Contract No: HK/2011/07

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 2)

 

Environmental Permit no. EP-364/2009/B,

Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/A, FEP-08/364/2009/A, FEP-09/364/2009/B and FEP-10/364/2009/B

 

Monthly Environmental Monitoring & Audit Report

 

-  December 2013 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

 

11 January 2014


Table of contents         

 

EXECUTIVE SUMMARY. 4

1.     Introduction. 11

1.1        Scope of the Report 13

1.2        Structure of the Report 13

2.     Project Background. 15

2.1        Background. 15

2.2        Scope of the Project and Site Description. 15

2.3        Division of the Project Responsibility. 16

2.4        Project Organization and Contact Personnel 17

3.     status of regulatory compliance. 23

3.1        Status of Environmental Licensing and Permitting under the Project 26

4.     Monitoring Requirements. 38

4.1        Noise Monitoring. 40

4.2        Air Monitoring. 42

5.     Monitoring Results. 44

5.1        Noise Monitoring Results. 44

5.2        Real Time Noise Monitoring Results. 47

5.3        Air Monitoring Results. 48

5.4        Waste Monitoring Results. 51

6.     Compliance Audit. 56

6.1        Noise Monitoring. 56

6.2        Real Time Noise Monitoring. 56

6.3        Air Monitoring. 57

6.4        Review of the Reasons for and the Implications of Non-compliance. 57

6.5        Summary of action taken in the event of and follow-up on non-compliance. 57

7.     Cumulative Construction Impact due to the Concurrent Projects. 58

8.     Environmental Site Audit. 60

9.     Complaints, Notification of Summons and Prosecution. 47

10.    Conclusion. 66


lIST OF TABLES

 

Table 2.1      Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 3.1      Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.4      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.5      Summary of submission status under FEP-02/364/2009

Table 3.6      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.7      Summary of submission status under FEP-01/364/2009

Table 3.8      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/18

Table 3.9      Summary of submission status under FEP-05/364/2009/A

Table 3.10    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.11    Summary of submission status under FEP-06/364/2009/A

Table 3.12    Cumulative Summary of Valid License and Permits under Contract no. HY/2009/19

Table 3.13   Summary of submission status under FEP-07/364/2009/A

Table 3.14    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2010/06

Table 3.15    Summary of submission status under FEP-08/364/2009/B

Table 3.16    Cumulative Summary of Valid License and Permits under Contract no. HK/2012/08

Table 3.17    Summary of submission status under FEP-09/364/2009/B

Table 3.18    Cumulative Summary of Valid License and Permits under Contract no. HY/2010/08

Table 3.19   Summary of submission status under FEP-10/364/2009/B

Table 4.1      Noise Monitoring Stations

Table 4.2      Real Time Noise Monitoring Stations

Table 4.3      Air Monitoring Stations

Table 5.1      Noise Monitoring Stations for Contract no. HY/2009/18

Table 5.2      Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02

Table 5.3      Noise Monitoring Stations for Contract no. HY/2009/15

Table 5.4      Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.5      Noise Monitoring Stations for Contract no. HY/2010/08

Table 5.7      Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.9      Air Monitoring Stations for Contract no. HY/2009/18

Table 5.10    Air Monitoring Station for Contract no. HK/2009/01

Table 5.11    Air Monitoring Station for Contract no. HK/2009/02

Table 5.12    Air Monitoring Station for Contract no. HY/2009/15

Table 5.13    Air Monitoring Stations for Contract no. HY/2009/19

Table 5.15    Details of Waste Disposal for Contract no. HK/2009/01

Table 5.16    Details of Waste Disposal for Contract no. HK/2009/02

Table 5.17    Details of Waste Disposal for Contract no. HY/2009/18

Table 5.18    Details of Waste Disposal for Contract no. HY/2009/15

Table 5.19    Details of Waste Disposal for Contract no. HY/2009/19

Table 5.20    Details of Waste Disposal for Contract no. HK/2010/06

Table 5.21    Details of Waste Disposal for Contract no. HK/2012/08

Table 5.22    Details of Waste Disposal for Contract no. HY/2010/08

Table 8.1      Summary of Environmental Inspections for Contract no. HY/2009/15

Table 8.2      Summary of Environmental Inspections for Contract no. HK/2009/18

Table 8.4     Summary of Environmental Inspections for Contract no. HK/2009/01

Table 8.5     Summary of Environmental Inspections for Contract no. HK/2009/02

Table 8.6     Summary of Environmental Inspections for Contract no. HK/2012/08

Table 8.7     Summary of Environmental Inspections for Contract no. HY/2010/08

Table 9.1      Cumulative Statistics on Complaints

Table 9.2      Cumulative Statistics on Successful Prosecutions

Table 10.1    Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

 

LIST OF FIGUREs

 

Figure 2.1              Project Layout

Figure 2.2              Project Organization Chart

Figure 4.1              Locations of Environmental Monitoring Stations

 

 

lIST OF APPENDIces

 

Appendix 3.1        Environmental Mitigation Implementation Schedule

Appendix 4.1        Action and Limit Level

Appendix 4.2        Copies of Calibration Certificates

Appendix 5.1        Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2        Noise Monitoring Results and Graphical Presentations

Appendix 5.3        Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4        Real-time Noise Monitoring Results and Graphical Presentations

Appendix 6.1        Event Action Plans

Appendix 6.2        Notification of Exceedance

Appendix 9.1        Complaint Log

Appendix 10.1      Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report ˇV December 2013 specific for Environmental Permit no. EP-364/2009/B, Further Environmental Permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009/B. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HK/2011/07 ˇV Wan Chai Development Phase II and Central Wanchai Bypass ˇV Sampling, Field Measurement and Testing Works (Stage 2). This report presents the environmental monitoring findings and information recorded during the period of December 2013. The cut-off date of reporting is at 27th of each reporting month.

