Contract No: HK/2011/07 Wanchai Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing Work (Stage
2) Environmental
Permit no. EP-364/2009/C, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/A, FEP-08/364/2009/A,
FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B Monthly Environmental Monitoring & Audit Report
- AUGUST 2014 -
|
CLIENTS: |
|
Civil Engineering
and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
10 September 2014 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3
status of regulatory compliance.
3.1 Status
of Environmental Licensing and Permitting under the Project
4.2 Air Monitoring
5.2 Real Time Noise Monitoring Results
6.3 Review
of the Reasons for and the Implications of Non-compliance
6.4 Summary
of action taken in the event of and follow-up on non-compliance
7.0
Cumulative Construction Impact due to the Concurrent Projects
9.0
Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects
under this Project
Table
2.2 Details of Individual Contracts
under the Project
Table
2.3 Contact Details of Key Personnel
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/01
Table
3.5 Summary of submission status
under FEP-02/364/2009
Table
3.6 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02
Table
3.7 Summary of submission status
under FEP-01/364/2009
Table
3.8 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/18
Table
3.9 Summary of submission status
under FEP-05/364/2009/A
Table
3.10 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/15
Table
3.11 Summary of submission status
under FEP-06/364/2009/A
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.13
Summary of submission status under FEP-07/364/2009/A
Table
3.14 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2010/06
Table 3.15 Summary of submission status under FEP-08/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.17 Summary of submission status under FEP-09/364/2009/B
Table 3.18 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.19 Summary of submission status under
FEP-10/364/2009/B
Table 3.20 Cumulative Summary of Valid
License and Permits under Contract no. HY/2011/08
Table 3.21 Summary of submission status under
FEP-11/364/2009
Table 4.1 Noise Monitoring
Stations
Table
4.2 Real Time Noise Monitoring
Stations
Table
4.3 Air Monitoring Stations
Table
5.1 Noise Monitoring Stations for
Contract no. HY/2009/18
Table
5.2 Noise Monitoring Station for
Contract no HK/2009/01 and HK/2009/02
Table
5.3 Noise Monitoring Stations for
Contract no. HY/2009/15
Table
5.4 Noise Monitoring Stations for
Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table
5.7 Real Time Noise Monitoring
Stations for Contract no. HY/2009/19
Table
5.9 Air Monitoring Stations for
Contract no. HY/2009/18
Table
5.10 Air Monitoring Station for Contract no. HK/2009/01
Table
5.11 Air Monitoring Station for Contract no. HK/2009/02
Table
5.12 Air Monitoring Station for Contract no. HY/2009/15
Table
5.13 Air Monitoring Stations for Contract no. HY/2009/19
Table
5.15 Details of Waste Disposal for
Contract no. HK/2009/01
Table
5.16 Details of Waste Disposal for
Contract no. HK/2009/02
Table
5.17 Details of Waste Disposal for
Contract no. HY/2009/18
Table
5.18 Details of Waste Disposal for
Contract no. HY/2009/15
Table
5.19 Details of Waste Disposal for Contract no. HY/2009/19
Table
5.20 Details of Waste Disposal for
Contract no. HK/2010/06
Table 5.21 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.22 Details of Waste Disposal
for Contract no. HY/2010/08
Table 5.23 Details of Waste Disposal for Contract no. HY/2011/08
Table 8.1 Summary of Environmental
Inspections for Contract no. HY/2009/15
Table 8.3
Summary of Environmental Inspections for Contract no. HK/2009/19
Table 8.4
Summary of Environmental Inspections for Contract no. HK/2009/01
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table
8.7 Summary of Enviromental Inspections for
Contract no. HK/2012/08
Table 8.8 Summary of Environmental Inspections for Contract no. HY/2010/08
Table
9.1 Cumulative Statistics on
Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring
Results and Graphical Presentations
Appendix
5.4 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of
Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Drainage works
¡P
Tunnel works including scaffolding erection, excavation, OHVD
installation, roadside barriers, top and base slab construction
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
Bridges construction
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
¡P
Stage 1 construction of tunnel structures
