Contract No: HK/2011/07 Wanchai Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing Work (Stage
2) Environmental
Permit no. EP-364/2009/C, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/A,
FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B Monthly Environmental Monitoring & Audit Report
- april 2015 -
|
CLIENTS: |
|
Civil Engineering
and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
12 May 2015 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3.
status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring Results
6.3 Review
of the Reasons for and the Implications of Non-compliance
6.4 Summary
of action taken in the event of and follow-up on non-compliance
7.
Cumulative Construction Impact due to the Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table
2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.3 Summary
of submission status under FEP-02/364/2009
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.5 Summary
of submission status under FEP-01/364/2009
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Table 3.7 Summary
of submission status under FEP-05/364/2009/A
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table 3.9 Summary
of submission status under FEP-06/364/2009/A
Table 3.10 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.11
Summary of submission status under FEP-07/364/2009/A
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.13 Summary of submission status under FEP-09/364/2009/B
Table 3.14 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.15 Summary of submission status under
FEP-10/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HY/2011/08
Table 3.17 Summary of submission status under FEP-11/364/2009
Table 4.1 Noise Monitoring
Stations
Table 4.2 Real
Time Noise Monitoring Stations
Table 4.3 Air
Monitoring Stations
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/18
Table 5.2 Noise
Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Table 5.3 Noise
Monitoring Stations for Contract no. HY/2009/15
Table 5.4 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table 5.6 Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.7 Real
Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Air
Monitoring Stations for Contract no. HY/2009/18
Table 5.9 Air
Monitoring Station for Contract no. HK/2009/01
Table 5.10 Air Monitoring
Station for Contract no. HK/2009/02
Table 5.11 Air Monitoring
Station for Contract no. HY/2009/15
Table 5.12 Air Monitoring
Stations for Contract no. HY/2009/19
Table 5.13 Air
Monitoring Station for Contract no. HK/2012/08
Table 5.14 Air
Monitoring Station for Contract no. HY/2010/08
Table 5.15 Air
Monitoring Stations for Contract no. HY/2011/08
Table 5.16 Details
of Waste Disposal for Contract no. HK/2009/01
Table 5.17 Details
of Waste Disposal for Contract no. HK/2009/02
Table 5.18 Details
of Waste Disposal for Contract no. HY/2009/18
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/15
Table 5.20 Details
of Waste Disposal for Contract no. HY/2009/19
Table 5.21 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.22 Details of Waste Disposal
for Contract no. HY/2010/08
Table 5.23 Details of Waste Disposal for Contract no. HY/2011/08
Table 8.1 Summary of Environmental
Inspections for Contract no. HY/2009/15
Table 8.4
Summary of Environmental Inspections for Contract no. HK/2009/01
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.7 Summary of Environmental Inspections for
Contract no. HK/2012/08
Table 8.8 Summary of Environmental Inspections for Contract no. HY/2010/08
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring
Results and Graphical Presentations
Appendix
5.4 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of
Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
ˇP
Planting trees and shrubs
ˇP
Transplanting of trees
ˇP
Drainage works
ˇP
Trough structure construction including excavation, concreting and
waterproofing and backfill
ˇP
Road works
ˇP
Bridges construction
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
ˇP
Stage 1 Construction of roadside barrier and defect rectification
ˇP
Stage 2 Backfilling of retaining wall RW1 at slip road 2
ˇP
Stage 2 ELS and demolition works of bulkhead wall at Bay 10
ˇP
Stage 2 Steel fixing and formwork erection at Bay 7, 8 and 9 OHVD
ˇP
Stage 2 Construction of exhaust duct at slip road 3
ˇP
Stage 3 ELS excavation and strut installing works
ˇP
Stage 3 Base slab construction of box culvert Bay 2 and Bay 7
ˇP
Stage 3 Construction of box culvert Bay 1
ˇP
Stage 3 Construction of Outfall at Expo Drive East and backfilling work
ˇP
Sewerage pipeline at Fenwick Pier Street
ˇP
Pipe laying works for Cooling Main (BI/BG/BF)
ˇP
Work zone X1-1 to X1-4 at Fleming Road
ˇP
Pipe laying works of C3-1B and backfilling works of C3-1A
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
ˇP
Bulkhead wall breakthrough by Robot at the north side
ˇP
Bulkhead wall breakthrough by saw cut and wire cut
ˇP
Waterproofing application for north and south walls
ˇP
Rebar fixing at the north wall from Bay 1 to Bay 4
ˇP
Rebar fixing at the south wall of Bay 3 and Bay 4
ˇP
Formworks erection was now in progress at central wall of Bay 4, at south
wall and north wall of Bay 1
ˇP
Concrete cast for central wall at Bay 1, Bay 2 and Bay 3
ˇP
Excavation at the west side and struts installation.
