Contract No: HK/2011/07

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 2)

 

Environmental Permit no. EP-364/2009/B,

Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009/B

 

Monthly Environmental Monitoring & Audit Report

 

-  June 2013 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

12 July 2013


Table of contents         

 

EXECUTIVE SUMMARY. 4

1.     Introduction. 11

1.1        Scope of the Report 12

1.2        Structure of the Report 12

2.     Project Background. 14

2.1        Background. 14

2.2        Scope of the Project and Site Description. 14

2.3        Division of the Project Responsibility. 15

2.4        Project Organization and Contact Personnel 16

3.     status of regulatory compliance. 22

3.1        Status of Environmental Licensing and Permitting under the Project 23

4.     Monitoring Requirements. 35

4.1        Noise Monitoring. 36

4.2        Air Monitoring. 38

5.     Monitoring Results. 40

5.1        Noise Monitoring Results. 40

5.2        Real Time Noise Monitoring Results. 43

5.3        Air Monitoring Results. 44

5.4        Waste Monitoring Results. 46

6.     Compliance Audit. 50

6.1        Noise Monitoring. 50

6.2        Real Time Noise Monitoring. 50

6.3        Air Monitoring. 51

6.4        Review of the Reasons for and the Implications of Non-compliance. 51

6.5        Summary of action taken in the event of and follow-up on non-compliance. 52

7.     Cumulative Construction Impact due to the Concurrent Projects. 52

8.     Environmental Site Audit. 54

9.     Complaints, Notification of Summons and Prosecution. 47

10.    Conclusion. 60


lIST OF TABLES

 

Table 2.1      Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 3.1      Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.4      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.5      Summary of submission status under FEP-02/364/2009

Table 3.6      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.7      Summary of submission status under FEP-01/364/2009

Table 3.8      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/18

Table 3.9      Summary of submission status under FEP-05/364/2009/A

Table 3.10    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.11    Summary of submission status under FEP-06/364/2009/A

Table 3.12    Cumulative Summary of Valid License and Permits under Contract no. HY/2009/19

Table 3.13   Summary of submission status under FEP-07/364/2009/A

Table 3.14    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2010/06

Table 3.15    Summary of submission status under FEP-08/364/2009/B

Table 3.16    Cumulative Summary of Valid License and Permits under Contract no. HK/2012/08

Table 3.17    Summary of submission status under FEP-09/364/2009/B

Table 4.1      Noise Monitoring Stations

Table 4.2      Real Time Noise Monitoring Stations

Table 4.3      Air Monitoring Stations

Table 5.2      Noise Monitoring Stations for Contract no. HY/2009/18

Table 5.3      Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02

Table 5.4      Noise Monitoring Stations for Contract no. HY/2009/15

Table 5.5      Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.7      Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.9      Air Monitoring Stations for Contract no. HY/2009/18

Table 5.10    Air Monitoring Station for Contract no. HK/2009/01

Table 5.11    Air Monitoring Station for Contract no. HK/2009/02

Table 5.12    Air Monitoring Station for Contract no. HY/2009/15

Table 5.13    Air Monitoring Stations for Contract no. HY/2009/19

Table 5.15    Details of Waste Disposal for Contract no. HK/2009/01

Table 5.16    Details of Waste Disposal for Contract no. HK/2009/02

Table 5.17    Details of Waste Disposal for Contract no. HY/2009/18

Table 5.18    Details of Waste Disposal for Contract no. HY/2009/15

Table 5.19    Details of Waste Disposal for Contract no. HY/2009/19

Table 5.20    Details of Waste Disposal for Contract no. HK/2010/06

Table 5.21    Details of Waste Disposal for Contract no. HK/2012/08

Table 8.1      Summary of Environmental Inspections for Contract no. HY/2009/15

Table 8.2      Summary of Environmental Inspections for Contract no. HK/2009/18

Table 8.3      Summary of Environmental Inspections for Contract no. HK/2009/01

Table 8.4      Summary of Environmental Inspections for Contract no. HK/2009/02

Table 9.1      Cumulative Statistics on Complaints

Table 9.2      Cumulative Statistics on Successful Prosecutions

Table 10.1    Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

 

 

 

 

 

LIST OF FIGUREs

 

Figure 2.1              Project Layout

Figure 2.2              Project Organization Chart

Figure 4.1              Locations of Environmental Monitoring Stations

 

 

lIST OF APPENDIces

 

Appendix 3.1        Environmental Mitigation Implementation Schedule

Appendix 4.1        Action and Limit Level

Appendix 4.2        Copies of Calibration Certificates

Appendix 5.1        Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2        Noise Monitoring Results and Graphical Presentations

