Contract No: HK/2011/07 Wanchai
Development Phase II and Central Wanchai Bypass Sampling,
Field Measurement and Testing Work (Stage 2) Environmental Permit no. EP-364/2009/C, Further
Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/A,
FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B Monthly Environmental Monitoring &
Audit Report
- JUNE 2015 -
|
CLIENTS: |
|
Civil Engineering
and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
09 July 2015 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3.
status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring Results
5.3 Air
Quality Monitoring Results
6.3 Review
of the Reasons for and the Implications of Non-compliance
6.4 Summary
of action taken in the event of and follow-up on non-compliance
7.
Cumulative Construction Impact due to the Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table
2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.3 Summary
of submission status under FEP-02/364/2009
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.5 Summary
of submission status under FEP-01/364/2009
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Table 3.7 Summary
of submission status under FEP-05/364/2009/A
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table 3.9 Summary
of submission status under FEP-06/364/2009/A
Table 3.10 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.11
Summary of submission status under FEP-07/364/2009/A
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.13 Summary of submission status under FEP-09/364/2009/B
Table 3.14 Cumulative Summary of Valid License
and Permits under Contract no. HY/2010/08
Table 3.15 Summary of submission status under
FEP-10/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HY/2011/08
Table 3.17 Summary of submission status under FEP-11/364/2009/B
Table 4.1 Noise Monitoring
Stations
Table 4.2 Real
Time Noise Monitoring Stations
Table 4.3 Air
Quality Monitoring Stations
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/18
Table 5.2 Noise
Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Table 5.3 Noise
Monitoring Stations for Contract no. HY/2009/15
Table 5.4 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table 5.6 Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.7 Real
Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Air
Quality Monitoring Stations for Contract no. HY/2009/18
Table 5.9 Air
Quality Monitoring Station for Contract no. HK/2009/01
Table 5.10 Air Quality Monitoring
Station for Contract no. HK/2009/02
Table 5.11 Air Quality Monitoring
Station for Contract no. HY/2009/15
Table 5.12 Air Quality Monitoring
Stations for Contract no. HY/2009/19
Table 5.13 Air Quality
Monitoring Station for Contract no. HK/2012/08
Table 5.14 Air Quality
Monitoring Station for Contract no. HY/2010/08
Table 5.15 Air Quality Monitoring Stations for
Contract no. HY/2011/08
Table 5.16 Details
of Waste Disposal for Contract no. HK/2009/01
Table 5.17 Details
of Waste Disposal for Contract no. HK/2009/02
Table 5.18 Details
of Waste Disposal for Contract no. HY/2009/18
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/15
Table 5.20 Details
of Waste Disposal for Contract no. HY/2009/19
Table 5.21 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.22 Details of Waste Disposal
for Contract no. HY/2010/08
Table 5.23 Details of Waste Disposal for Contract no. HY/2011/08
Table 8.1 Summary of Environmental
Inspections for Contract no. HY/2009/15
Table 8.4
Summary of Environmental Inspections for Contract no. HK/2009/01
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.7 Summary of Environmental Inspections for
Contract no. HK/2012/08
Table 8.8 Summary of Environmental Inspections for Contract no. HY/2010/08
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring
Results and Graphical Presentations
Appendix
5.4 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of
Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
¡P
Planting trees and shrubs
¡P
Transplanting of trees
¡P
Drainage works
¡P
Trough structure construction including excavation, concreting and
waterproofing and backfill
¡P
Road works
¡P
Bridges construction
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
¡P
Stage 1 Defect rectification
¡P
Stage 2 Construction of exhaust duct
¡P
Stage 2 Construction of Bay 7, 8 and 9 top slab
¡P
Stage 2 Construction of Bay 10 wall
¡P
Stage 3 ELS excavation works
¡P
Stage 3 RC structure for CWB Tunnel Bay 11 and 12
¡P
Stage 3 Box culvert diversion
¡P
Stage 3 Construction works of Outfall at Expo Drive East
¡P
Cooling Main Installation (BI/BG) at Expo Drive East
¡P
Removal of abandoned cooling main (P7/P8) at Convention Avenue
¡P
Sewerage Pipeline A3-4B at Fenwick Pier Street
¡P
Roadworks /drains for Expo Drive East
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Removal of scaffolding and clearance works at OHVD at Tunnel Portion 1.
