Contract No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and Testing Work (Stage
2) Environmental
Permit no. EP-364/2009/B, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/A, FEP-08/364/2009/A
and FEP-09/364/2009/B Monthly Environmental Monitoring & Audit Report
- June 2013 -
|
CLIENTS: |
|
Civil Engineering
and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
12 July 2013 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status of Environmental Licensing and Permitting under the
Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring.
6.4 Review of the Reasons for and the Implications of
Non-compliance
6.5 Summary of action taken in the event of and follow-up on
non-compliance
7. Cumulative Construction Impact
due to the Concurrent Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects
under this Project
Table
2.2 Details of Individual Contracts
under the Project
Table
2.3 Contact Details of Key Personnel
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/01
Table
3.5 Summary of submission status
under FEP-02/364/2009
Table
3.6 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/02
Table
3.7 Summary of submission status
under FEP-01/364/2009
Table
3.8 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/18
Table
3.9 Summary of submission status
under FEP-05/364/2009/A
Table
3.10 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/15
Table
3.11 Summary of submission status
under FEP-06/364/2009/A
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.13
Summary of submission status under FEP-07/364/2009/A
Table
3.14 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2010/06
Table 3.15 Summary of submission status under
FEP-08/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.17 Summary of submission status under FEP-09/364/2009/B
Table 4.1 Noise Monitoring Stations
Table
4.2 Real Time Noise Monitoring
Stations
Table
4.3 Air Monitoring Stations
Table
5.2 Noise Monitoring Stations for
Contract no. HY/2009/18
Table
5.3 Noise Monitoring Station for
Contract no HK/2009/01 and HK/2009/02
Table
5.4 Noise Monitoring Stations for
Contract no. HY/2009/15
Table
5.5 Noise Monitoring Stations for
Contract no. HY/2009/19
Table
5.7 Real Time Noise Monitoring
Stations for Contract no. HY/2009/19
Table
5.9 Air Monitoring Stations for
Contract no. HY/2009/18
Table
5.10 Air Monitoring Station for Contract no. HK/2009/01
Table
5.11 Air Monitoring Station for Contract no. HK/2009/02
Table
5.12 Air Monitoring Station for Contract no. HY/2009/15
Table
5.13 Air Monitoring Stations for Contract no. HY/2009/19
Table
5.15 Details of Waste Disposal for
Contract no. HK/2009/01
Table
5.16 Details of Waste Disposal for
Contract no. HK/2009/02
Table
5.17 Details of Waste Disposal for
Contract no. HY/2009/18
Table
5.18 Details of Waste Disposal for
Contract no. HY/2009/15
Table
5.19 Details of Waste Disposal for Contract no. HY/2009/19
Table
5.20 Details of Waste Disposal for
Contract no. HK/2010/06
Table 5.21 Details of Waste Disposal for Contract no. HK/2012/08
Table 8.1 Summary of Environmental
Inspections for Contract no. HY/2009/15
Table
8.2 Summary of Environmental Inspections
for Contract no. HK/2009/18
Table 8.3
Summary of Environmental Inspections for Contract no. HK/2009/01
Table 8.4
Summary of Environmental Inspections for Contract no. HK/2009/02
Table
9.1 Cumulative Statistics on
Complaints
Table
9.2 Cumulative Statistics on
Successful Prosecutions
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming
month
Appendix 5.2 Noise Monitoring Results and Graphical
Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix
5.4 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification
of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
¡P Excavation of trial pit
¡P Transplanting of trees
¡P Hoarding erection and modification
¡P Installation of couplers, UU detection,
trial trench, pre-drilling
¡P Excavation
¡P Drainage works
¡P Tunnel works
¡P Trough structure construction and associated
drilling and grouting
¡P Road works
¡P OHVD installation
¡P Pre-bored H-piling
¡P Bridges construction
¡P Scaffolding / false-work erection
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at
¡P Pre-drilling works for CWB (Stage 2).
¡P Diaphragm wall construction works at
Stage 2 (North).
¡P Temporary bulkhead wall construction
works at CH3129 (between Stage2 / Stage3).
¡P Pre-bored H piling works for CWB (Stage1b).
¡P Excavation and grouting of Pre-bored
H-pile.
¡P Pre-bored H piling works for CWB
(Stage2).