 

  1. In the reporting month, the principal work activities of individual contracts are included as follows:

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A

ˇP          Excavation of trial pit

ˇP          Transplanting of trees

ˇP          Drainage works

ˇP          Tunnel works including scaffolding erection, excavation, OHVD installation, roadside barriers, top and base slab construction

ˇP          Trough structure construction and associated drilling and grouting

ˇP          Road works

ˇP          Bridges construction

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

ˇP          Installation of pre-bored H-pile in CWB Stage 2 Atrium Link

ˇP          Installation of pre-bored H-pile in CWB Stage 3 Atrium Link

ˇP          Construction of the Common D-wall

ˇP          Backfilling of Temporary Water Channel & Reclaim Land at CH220 ˇV CH260

ˇP          Installation of sheet pile for demolition of P5 Pump house

ˇP          Installation of ELS at first layer for Stage 1.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

ˇP          S4 ELS removal Stage 2 (Bay 7 to Bay 8). Infill concrete was subsequently removed.

ˇP          S4 ELS removal Stage 3 (Bay 1 to Bay 4). Infill concrete was subsequently removed.

ˇP          Construction of OHVD base slab at Eastbound and upper side wall at Westbound

ˇP          Eastbound OHVD base slab Bay 4 between CH3555 and CH3577. Its hanger wall was subsequently casted.

ˇP          Eastbound OHVD base slab Bay 5 between CH3577 and CH3597 was casted

ˇP          Westbound upper side wall Bay 5 between CH3565 and CH3584 was casted

ˇP          For Eastbound, scaffolding erection for OHVD base slab construction from CH3550 westwards. Scaffolding erection for OHVD base slab construction between CH3597 and CH3630. Formwork erection and rebar fixing from CH3597 eastwards.

ˇP          For Westbound, temporary platform for upper side wall construction. Formwork erection and rebar fixing from CH3584 eastwards.

ˇP          Grouting works for completed D-Wall and bored piles.

ˇP          Partial demolition of Box Culvert O Bay 13 & Bay 14 for D-Wall construction was commenced.

ˇP          Pre-drilling works at WCR4/TWCR4 area, Hung Hing Road slow lane and for bridge 3 of Hung Hing Road flyover diversion stage 2.

ˇP          Bored Pile Nos. F01 and PS39 were casted. Installation of Bored Pile Nos. PN31and PC33 were commenced.

ˇP          Existing underground utilities between boundary wall of DSD Wanchai East Sewage Screening Plant and Hung Hing Road Flyover was being identified and exposed.

ˇP          Ground treatment and guide wall for D-Wall construction for Tunnel Portion 6

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ˇV Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

ˇP          ELS works, water proofing and tunnel construction at TS4

ˇP          Cut and cover tunnel construction at TPCWAE

ˇP          Excavation, installation of steel ribs and tunnel lining construction for mined tunnel

ˇP          ELS works at TS2

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

ˇP      Road works at Watson Road

ˇP      Bored piling (Land)

ˇP      Removal of strut at ELS will commence

ˇP      Construction works for Box Culvert T1

ˇP      Construction of Pile cap (Land)

ˇP      Removal of marine platform

ˇP      Construction of pile cap, pier & cross head (Marine)

ˇP      ELS, EVB and Cut & Cover Tunnel

ˇP      Installation of dewatering well

ˇP      Laying of 1500 pipe

ˇP      Launching of segments

ˇP      Extraction of temporary pile from marine section

ˇP      Construction of bridge truss TA1

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

ˇP      Stitching Works

ˇP      Grouting Works

 

Contract no. HK/2012/08 ˇV Wan Chai Development Phase II ˇV Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009B

ˇP      Site preparation works

ˇP      Site survey

 

Contract no. HY/2010/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel (Slip Road 8) under FEP-10/364/2009B

ˇP      Tree pruning works

ˇP      Tree removal works,

ˇP      Tree transplanting works,

ˇP      Tree works within off-site nursery compound,

ˇP      Sheet piling works,

ˇP      Demarcation of graphics,

ˇP      Pipe pile & pre-boring works, &

ˇP      Re-provisional of turtle pond.