¡P
Concreting for upper central wall at Bay 1 and Bay 2
¡P
Concreting for upper north wall
¡P
Concreting for upper south wall
¡P
Concreting for south side OHVD at Bay 1, Bay 2 and Bay 3
¡P
Concreting for north side OHVD at Bay 1, Bay 2 an d Bay 3
¡P
Concreting for top slab at Bay 1
¡P
Approximately 80% excavation in layer S2
¡P
Struts installation for layer S
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
¡P
Construction of OHVD and base slab at Mined Tunnel
¡P
Inner bench excavation
¡P
Permanent lining structure at Mined Tunnel
¡P
Construction of diaphragm wall at TPCWAW
¡P
Installation of king post
¡P
Fabrication of third layer of ELS for TPCWAW
¡P
Excavation of ELS at TPCWAW
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Demolition of ELS for EVB
¡P
Pre-bored H-pile for Pier 23
¡P
Construction of TA2 bridge
¡P
Construction of temporary steel tower for IEC demolition
¡P
Saw cut of existing west bound of IEC bridge
¡P
Demolition of bulk head wall between C15 to C19
¡P
Construction works of EVB and APS structure
¡P
Column modification at F1 to F8
¡P
Demolition of IEC west bound deck/crosshead/column/pile cap
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
¡P
Diaphragm wall construction
¡P
Installation of dewatering wells
¡P
Grouting
¡P
Construction of ELS at MVB
¡P
Pre-bored H-pile construction
Contract
no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under
FEP-10/364/2009B
¡P
Tree protection works next to existing BGO,
¡P
Drainage improvement works,
¡P
Sheet piling works,
¡P
Excavation and Lateral Support for U-structure works,
¡P
Erection of noise absorption sheetings,
¡P
Pipe piling & grouting works,
¡P
Utility diversion works,
¡P
Waterproofing works &
¡P
Demolition of an existing bowling green office.
Contract
no. HY/2011/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
¡P
West Ventilation Building structure construction
¡P
Install VE panels bracket and thermal barrier for Tunnel
¡P
Construct reinforcement concrete structure for EVS
Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of Summons
and Successful Prosecutions
ET confirmed with the Resident Site
Staff that on 29 May 2015, vehicle record indicated that concerned vehicle TG
2426 has entered and exited the construction site via gate V3. Mitigation
measures adopted by the Contractor of HK/2009/01 at the above locations
include, water hose was provided for wheel washing at Gate V2 and Gate V3.
According to the relevant site records
under Contract HK/2009/01, vehicle record indicated that concerned vehicle TG
2426 has entered and exited the construction site via gate V3 on 29 May 2015
under Contract HK/2009/01. As confirmed by WDII RSS, the concerned construction
site Gate V2 and Gate V3 have been closed from 31 May 2015 and formed part of
the construction site area. Follow up inspection was conducted on 3 June 2015
during weekly environmental inspection and mitigation measures including wheel
washing were implemented at construction exit gates around the concerned location
despite a vehicle was observed leaving the construction site via Gate V8
without wheel washing. The Contractor was immediately advised to review and
strengthen the control measures for vehicle exits to ensure wheel washing are
provided for exiting vehicles.
In view of the public concern and the
site observation, the Contractor of HK/2009/01 has implemented enhanced site
exit control measures using red string to alert drivers to stop their vehicles
for cleaning before leaving the construction site and wheel washing facilities
including water hose were implemented at Gate V1 and Gate V10 around the
concerned location and the vehicle gate V8 was subsequently closed. In
addition, removal of spoil arising from wheel washing around site exit location
would be conducted by the Contractor of HK/2009/01 as appropriate to alleviate
for potential dust impact at construction site exits.
