Contract No: HK/2015/01 Wanchai Development Phase II and Central Wanchai
Bypass Sampling, Field Measurement and Testing Work (Stage 3) Environmental Permit
no. EP-364/2009/E, Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a,
FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/E,
FEP-12/364/2009/D Monthly
Environmental Monitoring & Audit Report
- february 2017 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre
Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
March 2017 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3
status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring Results
5.3 Air
Quality Monitoring Results
6.3 Review
of the Reasons for and the Implications of Non-compliance
6.4 Summary
of action taken in the event of and follow-up on non-compliance
7 Cumulative Construction
Impact due to the Concurrent Projects
9 Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details of Individual Contracts under
the Project
Table 2.3 Contact Details of Key Personnel
Table 3.1 Summary of the current status on
licences and/or permits on environmental
protection pertinent to the Project
Table 3.2 Cumulative Summary of Valid Licences
and Permits under Contract no.
Table 3.3 Summary of submission status under
FEP-02/364/2009
Table 3.4 Cumulative Summary of Valid Licences
and Permits under Contract no.
Table 3.5 Summary of submission status under
FEP-01/364/2009
Table 3.6 Cumulative Summary of Valid Licences
and Permits under Contract no.
Table 3.7 Summary of submission status under
FEP-05/364/2009/A
Table 3.8 Cumulative Summary of Valid Licences
and Permits under Contract no.
Table 3.9 Summary of submission status under
FEP-06/364/2009/A
Table 3.10 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.11 Summary of
submission status under FEP-07/364/2009/D
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.13 Summary of submission status under
FEP-12/364/2009/D
Table 3.14 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.15 Summary of submission status under
FEP-10/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HY/2011/08
Table 3.17 Summary of submission status under FEP-11/364/2009/E
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring Stations
Table 4.3 Air Quality Monitoring Stations
Table 5.1 Noise Monitoring Stations for Contract
no. HY/2009/18
Table 5.2 Noise Monitoring Station for Contract
no HK/2009/01 and HK/2009/02
Table 5.3 Noise Monitoring Stations for Contract
no. HY/2009/15
Table 5.4 Noise Monitoring Stations for Contract
no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table 5.6 Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.7 Real Time Noise Monitoring Stations
for Contract no. HY/2009/19
Table 5.8 Real Time Noise Monitoring Stations
for Contract no. HY/2011/08
Table 5.9 Air Quality Monitoring Station for
Contract no. HY/2009/18
Table 5.10 Air Quality Monitoring Station for Contract no.
HK/2009/01
Table 5.11 Air Quality Monitoring Station for Contract no.
HK/2009/02
Table 5.12 Air Quality Monitoring Stations for Contract no.
HY/2009/15
Table 5.13 Air Quality
Monitoring Station for Contract no. HY/2009/19
Table 5.14 Air Quality
Monitoring Station for Contract no. HK/2012/08
Table 5.15 Air Quality Monitoring Stations for
Contract no. HY/2010/08
Table 5.16 Air Quality Monitoring Stations for
Contract no. HY/2011/08
Table 5.17 Details of Waste Disposal for Contract
no. HK/2009/01
Table 5.18 Details of Waste Disposal for Contract
no. HK/2009/02
Table 5.19 Details of Waste Disposal for Contract
no. HY/2009/18
Table 5.20 Details of Waste Disposal for Contract
no. HY/2009/15
Table 5.21 Details of Waste Disposal
for Contract no. HY/2009/19
Table 5.22 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.23 Details of Waste Disposal
for Contract no. HY/2010/08
Table 5.24 Details of Waste Disposal for Contract
no. HY/2011/08
Table 8.1
Summary of Environmental Inspections for Contract no. HY/2009/15
Table 8.2 Summary of Environmental Inspections
for Contract no. HY/2009/18 (NOT USED)
Table 8.3
Summary of Environmental Inspections for Contract no. HY/2009/19 (NOT
USED)
Table 8.4 Summary of
Environmental Inspections for Contract no. HK/2009/01 (NOT USED)
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.6 Summary of
Environmental Inspections for Contract no. HK/2012/08
Table 8.7 Summary of Environmental
Inspections for Contract no. HY/2010/08
Table 8.8 Summary of
Environmental Inspections for Contract no. HY/2011/08)
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful
Prosecutions
Table 10.1 Summary of Key Construction Activities
of Individual Contract(s) to be
commenced in Coming Reporting Month
LIST
OF FIGUREs
Figure 2.1 Project Layout
Figure 2.2 Project Organization Chart
Figure 4.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation
Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration
Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and
Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix 5.4 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification
of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of
Individual Contracts
Contract no. HY/2009/18 - Central - Wan Chai
Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
·
Drainage works
·
Road works
·
Landscaping works
·
Modification and Construction of Sign
Gantries / Traffic Signs
·
Maintenance works
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
Reinstatement of amenity area
·
Road and Drain works
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Rectification works for cross road ducts
·
Rectification works for cracks/joints with
water leakage inside OHVD cells.