 

Noise Monitoring

  1. Noise monitoring during daytime was conducted at M1a - Harbour Road Sports Center; M2b - Noon-day gun area; M3a - Tung Lo Wan Fire Station; M4b - Victoria Center; M5b - City Garden, M6 - HK Baptist Church Henrietta Secondary School, M7e and M7w ˇV International Finance Centre Eastern and Western End of Podium, and M8 - City Hall on a weekly basis.
  2. Due to adverse weather condition, noise monitoring at station M2b, M3a, M4b and M6 was rescheduled from 16 Dec 2013 to 18 Dec 2013 and monitoring at station M1a, M7e, M7w and M8 was rescheduled from 16 Dec 2013 to 19 Dec 2013.
  3. No action and 2 limit level exceedances at M6 ˇV HK Baptist Church Henrietta Secondary School were recorded on 10 and 18 December 2013 in this reporting month. The exceedances were concluded as non-project related.
  4. 24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot for construction activities at IEC bridge deck. No limit level exceedance was recorded in the reporting month.
  5. 24-hour real time noise monitoring was conducted at RTN2a ˇV Hong Kong Electric Centre. No project related exceedance was recorded in the reporting month.
  6. 24-hour real time noise monitoring was conducted at RTN3 ˇV Yu Lee Mo Fan Memorial School. No limit level exceedance was recorded in the reporting month.
  7. 24-hour real time noise monitoring was conducted at RTN4 ˇV Causeway Bay Community Centre. No limit level exceedance was recorded in the reporting month.
  8. Liaison was conducted with HK Baptist Church Henrietta Secondary School and Po Leung Kuk Yu Lee Mo Fan Memorial School regarding the set up of RTN3 real time noise monitoring station.  Po Leung Kuk Yu Lee Mo Fan Memorial School grant permission for set up on 4 Sep 2012 and station set up was performed on 14 Sep 2012.
  9. Real time noise monitoring station at Oil Street Community Liaison Centre (RTN2- Oil Street Community Centre) was relocated from Oil Street Community Liaison Centre to Hong Kong Electric (RTN2a- Electric Centre) on 5 Oct 2012 which is a representative of the noise sensitive receiver City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.
  10. Real-time noise baseline capturing was conducted from 21 Sep 2012 to 04 Oct 2012 at RTN3-Po Leung Kuk Yu Lee Mo Fan Memorial School.
  11. Real-time Noise Monitoring at RTN3- Po Leung Kuk Yu Lee Mo Fan Memorial School was commenced since 06 Oct 2012.
  12. Causeway Bay Community Centre has granted permission for set up of real time noise monitoring station on 21 Dec 2012 and station set up was performed on 27 Dec 2012.  The Baseline noise level of RTN4- Causeway Bay Community Centre will adopt the results from the baseline noise monitoring report for EP/364/2009 in 22 April 2010 in which approved by EPD.
  13. According to clause 3.1 stated in EP-364/2009/B, ˇ§the real-time monitoring system shall be in place no later than two weeks before the commencement date of demolition works of the existing Island Eastern Corridorˇ¨. IEC demolition associated construction works was commenced on 3 Feb 2013 and Real time noise monitoring at RTN4-Causeway Bay Community Centre was commenced on 13 Jan 2013.
  14. Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with respect to the commencement of advance works for IEC parapet demolition.

 

Air Monitoring

  1. Due to extension of site boundary by contractor of HY/2009/19, location of air monitoring station CMA1b ˇV Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.
  2. The location ID of air monitoring station CMA1b was updated as Oil Street Site Office in April 2013.

 xix.        Due to electricity interruption, the 24hr TSP monitoring at CMA2a was rescheduled from 23 December 2013 to 24 December 2013.

  1. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b ˇV Oil Street Site Office; CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site Office Area; CMA4a ˇV Society for the Prevention of Cruelty to Animals; CMA5a - Children Garden opposite to Pedestrian Plaza; MA1e and MA1w ˇV International Finance Centre eastern and western podium on every six days basis.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. Two environmental complaints under FEP-05/364/2009/B were received in the reporting period.
  2. A public complaint regarding water quality impact referred by RSS was received by ET on 17 December 2013 (ICC Case Ref.: 1-484998552 dated 17 December 2013). The complainant reported that workers of construction site HY/2010/08 were sweeping muddy water into the rain water drain and concerned about resulting pollution of habour. The complainant further follow-up and reported on 19 Dec 2013 that sandbags were placed out in the public area around the drain, these bags were outside of the site area and all preventive measures should have been carried out within the site. ET confirmed with the Resident Site Staff that the major construction activities around the concerned location conducted on 16 Dec 2013 a.m. include preparation work of root ball for tree transplanting.

 

According to the information provided by RSS, the construction activities around the concerned location on 16 Dec 2013 include preparation work of root ball for tree transplanting at Zone 17/18.

 

A further investigation on the complaint was conducted on 19 Dec 2013 during weekly environmental inspection. It was observed that a tree works area comprised of mainly loosen

soil was located near the concerned location. It was considered that the inclined surface and

loosen soil nature of the concerned works area could have led to the muddy surface runoff in rain. Deposition of muddy runoff onto nearby public pavement outside works area was hence resulted and was subsequently cleaned into nearby public stormwater drain by the Contractorˇ¦s workers on the complaint date. As such, the case was considered as works related. Sandbags, geotextile and gravels were immediately placed by the Contractor around the gullies at the concerned location to prevent leftover muddy runoff to the public stormwater drain as observed during the weekly inspection on 19 Dec 2013.