Appendix 5.3        Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4        Real-time Noise Monitoring Results and Graphical Presentations

Appendix 6.1        Event Action Plans

Appendix 6.2        Notification of Exceedance

Appendix 9.1        Complaint Log

Appendix 10.1      Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report ¡V June 2013 specific for Environmental Permit no. EP-364/2009/B, Further Environmental Permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009/B. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HK/2011/07 ¡V Wan Chai Development Phase II and Central Wanchai Bypass ¡V Sampling, Field Measurement and Testing Works (Stage 2). This report presents the environmental monitoring findings and information recorded during the period of June 2013. The cut-off date of reporting is at 27th of each reporting month.

 

  1. In the reporting month, the principal work activities of individual contracts are included as follows:

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A

¡P      Excavation of trial pit

¡P      Transplanting of trees

¡P      Hoarding erection and modification

¡P      Installation of couplers, UU detection, trial trench, pre-drilling

¡P      Excavation

¡P      Drainage works

¡P      Tunnel works

¡P      Trough structure construction and associated drilling and grouting

¡P      Road works

¡P      OHVD installation

¡P      Pre-bored H-piling

¡P      Bridges construction

¡P      Scaffolding / false-work erection

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

¡P      Pre-drilling works for CWB (Stage 2).

¡P      Diaphragm wall construction works at Stage 2 (North).

¡P      Temporary bulkhead wall construction works at CH3129 (between Stage2 / Stage3).

¡P      Pre-bored H piling works for CWB (Stage1b).

¡P      Excavation and grouting of Pre-bored H-pile.

¡P      Pre-bored H piling works for CWB (Stage2).

¡P      Installation of dewatering well at CWB (Stage 1 & 1b).

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

 

¡P      Base Slab for Tunnel Portion 1

¡P      Bored piles PN17 was concreted

¡P      Casting Base slab for silo setup

¡P      Desander setup and its mud pit construction for D-Wall construction at Tunnel Portion 2 Ground treatment for D-wall at WCR2 was commenced on 10 Jun 2013.

¡P      Backfilling works for pipe trenches and the road modification works along Wan Shing Street for HHR Flyover Diversion (Stage 1)

¡P      Casting of Base slab at Bay 4 of Box Culvert N.

¡P      Sheet pile cutting works at Bay5 / Bay 6 interface for subsequent construction of water plug beneath the installed precast unit (Bay 6)

¡P      Panel (BHC2) of Eastern Bulkhead Wall was concreted

¡P      Excavation for P129 and the remaining panel of Eastern Bulkhead Wall BHC12

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

¡P      ELS works and pipe roofing works at TS4

¡P      Cut and cover tunnel construction at TPCWAE

¡P      Construction of OHVD at TS1

¡P      Excavation for mined tunnel

¡P      Construction of Diaphragm Wall at TS2

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

¡P      Road works at Watson Road

¡P      Bored piling (Land)

¡P      D-wall and Barrette Construction

¡P      Construction works for Box Culvert T1

¡P      Construction works for Culvert U1

¡P      Construction of Pile cap (Land)

¡P      Demolition of parapet at IEC Link

¡P      Construction of dewatering well for Cut & Cover Tunnel

¡P      Removal of marine platform

¡P      Construction of pile cap, column & cross head (Marine)

¡P      ELS for Cut & Cover Tunnel

¡P      Laying of 1500 pipe

¡P      Launching of segments

¡P      Unloading segments from derrick

¡P      Extraction of temporary pile from marine section

 

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

¡P      Nil

 

 

 

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009B

¡P      Site preparation works

¡P      Site survey

¡P      Hoarding erection

 

Noise Monitoring

  1. Noise monitoring during daytime was conducted at M1a - Harbour Road Sports Center; M2b - Noon-day gun area; M3a - Tung Lo Wan Fire Station; M4b - Victoria Center; M5b - City Garden, M6 - HK Baptist Church Henrietta Secondary School, M7e and M7w ¡V International Finance Centre Eastern and Western End of Podium, and M8 - City Hall on a weekly basis.
  2. Due to adverse weather condition, the noise monitoring at the following stations were rescheduled:

