Contract No:
HK/2015/01 Wanchai
Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing
Work (Stage 3) Environmental Permit no. EP-364/2009/D, Further
Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/D,
FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B Monthly Environmental Monitoring &
Audit Report
- april 2016 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
09 May 2016 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3.
status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring Results
5.3 Air
Quality Monitoring Results
6.3 Review
of the Reasons for and the Implications of Non-compliance
6.4 Summary
of action taken in the event of and follow-up on non-compliance
7.
Cumulative Construction Impact due to the Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details of Individual Contracts
under the Project
Table 2.3 Contact Details of Key
Personnel
Table 3.1 Summary of the current status
on licences and/or permits on environmental
protection pertinent to the Project
Table 3.2 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.3 Summary of submission status
under FEP-02/364/2009
Table 3.4 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.5 Summary of submission status
under FEP-01/364/2009
Table 3.6 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.7 Summary of submission status
under FEP-05/364/2009/A
Table 3.8 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.9 Summary of submission status
under FEP-06/364/2009/A
Table 3.10 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.11
Summary of submission status under FEP-07/364/2009/D
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.13 Summary
of submission status under FEP-09/364/2009/B
Table 3.14 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.15 Summary of submission status under
FEP-10/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HY/2011/08
Table 3.17 Summary of submission status under FEP-11/364/2009/B
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring
Stations
Table 4.3 Air Quality Monitoring Stations
Table 5.1 Noise Monitoring
Stations for Contract no. HY/2009/18
Table 5.2 Noise Monitoring
Station for Contract no HK/2009/01 and HK/2009/02
Table 5.3 Noise Monitoring
Stations for Contract no. HY/2009/15
Table 5.4 Noise Monitoring
Stations for Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table 5.6 Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Real Time Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.9 Air Quality Monitoring
Station for Contract no. HY/2009/18
Table 5.10 Air Quality Monitoring Station
for Contract no. HK/2009/01
Table 5.11 Air Quality Monitoring Station
for Contract no. HK/2009/02
Table 5.12 Air Quality Monitoring Stations
for Contract no. HY/2009/15
Table 5.13 Air Quality
Monitoring Station for Contract no. HY/2009/19
Table 5.14 Air Quality
Monitoring Station for Contract no. HK/2012/08
Table 5.15 Air Quality Monitoring Stations for Contract no. HY/2010/08
Table 5.16 Air Quality Monitoring
Stations for Contract no. HY/2011/08
Table 5.17 Details of Waste Disposal
for Contract no. HK/2009/01
Table 5.18 Details of Waste
Disposal for Contract no. HK/2009/02
Table 5.19 Details of Waste
Disposal for Contract no. HY/2009/18
Table 5.20 Details of Waste
Disposal for Contract no. HY/2009/15
Table 5.21 Details of Waste Disposal
for Contract no. HY/2009/19
Table 5.22 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.23 Details of Waste Disposal
for Contract no. HY/2010/08
Table 5.24 Details of Waste Disposal for Contract
no. HY/2011/08
Table 8.1 Summary
of Environmental Inspections for Contract no. HY/2009/15
Table 8.4 Summary of
Environmental Inspections for Contract no. HK/2009/01
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.6 Summary of
Environmental Inspections for Contract no. HK/2012/08
Table 8.7 Summary of Environmental
Inspections for Contract no. HY/2010/08
Table 9.1 Cumulative Statistics on
Complaints
Table 9.2 Cumulative Statistics on
Successful Prosecutions
Table 10.1 Summary of Key
Construction Activities of Individual Contract(s) to be
commenced in Coming Reporting Month
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix
5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring Results and Graphical Presentations
Appendix
5.3 Air Quality Monitoring Results and
Graphical Presentations
Appendix 5.4 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of
Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under
FEP-05/364/2009/A
¡P
Drainage
works
¡P
Road
works
¡P
Landscaping
works
¡P
Modification
and Construction of Sign Gantries / Traffic Signs
¡P
Maintenance
works
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under
FEP-02/364/2009
¡P
Stage 3a
backfilling works
¡P
Stage 3b
backfilling works
¡P
Stage 4
construction tunnel structure
¡P
Reinstatement
of outfall
¡P
Reinstatement
of triangular planter at Fenwick Pier Street
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Site
clearance works was on going at OHVD at Tunnel Portion 1.
¡P
Waterproofing
works and base slab construction were completed
¡P
Middle
wall and side wall construction
¡P
Diaphragm
wall panel construction
¡P
King post
work was completed
¡P
Instrumentation
work was on going
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
¡P
Backfilling
works at TPCWAW
¡P
Dismantle
steel work at TPCWAW
¡P
Remaining
works inside tunnel at TS4 and TPCWAE
¡P
Remedial
works at Mined Tunnel
¡P
Reinstatement
of Shaft B between TPCWAW and TPCWAE
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/D
¡P
Pier
construction for IEC
¡P
Construction
of EVB
¡P
Column
modification at F1 to F8
¡P
Watson
Road laying of new water pipe
¡P
Oil
Street drainage works
¡P
Excavation
/ Construction of retaining wall/Piling works/Approach Ramp
¡P
Bridge
segment erections
¡P
Hing Fat
Street modification works
¡P
EVA
bulkhead removal
¡P
Hing Fat
Street Slip Road Bridge E parapet construction
Contract no.
HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan
Chai West under FEP-09/364/2009B
¡P
Grouting
¡P
Construction
of MVB
¡P
Pre-bored
H-pile construction
¡P
Construction
of concrete plug
¡P
Excavation
and lateral support installation for CWB tunnel
Contract no.
HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under
FEP-10/364/2009B
¡P
Tree
protection works next to existing BGO,
¡P
Drainage
improvement works,
¡P
Excavation
and Lateral Support for U-structure,
¡P
Pipe
piling & grouting works,
¡P
Utility
diversion works,
¡P
Retaining
wall works
¡P
ELS
works,
¡P
D-wall
drill cutting works
¡P
Construction
works for subway extension
Contract no.
HY/2011/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
¡P
Construction
of Ventilation Buildings, inclusive of Administrative Building, East
Ventilation Shaft, West Ventilation Building
¡P
Construction
of Tunnel Thermal Barrier
¡P
Installation
of Electricals and Mechanicals
¡P
Installation
of Tunnel Features
Noise Monitoring
Air Quality Monitoring
The 24hr TSP monitoring at air quality
monitoring station CMA1b was rescheduled from 13 April 2016 to 14 April 2016
The 24hr TSP monitoring at air quality
monitoring station CMA3a was rescheduled from 01 April 2016 to 02 April 2016.
The 24hr TSP monitoring at air quality
monitoring station CMA5b was rescheduled from 13 April 2016 to 14 April 2016
Complaints, Notifications of Summons and Successful Prosecutions
ET confirmed with the Resident Site
Staff that pipe Laying works between Pier 32 and Pier 33 and excavation and
blinding works for Manhole at Pier 34 were in progress on 22 March 2016.
The observed drain hole was identified
to be the outlet point of a manhole and a section of an abandoned U-channel
(extending from the concerned manhole to the Hong Kong Electric Substation in
length along the site boundary) was adjoining the concerned manhole and sandbag
was previously placed at the U-channel at the location near the inlet point to
the concerned manhole.
Based on the site records confirmed by
RSS, pipe laying works between Pier 32 and Pier 33 and excavation and blinding
works for Manhole at Pier 34 were in progress on 22 March 2016. The observed
drain hole was identified to be the outlet point of a manhole and a section of
an abandoned U-channel (extending from the concerned manhole to the Hong Kong
Electric Substation in length along the site boundary) was adjoining the
concerned manhole and sandbag was previously placed at the U-channel at the
location near the inlet point to the concerned manhole. In addition, no site
discharge point was connected to the aforesaid U-channel and the concerned
manhole. In view of the environmental concern, the following remedial and
precautionary actions were taken by the Contractor of HY/2009/19 on 29 March
2016.
i)
Plugging
the inlet point of the concerned manhole (connecting to the abandoned
U-channel) with concrete;
ii)
Plugging
the outlet of the concerned manhole (connecting to the observed drain hole)
with concrete;
iii)
Filling
the concerned manhole with rubbles;
iv)
Shifting
the unused wastewater treatment plant around the concerned location to other
site location for use.
Follow-up inspection was conducted by
the Environmental Team on 06 April 2016. No further contaminated runoff
discharge was observed from the concerned drain hole and precautionary measures
including provision of concrete bunding was implemented along the site boundary
at the concerned location to avoid potential surface overflow. The pipe laying
works and the excavation works was found at distant location away from the
concerned drain hole with no surface drain connection and no particular
effluent was generated from the work. As such, no information indicate the
discharge was related to the above construction activities.
However, it was noted that another
section of surface drainage channel within the construction site (perpendicular
in direction to the initial identified abandoned U-channel) was also in
connection to concerned manhole and minor residue mud deposition was observed
within the surface drainage channel. Despite the above additional surface
drainage channel identified, the outlet point of concerned final manhole (in
connection with the observed drain hole) was observed plugged with concrete and
filled with rubbles as rectification measure to avoid any further contaminated
runoff discharge via the observed drain hole.
Nevertheless, the Contractor of
HY/2009/19 was reminded to conduct regular cleaning works for site surface
drainage channel to avoid accumulation of silt and soil and avoid potential
overflow by directing the surface runoff within the surface drainage channel to
proper collection point for necessary treatment prior to discharge. The
Contractor of HY/2009/19 was also reminded to check and review other surface
drainage channel within the construction site to avoid potential runoff related
impact via surface drainage channel to the nearby waters.
In addition, it was noticed that water
was discharged from a piping extending from City Garden and the discharged
water would result in seepage across the site hoarding into the abandoned
U-channel. The Contractor of HY/2009/19 was suggested to liaise with the City
Garden Management Office for proper connection of the observed pipping with
discharge to prevent further seepage water into the construction site.
ET confirmed with the Resident Site
Staff that drilling holes for installation of starter bars was carried out
under Contract HY/2009/19 at the vertical cut face of the existing IEC road
slab on 05 April 2016
Based on the site records confirmed by
RSS, drilling holes for installation of starter bars was carried out under
Contract HY/2009/19 at the vertical cut face of the existing IEC road slab on
05 April 2016 and according to the photo information provided by the EPD, no
dust suppression measures was implemented during the observed drilling works on
05 April 2016.
According to Air Pollution Control
Ordinance, for pneumatic or power-driven drilling, cutting and polishing, water
or a dust suppression chemical shall be continuously sprayed on the surface
where any pneumatic or power-driven drilling, cutting, polishing or other
mechanical breaking operation that causes dust emission is carried out, unless
the process is accompanied by the operation of an effective dust extraction and
filtering device.
Follow-up inspection was conducted on 06
April 2016, rectification actions including the use of vacuum suction to
extract dust generated during the concerned drilling works was observed
implemented by the Contractor of HY/2009/19 for starter bars drilling works.
ET confirmed with the Resident Site
Staff that the concerned tree was identified as T710 and no construction
activity in the vicinity of tree T710 on 27 March 2016 and no construction
works are required in or near its vicinity.
Based on the site records confirmed by
RSS, the concerned tree was identified as the retained tree T710 maintained
under the Contract of HY/2010/08 and the concerned tree T710 was located
outside the assessment area in the relevant Project EIA Report. No construction
works are required in the vicinity of concerned tree T710 and no construction
activity was conducted in the vicinity of tree T710 on 27 March 2016.
Nevertheless, based on RSS information, recent tree monitoring report indicates
an existing cavity at trunk and the concerned tree T710 has been recommended to
be felled in the tree risk assessment Form 2.
With respect to the observed incident of
the toppling of the concerned tree T710, the Contractor of HY/2010/08 was
instructed by RSS to remove the broken trunk/ remains to avoid impact to the
surroundings. The concerned tree T710 shall be compensated by the Contractor of
HY/2010/08 in accordance with the Development Bureau Technical Circular (Works)
No. 7/2015 and the detail on compensation would be further agreed with Victoria
Park Management Office. Follow-up inspection was conducted on 13 April 2016,
and the remaining parts of the concerned tree T710 was observed felled to avoid
further impact to nearby public road.
ET confirmed with the Resident Site
Staff that no marine construction activities or land construction activities
under Contract HK/2009/02 at the concerned location on 12 April 2016.
Surface runoff control measures
including provision of concrete bund at the concerned location was implemented
by Contract HK/2009/02.
No soil & silt deposition along the
seawall at the concerned location on 12 April 2016.
No discharge point located in the
vicinity of the concerned location under Contract HK/2009/02.
Silt curtain with buoyancy floats acting
as anchor points was installed at Monitoring Station RW21-P789 for Water
intakes.
Based on the site records confirmed by
RSS, no marine construction activities or land construction activities was carried
out under Contract HK/2009/02 at the concerned location on 12 April 2016 and no
soil and silt deposition was found along the seawall at the concerned location
and precautionary measures for site runoff control including provision of
concrete bund along boundary of site area near the waterfront around the
concerned location was implemented by the Contractor HK/2009/02. In addition,
no discharge point under Contract HK/2009/02 was located in the vicinity of the
concerned location. Based on information confirmed by RSS, the buoyancy floats
deployed at the concerned location are acting as the anchor points for the silt
curtain deployed around the WQM Station RW21-P789 for the WSD and Cooling Water
Intakes group.
Follow-up inspection was conducted on 14
April 2016, no surface runoff from the construction site nor discharge of
contaminated effluent was observed around the concerned location and
precautionary measures including the provision of concrete bund at the
concerned location was observed maintained by the Contractor of HK/2009/02 and
the silt curtain deployed around the WQM station RW21-P789 was generally in
order.
In view of the public concern on the
water quality, the Contractor of HK/2009/02 was reminded to maintain effective
surface runoff protection and provide proper collection point of construction
effluent around the concerned location to avoid potential surface runoff
related impact.
ET confirmed with the Resident Site
Staff that internal transport of soil to the hopper barge for storage via
landing barge was conducted by Contractor of HK/2012/08 during 0800 hours to
1000 hours on 13 April 2016 at the sea outside the concerned location and 3 nos.
of dump trucks were deployed for the operation.
Protection measure including provision
of sandbag bunding along the side of the landing barge was implemented by the
Contractor of HK/2012/08.
According to the relevant site records
provided by RSS, internal transport of soil to the hopper barge for storage via
landing barge was conducted by Contractor of HK/2012/08 during 0800 hours to
1000 hours on 13 April 2016 at the sea outside the concerned location and 3
nos. of dump trucks were deployed for the operation. Protection measure
including provision of sandbag bunding along the side of the landing barge was
implemented by the Contractor of HK/2012/08. In addition, amber rainstorm
warning signal was hoisted from 0630 hours to 1200 hours on 13 April 2016 and
during the above time period, muddy water was observed from the upstream of
culvert L outside the HK/2012/08 site.
Follow up inspection was conducted on 19
April 2016, protection measures including provision of sandbag bunding along
the side of the landing barge was implemented and no mud or soil deposition was
observed along the seawall and no discharge point was located within the
temporary water channel connecting the Culvert L outfall location to the
Victoria Harbour. In addition, piling works was observed at the north side of
Zone A1 on 19 April 2016 and construction effluent collection from piling work
via sedimentation tank to wastewater treatment facility was implemented and
steel barrier was installed around the piling works area to mitigate against
potential surface runoff related impact.
Nevertheless, in view of the public
concern, the Contractor was reminded to maintain adequate perimeter embankment
protection along the seawall boundary and maintain proper construction effluent
collection system to avoid potential runoff related impact to nearby waters.
Site Inspections and Audit
Future
Key Issues
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Drainage
works
¡P
Road
works
¡P
Landscaping
works
¡P
Modification
and Construction of Sign Gantries / Traffic Signs
¡P
Maintenance
works
Contract
no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
¡P
Stage 3b
backfilling works
¡P
Stage 4
construction tunnel structure
¡P
Reinstatement
of outfall
¡P
Reinstatement
of triangular planter at Fenwick Pier Street
Contract
no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Construction
of pre-cast concrete cover
¡P
Tunnel
OHVD construction
¡P
Tunnel
wall and top slab construction
¡P
Waterproofing
layer at side wall slap application
¡P
Road side
barrier construction
¡P
Removal
of remaining temporary sheetpile seawall
¡P
Removal
of blockwork seawall near the interface between Portion 2 and Portion 5
¡P
Diaphragm
wall construction
¡P
Excavation
work
¡P
Strut
installation
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Remedial
works at Mined Tunnel
¡P
Remaining
works inside tunnel at TS4 and TPCWAE
¡P
Removal
of ELS and backfilling works at TPCWAW
¡P
Reinstatement
of Shaft B between TPCWAW and TPCWAE
¡P
Saw
cutting of diaphragm wall at TPCWAW
Contract
no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/D
¡P
Construction
of EVB
¡P
Column
modification at F1 to F8
¡P
Watson
Road laying of new water pipe
¡P
Oil
Street drainage works
¡P
Excavation
/ Construction of retaining wall/Piling works/Approach Ramp
¡P
Bridge
segment erections
¡P
Hing Fat
Street modification works
¡P
EVA
bulkhead removal
¡P
Hing Fat
Street Slip Road Bridge E parapet construction
Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan
Chai Bypass at Wan Chai West under FEP-09/364/2009/B
¡P
Grouting
¡P
Construction
of MVB
¡P
Pre-bored
H-pile construction
¡P
Construction
of concrete plug
¡P
Excavation
and lateral support installation for CWB tunnel
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009
¡P
Tree
protection works next to existing BGO,
¡P
Drainage
improvement works,
¡P
Excavation
and Lateral Support for U-structure,
¡P
Pipe
piling & grouting works,
¡P
Utility
diversion works,
¡P
Retaining
wall works
¡P
ELS
works,
¡P
D-wall
drill cutting works
¡P
Construction
works for subway extension
Contract no. HY/2011/08 ¡V Central - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
¡P
Construction
of Ventilation Buildings, inclusive of Administrative Building, East
Ventilation Shaft, West Ventilation Building
¡P
Construction
of Tunnel Thermal Barrier
¡P
Installation
of Electricals and Mechanicals
¡P
Installation
of Tunnel Features
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/D and
Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/D,
FEP-09/364/2009/B, FEP-10/364/2009B and FEP-11/364/2009B to implement the Environmental Monitoring and Audit (EM&A) programme
as stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit
Requirements¡¨ under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/D, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A, FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B
during the period 27 March 2016 to 26 April 2016.
Section 1 Introduction ¡V details the scope
and structure of the report.
Section 2 Project
Background
¡V summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance ¡V summarizes the
status of valid Environmental Permits / Licenses during the reporting period.
Section 4 Monitoring
Requirements
¡V summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section 5 Monitoring
Results
¡V summarizes the monitoring results obtained in the reporting period.
Section 6 Compliance
Audit
¡V summarizes the auditing of monitoring results, all exceedances
environmental parameters.
Section 7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Environmental Site Audit ¡V summarizes the
findings of weekly site inspections undertaken within the reporting period,
with a review of any
relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of summons and Prosecution
¡V
summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and
¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called
¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested east-west Connaught Road Central/Harcourt Road / Gloucester
Road Corridor (the Corridor) which is currently operating beyond its capacity.
The CWB will provide relief to the existing congestion along the Corridor and
cater for the anticipated growth of traffic on Hong Kong Island. Without the
CWB and its access roads, there will not be sufficient capacity to serve the
heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central ¡V Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
¡P
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
¡P
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
¡P
Tunnel
control buildings and ventilation buildings;
¡P
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
Causeway Bay area;
¡P
Associated
road lighting, road signing, traffic control and surveillance system; and
¡P
Other
associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further Environmental
Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre ¡V Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1,DP3 |
13 July 2011 |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai Bypass at Wan Chai
West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel ¡V Tunnel (Slip Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Manager |
Mr. Simon Liu |
2162 9909 |
2634 1626 |
Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction Manager |
Mr. Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Terry
Tsang |
6683 9394 |
|||
Environmental
Officer |
Ms. Wendy Ng |
9803 0057 |
|||
Assistant Environmental
Engineer |
Ms. Connie Chan |
6157 7057 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827 9996 |
Project Manager |
Mr. Paul Yu |
3658 3085 |
|||
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570 8013 |
Deputy Project Manager |
Mr. William Luk |
9456 9819 |
|||
Deputy Site Agent |
Eric Fong |
6191 9337 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214 7700 |
|
Deputy Site Agent |
Mr. Bob Yeung |
2214 7703 |
|||
Environmental Officer |
Mr. Chris Chan |
2823 1161 |
|||
Assistant Environmental Engineer |
Mr. Christy So |
3937 1065 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2865 5229 |
Site Manager |
Mr. Y. Huo |
3557 6368 |
2566 2192 |
||
Contractor¡¦s
Representative |
Mr. Andrew Wong |
3557 6371 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Mr. Harry Wong |
3557 6348 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N. Lai |
9137 1811 |
2877 1522 |
Project
Manager |
Mr. Eddie
Chung |
9193 8871 |
|||
Site Agent |
Mr. Keith Tse |
9095 7922 |
|||
Environmental
Officer |
Mr. James MA |
9130 9549 |
|||
Environmental
Supervisor |
Mr. Y.L. Ho |
6050 4919 |
|||
China State |
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung Kit
Cheung |
3557 6399 |
2566 8061 |
Project
Manager |
Chan Ying
Lun |
9812 0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467 4299 |
|||
Site Agent |
Dr. Dave Chan |
3467 4277 |
|||
Environmental
Officer |
Mr. C.M. Wong |
3557 6464 |
|||
Environmental
Supervisor |
Mr. Louis Lam
Tsz Kwan |
3557 6470 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Project
Manager |
Paul Evans |
2823 1111 |
21406799 |
Site Agent |
Colman Wong |
9730 0806 |
|||
Environmental
Officer |
Malcom
Leung |
3973 0850 |
|||
Environmental
Supervisor |
Christy So |
3973 1065 |
|||
Ramboll Environ Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
FEP-05/364/2009/A
¡P
Drainage
works
¡P
Road
works
¡P
Landscaping
works
¡P
Modification
and Construction of Sign Gantries / Traffic Signs
¡P
Maintenance
works
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
¡P
Stage 3a
backfilling works
¡P
Stage 3b
backfilling works
¡P
Stage 4
construction tunnel structure
¡P
Reinstatement
of outfall
¡P
Reinstatement
of triangular planter at Fenwick Pier Street
Contract
no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai
East (CWB Tunnel) under FEP-01/364/2009
¡P
Site
clearance works was on going at OHVD at Tunnel Portion 1.
¡P
Waterproofing
works and base slab construction were completed
¡P
Middle
wall and side wall construction
¡P
Diaphragm
wall panel construction
¡P
King post
work was completed
¡P
Instrumentation
work was on going
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Backfilling
works at TPCWAW
¡P
Dismantle
steel work at TPCWAW
¡P
Remaining
works inside tunnel at TS4 and TPCWAE
¡P
Remedial
works at Mined Tunnel
¡P
Reinstatement
of Shaft B between TPCWAW and TPCWAE
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
¡P
Pier
construction for IEC
¡P
Construction
of EVB
¡P
Column
modification at F1 to F8
¡P
Watson
Road laying of new water pipe
¡P
Oil
Street drainage works
¡P
Excavation
/ Construction of retaining wall/Piling works/Approach Ramp
¡P
Bridge
segment erections
¡P
Hing Fat
Street modification works
¡P
EVA
bulkhead removal
¡P
Hing Fat
Street Slip Road Bridge E parapet construction
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009B
¡P
Grouting
¡P
Construction
of MVB
¡P
Pre-bored
H-pile construction
¡P
Construction
of concrete plug
¡P
Excavation
and lateral support installation for CWB tunnel
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009B
¡P
Tree
protection works next to existing BGO,
¡P
Drainage
improvement works,
¡P
Excavation
and Lateral Support for U-structure,
¡P
Pipe
piling & grouting works,
¡P
Utility
diversion works,
¡P
Retaining
wall works
¡P
ELS
works,
¡P
D-wall
drill cutting works
¡P
Construction
works for subway extension
Contract no. HY/2011/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
¡P
Construction
of Ventilation Buildings, inclusive of Administrative Building, East
Ventilation Shaft, West Ventilation Building
¡P
Construction
of Tunnel Thermal Barrier
¡P
Installation
of Electricals and Mechanicals
¡P
Installation
of Tunnel Features
2.4.4.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no.
HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under
FEP-05/364/2009/A
¡P
Drainage
works
¡P
Road
works
¡P
Landscaping
works
¡P
Modification
and Construction of Sign Gantries / Traffic Signs
¡P
Maintenance
works
Contract
no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
¡P
Stage 3b
backfilling works
¡P
Stage 4
construction tunnel structure
¡P
Reinstatement
of outfall
¡P
Reinstatement
of triangular planter at Fenwick Pier Street
Contract
no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Construction
of pre-cast concrete cover
¡P
Tunnel
OHVD construction
¡P
Tunnel
wall and top slab construction
¡P
Waterproofing
layer at side wall slap application
¡P
Road side
barrier construction
¡P
Removal
of remaining temporary sheetpile seawall
¡P
Removal
of blockwork seawall near the interface between Portion 2 and Portion 5
¡P
Diaphragm
wall construction
¡P
Excavation
work
¡P
Strut
installation
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Remedial
works at Mined Tunnel
¡P
Remaining
works inside tunnel at TS4 and TPCWAE
¡P
Removal
of ELS and backfilling works at TPCWAW
¡P
Reinstatement
of Shaft B between TPCWAW and TPCWAE
¡P
Saw
cutting of diaphragm wall at TPCWAW
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
¡P
Pier
construction for IEC
¡P
Construction
of EVB
¡P
Column
modification at F1 to F8
¡P
Watson
Road laying of new water pipe
¡P
Oil
Street drainage works
¡P
Excavation
/ Construction of retaining wall/Piling works/Approach Ramp
¡P
Bridge
segment erections
¡P
Hing Fat
Street modification works
¡P
EVA
bulkhead removal
¡P
Hing Fat
Street Slip Road Bridge E parapet construction
Contract no.
HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan
Chai West under FEP-09/364/2009/B
¡P
Grouting
¡P
Construction
of MVB
¡P
Pre-bored
H-pile construction
¡P
Construction
of concrete plug
¡P
Excavation
and lateral support installation for CWB tunnel
Contract
no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under
FEP-10/364/2009
¡P
Tree
protection works next to existing BGO,
¡P
Drainage
improvement works,
¡P
Excavation
and Lateral Support for U-structure,
¡P
Pipe
piling & grouting works,
¡P
Utility
diversion works,
¡P
Retaining
wall works
¡P
ELS
works,
¡P
D-wall
drill cutting works
¡P
Construction
works for subway extension
Contract
no. HY/2011/08 ¡V Central - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
¡P
Construction
of Ventilation Buildings, inclusive of Administrative Building, East
Ventilation Shaft, West Ventilation Building
¡P
Construction
of Tunnel Thermal Barrier
¡P
Installation
of Electricals and Mechanicals
¡P
Installation
of Tunnel Features
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of the current status
on licences and/or permits on environmental protection pertinent to the Project
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-364/2009/A |
4 Aug
2010 |
Superseded |
Environmental
Permit |
EP-364/2009/B |
20 Sep
2012 |
Superseded |
Environmental
Permit |
EP-364/2009/C |
11 Jul
2014 |
Superseded |
Environmental
Permit |
EP-364/2009/D |
24 Nov
2015 |
Valid |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Surrendered |
Further Environmental Permit |
FEP-06/356/2009 |
5
March 2013 |
Valid |
Further Environmental Permit |
FEP-07/356/2009 |
26
July 2013 |
Valid |
Further
Environmental Permit |
24 Mar
2010 |
Valid |
|
Further
Environmental Permit |
21 Apr 2010 |
Valid |
|
Further
Environmental Permit |
12 July 2010 |
Surrendered
|
|
Further
Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further
Environmental Permit |
15 Nov 2010 |
Valid |
|
Further
Environmental Permit |
22 Nov 2010 |
Valid |
|
Further
Environmental Permit |
25 Feb 2011 |
Superseded |
|
Further
Environmental Permit |
24 Nov 2015 |
Valid |
|
Further
Environmental Permit |
15 June 2012 |
Surrendered |
|
Further
Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further
Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further
Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai
Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.
Contract no. 04/HY/2006 ¡V Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP-04/HY/2006 was
surrendered by the Contractor on 11 February 2011.
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
3.1.5. The construction works was completed, and the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
Contract no.
HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.2 and Table 3.3.
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits
and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling equipment |
GW-RS1134-15 |
23 Oct 2015 |
08 Nov 2015 to 07 May 2016 |
Valid |
GW-RS1135-15 |
23 Oct 2015 |
26 Nov 2015 to 25 May 2016 |
Valid |
|
GW-RS1228-15 |
13 Nov 2015 |
16 Nov 2015 to 13 May 2016 |
Valid |
|
GW-RS1309-15 |
27 Nov 2015 |
30 Nov 2015 to 26 May 2016 |
Valid |
|
GW-RS1338-15 |
11 Dec 2015 |
01 Jan 2016 to 30 June 2016 |
Valid |
|
GW-RS0041-16 |
22 Jan 2016 |
25 Jan 2016 to 23 Jul 2016 |
Valid |
|
GW-RS0089-16 |
05 Feb 2016 |
20 Feb 2016 to 19 July 2016 |
Valid |
|
GW-RS0093-16 |
05 Feb 2016 |
22 Feb 2016 to 21 July 2016 |
Valid |
|
GW-RS0152-16 |
18 Feb 2016 |
25 Feb 2016 to 24 Aug 2016 |
Valid |
|
GW-RS0243-16 |
11 Mar 2016 |
14 Mar 2016 to 13 Sep 2016 |
Valid |
|
GW-RS0384-16 |
19 Apr 2016 |
22 Apr 2016 to 19 Oct 2016 |
Valid |
|
Discharge License |
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
WT00021138-2015 |
17 Mar 2014 |
31 Mar 2020 |
Valid |
|
Billing account under
Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.3 Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May 2011 |
Condition 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Condition 1.12 |
Commencement Date of Works |
20 Jun 2011 |
Condition 2.9 |
Noise Management Plan |
10 Jun 2011 |
Condition 2.11 |
Landscape Plan (Rev.4) |
8 July 2015 |
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.7.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.4 and Table 3.5.
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of
Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-pilling equipment |
GW-RS1121-15 |
20 Oct 2015 |
22 Oct 2015 to 18 Apr 2016 |
Cancelled |
GW-RS1150-15 |
26 Oct 2015 |
28 Oct 2015 to 27 Apr 2016 |
Valid |
|
GW-RS1187-15 |
28 Oct 2015 |
30 Oct 2015 to 27 Apr 2016 |
Valid |
|
GW-RS1413-15 |