 

With respect to the follow-up raised by the complainant on 19 Dec 2013, sandbags, geotextile and gravels placed at gullies located at public area were removed by the Contractor on the same day for maintaining passable public pavement. Follow up measures including sandbag bundle and covering of works area with impervious sheeting was immediately placed at the source of impact at the concerned works area boundary by the Contractor.

 

  1. A public complaint regarding air quality impact referred by RSS was received by ET on 24 December 2013 (ICC Case Ref.: 1-486434321 dated 24 December 2013). The complainant reported that the equipment used at the construction area next to Victoria Park Children Playground has generated a strong odour and large amount of dust particles which affect the public user of the Victoria Park. Upon further inquiry by ICC operator, the complainant further supplemented on 31 Dec 2013 that, he was annoyed by the smell and exhaust fumes emitted from machines/tools as well as dusty particles in the vicinity when he was sitting next to the toilet and Children Playground on the complaint date at about 1140 hrs.

 

ET confirmed with the Resident Site Staff that the major construction activities around the concerned location conducted on 24 Dec 2013 include breaking up existing pillar box for new children playground Portion II, pressing of sheet pile at bowling green for ELS works Portion XII, welding work for preparation of sheet piling work at bowling green Portion VI, Demolition of existing pavilion for bowling green Portion VI and felling of tree TA50 at Victoria Park Zone 13. Mitigation measures implemented by the Contractor for the above construction works include water spraying for demolition and other dust generating works.

 

According to the relevant site records, breaking up of existing pillar box, pressing of sheet pile, welding work for preparation of sheet piling, demolition of existing pavilion and felling of tree TA50 at Victoria Park Zone 13 were conducted at the concerned location during the time of complaint. Based on information and photo record provided by the RSS, dust mitigation measures including water spraying during dust generating works were implemented by the Contractor at the concerned location on 24 Dec 2013.

Follow-up investigation was conducted on 27 Dec 2013 during weekly environmental inspection, dust mitigation measures including water spraying to dusty area and major dust generation works were confirmed in place despite a general reminder was given to the contractor to enhance the water spraying to dusty haul road during dry season. Based on on-going site inspection and the follow-up investigation, the site condition was considered generally satisfactory and no non-conformance was identified.

 

Upon further review on the supplementary information provided by the complainant on 31 Dec 2013 and investigation conducted on 2 Jan 2014, the tree felling work of tree TA50 was located nearest to the location of the complainant. According to the location plan provided by the RSS and on site investigation, the tree felling work for TA50 was immediately in front of the location of the complainant. Based on site observation, scrap material of bark and leaves inevitably generated from cutting of branches during tree felling work was considered to be the most probable cause for the observation raised by the complainant at the concerned location on 24 Dec 2013.Furthermore, welding work was observed near the concerned location and was considered to be the potential source for the smell and exhaust fumes as described by the complainant. Notwithstanding the above, welding work was not identified as a work activity with air quality impact under Project EIA report but it would be desirable to implement preventive measures to minimize potential nuisance to nearby public.

 

Site Inspections and Audit

  1. The Environmental Team (ET) conducted weekly site inspections for Contract no. HY/2009/15, HY/2009/18, HY/2009/19, HY/2010/08, HK/2009/01, HK/2009/02, HK/2012/08 and HK/2010/06 in this reporting period. Construction of bored pile E3B under HY/2009/17 was confirmed completed and the respective work area under FEP was inspected under HY/2009/19 from 19 Dec 2012 onwards. The Contractors rectified major observations and recommendations made during the audit sessions. No non-conformance was identified during the site inspections.

 

 

 

 

 

 

 

 

 

Future Key Issues

  1. In the coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HY/2009/18 ˇV Central ˇV Wan Chai Bypass (CWB) ˇV Central Interchange under FEP-05/364/2009/A

ˇP          Excavation of trial pit

ˇP          Drainage works

ˇP          Tunnel works including scaffolding erection, excavation, OHVD installation, roadside barriers, top and base slab construction, extract sheet pile, waterproofing and backfill

ˇP          Trough structure construction and associated drilling and grouting

ˇP          Road works

ˇP          Bridges construction

 

Contract no. HK/2009/01 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ˇV Tunnel Works under FEP-02/364/2009

ˇP          Stage 3 tunnel works including installation of pre-bored H-pile and stage 3 Southern D-wall Construction.

ˇP          Demolition of the HKCEC Pump house was anticipated.

ˇP          ELS for Stage 1 CWB

ˇP          Backfilling Temporary Water Channel & Reclaim Land at CH220-CH260.

 

Contract no. HK/2009/02 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

ˇP          Completed S4 ELS removal.

ˇP          Falsework erection and waterproofing installation and commence rebar fixing for OHVD base slab construction at Tunnel Portion 1.

ˇP          Upper wall construction at Southern Side Wall Bay 3 to Bay 7.

ˇP          OHVD base slab construction at Tunnel Portion 1.

ˇP          Pre-drilling at Hung Hing Road slow line and WCR4/TWCR4.

ˇP          Bored pile construction (Stage 2) at Tunnel Portion 3 & 4 for areas at WCR4/TWCR4 and original slow lane of Hung Hing Road.

ˇP          Partial demolition of Box Culvert O Bay 13 & Bay 14 and commence mini-piling works for bridge 3 foundation of Stage 2 TTA diversion.