M1a and M2b: From 11 June 2013 to 14 June 2013

M3a, M4b and M5b and M6: From 11 June 2013 to 13 June 2013

  1. No action and 2 limit level exceedances at M6 ¡V HK Baptist Church Henrietta Secondary School were recorded on3 and 13 June 2013 in this reporting month. The exceedances were concluded as non-project related.
  2. One action level exceedance regarding noise complaint concerning location near Central Pier area was received by ET on 11 June 2013. After investigation, no non-compliance was identified.
  3. 24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot for construction activities under IECL bridge deck. No project related exceedance was recorded in the reporting month.
  4. 24-hour real time noise monitoring was conducted at RTN2a ¡V Hong Kong Electric Centre. No project related exceedance was recorded in the reporting month.
  5. 24-hour real time noise monitoring was conducted at RTN3 ¡V Yu Lee Mo Fan Memorial School. No limit level exceedance was recorded in the reporting month.
  6. 24-hour real time noise monitoring was conducted at RTN4 ¡V Causeway Bay Community Centre. No limit level exceedance was recorded in the reporting month.
  7. As confirmed by CWB RSS, the IECL parapet removal operations will commence in May 2013.  Liaison was conducted with HK Baptist Church Henrietta Secondary School and Po Leung Kuk Yu Lee Mo Fan Memorial School regarding the set up of RTN3 real time noise monitoring station.  Po Leung Kuk Yu Lee Mo Fan Memorial School grant permission for set up on 4 Sep 2012 and station set up was performed on 14 Sep 2012.
  8. Real time noise monitoring station at Oil Street Community Liaison Centre (RTN2- Oil Street Community Centre) was relocated from Oil Street Community Liaison Centre to Hong Kong Electric (RTN2a- Electric Centre) on 5 Oct 2012 which is a representative of the noise sensitive receiver City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.
  9. Real-time noise baseline capturing was conducted from 21 Sep 2012 to 04 Oct 2012 at RTN3-Po Leung Kuk Yu Lee Mo Fan Memorial School.
  10. Real-time Noise Monitoring at RTN3- Po Leung Kuk Yu Lee Mo Fan Memorial School was commenced since 06 Oct 2012.
  11. Causeway Bay Community Centre has granted permission for set up of real time noise monitoring station on 21 Dec 2012 and station set up was performed on 27 Dec 2012.  The Baseline noise level of RTN4- Causeway Bay Community Centre will adopt the results from the baseline noise monitoring report for EP/364/2009 in 22 April 2010 in which approved by EPD.
  12. According to clause 3.1 stated in EP-364/2009B, ¡§the real-time monitoring system shall be in place no later than two weeks before the commencement date of demolition works of the existing Island Eastern Corridor¡¨. IEC demolition associated construction works was commenced on 3 Feb 2013 and Real time noise monitoring at RTN4-Causeway Bay Community Centre was commenced on 13 Jan 2013.
  13. Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with respect to the commencement of advance works for IEC parapet demolition.

 

Air Monitoring

  1. Due to extension of site boundary by contractor of HY/2009/19, location of air monitoring station CMA1b ¡V Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.
  2. The location ID of air monitoring station CMA1b was updated as Oil Street Site Office in April 2013.
  3. Due to the interruption of electricity supply, the 1hr TSP monitoring at CMA5a was rescheduled from 22 June 2013 to 24 and 25 June 2013.

24hr-TSP monitoring at CMA5a scheduled on 21 June 2013 was temporarily suspended due to continuous electricity power supply for 24hrs was unavailable.

1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b ¡V Oil Street Site Office; CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site Office Area; CMA4a ¡V Society for the Prevention of Cruelty to Animals; CMA5a - Children Garden opposite to Pedestrian Plaza; MA1e and MA1w ¡V International Finance Centre eastern and western wing on every six days basis.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. There were two environmental complaints received in this reporting month.
  2. One environmental complaint under EP-364/2009/B was received on 6 June 2013 (ICC Ref: No: #1-430164728 dated 30 May 2013) regarding landscape aspect along Man Kat Street in this reporting month. The complaint reported that a number of trees (approximately more than ten) along Man Kat Street were found to be in poor health condition with withered and yellow leaves. The complainant has requested a follow-up by relevant department. RSS confirmed that 13 no. of the trees - Roystonea regia (T1674, T1675, T1676, T1677, T1678, T1679, T1680, T1681, T1683, T1644, T1643, T1641, T1639) at the concerned location raised by the complainant was found to be with withered and yellow leaves and 1 no. of tree- Khaya senegalensis (T1712) raised by the complainant was found to be in poor health condition. In addition, No construction works was undertaken by Contract HY/2009/18 at the concerned planter area where the affected trees are located. It was also observed that an active CEDD construction works area under a separate contractor not related to Central Wan Chai Bypass Project was found to be located within the concerned planter area.