ˇP
Packer tests at the east side
ˇP
Excavation at the east side and welding for struts installation
ˇP
Installation of observation well, dewatering well, piezometer at the east
side
ˇP
Pump test set up and schedule for pump test
Contract no. HY/2009/15 -
Central-Wanchai Bypass ˇV Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
ˇP
Mined Tunnel drill-and-break works at East and West Portal
ˇP
Permanent lining structure at Mined Tunnel
ˇP
Construction of diaphragm wall at TPCWAW
ˇP
Fabrication of first layer of ELS for TPCWAW
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
ˇP
Demolition of ELS for Cut &Cover Tunnel and EVB
ˇP
Pre-bored H-pile for Approach Ramp
ˇP
IECL Road modification and removal of Median Barrier
ˇP
Abutment D12 construction
ˇP
Saw cut of parapet at IEC East bound
ˇP
Construction of TA2 bridge
ˇP
Construction of temporary steel tower for IEC demolition
ˇP
Saw cut of existing west fast lane of IEC bridge
ˇP
Demolition of bulk head wall between C15 to C19
ˇP
Column modification at F1 to F8
Contract
no. HK/2012/08 ˇV Wan Chai Development Phase II ˇV Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
ˇP
Diaphragm wall construction
ˇP
Installation of dewatering wells
ˇP
Grouting
ˇP
Construction of ELS at MVB
ˇP
Excavation and installation of lateral support at top-down area
ˇP
Pre-bored H-pile construction
Contract
no. HY/2010/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel (Slip Road 8) under
FEP-10/364/2009B
ˇP
Drainage improvement works,
ˇP
Sheet piling works,
ˇP
Excavation and Lateral Support for U-structure works,
ˇP
Erection of noise absorption sheetings,
ˇP
Pipe piling & grouting works,
ˇP
Utility diversion works,
ˇP
Waterproofing works,
ˇP
Provisional of Bowling Green,
ˇP
Milling & paving works for TTA stage II ˇV westbound &.
ˇP
Construction of ramp for TTA stage II ˇV eastbound
ˇP
und
Contract
no. HY/2011/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
ˇP
West Ventilation Building structure construction
ˇP
Install VE panels bracket and thermal barrier for Tunnel
ˇP
Construct reinforcement concrete structure for EVS
Noise Monitoring
Air Monitoring
Complaints, Notifications of Summons
and Successful Prosecutions
ˇ§I live in a building next to Gloucester
Road in Causeway Bay. Recently, I am suffering from unnecessary light source
from the construction site. The banners of the construction companies are
always illuminated with very bright lights.ˇ¨
Site Inspections and Audit
Future Key Issues
Contract no. HY/2009/18 ˇV Central ˇV Wan
Chai Bypass (CWB) ˇV Central Interchange under FEP-05/364/2009/A
ˇP
Planting trees and shrubs
ˇP
Transplanting of trees
ˇP
Drainage works
ˇP
Retaining wall and trough
structure construction including excavation, concreting,
waterproofing and backfill
ˇP
Road works
ˇP
Bridges construction
Contract no. HK/2009/01 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre ˇV Tunnel Works under
FEP-02/364/2009
ˇP
Stage 1 Construction of roadside barrier and backfilling on top of CWB
tunnel
ˇP
Stage 2 Construction of roof slab Bay 7, 8 and 9
ˇP
Stage 2 Construction of base slab Bay 10
ˇP
Stage 2 Construction of exhaust duct
ˇP
Stage 3 ELS excavation and strut installing works
ˇP
Stage 3 Box culvert diversion
ˇP
Cooling Main Installation (BI/BG) at Expo Drive East
ˇP
Removal of abandoned cooling main (P7/P8) at Convention Avenue
ˇP
Sewerage Pipeline A3-4B at Fenwick Pier Street
ˇP
Installation works for Cooling Main (BI/BG) / Salt Watermain (S3)/ Fresh
Watermain (F3)
ˇP
Reinstatement of Expo Drive East
Contract no. HK/2009/02 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
ˇP
Continue tunnel structure works, i.e. concrete cast at side walls,
formworks and concreting at OHVD base slab
ˇP
Continue bulk head wall BW2 breakthrough.
ˇP
Complete pumping test
ˇP
Continue Strut layer S2 excavation and ELS installation at both sides.
Contract no. HY/2009/15 ˇV Central-Wanchai Bypass ˇV
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
ˇP
Construction of OHVD and base slab at Mined Tunnel
ˇP
Permanent lining structure at Mined Tunnel
ˇP
Inner bench excavation
ˇP
Construction of diaphragm wall at TPCWAW
ˇP
Installation of king post
ˇP
Fabrication of ELS steel works for TPCWAW
Contract no. HY/2009/19 ˇV Central ˇV Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
ˇP
Demolition of ELS for Cut &Cover Tunnel and EVB
ˇP
Pre-bored H-pile for Approach Ramp
ˇP
Abutment D12 construction
ˇP
Saw cut of parapet at IEC East bound
ˇP
Construction of TA2 bridge
ˇP
Construction of temporary steel tower for IEC demolition
ˇP
Saw cut of existing west bound of IEC bridge
ˇP
Demolition of bulk head wall between C15 to C19
ˇP
Column modification at F1 to F8
ˇP
Demolition of IEC west bound deck
Contract no. HK/2012/08 ˇV Wan Chai
Development Phase II ˇV Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009/B
ˇP
Diaphragm wall construction
ˇP
Installation of dewatering wells
ˇP
Grouting
ˇP
Construction of ELS at MVB
ˇP
Excavation and installation of lateral support at top-down area
ˇP
Pre-bored H-pile construction
Contract no. HY/2010/08 ˇVCentral - Wan
Chai Bypass (CWB) ˇVTunnel (Slip Road 8) under FEP-10/364/2009
ˇP
Tree protection works next to existing BGO
ˇP
Drainage improvement works,
ˇP
Sheet piling works,
ˇP
Excavation and Lateral Support for U-structure,
ˇP
Renovation works for Bowling Green Office,
ˇP
Pipe piling & grouting works,
ˇP
Utility diversion works,
ˇP
Waterproofing works,
ˇP
Demolition works of existing BGO &
ˇP
Provisional of Bowling Green
ˇP
Contract no. HY/2011/08 ˇV Central - Wan
Chai Bypass (CWB) ˇVTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
ˇP
West Ventilation Building structure construction
ˇP
Install VE panels bracket and thermal barrier for Tunnel
ˇP
Construct reinforcement concrete structure for EVS
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/C and
Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A,
FEP-09/364/2009/B, FEP-10/364/2009B and FEP-11/364/2009B to implement the Environmental Monitoring and Audit (EM&A)
programme as stipulated in the EM&A Manual of the approved Environmental
Impact Assessment (EIA) Report for Wan Chai Development phase II and
Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and ˇ§Environmental Monitoring and Audit
Requirementsˇ¨ under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/B, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A, FEP-09/364/2009B, FEP-10/364/2009B
and FEP-11/364/2009B during the period March 2015 to April 2015. The cut-off
date of reporting is at 27th of each reporting month
Section
1 Introduction ˇV
details the scope and structure of the report.
Section
2 Project
Background ˇV summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ˇV
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ˇV summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ˇV summarizes the monitoring results obtained
in the reporting period.
Section
6 Compliance
Audit ˇV summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects ˇV summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Environmental Site Audit ˇV
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
ˇV summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
ˇ§Wan Chai Development phase II and Central-Wan Chai Bypassˇ¨ and
ˇ§Central-Wan Chai Bypass and Island Eastern Corridor Linkˇ¨ (hereafter called
ˇ§the Projectˇ¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested east-west Connaught Road Central/Harcourt Road / Gloucester
Road Corridor (the Corridor) which is currently operating beyond its capacity.
The CWB will provide relief to the existing congestion along the Corridor and
cater for the anticipated growth of traffic on Hong Kong Island. Without the
CWB and its access roads, there will not be sufficient capacity to serve the
heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central ˇV Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
ˇP
A dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
ˇP
The Central Interchange near the Rumsey Street Flyover to provide road
connections to the Central area;
ˇP
Tunnel control buildings and ventilation buildings;
ˇP
Slip roads to connect the CWB to the local road system in the Wan Chai
North and Causeway Bay area;
ˇP
Associated road lighting, road signing, traffic control and surveillance
system; and
ˇP
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason
for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in
length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging
works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging
operation less than 100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter
more than 1,200 mm and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from
Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a
seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further
Environmental Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ˇV Wan Chai Bypass (CWB) at FEHD Whitfield
Depot ˇV Advanced piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central ˇV Wan Chai Bypass (CWB) ˇV Central
Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu
Street and Man Kwong Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ˇV Central ˇV Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre ˇV Tunnel Works |
DP1,
DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ˇV Central ˇV Wan
Chai Bypass at Wan Chai East(CWB Tunnel) |
DP1 |
26
April 2011 |
HY/2009/15 |
Central-Wanchai Bypass ˇV Tunnel (Causeway Bay
Typhoon Shelter Section) |
DP1,DP3 |
13
July 2011 |
HY/2009/19 |
Central ˇV Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link |
DP1 |
24
March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai
Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel ˇV Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) ˇVTunnel Buildings,
Systems and Fittings, and Works Associated with Tunnel Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineerˇ¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587
1877 |
Engineerˇ¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912
3010 |
|
Chun Wo ˇV Leader
Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Mr. Simon Liu |
2162 9909 |
2634
1626 |
Construction
Manager |
Mr. Terry Wong |
9757 9846 |
|||
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack
Chu |
9775 2467 |
|||
Environmental
Officer |
Ms. Wendy
Ng |
9103
2370 |
|||
Assistant
Environmental Engineer |
Ms. Connie Chan |
9047 6148 |
|||
Chun Wo ˇV CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827
9996 |
Project Manager |
Mr. Alfred Leung |
3658-3022 |
|||
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint
Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570
8013 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Construction Manager (Marine) |
Mr. William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Mr. Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Mr. Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Mr. Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214
7700 |
|
Deputy Site Agent |
Mr. Bob Yeung |
2214
7703 |
|||
Environmental Officer |
Ms. Lighting Chan |
2823
1161 |
|||
Environmental Engineer |
Mr. Chris Chan |
2214
7721 |
|||
Assistant Environmental Engineer |
Mr. Penny Yiu |
2214
7738 |
|||
Environmental Supervisor |
Mr. K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Mr. Ray Cheng |
2214 7742 |
|||
Environmental Supervisor |
Mr. K. W. Lee |
6461 4623 |
|||
Environmental Supervisor |
Mr. Dorothy Shing |
2214
7705 |
|||
Environmental Supervisor |
Mr. C. Y. Au Yeung |
6461
8631 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2865 5229 |
Site Manager |
Mr. Y. Huo |
3557 6368 |
2566 2192 |
||
Contractorˇ¦s
Representative |
Mr. Gene Cheung |
3557
6395 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Ms. Esther Choi |
35576348 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N.
Lai |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Eddie
Chung |
9193
8871 |
|||
Site
Agent |
Mr. Keith
Tse |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Y.L.
Ho |
6050
4919 |
|||
China State |
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung
Kit Cheung |
3557
6399 |
2566
8061 |
Project
Manager |
Chan
Ying Lun |
9812
0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467
4299 |
|||
Site
Agent |
Dr. Dave
Chan |
3467
4277 |
|||
Environmental
Officer |
Mr. C.M.
Wong |
3557
6464 |
|||
Environmental
Supervisor |
Mr. Louis
Lam Tsz Kwan |
3557
6470 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Project
Manager |
Paul
Evans |
2823 1111 |
21406799 |
Site
Agent |
Colman Wong |
2140
6799 |
|||
Environmental
Officer |
Malcom
Leung |
2214 7721 |
|||
Environmental
Supervisor |
Penny Yiu |
2214
7738 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics
Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882
3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. HY/2009/18 - Central - Wan
Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
ˇP
Planting trees and shrubs
ˇP
Transplanting of trees
ˇP
Drainage works
ˇP
Trough structure construction including excavation, concreting and
waterproofing and backfill
ˇP
Road works
ˇP
Bridges construction
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
ˇP
Stage 1 Construction of roadside barrier and defect rectification
ˇP
Stage 2 Backfilling of retaining wall RW1 at slip road 2
ˇP
Stage 2 ELS and demolition works of bulkhead wall at Bay 10
ˇP
Stage 2 Steel fixing and formwork erection at Bay 7, 8 and 9 OHVD
ˇP
Stage 2 Construction of exhaust duct at slip road 3
ˇP
Stage 3 ELS excavation and strut installing works
ˇP
Stage 3 Base slab construction of box culvert Bay 2 and Bay 7
ˇP
Stage 3 Construction of box culvert Bay 1
ˇP
Stage 3 Construction of Outfall at Expo Drive East and backfilling work
ˇP
Sewerage pipeline at Fenwick Pier Street
ˇP
Pipe laying works for Cooling Main (BI/BG/BF)
ˇP
Work zone X1-1 to X1-4 at Fleming Road
ˇP
Pipe laying works of C3-1B and backfilling works of C3-1A
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
ˇP
Bulkhead wall breakthrough by Robot at the north side
ˇP
Bulkhead wall breakthrough by saw cut and wire cut
ˇP
Waterproofing application for north and south walls
ˇP
Rebar fixing at the north wall from Bay 1 to Bay 4
ˇP
Rebar fixing at the south wall of Bay 3 and Bay 4
ˇP
Formworks erection was now in progress at central wall of Bay 4, at south
wall and north wall of Bay 1
ˇP
Concrete cast for central wall at Bay 1, Bay 2 and Bay 3
ˇP
Excavation at the west side and struts installation.
ˇP
Packer tests at the east side
ˇP
Excavation at the east side and welding for struts installation
ˇP
Installation of observation well, dewatering well, piezometer at the east
side
ˇP
Pump test set up and schedule for pump test
Contract no. HY/2009/15 - Central-Wanchai Bypass ˇV Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
ˇP
Mined Tunnel drill-and-break works at East and West Portal
ˇP
Permanent lining structure at Mined Tunnel
ˇP
Construction of diaphragm wall at TPCWAW
ˇP
Fabrication of first layer of ELS for TPCWAW
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
ˇP
Demolition of ELS for Cut &Cover Tunnel and EVB
ˇP
Pre-bored H-pile for Approach Ramp
ˇP
IECL Road modification and removal of Median Barrier
ˇP
Abutment D12 construction
ˇP
Saw cut of parapet at IEC East bound
ˇP
Construction of TA2 bridge
ˇP
Construction of temporary steel tower for IEC demolition
ˇP
Saw cut of existing west fast lane of IEC bridge
ˇP
Demolition of bulk head wall between C15 to C19
ˇP
Column modification at F1 to F8
Contract no. HK/2012/08 ˇV Wan Chai
Development Phase II ˇV Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009B
ˇP
Diaphragm wall construction
ˇP
Installation of dewatering wells
ˇP
Grouting
ˇP
Construction of ELS at MVB
ˇP
Excavation and installation of lateral support at top-down area
ˇP
Pre-bored H-pile construction
Contract no. HY/2010/08 ˇVCentral - Wan
Chai Bypass (CWB) ˇVTunnel (Slip Road 8) under FEP-10/364/2009B
ˇP
Drainage improvement works,
ˇP
Sheet piling works,
ˇP
Excavation and Lateral Support for U-structure works,
ˇP
Erection of noise absorption sheetings,
ˇP
Pipe piling & grouting works,
ˇP
Utility diversion works,
ˇP
Waterproofing works,
ˇP
Provisional of Bowling Green,
ˇP
Milling & paving works for TTA stage II ˇV westbound &.
ˇP
Construction of ramp for TTA stage II ˇV eastbound
Contract no. HY/2011/08 ˇVCentral - Wan
Chai Bypass (CWB) ˇVTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
ˇP
West Ventilation Building structure construction
ˇP
Install VE panels bracket and thermal barrier for Tunnel
ˇP
Construct reinforcement concrete structure for EVS
2.4.4.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract
no. HY/2009/18 ˇV Central ˇV Wan Chai Bypass (CWB) ˇV Central Interchange under
FEP-05/364/2009/A
ˇP
Planting trees and shrubs
ˇP
Transplanting of trees
ˇP
Drainage works
ˇP
Retaining wall and trough
structure construction including excavation, concreting,
waterproofing and backfill
ˇP
Road works
ˇP
Bridges construction
Contract no. HK/2009/01 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre ˇV Tunnel Works under
FEP-02/364/2009
ˇP
Stage 1 Construction of roadside barrier and backfilling on top of CWB
tunnel
ˇP
Stage 2 Construction of roof slab Bay 7, 8 and 9
ˇP
Stage 2 Construction of base slab Bay 10
ˇP
Stage 2 Construction of exhaust duct
ˇP
Stage 3 ELS excavation and strut installing works
ˇP
Stage 3 Box culvert diversion
ˇP
Cooling Main Installation (BI/BG) at Expo Drive East
ˇP
Removal of abandoned cooling main (P7/P8) at Convention Avenue
ˇP
Sewerage Pipeline A3-4B at Fenwick Pier Street
ˇP
Installation works for Cooling Main (BI/BG) / Salt Watermain (S3)/ Fresh
Watermain (F3)
ˇP
Reinstatement of Expo Drive East
Contract no. HK/2009/02 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
ˇP
Continue tunnel structure works, i.e. concrete cast at side walls,
formworks and concreting at OHVD base slab
ˇP
Continue bulk head wall BW2 breakthrough.
ˇP
Complete pumping test
ˇP
Continue Strut layer S2 excavation and ELS installation at both sides.
Contract no. HY/2009/15 ˇV Central-Wanchai Bypass ˇV
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
ˇP
Construction of OHVD and base slab at Mined Tunnel
ˇP
Permanent lining structure at Mined Tunnel
ˇP
Inner bench excavation
ˇP
Construction of diaphragm wall at TPCWAW
ˇP
Installation of king post
ˇP
Fabrication of ELS steel works for TPCWAW
Contract no. HY/2009/19 ˇV Central ˇV Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
ˇP
Demolition of ELS for Cut &Cover Tunnel and EVB
ˇP
Pre-bored H-pile for Approach Ramp
ˇP
Abutment D12 construction
ˇP
Saw cut of parapet at IEC East bound
ˇP
Construction of TA2 bridge
ˇP
Construction of temporary steel tower for IEC demolition
ˇP
Saw cut of existing west bound of IEC bridge
ˇP
Demolition of bulk head wall between C15 to C19
ˇP
Column modification at F1 to F8
ˇP
Demolition of IEC west bound deck
Contract
no. HK/2012/08 ˇV Wan Chai Development Phase II ˇV Central- Wan Chai Bypass at Wan
Chai West under FEP-09/364/2009/B
ˇP
Diaphragm wall construction
ˇP
Installation of dewatering wells
ˇP
Grouting
ˇP
Construction of ELS at MVB
ˇP
Excavation and installation of lateral support at top-down area
ˇP
Pre-bored H-pile construction
Contract no. HY/2010/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel (Slip
Road 8) under FEP-10/364/2009
ˇP
Tree protection works next to existing BGO
ˇP
Drainage improvement works,
ˇP
Sheet piling works,
ˇP
Excavation and Lateral Support for U-structure,
ˇP
Renovation works for Bowling Green Office,
ˇP
Pipe piling & grouting works,
ˇP
Utility diversion works,
ˇP
Waterproofing works,
ˇP
Demolition works of existing BGO &
ˇP
Provisional of Bowling GreenˇV eastbound
Contract no. HY/2011/08 ˇV Central - Wan Chai Bypass (CWB) ˇVTunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009B
ˇP
West Ventilation Building structure construction
ˇP
Install VE panels bracket and thermal barrier for Tunnel
ˇP
Construct reinforcement concrete structure for EVS
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of the current status
on licences and/or permits on environmental protection pertinent to the Project
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Superseded |
Environmental Permit |
EP-364/2009/C |
11 Jul 2014 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Surrendered |
Further
Environmental Permit |
FEP-06/356/2009 |
5 March 2013 |
Valid |
Further
Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Surrendered |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Surrendered |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ˇV Central ˇV Wan Chai
Bypass (CWB) at FEHD Whitfield Depot ˇV Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.
Contract no. 04/HY/2006 ˇV Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP-04/HY/2006 was
surrendered by the Contractor on 11 February 2011.
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
3.1.5. The construction works was completed, and the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
Contract no.
HK/2009/01 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre ˇV Tunnel Works under FEP-02/364/2009
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.2 and Table 3.3
Table 3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-pilling equipment |
GW-RS0243-15 |
16 Mar 2015 |
25 Mar 2015 to 24 Sept 2015 |
Valid |
GW-RS1056-14 |
29 Sept 2014 |
08 Oct 2014 to 7 April 2015 |
Cancelled |
|
GW-RS1274-14 |
17 Nov 2014 |
17 Nov 2014 to 16 May 2015 |
Valid |
|
GW-RS1051-14 |
29 Sept 2014 |
9 Oct 2014 to 8 April 2015 |
Expired |
|
GW-RS1222-14 |
05 Nov 2014 |
08 Nov 2014 to 07 May 2015 |
Valid |
|
GW-RS1309-14 |
24 Nov 2014 |
26 Nov 2014 to 25 May 2015 |
Valid |
|
|
GW-RS1472-14 |
2 Jan 2015 |
22 Jan 2015 to 21 Jul 2015 |
Cancelled |
|
GW-RS0079-15 |
27 Jan 2015 |
16 Feb 2015 to 14 Aug 2015 |
Valid |
|
GW-RS0074-15 |
22 Jan
2015 |
10 Feb 2015 to 9 Aug 2015 |
Valid |
|
GW-RS0104-15 |
3 Feb 2015 |
22 Feb 2015 to 21 Aug 2015 |
Valid |
|
GW-RS0101-15 |
3 Feb 2015 |
22 Feb 2015 to 21 Aug 2015 |
Valid |
|
GW-RS0269-15 |
16 Mar 2015 |
8 Apr 2015 to 7 Oct 2015 |
Valid |