·
Removal works for ELS S2
·
Removal works for ELS S1
·
Demolition works for HHR flyover abutment
·
Backfilling of sorted public fill
·
Temporary wall for construction of Hung Hing
Road Flyover
·
Delivery of precast concrete seawall block
·
Rectification works against water leakage and
remedial works against concrete defects of the tunnel structure
·
Concreting mass concrete underneath HHR
flyover
·
Breakthrough of bulkhead wall BW1
·
Waterproofing laying work
·
Concreting for base slab
·
Removal of ELS layer S2 & S3
·
Tunnel wall structure
·
Remedial works for marine deposit at Portion
1&2
·
Demolition of sub-structure for Ex-WSD Salt
Water Pumping Station
·
Demolition of remaining seawall coping up to
edge of the existing temporary covered walkway
·
Relocation of the temporary pillar box for
temporary site office.
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at
Mined Tunnel, TS4, TPCWAE and TPCWAW
·
Reinstatement of drainage pipes and manhole
at TPCWAE
Contract no. HY/2009/19 - Central - Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored
piling and top soil removal works
·
Hing Fat Street modification works
·
Bridge Demolition / Construction
·
Hotel Carpark Reinstatement
·
Bridge E noise barrier installation
·
IEC noise enclosure/barrier installation
Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan
Chai Bypass at Wan Chai West under FEP-12/364/2009/D
·
Grouting
·
Construction of MVB and CWB Tunnel and Slip
Road 1
·
Construction of concrete plug
·
Excavation and lateral support installation
for CWB tunnel, Slip Road 1, Plant Room and Exhaust Duct
·
Bulkhead removal
·
Back-filling at CWB tunnel
Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip
Road 8) under FEP-10/364/2009/B
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Excavation and Lateral Support for
U-structure,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009/E
·
Construction of Ventilation Buildings,
inclusive of Administration Building, East Ventilation Shaft/Building, West
Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
Noise Monitoring
Air Quality Monitoring
The 24hr TSP
monitoring at CMA1b were rescheduled from 01 and 13 February 2017 to 02 and 14 February
2017 respectively
The 24hr TSP
monitoring at CMA3a were rescheduled from 13 February 2017 to 14 February 2017.
The 24hr TSP monitoring
at MA1w were rescheduled from 18 February 2017 to 20 February 2017.
Complaints,
Notifications of Summons and Successful Prosecutions
No works was
conducted under Contract HY/2010/08near Victoria Park Swimming Pool (Hing Fat
Street) during the restricted hours (from 1900hrs to 0700hrs on the following
day) from 21 December 2016 to 20 February 2017.
Nevertheless, in
view of the public concern, the Contractor of HY/2010/08 was reminded to
maintain the site control system for construction works carried out during
restricted hours to ensure the PMEs deployed are in compliance with relevant
Construction Noise Permit. The Contractor of HY/2010/08 was also reminded to
maintain regular maintenance of the plant and equipment deployed to avoid
potential nuisance to the nearby public
ET confirmed with
the Resident Site Staff that concreting of tunnel structure at Temporary
Reclamation Area TS3 were conducted under Contract HY/2010/08 between 1900hrs
and 2300hrs on 13, 14, 15, 16 and 18 February 2017. Total 3 nos. of concrete
pump and 6 nos. of concrete lorry mixers were operated. Concreting of tunnel
structure at Temporary Reclamation Area TS3 were conducted under Contract
HY/2010/08 between 1900hrs and 2100hrs on 21 February 2017. Total 3 nos. of
concrete pump and 6 nos. of concrete lorry mixers were operated. Concreting of
tunnel structure at Zone C was conducted under Contract HY/2010/08 between
1900hrs to 2300hrs on 17 and 20 February 2017. Total 1 no. of concrete pump and
2 nos. of concrete mixers were operated. Bar bending at Zone C was conducted
under Contract HY/2010/08 between 1900hrs to 2300hrs on 13, 14, 15, 16, 18 and
19 February 2017. Total 1 no. bar bender and cutter was operated. No works was
conducted under Contract HY/2010/08 near Victoria Park Swimming Pool (Hing Fat
Street) during the restricted hours (from 1900hrs to 0700hrs on the following
day) across the period from 13 February 2017 to 21 February 2017.