             A follow-up joint inspection with RSS and Landscape specialist was conducted on 10 June2013, it was considered that the withered and yellow leaves of the affected trees (T1674,T1675,T1676,T1677,T1678,T1679,T1680,T1681,T1683,T1644,T1643,T1641,T1639) at the concerned planter area were contributed by natural life cycle of the affected trees and the health condition of the affected trees were considered to be fair. It was also noted that an active CEDD works area was located within the concerned planter area in close proximity to few of the concerned trees (T1644, T1643, T1641, and T1639)

According to tree inspection records from Jan 2013 to May 2013 confirmed by RSS (Document Ref: CI-F1-043b, CI-F1-044b, CI-F1-045b, CI-F1-046b, CI-F1-047b), the affected tree (T1712) at the concerned planter area was considered to show sign of withering and considered to be in poor health condition in latest tree survey report confirmed by RSS.

During the follow-up inspection on 10 June 2013, it was observed those construction material and oil drums were placed near the roots area of other trees within the CEDD works. Despite the above observation, no direct evidence was found on site which indicates the work front have contributed to the poor health condition of the affected tree (T1712) at the time of investigation.

Nevertheless, regular inspection to check the health condition of the trees and regular removal of withered leaves or dead branches which deemed appropriate to maintain the overall tree appearance were implemented by the contractor.

xxiii.        One environmental complaint under EP-364//2009/B was received on 11 June 2013 (EPD Ref.:H04/RS/00011587-13) dated 11 June 2013) regarding noise impact near Central Piers in the reporting month.

The complaint reported that the noise was emanated from the construction site near the Central Piers at around 0900 hrs on 30 May 2013 and other days and requested follow up action by relevant department. RSS confirmed that major noise generating construction activities undertaken at works area near Central Pier during the concerned time include breaking up existing D-wall concrete and excavation at portion 4B, 4C and sheet pilling works at Portion VI (Man Kat Street)

Total 1 no. of Backhoe with breaker, 1 no. of Backhoe with vibratory hammer and 4 no.s of pneumatic breakers were deployed for the above construction activities.

Reviewing the noise monitoring data at monitoring stations (M7e- Internation Finance Centre Eastern End of Podium and M7w- International Finance Centre Western End of Podium), no limit level exceedances were recorded during routine noise monitoring event on 28 May 2013 and 03 June 2013. As similar construction works activities conducted on 30 May 2013 was continued across the above monitoring period, the noise emanated from the construction activities under Contract HY/2009/18 was considered complied with the statutory requirement.

In addition, weekly environmental site inspection was conducted on 30 May 2013 at around 10:00. According to the inspection record, no particular observation regarding noise impact was recorded and the mitigation measures including erection of temporary noise barrier was observed in place.

  1. Nevertheless, the contractor was recommended to review the need of additional noise mitigation measures to further reduce the noise emanated during construction works for pier side public area.

 

Site Inspections and Audit

  1. The Environmental Team (ET) conducted weekly site inspections for Contract no. HY/2009/15, HY/2009/18, HY/2009/19, HK/2009/01, HK/2009/02, HK/2012/08 and HK/2010/06 in this reporting period. Construction of bored pile E3B under HY/2009/17 was confirmed completed and the respective work area under FEP was inspected under HY/2009/19 from 19 Dec 2012 onwards. The Contractors rectified major observations and recommendations made during the audit sessions. No non-conformance was identified during the site inspections.

 

Future Key Issues

  1. In the coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

¡P      Excavation of trial pit

¡P      Transplanting of trees

¡P      Hoarding erection and modification

¡P      Installation of couplers, UU detection, trial trench, pre-drilling

¡P      Excavation

¡P      Drainage works

¡P      Tunnel works

¡P      Trough structure construction and associated drilling and grouting

¡P      Road works

¡P      OHVD installation

¡P      Bridges construction

¡P      Scaffolding / false-work erection

¡P      Profile barrier construction

 

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

¡P      Installation of pre-bored H-pile in CWB Stage 1B under the atrium link (from Ch80 to Ch220)

¡P      Installation of pre-bored H-pile in CWB Stage 1B under the atrium link (from Ch120 to Ch220)

¡P      Construction of bulkhead Wall at Ch3129

¡P      Demolition of the promenade deck and pumping stations at HKCEC Water Channel

¡P      Installation of dewatering well at CWB

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

¡P      Construction of Eastern Bulkhead wall.

¡P      Wall construction at Tunnel Portion 1.

¡P      D-Wall construction at Tunnel Portion 2.

