Contract No: HK/2011/07

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 2)

 

Environmental Permit no. EP-364/2009/C,

Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/A, FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B

 

Monthly Environmental Monitoring & Audit Report

 

-  april 2015 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and                                            

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

12 May 2015


Table of contents         

 

EXECUTIVE SUMMARY.. 4

1.         Introduction.. 15

1.1        Scope of the Report 15

1.2        Structure of the Report 15

 

2.         Project Background.. 17

2.1        Background. 17

2.2        Scope of the Project and Site Description. 17

2.3        Division of the Project Responsibility. 18

2.4        Project Organization and Contact Personnel 19

 

3.         status of regulatory compliance.. 26

3.1        Status of Environmental Licensing and Permitting under the Project 28

 

4.          Monitoring Requirements.. 42

4.1        Noise Monitoring. 42

4.2        Air Monitoring. 44

 

5.         Monitoring Results.. 46

5.1        Noise Monitoring Results. 47

5.2        Real Time Noise Monitoring Results. 50

5.3        Air Monitoring Results. 53

5.4       Waste Monitoring Results. 56

 

6.         Compliance Audit.. 61

6.1        Noise Monitoring. 61

6.2        Air Monitoring. 62

6.3        Review of the Reasons for and the Implications of Non-compliance. 63

6.4        Summary of action taken in the event of and follow-up on non-compliance. 63

 

7.         Cumulative Construction Impact due to the Concurrent Projects.. 64

8.         Enviromental site audit.. 65

9.         Complaints, Notification of Summons and Prosecution.. 68

10.       Conclusion.. 71


lIST OF TABLES

Table 2.1      Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 3.1      Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.2      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.3      Summary of submission status under FEP-02/364/2009

Table 3.4      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.5      Summary of submission status under FEP-01/364/2009

Table 3.6      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/18

Table 3.7      Summary of submission status under FEP-05/364/2009/A

Table 3.8      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.9      Summary of submission status under FEP-06/364/2009/A

Table 3.10    Cumulative Summary of Valid License and Permits under Contract no. HY/2009/19

Table 3.11   Summary of submission status under FEP-07/364/2009/A

Table 3.12    Cumulative Summary of Valid License and Permits under Contract no. HK/2012/08

Table 3.13    Summary of submission status under FEP-09/364/2009/B

Table 3.14    Cumulative Summary of Valid License and Permits under Contract no. HY/2010/08

Table 3.15    Summary of submission status under FEP-10/364/2009/B

Table 3.16    Cumulative Summary of Valid License and Permits under Contract no. HY/2011/08

Table 3.17    Summary of submission status under FEP-11/364/2009

Table 4.1      Noise Monitoring Stations

Table 4.2      Real Time Noise Monitoring Stations

Table 4.3      Air Monitoring Stations

Table 5.1      Noise Monitoring Stations for Contract no. HY/2009/18

Table 5.2      Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02

Table 5.3      Noise Monitoring Stations for Contract no. HY/2009/15

Table 5.4      Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.5      Noise Monitoring Stations for Contract no. HY/2010/08

Table 5.6      Noise Monitoring Stations for Contract no. HY/2011/08

Table 5.7      Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.8      Air Monitoring Stations for Contract no. HY/2009/18

Table 5.9      Air Monitoring Station for Contract no. HK/2009/01

Table 5.10    Air Monitoring Station for Contract no. HK/2009/02

Table 5.11    Air Monitoring Station for Contract no. HY/2009/15

Table 5.12    Air Monitoring Stations for Contract no. HY/2009/19

Table 5.13    Air Monitoring Station for Contract no. HK/2012/08

Table 5.14    Air Monitoring Station for Contract no. HY/2010/08

Table 5.15   Air Monitoring Stations for Contract no. HY/2011/08

Table 5.16    Details of Waste Disposal for Contract no. HK/2009/01

Table 5.17    Details of Waste Disposal for Contract no. HK/2009/02

Table 5.18    Details of Waste Disposal for Contract no. HY/2009/18

Table 5.19    Details of Waste Disposal for Contract no. HY/2009/15

Table 5.20    Details of Waste Disposal for Contract no. HY/2009/19

Table 5.21    Details of Waste Disposal for Contract no. HK/2012/08

Table 5.22    Details of Waste Disposal for Contract no. HY/2010/08

Table 5.23    Details of Waste Disposal for Contract no. HY/2011/08

Table 8.1      Summary of Environmental Inspections for Contract no. HY/2009/15

Table 8.4      Summary of Environmental Inspections for Contract no. HK/2009/01

Table 8.5      Summary of Environmental Inspections for Contract no. HK/2009/02

Table 8.7      Summary of Environmental Inspections for Contract no. HK/2012/08

Table 8.8      Summary of Environmental Inspections for Contract no. HY/2010/08

Table 9.1      Cumulative Statistics on Complaints

Table 9.2      Cumulative Statistics on Successful Prosecutions

Table 10.1    Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

 

LIST OF FIGUREs

 

Figure 2.1         Project Layout

Figure 2.2         Project Organization Chart

Figure 4.1         Locations of Environmental Monitoring Stations

 

 

lIST OF APPENDIces

 

Appendix 3.1    Environmental Mitigation Implementation Schedule

Appendix 4.1    Action and Limit Level

Appendix 4.2    Copies of Calibration Certificates

Appendix 5.1    Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2    Noise Monitoring Results and Graphical Presentations

Appendix 5.3    Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4    Real-time Noise Monitoring Results and Graphical Presentations

Appendix 6.1    Event Action Plans

Appendix 6.2    Notification of Exceedance

Appendix 9.1    Complaint Log

Appendix 10.1   Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report ˇV April 2015 specific for Environmental Permit no. EP-364/2009/C, Further Environmental Permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/A, FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HK/2011/07 ˇV Wan Chai Development Phase II and Central Wanchai Bypass ˇV Sampling, Field Measurement and Testing Works (Stage 2). This report presents the environmental monitoring findings and information recorded during the period of April 2015. The cut-off date of reporting is at 27th of each reporting month.

