Contract No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and Testing Work (Stage
2) Environmental
Permit no. EP-364/2009/B, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/A, FEP-08/364/2009/A,
FEP-09/364/2009/B and FEP-10/364/2009/B Monthly Environmental Monitoring & Audit Report
- December 2013 -
|
CLIENTS: |
|
Civil Engineering
and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
11 January 2014 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status of Environmental Licensing and Permitting under the
Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring.
6.4 Review of the Reasons for and the Implications of
Non-compliance
6.5 Summary of action taken in the event of and follow-up on
non-compliance
7. Cumulative Construction Impact
due to the Concurrent Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects
under this Project
Table
2.2 Details of Individual Contracts
under the Project
Table
2.3 Contact Details of Key Personnel
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/01
Table
3.5 Summary of submission status
under FEP-02/364/2009
Table
3.6 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02
Table
3.7 Summary of submission status
under FEP-01/364/2009
Table
3.8 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/18
Table
3.9 Summary of submission status
under FEP-05/364/2009/A
Table
3.10 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/15
Table
3.11 Summary of submission status
under FEP-06/364/2009/A
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.13 Summary of submission status under
FEP-07/364/2009/A
Table
3.14 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2010/06
Table 3.15 Summary of submission status under FEP-08/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.17 Summary of submission status under FEP-09/364/2009/B
Table 3.18 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.19 Summary of submission status under
FEP-10/364/2009/B
Table 4.1 Noise Monitoring
Stations
Table
4.2 Real Time Noise Monitoring
Stations
Table
4.3 Air Monitoring Stations
Table
5.1 Noise Monitoring Stations for
Contract no. HY/2009/18
Table
5.2 Noise Monitoring Station for
Contract no HK/2009/01 and HK/2009/02
Table
5.3 Noise Monitoring Stations for
Contract no. HY/2009/15
Table
5.4 Noise Monitoring Stations for
Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table
5.7 Real Time Noise Monitoring
Stations for Contract no. HY/2009/19
Table
5.9 Air Monitoring Stations for
Contract no. HY/2009/18
Table
5.10 Air Monitoring Station for Contract no. HK/2009/01
Table
5.11 Air Monitoring Station for Contract no. HK/2009/02
Table
5.12 Air Monitoring Station for Contract no. HY/2009/15
Table
5.13 Air Monitoring Stations for Contract no. HY/2009/19
Table
5.15 Details of Waste Disposal for
Contract no. HK/2009/01
Table
5.16 Details of Waste Disposal for
Contract no. HK/2009/02
Table
5.17 Details of Waste Disposal for
Contract no. HY/2009/18
Table
5.18 Details of Waste Disposal for
Contract no. HY/2009/15
Table
5.19 Details of Waste Disposal for Contract no. HY/2009/19
Table
5.20 Details of Waste Disposal for
Contract no. HK/2010/06
Table 5.21 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.22 Details of Waste Disposal for Contract no. HY/2010/08
Table 8.1 Summary of Environmental
Inspections for Contract no. HY/2009/15
Table 8.2
Summary of Environmental Inspections for Contract no. HK/2009/18
Table 8.4 Summary of Environmental Inspections for
Contract no. HK/2009/01
Table 8.5 Summary of Environmental Inspections for Contract no. HK/2009/02
Table 8.6
Summary of Environmental Inspections for Contract no. HK/2012/08
Table 8.7 Summary of Environmental Inspections for Contract no. HY/2010/08
Table
9.1 Cumulative Statistics on
Complaints
Table
9.2 Cumulative Statistics on
Successful Prosecutions
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming
month
Appendix 5.2 Noise Monitoring Results and Graphical
Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix
5.4 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification
of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
ˇP
Excavation of trial pit
ˇP
Transplanting of trees
ˇP
Drainage works
ˇP
Tunnel works including scaffolding erection, excavation, OHVD
installation, roadside barriers, top and base slab construction
ˇP
Trough structure construction and associated drilling and grouting
ˇP
Road works
ˇP
Bridges construction
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at
ˇP
Installation of pre-bored H-pile in CWB Stage 2 Atrium Link
ˇP
Installation of pre-bored H-pile in CWB Stage 3 Atrium Link
ˇP
Construction of the Common D-wall
ˇP
Backfilling of
ˇP
Installation of sheet pile for demolition of P5 Pump house
ˇP
Installation of ELS at first layer for Stage 1.