¡P      Rock filling and leveling stone installation for seawall construction at both WCR4 & TWCR4.

¡P      Geotextile installation for temporary reclamation at TWCR4

¡P      Precast concrete seawall installation at WCR4 & TWCR4.

¡P      Continue backfilling and road reinstatement works at Hung Hing Road & Wan Shing Street for successful implementation of HHR Flyover Diversion (Stage 1)

¡P       Complete water plug construction works at Bay5/Bay6 interface and commence construction of Bay 5 Box Culvert N1.

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

¡P      ELS works and pipe roofing works at TS4

¡P      Cut and cover tunnel construction at TPCWAE

¡P      Construction of OHVD at TS1

¡P      Excavation for mined tunnel

¡P      Construction of Diaphragm Wall and Installation of King Post at TS2

 

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

¡P      Road works at Watson Road

¡P      Bored piling (Land)

¡P      D-wall and Barrette Construction

¡P      Construction works for Box Culvert T1

¡P      Construction works for Culvert U1

¡P      Construction of Pile cap (Land)

¡P      Demolition of parapet at IEC Link

¡P      Construction of dewatering well for Cut & Cover Tunnel

¡P      Removal of marine platform

¡P      Construction of pile cap, column & cross head (Marine)

¡P      ELS for Cut & Cover Tunnel

¡P      Laying of 1500f pipe

¡P      Launching of segments

¡P      Unloading segments from derrick

¡P      Extraction of temporary pile from marine section

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

¡P      Installation works of Precast Concrete Box Unit

¡P      Remaining works in box unit (Installation of foam concrete)

 

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B

¡P      Hoarding erection

 

 

 

 

 

1          Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009/B and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009/B to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/B, Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009B during the period May to June 2013. The cut-off date of reporting is at 27th of each reporting month

 

1.2          Structure of the Report

 

Section 1          Introduction ¡V details the scope and structure of the report.

 

Section 2          Project Background ¡V summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3          Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4          Monitoring Requirements ¡V summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5          Monitoring Results ¡V summarizes the monitoring results obtained in the reporting period.

 

Section 6          Compliance Audit ¡V summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7          Cumulative Construction Impact due to the Concurrent Projects ¡V summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8          Site Inspection ¡V summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9          Complaints, Notification of summons and Prosecution ¡V summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10        Conclusion

22    Project Background

2.1          Background

2.1.1.     ¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called ¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2          Scope of the Project and Site Description

2.2.1.     Design and Construction of Central ¡V Wan Chai Bypass and Island Eastern Corridor Link under the Project involves the construction and operation of a trunk road and its road tunnel more than 800m in length between portals that is shown at Figure 2.1.

2.2.2.     The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:

¡P      A dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);

¡P      The Central Interchange near the Rumsey Street Flyover to provide road connections to the Central area;

¡P      Tunnel control buildings and ventilation buildings;

¡P      Slip roads to connect the CWB to the local road system in the Wan Chai North and Causeway Bay area;

¡P      Associated road lighting, road signing, traffic control and surveillance system; and

¡P      Other associated works.

 

2.2.3.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3          Division of the Project Responsibility

2.3.1.     Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.     The details of individual contracts are summarized in Table2.2.

Table 2.2    Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HY/2009/17

Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works.

DP1

5 October 2010

HY/2009/18

Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange

DP1

21 April 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010 (Completed)

HK/2009/01

Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works

 

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East(CWB Tunnel)

DP1

26 April 2011

HY/2009/15

Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

DP1

13 July 2011

HY/2009/19

Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

HK/2012/08

Wan Chai Development Phase II- Central-Wan Chai Bypass at Wan Chai West

DP1,DP2, DP3

DP works under
EP-364 to be commenced tentatively in June 2013.

 

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer¡¦s Representative for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer¡¦s Representative for CWB

Principal Resident Engineer

Mr. Peter Poon

3922 3388

3912 3010

Lam Woo & CO., LTD.