ˇP          D-Wall construction at Tunnel Portion 6 (Site under possession by HK/2009/01 contractor).

 

 

 

 

 

 

 

Contract no. HY/2009/15 ˇV Central-Wanchai Bypass ˇV Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

ˇP      Breaking of temporary bulkhead between TS1 and TS2

ˇP      Construction of binding layer, Tunnel construction  at TS2

ˇP      Tunnel construction and dismantling of struts at TS4 & TPCWAE

ˇP      Mined Tunnel drill-and-break works and installation of steel ribs at East and West

Portal

ˇP      Mined tunnel lining construction

 

Contract no. HY/2009/19 ˇV Central ˇV Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

ˇP      Road works at Watson Road

ˇP      Bored piling (Land)

ˇP      Removal of strut at ELS will commence

ˇP      Construction works for Box Culvert T1

ˇP      Construction of Pile cap (Land)

ˇP      Removal of marine platform

ˇP      Construction of pile cap, pier & cross head (Marine)

ˇP      ELS, EVB and Cut & Cover Tunnel

ˇP      Installation of dewatering well

ˇP      Laying of 1500 pipe

ˇP      Launching of segments

ˇP      Extraction of temporary pile from marine section

ˇP      Construction of bridge truss TA1

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

ˇP      Stitching Works

ˇP      Grouting Works

ˇP      Repair and Installation of Slotted Panels

ˇP      In-Filling works

 

Contract no. HK/2012/08 ˇV Wan Chai Development Phase II ˇV Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B

ˇP          Site preparation works

ˇP          Site survey

 

 

 

 

 

 

 

 

 

Contract no. HY/2010/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel (Slip Road 8) under FEP-10/364/2009B

ˇP      Tree pruning works

ˇP      Tree removal works,

ˇP      Tree transplanting works,

ˇP      Tree works within off-site nursery compound,

ˇP      Sheet piling works,

ˇP      Demarcation of graphics,

ˇP      Pipe pile & pre-boring works, &

ˇP      Re-provisional of turtle pond.

1          Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009/B and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009/B to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and ˇ§Environmental Monitoring and Audit Requirementsˇ¨ under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/B, Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009B during the period November to December 2013. The cut-off date of reporting is at 27th of each reporting month

 

1.2          Structure of the Report

 

Section 1          Introduction ˇV details the scope and structure of the report.

 

Section 2          Project Background ˇV summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3          Status of Regulatory Compliance ˇV summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4          Monitoring Requirements ˇV summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5          Monitoring Results ˇV summarizes the monitoring results obtained in the reporting period.

 

Section 6          Compliance Audit ˇV summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7          Cumulative Construction Impact due to the Concurrent Projects ˇV summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8          Site Inspection ˇV summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9          Complaints, Notification of summons and Prosecution ˇV summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10        Conclusion

2          Project Background

2.1          Background

2.1.1.     ˇ§Wan Chai Development phase II and Central-Wan Chai Bypassˇ¨ and ˇ§Central-Wan Chai Bypass and Island Eastern Corridor Linkˇ¨ (hereafter called ˇ§the Projectˇ¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2          Scope of the Project and Site Description

2.2.1.     Design and Construction of Central ˇV Wan Chai Bypass and Island Eastern Corridor Link under the Project involves the construction and operation of a trunk road and its road tunnel more than 800m in length between portals that is shown at Figure 2.1.

2.2.2.     The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:

ˇP      A dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);

ˇP      The Central Interchange near the Rumsey Street Flyover to provide road connections to the Central area;

ˇP      Tunnel control buildings and ventilation buildings;

ˇP      Slip roads to connect the CWB to the local road system in the Wan Chai North and Causeway Bay area;

ˇP      Associated road lighting, road signing, traffic control and surveillance system; and

ˇP      Other associated works.

 

2.2.3.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3          Division of the Project Responsibility

2.3.1.     Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.     The details of individual contracts are summarized in Table2.2.

Table 2.2    Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HY/2009/17

Central ˇV Wan Chai Bypass (CWB) at FEHD Whitfield Depot ˇV Advanced piling works.

DP1

5 October 2010

HY/2009/18

Central ˇV Wan Chai Bypass (CWB) ˇV Central Interchange

DP1

21 April 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010 (Completed)

HK/2009/01

Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ˇV Tunnel Works

 

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at Wan Chai East(CWB Tunnel)

DP1

26 April 2011

HY/2009/15

Central-Wanchai Bypass ˇV Tunnel (Causeway Bay Typhoon Shelter Section)

DP1,DP3

13 July 2011

HY/2009/19

Central ˇV Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

HK/2012/08

Wan Chai Development Phase II- Central-Wan Chai Bypass at Wan Chai West

DP1,DP2, DP3

DP works under
EP-364 to be commenced tentatively in early 2014.

HY/2010/08

Central- Wanchai Bypass Tunnel ˇV Tunnel (Slip Road 8)

DP1, DP2, DP3

21 March 2013

 

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineerˇ¦s Representative for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineerˇ¦s Representative for CWB

Principal Resident Engineer

Mr. Peter Poon

3922 3388

3912 3010

Lam Woo & CO., LTD.