ET confirmed with the Resident Site
Staff that from 08:00hrs to 18:00hrs on 31 May 2015 (Sunday), construction work
including steel welding was conducted under Contract HK/2012/08 at site portion
zone A1 opposite to Fleet Arcade. Total one welding machine was in operation.
According to the relevant site records
under Contract HK/2012/08, from 08:00hrs to 18:00hrs on 31 May 2015 (Sunday),
construction work including steel welding was conducted under Contract
HK/2012/08 site portion zone A1 opposite to Fleet Arcade. Total one welding
machine was in operation and the relevant Construction Noise Permit
GW-RS0296-15 was confirmed in place. The construction activity conducted under
Contract HK/2012/08 during the concerned period was in compliance with the
statutory requirement. Ad-hoc
inspection was conducted during weekly environmental inspection on 9 June 2015
and it was noted that Construction Noise Permits under Contract HK/2012/08 were
posted at site entrance locations for public inspection. In view of the
potential noise nuisance, the Contractor was reminded to upkeep the site
control system for construction works carrying out at restricted hours and
night time for Construction Noise Permit compliance. Besides, other
construction sites at the concerned location were observed.
Furthermore, a meeting was held on 15
June 2015 between the EPD, Contractor of HK/2012/08, WDII RSS team and the
Environmental Team on the public concern and the Contractor of HK/2012/08 has
committed to review the re-application for the Construction Noise Permits
GW-RS0223-15 and GW-RS0296-15 on usage of PMEs at a portion of site area
outside the Fleet Arcade during public holiday including Sundays to minimize
for the potential noise nuisance to nearby public.
ET confirmed with the Resident Site
Staff that reinforced bar fixing and concreting work (on 17 June 2015 only)
were conducted at Portion 2 from 15 June 2015 to 19 June 2015. Total 3 nos. of
mobile crane were in operation. On 17 June 2015, one no. of concrete pump truck
and two nos. of concrete mixer were in operation. Excavation and Lateral
Support was conducted at Portions 3 & 4 from 15 June 2015 to 19 June 2015.
Total 4 nos. of excavator, 2 nos. of truck and 2 nos. of crawler crane were in
operation. In addition, on 15 June 2015, 17 June 2015 and 19 June 2015, 1 no.
of derrick barge was moored near Portions 3 & 4 for transportation of the
excavated material away from site.
According to the relevant site records
under Contract HK/2009/02, from 15 June 2015 to 19 June 2015, reinforced bar
fixing and concreting work (on 17 June 2015 only) were conducted at Portion 2
and total 3 nos. of mobile crane, one no. of concrete pump truck (on 17 June
2015 only) and two nos. of concrete mixer (on 17 June 2015 only) were in
operation; excavation and lateral support was conducted at Portions 3 & 4
and total 4 nos. of excavator, 2 nos. of truck and 2 nos. of crawler crane were
in operation. Based on relevant site record, no hopper barge was moored under
Contract HK/2009/02 around the concerned location while 1 no. of derrick barge
was moored under Contract HK/2009/02 near Portions 3 & 4 for transportation
of the excavated material from Portions 3 & 4 away from site on 15 June
2015, 17 June 2015 and 19 June 2015 respectively.
Follow-up inspection was conducted
during weekly environmental inspection on 25 June 2015, no dark smoke and
malodour emission was observed from the PMEs operating on-site. A derrick barge
was observed moored near Portions 3 & 4 and excavated material was
transferred to the derrick barge by the excavators on land without barge
operation and no particular dark smoke and malodour emission was observed.
Nevertheless, the Contractor was reminded to conduct regular checking on the
condition of the derrick barge and other PMEs deployed on site to ensure only
well maintained PMEs are used to avoid potential dark smoke and maldour
emission affecting nearby public.