Contractor under Contract no. HY/2009/17

General Manager

Mr. Thomas Tang

6111 5351

2566 7522

Contractor¡¦s Representative

Mr. Chung Man Shek

2566 4866

Site Agent

Mr. Tong Au

9725 5874

Environmental Officer

Dr. Priscilla Choy

9161 7287

Environmental Supervisor

Mr. Tam Chun Pong

6461 3062

Chun Wo ¡V Leader Joint Venture

Contractor under Contract no. HK/2009/01

Joint Venture Board Representative

Mr. PL Yue

2162 9909

2634 1626

Construction  Manager

Mr. Terry Wong

9757 9846

Deputy Site Agent

Mr. Andy Yu

9648 4896

Construction Manager

Mr. Wyman Wong

9627 2467

Construction Manager

Mr. Jack Chu

9775 2467

Environmental Officer (Compliance Manager)

Mr. Andy Mak

9103 2370

Environmental Supervisor

Mr. Kwong Weng Kit

6253 3356

Chun Wo ¡V CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Site Agent

Mr. Chan Sing Cho

3658-3002

2827 9996

Quality & Environmental Manager

(Environmental Officer)

Mr. C.P. Ho

3658-3000

Chun Wo - CRGL - MBEC Joint Venture

 

Contractor under Contract no. HY/2009/19

Project Manager

Mr. Rayland Lee

3758 8879

2570 8013

Site Agent

Mr. Paul Yu

9456 9819

Environmental Manager /

Environmental Officer

Mr. M.H. Isa

9884 0810

Environmental Engineer

Mr. Calvin Leung

9286 9208

Construction Manager (Marine)

Mr. William Luk

9610 1101

Construction Manager

(Land)

Mr. Patrick Cheung

9643 3012

Construction Manager

(Land)

Mr. Eric Fong

6191 9337

Operation Manager (Land)

Mr. Yung Kwok Wah

9834 1010

Leighton Contractors (Asia) Limited

Contractor under Contract no. HY/2009/18

Site Agent

Mr. Jimmy Chu

2214 7700

2140 6799

Deputy Site Agent

Mr. Roger Wong

2214 7703

Environmental Officer

Ms. Lighting Chan

2823 1161

Environmental Engineer

Mr. Donald Yip

2214 7721

Environmental Engineer Graduate

Mr. Phil Mak

2214 7738

Environmental Supervisor

Mr. K. P. Lai

6461 4660

Environmental Supervisor

Mr. Ray Cheng

2214 7742

Environmental Supervisor

Mr. K. W. Lee

6461 4623

Environmental Supervisor

Mr. Ryan Tsui

2214 7705

Environmental Supervisor

Mr. C. Y. Au Yeung

6461 8631

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Mr. K C Cheung

2823 7813

2865 5229

Site Manager

Mr. J.H. Chen

3557 6368

2566 2192

Contractor¡¦s Representative

Mr. Andrew Wong

3557 6407

Head of construction

Mr. Roger Cheung

3557 6371

Environmental Officer

Mr. Daniel Sin

3557 6215

Enviromental Supervisor

Ms. Esther Choi

35576348

Gammon -Leader JV

Contractor under Contract no. HK/2010/06

Project Manager

Mr. Paul Lui

9095 7922

2529 2880

Site Agent

Mr. Keith Tse

2529 2068

Environmental Officer

Mr. Clement Pang

9481 6024

Environmental Supervisor

Mr. Jacky Cheung

9735 9200

China State- Leader JV

Contractor under Contract no. HK/2012/08

Project Director

Mr. Andrew TSE

9137 1811

2877 1522

Project Manager

Mr. Victor WU

9193 8871

Deputy Project Manager

Mr. George CHEUNG

9268 1918

Site Agent

Mr. Paul LUI

9095 7922

Environmental Officer

Mr. James MA

9130 9549

Environmental Supervisor

Mr. Ching Man, CHAN

6050 4919

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3465 2888

3465 2899

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

2.4.3.     In this reporting month, the principal work activities of individual contracts are included as follows:

 

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

¡P      Excavation of trial pit

¡P      Transplanting of trees

¡P      Hoarding erection and modification

¡P      Installation of couplers, UU detection, trial trench, pre-drilling

¡P      Excavation

¡P      Drainage works

¡P      Tunnel works

¡P      Trough structure construction and associated drilling and grouting

¡P      Road works

¡P      OHVD installation

¡P      Pre-bored H-piling

¡P      Bridges construction

¡P      Scaffolding / false-work erection

 

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

¡P      Pre-drilling works for CWB (Stage 2).

¡P      Diaphragm wall construction works at Stage 2 (North).

¡P      Temporary bulkhead wall construction works at CH3129 (between Stage2 / Stage3).

¡P      Pre-bored H piling works for CWB (Stage1b).

¡P      Excavation and grouting of Pre-bored H-pile.

¡P      Pre-bored H piling works for CWB (Stage2).

¡P      Installation of dewatering well at CWB (Stage 1 & 1b).