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
ˇP
S4 ELS removal Stage 2 (Bay 7 to Bay 8). Infill concrete was
subsequently removed.
ˇP
S4 ELS removal Stage 3 (Bay 1 to Bay 4). Infill concrete was
subsequently removed.
ˇP
Construction of OHVD base slab at Eastbound and upper side wall at Westbound
ˇP
Eastbound OHVD base slab Bay 4 between CH3555 and CH3577. Its hanger
wall was subsequently casted.
ˇP
Eastbound OHVD base slab Bay 5 between CH3577 and CH3597 was casted
ˇP
Westbound upper side wall Bay 5 between CH3565 and CH3584 was casted
ˇP
For Eastbound, scaffolding erection for OHVD base slab construction from
CH3550 westwards. Scaffolding erection for OHVD base slab construction between
CH3597 and CH3630. Formwork erection and rebar fixing from CH3597 eastwards.
ˇP
For Westbound, temporary platform for upper side wall construction. Formwork
erection and rebar fixing from CH3584 eastwards.
ˇP
Grouting works for completed D-Wall and bored piles.
ˇP
Partial demolition of Box Culvert O Bay 13 & Bay 14 for D-Wall
construction was commenced.
ˇP
Pre-drilling works at WCR4/TWCR4 area,
ˇP
Bored Pile Nos. F01 and PS39 were casted. Installation of Bored Pile Nos.
PN31and PC33 were commenced.
ˇP
Existing underground utilities between boundary wall of DSD Wanchai East
Sewage Screening Plant and Hung Hing Road Flyover was being identified and
exposed.
ˇP
Ground treatment and guide wall for D-Wall construction for Tunnel
Portion 6
Contract no. HY/2009/15 -
Central-Wanchai Bypass ˇV Tunnel (
ˇP
ELS works, water proofing and tunnel construction at TS4
ˇP
Cut and cover tunnel construction at TPCWAE
ˇP
Excavation, installation of steel ribs and tunnel lining construction for
mined tunnel
ˇP
ELS works at TS2
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
ˇP Road works at
ˇP Bored piling (Land)
ˇP Removal of strut at ELS will commence
ˇP Construction works for Box Culvert T1
ˇP Construction of Pile cap (Land)
ˇP Removal of marine platform
ˇP Construction of pile cap, pier &
cross head (Marine)
ˇP ELS, EVB and Cut & Cover Tunnel
ˇP Installation of dewatering well
ˇP Laying of 1500 pipe
ˇP Launching of segments
ˇP Extraction of temporary pile from marine
section
ˇP Construction of bridge truss TA1
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
ˇP Stitching Works
ˇP Grouting Works
Contract
no. HK/2012/08 ˇV Wan Chai Development Phase II ˇV Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
ˇP Site preparation works
ˇP Site survey
Contract
no. HY/2010/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel (Slip Road 8) under
FEP-10/364/2009B
ˇP Tree pruning works
ˇP Tree removal works,
ˇP Tree transplanting works,
ˇP Tree works within off-site nursery
compound,
ˇP Sheet piling works,
ˇP Demarcation of graphics,
ˇP Pipe pile & pre-boring works, &
ˇP Re-provisional of turtle pond.
Noise
Monitoring
Air Monitoring
xix.
Due to electricity interruption, the 24hr TSP monitoring at CMA2a was
rescheduled from 23 December 2013 to 24 December 2013.
Complaints, Notifications of Summons
and Successful Prosecutions
According to the
information provided by RSS, the construction activities around the concerned
location on 16 Dec 2013 include preparation work of root ball for tree
transplanting at Zone 17/18.
A further investigation
on the complaint was conducted on 19 Dec 2013 during weekly environmental
inspection. It was observed that a tree works area comprised of mainly loosen
soil was located near
the concerned location. It was considered that the inclined surface and
loosen soil nature of
the concerned works area could have led to the muddy surface runoff in rain.
