Contract No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and Testing Work (Stage
2) Environmental
Permit no. EP-364/2009/B, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/A, FEP-08/364/2009/A
and FEP-09/364/2009/B Monthly Environmental Monitoring & Audit Report
- March 2013 -
|
CLIENTS: |
|
Civil Engineering
and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
11 April 2013 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status of Environmental Licensing and Permitting under the
Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring.
6.4 Review of the Reasons for and the Implications of
Non-compliance
6.5 Summary of action taken in the event of and follow-up on
non-compliance
7. Cumulative Construction Impact
due to the Concurrent Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects
under this Project
Table
2.2 Details of Individual Contracts
under the Project
Table
2.3 Contact Details of Key Personnel
Table
3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/01
Table
3.5 Summary of submission status
under FEP-02/364/2009
Table
3.6 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02
Table
3.7 Summary of submission status
under FEP-01/364/2009
Table
3.8 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/18
Table
3.9 Summary of submission status
under FEP-05/364/2009/A
Table
3.10 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/15
Table
3.11 Summary of submission status
under FEP-06/364/2009/A
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.13
Summary of submission status under FEP-07/364/2009/A
Table
3.14 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2010/06
Table
3.15 Summary of submission status
under FEP-08/364/2009
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 4.1 Noise Monitoring Stations
Table
4.2 Real Time Noise Monitoring
Stations
Table
4.3 Air Monitoring Stations
Table
5.1 Noise Monitoring Stations for
Contract no. HY/2009/17
Table
5.2 Noise Monitoring Stations for
Contract no. HY/2009/18
Table
5.3 Noise Monitoring Station for
Contract no HK/2009/01 and HK/2009/02
Table
5.4 Noise Monitoring Stations for
Contract no. HY/2009/15
Table
5.5 Noise Monitoring Stations for
Contract no. HY/2009/19
Table
5.6 Real Time Noise Monitoring
Stations for Contract no. HY/2009/17
Table
5.7 Real Time Noise Monitoring
Stations for Contract no. HY/2009/19
Table
5.8 Air Monitoring Station for
Contract no. HY/2009/17
Table
5.9 Air Monitoring Stations for
Contract no. HY/2009/18
Table
5.10 Air Monitoring Station for Contract no. HK/2009/01
Table
5.11 Air Monitoring Station for Contract no. HK/2009/02
Table
5.12 Air Monitoring Station for Contract no. HY/2009/15
Table
5.13 Air Monitoring Stations for Contract no. HY/2009/19
Table
5.15 Details of Waste Disposal for
Contract no. HK/2009/01
Table
5.16 Details of Waste Disposal for
Contract no. HK/2009/02
Table
5.17 Details of Waste Disposal for
Contract no. HY/2009/18
Table
5.18 Details of Waste Disposal for
Contract no. HY/2009/15
Table
5.19 Details of Waste Disposal for Contract no. HY/2009/19
Table
5.20 Details of Waste Disposal for
Contract no. HK/2010/06
Table 5.21 Details of Waste Disposal for Contract no. HK/2012/08
Table 8.1 Summary of Environmental
Inspections for Contract no. HY/2009/15
Table
8.2 Summary of Environmental
Inspections for Contract no. HK/2009/01
Table
8.3 Summary of Environmental
Inspections for Contract no. HK/2009/02
Table
8.4 Summary of Environmental
Inspections for Contract no. HK/2010/06
Table
9.1 Cumulative Statistics on
Complaints
Table
9.2 Cumulative Statistics on
Successful Prosecutions
lIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming
month
Appendix 5.2 Noise Monitoring Results and Graphical
Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix
5.4 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification
of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
¡P
No further work under designated project1
1Remarks: The construction of bored pile
E3B under FEP-03/364/2009 was confirmed completed and the bored pile E3B and
the works area was handover
to contract no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Hoarding erection and modification
¡P
Installation of couplers, UU detection, trial trench, pre-drilling
¡P
Excavation
¡P
Drainage works
¡P
Tunnel works
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
OHVD installation
¡P
Pre-bored H-piling
¡P
Bridges construction
¡P
Scaffolding / false-work erection
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at
¡P
Pre-drilling works for CWB (Stage 2).
¡P
Diaphragm wall construction works at Stage 2 (North).
¡P
Mobilization of 1st Piling rig for pre-bored H piling works
under atrium.
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Casting of Base slab Bay 4, Bay8, Bay9 & Bay10
¡P
Waterproofing installation at WCR1 of Tunnel Portion 1
¡P
Rebar fixing for base slab Bay 11 to Bay 14
¡P
3 nos. bored piles PN12, PC12 & PS14 were concreted
¡P
Excavation for other 4 nos. bored
piles PS13, PC14, PS18 &
PS19
¡P
The outstanding sewerage works in
¡P
Silt curtain installation for dredging works at TWCR4 was completed on 5
Mar 2013.
¡P
Works associated with footpath modification and proposed sewerage works
for Hung Hing Road Flyover Diversion Stage 1 implementation.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
¡P
ELS works at TS4
¡P
Rock breaking works at TPCWAE
¡P
Tunnel works at TS1
¡P
Horizontal drilling for mined tunnel
¡P
Construction of Diaphragm Wall at TS2
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road works at
¡P
Bored piling (Land)
¡P
D-wall Construction (North & South Section)
¡P
Guide wall construction for D-wall / Barrette at North side
¡P
Construction works for Box Culvert T1
¡P
Construction of socket-H pile
¡P
Construction works for Culvert U1
¡P
Construction of Pile caps & columns (Land)
¡P
Demolition of parapet at IEC Link
¡P
Construction of Pile caps & columns (Marine)
¡P
Construction of dewatering well for Cut & Cover Tunnel
¡P
D8-D9 Gantry Fabrication for precast segment
¡P
ELS for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P
Utility works in section 2
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West
¡P
Site preparation works
¡P
Site survey
Noise
Monitoring
Air Monitoring
rescheduled
CMA2a: from
4 Mar 2013 to 5 Mar 2013
Complaints, Notifications of Summons
and Successful Prosecutions
Site Inspections and Audit
Contract
no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V
Advanced piling works under FEP-03/364/2009
¡P
No further work under designated project1
1Remarks: The construction of bored pile
E3B under FEP-03/364/2009 was confirmed completed and the bored pile E3B and
the works area was handover
to contract no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Hoarding erection and modification
¡P
Installation of couplers, UU detection, trial trench, pre-drilling
¡P
Excavation
¡P
Drainage works
¡P
Tunnel works
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
OHVD installation
¡P
Pre-bored H-piling
¡P
Bridges construction
¡P
Scaffolding / false-work erection
¡P
Profile barrier construction
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
¡P
Installation of pre-bored H-pile in CWB Stage 2 under the atrium link
(from Ch120 to Ch220).
¡P
CWB diaphragm wall construction under the atrium link.
¡P
Mobilization of Trench cutter to Site.
¡P
Bulkhead Wall at Ch120.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P
Complete blinding layer & water proofing membrane installation
¡P
Construction of base slab between Bay 1 to Bay 2 & Bay 11 to Bay 16 and
commence the subsequent wall construction from Bay 1 to Bay 5.
¡P
Continue removal of the temporary sheetpile wall at WCR2
¡P
Continue bored pile construction.
¡P
Complete both outstanding sewerage works at WSS and all road
reinstatement works at Hung Hing Road & WSS for implementation of HHR
Flyover Diversion (Stage 1)
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
¡P
ELS works at TS4
¡P
Rock trimming and concrete works at TPCWAE
¡P
Tunnel works at TS1
¡P
Horizontal drilling for mined tunnel
¡P
Construction of Diaphragm Wall at TS2
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road works at
¡P
Bored piling (Land)
¡P
D-wall Construction (North & South Section)
¡P
Guide wall construction for D-wall / Barrette at North side
¡P
Construction works for Box Culvert T1
¡P
Construct ion of socket-H pile
¡P
Construction works for Culvert U1
¡P
Construction of Pile caps & columns (Land)
¡P
Demolition of parapet at IEC Link
¡P
Construction of dewatering well for Cut & Cover Tunnel
¡P
D8-D9 Gantry Fabrication for precast segment
¡P
ELS for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West
¡P
Hoarding erection
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/B and
Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A,
FEP-08/364/2009/A and FEP-09/364/2009/B to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit
Requirements¡¨ under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/B, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-03/364/2009,
FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A and
FEP-09/364/2009B during the period Feb to Mar 2013. The cut-off date of reporting is at 27th
of each reporting month
Section
1 Introduction ¡V
details the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results obtained
in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the Concurrent
Projects ¡V summarizes
the relevant cumulative construction impact due to the concurrent activities of
the concurrent Projects.
Section
8 Site Inspection ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and
¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called
¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested
2.2.1.
Design and Construction of Central ¡V Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
¡P
A dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
¡P
The Central Interchange near the Rumsey Street Flyover to provide road
connections to the Central area;
¡P
Tunnel control buildings and ventilation buildings;
¡P
Slip roads to connect the CWB to the local road system in the Wan Chai
North and
¡P
Associated road lighting, road signing, traffic control and surveillance
system; and
¡P
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2
DPs.
Table
2.1 Schedule 2 Designated
Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason
for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in
length |
DP2 |
Road P2 and other roads which are classified as
primary/district distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging
works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging
operation less than 100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter
more than 1,200 mm and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from
Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a
seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further
Environmental Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table
2.2 Details of Individual
Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield
Depot ¡V Advanced piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at |
DP1,
DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East(CWB Tunnel) |
DP1 |
26
April 2011 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel ( |
DP1 |
13
July 2011 |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link |
DP1 |
24
March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai
Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
March 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587
1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912
3010 |
|
Lam Woo & CO.,
LTD. |
Contractor under Contract no. HY/2009/17 |
General Manager |
Mr. Thomas Tang |
6111 5351 |
2566
7522 |
Contractor¡¦s Representative |
Mr. Chung Man Shek |
2566 4866 |
|||
Site Agent |
Mr. Tong Au |
9725 5874 |
|||
Environmental Officer |
Dr. Priscilla Choy |
9161 7287 |
|||
Environmental Supervisor |
Mr. Tam Chun Pong |
6461 3062 |
|||
Chun Wo ¡V Leader
Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
|
2162 9909 |
2634
1626 |
Site
Agent |
Mr. Paul
Yu |
9456
9819 |
|||
Construction
Manager |
Mr. Terry Wong |
9757 9846 |
|||
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack
Chu |
9775 2467 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103
2370 |
|||
Environmental
Supervisor |
Mr. Kwong
Weng Kit |
6253
3356 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658-3002 |
2827
9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint
Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570
8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Mr. |
9286 9208 |
|||
Construction Manager (Marine) |
Mr. William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Mr. Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Mr. Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Mr. Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214
7700 |
|
Deputy Site Agent |
Mr. Roger Wong |
2214
7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214
7721 |
|||
Environmental Engineer Graduate |
Mr. Phil Mak |
2214
7738 |
|||
Environmental Supervisor |
Mr. K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Mr. Ray Cheng |
2214 7742 |
|||
Environmental Supervisor |
Mr. K. W. Lee |
6461 4623 |
|||
|
|
Environmental Supervisor |
Mr. Ryan Tsui |
2214
7705 |
|
|
|
Environmental Supervisor |
Mr. Bosco Lee |
2214
7711 |
|
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
Mr. P.J. Fan |
3557 6368 |
2566 2192 |
||
Contractor¡¦s
Representative |
Mr. David Lau |
3557
6358 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Enviromental Supervisor |
Ms. Esther Choi |
35576348 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529
2880 |
Site
Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee
Wai Man |
9481 6024 |
|||
Environmental
Supervisor |
Mr.
Clement Pang |
9735 9200 |
|||
|
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. Andrew
TSE |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Victor
WU |
9193
8871 |
|||
Deputy
Project Manager |
Mr. George
CHEUNG |
9268
1918 |
|||
Site
Agent |
Mr. Paul
LUI |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Ching
Man, CHAN |
6050
4919 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics
Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882
3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract
no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V
Advanced piling works under FEP-03/364/2009
¡P
No further work under designated project1
1Remarks: The construction of bored pile
E3B under FEP-03/364/2009 was confirmed completed and the bored pile E3B and
the works area was handover
to contract no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Hoarding erection and modification
¡P
Installation of couplers, UU detection, trial trench, pre-drilling
¡P
Excavation
¡P
Drainage works
¡P
Tunnel works
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
OHVD installation
¡P
Pre-bored H-piling
¡P
Bridges construction
¡P
Scaffolding / false-work erection
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
¡P
Pre-drilling works for CWB (Stage 2).
¡P
Diaphragm wall construction works at Stage 2 (North).
¡P
Mobilization of 1st Piling rig for pre-bored H piling works
under atrium.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P
Casting of Base slab Bay 4, Bay8, Bay9 & Bay10
¡P
Waterproofing installation at WCR1 of Tunnel Portion 1
¡P
Rebar fixing for base slab Bay 11 to Bay 14
¡P
3 nos. bored piles PN12, PC12 & PS14 were concreted
¡P
Excavation for other 4 nos. bored
piles PS13, PC14, PS18 &
PS19
¡P
The outstanding sewerage works in
¡P
Silt curtain installation for dredging works at TWCR4 was completed on 5
Mar 2013.
¡P
Works associated with footpath modification and proposed sewerage works
for Hung Hing Road Flyover Diversion Stage 1 implementation.
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (
¡P
ELS works at TS4
¡P
Rock breaking works at TPCWAE
¡P
Tunnel works at TS1
¡P
Horizontal drilling for mined tunnel
¡P
Construction of Diaphragm Wall at TS2
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
¡P
Road works at
¡P
Bored piling (Land)
¡P
D-wall Construction (North & South Section)
¡P
Guide wall construction for D-wall / Barrette at North side
¡P
Construction works for Box Culvert T1
¡P
Construction of socket-H pile
¡P
Construction works for Culvert U1
¡P
Construction of Pile caps & columns (Land)
¡P
Demolition of parapet at IEC Link
¡P
Construction of Pile caps & columns (Marine)
¡P
Construction of dewatering well for Cut & Cover Tunnel
¡P
D8-D9 Gantry Fabrication for precast segment
¡P
ELS for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
2.4.4.
In coming reporting month, the principal work activities of individual
contracts are anticipated as follows:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass
(CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009
¡P
No further work under designated project1
1Remarks: The construction of bored pile
E3B under FEP-03/364/2009 was confirmed completed and the bored pile E3B and
the works area was handover to contract no. HY/2009/19 on 30 November
2012.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Hoarding erection and modification
¡P
Installation of couplers, UU detection, trial trench, pre-drilling
¡P
Excavation
¡P
Drainage works
¡P
Tunnel works
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
OHVD installation
¡P
Pre-bored H-piling
¡P
Bridges construction
¡P
Scaffolding / false-work erection
¡P
Profile barrier construction
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
¡P
Installation of pre-bored H-pile in CWB Stage 2 under the atrium link
(from Ch120 to Ch220).
¡P
CWB diaphragm wall construction under the atrium link.
¡P
Mobilization of Trench cutter to Site.
¡P
Bulkhead Wall at Ch120.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P
Complete blinding layer & water proofing membrane installation
¡P
Construction of base slab between Bay 1 to Bay 2 & Bay 11 to Bay 16 and
commence the subsequent wall construction from Bay 1 to Bay 5.
¡P
Continue removal of the temporary sheetpile wall at WCR2
¡P
Continue bored pile construction.
¡P
Complete both outstanding sewerage works at WSS and all road
reinstatement works at Hung Hing Road & WSS for implementation of HHR
Flyover Diversion (Stage 1)
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
¡P
ELS works at TS4
¡P
Rock trimming and concrete works at TPCWAE
¡P
Tunnel works at TS1
¡P
Horizontal drilling for mined tunnel
¡P
Construction of Diaphragm Wall at TS2
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road works at
¡P
Bored piling (Land)
¡P
D-wall Construction (North & South Section)
¡P
Guide wall construction for D-wall / Barrette at North side
¡P
Construction works for Box Culvert T1
¡P
Construct ion of socket-H pile
¡P
Construction works for Culvert U1
¡P
Construction of Pile caps & columns (Land)
¡P
Demolition of parapet at IEC Link
¡P
Construction of dewatering well for Cut & Cover Tunnel
¡P
D8-D9 Gantry Fabrication for precast segment
¡P
ELS for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West
¡P
Site preparation works
¡P
Site survey
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Valid |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai
Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009
3.1.3.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table 3.2 and Table 3.3.
