Contract No: HK/2011/07 Wanchai
Development Phase II and Sampling, Field Measurement and Testing Work (Stage 2) Environmental Permit
no. EP-364/2009/B, Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009,
FEP-03/364/2009, FEP-05/364/2009/A,
FEp-06/364/2009/a, FEP-07/364/2009/A and FEP-08/364/2009/A Monthly
Environmental Monitoring & Audit Report
- January 2013 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
February 2013 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. status of regulatory
compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring
6.4 Review of the Reasons for and the Implications of
Non-compliance
6.5 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction
Impact due to the Concurrent Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects under this
Project
Table 2.2 Details of Individual Contracts under the
Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/17
Table 3.4 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/01
Table 3.5 Summary of submission status under
FEP-02/364/2009
Table 3.6 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/02
Table 3.7 Summary of submission status under FEP-01/364/2009
Table 3.8 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/18
Table 3.9 Summary of submission status under
FEP-05/364/2009/A
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Table 3.11 Summary of submission status under
FEP-06/364/2009/A
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.13
Summary of submission status under FEP-07/364/2009/A
Table 3.14 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2010/06
Table 3.15 Summary of submission status under
FEP-08/364/2009
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring Stations
Table 4.3 Air Monitoring Stations
Table 5.1 Noise Monitoring Stations for Contract no.
HY/2009/17
Table 5.2 Noise Monitoring Stations for Contract no.
HY/2009/18
Table 5.3 Noise Monitoring Station for Contract no
HK/2009/01 and HK/2009/02
Table 5.4 Noise Monitoring Stations for Contract no.
HY/2009/15
Table 5.5 Noise Monitoring Stations for Contract no.
HY/2009/19
Table 5.6 Real Time Noise Monitoring Stations for
Contract no. HY/2009/17
Table 5.7 Real Time Noise Monitoring Stations for
Contract no. HY/2009/19
Table 5.8 Air Monitoring Station for Contract no.
HY/2009/17
Table 5.9 Air Monitoring Stations for Contract no.
HY/2009/18
Table 5.10 Air Monitoring Station for Contract no.
HK/2009/01
Table 5.11 Air Monitoring Station for Contract no.
HK/2009/02
Table 5.12 Air Monitoring Station for Contract no.
HY/2009/15
Table 5.13 Air Monitoring Stations for Contract no.
HY/2009/19
Table 5.15 Details of Waste Disposal for Contract no.
HK/2009/01
Table 5.16 Details of Waste Disposal for Contract no.
HK/2009/02
Table 5.17 Details of Waste Disposal for Contract no.
HY/2009/18
Table 5.18 Details of Waste Disposal for Contract no.
HY/2009/15
Table 5.19 Details of Waste
Disposal for Contract no. HY/2009/19
Table 5.20 Details of Waste Disposal for Contract no.
HK/2010/06
Table 8.1 Summary of Environmental Inspections for
Contract no. HY/2009/15
Table 8.2 Summary of Environmental Inspections for
Contract no. HY/2009/19
Table 8.3 Summary of Environmental Inspections for
Contract no. HK/2009/01
Table 8.4 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2010/06
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful
Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix
5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix
5.2 Noise
Monitoring Results and Graphical Presentations
Appendix
5.3 Air
Quality Monitoring Results and Graphical
Presentations
Appendix 5.4 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification
of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
¡P
No further work under designated project1
1Remarks: The construction of bored pile
E3B under FEP-03/364/2009 was confirmed completed and the bored pile E3B and
the works area was handover
to contract no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Hoarding erection and modification
¡P
Installation of couplers, UU detection, trial trench, pre-drilling
¡P
Excavation
¡P
Sheet Piling
¡P
Drainage works
¡P
Tunnel works
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
OHVD installation
¡P
Cooling main bridge construction
¡P
Pre-bored H-piling
¡P
Bridge construction
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at
¡P
Backfilling works on top of SCL protection works
¡P
Pre-bored H piling works for the proposed CWB.
¡P
Pre-drilling works for CWB (Stage 2)
¡P
Ground treatment works for proposed CWB diaphragm wall.
¡P
Plant Mobilization for diaphragm wall construction works at Stage 2.
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Placing concrete of the final portion for precast scission seawall 2X
¡P
Trimming of pile head at WCR1 of Tunnel Portion 1
¡P
Blinding laying construction at WCR1 of Tunnel Portion 1
¡P
Waterproofing installation at WCR1 of Tunnel Portion 1 Bay 1 - Bay 7
¡P
Rebar fixing for base slab.