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

¡P      Base Slab for Tunnel Portion 1

¡P      Bored piles PN17 was concreted

¡P      Casting Base slab for silo setup

¡P      Desander setup and its mud pit construction for D-Wall construction at Tunnel Portion 2 Ground treatment for D-wall at WCR2 was commenced on 10 Jun 2013.

¡P      Backfilling works for pipe trenches and the road modification works along Wan Shing Street for HHR Flyover Diversion (Stage 1)

¡P      Casting of Base slab at Bay 4 of Box Culvert N.

¡P      Sheet pile cutting works at Bay5 / Bay 6 interface for subsequent construction of water plug beneath the installed precast unit (Bay 6)

¡P      Panel (BHC2) of Eastern Bulkhead Wall was concreted

¡P      Excavation for P129 and the remaining panel of Eastern Bulkhead Wall BHC12

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

¡P      ELS works and pipe roofing works at TS4

¡P      Cut and cover tunnel construction at TPCWAE

¡P      Construction of OHVD at TS1

¡P      Excavation for mined tunnel

¡P      Construction of Diaphragm Wall at TS2

 

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

¡P      Road works at Watson Road

¡P      Bored piling (Land)

¡P      D-wall and Barrette Construction

¡P      Construction works for Box Culvert T1

¡P      Construction works for Culvert U1

¡P      Construction of Pile cap (Land)

¡P      Demolition of parapet at IEC Link

¡P      Construction of dewatering well for Cut & Cover Tunnel

¡P      Removal of marine platform

¡P      Construction of pile cap, column & cross head (Marine)

¡P      ELS for Cut & Cover Tunnel

¡P      Laying of 1500 pipe

¡P      Launching of segments

¡P      Unloading segments from derrick

¡P      Extraction of temporary pile from marine section

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

¡P      Nil

 

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B

¡P      Site preparation works

¡P      Site survey

¡P      Hoarding erection

 

 

 

 

 

 

 

 

 

 

2.4.4.     In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A

¡P      Excavation of trial pit

¡P      Transplanting of trees

¡P      Hoarding erection and modification

¡P      Installation of couplers, UU detection, trial trench, pre-drilling

¡P      Excavation

¡P      Drainage works

¡P      Tunnel works

¡P      Trough structure construction and associated drilling and grouting

¡P      Road works

¡P      OHVD installation

¡P      Bridges construction

¡P      Scaffolding / false-work erection

¡P      Profile barrier construction

 

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

¡P      Installation of pre-bored H-pile in CWB Stage 1B under the atrium link (from Ch80 to Ch220)

¡P      Installation of pre-bored H-pile in CWB Stage 1B under the atrium link (from Ch120 to Ch220)

¡P      Construction of bulkhead Wall at Ch3129

¡P      Demolition of the promenade deck and pumping stations at HKCEC Water Channel

¡P      Installation of dewatering well at CWB

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

¡P      Construction of Eastern Bulkhead wall.

¡P      Wall construction at Tunnel Portion 1.

¡P      D-Wall construction at Tunnel Portion 2.

¡P      Rock filling and leveling stone installation for seawall construction at both WCR4 & TWCR4.

¡P      Geotextile installation for temporary reclamation at TWCR4

¡P      Precast concrete seawall installation at WCR4 & TWCR4.

¡P      Continue backfilling and road reinstatement works at Hung Hing Road & Wan Shing Street for successful implementation of HHR Flyover Diversion (Stage 1)

¡P       Complete water plug construction works at Bay5/Bay6 interface and commence construction of Bay 5 Box Culvert N1.

 

Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

¡P      ELS works and pipe roofing works at TS4

¡P      Cut and cover tunnel construction at TPCWAE

¡P      Construction of OHVD at TS1

¡P      Excavation for mined tunnel

¡P      Construction of Diaphragm Wall and Installation of King Post at TS2

 

Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

¡P      Road works at Watson Road

¡P      Bored piling (Land)

¡P      D-wall and Barrette Construction

¡P      Construction works for Box Culvert T1

¡P      Construction works for Culvert U1

¡P      Construction of Pile cap (Land)

¡P      Demolition of parapet at IEC Link

¡P      Construction of dewatering well for Cut & Cover Tunnel

¡P      Construction of pile cap, column & cross head (Marine)

¡P      ELS for Cut & Cover Tunnel

¡P      Laying of 1500 pipe

¡P      Launching of segments

¡P      Unloading segments from derrick

¡P      Extraction of temporary pile from marine section

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

¡P      Installation works of Precast Concrete Box Unit

¡P      Remaining works in box unit (Installation of foam concrete)

 

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B

¡P      Hoarding erection

                                                                                               