Site Inspections and Audit
Future Key Issues
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Planting trees and shrubs
¡P
Transplanting of trees
¡P
Drainage works
¡P
Retaining wall and trough
structure construction including excavation, concreting,
waterproofing and backfill
¡P
Road works
¡P
Bridges construction
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under
FEP-02/364/2009
¡P
Stage 1 Defect rectification
¡P
Stage 2 Construction of slip road 2 and 3
¡P
Stage 2 Construction of Bay 10 and 9B
¡P
Stage 2 Construction of exhaust duct
¡P
Stage 3 ELS excavation and strut installing works
¡P
Stage 3 RC structure for Bay 11-13
¡P
Stage 3 Box culvert diversion
¡P
Removal of abandoned cooling main (P7/P8) at Convention Avenue
¡P
Sewerage Pipeline A3-4B at Fenwick Pier Street
¡P
Roadworks /drains for Expo Drive East
Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Tunnel structure works, i.e. OHVD base slab and top slab.
¡P
Strut layer S2 excavation and lateral support installation at both
sides.
¡P
Strut layer S3 excavation and lateral support installation at both sides
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Construction of OHVD and base slab at Mined Tunnel
¡P
Construction of wall and arch lining at Mined Tunnel
¡P
Fabrication of ELS steel works for TPCWAW
¡P
Excavation and installation of ELS at TPCWAW
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Pile cap construction for Pier 23, 29 & 30
¡P
Pre-bored H-pile for Approach Ramp
¡P
Abutment D12 construction
¡P
Saw cut of parapet at IEC West bound
¡P
Construction of TA2 bridge
¡P
Construction of temporary steel tower for IEC demolition
¡P
Saw cut of existing west bound of IEC bridge
¡P
Construction works of EVB and APS structure
¡P
Column modification at F1 to F8
¡P
Demolition of IEC west bound deck/crosshead/column/pile cap
¡P
Bridge E demolition works
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009/B
¡P
Diaphragm wall construction
¡P
Installation of dewatering wells
¡P
Grouting
¡P
Construction of ELS at MVB
¡P
Pre-bored H-pile construction
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009
¡P
Tree protection works next to existing BGO,
¡P
Drainage improvement works,
¡P
Sheet piling works,
¡P
Excavation and Lateral Support for U-structure,
¡P
Renovation works for Bowling Green Office,
¡P
Pipe piling & grouting works,
¡P
Utility diversion works,
¡P
Waterproofing works,
¡P
Reprovisional of Bowling Green.
Contract no. HY/2011/08 ¡V Central - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
¡P
West Ventilation Building structure construction
¡P
Install VE panels bracket and thermal barrier for Tunnel
¡P
Construct reinforcement concrete structure for EVS
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/C and
Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A,
FEP-09/364/2009/B, FEP-10/364/2009B and FEP-11/364/2009B to implement the Environmental Monitoring and Audit (EM&A) programme
as stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit
Requirements¡¨ under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/B, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A, FEP-09/364/2009B, FEP-10/364/2009B
and FEP-11/364/2009B during the period May 2015 to June 2015. The cut-off
date of reporting is at 27th of each reporting month
Section
1 Introduction ¡V details
the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results obtained
in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring results,
all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Environmental Site Audit ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and
¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called
¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested east-west Connaught Road Central/Harcourt Road / Gloucester
Road Corridor (the Corridor) which is currently operating beyond its capacity.
The CWB will provide relief to the existing congestion along the Corridor and
cater for the anticipated growth of traffic on Hong Kong Island. Without the
CWB and its access roads, there will not be sufficient capacity to serve the
heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central ¡V Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
¡P
A dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
¡P
The Central Interchange near the Rumsey Street Flyover to provide road
connections to the Central area;
¡P
Tunnel control buildings and ventilation buildings;
¡P
Slip roads to connect the CWB to the local road system in the Wan Chai
North and Causeway Bay area;
¡P
Associated road lighting, road signing, traffic control and surveillance
system; and
¡P
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason
for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in
length |
DP2 |
Road P2 and other roads which are classified as
primary/district distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging
works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging
operation less than 100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter
more than 1,200 mm and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from
Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a
seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield
Depot ¡V Advanced piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu
Street and Man Kwong Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works |
DP1,
DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East(CWB Tunnel) |
DP1 |
26
April 2011 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) |
DP1,DP3 |
13
July 2011 |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link |
DP1 |
24
March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai
Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel ¡V Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) ¡VTunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587
1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912
3010 |
|
Chun Wo ¡V Leader
Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Mr. Simon Liu |
2162 9909 |
2634
1626 |
Construction
Manager |
Mr. Terry Wong |
9757 9846 |
|||
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack
Chu |
9775 2467 |
|||
Environmental
Officer |
Ms. Wendy
Ng |
9103
2370 |
|||
Assistant
Environmental Engineer |
Ms. Connie Chan |
9047 6148 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827
9996 |
Project Manager |
Mr. Alfred Leung |
3658-3022 |
|||
Environmental Officer |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint
Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570
8013 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Construction Manager (Marine) |
Mr. William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Mr. Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Mr. Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Mr. Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214
7700 |
|
Deputy Site Agent |
Mr. Bob Yeung |
2214
7703 |
|||
Environmental Officer |
Ms. Lighting Chan |
2823
1161 |
|||
Assistant Environmental Engineer |
Mr. Penny Yiu |
2214
7738 |
|||
Environmental Supervisor |
Mr. K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Mr. Ray Cheng |
2214 7742 |
|||
Environmental Supervisor |
Mr. K. W. Lee |
6461 4623 |
|||
Environmental Supervisor |
Mr. Dorothy Shing |
2214
7705 |
|||
Environmental Supervisor |
Mr. C. Y. Au Yeung |
6461
8631 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2865 5229 |
Site Manager |
Mr. Y. Huo |
3557 6368 |
2566 2192 |
||
Contractor¡¦s
Representative |
Mr. Gene Cheung |
3557
6395 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Mr. Harry Wong |
3557 6348 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N.
Lai |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Eddie
Chung |
9193
8871 |
|||
Site
Agent |
Mr. Keith
Tse |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Y.L.
Ho |
6050
4919 |
|||
China State |
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung
Kit Cheung |
3557
6399 |
2566
8061 |
Project
Manager |
Chan
Ying Lun |
9812
0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467
4299 |
|||
Site
Agent |
Dr. Dave
Chan |
3467
4277 |
|||
Environmental
Officer |
Mr. C.M.
Wong |
3557
6464 |
|||
Environmental
Supervisor |
Mr. Louis
Lam Tsz Kwan |
3557
6470 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Project
Manager |
Paul
Evans |
2823 1111 |
21406799 |
Site
Agent |
Colman Wong |
2140
6799 |
|||
Environmental
Officer |
Malcom
Leung |
2214 7721 |
|||
Environmental
Supervisor |
Penny Yiu |
2214
7738 |
|||
Ramboll Environ Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics
Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882
3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. HY/2009/18 - Central - Wan
Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
¡P
Planting trees and shrubs
¡P
Transplanting of trees
¡P
Drainage works
¡P
Trough structure construction including excavation, concreting and
waterproofing and backfill
¡P
Road works
¡P
Bridges construction
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
¡P
Stage 1 Defect rectification
¡P
Stage 2 Construction of exhaust duct
¡P
Stage 2 Construction of Bay 7, 8 and 9 top slab
¡P
Stage 2 Construction of Bay 10 wall
¡P
Stage 3 ELS excavation works
¡P
Stage 3 RC structure for CWB Tunnel Bay 11 and 12
¡P
Stage 3 Box culvert diversion
¡P
Stage 3 Construction works of Outfall at Expo Drive East
¡P
Cooling Main Installation (BI/BG) at Expo Drive East
¡P
Removal of abandoned cooling main (P7/P8) at Convention Avenue
¡P
Sewerage Pipeline A3-4B at Fenwick Pier Street
¡P
Roadworks /drains for Expo Drive East
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai
Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Removal of scaffolding and clearance works at OHVD at Tunnel Portion 1.
¡P
Concreting for upper central wall at Bay 1 and Bay 2
¡P
Concreting for upper north wall
¡P
Concreting for upper south wall
¡P
Concreting for south side OHVD at Bay 1, Bay 2 and Bay 3
¡P
Concreting for north side OHVD at Bay 1, Bay 2 an d Bay 3
¡P
Concreting for top slab at Bay 1
¡P
Approximately 80% excavation in layer S2
¡P
Struts installation for layer S
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Construction of OHVD and base slab at Mined Tunnel
¡P
Inner bench excavation
¡P
Permanent lining structure at Mined Tunnel
¡P
Construction of diaphragm wall at TPCWAW
¡P
Installation of king post
¡P
Fabrication of third layer of ELS for TPCWAW
¡P
Excavation of ELS at TPCWAW
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
¡P
Demolition of ELS for EVB
¡P
Pre-bored H-pile for Pier 23
¡P
Construction of TA2 bridge
¡P
Construction of temporary steel tower for IEC demolition
¡P
Saw cut of existing west bound of IEC bridge
¡P
Demolition of bulk head wall between C15 to C19
¡P
Construction works of EVB and APS structure
¡P
Column modification at F1 to F8
¡P
Demolition of IEC west bound deck/crosshead/column/pile cap
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009B
¡P
Diaphragm wall construction
¡P
Installation of dewatering wells
¡P
Grouting
¡P
Construction of ELS at MVB
¡P
Pre-bored H-pile construction
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009B
¡P
Tree protection works next to existing BGO,
¡P
Drainage improvement works,
¡P
Sheet piling works,
¡P
Excavation and Lateral Support for U-structure works,
¡P
Erection of noise absorption sheetings,
¡P
Pipe piling & grouting works,
¡P
Utility diversion works,
¡P
Waterproofing works &
¡P
Demolition of an existing bowling green office.
Contract no. HY/2011/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
¡P
West Ventilation Building structure construction
¡P
Install VE panels bracket and thermal barrier for Tunnel
¡P
Construct reinforcement concrete structure for EVS
2.4.4.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract
no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under
FEP-05/364/2009/A
¡P
Planting trees and shrubs
¡P
Transplanting of trees
¡P
Drainage works
¡P
Retaining wall and trough
structure construction including excavation, concreting,
waterproofing and backfill
¡P
Road works
¡P
Bridges construction
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under
FEP-02/364/2009
¡P
Stage 1 Defect rectification
¡P
Stage 2 Construction of slip road 2 and 3
¡P
Stage 2 Construction of Bay 10 and 9B
¡P
Stage 2 Construction of exhaust duct
¡P
Stage 3 ELS excavation and strut installing works
¡P
Stage 3 RC structure for Bay 11-13
¡P
Stage 3 Box culvert diversion
¡P
Removal of abandoned cooling main (P7/P8) at Convention Avenue
¡P
Sewerage Pipeline A3-4B at Fenwick Pier Street
¡P
Roadworks /drains for Expo Drive East
Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Tunnel structure works, i.e. OHVD base slab and top slab.
¡P
Strut layer S2 excavation and lateral support installation at both
sides.
¡P
Strut layer S3 excavation and lateral support installation at both sides
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Construction of OHVD and base slab at Mined Tunnel
¡P
Construction of wall and arch lining at Mined Tunnel
¡P
Fabrication of ELS steel works for TPCWAW
¡P
Excavation and installation of ELS at TPCWAW
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Demolition of ELS for EVB
¡P
Pile cap construction for Pier 23, 29 & 30
¡P
Pre-bored H-pile for Approach Ramp
¡P
Abutment D12 construction
¡P
Saw cut of parapet at IEC West bound
¡P
Construction of TA2 bridge
¡P
Construction of temporary steel tower for IEC demolition
¡P
Saw cut of existing west bound of IEC bridge
¡P
Construction works of EVB and APS structure
¡P
Column modification at F1 to F8
¡P
Demolition of IEC west bound deck/crosshead/column/pile cap
¡P
Bridge E demolition works
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009/B
¡P
Diaphragm wall construction
¡P
Installation of dewatering wells
¡P
Grouting
¡P
Construction of ELS at MVB
¡P
Pre-bored H-pile construction
Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip
Road 8) under FEP-10/364/2009
¡P
Tree protection works next to existing BGO,
¡P
Drainage improvement works,
¡P
Sheet piling works,
¡P
Excavation and Lateral Support for U-structure,
¡P
Renovation works for Bowling Green Office,
¡P
Pipe piling & grouting works,
¡P
Utility diversion works,
¡P
Waterproofing works,
¡P
Reprovisional of Bowling Green.
Contract no. HY/2011/08 ¡V Central - Wan Chai Bypass (CWB) ¡VTunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009B
¡P
West Ventilation Building structure construction
¡P
Install VE panels bracket and thermal barrier for Tunnel
¡P
Construct reinforcement concrete structure for EVS
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of the current status
on licences and/or permits on environmental protection pertinent to the Project
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Superseded |
Environmental Permit |
EP-364/2009/C |
11 Jul 2014 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Surrendered |
Further
Environmental Permit |
FEP-06/356/2009 |
5 March 2013 |
Valid |
Further
Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Surrendered |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Surrendered |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai
Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.
Contract no. 04/HY/2006 ¡V Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP-04/HY/2006 was
surrendered by the Contractor on 11 February 2011.
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
3.1.5. The construction works was completed, and the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
Contract no.
HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.2 and Table 3.3.
Table 3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-pilling equipment |
GW-RS0243-15 |
16 Mar 2015 |
25 Mar 2015 to 24 Sept 2015 |
Valid |
|
GW-RS1472-14 |
2 Jan 2015 |
22 Jan 2015 to 21 Jul 2015 |
Cancelled |
|
GW-RS0079-15 |
27 Jan 2015 |
16 Feb 2015 to 14 Aug 2015 |
Valid |
|
GW-RS0074-15 |
22 Jan
2015 |
10 Feb 2015 to 9 Aug 2015 |
Valid |
|
GW-RS0104-15 |
3 Feb 2015 |
22 Feb 2015 to 21 Aug 2015 |
Valid |
|
GW-RS0101-15 |
3 Feb 2015 |
22 Feb 2015 to 21 Aug 2015 |
Valid |
|
GW-RS0269-15 |
16 Mar 2015 |
8 Apr 2015 to 7 Oct 2015 |
Valid |
|
GW-RS0408-15 |
13 Apr 2015 |
20 Apr 2015 to 19 Oct 2015 |
Cancelled |
|
GW-RS0416-15 |
16 Apr 2015 |
8 May 2015 to 7 Nov 2015 |
Valid |
GW-RS0445-15 |
30 Apr 2015 |
26 May 2015 to 25 Nov 2015 |
Valid |
|
GW-RS0462-15 |
30 Apr 2015 |
2 May 2015 to 1 Nov 2015 |
Valid |
|
Discharge Licence |
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
WT00021138-2015 |
17 Mar 2014 |
31 Mar 2020 |
Valid |
|
Billing account under
Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP_MD_16-018 |
02 Jun 2015 |
06 Jun 2015 to 30 Sept 2015 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) |
EP_MD_16_019 |
03 Jun 2015 |
06 Jun 2015 to 05 Jul 2015 |
Valid |
Table 3.3 Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of
Submission |