Based on the site
records confirmed by RSS, no works was conducted under Contract HY/2010/08 near
Victoria Park Swimming Pool (Hing Fat Street) during the restricted hours (from
1900hrs to 0700hrs on the following day) from 13 February 2017 to 20 February
2017. Concreting of tunnel structure at Temporary Reclamation Area TS3 was
conducted under Contract HY/2010/08 between 1900hrs and 2300hrs on 13, 14, 15,
16 and 18 February 2017 and total 3 nos. of concrete pumps and 6 nos. of
concrete lorry mixers were operated. Concreting of tunnel structure at
Temporary Reclamation Area TS3 were conducted under Contract HY/2010/08 between
1900hrs and 2100hrs on 21 February 2017 and total 3 nos. of concrete pump and 6
nos. of concrete lorry mixers were operated. Relevant Construction Noise Permit
GW-RS0029-17 was in place while it is considered that there is no sufficient
information to indicate whether the Powered Mechanical Equipment were deployed
at the designed location stipulated under the relevant Construction Noise
Permit with noise mitigation measures required.
Concreting of
tunnel structure at Zone C was conducted under Contract HY/2010/08 between
1900hrs to 2300hrs on 17 and 20 February 2017. Total 1 no. of concrete pump and
2 nos. concrete mixers were operated. Bar bending at Zone C was conducted under
Contract HY/2010/08 between 1900hrs to 2300hrs on 13, 14, 15, 16, 18 and 19
February 2017 and total 1 no. bar bender and cutter was operated. Relevant
Construction Noise Permit GW-RS1366-13 was in place while it is considered that
there is no sufficient information to indicate whether the Powered Mechanical
Equipment were deployed at the designed location stipulated under the relevant
Construction Noise Permit with noise mitigation measures required.
Nevertheless,
further to the joint ad-hoc inspection conducted by the ET/IEC on 13 February
2017 during restricted hours (between 1900hrs to 2200hrs), concurrent
operations of 4 nos. of concrete lorry trucks at the Southern Side of TS3 near
Construction Site Entrance and concurrent operations of 2 nos. of concrete
lorry pumps and 2 nos. of concrete lorry truck at Western and Northern Side of
TS3 were observed while the temporary noise barrier provided for the concrete
lorry pump and concrete lorry truck at the Northern Side of TS3 could not
screen entirely the concrete lorry truck and concrete lorry pump (Located at
Northern Side of TS3) from nearby sensitive receivers. Therefore, it is
considered that the above operations observed could not follow the PME grouping
requirement and the specific condition 3.d.4 under the relevant Construction
Noise Permit.
In view of the
above, the Contractor of HY/2010/08 was advised to enhance the site supervision
and strictly implement the site control system for construction works carried
out during restricted hours to ensure the PMEs deployed strictly comply with
relevant Construction Noise Permit. The Contractor of HY/2010/08 was also
reminded to maintain regular maintenance of the plant and equipment deployed to
avoid potential nuisance to the nearby public.
Site Inspections
and Audit
Contract no.
HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Drainage works
·
Road works
·
Landscaping works
·
Maintenance works
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre – Tunnel Works under FEP-02/364/2009
·
Reinstatement of amenity area
·
Road and Drain works
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
·
Rectification works for cross road ducts
·
Rectification works for cracks/joints with
water leakage inside OHVD cells
·
Rectification works for out of tolerance
cross passage CP22
·
Removal works for ELS S1 layer.
·
Concreting of mass concrete underneath HHR
flyover.