¡P Installation of dewatering well at CWB
(Stage 1 & 1b).
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P Base Slab for Tunnel Portion 1
¡P Bored piles PN17 was concreted
¡P Casting Base slab for silo setup
¡P Desander setup and its mud pit
construction for D-Wall construction at Tunnel Portion 2 Ground treatment for
D-wall at WCR2 was commenced on 10 Jun 2013.
¡P Backfilling works for pipe trenches and
the road modification works along
¡P Casting of Base slab at Bay 4 of Box
Culvert N.
¡P Sheet pile cutting works at Bay5 / Bay 6
interface for subsequent construction of water plug beneath the installed
precast unit (Bay 6)
¡P Panel (BHC2) of Eastern Bulkhead Wall
was concreted
¡P Excavation for P129 and the remaining
panel of Eastern Bulkhead Wall BHC12
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
¡P ELS works and pipe roofing works at TS4
¡P Cut and cover tunnel construction at
TPCWAE
¡P Construction of
OHVD at TS1
¡P Excavation for mined tunnel
¡P Construction of Diaphragm Wall at TS2
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P Road works at
¡P Bored piling (Land)
¡P D-wall and Barrette Construction
¡P Construction works for Box Culvert T1
¡P Construction works for Culvert U1
¡P Construction of Pile cap (Land)
¡P Demolition of parapet at IEC Link
¡P Construction of dewatering well for Cut
& Cover Tunnel
¡P Removal of marine platform
¡P Construction of pile cap, column &
cross head (Marine)
¡P ELS for Cut & Cover Tunnel
¡P Laying of 1500 pipe
¡P Launching of segments
¡P Unloading segments from derrick
¡P Extraction of temporary pile from marine
section
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P Nil
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
¡P Site preparation works
¡P Site survey
¡P Hoarding erection
Noise
Monitoring
M1a and M2b: From 11 June 2013 to 14
June 2013
M3a, M4b and M5b and M6: From 11 June
2013 to 13 June 2013
Air Monitoring
24hr-TSP monitoring at CMA5a scheduled
on 21 June 2013 was temporarily suspended due to continuous electricity power
supply for 24hrs was unavailable.
1-hour and 24-hour Total Suspended
Particulates (TSP) monitoring were conducted at CMA1b ¡V Oil Street Site Office;
CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site Office Area; CMA4a
¡V Society for the Prevention of Cruelty to Animals; CMA5a - Children Garden
opposite to Pedestrian Plaza; MA1e and MA1w ¡V International Finance Centre eastern
and western wing on every six days basis.
Complaints, Notifications of Summons
and Successful Prosecutions
A follow-up joint inspection with RSS and Landscape specialist was
conducted on 10 June2013, it was considered that the withered and yellow leaves
of the affected trees (T1674,T1675,T1676,T1677,T1678,T1679,T1680,T1681,T1683,T1644,T1643,T1641,T1639)
at the concerned planter area were contributed by natural life cycle of the
affected trees and the health condition of the affected trees were considered
to be fair. It was also noted that an active CEDD works area was located within
the concerned planter area in close proximity to few of the concerned trees
(T1644, T1643, T1641, and T1639)
According
to tree inspection records from Jan 2013 to May 2013 confirmed by RSS (Document
Ref: CI-F1-043b, CI-F1-044b, CI-F1-045b, CI-F1-046b, CI-F1-047b), the affected
tree (T1712) at the concerned planter area was considered to show sign of
withering and considered to be in poor health condition in latest tree survey
report confirmed by RSS.
During
the follow-up inspection on 10 June 2013, it was observed those construction
material and oil drums were placed near the roots area of other trees within
the CEDD works. Despite the above observation, no direct evidence was found on
site which indicates the work front have contributed to the poor health
condition of the affected tree (T1712) at the time of investigation.
Nevertheless,
regular inspection to check the health condition of the trees and regular
removal of withered leaves or dead branches which deemed appropriate to maintain
the overall tree appearance were implemented by the contractor.
xxiii.
One environmental complaint under EP-364//2009/B was received on 11 June 2013 (EPD
Ref.:H04/RS/00011587-13) dated 11 June 2013) regarding noise impact near
Central Piers in the reporting month.