Contractor under Contract no. HY/2009/17

General Manager

Mr. Thomas Tang

6111 5351

2566 7522

Contractorˇ¦s Representative

Mr. Chung Man Shek

2566 4866

Site Agent

Mr. Tong Au

9725 5874

Environmental Officer

Dr. Priscilla Choy

9161 7287

Environmental Supervisor

Mr. Tam Chun Pong

6461 3062

Chun Wo ˇV Leader Joint Venture

Contractor under Contract no. HK/2009/01

Joint Venture Board Representative

Mr. PL Yue

2162 9909

2634 1626

Construction  Manager

Mr. Terry Wong

9757 9846

Deputy Site Agent

Mr. Andy Yu

9648 4896

Construction Manager

Mr. Wyman Wong

9627 2467

Construction Manager

Mr. Jack Chu

9775 2467

Environmental Officer (Compliance Manager)

Mr. Frank So

9103 2370

Environmental Supervisor

Mr. Kwong Weng Kit

6253 3356

Chun Wo ˇV CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Site Agent

Mr. Chan Sing Cho

3658-3002

2827 9996

Project Manager

Mr. David Lau

3658-3022

Quality & Environmental Manager

(Environmental Officer)

Mr. C.P. Ho

3658-3000

Chun Wo - CRGL - MBEC Joint Venture

 

Contractor under Contract no. HY/2009/19

Project Manager

Mr. David Lau

3758 8879

2570 8013

Site Agent

Mr. Paul Yu

9456 9819

Environmental Manager /

Environmental Officer

Mr. M.H. Isa

9884 0810

Environmental Engineer

Mr. Calvin Leung

9286 9208

Construction Manager (Marine)

Mr. William Luk

9610 1101

Construction Manager

(Land)

Mr. Patrick Cheung

9643 3012

Construction Manager

(Land)

Mr. Eric Fong

6191 9337

Operation Manager (Land)

Mr. Yung Kwok Wah

9834 1010

Leighton Contractors (Asia) Limited

Contractor under Contract no. HY/2009/18

Site Agent

Mr. Desmond Sze

2214 7700

2140 6799

Deputy Site Agent

Mr. Roger Wong

2214 7703

Environmental Officer

Ms. Lighting Chan

2823 1161

Environmental Engineer

Mr. Donald Ip

2214 7721

Assistant Environmental Engineer

Mr. Penny Yiu

2214 7738

Environmental Supervisor

Mr. K. P. Lai

6461 4660

Environmental Supervisor

Mr. Ray Cheng

2214 7742

Environmental Supervisor

Mr. K. W. Lee

6461 4623

Environmental Supervisor

Mr. Dorothy Shing

2214 7705

Environmental Supervisor

Mr. C. Y. Au Yeung

6461 8631

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Mr. K C Cheung

2823 7813

2865 5229

Site Manager

Mr. J.H. Chen

3557 6368

2566 2192

Contractorˇ¦s Representative

Mr. Andrew Wong

3557 6407

Head of construction

Mr. Roger Cheung

3557 6371

Environmental Officer

Mr. Andy Mak

3557 6215

Environmental Supervisor

Ms. Esther Choi

35576348

Gammon -Leader JV

Contractor under Contract no. HK/2010/06

Project Manager

Mr. Paul Lui

9095 7922

2529 2880

Site Agent

Mr. Eric Yip

2529 2068

Environmental Officer

Mr. Clement Pang

9481 6024

Environmental Supervisor

Mr. Jacky Cheung

9735 9200

China State- Leader JV

Contractor under Contract no. HK/2012/08

Project Director

Mr. Andrew TSE

9137 1811

2877 1522

Project Manager

Mr. Victor WU

9193 8871

Deputy Project Manager

Mr. George CHEUNG

9268 1918

Site Agent

Mr. Paul LUI

9095 7922

Environmental Officer

Mr. James MA

9130 9549

Environmental Supervisor

Mr. Ching Man, CHAN

6050 4919

China State

Contractor under Contract no.HY/2010/08

Project Director

Cheung Kit Cheung

3557 6399

 

2566 8061

Project Manager

Chan Ying Lun

9812 0592

Deputy Project Manager

Chris Leung

3467 4299

 

 

Site Agent

Dr. Dave Chan

3467 4277

 

Environmental Officer

Mr. C.M. Wong

3557 6464

Environmental Supervisor

Mr. Louis Lam Tsz Kwan

3557 6470

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3465 2888

3465 2899

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

2.4.3.     In this reporting month, the principal work activities of individual contracts are included as follows:

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A

ˇP          Excavation of trial pit

ˇP          Transplanting of trees

ˇP          Drainage works

ˇP          Tunnel works including scaffolding erection, excavation, OHVD installation, roadside barriers, top and base slab construction

ˇP          Trough structure construction and associated drilling and grouting

ˇP          Road works

ˇP          Bridges construction

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

ˇP          Installation of pre-bored H-pile in CWB Stage 2 Atrium Link

ˇP          Installation of pre-bored H-pile in CWB Stage 3 Atrium Link

ˇP          Construction of the Common D-wall

ˇP          Backfilling of Temporary Water Channel & Reclaim Land at CH220 ˇV CH260

ˇP          Installation of sheet pile for demolition of P5 Pump house

ˇP          Installation of ELS at first layer for Stage 1.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

ˇP          S4 ELS removal Stage 2 (Bay 7 to Bay 8). Infill concrete was subsequently removed.