¡P
Backfilling of temporary sheet pile seawall
¡P
Extraction of total 150 nos. of western temporary sheet piling.
¡P
Casting of Diaphragm wall of panel P106, C107, P108, C109, P110, C111,
P112, C113, P114, C115 & P116. Total 11 out of 19 D-wall panels were
completed.
¡P
Panel BHP3 and BHP7 in Zone 3.
¡P
Trial excavation, Footpath Set back, UU Diversion and preparation works
for Hung Hing Road Flyover Diversion Stage 1.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
¡P
Excavation and Lateral Support works at TS4
¡P
Rock breaking works at TPCWAE
¡P
Tunnel works at TS1
¡P
Horizontal drilling for mined tunnel
¡P
Pipe roofing installation
¡P
Construction of diaphragm at TS2
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road works at
¡P
Bored piling (Land)
¡P
Pre-drilling works for bored pile and Diaphragm wall
¡P
D-wall Construction (North & South Section)
¡P
Guide wall construction for D-wall / Barrette at North side
¡P
Construction works for Box Culvert T1
¡P
Marine Piling
¡P
Construct ion of socket-H pile
¡P
Construction works for Culvert U1
¡P
Construction of Pile cap & column (Land)
¡P
Dismantling of marine platform
¡P
Demolition of parapet at IEC Link
¡P
Construction of Pile caps & columns (Marine)
¡P
Cut & Cover Tunnel sheet piling works and installation of King Post
¡P
Construction of dewatering well for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P
Utility works in section 2
Noise
Monitoring
Air Monitoring
Complaints, Notifications of Summons
and Successful Prosecutions
Site Inspections and Audit
Contract
no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V
Advanced piling works under FEP-03/364/2009
¡P
No further work under designated project1
1Remarks: The construction of bored pile
E3B under FEP-03/364/2009 was confirmed completed and the bored pile E3B and
the works area was handover
to contract no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Hoarding erection and modification
¡P
Installation of couplers, UU detection, trial trench, pre-drilling
¡P
Excavation
¡P
Sheet Piling
¡P
Drainage works
¡P
Tunnel works
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
OHVD installation
¡P
Cooling main bridge construction
¡P
Pre-bored H-piling
¡P
Bridge construction
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
¡P
Removal of remaining guide wall along
¡P
Backfilling at SCL section to the required level.
¡P
Installation of pre-bored H-pile in CWB Stage 1b (from Ch80 to Ch120).
¡P
Installation of pre-bored H-pile in CWB Stage 2 under the atrium link
(from Ch120 to Ch220).
¡P
CWB diaphragm wall construction under the atrium link.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P
Blinding for the base slab construction and waterproofing installation
at tunnel portion 1.
¡P
Rebar fixing fro the base slab construction at Tunnel Portion 1.
¡P
Base slab concreting at Tunnel Portion 1.
¡P
G.I. and remove the temporary sheetpile wall at WCR2
¡P
Diaphragm wall construction for Eastern Bulkhead Panel BHP3 and BHP7.
¡P
Bulkhead at Bay 14 of Box Culvert ¡§O¡¨ and stage 2 diversion of uncharted
drainage works at Box culvert ¡§O¡¨.
¡P
Preparation work for Bored Pile construction of EP01 ¡V EP11 at Tunnel Portion 3&4.
¡P
Trial excavation, footpath set back, UU diversion, reprovision of street
furniture and preparation works for Hung Hing Road Diversion Stage 1
¡P
Curing of caisson seawall precast unit 2X and protective coating on
flat-top barge.
¡P
Construction of 1800 connection of Box Culvert N1, Bay 4 & Bay 5 and
FRP installation at WCR1 area.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
¡P
ELS works at TS4
¡P
Rock breaking works at TPCWAE
¡P
Tunnel works at TS1
¡P
Horizontal drilling for mined tunnel
¡P
Pipe roofing installation
¡P
Construction of Diaphragm Wall at TS2
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road works at
¡P
Bored piling (Land)
¡P
Pre-drilling works for bored pile and Diaphragm wall
¡P
D-wall Construction (North & South Section)
¡P
Guide wall construction for D-wall / Barrette at North side
¡P
Construction works for Box Culvert T1
¡P
Marine Piling
¡P
Construct ion of socket-H pile
¡P
Construction works for Culvert U1
¡P
Construction of Pile caps & columns (Land)
¡P
Dismantling of marine platform
¡P
Demolition of parapet at IEC Link
¡P
Construction of Pile caps & columns (Marine)
¡P
Cut & Cover Tunnel sheet piling works and installation of King Pos
¡P
Construction of dewatering well for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/B and
Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009,
FEP-03/364/2009,
FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A and FEP-08/364/2009/A to implement the Environmental Monitoring and Audit (EM&A)
programme as stipulated in the EM&A Manual of the approved Environmental
Impact Assessment (EIA) Report for Wan Chai Development phase II and
Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and ¡§Environmental
Monitoring and Audit Requirements¡¨ under
Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no.