¡P
Stage 2 installation of pre-bored H-piles
¡P
Stage 2 installation of sheet pile at exhaust duct
¡P
Installation of dewatering well in Stage 2
¡P
Stage 2 excavations and ELS works
¡P
Demolition works of existing HKCEC pump house (Kiu Lok Portion)
¡P
Demolition of 10 nos. pump cells at Convention Avenue
¡P
Stage 3 construction of D-Wall
¡P
Stage 3 installation of pre-bored H-piles
¡P
Discharge cooling mainlaying works for BI, BG & BF
¡P
S8B and S9 saltwater mainlaying works
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Backfilling work for tunnel
¡P
Loading transfer of utility bridge for DSD Sewage Outfall pipes and WSD
Intake Culvert
¡P
Removal of Strut
¡P
Excavation for Tunnel Portion
¡P
Installation of dewatering system
¡P
Bored piling works
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
¡P
Dismantling of struts and backfilling at TS4 & TPCWAE
¡P
Mined Tunnel drill-and-break works and installation of steel ribs at
East and West Portal
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road works at Watson Road
¡P
Bored piling (Land)
¡P
Removal/Installation of strut at ELS
¡P
Construction of Dolphin Cap
¡P
ELS for Cut &Cover Tunnel and EVB
¡P
Excavation of ELS continue
¡P
Laying of 1350f pipe
¡P
Pre-bored H-pile for Admin. Building continue
¡P
Parapet construction continue
¡P
Wing slab extension continue
¡P
Construction of TD bridge continue
¡P
Construction of Bridge E
¡P
Construction of Bride F4 and F5
¡P
Dismantling of Launching Girder
¡P
Construction of Pump Sump E
¡P
Installation of Noise Barrier/enclosure
¡P
Modification of existing crosshead at Pier 17-18
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P
Cross wall sealing
¡P
Concreting of turret openings
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
¡P
Diaphragm wall construction
¡P
Site survey
Contract
no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under
FEP-10/364/2009B
¡P
Tree & root pruning works
¡P
Tree transplanting works,
¡P
Tree works within off-site nursery compound,
¡P
Drainage improvement works,
¡P
Sheet piling works,
¡P
Excavation and Lateral Support for U-structure,
¡P
Erection of noise absorption sheetings,
¡P
Pipe piling, ground pre-treatment, pre-boring works & jet grouting
works,
¡P
Utility diversion &
¡P
Construction of Bowling Green Office.
Contract
no. HY/2011/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
¡P
No physical construction activity on site
Noise
Monitoring
Air Monitoring
24hr TSP monitoring at CMA1b was
rescheduled from 14 August 2014 and 20 August 2014 to 15 August 2014 to 21
August 2014 respectively.
24hr TSP monitoring at CMA5a was
rescheduled from 14 August 2014 and 20 August 2014 to 15 August 2014 to 21
August 2014 respectively.
24hr TSP monitoring at MA1e was
rescheduled from 26 August 2014 to 27 August 2014.
Complaints, Notifications of Summons
and Successful Prosecutions
In addition, mobilization of PMEs was
performed at works area around Watson Road under HY/2009/19 from 00:45hrs to
01:30hrs on 30 July 2014. Total 1 no. of excavation machine and 1 no. of dump
truck were in operation. After reviewing relevant records and information
verified by RSS and the Construction Noise Permit (CNP) no.GW-RS0152-14, it was
considered the below condition of CNP GW-RS0152-14 was not fulfilled by the
Contractor of HY/2009/19. From around 00:45hrs to 01:30hrs on 30 July 2014, the
operation of PME(s) (1 no. of excavator and 1 no. of dump truck) under the
Contractor of HY/2009/19 on-site could not follow any given PME grouping
requirement(s) as stated in condition 3.a. and condition 3.d. in
no.GW-RS0152-14.
Site Inspections and Audit
Future Key Issues
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Drainage works
¡P
Tunnel works including scaffolding erection, excavation, OHVD
installation, roadside barriers, top and base slab construction, extract sheet
pile, waterproofing and backfill
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
Bridges construction
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under
FEP-02/364/2009
¡P
Stage 1 construction of tunnel structures
¡P
Stage 2 excavation and ELS works
¡P
Stage 3 construction of D-Wall
¡P
Demolition of the remaining East Bridge
¡P
pre-bored H piles
¡P
Excavation work
¡P
Pipe laying for discharge cooling main BF
Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Backfilling to Tunnel Portion 1.
¡P
Utility bridge load transfer for Box Culvert N1 & Cooling Watermains
¡P
Excavate and installation of ELS.
¡P
Pump test for continuing Tunnel Portion 2 excavation.