ˇP          S4 ELS removal Stage 3 (Bay 1 to Bay 4). Infill concrete was subsequently removed.

ˇP          Construction of OHVD base slab at Eastbound and upper side wall at Westbound

ˇP          Eastbound OHVD base slab Bay 4 between CH3555 and CH3577. Its hanger wall was subsequently casted.

ˇP          Eastbound OHVD base slab Bay 5 between CH3577 and CH3597 was casted

ˇP          Westbound upper side wall Bay 5 between CH3565 and CH3584 was casted

ˇP          For Eastbound, scaffolding erection for OHVD base slab construction from CH3550 westwards. Scaffolding erection for OHVD base slab construction between CH3597 and CH3630. Formwork erection and rebar fixing from CH3597 eastwards.

ˇP          For Westbound, temporary platform for upper side wall construction. Formwork erection and rebar fixing from CH3584 eastwards.

ˇP          Grouting works for completed D-Wall and bored piles.

ˇP          Partial demolition of Box Culvert O Bay 13 & Bay 14 for D-Wall construction was commenced.

ˇP          Pre-drilling works at WCR4/TWCR4 area, Hung Hing Road slow lane and for bridge 3 of Hung Hing Road flyover diversion stage 2.

ˇP          Bored Pile Nos. F01 and PS39 were casted. Installation of Bored Pile Nos. PN31and PC33 were commenced.

ˇP          Existing underground utilities between boundary wall of DSD Wanchai East Sewage Screening Plant and Hung Hing Road Flyover was being identified and exposed.

ˇP          Ground treatment and guide wall for D-Wall construction for Tunnel Portion 6

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ˇV Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

ˇP          ELS works, water proofing and tunnel construction at TS4

ˇP          Cut and cover tunnel construction at TPCWAE

ˇP          Excavation, installation of steel ribs and tunnel lining construction for mined tunnel

ˇP          ELS works at TS2

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

ˇP      Road works at Watson Road

ˇP      Bored piling (Land)

ˇP      Removal of strut at ELS will commence

ˇP      Construction works for Box Culvert T1

ˇP      Construction of Pile cap (Land)

ˇP      Removal of marine platform

ˇP      Construction of pile cap, pier & cross head (Marine)

ˇP      ELS, EVB and Cut & Cover Tunnel

ˇP      Installation of dewatering well

ˇP      Laying of 1500 pipe

ˇP      Launching of segments

ˇP      Extraction of temporary pile from marine section

ˇP      Construction of bridge truss TA1

 

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

ˇP      Stitching Works

ˇP      Grouting Works

 

Contract no. HK/2012/08 ˇV Wan Chai Development Phase II ˇV Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009B

ˇP      Site preparation works

ˇP      Site survey

 

Contract no. HY/2010/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel (Slip Road 8) under FEP-10/364/2009B

ˇP      Tree pruning works

ˇP      Tree removal works,

ˇP      Tree transplanting works,

ˇP      Tree works within off-site nursery compound,

ˇP      Sheet piling works,

ˇP      Demarcation of graphics,

ˇP      Pipe pile & pre-boring works,

ˇP      Re-provisional of turtle pond.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.4.4.     In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

Contract no. HY/2009/18 ˇV Central ˇV Wan Chai Bypass (CWB) ˇV Central Interchange under FEP-05/364/2009/A

ˇP          Excavation of trial pit

ˇP          Drainage works

ˇP          Tunnel works including scaffolding erection, excavation, OHVD installation, roadside barriers, top and base slab construction, extract sheet pile, waterproofing and backfill

ˇP          Trough structure construction and associated drilling and grouting

ˇP          Road works

ˇP          Bridges construction

 

Contract no. HK/2009/01 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ˇV Tunnel Works under FEP-02/364/2009

ˇP          Stage 3 tunnel works including installation of pre-bored H-pile and stage 3 Southern D-wall Construction.

ˇP          Demolition of the HKCEC Pump house was anticipated.

ˇP          ELS for Stage 1 CWB

ˇP          Backfilling Temporary Water Channel & Reclaim Land at CH220-CH260.

 

Contract no. HK/2009/02 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

ˇP          Completed S4 ELS removal.

ˇP          Falsework erection and waterproofing installation and commence rebar fixing for OHVD base slab construction at Tunnel Portion 1.

ˇP          Upper wall construction at Southern Side Wall Bay 3 to Bay 7.

ˇP          OHVD base slab construction at Tunnel Portion 1.

ˇP          Pre-drilling at Hung Hing Road slow line and WCR4/TWCR4.

ˇP          Bored pile construction (Stage 2) at Tunnel Portion 3 & 4 for areas at WCR4/TWCR4 and original slow lane of Hung Hing Road.

ˇP          Partial demolition of Box Culvert O Bay 13 & Bay 14 and commence mini-piling works for bridge 3 foundation of Stage 2 TTA diversion.

ˇP          D-Wall construction at Tunnel Portion 6 (Site under possession by HK/2009/01 contractor).