EP-364/2009/B, Further Environmental Permit (FEP) nos. FEP-01-364/2009,
FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A,
FEP-07/364/2009/A and FEP-08/364/2009/A during
the period Dec 2012 to Jan 2013. The
cut-off date of reporting is at 27th of each reporting month
Section 1 Introduction ¡V details the scope and structure of the report.
Section 2 Project
Background ¡V summarizes background and
scope of the project, site description, project organization and contact
details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits /
Licenses during the reporting period.
Section 4 Monitoring
Requirements ¡V summarizes all monitoring
parameters, monitoring methodology and equipment, monitoring locations,
monitoring frequency, criteria and respective event and action plan and
monitoring programmes.
Section 5 Monitoring
Results ¡V summarizes the monitoring
results obtained in the reporting period.
Section 6 Compliance Audit ¡V summarizes
the auditing of monitoring results, all exceedances environmental
parameters.
Section 7 Cumulative Construction Impact due
to the Concurrent Projects ¡V summarizes the relevant cumulative
construction impact due to the concurrent activities of the concurrent Projects.
Section 8 Site Inspection ¡V summarizes the findings of weekly site inspections
undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of
summons and Prosecution ¡V summarizes the cumulative statistics on
complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and
¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called
¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested
2.2.1.
Design and Construction of Central ¡V Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai
Bypass (CWB) and
Island Eastern Corridor Link (IECL) includes:
¡P
A
dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
¡P
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
¡P
Tunnel
control buildings and ventilation buildings;
¡P
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
¡P
Associated
road lighting, road signing, traffic control and surveillance system; and
¡P
Other
associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be
either constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these
Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be commenced. Contractors of individual contracts will
be required by the EP holder to apply Further Environmental Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual
Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel ( |
DP1 |
13 July 2011 |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars
are summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912
3010 |
|
Lam Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
General Manager |
Mr. Thomas Tang |
6111 5351 |
2566 7522 |
Contractor¡¦s Representative |
Mr. Chung Man Shek |
2566 4866 |
|||
Site Agent |
Mr. Tong Au |
9725 5874 |
|||
Environmental Officer |
Dr. Priscilla Choy |
9161 7287 |
|||
Environmental Supervisor |
Mr. Tam Chun Pong |
6461 3062 |
|||
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
|
2162 9909 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Construction Manager |
Mr. Terry Wong |
9757 9846 |
|||
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 2467 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Calvin Leung |
9286 9208 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
|
Deputy Site Agent |
Mr. Roger Wong |
2214
7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Engineer Graduate |
Phil Mak |
2214 7738 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ray Cheng |
2214 7742 |
|||
Environmental Supervisor |
K. W. Lee |
6461 4623 |
|||
|
|
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|
|
|
Environmental Supervisor |
Bosco Lee |
2214 7711 |
|
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
Mr. P.J. Fan |
3557 6368 |
2566 2192 |
||
Contractor¡¦s
Representative |
Mr. David Lau |
3557
6358 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Enviromental Supervisor |
Ms Esther Choi |
35576348 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529
2880 |
Site
Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee
Wai Man |
9481 6024 |
|||
Environmental
Supervisor |
Mr.
Clement Pang |
9735 9200 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3. In this
reporting month, the principal work activities of individual contracts are
included as follows:
Contract no.
HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works under FEP-03/364/2009
¡P
No further work under designated project1
1Remarks: The construction of bored pile
E3B under FEP-03/364/2009 was confirmed completed and the bored pile E3B and
the works area was handover
to contract no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Hoarding erection and modification
¡P
Installation of couplers, UU detection, trial trench, pre-drilling
¡P
Excavation
¡P
Sheet Piling
¡P
Drainage works
¡P
Tunnel works
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
OHVD installation
¡P
Cooling main bridge construction
¡P
Pre-bored H-piling
¡P
Bridge construction
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
¡P
Backfilling works on top of SCL protection works
¡P
Pre-bored H piling works for the proposed CWB.
¡P
Pre-drilling works for CWB (Stage 2)
¡P
Ground treatment works for proposed CWB diaphragm wall.
¡P
Plant Mobilization for diaphragm wall construction works at Stage 2.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P
Placing concrete of the final portion for precast scission seawall 2X
¡P
Trimming of pile head at WCR1 of Tunnel Portion 1
¡P
Blinding laying construction at WCR1 of Tunnel Portion 1
¡P
Waterproofing installation at WCR1 of Tunnel Portion 1 Bay 1 - Bay 7
¡P
Rebar fixing for base slab.
¡P
Backfilling of temporary sheet pile seawall
¡P
Extraction of total 150 nos. of western temporary sheet piling.
¡P
Casting of Diaphragm wall of panel P106, C107, P108, C109, P110, C111,
P112, C113, P114, C115 & P116. Total 11 out of 19 D-wall panels were
completed.
¡P
Panel BHP3 and BHP7 in Zone 3.
¡P
Trial excavation, Footpath Set back, UU Diversion and preparation works
for Hung Hing Road Flyover Diversion Stage 1.
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (
¡P
Excavation and Lateral Support works at TS4
¡P
Rock breaking works at TPCWAE
¡P
Tunnel works at TS1
¡P
Horizontal drilling for mined tunnel
¡P
Pipe roofing installation
¡P
Construction of diaphragm at TS2
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
¡P
Road works at
¡P
Bored piling (Land)
¡P
Pre-drilling works for bored pile and Diaphragm wall
¡P
D-wall Construction (North & South Section)
¡P
Guide wall construction for D-wall / Barrette at North side
¡P
Construction works for Box Culvert T1
¡P
Marine Piling
¡P
Construct ion of socket-H pile
¡P
Construction works for Culvert U1
¡P
Construction of Pile cap & column (Land)
¡P
Dismantling of marine platform
¡P
Demolition of parapet at IEC Link
¡P
Construction of Pile caps & columns (Marine)
¡P
Cut & Cover Tunnel sheet piling works and installation of King Post
¡P
Construction of dewatering well for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
2.4.4.
In coming reporting month, the principal work activities of individual
contracts are anticipated as follows:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass
(CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009
¡P
No further work under designated project1
1Remarks: The construction of bored pile
E3B under FEP-03/364/2009 was confirmed completed and the bored pile E3B and
the works area was handover
to contract no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Hoarding erection and modification
¡P
Installation of couplers, UU detection, trial trench, pre-drilling
¡P
Excavation
¡P
Sheet Piling
¡P
Drainage works
¡P
Tunnel works
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
OHVD installation
¡P
Cooling main bridge construction
¡P
Pre-bored H-piling
¡P
Bridge construction
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
¡P
Removal of remaining guide wall along
¡P
Backfilling at SCL section to the required level.
¡P
Installation of pre-bored H-pile in CWB Stage 1b (from Ch80 to Ch120).
¡P
Installation of pre-bored H-pile in CWB Stage 2 under the atrium link
(from Ch120 to Ch220).
¡P
CWB diaphragm wall construction under the atrium link.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P
Blinding for the base slab construction and waterproofing installation
at tunnel portion 1.
¡P
Rebar fixing fro the base slab construction at Tunnel Portion 1.
¡P
Base slab concreting at Tunnel Portion 1.
¡P
G.I. and remove the temporary sheetpile wall at WCR2
¡P
Diaphragm wall construction for Eastern Bulkhead Panel BHP3 and BHP7.
¡P
Bulkhead at Bay 14 of Box Culvert ¡§O¡¨ and stage 2 diversion of uncharted
drainage works at Box culvert ¡§O¡¨.
¡P
Preparation work for Bored Pile construction of EP01 ¡V EP11 at Tunnel Portion 3&4.
¡P
Trial excavation, footpath set back, UU diversion, reprovision of street
furniture and preparation works for Hung Hing Road Diversion Stage 1
¡P
Curing of caisson seawall precast unit 2X and protective coating on
flat-top barge.
¡P
Construction of 1800 connection of Box Culvert N1, Bay 4 & Bay 5 and
FRP installation at WCR1 area.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
¡P
ELS works at TS4
¡P
Rock breaking works at TPCWAE
¡P
Tunnel works at TS1
¡P
Horizontal drilling for mined tunnel
¡P
Pipe roofing installation
¡P
Construction of Diaphragm Wall at TS2
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road works at
¡P
Bored piling (Land)
¡P
Pre-drilling works for bored pile and Diaphragm wall
¡P
D-wall Construction (North & South Section)
¡P
Guide wall construction for D-wall / Barrette at North side
¡P
Construction works for Box Culvert T1
¡P
Marine Piling
¡P
Construct ion of socket-H pile
¡P
Construction works for Culvert U1
¡P
Construction of Pile caps & columns (Land)
¡P
Dismantling of marine platform
¡P
Demolition of parapet at IEC Link
¡P
Construction of Pile caps & columns (Marine)
¡P
Cut & Cover Tunnel sheet piling works and installation of King Pos
¡P
Construction of dewatering well for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Permits and/or
Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further Environmental
Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai
Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009
3.1.3.
Summary of the current status on licences
and/or permits on environmental protection pertinent and
submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table 3.2 and Table 3.3.
Table 3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul
2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul
2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 ¡V 31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13
July 2010 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance |
7010400 |
16
Mar 2010 |
N/A |
Valid |
Contract no. 04/HY/2006 ¡V
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP was surrendered by the
Contractor on 11 February 2011.
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
3.1.5. Summary of the current status on
licences and/or permits on environmental protection pertinent and
submission under FEP-02/364/2009 for contract no.
HK/2009/01 are shown in Table 3.4 and Table 3.5
Table 3.4 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling equipment |
GW-RS-1293-12 |
10 Dec
2012 |
10 Dec
2012 to 9 June 2013 |
Valid |
GW-RS0760-12 |
16 Jul
2012 |
20 Jul
2012 to 19 Jan 2013 |
Expired |
|
GW-RS0806-12 |
3 Aug 2012 |
4 Aug 2012 to 03
Feb 2013 |
Cancelled |
|
GW-RS0823-12 |
3 Aug 2012 |
3 Aug 2012 to 02 Feb 2013 |
Cancelled |
|
GW-RS0852-12 |
16 Aug 2012 |
16 Aug 2012 to 01
Feb 2013 |
Cancelled |
|
GW-RS0855-12 |
16 Aug 2012 |
17 Aug 2012
to 9 Feb 2013 |
Cancelled |
|
GW-RS0862-12 |
20 Aug 2012 |
28 Aug 2012 to 27
Feb 2013 |
Cancelled |
|
GW-RS0949-12 |
12 Sep 2012 |
16 Sep 2012 to 15
Mar 2013 |
Cancelled |
|
GW-RS-0052-13 |
18 Jan
2013 |
20 Jan
2013 to 19 July 2013 |
Valid |
|
GW-RS1011-12 |
26 Sep 2012 |
30 Sep 2012 to 29
Mar 2013 |
Cancelled |
|
GW-RS1017-12 |
27 Sep
2012 |
30 Sep
2012 to 24 Mar 2013 |
Valid |
|
GW-RS0793-12 |
21 Sep
2012 |
30 Sep
2012 to 29 Mar 2013 |
Valid |
|
GW-RS1040-12 |
8 Oct
2012 |
13 Oct
2012 to 12 Apr 2013 |
Valid |
|
GW-RS1177-12 |
15 Nov
2012 |
17 Nov
2012 to10 May 2013 |
Valid |
|
GW-RS1184
-12 |
15 Nov
2012 |
17 Nov
2012 to 8 May 2013 |
Valid |
|
GW-RS1185-12 |
19 Nov
2012 |
21 Nov
2012 to 8 May 2013 |
Valid |
|
GW-RS1179-12 |
20 Nov
2012 |
22 Nov
2012 to 21 May 2013 |
Valid |
|
GW-RS1187-12 |
20 Nov
2012 |
27 Nov
2012 to 26 May 2013 |
Valid |
|
GW-RS1199-12 |
20 Nov
2012 |
26 Nov
2012 to 25 May 2013 |
Valid |
|
Discharge Licence |
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
|
Billing account under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.5 Summary
of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
20 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
10 Jun 2011 |
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS1038-12 |
10 Oct 2012 |
10 Oct 2012 to 9 Apr
2013 |
Valid |
GW-RS1069-12 |
17 Oct 2012 |