¡P
Bored pile construction.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Post tunnel construction at TS1 and TS2
¡P
Mined Tunnel drill-and-break works at East and West Portal
¡P
Permanent lining structure at West Portal of Mined Tunnel
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road works at Watson Road
¡P
Bored piling (Land)
¡P
Removal/ Installation of strut at ELS
¡P
Construction of Dolphin Cap
¡P
ELS for Cut &Cover Tunnel and EVB
¡P
Excavation of ELS continue
¡P
Laying of 1350f pipe
¡P
Pre-bored H-pile for Admin. Building continue
¡P
Parapet construction continue
¡P
Construction of TD bridge continue
¡P
Construction of Bridge E
¡P
Construction of Bride F4 and F5
¡P
Construction of Pump Sump E
¡P
Installation of Noise Barrier/enclosure
¡P
Modification of existing crosshead at Pier 17-18
¡P
IECL Road modification and removal of Median Barrier
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009/B
¡P
Diaphragm wall construction
¡P
Site survey
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009B
¡P
Tree & root pruning works
¡P
Tree transplanting works,
¡P
Tree works within off-site nursery compound,
¡P
Drainage improvement works,
¡P
Sheet piling works,
¡P
Excavation and Lateral Support for U-structure,
¡P
Erection of noise absorption sheetings,
¡P
Pipe piling, ground pre-treatment, pre-boring works & jet grouting
works,
¡P
Utility diversion,
¡P
Construction of Bowling Green Office and
¡P
Temporary Traffic Arrangement & paving works for Victoria Park Road.
Contract no. HY/2011/08 ¡V Central - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
¡P
No physical construction activity on site
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/C and
Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A,
FEP-08/364/2009/A, FEP-09/364/2009/B, FEP-10/364/2009B and FEP-11/364/2009B to implement the Environmental Monitoring and Audit (EM&A)
programme as stipulated in the EM&A Manual of the approved Environmental
Impact Assessment (EIA) Report for Wan Chai Development phase II and
Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit
Requirements¡¨ under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/B, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A, FEP-09/364/2009B, FEP-10/364/2009B
and FEP-11/364/2009B during the period July 2014 to August 2014. The cut-off
date of reporting is at 27th of each reporting month
Section
1 Introduction ¡V
details the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key personnel
during the reporting period.
Section
3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results obtained
in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Site Inspection ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and
¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called
¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested east-west Connaught Road Central/Harcourt Road / Gloucester
Road Corridor (the Corridor) which is currently operating beyond its capacity.
The CWB will provide relief to the existing congestion along the Corridor and
cater for the anticipated growth of traffic on Hong Kong Island. Without the
CWB and its access roads, there will not be sufficient capacity to serve the
heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central ¡V Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
¡P
A dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
¡P
The Central Interchange near the Rumsey Street Flyover to provide road
connections to the Central area;
¡P
Tunnel control buildings and ventilation buildings;
¡P
Slip roads to connect the CWB to the local road system in the Wan Chai
North and Causeway Bay area;
¡P
Associated road lighting, road signing, traffic control and surveillance
system; and
¡P
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated
Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason
for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in
length |
DP2 |
Road P2 and other roads which are classified as
primary/district distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging
works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging
operation less than 100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter
more than 1,200 mm and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from
Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a
seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further
Environmental Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table
2.2 Details of
Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield
Depot ¡V Advanced piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu
Street and Man Kwong Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works |
DP1,
DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East(CWB Tunnel) |
DP1 |
26
April 2011 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) |
DP1,DP3 |
13
July 2011 |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link |
DP1 |
24
March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai
Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel ¡V Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) ¡VTunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning |
DP1 |
To be commenced tentatively on 4th
quarter in 2014. |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587
1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912
3010 |
|
Lam Woo & CO.,
LTD. |
Contractor under Contract no. HY/2009/17 |
General Manager |
Mr. Thomas Tang |
6111 5351 |
2566
7522 |
Contractor¡¦s Representative |
Mr. Chung Man Shek |
2566 4866 |
|||
Site Agent |
Mr. Tong Au |
9725 5874 |
|||
Environmental Officer |
Dr. Priscilla Choy |
9161 7287 |
|||
Environmental Supervisor |
Mr. Tam Chun Pong |
6461 3062 |
|||
Chun Wo ¡V Leader
Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Mr. Simon Liu |
2162 9909 |
2634
1626 |
Construction
Manager |
Mr. Terry Wong |
9757 9846 |
|||
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack
Chu |
9775 2467 |
|||
Environmental
Officer |
Ms. Wendy
Ng |
9103
2370 |
|||
Assistant
Environmental Engineer |
Ms. Connie Chan |
9047 6148 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827
9996 |
Project Manager |
Mr. Alfred Leung |
3658-3022 |
|||
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint
Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570
8013 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Construction Manager (Marine) |
Mr. William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Mr. Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Mr. Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Mr. Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Desmond Sze |
2214
7700 |
|
Deputy Site Agent |
Mr. Roger Wong |
2214
7703 |
|||
Environmental Officer |
Ms. Lighting Chan |
2823
1161 |
|||
Environmental Engineer |
Mr. David Hung |
2214
7721 |
|||
Assistant Environmental Engineer |
Mr. Penny Yiu |
2214
7738 |
|||
Environmental Supervisor |
Mr. K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Mr. Ray Cheng |
2214 7742 |
|||
Environmental Supervisor |
Mr. K. W. Lee |
6461 4623 |
|||
Environmental Supervisor |
Mr. Dorothy Shing |
2214
7705 |
|||
Environmental Supervisor |
Mr. C. Y. Au Yeung |
6461
8631 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. K C Cheung |
2823 7813 |
2865 5229 |
Site Manager |
Mr. J.H. Chen |
3557 6368 |
2566 2192 |
||
Contractor¡¦s
Representative |
Mr. Gene Cheung |
3557
6395 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Ms. Esther Choi |
35576348 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529
2880 |
Site
Agent |
Mr. Eric Yip |
2529 2068 |
|||
Environmental
Officer |
Mr. Clement Pang |
9481 6024 |
|||
Environmental
Supervisor |
Mr.