3          status of regulatory compliance

3.1          Status of Environmental Licensing and Permitting under the Project

 

3.1.1.     A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1    Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

Superseded

Environmental Permit

EP-364/2009/A

4 Aug 2010

Superseded

Environmental Permit

EP-364/2009/B

20 Sep 2012

Valid

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Surrendered

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

15 Nov 2010

Valid

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 July 2010

Surrendered

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Surrendered

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

Valid

Further Environmental Permit

FEP-08/364/2009/A

15 June 2012

Valid

Further Environmental Permit

FEP-09/364/2009/B

5 March 2013

Valid

 

3.1.2.     Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:


Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009

3.1.3.     The construction works was completed and the FEP was surrendered by the Contractor on 25 April 2013.

Contract no. 04/HY/2006 ¡V Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

3.1.4.     The construction works was completed, and the FEP was surrendered by the Contractor on 11 February 2011.

Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009

3.1.5.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5


Table 3.4    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

                 Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

N/A

Valid

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088

06 Jan 2010

N/A

Valid

Construction Noise Permit (CNP) for non-pilling equipment

GW-RS-1293-12

10 Dec 2012

10 Dec 2012 to 9 June 2013

Expired

GW-RS0166-13

14 Feb 2013

16 Feb 2013 to 13 Aug 2013

Valid

GW-RS0310-13

25 Mar 2013

27 Mar 2013 to 25 Sept 2013

Valid

GW-RE0274-13

26 Mar 2013

30 Mar 2013 to 29 Sept 2013

Valid

GW-RS0274-13

19 Mar 2013

25 Mar 2013 to 24 Sep 2013

Valid

GW-RS-0052-13

18 Jan 2013

20 Jan 2013 to 19 July 2013

Valid

GW-RE-0371-13

9 Apr 2013

13 Apr 2013 to 12 Oct 2013

Valid

GW-RE-0372-13

12 Apr 2013

15 Apr 2013 to 7 Oct 2013

Valid

GW-RS0368-13

12 Apr 2013

15 Apr 2013 to 7 Oct 2013

Valid

GW-RS1177-12

15 Nov 2012

17 Nov 2012 to10 May 2013

Expired

GW-RS1184 -12

15 Nov 2012

17 Nov 2012 to 8 May 2013

Cancelled

GW-RS1185-12

19 Nov 2012

21 Nov 2012 to 8 May 2013

Expired

GW-RS1179-12

20 Nov 2012

22 Nov 2012 to 21 May 2013

Cancelled

GW-RS1187-12

20 Nov 2012

27 Nov 2012 to 26 May 2013

Expired

GW-RS1199-12

20 Nov 2012

26 Nov 2012 to 25 May 2013

Cancelled

GW-RS0470-13

29 Apr 2013

9 May 2013 to 24 Oct 2013

Valid

GW-RS0501-13

9 May 2013

11 May 2013 to 8 Nov 2013

Valid

GW-RS0510-13

14 May 2013

15 May 2013 to 13 Nov 2013

Valid

GW-RS0579-13

29 May 2013

29 May 2013 to 26 Nov 2013

Valid

GW-RS0626-13

13 Jun 2013

15 Jun 2013 to 12 Dec 2013

Valid

GW-RS0631-13

14 Jun 2013

14 Jun 2013 to 13 Dec 2013

Valid

GW-RS0651-13

21 Jun 2013

22 Jun 2013 to 20 Dec 2013

Valid

Discharge Licence

WT00009641-2011

24 Jul 2011

31 Jul 2016

Valid

WT00006220-2010

18 Mar 2010

31 Mar 2015

Valid

Billing account under Waste Disposal Ordinance

7010069

21 Jan 2010

N/A

Valid

Registration as a Chemical Waste Producer

WPN5213-134-C3585-01

21 Jan 2010

N/A

Valid

 

 

Table 3.5    Summary of submission status under FEP-02/364/2009

EP Condition

Submission

Date of Submission

Special Conditions, Clause 2.7 & 2.8

Works Schedule and Location Plan

18 May 2011

Special Conditions, Clause 2.6

Environmental Management Organization Chart

18 May 2011

Special Conditions, Clause 2.6

Commencement Date of Works

20 Jun 2011

Special Conditions, Clause 2.9

Noise Management Plan

10 Jun 2011

 

 

 

 

 

 

Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

3.1.6.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.

Table 3.6    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

N/A

Valid

FEP-01/364/2009

24 Mar 2010

N/A

Valid

Notification of Works Under APCO

313962

2 Feb 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment