project1
1Remarks: The construction of bored pile E3B under
FEP-03/364/2009 was confirmed completed and the bored pile E3B and the works
area was handover to contract
no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
·
Excavation
of trial pit
·
Transplanting
of trees
·
Hoarding
erection and modification
·
Installation
of couplers, UU detection, trial trench, pre-drilling
·
Excavation
·
Sheet
Piling
·
Drainage
works
·
Tunnel
works
·
Trough
structure construction and associated drilling and grouting
·
Road
works
·
OHVD
installation
·
Pipe-piling
works
·
Pre-bored
H-piling
·
Bridge
construction
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
·
Backfilling
works on top of SCL protection works.
·
Jet
grouting to HKCEC new extension foundation.
·
Plant
mobilization for installation of pre-bored H-pile works at Stage 1b & Stage
2
·
Pre-drilling
works for CWB (Stage 2).
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Trimming
of pile head and blinding laying construction at WCR1 of Tunnel Portion 1
·
Waterproofing
installation at WCR1 of Tunnel Portion 1 Bay 2 - Bay 7 together with Bay 8 – Bay
16
·
Preparation
works for extract the western temporary sheetpile wall
·
Diaphragm
wall of panel P106, C107, P108, C109, P110, C111, P112, P114, C115 & P116.
Panel P113.
·
Preparation
works of saw cut Southern Diaphragm wall for the connection between existing
drainage and Bay 1 of Box Culvert N1.
·
Trial
excavation, Footpath Set back, UU Diversion and preparation works for Hung Hing
Road Diversion Stage.
·
Installation
of precast concrete short pipe extended from the existing 1800 drainage at Box
Culvert N landside.
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
·
Excavation
and Lateral Support works at TS4
·
Rock
breaking works at TPCWAE
·
Tunnel
works at TS1
·
Bored
piling at eastern breakwater
·
Horizontal
drilling for mined tunnel
·
Pipe
roofing installation
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Road
works at
·
Bored
piling (Land)
·
Pre-drilling
works for bored pile and Diaphragm wall
·
D-wall
Construction (North & South Section)
·
Guide
wall construction for D-wall / Barrette at North side
·
Construction
works for Box Culvert T1
·
Marine
Piling
·
Construct
ion of socket-H pile
·
Construction
works for Culvert U1
·
Construction
of 1500f drainage pipe
·
Construction
of Pile cap & column (Land)
·
Dismantling
of marine platform
·
Cut
& Cover Tunnel sheet piling works
·
Construction
of dewatering well for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
·
Construction
of Pre-cast Unit in
Noise Monitoring
Air Monitoring
CMA2a: from 13 December 2012 to 14 December 2012
CMA3a: from 22 December 2012 to 24 December 2012
Complaints, Notifications of Summons and Successful
Prosecutions
Site Inspections and Audit
Contract no.
HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works under FEP-03/364/2009
·
No
further work under designated project1
1Remarks: The construction of bored pile E3B under
FEP-03/364/2009 was confirmed completed and the bored pile E3B and the works
area was handover to contract
no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 – Central – Wan
Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Excavation
of trial pit
·
Transplanting
of trees
·
Hoarding
erection and modification
·
Installation
of couplers, UU detection, trial trench, pre-drilling
·
Excavation
·
Sheet
Piling
·
Drainage
works
·
Tunnel
works
·
Trough
structure construction and associated drilling and grouting
·
Road
works
·
OHVD
installation
·
Pipe-piling
works
·
Cooling
main bridge construction
·
Pre-bored
H-piling
·
Bridge
construction
·
Cooling
main bridge construction
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at
·
Removal
of remaining guide wall along
·
Installation
of pre-bored H-pile in CWB stage 2 (from Ch120 to Ch220)
·
Backfilling
works at SCL section
·
Plant
mobilization for CWB diaphragm wall construction work
·
Pre-treatment
works and guide wall construction for CWB Diaphragm Wall
Contract no. HK/2009/02 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
·
Trimming
of bored pile head and blinding for the base slab construction at tunnel
portion 1.
·
Waterproofing
installation for the base slab at tunnel portion 1.
·
Rebar
fixing and base slab concreting at Tunnel Portion 1.
·
G.I.
and remove the temporary sheetpile wall at WCR2
·
Diaphragm
wall construction for Eastern Bulkhead Panel BHP3 and BHP7.
·
Bulkhead
at Bay 14 of Box Culvert “O” and stage 2 diversion of uncharted drainage works
at Box culvert “O”.
·
Trial
excavation, footpath set back, UU diversion, tree transplantation, reprovision
of street furniture and preparation works for Hung Hing Road Diversion Stage 1.
·
Caisson
seawall precast unit 2X in-situ work on flat-top barge.
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
·
ELS
works at TS4
·
Rock
breaking works at TPCWAE
·
Tunnel
works at TS1
·
Horizontal
drilling for mined tunnel
·
Pipe
roofing installation
·
Construction
of Diaphragm Wall at TS2
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Road
works at
·
Bored
piling (Land)
·
Pre-drilling
works for bored pile and Diaphragm wall
·
D-wall
Construction (North & South Section)
·
Guide
wall construction for D-wall / Barrette at North side
·
Construction
works for Box Culvert T1
·
Marine
Piling
·
Construct
ion of socket-H pile
·
Construction
works for Culvert U1
·
Construction
of 1500f drainage pipe
·
Construction
of Pile caps & columns (Land)
·
Dismantling
of marine platform
·
Demolition
of parapet at IEC Link
·
Construction
of Pile caps & columns (Marine)
·
Cut
& Cover Tunnel sheet piling works
·
Construction
of dewatering well for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
·
Construction
of Pre-cast Unit in
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009/B and Further Environmental permit
nos. FEP-01/364/2009,
FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A and FEP-08/364/2009/A
to implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the
Section 10.3 of EM&A Manual and “Environmental Monitoring and Audit
Requirements” under Particular Specification
Section 27.
1.1.3.
This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/B,
Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009,
FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A and
FEP-08/364/2009/A during the period Sep to Oct 2012. The cut-off date of reporting is at 27th of
each reporting month
Section
1 Introduction –
details the scope and structure of the report.
Section
2 Project
Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance –
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements – summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results – summarizes the monitoring results
obtained in the reporting period.
Section
6 Compliance
Audit – summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects – summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Site Inspection –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review
of any relevant
follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
– summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designated
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane
trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in
length defined from the connection with the existing Rumsey Street Flyover in
Central, through to a connection with the existing Island Eastern Corridor to
the east of the Causeway Bay Typhoon Shelter (CBTS);
·
The Central
Interchange near the Rumsey Street Flyover to provide road connections to the
Central area;
·
Tunnel control
buildings and ventilation buildings;
·
Slip roads to
connect the CWB to the local road system in the Wan Chai North and
·
Associated road
lighting, road signing, traffic control and surveillance system; and
·
Other associated
works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs)
to be granted by the DEP before they may be either constructed or operated. Table
2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these
Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
The
details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual
Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel ( |
DP1 |
13 July 2011 |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key personnel and contact particulars
are summarized in Table 2.3:
Table 2.3 Contact
Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912 3010 |
|
Lam Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
General Manager |
Mr. Thomas Tang |
6111 5351 |
2566 7522 |
Contractor’s Representative |
Mr. Chung Man Shek |
2566 4866 |
|||
Site Agent |
Mr. Tong Au |
9725 5874 |
|||
Environmental Officer |
Dr. Priscilla Choy |
9161 7287 |
|||
Environmental Supervisor |
Mr. Tam Chun Pong |
6461 3062 |
|||
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
|
2162 9909 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Construction Manager |
Mr. Terry Wong |
9757 9846 |
|||
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction Manager |
Mr. Jack Chu |
9775 2467 |
|||
Environmental Officer
(Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Calvin Leung |
9286 9208 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
|
Deputy Site Agent |
Mr. Roger Wong |
2214 7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Engineer Graduate |
Phil Mak |
2214 7738 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ray Cheng |
2214 7742 |
|||
Environmental Supervisor |
K. W. Lee |
6461 4623 |
|||
|
|
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|
|
|
Environmental Supervisor |
Bosco Lee |
2214 7711 |
|
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
Mr. P.J. Fan |
3557 6368 |
2566 2192 |
||
Contractor’s
Representative |
Mr. David Lau |
3557 6358 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Enviromental Supervisor |
Ms Esther Choi |
35576348 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee Wai Man |
9481 6024 |
|||
Environmental
Supervisor |
Mr. Clement
Pang |
9735 9200 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. HY/2009/17 – Central
– Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under
FEP-03/364/2009
·
No
further work under designated project1
1Remarks:
The construction of bored pile E3B under FEP-03/364/2009 was confirmed
completed and the bored pile E3B and the works area was handover to contract no. HY/2009/19 on 30
November 2012.
Contract
no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
·
Excavation
of trial pit
·
Transplanting
of trees
·
Hoarding
erection and modification
·
Installation
of couplers, UU detection, trial trench, pre-drilling
·
Excavation
·
Sheet
Piling
·
Drainage
works
·
Tunnel
works
·
Trough
structure construction and associated drilling and grouting
·
Road
works
·
OHVD
installation
·
Pipe-piling
works
·
Pre-bored
H-piling
·
Bridge
construction
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at
·
Backfilling
works on top of SCL protection works.
·
Jet
grouting to HKCEC new extension foundation.
·
Plant
mobilization for installation of pre-bored H-pile works at Stage 1b & Stage
2
·
Pre-drilling
works for CWB (Stage 2).
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
·
Trimming
of pile head and blinding laying construction at WCR1 of Tunnel Portion 1
·
Waterproofing
installation at WCR1 of Tunnel Portion 1 Bay 2 - Bay 7 together with Bay 8 – Bay
16
·
Preparation
works for extract the western temporary sheetpile wall
·
Diaphragm
wall of panel P106, C107, P108, C109, P110, C111, P112, P114, C115 & P116.
Panel P113.
·
Preparation
works of saw cut Southern Diaphragm wall for the connection between existing
drainage and Bay 1 of Box Culvert N1.
·
Trial
excavation, Footpath Set back, UU Diversion and preparation works for Hung Hing
Road Diversion Stage.
·
Installation
of precast concrete short pipe extended from the existing 1800 drainage at Box
Culvert N landside.
Contract no. HY/2009/15 – Central-Wanchai
Bypass – Tunnel (
·
Excavation
and Lateral Support works at TS4
·
Rock
breaking works at TPCWAE
·
Tunnel
works at TS1
·
Bored
piling at eastern breakwater
·
Horizontal
drilling for mined tunnel
·
Pipe
roofing installation
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
·
Road
works at
·
Bored
piling (Land)
·
Pre-drilling
works for bored pile and Diaphragm wall
·
D-wall
Construction (North & South Section)
·
Guide
wall construction for D-wall / Barrette at North side
·
Construction
works for Box Culvert T1
·
Marine
Piling
·
Construct
ion of socket-H pile
·
Construction
works for Culvert U1
·
Construction
of 1500f
drainage pipe
·
Construction
of Pile cap & column (Land)
·
Dismantling
of marine platform
·
Cut
& Cover Tunnel sheet piling works
·
Construction
of dewatering well for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
·
Construction
of Pre-cast Unit in
2.4.4.
In coming
reporting month, the principal work activities of
individual contracts are anticipated as follows:
Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD
Whitfield Depot – Advanced piling works under FEP-03/364/2009
·
No
further work under designated project1
1Remarks: The construction of bored pile E3B under
FEP-03/364/2009 was confirmed completed and the bored pile E3B and the works
area was handover to contract
no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 – Central – Wan
Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Excavation
of trial pit
·
Transplanting
of trees
·
Hoarding
erection and modification
·
Installation
of couplers, UU detection, trial trench, pre-drilling
·
Excavation
·
Sheet
Piling
·
Drainage
works
·
Tunnel
works
·
Trough
structure construction and associated drilling and grouting
·
Road
works
·
OHVD
installation
·
Pipe-piling
works
·
Cooling
main bridge construction
·
Pre-bored
H-piling
·
Bridge
construction
·
Cooling
main bridge construction
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at
·
Removal
of remaining guide wall along
·
Installation
of pre-bored H-pile in CWB stage 2 (from Ch120 to Ch220)
·
Backfilling
works at SCL section
·
Plant
mobilization for CWB diaphragm wall construction work
·
Pre-treatment
works and guide wall construction for CWB Diaphragm Wall
Contract no. HK/2009/02 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
·
Trimming
of bored pile head and blinding for the base slab construction at tunnel
portion 1.
·
Waterproofing
installation for the base slab at tunnel portion 1.
·
Rebar
fixing and base slab concreting at Tunnel Portion 1.
·
G.I.
and remove the temporary sheetpile wall at WCR2
·
Diaphragm
wall construction for Eastern Bulkhead Panel BHP3 and BHP7.
·
Bulkhead
at Bay 14 of Box Culvert “O” and stage 2 diversion of uncharted drainage works
at Box culvert “O”.
·
Trial
excavation, footpath set back, UU diversion, tree transplantation, reprovision
of street furniture and preparation works for Hung Hing Road Diversion Stage 1.
·
Caisson
seawall precast unit 2X in-situ work on flat-top barge.
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
·
ELS
works at TS4
·
Rock
breaking works at TPCWAE
·
Tunnel
works at TS1
·
Horizontal
drilling for mined tunnel
·
Pipe
roofing installation
·
Construction
of Diaphragm Wall at TS2
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Road
works at
·
Bored
piling (Land)
·
Pre-drilling
works for bored pile and Diaphragm wall
·
D-wall
Construction (North & South Section)
·
Guide
wall construction for D-wall / Barrette at North side
·
Construction
works for Box Culvert T1
·
Marine
Piling
·
Construct
ion of socket-H pile
·
Construction
works for Culvert U1
·
Construction
of 1500f drainage pipe
·
Construction
of Pile caps & columns (Land)
·
Dismantling
of marine platform
·
Demolition
of parapet at IEC Link
·
Construction
of Pile caps & columns (Marine)
·
Cut
& Cover Tunnel sheet piling works
·
Construction
of dewatering well for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
·
Construction
of Pre-cast Unit in
3.1.1.
A
summary of the current status on licences and/or permits on environmental
protection pertinent to the Project is shown in Table 3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-364/2009/A |
4 Aug
2010 |
Superseded |
Environmental
Permit |
EP-364/2009/B |
20 Sep
2012 |
Valid |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Valid |
Further
Environmental Permit |
24 Mar
2010 |
Valid |
|
Further
Environmental Permit |
21 Apr 2010 |
Valid |
|
Further
Environmental Permit |
12 July 2010 |
Valid |
|
Further
Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further
Environmental Permit |
15 Nov 2010 |
Valid |
|
Further
Environmental Permit |
22 Nov 2010 |
Valid |
|
Further
Environmental Permit |
25 Feb 2011 |
Valid |
|
Further
Environmental Permit |
15 June 2012 |
Valid |
3.1.2.
Due
to the multi-contract nature of the Project, the status of permits and/or
licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 – Central – Wan Chai Bypass
(CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009
3.1.3.
Summary of the current status on licences and/or
permits on environmental protection pertinent and
submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table 3.2 and Table 3.3.
Table 3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 – 31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 July 2010 |
N/A |
Valid |
Billing Account
under Waste Disposal Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4.
The construction works was completed,
and the FEP was surrendered by the Contractor on 11 February 2011.
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at
3.1.5.
Summary of the current status on licences and/or
permits on environmental protection pertinent and
submission under FEP-02/364/2009 for contract no.
HK/2009/01
are shown in Table 3.4 and Table 3.5
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-pilling equipment |
GW-RS-1293-12 |
10 Dec 2012 |
10 Dec 2012 to 9 June 2013 |
Valid |
GW-RS0760-12 |
16 Jul 2012 |
20 Jul 2012 to 19 Jan 2013 |
Valid |
|
GW-RS0806-12 |
3 Aug 2012 |
4 Aug 2012 to 03 Feb 2013 |
Cancelled |
|
GW-RS0823-12 |
3 Aug 2012 |
3 Aug 2012 to 02 Feb 2013 |
Cancelled |
|
GW-RS0852-12 |
16 Aug 2012 |
16 Aug 2012 to 01 Feb 2013 |
Cancelled |
|
GW-RS0855-12 |
16 Aug 2012 |
17 Aug 2012 to 9 Feb 2013 |
Cancelled |
|
GW-RS0862-12 |
20 Aug 2012 |
28 Aug 2012 to 27 Feb 2013 |
Cancelled |
|
GW-RS0949-12 |
12 Sep 2012 |
16 Sep 2012 to 15 Mar 2013 |
Cancelled |
|
GW-RS0994-12 |
25 Sep 2012 |
25 Sep 2012 to 19 Nov 2012 |
Expired |
|
GW-RS1011-12 |
26 Sep 2012 |
30 Sep 2012 to 29 Mar 2013 |
Cancelled |
|
GW-RS1017-12 |
27 Sep 2012 |
30 Sep 2012 to 24 Mar 2013 |
Valid |
|
GW-RS0793-12 |
21 Sep 2012 |
30 Sep 2012 to 29 Mar 2013 |
Valid |
|
GW-RS1040-12 |
8 Oct 2012 |
13 Oct 2012 to 12
Apr 2013 |
Valid |
|
GW-RS1177-12 |
15 Nov 2012 |
17 Nov 2012 to10
May 2013 |
Valid |
|
GW-RS1184 -12 |
15 Nov 2012 |
17 Nov 2012 to 8
May 2013 |
Valid |
|
GW-RS1185-12 |
19 Nov 2012 |
21 Nov 2012 to 8
May 2013 |
Valid |
|
GW-RS1179-12 |
20 Nov 2012 |
22 Nov 2012 to 21
May 2013 |
Valid |
|
GW-RS1187-12 |
20 Nov 2012 |
27 Nov 2012 to 26
May 2013 |
Valid |
|
GW-RS1199-12 |
20 Nov 2012 |
26 Nov 2012 to 25
May 2013 |
Valid |
|
Discharge Licence |
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
WT00006220-2010 |
18 Mar 2010 |
31
Mar 2015 |
Valid |
|
Billing
account under Waste Disposal Ordinance |
7010069 |
21
Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.5 Summary
of submission
status under FEP-02/364/2009
EP Condition |
Submission |
Date of
Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May
2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
20 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
10 Jun 2011 |
Contract no. HK/2009/02 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
3.1.6.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission
under FEP-01/364/2009 for
contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of
Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS1038-12 |
10 Oct 2012 |
10 Oct 2012 to 9 Apr 2013 |
Valid |
GW-RS1069-12 |
17 Oct 2012 |
19 Oct 2012 to 18 Apr 2013 |
Valid |
|
GW-RS1076-12 |
25 Oct 2012 |
1 Nov 2012 to 30 Apr 2013 |
Valid |
|
GW-RS1204-12 |
9 Nov 2012 |
29 Nov 2012 to 23 May 2013 |
Valid |
|
GW-RS1272-12 |
5 Dec 2012 |
5 Dec 2012 to 26 May 2013 |
Valid |
|
GW-RS1223-12 |
27 Nov 2012 |
7 Dec 2012 to 5 June 2013 |
Valid |
|
GW-RS1243-12 |
3 Dec 2012 |
5 Dec 2012 to 29 May 2013 |
Valid |
|
GW-RE1055-12 |
30 Nov 2012 |
3 Dec 2012 to 29 May 2013 |
Valid |
|
GW-RS1228-12 |
30 Nov 2012 |
30 Nov 2012 to 29 May 2013 |
Valid |
|
GW-RS1245-12 |
5 Dec 2012 |
6 Dec 2012 to 5 May 2013 |
Valid |
|
GW-RS0550-12 |
25 May 2012 |
7 June 2012 to 6 Dec 2012 |
Expired |
|
GW-RS0611-12 |
14 Jun 2012 |
15 Jun 2012 to 28 Nov 2012 |
Expired |
|
GW-RS0633-12 |
13 Jun 2012 |
16 Jun 2012 to 14 Dec 2012 |
Expired |
|
GW-RS0671-12 |
25 Jun 2012 |
17 Jul 2012 to 16 Jan 2013 |
Valid |
|
GW-RS0730-12 |
9 July 2012 |
10 Jul 2012 to 8 Jan 2013 |
Valid |
|
GW-RS0736-12 |
9 July 2012 |
9 Jul 2012 to 8 Jan
2013 |
Valid |
|
GW-RS0739-12 |
9 July 2012 |
1 Aug 2012 to 31 Jan 2013 |
Valid |
|
GW-RS0814-12 |
3 Aug 2012 |
6 Aug 2012 to 5 Dec 2012 |
Expired |
|
GW-RS0850-12 |
10 Aug 2012 |
14 Aug 2012 to 13 Feb 2013 |
Valid |
|
GW-RS0870-12 |
21 Aug 2012 |
16 Sept 2012 to 31 Dec 2012 |
Valid |
|
GW-RS0996-12 |
25 Sept 2012 |
26 Sept 2012 to 25 Mar 2013 |
Valid |
|
GW-RS1084-12 |
25 Oct 2012 |
1 Nov 2012 to 30 Apr 2013 |
Valid |
|
GW-RS1086-12 |
25 Oct 2012 |
28 Oct 2012 to 16 Apr 2013 |
Valid |
|
GW-RS1174-12 |
9 Nov 2012 |
11 Nov 2012 to 10 May 2013 |
Valid |
|
GW-RS1158-12 |
16 Nov 2012 |
18 Nov 2012 to 16 May 2013 |
Valid |
|
GW-RS1167-12 |
16 Nov 2012 |
23 Nov 2012 to 21 May 2013 |
Valid |
|
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|