Jacky Cheung |
9735 9200 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. Andrew
TSE |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Victor
WU |
9193
8871 |
|||
Deputy
Project Manager |
Mr. George
CHEUNG |
9268
1918 |
|||
Site
Agent |
Mr. Paul
LUI |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Ching
Man, CHAN |
6050
4919 |
|||
China State |
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung
Kit Cheung |
3557
6399 |
2566
8061 |
Project
Manager |
Chan
Ying Lun |
9812
0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467
4299 |
|||
Site
Agent |
Dr. Dave
Chan |
3467
4277 |
|||
Environmental
Officer |
Mr. C.M.
Wong |
3557
6464 |
|||
Environmental
Supervisor |
Mr. Louis
Lam Tsz Kwan |
3557
6470 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Project
Manager |
Paul
Evans |
2823
1111 |
21406799 |
Site
Agent |
Colman Wong |
9730
0806 |
|||
Environmental
Officer |
David
Hung |
9765 6151 |
|||
Environmental
Supervisor |
Penny Yiu |
2214
7738 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics
Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882
3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. HY/2009/18 - Central - Wan
Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Drainage works
¡P
Tunnel works including scaffolding erection, excavation, OHVD
installation, roadside barriers, top and base slab construction
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
Bridges construction
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
¡P
Stage 1 construction of tunnel structures
¡P
Stage 2 installation of pre-bored H-piles
¡P
Stage 2 installation of sheet pile at exhaust duct
¡P
Installation of dewatering well in Stage 2
¡P
Stage 2 excavations and ELS works
¡P
Demolition works of existing HKCEC pump house (Kiu Lok Portion)
¡P
Demolition of 10 nos. pump cells at Convention Avenue
¡P
Stage 3 construction of D-Wall
¡P
Stage 3 installation of pre-bored H-piles
¡P
Discharge cooling mainlaying works for BI, BG & BF
¡P
S8B and S9 saltwater mainlaying works
Contract
no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Backfilling work for tunnel
¡P
Loading transfer of utility bridge for DSD Sewage Outfall pipes and WSD
Intake Culvert
¡P
Removal of Strut
¡P
Excavation for Tunnel Portion
¡P
Installation of dewatering system
¡P
Bored piling works
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Dismantling of struts and backfilling at TS4 & TPCWAE
¡P
Mined Tunnel drill-and-break works and installation of steel ribs at
East and West Portal
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
¡P
Road works at Watson Road
¡P
Bored piling (Land)
¡P
Removal/Installation of strut at ELS
¡P
Construction of Dolphin Cap
¡P
ELS for Cut &Cover Tunnel and EVB
¡P
Excavation of ELS continue
¡P
Laying of 1350f pipe
¡P
Pre-bored H-pile for Admin. Building continue
¡P
Parapet construction continue
¡P
Wing slab extension continue
¡P
Construction of TD bridge continue
¡P
Construction of Bridge E
¡P
Construction of Bride F4 and F5
¡P
Dismantling of Launching Girder
¡P
Construction of Pump Sump E
¡P
Installation of Noise Barrier/enclosure
¡P
Modification of existing crosshead at Pier 17-18
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
¡P
Cross wall sealing
¡P
Concreting of turret openings
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009B
¡P
Diaphragm wall construction
¡P
Site survey
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009B
¡P
Tree & root pruning works
¡P
Tree transplanting works,
¡P
Tree works within off-site nursery compound,
¡P
Drainage improvement works,
¡P
Sheet piling works,
¡P
Excavation and Lateral Support for U-structure,
¡P
Erection of noise absorption sheetings,
¡P
Pipe piling, ground pre-treatment, pre-boring works & jet grouting
works,
¡P
Utility diversion &
¡P
Construction of Bowling Green Office.
Contract no. HY/2011/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
¡P
No physical construction activity on site
2.4.4.
In coming reporting month, the principal work activities of individual
contracts are anticipated as follows:
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Drainage works
¡P
Tunnel works including scaffolding erection, excavation, OHVD
installation, roadside barriers, top and base slab construction, extract sheet
pile, waterproofing and backfill
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
Bridges construction
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
¡P
Stage 1 construction of tunnel structures
¡P
Stage 2 excavation and ELS works
¡P
Stage 3 construction of D-Wall
¡P
Demolition of the remaining East Bridge
¡P
pre-bored H piles
¡P
Excavation work
¡P
Pipe laying for discharge cooling main BF
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P
Backfilling to Tunnel Portion 1.
¡P
Utility bridge load transfer for Box Culvert N1 & Cooling Watermains
¡P
Excavate and installation of ELS.
¡P
Pump test for continuing Tunnel Portion 2 excavation.
¡P
Bored pile construction.
Contract
no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
¡P
Post tunnel construction at TS1 and TS2
¡P
Mined Tunnel drill-and-break works at East and West Portal
¡P
Permanent lining structure at West Portal of Mined Tunnel
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
¡P
Road works at Watson Road
¡P
Bored piling (Land)
¡P
Removal/ Installation of strut at ELS
¡P
Construction of Dolphin Cap
¡P
ELS for Cut &Cover Tunnel and EVB
¡P
Excavation of ELS continue
¡P
Laying of 1350f pipe
¡P
Pre-bored H-pile for Admin. Building continue
¡P
Parapet construction continue
¡P
Construction of TD bridge continue
¡P
Construction of Bridge E
¡P
Construction of Bride F4 and F5
¡P
Construction of Pump Sump E
¡P
Installation of Noise Barrier/enclosure
¡P
Modification of existing crosshead at Pier 17-18
¡P
IECL Road modification and removal of Median Barrier
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
¡P
Sealing at turret openings
Contract no. HK/2012/08 ¡V Wan Chai Development
Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B
¡P
Diaphragm wall construction
¡P
Site survey
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009B
¡P
Tree & root pruning works
¡P
Tree transplanting works,
¡P
Tree works within off-site nursery compound,
¡P
Drainage improvement works,
¡P
Sheet piling works,
¡P
Excavation and Lateral Support for U-structure,
¡P
Erection of noise absorption sheetings,
¡P
Pipe piling, ground pre-treatment, pre-boring works & jet grouting
works,
¡P
Utility diversion,
¡P
Construction of Bowling Green Office and
¡P
Temporary Traffic Arrangement & paving works for Victoria Park Road.
Contract no. HY/2011/08 ¡V Central - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
¡P
No physical construction activity on site
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Superseded |
Environmental Permit |
EP-364/2009/C |
11 Jul 2014 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further
Environmental Permit |
FEP-06/356/2009 |
5 March 2013 |
Valid |
Further
Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Surrendered |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Valid |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai
Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP was surrendered by the Contractor on 25 April 2013.
Contract no. 04/HY/2006 ¡V Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP was surrendered by the
Contractor on 11 February 2011.
Contract no.
HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
3.1.5.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5
Table
3.4 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-pilling equipment |
GW-RS0111-14 |
11 Feb 2014 |
15 Feb 2014 to 14 Aug 2014 |
Cancelled |
GW-RS0200-14 |
18 Mar 2014 |
21 Mar 2014 to |
Valid |
|
GW-RS0317-14 |
7 Apr 2014 |
8 Apr 2014 to |
Valid |
|
GW-RS0362-14 |
17 Apr 2014 |
20 Apr 2014 to 8 Oct 2014 |
Valid |
|
GW-RS0381-14 |
8 Apr 2014 |
9 May 2014 to 11 Nov 2014 |
Valid |
|
GW-RS0435-14 |
30 Apr 2014 |
13 May 2014 to 12 Nov 2014 |
Valid |
|
GW-RS0437-14 |
7 May 2014 |
8 May 2014 to |
Valid |
|
|
GW-RS0451-14 |
5 May 2014 |
12 May 2014 to 11 Nov 2014 |
Valid |
|
GW-RS0462-14 |
17 Apr 2014 |
18 Apr 2014 to 17 Oct 2014 |
Valid |
|
GW-RS0498-14 |
22 May 2014 |
24 May 2014 to 22 Nov 2014 |
Cancelled |
|
GW-RS0875-14 |
|