The
complaint reported that the noise was emanated from the construction site near
the Central Piers at around 0900 hrs on 30 May 2013 and other days and
requested follow up action by relevant department. RSS confirmed that major
noise generating construction activities undertaken at works area near Central
Pier during the concerned time include breaking up existing D-wall concrete and
excavation at portion 4B, 4C and sheet pilling works at Portion VI (
Total 1
no. of Backhoe with breaker, 1 no. of Backhoe with vibratory hammer and 4 no.s
of pneumatic breakers were deployed for the above construction activities.
Reviewing
the noise monitoring data at monitoring stations (M7e- Internation Finance
Centre Eastern End of Podium and M7w- International Finance Centre Western End
of Podium), no limit level exceedances were recorded during routine noise
monitoring event on 28 May 2013 and 03 June 2013. As similar construction works
activities conducted on 30 May 2013 was continued across the above monitoring
period, the noise emanated from the construction activities under Contract
HY/2009/18 was considered complied with the statutory requirement.
In
addition, weekly environmental site inspection was conducted on 30 May 2013 at
around 10:00. According to the inspection record, no particular observation
regarding noise impact was recorded and the mitigation measures including
erection of temporary noise barrier was observed in place.
Site Inspections and Audit
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P Excavation of trial pit
¡P Transplanting of trees
¡P Hoarding erection and modification
¡P Installation of couplers, UU detection,
trial trench, pre-drilling
¡P Excavation
¡P Drainage works
¡P Tunnel works
¡P Trough structure construction and
associated drilling and grouting
¡P Road works
¡P OHVD installation
¡P Bridges construction
¡P Scaffolding / false-work erection
¡P Profile barrier construction
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
¡P Installation of pre-bored H-pile in CWB
Stage 1B under the atrium link (from Ch80 to Ch220)
¡P Installation of pre-bored H-pile in CWB
Stage 1B under the atrium link (from Ch120 to Ch220)
¡P Construction of bulkhead Wall at Ch3129
¡P Demolition of the promenade deck and
pumping stations at HKCEC Water Channel
¡P Installation of dewatering well at CWB
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P Construction of Eastern Bulkhead wall.
¡P Wall construction at Tunnel Portion 1.
¡P D-Wall construction at Tunnel Portion 2.
¡P Rock filling and leveling stone
installation for seawall construction at both WCR4 & TWCR4.
¡P Geotextile installation for temporary
reclamation at TWCR4
¡P Precast concrete seawall installation at
WCR4 & TWCR4.
¡P Continue backfilling and road
reinstatement works at Hung Hing Road & Wan Shing Street for successful
implementation of HHR Flyover Diversion (Stage 1)
¡P Complete water plug construction works at
Bay5/Bay6 interface and commence construction of Bay 5 Box Culvert N1.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
¡P ELS works and pipe roofing works at TS4
¡P Cut and cover tunnel construction at
TPCWAE
¡P Construction of
OHVD at TS1
¡P Excavation for mined tunnel
¡P Construction of Diaphragm Wall and
Installation of King Post at TS2
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P Road works at
¡P Bored piling (Land)
¡P D-wall and Barrette Construction
¡P Construction works for Box Culvert T1
¡P Construction works for Culvert U1
¡P Construction of Pile cap (Land)
¡P Demolition of parapet at IEC Link
¡P Construction of dewatering well for Cut
& Cover Tunnel
¡P Removal of marine platform
¡P Construction of pile cap, column & cross
head (Marine)
¡P ELS for Cut & Cover Tunnel
¡P Laying of 1500f pipe
¡P Launching of segments
¡P Unloading segments from derrick
¡P Extraction of temporary pile from marine
section
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P Installation works of Precast Concrete
Box Unit
¡P Remaining works in box unit
(Installation of foam concrete)
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009/B
¡P Hoarding erection
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/B and
Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A,
FEP-08/364/2009/A and FEP-09/364/2009/B to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit
Requirements¡¨ under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/B, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009B during the period May to June 2013. The cut-off
date of reporting is at 27th of each reporting month
Section
1 Introduction ¡V
details the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results obtained
in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the Concurrent
Projects ¡V summarizes
the relevant cumulative construction impact due to the concurrent activities of
the concurrent Projects.
Section
8 Site Inspection ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and
¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called
¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested
2.2.1.
Design and Construction of Central ¡V Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
¡P
A dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
¡P
The Central Interchange near the Rumsey Street Flyover to provide road
connections to the Central area;
¡P
Tunnel control buildings and ventilation buildings;
¡P
Slip roads to connect the CWB to the local road system in the Wan Chai
North and
¡P
Associated road lighting, road signing, traffic control and surveillance
system; and
¡P
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2
DPs.
Table
2.1 Schedule 2 Designated
Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason
for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in
length |
DP2 |
Road P2 and other roads which are classified as
primary/district distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging
works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging
operation less than 100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter
more than 1,200 mm and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from
Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a
seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further Environmental
Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table
2.2 Details of
Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield
Depot ¡V Advanced piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at |
DP1,
DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East(CWB Tunnel) |
DP1 |
26
April 2011 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel ( |
DP1 |
13
July 2011 |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link |
DP1 |
24
March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai
Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
DP works under |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587
1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912
3010 |
|
Lam Woo & CO.,
LTD. |
Contractor under Contract no. HY/2009/17 |
General Manager |
Mr. Thomas Tang |
6111 5351 |
2566
7522 |
Contractor¡¦s Representative |
Mr. Chung Man Shek |
2566 4866 |
|||
Site Agent |
Mr. Tong Au |
9725 5874 |
|||
Environmental Officer |
Dr. Priscilla Choy |
9161 7287 |
|||
Environmental Supervisor |
Mr. Tam Chun Pong |
6461 3062 |
|||
Chun Wo ¡V Leader
Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
|
2162 9909 |
2634
1626 |
Construction
Manager |
Mr. Terry Wong |
9757 9846 |
|||
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack
Chu |
9775 2467 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103
2370 |
|||
Environmental
Supervisor |
Mr. Kwong
Weng Kit |
6253
3356 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658-3002 |
2827
9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint
Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570
8013 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Mr. |
9286 9208 |
|||
Construction Manager (Marine) |
Mr. William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Mr. Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Mr. Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Mr. Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214
7700 |
|
Deputy Site Agent |
Mr. Roger Wong |
2214
7703 |
|||
Environmental Officer |
Ms. |
2823
1161 |
|||
Environmental Engineer |
Mr. Donald Yip |
2214
7721 |
|||
Environmental Engineer Graduate |
Mr. Phil Mak |
2214
7738 |
|||
Environmental Supervisor |
Mr. K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Mr. Ray Cheng |
2214 7742 |
|||
Environmental Supervisor |
Mr. K. W. Lee |
6461 4623 |
|||
Environmental Supervisor |
Mr. Ryan Tsui |
2214
7705 |
|||
Environmental Supervisor |
Mr. C. Y. Au Yeung |
6461
8631 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. K C Cheung |
2823 7813 |
2865 5229 |
Site Manager |
Mr. J.H. Chen |
3557 6368 |
2566 2192 |
||
Contractor¡¦s
Representative |
Mr. Andrew Wong |
3557
6407 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Enviromental Supervisor |
Ms. Esther Choi |
35576348 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529
2880 |
Site
Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Clement Pang |
9481 6024 |
|||
Environmental
Supervisor |
Mr.
Jacky Cheung |
9735 9200 |
|||
|
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. Andrew
TSE |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Victor
WU |
9193
8871 |
|||
Deputy
Project Manager |
Mr. George
CHEUNG |
9268
1918 |
|||
Site
Agent |
Mr. Paul
LUI |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Ching
Man, CHAN |
6050
4919 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics
Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882
3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Hoarding erection and modification
¡P
Installation of couplers, UU detection, trial trench, pre-drilling
¡P
Excavation
¡P
Drainage works
¡P
Tunnel works
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
OHVD installation
¡P
Pre-bored H-piling
¡P
Bridges construction
¡P
Scaffolding / false-work erection
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
¡P
Pre-drilling works for CWB (Stage 2).
¡P
Diaphragm wall construction works at Stage 2 (North).
¡P
Temporary bulkhead wall construction works at CH3129 (between Stage2 /
Stage3).
¡P
Pre-bored H piling works for CWB (Stage1b).
¡P
Excavation and grouting of Pre-bored H-pile.
¡P
Pre-bored H piling works for CWB (Stage2).
¡P
Installation of dewatering well at CWB (Stage 1 & 1b).
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P
Base Slab for Tunnel Portion 1
¡P
Bored piles PN17 was concreted
¡P
Casting Base slab for silo setup
¡P
Desander setup and its mud pit construction for D-Wall construction at Tunnel
Portion 2 Ground treatment for D-wall at WCR2 was commenced on 10 Jun 2013.
¡P
Backfilling works for pipe trenches and the road modification works along
¡P
Casting of Base slab at Bay 4 of Box Culvert N.
¡P
Sheet pile cutting works at Bay5 / Bay 6 interface for subsequent
construction of water plug beneath the installed precast unit (Bay 6)
¡P
Panel (BHC2) of Eastern Bulkhead Wall was concreted
¡P
Excavation for P129 and the remaining panel of Eastern Bulkhead Wall
BHC12
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (
¡P
ELS works and pipe roofing works at TS4
¡P
Cut and cover tunnel construction at TPCWAE
¡P Construction of
OHVD at TS1
¡P
Excavation for mined tunnel
¡P
Construction of Diaphragm Wall at TS2
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
¡P
Road works at
¡P
Bored piling (Land)
¡P
D-wall and Barrette Construction
¡P
Construction works for Box Culvert T1
¡P
Construction works for Culvert U1
¡P
Construction of Pile cap (Land)
¡P
Demolition of parapet at IEC Link
¡P
Construction of dewatering well for Cut & Cover Tunnel
¡P
Removal of marine platform
¡P
Construction of pile cap, column & cross head (Marine)
¡P
ELS for Cut & Cover Tunnel
¡P
Laying of 1500 pipe
¡P
Launching of segments
¡P
Unloading segments from derrick
¡P
Extraction of temporary pile from marine section
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009/B
¡P
Site preparation works
¡P
Site survey
¡P
Hoarding erection
2.4.4.
In coming reporting month, the principal work activities of individual
contracts are anticipated as follows:
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P Excavation of trial pit
¡P Transplanting of trees
¡P Hoarding erection and modification
¡P Installation of couplers, UU detection,
trial trench, pre-drilling
¡P Excavation
¡P Drainage works
¡P Tunnel works
¡P Trough structure construction and
associated drilling and grouting
¡P Road works
¡P OHVD installation
¡P Bridges construction
¡P Scaffolding / false-work erection
¡P Profile barrier construction
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
¡P Installation of pre-bored H-pile in CWB
Stage 1B under the atrium link (from Ch80 to Ch220)
¡P Installation of pre-bored H-pile in CWB
Stage 1B under the atrium link (from Ch120 to Ch220)
¡P Construction of bulkhead Wall at Ch3129
¡P Demolition of the promenade deck and
pumping stations at HKCEC Water Channel
¡P Installation of dewatering well at CWB
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P Construction of Eastern Bulkhead wall.
¡P Wall construction at Tunnel Portion 1.
¡P D-Wall construction at Tunnel Portion 2.
¡P Rock filling and leveling stone
installation for seawall construction at both WCR4 & TWCR4.
¡P Geotextile installation for temporary
reclamation at TWCR4
¡P Precast concrete seawall installation at
WCR4 & TWCR4.
¡P Continue backfilling and road
reinstatement works at Hung Hing Road & Wan Shing Street for successful
implementation of HHR Flyover Diversion (Stage 1)
¡P Complete water plug construction works at
Bay5/Bay6 interface and commence construction of Bay 5 Box Culvert N1.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
¡P ELS works and pipe roofing works at TS4
¡P Cut and cover tunnel construction at
TPCWAE
¡P Construction of
OHVD at TS1
¡P Excavation for mined tunnel
¡P Construction of Diaphragm Wall and
Installation of King Post at TS2
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P Road works at
¡P Bored piling (Land)
¡P D-wall and Barrette Construction
¡P Construction works for Box Culvert T1
¡P Construction works for Culvert U1
¡P Construction of Pile cap (Land)
¡P Demolition of parapet at IEC Link
¡P Construction of dewatering well for Cut
& Cover Tunnel
¡P Construction of pile cap, column &
cross head (Marine)
¡P ELS for Cut & Cover Tunnel
¡P Laying of 1500 pipe
¡P Launching of segments
¡P Unloading segments from derrick
¡P Extraction of temporary pile from marine
section
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P Installation works of Precast Concrete
Box Unit
¡P Remaining works in box unit
(Installation of foam concrete)
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009/B
¡P Hoarding erection
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Surrendered |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Valid |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai
Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP was surrendered by the Contractor on 25 April 2013.
Contract no. 04/HY/2006 ¡V Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP was surrendered by the
Contractor on 11 February 2011.
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
3.1.5.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5
Table 3.4 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr
2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
06 Jan
2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling
equipment |
GW-RS-1293-12 |
10 Dec
2012 |
10 Dec
2012 to 9 June 2013 |
Expired |
GW-RS0166-13 |
14 Feb
2013 |
16 Feb
2013 to 13 Aug 2013 |
Valid |
|
GW-RS0310-13 |
25 Mar
2013 |
27 Mar
2013 to 25 Sept 2013 |
Valid |
|
GW-RE0274-13 |
26 Mar
2013 |
30 Mar
2013 to 29 Sept 2013 |
Valid |
|
GW-RS0274-13 |
19 Mar
2013 |
25 Mar
2013 to 24 Sep 2013 |
Valid |
|
GW-RS-0052-13 |
18 Jan
2013 |
20 Jan
2013 to 19 July 2013 |
Valid |
|
GW-RE-0371-13 |
9 Apr
2013 |
13 Apr
2013 to 12 Oct 2013 |
Valid |
|
GW-RE-0372-13 |
12 Apr
2013 |
15 Apr
2013 to 7 Oct 2013 |
Valid |
|
GW-RS0368-13 |
12 Apr
2013 |
15 Apr
2013 to 7 Oct 2013 |
Valid |
|
GW-RS1177-12 |
15 Nov
2012 |
17 Nov
2012 to10 May 2013 |
Expired |
|
GW-RS1184
-12 |
15 Nov
2012 |
17 Nov
2012 to 8 May 2013 |
Cancelled |
|
GW-RS1185-12 |
19 Nov
2012 |
21 Nov
2012 to 8 May 2013 |
Expired |
|
GW-RS1179-12 |
20 Nov
2012 |
22 Nov
2012 to 21 May 2013 |
Cancelled |
|
GW-RS1187-12 |
20 Nov
2012 |
27 Nov
2012 to 26 May 2013 |
Expired |
|
GW-RS1199-12 |
20 Nov
2012 |
26 Nov
2012 to 25 May 2013 |
Cancelled |
|
GW-RS0470-13 |
29 Apr
2013 |
9 May
2013 to 24 Oct 2013 |
Valid |
|
GW-RS0501-13 |
9 May
2013 |
11 May
2013 to 8 Nov 2013 |
Valid |
|
GW-RS0510-13 |
14 May
2013 |
15 May
2013 to 13 Nov 2013 |
Valid |
|
GW-RS0579-13 |
29 May
2013 |
29 May
2013 to 26 Nov 2013 |
Valid |
|
GW-RS0626-13 |
13 Jun
2013 |
15 Jun
2013 to 12 Dec 2013 |
Valid |
|
GW-RS0631-13 |
14 Jun
2013 |
14 Jun
2013 to 13 Dec 2013 |
Valid |
|
GW-RS0651-13 |
21 Jun
2013 |
22 Jun
2013 to 20 Dec 2013 |
Valid |
|
Discharge
Licence |
WT00009641-2011 |
24 Jul
2011 |
31 Jul
2016 |
Valid |
WT00006220-2010 |
18 Mar
2010 |
31 Mar 2015 |
Valid |
|
Billing account under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration
as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan
2010 |
N/A |
Valid |
Table 3.5 Summary of submission
status under FEP-02/364/2009
EP Condition |
Submission |
Date
of
Submission |
Special
Conditions, Clause 2.7 & 2.8 |
Works
Schedule and Location Plan |
18 May
2011 |
Special
Conditions, Clause 2.6 |
Environmental
Management Organization Chart |
18 May
2011 |
Special
Conditions, Clause 2.6 |
Commencement
Date of Works |
20 Jun 2011 |
Special
Conditions, Clause 2.9 |
Noise
Management Plan |
10
Jun 2011 |
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |