Contract No:
HK/2015/01 Wanchai
Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing
Work (Stage 3) Environmental Permit no. EP-364/2009/D, Further
Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/D,
FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B Monthly Environmental Monitoring &
Audit Report
- MAY 2016 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
June 2016 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3.
status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring Results
5.3 Air
Quality Monitoring Results
6.3 Review
of the Reasons for and the Implications of Non-compliance
6.4 Summary
of action taken in the event of and follow-up on non-compliance
7.
Cumulative Construction Impact due to the Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details of Individual Contracts
under the Project
Table 2.3 Contact Details of Key
Personnel
Table 3.1 Summary of the current status
on licences and/or permits on environmental
protection pertinent to the Project
Table 3.2 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.3 Summary of submission status
under FEP-02/364/2009
Table 3.4 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.5 Summary of submission status
under FEP-01/364/2009
Table 3.6 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.7 Summary of submission status
under FEP-05/364/2009/A
Table 3.8 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.9 Summary of submission status
under FEP-06/364/2009/A
Table 3.10 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.11
Summary of submission status under FEP-07/364/2009/D
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.13 Summary
of submission status under FEP-09/364/2009/B
Table 3.14 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.15 Summary of submission status under
FEP-10/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HY/2011/08
Table 3.17 Summary of submission status under FEP-11/364/2009/B
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring
Stations
Table 4.3 Air Quality Monitoring Stations
Table 5.1 Noise Monitoring
Stations for Contract no. HY/2009/18
Table 5.2 Noise Monitoring
Station for Contract no HK/2009/01 and HK/2009/02
Table 5.3 Noise Monitoring
Stations for Contract no. HY/2009/15
Table 5.4 Noise Monitoring
Stations for Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table 5.6 Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Real Time Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.9 Air Quality Monitoring
Station for Contract no. HY/2009/18
Table 5.10 Air Quality Monitoring Station
for Contract no. HK/2009/01
Table 5.11 Air Quality Monitoring Station
for Contract no. HK/2009/02
Table 5.12 Air Quality Monitoring Stations
for Contract no. HY/2009/15
Table 5.13 Air Quality
Monitoring Station for Contract no. HY/2009/19
Table 5.14 Air Quality
Monitoring Station for Contract no. HK/2012/08
Table 5.15 Air Quality Monitoring Stations for Contract no. HY/2010/08
Table 5.16 Air Quality Monitoring
Stations for Contract no. HY/2011/08
Table 5.17 Details of Waste Disposal
for Contract no. HK/2009/01
Table 5.18 Details of Waste
Disposal for Contract no. HK/2009/02
Table 5.19 Details of Waste
Disposal for Contract no. HY/2009/18
Table 5.20 Details of Waste
Disposal for Contract no. HY/2009/15
Table 5.21 Details of Waste Disposal
for Contract no. HY/2009/19
Table 5.22 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.23 Details of Waste Disposal
for Contract no. HY/2010/08
Table 5.24 Details of Waste Disposal for Contract
no. HY/2011/08
Table 8.1 Summary
of Environmental Inspections for Contract no. HY/2009/15
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.6 Summary of
Environmental Inspections for Contract no. HK/2012/08
Table 8.7 Summary of Environmental Inspections
for Contract no. HY/2010/08
Table 9.1 Cumulative Statistics on
Complaints
Table 9.2 Cumulative Statistics on
Successful Prosecutions
Table 10.1 Summary of Key
Construction Activities of Individual Contract(s) to be
commenced in Coming Reporting Month
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix
5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring Results and Graphical Presentations
Appendix
5.3 Air Quality Monitoring Results and
Graphical Presentations
Appendix 5.4 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of
Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under
FEP-05/364/2009/A
¡P
Drainage
works
¡P
Road
works
¡P
Landscaping
works
¡P
Modification
and Construction of Sign Gantries / Traffic Signs
¡P
Maintenance
works
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under
FEP-02/364/2009
¡P
Stage 3b
backfilling works
¡P
Stage 4
construction tunnel structure
¡P
Reinstatement
of outfall
¡P
Reinstatement
of triangular planter at Fenwick Pier Street
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Site clearance
works was on going at OHVD at Tunnel Portion 1.
¡P
Site clearance
works was on going at OHVD at Tunnel Portion 2.
¡P
Waterproofing
work for side wall
¡P
Middle
wall and side wall construction
¡P
Tunnel
top slab construction
¡P
Diaphragm
wall panel construction
¡P
Instrumentation
work was on going
¡P
Excavation
work
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
¡P
Dismantle
steel work at TPCWAW
¡P
Remedial
works at Mined Tunnel
¡P
Remedial
works at TS4, TPCWAE
¡P
Reinstatement
of Shaft B between TPCWAW and TPCWAE
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/D
¡P
Pier
construction for IEC
¡P
Construction
of EVB
¡P
Column
modification at F1 to F8
¡P
Oil
Street drainage works
¡P
Bridge
construction and segment erection
¡P
Hing Fat
Street modification works
¡P
EVA
structure construction
¡P
Hing Fat
Street Slip Road Bridge E L3 railing construction
¡P
Approach
ramp sheet piling works
¡P
EVB
waterproofing works
Contract no.
HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan
Chai West under FEP-09/364/2009B
¡P
Grouting
¡P
Construction
of MVB
¡P
Construction
of concrete plug
¡P
Excavation
and lateral support installation for CWB tunnel
¡P
Structural
works for CWB tunnel construction
Contract no.
HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under
FEP-10/364/2009B
¡P
Tree
protection works next to existing BGO,
¡P
Drainage
improvement works,
¡P
Excavation
and Lateral Support for U-structure,
¡P
Pipe
piling & grouting works,
¡P
Utility
diversion works,
¡P
Retaining
wall works
¡P
ELS works,
¡P
Construction
works for subway extension
Contract no.
HY/2011/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
¡P
Construction
of Ventilation Buildings, inclusive of Administration Building, East
Ventilation Shaft West Ventilation Building
¡P
Construction
of Tunnel Thermal Barrier
¡P
Installation
of Electricals and Mechanicals
¡P
Installation
of Tunnel Features
Noise Monitoring
Air Quality Monitoring
The 24hr TSP monitoring at air quality
monitoring station CMA5b was rescheduled from 20 May 2016 to 21 May 2016.
The 1hr TSP monitoring at air quality
monitoring station CMA2a was rescheduled from 05 May 2016 to 07 May 2016.
The 1hr TSP monitoring at air quality
monitoring station CMA5b was rescheduled from 17 May 2016 to 20 May 2016.
Complaints, Notifications of Summons and Successful Prosecutions
ET confirmed with the Resident Site
Staff that a generator deployed under Contract HK/2009/02 near the covered
walkway for Wanchai Ferry Pier at Portion 2 area and was operated from 1900hrs
on 24 May 2016 to 0700hrs on 25 May 2016 and from 1900hrs on 25 May 2016 to
0700hrs on 26 May 2016. The generator was used for the power supply of lighting
inside Tunnel Portions 1 and 2.
According to the relevant site records
provided by RSS, a generator deployed under Contract HK/2009/02 near the covered
walkway for Wanchai Ferry Pier at Portion 2 area and was operated from 1900hrs
on 24 May 2016 to 0700hrs on 25 May 2016 and from 1900hrs on 25 May 2016 to
0700hrs on 26 May 2016. The generator was used for the power supply of lighting
inside Tunnel Portions 1 and 2. Based on review on site information, relevant
Construction Noise Permits GW-RS0516-16 and GW-RS0390-16 for the operation of
the concerned generator were confirmed in place while no sufficient site
information was considered available to demonstrate the use of acoustic
enclosure for the operation of the generator following the special condition 3d
item 4. Despite the above, the Contractor of HK/2009/02 has suspended the use
of the generator at the concerned location after 2300hours to minimize
potential noise concern to the surroundings from 28 May 2016.
Nevertheless, the Contractor of
HK/2009/02 was reminded to upkeep the site control system for construction
works carried out during restricted hours and night time for Construction Noise
Permit compliance and maintain regular maintenance of the plant and equipment
deployed to avoid potential nuisance to the nearby public.
Site Inspections and Audit
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Drainage
works
¡P
Road
works
¡P
Landscaping
works
¡P
Modification
and Construction of Sign Gantries / Traffic Signs
¡P
Maintenance
works
Contract
no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
¡P
Stage 4
backfilling works
¡P
Reinstatement
of outfall
Contract
no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Construction
of pre-cast concrete cover
¡P
Tunnel
OHVD construction
¡P
Tunnel
wall and top slab construction
¡P
Waterproofing
layer at tunnel top slab
¡P
Road side
barrier construction
¡P
ELS S4
removal and king post load transfer
¡P
Tunnel
backfilling
¡P
Removal
of remaining temporary sheet-pile seawall
¡P
Removal
of blockwork seawall near the interface between Portion 2 and Portion 5
¡P
Diaphragm
wall construction
¡P
Excavation
work
¡P
Strut
installation
¡P
Demolition
of ex-WSD salt water pumping station
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Remedial
works at Mined Tunnel
¡P
Remaining
works inside tunnel at TS4 and TPCWAE
¡P
Removal
of temporary reclamation at TPCWAW
Contract
no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/D
¡P
Construction
of EVB
¡P
Column
modification at F1 to F8
¡P
Oil
Street drainage works
¡P
Approach
ramp sheet piling and pre-bored piling works
¡P
Bridge
construction and segment erection
¡P
Hing Fat
Street modification works
¡P
EVA
structure construction
¡P
Hing Fat
Street Slip Road Bridge E parapet construction
¡P
EVB
waterproofing works
¡P
Excavation
/ Construction of retaining wall
Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan
Chai Bypass at Wan Chai West under FEP-09/364/2009/B
¡P
Grouting
¡P
Construction
of MVB
¡P
Construction
of concrete plug
¡P
Excavation
and lateral support installation for CWB tunnel
¡P
Structural
works for CWB tunnel construction
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009
¡P
Tree
protection works next to existing BGO,
¡P
Drainage
improvement works,
¡P
Excavation
and Lateral Support for U-structure,
¡P
Pipe
piling & grouting works,
¡P
Utility
diversion works,
¡P
Retaining
wall works
¡P
ELS
works,
¡P
D-wall
drill cutting works
¡P
Construction
works for subway extension
Contract no. HY/2011/08 ¡V Central - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
¡P
Construction
of Ventilation Buildings, inclusive of Administration Building, East
Ventilation Shaft, West Ventilation Building
¡P
Construction
of Tunnel Thermal Barrier
¡P
Installation
of Electricals and Mechanicals
¡P
Installation
of Tunnel Features
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/D and
Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/D,
FEP-09/364/2009/B, FEP-10/364/2009B and FEP-11/364/2009B to implement the Environmental Monitoring and Audit (EM&A)
programme as stipulated in the EM&A Manual of the approved Environmental
Impact Assessment (EIA) Report for Wan Chai Development phase II and
Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit
Requirements¡¨ under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/D, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A, FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B
during the period 27 April 2016 to 26 May 2016.
Section 1 Introduction ¡V details the scope
and structure of the report.
Section 2 Project
Background
¡V summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance ¡V summarizes the
status of valid Environmental Permits / Licenses during the reporting period.
Section 4 Monitoring
Requirements
¡V summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and action
plan and monitoring programmes.
Section 5 Monitoring
Results
¡V summarizes the monitoring results obtained in the reporting period.
Section 6 Compliance
Audit
¡V summarizes the auditing of monitoring results, all exceedances
environmental parameters.
Section 7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Environmental Site Audit ¡V summarizes the
findings of weekly site inspections undertaken within the reporting period,
with a review of any
relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of summons and Prosecution
¡V
summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and
¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called
¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested east-west Connaught Road Central/Harcourt Road / Gloucester
Road Corridor (the Corridor) which is currently operating beyond its capacity.
The CWB will provide relief to the existing congestion along the Corridor and
cater for the anticipated growth of traffic on Hong Kong Island. Without the
CWB and its access roads, there will not be sufficient capacity to serve the
heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central ¡V Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
¡P
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
¡P
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
¡P
Tunnel
control buildings and ventilation buildings;
¡P
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
Causeway Bay area;
¡P
Associated
road lighting, road signing, traffic control and surveillance system; and
¡P
Other
associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further
Environmental Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre ¡V Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1,DP3 |
13 July 2011 |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai Bypass at Wan Chai
West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel ¡V Tunnel (Slip Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Manager |
Mr. Simon Liu |
2162 9909 |
2634 1626 |
Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction Manager |
Mr. Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Terry
Tsang |
6683 9394 |
|||
Environmental
Officer |
Ms. Wendy Ng |
9803 0057 |
|||
Assistant Environmental
Engineer |
Ms. Connie Chan |
6157 7057 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827 9996 |
Project Manager |
Mr. Paul Yu |
3658 3085 |
|||
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570 8013 |
Deputy Project Manager |
Mr. William Luk |
9456 9819 |
|||
Deputy Site Agent |
Eric Fong |
6191 9337 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214 7700 |
|
Deputy Site Agent |
Mr. Bob Yeung |
2214 7703 |
|||
Environmental Officer |
Mr. Chris Chan |
2823 1161 |
|||
Assistant Environmental Engineer |
Mr. Christy So |
3937 1065 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2865 5229 |
Site Manager |
Mr. Y. Huo |
3557 6368 |
2566 2192 |
||
Contractor¡¦s
Representative |
Mr. Andrew Wong |
3557 6371 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Mr. Harry Wong |
3557 6348 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N. Lai |
9137 1811 |
2877 1522 |
Project
Manager |
Mr. Eddie
Chung |
9193 8871 |
|||
Site Agent |
Mr. Keith Tse |
9095 7922 |
|||
Environmental
Officer |
Mr. James MA |
9130 9549 |
|||
Environmental
Supervisor |
Mr. Y.L. Ho |
6050 4919 |
|||
China State |
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung Kit
Cheung |
3557 6399 |
2566 8061 |
Project
Manager |
Chan Ying
Lun |
9812 0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467 4299 |
|||
Site Agent |
Dr. Dave Chan |
3467 4277 |
|||
Environmental
Officer |
Mr. C.M. Wong |
3557 6464 |
|||
Environmental
Supervisor |
Mr. Louis Lam
Tsz Kwan |
3557 6470 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Project
Manager |
Paul Evans |
2823 1111 |
21406799 |
Site Agent |
Colman Wong |
9730 0806 |
|||
Environmental
Officer |
Malcom
Leung |
3973 0850 |
|||
Environmental
Supervisor |
Christy So |
3973 1065 |
|||
Ramboll Environ Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. HY/2009/18 - Central - Wan
Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
¡P
Drainage
works
¡P
Road
works
¡P
Landscaping
works
¡P
Modification
and Construction of Sign Gantries / Traffic Signs
¡P
Maintenance
works
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
¡P
Stage 3b
backfilling works
¡P
Stage 4
construction tunnel structure
¡P
Reinstatement
of outfall
¡P
Reinstatement
of triangular planter at Fenwick Pier Street
Contract
no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai
East (CWB Tunnel) under FEP-01/364/2009
¡P
Site clearance
works was on going at OHVD at Tunnel Portion 1.
¡P
Site clearance
works was on going at OHVD at Tunnel Portion 2.
¡P
Waterproofing work for side wall
¡P
Middle
wall and side wall construction
¡P
Tunnel
top slab construction
¡P
Diaphragm
wall panel construction
¡P
Instrumentation
work was on going
¡P
Excavation
work
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Dismantle
steel work at TPCWAW
¡P
Remedial
works at Mined Tunnel
¡P
Remedial
works at TS4, TPCWAE
¡P
Reinstatement
of Shaft B between TPCWAW and TPCWAE
Contract no. HY/2009/19 - Central - Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/D
¡P
Pier
construction for IEC
¡P
Construction
of EVB
¡P
Column
modification at F1 to F8
¡P
Oil
Street drainage works
¡P
Bridge
construction and segment erection
¡P
Hing Fat Street
modification works
¡P
EVA
structure construction
¡P
Hing Fat
Street Slip Road Bridge E L3 railing construction
¡P
Approach
ramp sheet piling works
¡P
EVB
waterproofing works
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009B
¡P
Grouting
¡P
Construction
of MVB
¡P
Construction
of concrete plug
¡P
Excavation
and lateral support installation for CWB tunnel
¡P
Structural
works for CWB tunnel construction
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009B
¡P
Tree
protection works next to existing BGO,
¡P
Drainage
improvement works,
¡P
Excavation
and Lateral Support for U-structure,
¡P
Pipe
piling & grouting works,
¡P
Utility
diversion works,
¡P
Retaining
wall works
¡P
ELS
works,
¡P
Construction
works for subway extension
Contract no. HY/2011/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
¡P
Construction
of Ventilation Buildings, inclusive of Administration Building, East
Ventilation Shaft West Ventilation Building
¡P
Construction
of Tunnel Thermal Barrier
¡P
Installation
of Electricals and Mechanicals
¡P
Installation
of Tunnel Features
2.4.4.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no.
HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under
FEP-05/364/2009/A
¡P
Drainage
works
¡P
Road
works
¡P
Landscaping
works
¡P
Modification
and Construction of Sign Gantries / Traffic Signs
¡P
Maintenance
works
Contract
no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
¡P
Stage 4
backfilling works
¡P
Reinstatement
of outfall
Contract
no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Construction
of pre-cast concrete cover
¡P
Tunnel
OHVD construction
¡P
Tunnel
wall and top slab construction
¡P
Waterproofing
layer at tunnel top slab
¡P
Road side
barrier construction
¡P
ELS S4
removal and king post load transfer
¡P
Tunnel
backfilling
¡P
Removal
of remaining temporary sheet-pile seawall
¡P
Removal
of blockwork seawall near the interface between Portion 2 and Portion 5
¡P
Diaphragm
wall construction
¡P
Excavation
work
¡P
Strut
installation
¡P
Demolition
of ex-WSD salt water pumping station
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
¡P
Remedial
works at Mined Tunnel
¡P
Remaining
works inside tunnel at TS4 and TPCWAE
¡P
Removal
of temporary reclamation at TPCWAW
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
¡P
Pier
construction for IEC
¡P
Construction
of EVB
¡P
Column
modification at F1 to F8
¡P
Oil
Street drainage works
¡P
Approach
ramp sheet piling and pre-bored piling works
¡P
Bridge
construction and segment erection
¡P
Hing Fat
Street modification works
¡P
EVA
structure construction
¡P
Hing Fat
Street Slip Road Bridge E parapet construction
¡P
EVB
waterproofing works
¡P
Excavation
/ Construction of retaining wall
Contract no.
HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan
Chai West under FEP-09/364/2009/B
¡P
Grouting
¡P
Construction
of MVB
¡P
Construction
of concrete plug
¡P
Excavation
and lateral support installation for CWB tunnel
¡P
Structural
works for CWB tunnel construction
Contract
no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under
FEP-10/364/2009
¡P
Tree
protection works next to existing BGO,
¡P
Drainage
improvement works,
¡P
Excavation
and Lateral Support for U-structure,
¡P
Pipe
piling & grouting works,
¡P
Utility
diversion works,
¡P
Retaining
wall works
¡P
ELS
works,
¡P
D-wall
drill cutting works
¡P
Construction
works for subway extension
Contract
no. HY/2011/08 ¡V Central - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
¡P
Construction
of Ventilation Buildings, inclusive of Administration Building, East
Ventilation Shaft, West Ventilation Building
¡P
Construction
of Tunnel Thermal Barrier
¡P
Installation
of Electricals and Mechanicals
¡P
Installation
of Tunnel Features
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of the current status
on licences and/or permits on environmental protection pertinent to the Project
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-364/2009/A |
4 Aug
2010 |
Superseded |
Environmental
Permit |
EP-364/2009/B |
20 Sep
2012 |
Superseded |
Environmental
Permit |
EP-364/2009/C |
11 Jul
2014 |
Superseded |
Environmental
Permit |
EP-364/2009/D |
24 Nov
2015 |
Valid |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Surrendered |
Further Environmental Permit |
FEP-06/356/2009 |
5
March 2013 |
Valid |
Further Environmental Permit |
FEP-07/356/2009 |
26
July 2013 |
Valid |
Further
Environmental Permit |
24 Mar
2010 |
Valid |
|
Further
Environmental Permit |
21 Apr 2010 |
Valid |
|
Further
Environmental Permit |
12 July 2010 |
Surrendered
|
|
Further
Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further
Environmental Permit |
15 Nov 2010 |
Valid |
|
Further
Environmental Permit |
22 Nov 2010 |
Valid |
|
Further
Environmental Permit |
25 Feb 2011 |
Superseded |
|
Further
Environmental Permit |
24 Nov 2015 |
Valid |
|
Further
Environmental Permit |
15 June 2012 |
Surrendered |
|
Further
Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further
Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further
Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai
Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.
Contract no. 04/HY/2006 ¡V Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP-04/HY/2006 was
surrendered by the Contractor on 11 February 2011.
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
3.1.5. The construction works was completed, and the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
Contract no.
HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.2 and Table 3.3.
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits
and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling equipment |
GW-RS1134-15 |
23 Oct 2015 |
08 Nov 2015 to 07 May 2016 |
Cancelled |
GW-RS1135-15 |
23 Oct 2015 |
26 Nov 2015 to 25 May 2016 |
Expired |
|
GW-RS1228-15 |
13 Nov 2015 |
16 Nov 2015 to 13 May 2016 |
Expired |
|
GW-RS1309-15 |
27 Nov 2015 |
30 Nov 2015 to 26 May 2016 |
Expired |
|
GW-RS1338-15 |
11 Dec 2015 |
01 Jan 2016 to 30 June 2016 |
Cancelled |
|
GW-RS0041-16 |
22 Jan 2016 |
25 Jan 2016 to 23 Jul 2016 |
Cancelled |
|
GW-RS0089-16 |
05 Feb 2016 |
20 Feb 2016 to 19 July 2016 |
Cancelled |
|
GW-RS0093-16 |
05 Feb 2016 |
22 Feb 2016 to 21 July 2016 |
Cancelled |
|
GW-RS0152-16 |
18 Feb 2016 |
25 Feb 2016 to 24 Aug 2016 |
Cancelled |
|
GW-RS0243-16 |
11 Mar 2016 |
14 Mar 2016 to 13 Sep 2016 |
Cancelled |
|
GW-RS0384-16 |
19 Apr 2016 |
22 Apr 2016 to 19 Oct 2016 |
Valid |
|
GW-RS0435-16 |
03 May 2016 |
08 May 2016 to 07 Nov 2016 |
Valid |
|
GW-RS0482-16 |
17 May 2016 |
19 May 2016 to 18 Nov 2016 |
Valid |
|
GW-RS0486-16 |
17 May 2016 |
19 May 2016 to 18 Nov 2016 |
Valid |
|
GW-RS0488-16 |
17 May 2016 |
19 May 2016 to 18 Nov 2016 |
Valid |
|
GW-RS0492-16 |
20 May 2016 |
23 May 2016 to 22 Nov 2016 |
Valid |
|
GW-RS0493-16 |
20 May 2016 |
23 May 2016 to 22 Nov 2016 |
Valid |
|
GW-RS0495-16 |
20 May 2016 |
19 May 2016 to 18 Nov 2016 |
Valid |
|
Discharge License |
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
WT00021138-2015 |
17 Mar 2014 |
31 Mar 2020 |
Valid |
|
Billing account under
Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.3 Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May 2011 |
Condition 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Condition 1.12 |
Commencement Date of Works |
20 Jun 2011 |
Condition 2.9 |
Noise Management Plan |
10 Jun 2011 |
Condition 2.11 |
Landscape Plan (Rev.4) |
8 July 2015 |
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.7.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.4 and Table 3.5.
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of
Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-pilling equipment |
GW-RS1150-15 |
26 Oct 2015 |
28 Oct 2015 to 27 Apr 2016 |
Expired |
GW-RS1187-15 |
28 Oct 2015 |
30 Oct 2015 to 27 Apr 2016 |
Expired |
|
GW-RS1413-15 |
24 Dec 2015 |
02 Jan 2016 to 01 Jul 2016 |
Cancelled |
|
GW-RS0083-16 |
01 Feb 2016 |
3 Feb 2016 to 01 Aug 2016 |
Cancelled |
|
GW-RS0311-16 |
24 Mar 2016 |
25 Apr 2016 to 24 May 2016 |
Expired |
|
GW-RS0310-16 |
24 Mar 2016 |
27 Apr 2016 to 30 Apr 2016 |
Expired |
|
GW-RS0321-16 |