Deposition of muddy runoff onto nearby public pavement outside works area was
hence resulted and was subsequently cleaned into nearby public stormwater drain
by the Contractorˇ¦s workers on the complaint date. As such, the case was
considered as works related. Sandbags, geotextile and gravels were immediately
placed by the Contractor around the gullies at the concerned location to
prevent leftover muddy runoff to the public stormwater drain as observed during
the weekly inspection on 19 Dec 2013.
With respect to the
follow-up raised by the complainant on 19 Dec 2013, sandbags, geotextile and
gravels placed at gullies located at public area were removed by the Contractor
on the same day for maintaining passable public pavement. Follow up measures
including sandbag bundle and covering of works area with impervious sheeting
was immediately placed at the source of impact at the concerned works area
boundary by the Contractor.
ET confirmed with the
Resident Site Staff that the major construction activities around the concerned
location conducted on 24 Dec 2013 include breaking up existing pillar box for
new children playground Portion II, pressing of sheet pile at bowling green for
ELS works Portion XII, welding work for preparation of sheet piling work at
bowling green Portion VI, Demolition of existing pavilion for bowling green
Portion VI and felling of tree TA50 at Victoria Park Zone 13. Mitigation
measures implemented by the Contractor for the above construction works include
water spraying for demolition and other dust generating works.
According to the
relevant site records, breaking up of existing pillar box, pressing of sheet
pile, welding work for preparation of sheet piling, demolition of existing
pavilion and felling of tree TA50 at Victoria Park Zone 13 were conducted at
the concerned location during the time of complaint. Based on information and
photo record provided by the RSS, dust mitigation measures including water
spraying during dust generating works were implemented by the Contractor at the
concerned location on 24 Dec 2013.
Follow-up investigation
was conducted on 27 Dec 2013 during weekly environmental inspection, dust
mitigation measures including water spraying to dusty area and major dust
generation works were confirmed in place despite a general reminder was given
to the contractor to enhance the water spraying to dusty haul road during dry
season. Based on on-going site inspection and the follow-up investigation, the
site condition was considered generally satisfactory and no non-conformance was
identified.
Upon further review on
the supplementary information provided by the complainant on 31 Dec 2013 and
investigation conducted on 2 Jan 2014, the tree felling work of tree TA50 was
located nearest to the location of the complainant. According to the location
plan provided by the RSS and on site investigation, the tree felling work for
TA50 was immediately in front of the location of the complainant. Based on site
observation, scrap material of bark and leaves inevitably generated from
cutting of branches during tree felling work was considered to be the most
probable cause for the observation raised by the complainant at the concerned
location on 24 Dec 2013.Furthermore, welding work was observed near the
concerned location and was considered to be the potential source for the smell
and exhaust fumes as described by the complainant. Notwithstanding the above,
welding work was not identified as a work activity with air quality impact
under Project EIA report but it would be desirable to implement preventive
measures to minimize potential nuisance to nearby public.
Site Inspections and Audit
Future Key Issues
Contract no. HY/2009/18 ˇV Central ˇV Wan
Chai Bypass (CWB) ˇV Central Interchange under FEP-05/364/2009/A
ˇP
Excavation of trial pit
ˇP
Drainage works
ˇP
Tunnel works including scaffolding erection, excavation, OHVD installation,
roadside barriers, top and base slab construction, extract sheet pile,
waterproofing and backfill
ˇP
Trough structure construction and associated drilling and grouting
ˇP
Road works
ˇP
Bridges construction
Contract no. HK/2009/01 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan
Chai Bypass at
ˇP
Stage 3 tunnel works including installation of pre-bored H-pile and
stage 3 Southern D-wall Construction.
ˇP
Demolition of the HKCEC Pump house was anticipated.
ˇP
ELS for Stage 1 CWB
ˇP
Contract no. HK/2009/02 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
ˇP
Completed S4 ELS removal.
ˇP
Falsework erection and waterproofing installation and commence rebar
fixing for OHVD base slab construction at Tunnel Portion 1.
ˇP
Upper wall construction at Southern Side Wall Bay 3 to Bay 7.
ˇP
OHVD base slab construction at Tunnel Portion 1.
ˇP
Pre-drilling at
ˇP
Bored pile construction (Stage 2) at Tunnel Portion 3 & 4 for areas
at WCR4/TWCR4 and original slow lane of
ˇP
Partial demolition of Box Culvert O Bay 13 & Bay 14 and commence
mini-piling works for bridge 3 foundation of Stage 2 TTA diversion.
ˇP
D-Wall construction at Tunnel Portion 6 (Site under possession by
HK/2009/01 contractor).
Contract no. HY/2009/15 ˇV Central-Wanchai Bypass ˇV Tunnel (
ˇP Breaking of temporary bulkhead between
TS1 and TS2
ˇP Construction of binding layer, Tunnel
construction at TS2
ˇP Tunnel construction and dismantling of
struts at TS4 & TPCWAE
ˇP Mined Tunnel drill-and-break works and
installation of steel ribs at East and West
Portal
ˇP Mined tunnel lining construction
Contract no. HY/2009/19 ˇV Central ˇV Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
ˇP Road works at
ˇP Bored piling (Land)
ˇP Removal of strut at ELS will commence
ˇP Construction works for Box Culvert T1
ˇP Construction of Pile cap (Land)
ˇP Removal of marine platform
ˇP Construction of pile cap, pier &
cross head (Marine)
ˇP ELS, EVB and Cut & Cover Tunnel
ˇP Installation of dewatering well
ˇP Laying of 1500 pipe
ˇP Launching of segments
ˇP Extraction of temporary pile from marine
section
ˇP Construction of bridge truss TA1
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
ˇP Grouting Works
ˇP Repair and Installation of Slotted
Panels
ˇP In-Filling works
Contract
no. HK/2012/08 ˇV Wan Chai Development Phase II ˇV Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009/B
ˇP
Site preparation works
ˇP
Site survey
Contract
no. HY/2010/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel (Slip Road 8) under
FEP-10/364/2009B
ˇP Tree removal works,
ˇP Tree transplanting works,
ˇP Tree works within off-site nursery
compound,
ˇP Sheet piling works,
ˇP Demarcation of graphics,
ˇP Pipe pile & pre-boring works, &
ˇP Re-provisional of turtle pond.
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/B and
Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A,
FEP-08/364/2009/A and FEP-09/364/2009/B to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and ˇ§Environmental Monitoring and Audit
Requirementsˇ¨ under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/B, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009B during the period November to December 2013. The cut-off
date of reporting is at 27th of each reporting month
Section
1 Introduction ˇV
details the scope and structure of the report.
Section
2 Project
Background ˇV summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ˇV
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ˇV summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ˇV summarizes the monitoring results obtained
in the reporting period.
Section
6 Compliance
Audit ˇV summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects ˇV summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Site Inspection ˇV
summarizes the findings of weekly site inspections undertaken within the reporting
period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
ˇV summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
ˇ§Wan Chai Development phase II and Central-Wan Chai Bypassˇ¨ and
ˇ§Central-Wan Chai Bypass and Island Eastern Corridor Linkˇ¨ (hereafter called
ˇ§the Projectˇ¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested
2.2.1.
Design and Construction of Central ˇV Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
ˇP
A dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
ˇP
The Central Interchange near the Rumsey Street Flyover to provide road
connections to the Central area;
ˇP
Tunnel control buildings and ventilation buildings;
ˇP
Slip roads to connect the CWB to the local road system in the Wan Chai
North and
ˇP
Associated road lighting, road signing, traffic control and surveillance
system; and
ˇP
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2
DPs.
Table
2.1 Schedule 2 Designated
Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason
for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length
|
DP2 |
Road P2 and other roads which are classified as
primary/district distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging
works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging
operation less than 100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter
more than 1,200 mm and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from
Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a
seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further
Environmental Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table
2.2 Details of
Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ˇV Wan Chai Bypass (CWB) at FEHD Whitfield
Depot ˇV Advanced piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central ˇV Wan Chai Bypass (CWB) ˇV Central
Interchange |
DP1 |
21 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ˇV Central ˇV Wan Chai
Bypass at |
DP1,
DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ˇV Central ˇV Wan
Chai Bypass at Wan Chai East(CWB Tunnel) |
DP1 |
26 |
HY/2009/15 |
Central-Wanchai Bypass ˇV Tunnel ( |
DP1,DP3 |
13
July 2011 |
HY/2009/19 |
Central ˇV Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link |
DP1 |
24
March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai
Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
DP works under |
HY/2010/08 |
Central- Wanchai Bypass Tunnel ˇV Tunnel (Slip Road
8) |
DP1, DP2, DP3 |
21 March 2013 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineerˇ¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587
1877 |
Engineerˇ¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912
3010 |
|
Lam Woo & CO.,
LTD. |
Contractor under Contract no. HY/2009/17 |
General Manager |
Mr. Thomas Tang |
6111 5351 |
2566
7522 |
Contractorˇ¦s Representative |
Mr. Chung Man Shek |
2566 4866 |
|||
Site Agent |
Mr. Tong Au |
9725 5874 |
|||
Environmental Officer |
Dr. Priscilla Choy |
9161 7287 |
|||
Environmental Supervisor |
Mr. Tam Chun Pong |
6461 3062 |
|||
Chun Wo ˇV Leader
Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
|
2162 9909 |
2634
1626 |
Construction
Manager |
Mr. Terry Wong |
9757 9846 |
|||
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack
Chu |
9775 2467 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Frank
So |
9103
2370 |
|||
Environmental
Supervisor |
Mr. Kwong
Weng Kit |
6253
3356 |
|||
Chun Wo ˇV CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658-3002 |
2827
9996 |
Project Manager |
Mr. David Lau |
3658-3022 |
|||
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint
Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570
8013 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Mr. |
9286 9208 |
|||
Construction Manager (Marine) |
Mr. William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Mr. Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Mr. Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Mr. Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Desmond Sze |
2214
7700 |
|
Deputy Site Agent |
Mr. Roger Wong |
2214
7703 |
|||
Environmental Officer |
Ms. |
2823
1161 |
|||
Environmental Engineer |
Mr. Donald Ip |
2214
7721 |
|||
Assistant Environmental Engineer |
Mr. Penny Yiu |
2214
7738 |
|||
Environmental Supervisor |
Mr. K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Mr. Ray Cheng |
2214 7742 |
|||
Environmental Supervisor |
Mr. K. W. Lee |
6461 4623 |
|||
Environmental Supervisor |
Mr. Dorothy Shing |
2214
7705 |
|||
Environmental Supervisor |
Mr. C. Y. Au Yeung |
6461
8631 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. K C Cheung |
2823 7813 |
2865 5229 |
Site Manager |
Mr. J.H. Chen |
3557 6368 |
2566 2192 |
||
Contractorˇ¦s
Representative |
Mr. Andrew Wong |
3557
6407 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Ms. Esther Choi |
35576348 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529
2880 |
Site
Agent |
Mr. Eric Yip |
2529 2068 |
|||
Environmental
Officer |
Mr. Clement Pang |
9481 6024 |
|||
Environmental
Supervisor |
Mr.
Jacky Cheung |
9735 9200 |
|||
|
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. Andrew
TSE |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Victor
WU |
9193
8871 |
|||
Deputy
Project Manager |
Mr. George
CHEUNG |
9268
1918 |
|||
Site
Agent |
Mr. Paul
LUI |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Ching
Man, CHAN |
6050
4919 |
|||
|
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung
Kit Cheung |
3557
6399 |
2566
8061 |
Project
Manager |
Chan
Ying Lun |
9812
0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467
4299 |
|||
|
|
Site
Agent |
Dr. Dave
Chan |
3467
4277 |
|
Environmental
Officer |
Mr. C.M.
Wong |
3557
6464 |
|||
Environmental
Supervisor |
Mr. Louis
Lam Tsz Kwan |
3557
6470 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics
Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882
3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. HY/2009/18 - Central - Wan
Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
ˇP
Excavation of trial pit
ˇP
Transplanting of trees
ˇP
Drainage works
ˇP
Tunnel works including scaffolding erection, excavation, OHVD
installation, roadside barriers, top and base slab construction
ˇP
Trough structure construction and associated drilling and grouting
ˇP
Road works
ˇP
Bridges construction
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at
ˇP
Installation of pre-bored H-pile in CWB Stage 2 Atrium Link
ˇP
Installation of pre-bored H-pile in CWB Stage 3 Atrium Link
ˇP
Construction of the Common D-wall
ˇP
Backfilling of
ˇP
Installation of sheet pile for demolition of P5 Pump house
ˇP
Installation of ELS at first layer for Stage 1.
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
ˇP
S4 ELS removal Stage 2 (Bay 7 to Bay 8). Infill concrete was
subsequently removed.
ˇP
S4 ELS removal Stage 3 (Bay 1 to Bay 4). Infill concrete was
subsequently removed.
ˇP
Construction of OHVD base slab at Eastbound and upper side wall at
Westbound
ˇP
Eastbound OHVD base slab Bay 4 between CH3555 and CH3577. Its hanger
wall was subsequently casted.
ˇP
Eastbound OHVD base slab Bay 5 between CH3577 and CH3597 was casted
ˇP
Westbound upper side wall Bay 5 between CH3565 and CH3584 was casted
ˇP
For Eastbound, scaffolding erection for OHVD base slab construction from
CH3550 westwards. Scaffolding erection for OHVD base slab construction between
CH3597 and CH3630. Formwork erection and rebar fixing from CH3597 eastwards.
ˇP
For Westbound, temporary platform for upper side wall construction.
Formwork erection and rebar fixing from CH3584 eastwards.
ˇP
Grouting works for completed D-Wall and bored piles.
ˇP
Partial demolition of Box Culvert O Bay 13 & Bay 14 for D-Wall construction
was commenced.
ˇP
Pre-drilling works at WCR4/TWCR4 area,
ˇP
Bored Pile Nos. F01 and PS39 were casted. Installation of Bored Pile
Nos. PN31and PC33 were commenced.
ˇP
Existing underground utilities between boundary wall of DSD Wanchai East
Sewage Screening Plant and Hung Hing Road Flyover was being identified and
exposed.
ˇP
Ground treatment and guide wall for D-Wall construction for Tunnel
Portion 6
Contract no. HY/2009/15 - Central-Wanchai Bypass ˇV Tunnel (
ˇP
ELS works, water proofing and tunnel construction at TS4
ˇP
Cut and cover tunnel construction at TPCWAE
ˇP
Excavation, installation of steel ribs and tunnel lining construction for
mined tunnel
ˇP
ELS works at TS2
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
ˇP
Road works at
ˇP
Bored piling (Land)
ˇP
Removal of strut at ELS will commence
ˇP
Construction works for Box Culvert T1
ˇP
Construction of Pile cap (Land)
ˇP
Removal of marine platform
ˇP
Construction of pile cap, pier & cross head (Marine)
ˇP
ELS, EVB and Cut & Cover Tunnel
ˇP
Installation of dewatering well
ˇP
Laying of 1500 pipe
ˇP
Launching of segments
ˇP
Extraction of temporary pile from marine section
ˇP
Construction of bridge truss TA1
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
ˇP
Stitching Works
ˇP
Grouting Works
Contract no. HK/2012/08 ˇV Wan Chai
Development Phase II ˇV Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009B
ˇP
Site preparation works
ˇP
Site survey
Contract no. HY/2010/08 ˇVCentral - Wan
Chai Bypass (CWB) ˇVTunnel (Slip Road 8) under FEP-10/364/2009B
ˇP
Tree pruning works
ˇP
Tree removal works,
ˇP
Tree transplanting works,
ˇP
Tree works within off-site nursery compound,
ˇP
Sheet piling works,
ˇP
Demarcation of graphics,
ˇP
Pipe pile & pre-boring works,
ˇP
Re-provisional of turtle pond.
2.4.4.
In coming reporting month, the principal work activities of individual
contracts are anticipated as follows:
ˇP
Excavation of trial pit
ˇP
Drainage works
ˇP
Tunnel works including scaffolding erection, excavation, OHVD
installation, roadside barriers, top and base slab construction, extract sheet
pile, waterproofing and backfill
ˇP
Trough structure construction and associated drilling and grouting
ˇP
Road works
ˇP
Bridges construction
Contract no. HK/2009/01 ˇV Wan Chai
Development Phase II ˇV Central ˇV Wan Chai Bypass at
ˇP
Stage 3 tunnel works including installation of pre-bored H-pile and
stage 3 Southern D-wall Construction.
ˇP
Demolition of the HKCEC Pump house was anticipated.
ˇP
ELS for Stage 1 CWB
ˇP
Contract no. HK/2009/02 ˇV Wan Chai
Development Phase II ˇV Central ˇV Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
ˇP
Completed S4 ELS removal.
ˇP
Falsework erection and waterproofing installation and commence rebar
fixing for OHVD base slab construction at Tunnel Portion 1.
ˇP
Upper wall construction at Southern Side Wall Bay 3 to Bay 7.
ˇP
OHVD base slab construction at Tunnel Portion 1.
ˇP
Pre-drilling at
ˇP
Bored pile construction (Stage 2) at Tunnel Portion 3 & 4 for areas
at WCR4/TWCR4 and original slow lane of
ˇP
Partial demolition of Box Culvert O Bay 13 & Bay 14 and commence
mini-piling works for bridge 3 foundation of Stage 2 TTA diversion.
ˇP
D-Wall construction at Tunnel Portion 6 (Site under possession by
HK/2009/01 contractor).
Contract no. HY/2009/15 ˇV
Central-Wanchai Bypass ˇV Tunnel (
ˇP
Breaking of temporary bulkhead between TS1 and TS2
ˇP
Construction of binding layer, Tunnel construction at TS2
ˇP
Tunnel construction and dismantling of struts at TS4 & TPCWAE
ˇP
Mined Tunnel drill-and-break works and installation of steel ribs at
East and West
Portal
ˇP
Mined tunnel lining construction
Contract no. HY/2009/19 ˇV Central ˇV
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
ˇP
Road works at
ˇP
Bored piling (Land)
ˇP
Removal of strut at ELS will commence
ˇP
Construction works for Box Culvert T1
ˇP
Construction of Pile cap (Land)
ˇP
Removal of marine platform
ˇP
Construction of pile cap, pier & cross head (Marine)
ˇP
ELS, EVB and Cut & Cover Tunnel
ˇP
Installation of dewatering well
ˇP
Laying of 1500 pipe
ˇP
Launching of segments
ˇP
Extraction of temporary pile from marine section
ˇP
Construction of bridge truss TA1
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
ˇP
Stitching Works
ˇP
Grouting Works
ˇP
Repair and Installation of Slotted Panels
ˇP
In-Filling works
Contract no. HK/2012/08 ˇV Wan Chai
Development Phase II ˇV Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009/B
ˇP
Site preparation works
ˇP
Site survey
Contract no. HY/2010/08 ˇVCentral - Wan
Chai Bypass (CWB) ˇVTunnel (Slip Road 8) under FEP-10/364/2009B
ˇP
Tree pruning works
ˇP
Tree removal works,
ˇP
Tree transplanting works,
ˇP
Tree works within off-site nursery compound,
ˇP
Sheet piling works,
ˇP
Demarcation of graphics,
ˇP
Pipe pile & pre-boring works, &
ˇP
Re-provisional of turtle pond.
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further
Environmental Permit |
FEP-06/356/2009 |
5 March 2013 |
Valid |
Further
Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Surrendered |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Valid |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ˇV Central ˇV Wan Chai
Bypass (CWB) at FEHD Whitfield Depot ˇV Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP was surrendered by the Contractor on 25
Contract no. 04/HY/2006 ˇV Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP was surrendered by the
Contractor on 11 February 2011.
Contract no. HK/2009/01 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan
Chai Bypass at
3.1.5.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5
Table
3.4 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/01