 

  1. In the reporting month, the principal work activities of individual contracts are included as follows:

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A

ˇP          Planting trees and shrubs

ˇP          Transplanting of trees

ˇP          Drainage works

ˇP          Trough structure construction including excavation, concreting and
waterproofing and backfill

ˇP          Road works

ˇP          Bridges construction

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

ˇP          Stage 1 Construction of roadside barrier and defect rectification

ˇP          Stage 2 Backfilling of retaining wall RW1 at slip road 2

ˇP          Stage 2 ELS and demolition works of bulkhead wall at Bay 10

ˇP          Stage 2 Steel fixing and formwork erection at Bay 7, 8 and 9 OHVD

ˇP          Stage 2 Construction of exhaust duct at slip road 3

ˇP          Stage 3 ELS excavation and strut installing works

ˇP          Stage 3 Base slab construction of box culvert Bay 2 and Bay 7

ˇP          Stage 3 Construction of box culvert Bay 1

ˇP          Stage 3 Construction of Outfall at Expo Drive East and backfilling work

ˇP          Sewerage pipeline at Fenwick Pier Street

ˇP          Pipe laying works for Cooling Main (BI/BG/BF)

ˇP          Work zone X1-1 to X1-4 at Fleming Road

ˇP          Pipe laying works of C3-1B and backfilling works of C3-1A

 

 

 

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009                                     

ˇP          Bulkhead wall breakthrough by Robot at the north side

ˇP          Bulkhead wall breakthrough by saw cut and wire cut

ˇP          Waterproofing application for north and south walls

ˇP          Rebar fixing at the north wall from Bay 1 to Bay 4

ˇP          Rebar fixing at the south wall of Bay 3 and Bay 4

ˇP          Formworks erection was now in progress at central wall of Bay 4, at south wall and north wall of Bay 1

ˇP          Concrete cast for central wall at Bay 1, Bay 2 and Bay 3

ˇP          Excavation at the west side and struts installation.

ˇP          Packer tests at the east side

ˇP          Excavation at the east side and welding for struts installation

ˇP          Installation of observation well, dewatering well, piezometer at the east side

ˇP          Pump test set up and schedule for pump test

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ˇV Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

 

ˇP          Mined Tunnel drill-and-break works at East and West Portal

ˇP          Permanent lining structure at Mined Tunnel

ˇP          Construction of diaphragm wall at TPCWAW

ˇP          Fabrication of first layer of ELS for TPCWAW

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

ˇP          Demolition of ELS for Cut &Cover Tunnel and EVB

ˇP          Pre-bored H-pile for Approach Ramp

ˇP          IECL Road modification and removal of Median Barrier

ˇP          Abutment D12 construction

ˇP          Saw cut of parapet at IEC East bound

ˇP          Construction of TA2 bridge

ˇP          Construction of temporary steel tower for IEC demolition

ˇP          Saw cut of existing west fast lane of IEC bridge

ˇP          Demolition of bulk head wall between C15 to C19

ˇP          Column modification at F1 to F8

 

 

 

 

 

 

 

 

 

 

Contract no. HK/2012/08 ˇV Wan Chai Development Phase II ˇV Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009B

ˇP          Diaphragm wall construction

ˇP          Installation of dewatering wells

ˇP          Grouting

ˇP          Construction of ELS at MVB

ˇP          Excavation and installation of lateral support at top-down area

ˇP          Pre-bored H-pile construction

 

Contract no. HY/2010/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel (Slip Road 8) under FEP-10/364/2009B

 

ˇP          Drainage improvement works,

ˇP          Sheet piling works,

ˇP          Excavation and Lateral Support for U-structure works,

ˇP          Erection of noise absorption sheetings,

ˇP          Pipe piling & grouting works,

ˇP          Utility diversion works,

ˇP          Waterproofing works,

ˇP          Provisional of Bowling Green,

ˇP          Milling & paving works for TTA stage II ˇV westbound &.

ˇP          Construction of ramp for TTA stage II ˇV eastbound

ˇP          und

Contract no. HY/2011/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

ˇP          West Ventilation Building structure construction

ˇP          Install VE panels bracket and thermal barrier for Tunnel

ˇP          Construct reinforcement concrete structure for EVS

 

 

Noise Monitoring

  1. Noise monitoring during daytime was conducted at M1a - Harbour Road Sports Center; M2b - Noon-day gun area; M3a - Tung Lo Wan Fire Station; M4b - Victoria Center; M5b - City Garden, M6 - HK Baptist Church Henrietta Secondary School, M7e and M7w ˇV International Financial Centre East Podium and International Finance Centre West Podium and M8 ˇV City Hall on weekly basis in the reporting month.
  2. One limit level exceedances at M6 ˇV HK Baptist Church Henrietta Secondary School was recorded 21 April 2015 in this reporting month. The exceedance was concluded as non-project related.
  3. 24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot for construction activities at IEC bridge deck. No limit level exceedance was recorded in the reporting month.
  4. 24-hour real time noise monitoring was conducted at RTN2a ˇV Hong Kong Electric Centre. No project related exceedance was recorded in the reporting month.
  5. 24-hour real time noise monitoring was conducted at RTN3 ˇV Yu Lee Mo Fan Memorial School. No project related exceedance was recorded in the reporting month.
  6. 24-hour real time noise monitoring was conducted at RTN4 ˇV Causeway Bay Community Centre. No limit level exceedance was recorded in the reporting month.
  7. Liaison was conducted with HK Baptist Church Henrietta Secondary School and Po Leung Kuk Yu Lee Mo Fan Memorial School regarding the set up of RTN3 real time noise monitoring station.  Po Leung Kuk Yu Lee Mo Fan Memorial School grant permission for set up on 4 Sep 2012 and station set up was performed on 14 Sep 2012.
  8. Real time noise monitoring station at Oil Street Community Liaison Centre (RTN2- Oil Street Community Centre) was relocated from Oil Street Community Liaison Centre to Hong Kong Electric (RTN2a- Electric Centre) on 5 Oct 2012 which is a representative of the noise sensitive receiver City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.
  9. Real-time noise baseline capturing was conducted from 21 Sep 2012 to 04 Oct 2012 at RTN3-Po Leung Kuk Yu Lee Mo Fan Memorial School.
  10. Real-time Noise Monitoring at RTN3- Po Leung Kuk Yu Lee Mo Fan Memorial School was commenced since 06 Oct 2012.
  11. Causeway Bay Community Centre has granted permission for set up of real time noise monitoring station on 21 Dec 2012 and station set up was performed on 27 Dec 2012.  The Baseline noise level of RTN4- Causeway Bay Community Centre will adopt the results from the baseline noise monitoring report for EP/364/2009 in 22 April 2010 in which approved by EPD.
  12. According to clause 3.1 stated in EP-364/2009/B, ˇ§the real-time monitoring system shall be in place no later than two weeks before the commencement date of demolition works of the existing Island Eastern Corridorˇ¨. IEC demolition associated construction works was commenced on 3 Feb 2013 and Real time noise monitoring at RTN4-Causeway Bay Community Centre was commenced on 13 Jan 2013.
  13. Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with respect to the commencement of advance works for IEC parapet demolition.
  14. With respect to the completion of Victoria Car Park refurbishment, the noise monitoring at M4b-Victora Center was reverted from 3/F to 2/F since 24 June 2014.

 

Air Monitoring

  1. With respect to the area handover, the air quality monitoring station CMA5a at Children Playgrounds opposite to the Pedestrian Plaza was relocated to the Pedestrian Plaza on 3 December 2014. The station reference and location ID of the air quality monitoring station CMA5a was updated as CMA5b and Pedestrian Plaza respectively.
  2. Due to extension of site boundary by contractor of HY/2009/19, location of air monitoring station CMA1b ˇV Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.
  3. The location ID of air monitoring station CMA1b was updated as Oil Street Site Office in April 2013.
  4. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b ˇV Oil Street Site Office; CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site Office Area; CMA4a ˇV Society for the Prevention of Cruelty to Animals; CMA5b - Pedestrian Plaza; MA1e and MA1w ˇV International Finance Centre eastern and western podium on every six days basis.
  5. No project related exceedance was recorded in the reporting month.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. Four environmental complaints were received in the reporting month.

 

  1. First public complaint regarding construction dust impact referred by EPD was received by ET on 09 April 2015 (EPD Ref.:H05/RS/00008074-15 dated 9 April 2015). The complainant reported that:
  2. Construction dust was generated from lorries transporting out of the construction via site exit near Expo Drive Central without wheel washing at the morning of 7 April 2015. Lorries were also found transporting out of the construction site via gates V2 and V8 without wheel washing and causing dust nuisance at about 10:30 hours on 9 April 2015.
  3. ET confirmed with the Resident Site Staff that on 7 April 2015, major vehicle movements included oil tanker passing at Gate V2 at Expo Drive East and dump truck passing at Gate V8 at Expo Drive Central under Contract HK/2009/01. On 9 April 2015. major vehicle movements include oil tanker, crane lorry and dump truck passing at Gate V2 at Expo Drive East and dump truck at Gate V8 at Expo Drive Central under Contract HK/2009/01.
  4. Mitigation measures adopted by the Contractor of HK/2009/01 at the above locations include water hose was provided for wheel washing at Gate V2 and Gate V8, concrete paving at site exit, dump truck fitted with mechanic cover and cleaned before leaving construction site and regular street washing at Expo Drive Central.
  5. According to the relevant site records under Contract HK/2009/01, on 7 April 2015, major vehicle movements included oil tanker passing at Gate V2 at Expo Drive East and dump truck passing at Gate V8 at Expo Drive Central under Contract HK/2009/01 while on 9 April 2015 major vehicle movements include oil tanker, crane lorry and dump truck passing at Gate V2 at Expo Drive East and dump truck at Gate V8 at Expo Drive Central under Contract HK/2009/01.
  6. At the above locations, mitigation measures including water hose for wheel washing at Gate V2 and Gate V8; concrete paving at site exit; dump truck fitted with mechanic cover and cleaned before leaving construction site and regular street washing at Expo Drive Central were generally adopted by the Contractor of HK/2009/01.
  7. In view of the public concern on the complaint date, the Contractor of HK/2009/01 was advised to conduct cleaning at the concerned site exit point and the section of public road adjoining the site exit to clear any residue grit and silt deposit to avoid further dust impact.
  8. Follow up inspection was conducted on 16 April 2015 during weekly environmental inspection and mitigation measures including water spraying for dusty haul road and provision of wheel washing were in place. The construction site exit was observed clear from residue silt / grit at the concerned location.
  9. In view of the public concern, the contractor was advised to conduct training to the construction site workers to enhance the effectiveness of wheel washing and to ensure proper wheel washing is provided for dump truck and other vehicle prior to leaving the construction site to avoid generating any dust nuisance.

 

  1. Second public complaint regarding construction noise impact referred by EPD was received by ET on 09 April 2015 (EPD Ref.:H05/RS/00007861-15 dated 9 April 2015). The complainant reported that construction noise was emanated from the construction site at Convention Avenue near Renaissance Harbor View Hotel during the period of Easter Holiday, including April 3 at about 13:00 hours.
  2. ET confirmed with the Resident Site Staff that from 3 April 2015 to 7 April 2015, from 08:00 hours to 18:00 hours, and at about 13:00 hours on 3 April 2015 at area CWB Tunnel Stage 3, backfilling works was conducted under HK/2009/01. Either 1 no. of dump truck and 1. no. of excavator was operated on site at each given time during the concerned period.
  3. According to the relevant site records under Contract HK/2009/01, from across 08:00hrs to 18:00hrs during the period from 3 April 2015 to 7 April 2015, backfilling works was conducted under Contract HK/2009/01 at CWB Tunnel Stage 3. Either 1 no. of dump truck and 1 no. of excavator was operated on site at each given time during the concerned period and the relevant Construction Noise Permit GW-RS0104-15 for the works was in place and the same construction activity was undertaken at around 13:00hrs on 3 April 2015.
  4. No other concurrent construction activity was undertaken at the concerned location during the concerned period under Contract HK/2009/01. The construction activity conducted under Contract HK/2009/01 during the concerned period was in compliance with the statutory requirement.
  5. Nevertheless, in view of the concern regarding the noise nuisance raised by the public at the concerned location, it is considered desirable for the Contractor of HK/2009/01 to review the truck unloading procedures of the specific construction task to minimize potential noise emanated during the course for work.

 

  1. Third public complaint regarding visual impact received by the RSS was referred to the ET on 15 April 2015 (ICC Case Ref.: 2-885677297 dated 13 April 2015). The complainant reported that:

ˇ§I live in a building next to Gloucester Road in Causeway Bay. Recently, I am suffering from unnecessary light source from the construction site. The banners of the construction companies are always illuminated with very bright lights.ˇ¨

  1. ET confirmed with the Resident Site Staff that the concerned lighting for the banners was maintained under Contract HY/2010/08.
  2. The concerned lighting for the banners was maintained under Contract HY/2010/08 and the concerned lighting was subsequently switched off at all times since 13 April 2015 to alleviate the lighting nuisance caused to the surroundings.

 

  1. Fourth public complaint regarding construction noise impact referred by EPD was received by ET on 23 April 2015 (EPD Ref.:H05/RS/00009456-15 dated 23 April 2015). The complainant reported that construction noise emanated from the road work at Fleming Road and Convention Avenue near Renaissance Harbour View Hotel almost every night recently causing nuisance.
  2. ET confirmed with the Resident Site Staff that from 21:00hrs on 20 April 2015 to 06:00hrs on 21 April 2015 and from 21:00hrs on 21 April 2015 to 06:00hrs on 22 April 2015, cooling main connection works was undertaken by the Contractor of Contract HK/2009/01 at the concerned location. Total 1 no. of crane lorry and 1 no. of excavator were in operation.
  3. According to the relevant site records under Contract HK/2009/01, from 21:00hrs on 20 April 2015 to 06:00hrs on 21 April 2015 and from 21:00hrs on 21 April 2015 to 06:00hrs on 22 April 2015, cooling main connection works was undertaken by the Contractor of Contract HK/2009/01 at the concerned location. Total 1 no. of crane lorry and 1 no. of excavator were in operation during the concerned period and the relevant Construction Noise Permit GW-RS0269-15 was confirmed in place. The construction activity conducted under Contract HK/2009/01 during the concerned period was in compliance with the statutory requirement.
  4. In view of the potential noise nuisance, a notice to affected parties was issued by the Contractor of Contract HK/2009/01 to the nearby residents including Renaissance Harbour View Hotel on 17 April 2015. Besides, construction works undertaken by other parties at the concerned location was observed at the concerned period.

 

Site Inspections and Audit

  1. The Environmental Team (ET) conducted weekly site inspections for Contract no. HY/2009/15, HY/2009/18, HY/2009/19, HY/2010/08, HK/2009/01, HK/2009/02, HK/2012/08 and HY/2011/08 in this reporting period.
  2. Construction of bored pile E3B under HY/2009/17 was confirmed completed and the respective work area under FEP-03/364/2009 was handover and inspected under HY/2009/19 from 19 Dec 2012 onwards.
  3. Construction works under HK/2010/06 was confirmed completed and the respective work area under FEP-08/364/2009/A was handover and inspected under HK/2012/08 from 22 Sep 2014 onwards.
  4. The Contractors rectified major observations and recommendations made during the audit sessions. No non-conformance was identified during the site inspections.

Future Key Issues

  1. In the coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HY/2009/18 ˇV Central ˇV Wan Chai Bypass (CWB) ˇV Central Interchange under FEP-05/364/2009/A

ˇP          Planting trees and shrubs

ˇP          Transplanting of trees

ˇP          Drainage works

ˇP          Retaining wall and  trough structure construction including excavation, concreting,
waterproofing and backfill

ˇP          Road works

ˇP          Bridges construction

 

Contract no. HK/2009/01 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ˇV Tunnel Works under FEP-02/364/2009

 

ˇP          Stage 1 Construction of roadside barrier and backfilling on top of CWB tunnel

ˇP          Stage 2 Construction of roof slab Bay 7, 8 and 9

ˇP          Stage 2 Construction of base slab Bay 10

ˇP          Stage 2 Construction of exhaust duct

ˇP          Stage 3 ELS excavation and strut installing works

ˇP          Stage 3 Box culvert diversion

ˇP          Cooling Main Installation (BI/BG) at Expo Drive East

ˇP          Removal of abandoned cooling main (P7/P8) at Convention Avenue

ˇP          Sewerage Pipeline A3-4B at Fenwick Pier Street

ˇP          Installation works for Cooling Main (BI/BG) / Salt Watermain (S3)/ Fresh Watermain (F3)

ˇP          Reinstatement of Expo Drive East

 

Contract no. HK/2009/02 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

 

ˇP          Continue tunnel structure works, i.e. concrete cast at side walls, formworks and concreting at OHVD base slab

ˇP          Continue bulk head wall BW2 breakthrough.

ˇP          Complete pumping test

ˇP          Continue Strut layer S2 excavation and ELS installation at both sides.

 

 

 

 

 

Contract no. HY/2009/15 ˇV Central-Wanchai Bypass ˇV Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

ˇP          Construction of OHVD and base slab at Mined Tunnel

ˇP          Permanent lining structure at Mined Tunnel

ˇP          Inner bench excavation

ˇP          Construction of diaphragm wall at TPCWAW

ˇP          Installation of king post

ˇP          Fabrication of ELS steel works for TPCWAW

 

Contract no. HY/2009/19 ˇV Central ˇV Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

ˇP          Demolition of ELS for Cut &Cover Tunnel and EVB

ˇP          Pre-bored H-pile for Approach Ramp

ˇP          Abutment D12 construction

ˇP          Saw cut of parapet at IEC East bound

ˇP          Construction of TA2 bridge

ˇP          Construction of temporary steel tower for IEC demolition

ˇP          Saw cut of existing west bound of IEC bridge

ˇP          Demolition of bulk head wall between C15 to C19

ˇP          Column modification at F1 to F8

ˇP          Demolition of IEC west bound deck

 

Contract no. HK/2012/08 ˇV Wan Chai Development Phase II ˇV Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B

ˇP          Diaphragm wall construction

ˇP          Installation of dewatering wells

ˇP          Grouting

ˇP          Construction of ELS at MVB

ˇP          Excavation and installation of lateral support at top-down area

ˇP          Pre-bored H-pile construction

 

Contract no. HY/2010/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel (Slip Road 8) under FEP-10/364/2009

ˇP          Tree protection works next to existing BGO

ˇP          Drainage improvement works,

ˇP          Sheet piling works,

ˇP          Excavation and Lateral Support for U-structure,

ˇP          Renovation works for Bowling Green Office,

ˇP          Pipe piling & grouting works,

ˇP          Utility diversion works,

ˇP          Waterproofing works,

ˇP          Demolition works of existing BGO &

ˇP          Provisional of Bowling Green

ˇP           

 

Contract no. HY/2011/08 ˇV Central - Wan Chai Bypass (CWB) ˇVTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

ˇP          West Ventilation Building structure construction

ˇP          Install VE panels bracket and thermal barrier for Tunnel

ˇP          Construct reinforcement concrete structure for EVS

1            Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009/C and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-09/364/2009/B, FEP-10/364/2009B and FEP-11/364/2009B to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and ˇ§Environmental Monitoring and Audit Requirementsˇ¨ under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/B, Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A, FEP-09/364/2009B, FEP-10/364/2009B and FEP-11/364/2009B during the period March 2015 to April 2015. The cut-off date of reporting is at 27th of each reporting month

 

1.2          Structure of the Report

 

Section 1          Introduction ˇV details the scope and structure of the report.

 

Section 2          Project Background ˇV summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3          Status of Regulatory Compliance ˇV summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4          Monitoring Requirements ˇV summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5          Monitoring Results ˇV summarizes the monitoring results obtained in the reporting period.

 

Section 6          Compliance Audit ˇV summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7          Cumulative Construction Impact due to the Concurrent Projects ˇV summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8        Environmental Site Audit ˇV summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9          Complaints, Notification of summons and Prosecution ˇV summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10        Conclusion

2      Project Background

2.1          Background

2.1.1.     ˇ§Wan Chai Development phase II and Central-Wan Chai Bypassˇ¨ and ˇ§Central-Wan Chai Bypass and Island Eastern Corridor Linkˇ¨ (hereafter called ˇ§the Projectˇ¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2          Scope of the Project and Site Description

2.2.1.     Design and Construction of Central ˇV Wan Chai Bypass and Island Eastern Corridor Link under the Project involves the construction and operation of a trunk road and its road tunnel more than 800m in length between portals that is shown at Figure 2.1.

2.2.2.     The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:

ˇP      A dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);

ˇP      The Central Interchange near the Rumsey Street Flyover to provide road connections to the Central area;

ˇP      Tunnel control buildings and ventilation buildings;

ˇP      Slip roads to connect the CWB to the local road system in the Wan Chai North and Causeway Bay area;

ˇP      Associated road lighting, road signing, traffic control and surveillance system; and

ˇP      Other associated works.

 

2.2.3.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3          Division of the Project Responsibility

2.3.1.     Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.     The details of individual contracts are summarized in Table2.2.

Table 2.2    Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HY/2009/17

Central ˇV Wan Chai Bypass (CWB) at FEHD Whitfield Depot ˇV Advanced piling works.

DP1

5 October 2010

(Completed)

HY/2009/18

Central ˇV Wan Chai Bypass (CWB) ˇV Central Interchange

DP1

21 April 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010 (Completed)

HK/2009/01

Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ˇV Tunnel Works

 

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at Wan Chai East(CWB Tunnel)

DP1

26 April 2011

HY/2009/15

Central-Wanchai Bypass ˇV Tunnel (Causeway Bay Typhoon Shelter Section)

DP1,DP3

13 July 2011

HY/2009/19

Central ˇV Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

(Completed)

HK/2012/08

Wan Chai Development Phase II- Central-Wan Chai Bypass at Wan Chai West

DP1,DP2, DP3

10 March 2014

HY/2010/08

Central- Wanchai Bypass Tunnel ˇV Tunnel (Slip Road 8)

DP1, DP2, DP3

21 March 2013

HY/2011/08

Central - Wan Chai Bypass (CWB) ˇVTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

DP1

8 October 2014

 

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineerˇ¦s Representative for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineerˇ¦s Representative for CWB

Principal Resident Engineer

Mr. Peter Poon

3922 3388

3912 3010

Chun Wo ˇV Leader Joint Venture

Contractor under Contract no. HK/2009/01

Site Agent

Mr. Simon Liu

2162 9909

2634 1626

Construction  Manager

Mr. Terry Wong

9757 9846

Deputy Site Agent

Mr. Andy Yu

9648 4896

Construction Manager

Mr. Wyman Wong

9627 2467

Construction Manager

Mr. Jack Chu

9775 2467

Environmental Officer

Ms. Wendy Ng

9103 2370

Assistant Environmental Engineer

Ms. Connie Chan

9047 6148

Chun Wo ˇV CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Site Agent

Mr. K.K. Yuen

3658-3002

2827 9996

Project Manager

Mr. Alfred Leung

3658-3022

Quality & Environmental Manager

(Environmental Officer)

Mr. C.P. Ho

3658-3000

Chun Wo - CRGL - MBEC Joint Venture

 

Contractor under Contract no. HY/2009/19

Project Manager

Mr. David Lau

3758 8879

2570 8013

Site Agent

Mr. Paul Yu

9456 9819

Environmental Manager /

Environmental Officer

Mr. M.H. Isa

9884 0810

Environmental Engineer

Mr. Calvin Leung

9286 9208

Construction Manager (Marine)

Mr. William Luk

9610 1101

Construction Manager

(Land)

Mr. Patrick Cheung

9643 3012

Construction Manager

(Land)

Mr. Eric Fong

6191 9337

Operation Manager (Land)

Mr. Yung Kwok Wah

 

 

9834 1010

 

 

Leighton Contractors (Asia) Limited

Contractor under Contract no. HY/2009/18

Site Agent

Mr. Jimmy Chu

2214 7700

2140 6799

Deputy Site Agent

Mr. Bob Yeung

2214 7703

Environmental Officer

Ms. Lighting Chan

2823 1161

Environmental Engineer

Mr. Chris Chan

2214 7721

Assistant Environmental Engineer

Mr. Penny Yiu

2214 7738

Environmental Supervisor

Mr. K. P. Lai

6461 4660

Environmental Supervisor

Mr. Ray Cheng

2214 7742

Environmental Supervisor

Mr. K. W. Lee

6461 4623

Environmental Supervisor

Mr. Dorothy Shing

2214 7705

Environmental Supervisor

Mr. C. Y. Au Yeung

6461 8631

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Mr. Chris Leung

3557 6393

2865 5229

Site Manager

Mr. Y. Huo

3557 6368

2566 2192

Contractorˇ¦s Representative

Mr. Gene Cheung

3557 6395

Environmental Officer

Mr. Andy Mak

3557 6215

Environmental Supervisor

Ms. Esther Choi

35576348

China State- Leader JV

Contractor under Contract no. HK/2012/08

Project Director

Mr. C.N. Lai

9137 1811

2877 1522

Project Manager

Mr. Eddie Chung

9193 8871

Site Agent

Mr. Keith Tse

9095 7922

Environmental Officer

Mr. James MA

9130 9549

Environmental Supervisor

Mr. Y.L. Ho

6050 4919

China State

Contractor under Contract no.HY/2010/08

Project Director

Cheung Kit Cheung

 

 

3557 6399

 

2566 8061

Project Manager

Chan Ying Lun

9812 0592

Deputy Project Manager

Chris Leung

3467 4299

Site Agent

Dr. Dave Chan

3467 4277

Environmental Officer

Mr. C.M. Wong

3557 6464

Environmental Supervisor

Mr. Louis Lam Tsz Kwan

3557 6470

Leighton Joint Venture

Contractor under Contract no. HY/2011/08

Project Manager

Paul Evans

2823 1111

21406799

Site Agent

Colman Wong

2140 6799

Environmental Officer

Malcom Leung

2214 7721

Environmental Supervisor

Penny Yiu

2214 7738

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3465 2888

3465 2899

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

 

 

 

 

 

 

 

 

 

 

 

 

2.4.3.     In this reporting month, the principal work activities of individual contracts are included as follows:

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A

ˇP          Planting trees and shrubs

ˇP          Transplanting of trees

ˇP          Drainage works

ˇP          Trough structure construction including excavation, concreting and
waterproofing and backfill

ˇP          Road works

ˇP          Bridges construction

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

ˇP          Stage 1 Construction of roadside barrier and defect rectification

ˇP          Stage 2 Backfilling of retaining wall RW1 at slip road 2

ˇP          Stage 2 ELS and demolition works of bulkhead wall at Bay 10

ˇP          Stage 2 Steel fixing and formwork erection at Bay 7, 8 and 9 OHVD

ˇP          Stage 2 Construction of exhaust duct at slip road 3

ˇP          Stage 3 ELS excavation and strut installing works

ˇP          Stage 3 Base slab construction of box culvert Bay 2 and Bay 7

ˇP          Stage 3 Construction of box culvert Bay 1

ˇP          Stage 3 Construction of Outfall at Expo Drive East and backfilling work

ˇP          Sewerage pipeline at Fenwick Pier Street

ˇP          Pipe laying works for Cooling Main (BI/BG/BF)

ˇP          Work zone X1-1 to X1-4 at Fleming Road

ˇP          Pipe laying works of C3-1B and backfilling works of C3-1A

 

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009                                     

ˇP          Bulkhead wall breakthrough by Robot at the north side

ˇP          Bulkhead wall breakthrough by saw cut and wire cut

ˇP          Waterproofing application for north and south walls

ˇP          Rebar fixing at the north wall from Bay 1 to Bay 4

ˇP          Rebar fixing at the south wall of Bay 3 and Bay 4

ˇP          Formworks erection was now in progress at central wall of Bay 4, at south wall and north wall of Bay 1

ˇP          Concrete cast for central wall at Bay 1, Bay 2 and Bay 3

ˇP          Excavation at the west side and struts installation.

ˇP          Packer tests at the east side

ˇP          Excavation at the east side and welding for struts installation

ˇP          Installation of observation well, dewatering well, piezometer at the east side

ˇP          Pump test set up and schedule for pump test

Contract no. HY/2009/15 - Central-Wanchai Bypass ˇV Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

 

ˇP          Mined Tunnel drill-and-break works at East and West Portal

ˇP          Permanent lining structure at Mined Tunnel

ˇP          Construction of diaphragm wall at TPCWAW

ˇP          Fabrication of first layer of ELS for TPCWAW

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

ˇP          Demolition of ELS for Cut &Cover Tunnel and EVB

ˇP          Pre-bored H-pile for Approach Ramp

ˇP          IECL Road modification and removal of Median Barrier

ˇP          Abutment D12 construction

ˇP          Saw cut of parapet at IEC East bound

ˇP          Construction of TA2 bridge

ˇP          Construction of temporary steel tower for IEC demolition

ˇP          Saw cut of existing west fast lane of IEC bridge

ˇP          Demolition of bulk head wall between C15 to C19

ˇP          Column modification at F1 to F8

 

Contract no. HK/2012/08 ˇV Wan Chai Development Phase II ˇV Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009B

ˇP          Diaphragm wall construction

ˇP          Installation of dewatering wells

ˇP          Grouting

ˇP          Construction of ELS at MVB

ˇP          Excavation and installation of lateral support at top-down area

ˇP          Pre-bored H-pile construction

 

Contract no. HY/2010/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel (Slip Road 8) under FEP-10/364/2009B

ˇP          Drainage improvement works,

ˇP          Sheet piling works,

ˇP          Excavation and Lateral Support for U-structure works,

ˇP          Erection of noise absorption sheetings,

ˇP          Pipe piling & grouting works,

ˇP          Utility diversion works,

ˇP          Waterproofing works,

ˇP          Provisional of Bowling Green,

ˇP          Milling & paving works for TTA stage II ˇV westbound &.

ˇP          Construction of ramp for TTA stage II ˇV eastbound

 

 

 

 

Contract no. HY/2011/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

ˇP          West Ventilation Building structure construction

ˇP          Install VE panels bracket and thermal barrier for Tunnel

ˇP          Construct reinforcement concrete structure for EVS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.4.4.     In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

Contract no. HY/2009/18 ˇV Central ˇV Wan Chai Bypass (CWB) ˇV Central Interchange under FEP-05/364/2009/A

ˇP          Planting trees and shrubs

ˇP          Transplanting of trees

ˇP          Drainage works

ˇP          Retaining wall and  trough structure construction including excavation, concreting,
waterproofing and backfill

ˇP          Road works

ˇP          Bridges construction

 

Contract no. HK/2009/01 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ˇV Tunnel Works under FEP-02/364/2009

ˇP          Stage 1 Construction of roadside barrier and backfilling on top of CWB tunnel

ˇP          Stage 2 Construction of roof slab Bay 7, 8 and 9

ˇP          Stage 2 Construction of base slab Bay 10

ˇP          Stage 2 Construction of exhaust duct

ˇP          Stage 3 ELS excavation and strut installing works

ˇP          Stage 3 Box culvert diversion

ˇP          Cooling Main Installation (BI/BG) at Expo Drive East

ˇP          Removal of abandoned cooling main (P7/P8) at Convention Avenue

ˇP          Sewerage Pipeline A3-4B at Fenwick Pier Street

ˇP          Installation works for Cooling Main (BI/BG) / Salt Watermain (S3)/ Fresh Watermain (F3)

ˇP          Reinstatement of Expo Drive East

 

Contract no. HK/2009/02 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

ˇP          Continue tunnel structure works, i.e. concrete cast at side walls, formworks and concreting at OHVD base slab

ˇP          Continue bulk head wall BW2 breakthrough.

ˇP          Complete pumping test

ˇP          Continue Strut layer S2 excavation and ELS installation at both sides.

 

Contract no. HY/2009/15 ˇV Central-Wanchai Bypass ˇV Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

ˇP          Construction of OHVD and base slab at Mined Tunnel

ˇP          Permanent lining structure at Mined Tunnel

ˇP          Inner bench excavation

ˇP          Construction of diaphragm wall at TPCWAW

ˇP          Installation of king post

ˇP          Fabrication of ELS steel works for TPCWAW

Contract no. HY/2009/19 ˇV Central ˇV Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

ˇP          Demolition of ELS for Cut &Cover Tunnel and EVB

ˇP          Pre-bored H-pile for Approach Ramp

ˇP          Abutment D12 construction

ˇP          Saw cut of parapet at IEC East bound

ˇP          Construction of TA2 bridge

ˇP          Construction of temporary steel tower for IEC demolition

ˇP          Saw cut of existing west bound of IEC bridge

ˇP          Demolition of bulk head wall between C15 to C19

ˇP          Column modification at F1 to F8

ˇP          Demolition of IEC west bound deck

 

Contract no. HK/2012/08 ˇV Wan Chai Development Phase II ˇV Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B

ˇP          Diaphragm wall construction

ˇP          Installation of dewatering wells

ˇP          Grouting

ˇP          Construction of ELS at MVB

ˇP          Excavation and installation of lateral support at top-down area

ˇP          Pre-bored H-pile construction

 

Contract no. HY/2010/08 ˇVCentral - Wan Chai Bypass (CWB) ˇVTunnel (Slip Road 8) under FEP-10/364/2009

 

ˇP          Tree protection works next to existing BGO

ˇP          Drainage improvement works,

ˇP          Sheet piling works,

ˇP          Excavation and Lateral Support for U-structure,

ˇP          Renovation works for Bowling Green Office,

ˇP          Pipe piling & grouting works,

ˇP          Utility diversion works,

ˇP          Waterproofing works,

ˇP          Demolition works of existing BGO &

ˇP          Provisional of Bowling GreenˇV eastbound

 

Contract no. HY/2011/08 ˇV Central - Wan Chai Bypass (CWB) ˇVTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

ˇP          West Ventilation Building structure construction

ˇP          Install VE panels bracket and thermal barrier for Tunnel

ˇP          Construct reinforcement concrete structure for EVS

3         status of regulatory compliance

3.1          Status of Environmental Licensing and Permitting under the Project

3.1.1.     A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1    Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

Superseded

Environmental Permit

EP-364/2009/A

4 Aug 2010

Superseded

Environmental Permit

EP-364/2009/B

20 Sep 2012

Superseded

Environmental Permit

EP-364/2009/C

11 Jul 2014

Valid

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Surrendered

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

15 Nov 2010

Valid

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

Surrendered

Further Environmental Permit

FEP-06/356/2009

5 March 2013

Valid

Further Environmental Permit

FEP-07/356/2009

26 July 2013

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 July 2010

Surrendered

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Surrendered

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

Valid

Further Environmental Permit

FEP-08/364/2009/A

15 June 2012

Surrendered

Further Environmental Permit

FEP-09/364/2009/B

5 March 2013

Valid

Further Environmental Permit

FEP-10/364/2009/B

26 July 2013

Valid

Further Environmental Permit

FEP-11/364/2009/B

2 May 2014

Valid

3.1.2.     Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HY/2009/17 ˇV Central ˇV Wan Chai Bypass (CWB) at FEHD Whitfield Depot ˇV Advanced piling works under FEP-03/364/2009

3.1.3.     The construction works was completed and the FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.

Contract no. 04/HY/2006 ˇV Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

3.1.4.     The construction works was completed, and the FEP-04/HY/2006 was surrendered by the Contractor on 11 February 2011.

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

3.1.5.     The construction works was completed, and the FEP-08/364/2009/A was surrendered by the Contractor on 3 October 2014.

 

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HK/2009/01 ˇV Wan Chai Development Phase II ˇV Central ˇV Wan Chai Bypass at Hong Kong Convention and Exhibition Centre ˇV Tunnel Works under FEP-02/364/2009

3.1.6.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.2 and Table 3.3

Table 3.2    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

N/A

Valid

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088

06 Jan 2010

N/A

Valid

Construction Noise Permit (CNP) for non-pilling equipment

GW-RS0243-15

16 Mar 2015

25 Mar 2015 to 24 Sept 2015

Valid

GW-RS1056-14

29 Sept 2014

08 Oct 2014 to 7 April 2015

Cancelled

GW-RS1274-14

17 Nov 2014

17 Nov 2014 to 16 May 2015

Valid

GW-RS1051-14

29 Sept 2014

9 Oct 2014 to 8 April 2015

Expired

GW-RS1222-14

05 Nov 2014

08 Nov 2014 to 07 May 2015

Valid

GW-RS1309-14

24 Nov 2014

26 Nov 2014 to 25 May 2015

Valid

 

GW-RS1472-14

2 Jan 2015

22 Jan 2015 to 21 Jul 2015

Cancelled

 

GW-RS0079-15

27 Jan 2015

16 Feb 2015 to 14 Aug 2015

Valid

 

GW-RS0074-15

22 Jan 2015

10 Feb 2015 to 9 Aug 2015

 

Valid

 

GW-RS0104-15

3 Feb 2015

22 Feb 2015 to 21 Aug 2015

Valid

 

GW-RS0101-15

3 Feb 2015

22 Feb 2015 to 21 Aug 2015

 

Valid

 

GW-RS0269-15

16 Mar 2015

8 Apr 2015 to 7 Oct 2015

Valid