Table
3.2 Cumulative Summary
of Valid Licences and Permits under Contract no.
HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul
2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul
2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 ¡V 31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13
July 2010 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance |
7010400 |
16
Mar 2010 |
N/A |
Valid |
Contract no. 04/HY/2006 ¡V Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP was surrendered by the
Contractor on 11 February 2011.
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
3.1.5.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5
Table 3.4 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr
2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
06 Jan
2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling
equipment |
GW-RS-1293-12 |
10 Dec
2012 |
10 Dec
2012 to 9 June 2013 |
Valid |
GW-RS0166-13 |
14 Feb
2013 |
16 Feb
2013 to 13 Aug 2013 |
Valid |
|
GW-RS0124-13 |
19 Mar
2013 |
25 Mar
2013 to 24 Sept 2013 |
Valid |
|
GW-RS0310-13 |
25 Mar
2013 |
27 Mar
2013 to 25 Sept 2013 |
Valid |
|
GW-RE0274-13 |
26 Mar
2013 |
30 Mar
2013 to 29 Sept 2013 |
Valid |
|
GW-RS0949-12 |
12 Sep
2012 |
16 Sep
2012 to 15 Mar 2013 |
Cancelled |
|
GW-RS-0052-13 |
18 Jan
2013 |
20 Jan
2013 to 19 July 2013 |
Valid |
|
GW-RS1011-12 |
26 Sep
2012 |
30 Sep
2012 to 29 Mar 2013 |
Cancelled |
|
GW-RS1017-12 |
27 Sep
2012 |
30 Sep
2012 to 24 Mar 2013 |
Expired |
|
GW-RS0793-12 |
21 Sep
2012 |
30 Sep
2012 to 29 Mar 2013 |
Expired |
|
GW-RS1040-12 |
8 Oct
2012 |
13 Oct
2012 to 12 Apr 2013 |
Valid |
|
GW-RS1177-12 |
15 Nov
2012 |
17 Nov
2012 to10 May 2013 |
Valid |
|
GW-RS1184
-12 |
15 Nov
2012 |
17 Nov
2012 to 8 May 2013 |
Valid |
|
GW-RS1185-12 |
19 Nov
2012 |
21 Nov
2012 to 8 May 2013 |
Valid |
|
GW-RS1179-12 |
20 Nov
2012 |
22 Nov
2012 to 21 May 2013 |
Valid |
|
GW-RS1187-12 |
20 Nov
2012 |
27 Nov
2012 to 26 May 2013 |
Valid |
|
GW-RS1199-12 |
20 Nov
2012 |
26 Nov
2012 to 25 May 2013 |
Valid |
|
Discharge
Licence |
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
WT00006220-2010 |
18 Mar
2010 |
31 Mar 2015 |
Valid |
|
Billing account under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration
as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan
2010 |
N/A |
Valid |
Table 3.5 Summary of submission
status under FEP-02/364/2009
EP Condition |
Submission |
Date
of
Submission |
Special
Conditions, Clause 2.7 & 2.8 |
Works
Schedule and Location Plan |
18 May
2011 |
Special
Conditions, Clause 2.6 |
Environmental
Management Organization Chart |
18 May
2011 |
Special
Conditions, Clause 2.6 |
Commencement
Date of Works |
20 Jun 2011 |
Special
Conditions, Clause 2.9 |
Noise
Management Plan |
10
Jun 2011 |
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS1038-12 |
10 Oct 2012 |
10 Oct 2012 to 9 Apr
2013 |
Valid |
GW-RS1069-12 |
17 Oct 2012 |
19 Oct 2012 to 18 Apr
2013 |
Valid |
|
GW-RS1076-12 |
25 Oct 2012 |
1 Nov 2012 to 30 Apr 2013 |
Valid |
|
GW-RS1204-12 |
9 Nov 2012 |
29 Nov 2012 to 23 May 2013 |
Valid |
|
GW-RS1272-12 |
5 Dec 2012 |
5 Dec 2012 to 26 May 2013 |
Valid |
|