 

 

 

 

 

 

 

 

 

 

Contract no. HY/2009/15 ˇV Central-Wanchai Bypass ˇV Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

ˇP      Breaking of temporary bulkhead between TS1 and TS2

ˇP      Construction of binding layer, Tunnel construction  at TS2

ˇP      Tunnel construction and dismantling of struts at TS4 & TPCWAE

ˇP      Mined Tunnel drill-and-break works and installation of steel ribs at East and West

Portal

ˇP      Mined tunnel lining construction

 

Contract no. HY/2009/19 ˇV Central ˇV Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

ˇP      Road works at Watson Road

ˇP      Bored piling (Land)

ˇP      Removal of strut at ELS will commence

ˇP      Construction works for Box Culvert T1

ˇP      Construction of Pile cap (Land)

ˇP      Removal of marine platform

ˇP      Construction of pile cap, pier & cross head (Marine)

ˇP      ELS, EVB and Cut & Cover Tunnel

ˇP      Installation of dewatering well

ˇP      Laying of 1500 pipe

ˇP      Launching of segments

ˇP      Extraction of temporary pile from marine section

ˇP      Construction of bridge truss TA1

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

ˇP      Stitching Works

ˇP      Grouting Works

ˇP      Repair and Installation of Slotted Panels

ˇP      In-Filling works

 

Contract no. HK/2012/08 ˇV Wan Chai Development Phase II ˇV Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B

ˇP          Site preparation works

ˇP          Site survey

 

 

 

 

 

 

 

 

 

Contract no. HY/2010/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel (Slip Road 8) under FEP-10/364/2009B

ˇP      Tree pruning works

ˇP      Tree removal works,

ˇP      Tree transplanting works,

ˇP      Tree works within off-site nursery compound,

ˇP      Sheet piling works,

ˇP      Demarcation of graphics,

ˇP      Pipe pile & pre-boring works, &

ˇP      Re-provisional of turtle pond.

 

3          status of regulatory compliance

3.1          Status of Environmental Licensing and Permitting under the Project

 

3.1.1.     A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1    Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

Superseded

Environmental Permit

EP-364/2009/A

4 Aug 2010

Superseded

Environmental Permit

EP-364/2009/B

20 Sep 2012

Valid

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Surrendered

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

15 Nov 2010

Valid

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

Valid

Further Environmental Permit

FEP-06/356/2009

5 March 2013

Valid

Further Environmental Permit

FEP-07/356/2009

26 July 2013

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 July 2010

Surrendered

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Surrendered

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

Valid

Further Environmental Permit

FEP-08/364/2009/A

15 June 2012

Valid

Further Environmental Permit

FEP-09/364/2009/B

5 March 2013

Valid

Further Environmental Permit

FEP-10/364/2009/B

26 July 2013

Valid

 

3.1.2.     Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HY/2009/17 ˇV Central ˇV Wan Chai Bypass (CWB) at FEHD Whitfield Depot ˇV Advanced piling works under FEP-03/364/2009

3.1.3.     The construction works was completed and the FEP was surrendered by the Contractor on 25 April 2013.

Contract no. 04/HY/2006 ˇV Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

3.1.4.     The construction works was completed, and the FEP was surrendered by the Contractor on 11 February 2011.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HK/2009/01 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ˇV Tunnel Works under FEP-02/364/2009

3.1.5.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5

Table 3.4    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

                 Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

N/A

Valid

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088

06 Jan 2010

N/A

Valid

Construction Noise Permit (CNP) for non-pilling equipment

GW-RS0797-13

16 Jul 2013

18 Jul 2013 to 15 Jan 2014

Cancelled

GW-RS0773-13

16 Jul 2013

20 July 2013 to 19 Jan 2014

Cancelled

GW-RS0807-13

24 Jul 2013

25 Jul 2013 to 21 Jan 2014

Cancelled

GW-RS0626-13

13 Jun 2013

15 Jun 2013 to 12 Dec 2013

Cancelled

GW-RS0631-13

14 Jun 2013

14 Jun 2013 to 13 Dec 2013

Cancelled

GW-RS0651-13

21 Jun 2013

22 Jun 2013 to 20 Dec 2013

Cancelled

GW-RS0856-13

7 Aug 2013

10 Aug 2013 to 1 Feb 2014

Valid

GW-RS0883-13

12 Aug 2013

14 Aug 2013 to 13 Feb 2014

Valid

GW-RS0937-13

23 Aug 2013

25 Aug 2013 to 22 Feb 2014

Valid

GW-RS1063-13

24 Sep 2013

26 Sep 2013 to 23 Mar 2014

Valid

GW-RE1034-13

27 Sep 2013

30 Sep 2013 to 29 Mar 2014

Valid

GW-RS0626-13

13 Jun 2013

15 Jun 2013 to 12 Dec 2013

Cancelled

GW-RS1094-13

7 Oct 2013

08 Oct 2013 to 07 Apr 2014

Valid

GW-RS1114-13

11 Oct 2013

13 Oct 2013 to 12 Apr 2014

Valid

GW-RS1153-13

21Oct 2013

23 Oct 2013 to 20 Apr 2014

Cancelled

GW-RS1083-13

27 Sep 2013

29 Sep 2013 to 26 Mar 2014

Cancelled

GW-RS1091-13

7 Oct 2013