·
Tunnel backfilling & construction of
seawall foundation with Grade 400 rock fill.
·
Construction of temporary wall for Hung Hing
Road Flyover.
·
Demolition works for HHR flyover abutment.
·
Concreting blinding layer for HHR flyer.
·
Rebar fixing for HHR flyover.
·
Demolition of D-Wall
·
Remedial works of tunnel wall, base slab and
OHVD.
·
General cleaning and rectification works of
OHVD, tunnel base slab, carrier drain, cross road duct and manhole gully.
·
Rectification works for out of tolerance
cross passage CP23
·
Rebar fixing and concreting of base slab and
walls.
·
Waterproofing membrane laying works for side
walls.
·
Removal works for ELS S2 & S3 layer.
·
Rebar fixing and concreting of roadside
barrier.
·
Erect scaffolding for OHVD slab.
·
Rebar fixing and concreting of OHVD slab.
·
Relocation of the pillar.
·
Excavation works for trial pit for the 132kV
HK Electric cables.
Contract no. HY/2009/15 –
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
·
Remedial works inside tunnel structure at
Mined Tunnel, TS4, TPCWAE and TPCWAW
·
Reinstatement of drainage pipes and manhole
at TPCWAE
Contract no. HY/2009/19 – Central – Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored
piling and top soil removal works
·
Hing Fat Street modification works
·
Bridge Demolition / Construction
·
Hotel Carpark Reinstatement
·
Oil Street drainage works
·
Bridge E noise barrier installation
·
IEC noise enclosure/barrier installation
·
Excavation / Construction of retaining wall
Contract no.
HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West under FEP-12/364/2009/D
·
Grouting
·
Construction of MVB and CWB Tunnel and Slip
Road 1
·
Construction of concrete plug
·
Lateral support installation for CWB tunnel,
Slip Road 1, Plant Room and Exhaust Duct
·
Bulkhead removal
·
Back-filling at CWB tunnel
Contract no.
HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8) under
FEP-10/364/2009
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Excavation and Lateral Support for
U-structure,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction of Ventilation Buildings,
inclusive of Administration Building, East Ventilation Shaft/Building, West
Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed
to work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009/E and Further Environmental permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/D, FEP-10/364/2009/B,
FEP-11/364/2009/E and FEP-12/364/2009/D to implement the Environmental Monitoring and Audit (EM&A) programme
as stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental
monitoring and auditing work carried out in accordance to the Section 10.3 of
EM&A Manual and “Environmental Monitoring and Audit Requirements” under Particular Specification Section 27.
1.1.3.
This report documents
the finding of EM&A works for Environmental
Permit (EP) no. EP-364/2009/E, Further Environmental Permit (FEP) nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A
FEP-07/364/2009/D, FEP-09/364/2009/D, FEP-10/364/2009/B, FEP-11/364/2009/E and FEP-12/364/2009/D during the period 27 January 2017 to 26 February 2017.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project
Background – summarizes
background and scope of the project, site description, project organization and
contact details of key personnel during the reporting period.
Section 3 Status of
Regulatory Compliance – summarizes the status of valid Environmental Permits / Licenses
during the reporting period.
Section 4 Monitoring
Requirements – summarizes
all monitoring parameters, monitoring methodology and equipment, monitoring
locations, monitoring frequency, criteria and respective event and action plan
and monitoring programmes.
Section 5 Monitoring
Results – summarizes
the monitoring results obtained in the reporting period.
Section 6 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances
environmental parameters.
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Environmental Site
Audit – summarizes
the findings of weekly site inspections undertaken within the reporting period,
with a review of any relevant
follow-up actions within the
reporting period.
Section 9 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan
Chai Bypass” and “Central-Wan Chai Bypass and Island Eastern Corridor Link”
(hereafter called “the Project”) are Designated Project (DP) under the Environmental Impact
Assessment Ordinance (Cap. 499) (EIAO).
The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai
Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan
Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008
respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the
CWB to provide relief to the very congested east-west Connaught Road
Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1.
Design and
Construction of Central – Wan Chai Bypass and Island Eastern Corridor Link
under the Project involves the construction and operation of a trunk road and
its road tunnel more than 800m in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments
from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern
Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately
4.5 km in length, and tunnel approximately 3.7 km in length defined from the
connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing Island Eastern Corridor to the east of the
Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey
Street Flyover to provide road connections to the Central area;
·
Tunnel control buildings and ventilation
buildings;
·
Slip roads to connect the CWB to the local
road system in the Wan Chai North and Causeway Bay area;
·
Associated road lighting, road signing,
traffic control and surveillance system; and
·
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table
2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB)
including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and
A.7 |
Trunk road and road tunnel
more than 800 m in length |
DP2 |
Road P2 and other roads
which are classified as primary/district distributor roads |
Schedule 2, Part I, A.1 |
Primary / district
distributor roads |
DP3 |
Reclamation works including
associated dredging works |
Schedule 2, Part I, C.1 and
C.12 |
Reclamation more than 5 ha
in size and a dredging operation less than 100 m from a seawater intake point
|
DP5 |
Wan Chai East Sewage Outfall
|
Schedule 2, Part I, F.5 and
F.6 |
Submarine sewage pipelines
with a total diameter more than 1,200 mm and include a submarine sewage
outfall |
DP6 |
Dredging for the
Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less
than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced.
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are
summarized in Table2.2.
Table 2.2 Details of Individual
Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass
(CWB) at FEHD Whitfield Depot – Advanced piling works. |
DP1 |
5 October
2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass
(CWB) – Central Interchange |
DP1 |
21 April
2011 |
04/HY/2006 |
Reconstruction of Bus
Terminus near Man Yiu Street and Man Kwong Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase
II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre
– Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase
II – Central – Wan Chai Bypass at Wan Chai East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1,DP3 |
13 July 2011 |
HY/2009/19 |
Central – Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase
II-Central-Wan Chai Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase
II- Central-Wan Chai Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass
Tunnel – Tunnel (Slip Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with
Tunnel Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and
Development Department and Highways Department are the overall project
controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass
respectively. For the
construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars
are summarized in Table 2.3:
Table 2.3 Contact
Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative
for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative
for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun
Wo – Leader Joint Venture |
Contractor under Contract
no. HK/2009/01 |
Project Manager |
Mr. Simon Liu |
2162 9909 |
2634 1626 |
Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction Manager |
Mr. Terry Wong |
9757 9846 |
|||
Construction Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction Manager |
Mr. Terry Tsang |
6683 9394 |
|||
Environmental Officer |
Ms. Wendy Ng |
9803 0057 |
|||
Assistant Environmental Engineer |
Ms. Connie Chan |
6157 7057 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract
no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827 9996 |
Project Manager |
Mr. Paul Yu |
3658 3085 |
|||
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract
no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Deputy Project Manager |
Mr. William Luk |
9456 9819 |
|||
Site Agent |
Mr. David Lau |
3758 8879 |
|||
Deputy Site Agent |
Mr. Eric Fong |
6191 9337 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
3757 8218 |
|||
Assistant Environmental
Officer |
Mr. Tom Ding |
3757 8217 |
|||
Leighton Contractors (Asia)
Limited |
Contractor under Contract
no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214 7700 |
|
Environmental Officer |
Mr. Chris Chan |
3973 1065 |
|||
Environmental Supervisor |
Ms. Christy So |
3973 1065 |
|||
China State Construction
Engineering (HK) Ltd. |
Contractor under Contract
no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2865 5229 |
Site Manager |
Mr. Y. Huo |
3557 6368 |
2566
2192 |
||
Contractor’s Representative |
Mr. Rex Chan |
3557 6371 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Mr. Harry Wong |
3557 6348 |
|||
China State- Build King JV |
Contractor under Contract
no. HK/2012/08 |
Project Director |
Mr. C.N. Lai |
9137 1811 |
2877 1522 |
Project Manager |
Mr. Eddie Chung |
9193 8871 |
|||
Site Agent |
Mr. Keith Tse |
9095 7922 |
|||
Environmental Officer |
Mr. James MA |
9130 9549 |
|||
Environmental Supervisor |
Mr. Y.L. Ho |
6050 4919 |
|||
China State |
Contractor under Contract
no.HY/2010/08 |
Project Director |
Chris Leung |
3467 4299 |
2566 8061 |
Site Agent |
Mr. Francis Suen |
3467 4277 |
|||
Environmental Officer |
Mr. Gabriel Wong |
3557 6464 |
|||
Environmental Supervisor |
Mr. Desmond Ho |
3557 6470 |
|||
Leighton Joint Venture |
Contractor under Contract
no. HY/2011/08 |
Site Agent |
Mr. Colman Wong |
2823 1410 |
21406799 |
Environmental Officer |
Mr. Malcolm Leung |
3973 0850 |
|||
Environmental Supervisor |
Ms. Christy So |
3973 1065 |
|||
Ramboll Environ Hong Kong Limited |
Independent Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader
(ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3. In this reporting month, the principal work activities of individual
contracts are included as follows:
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
·
Drainage works
·
Road works
·
Landscaping works
·
Modification and Construction of Sign
Gantries / Traffic Signs
·
Maintenance works
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
Reinstatement of amenity area
·
Road and Drain works
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Rectification works for cross road ducts
·
Rectification works for cracks/joints with
water leakage inside OHVD cells.
·
Removal works for ELS S2
·
Removal works for ELS S1
·
Demolition works for HHR flyover abutment
·
Backfilling of sorted public fill
·
Temporary wall for construction of Hung Hing
Road Flyover
·
Delivery of precast concrete seawall block
·
Rectification works against water leakage and
remedial works against concrete defects of the tunnel structure
·
Concreting mass concrete underneath HHR
flyover
·
Breakthrough of bulkhead wall BW1
·
Waterproofing laying work
·
Concreting for base slab
·
Removal of ELS layer S2 & S3
·
Tunnel wall structure
·
Remedial works for marine deposit at Portion
1&2
·
Demolition of sub-structure for Ex-WSD Salt
Water Pumping Station
·
Demolition of remaining seawall coping up to
edge of the existing temporary covered walkway
·
Relocation of the temporary pillar box for
temporary site office.
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at
Mined Tunnel, TS4, TPCWAE and TPCWAW
·
Reinstatement of drainage pipes and manhole
at TPCWAE
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored
piling and top soil removal works
·
Hing Fat Street modification works
·
Bridge Demolition / Construction
·
Hotel Carpark Reinstatement
·
Bridge E noise barrier installation
·
IEC noise enclosure/barrier installation
Contract no. HK/2012/08
– Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West
under FEP-12/364/2009/D
·
Grouting
·
Construction of MVB and CWB Tunnel and Slip
Road 1
·
Construction of concrete plug
·
Excavation and lateral support installation
for CWB tunnel, Slip Road 1, Plant Room and Exhaust Duct
·
Bulkhead removal
·
Back-filling at CWB tunnel
Contract no.
HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009/B
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Excavation and Lateral Support for
U-structure,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract no.
HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under
FEP-11/364/2009/E
·
Construction of Ventilation Buildings,
inclusive of Administration Building, East Ventilation Shaft/Building, West
Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
2.4.4. In coming reporting month, the principal work activities of individual
contracts are anticipated as follows:
·
Drainage works
·
Road works
·
Landscaping works
·
Maintenance works
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009
·
Reinstatement of amenity area
·
Road and Drain works
Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
·
Rectification works for cross road ducts
·
Rectification works for cracks/joints with
water leakage inside OHVD cells
·
Rectification works for out of tolerance
cross passage CP22
·
Removal works for ELS S1 layer.
·
Concreting of mass concrete underneath HHR
flyover.
·
Tunnel backfilling & construction of
seawall foundation with Grade 400 rock fill.
·
Construction of temporary wall for Hung Hing
Road Flyover.
·
Demolition works for HHR flyover abutment.
·
Concreting blinding layer for HHR flyer.
·
Rebar fixing for HHR flyover.
·
Demolition of D-Wall
·
Remedial works of tunnel wall, base slab and
OHVD.
·
General cleaning and rectification works of
OHVD, tunnel base slab, carrier drain, cross road duct and manhole gully.
·
Rectification works for out of tolerance
cross passage CP23
·
Rebar fixing and concreting of base slab and
walls.
·
Waterproofing membrane laying works for side
walls.
·
Removal works for ELS S2 & S3 layer.
·
Rebar fixing and concreting of roadside
barrier.
·
Erect scaffolding for OHVD slab.
·
Rebar fixing and concreting of OHVD slab.
·
Relocation of the pillar.
·
Excavation works for trial pit for the 132kV
HK Electric cables.
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at
Mined Tunnel, TS4, TPCWAE and TPCWAW
·
Reinstatement of drainage pipes and manhole
at TPCWAE
Contract no.
HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored
piling and top soil removal works
·
Hing Fat Street modification works
·
Bridge Demolition / Construction
·
Hotel Carpark Reinstatement
·
Oil Street drainage works
·
Bridge E noise barrier installation
·
IEC noise enclosure/barrier installation
·
Excavation / Construction of retaining wall
Contract no.
HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West under FEP-12/364/2009/D
·
Grouting
·
Construction of MVB and CWB Tunnel and Slip
Road 1
·
Construction of concrete plug
·
Lateral support installation for CWB tunnel,
Slip Road 1, Plant Room and Exhaust Duct
·
Bulkhead removal
·
Back-filling at CWB tunnel
Contract no.
HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8) under
FEP-10/364/2009
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Excavation and Lateral Support for
U-structure,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under
FEP-11/364/2009/E
·
Construction of Ventilation Buildings,
inclusive of Administration Building, East Ventilation Shaft/Building, West
Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
3.1.1.
A summary of the current status on licences
and/or permits on environmental protection pertinent to the Project is shown in
Table 3.1.
Table 3.1 Summary
of the current status on licences and/or permits on environmental protection
pertinent to the Project
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Superseded |
Environmental Permit |
EP-364/2009/C |
11 Jul 2014 |
Superseded |
Environmental Permit |
EP-364/2009/D |
24 Nov 2015 |
Superseded |
Environmental Permit |
EP-364/2009/E |
22 Dec 2016 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Surrendered |
Further Environmental Permit |
FEP-06/356/2009 |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Surrendered |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Superseded |
|
Further Environmental Permit |
24 Nov 2015 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Surrendered |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
Superseded |
Further Environmental Permit |
FEP-11/364/2009/E |
22 Dec 2016 |
Valid |
Further Environmental Permit |
FEP-12/364/2009/D |
01 Aug
2016 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no.
HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works under FEP-03/364/2009
3.1.3.
The construction
works was completed and the FEP-03/364/2009 was surrendered by the Contractor
on 28 March 2013.
Contract no.
04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street
under FEP-04/364/2009/A
3.1.4.
The
construction works was completed, and the FEP-04/HY/2006 was surrendered by the
Contractor on 11 February 2011.
Contract no.
HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR
Tsuen Wan Line under FEP-08/364/2009/A
3.1.5.
The
construction works was completed, and the FEP-08/364/2009/A was surrendered by
the Contractor on 3 October 2014.
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under
FEP-02/364/2009
3.1.6. Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.2 and Table 3.3.
Table 3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference
No. |
Issued Date
|
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-pilling equipment |
GW-RS0822-16 |
28 Jul 2016 |
7 Aug 2016 to 31 Jan 2017 |
Cancelled |
GW-RS1004-16 |
28 Sep 2016 |
29 Sep 2016 to 27 Mar 2017 |
Valid |
|
GW-RS1079-16 |
27 Oct 2016 |
27 Oct 2016 to 20 Apr 2017 |
Valid |
|
GW-RS1241-16 |
12 Dec 2016 |
15 Dec 2016 to 06 Jun 2017 |
Valid |
|
GW-RS1240-16 |
12 Dec 2016 |
13 Dec 2016 to 06 Jun 2017 |
Valid |
|
GW-RS1233-16 |
12 Dec 2016 |
14 Dec 2016 to 06 Jun 2017 |
Valid |
|
GW-RS1234-16 |
12 Dec 2016 |
20 Dec 2016 to 19 Jun 2017 |
Valid |
|
Discharge
License |
WT00024952-2016 |
06 Jul 2016 |
31 Jul 2021 |
Valid |
WT00021138-2015 |
17 Mar 2014 |
31 Mar 2020 |
Valid |
|
Billing
account under Waste Disposal Ordinance |
7010069 |
21
Jan 2010 |
N/A |
Valid |
Registration as a Chemical
Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.3 Summary
of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.7 & 2.8 |
Works Schedule and Location
Plan |
18 May 2011 |
Condition 2.6 |
Environmental Management
Organization Chart |
18 May 2011 |
Condition 1.12 |
Commencement Date of Works |
20 Jun 2011 |
Condition 2.9 |
Noise Management Plan |
10 Jun 2011 |
Condition 2.11 |
Landscape Plan (Rev.4) |
8 July 2015 |
Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East (CWB Tunnel) under FEP-01/364/2009
3.1.7. Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.4 and Table 3.5.
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits
and/or Licenses |
Reference
No. |
Issued Date
|
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-pilling equipment |
GW-RS0803-16 |
28 Jul 2016 |
30 Jul 2016 to 27 Jan 2017 |
Cancelled |
GW-RS0926-16 |
05 Sep 2016 |
07 Sep 2016 to 04 Mar 2017 |
Cancelled |
|
GW-RS0985-16 |
19 Sep 2016 |
20 Sep 2016 to 18 Mar 2017 |
Cancelled |
|
GW-RS1047-16 |
13 Oct 2016 |
26 Oct 2016 to 25 Apr 2017 |
Valid |
|
GW-RS1140-16 |
11 Nov 2016 |
14 Nov 2016 to 09 May 2017 |
Valid |
|
GW-RS1153-16 |
17 Nov 2016 |
18 Nov 2016 to 13 May 2017 |
Cancelled |
|
GW-RS1297-16 |
15 Dec 2016 |
16 Dec 2016 to 14 Jun 2017 |
Valid |
|
GW-RS1305-16 |
22 Dec 2016 |
24 Dec 2016 to 13 Jun 2017 |
Valid |
|
Water Discharge License |
WT00022295-2015 |
12 Aug 2015 |
31 July 2020 |
Valid |
WT00025276-2016 |
19 Sep 2016 |
31 July 2021 |
Valid |
|
Billing Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table 3.5 Summary
of submission status under FEP-01/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.7 and 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Condition 2.6 |
Environmental Management Organization Chart |
14 Jun 2011 |
Condition 1.12 |
Commencement Date of Works |
21 Jun 2011 |
Condition 2.11 |
Landscape Plan (Revision B) |
20 Nov 2012 |
Condition
2.9 |
Noise
Management Plan (Revision B) |
13 Jan 2012 |
Contract no. HY/2009/18 –
Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
3.1.8. Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.6 and Table
3.7.
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Permit / Licence / Notification / Approval |
Reference
No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Permit issued |
Valid |
Notification of Works Under APCO |
322293 |
07 Oct 2010 |
Notified |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS1102-16 |
28
Oct 2016 |
01 Nov 2016 to |
Expired |
GW-RS1161-16 |
17 Nov 2016 |
1 Dec 2016 to 31 Mar 2017 |
Valid |
|
GW-RS1164-16 |
17 Nov 2016 |
1 Dec 2016 to 31 Mar 2017 |
Cancelled |
|
GW-RS1307-16 |
21 Dec 2016 |
23 Dec 2016 to 30 Apr 2017 |
Valid |
|
GW-RS1338-16 |
28 Dec 2016 |
01 Jan 2017 to |
Valid |
|
Discharge Licenses |
WT00013967-2012 |
17 Sep 2012 |
30 Sep 2017 |
Cancelled |
WT00014966-2013 |
08 Jan 2013 |
31 Jan 2018 |
Cancelled |
|
WT00020725-2015 |
14 Jan 2015 |
30 Jul 2017 |
Valid |
|
WT00024255-2016 |
18 May 2016 |
31 Jan 2021 |
Valid |
|
Registration as a Chemical Waste Producer |
WPN: 8335-121-L1048-04 |
17 Dec 2010 |
N/A |
Registration completed |
Billing Account under Waste
Disposal Ordinance (Land) |
Account No.: 7011587 |
11 Oct 2010 |
Account approved |
Valid |
Table 3.7 Summary
of submission status under FEP-05/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan (Rev. 6) |
19 May 2014 |
Contract no. HY/2009/15 – Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
3.1.9. Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.8 and Table 3.9.
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference
No. |
Issued Date
|
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0884-16 |
23 Aug 2016 |
08 Sep 2016
to 07 Mar 2017 |
Valid |
GW-RS0886-16 |
23 Aug 2016 |
09 Sep 2016
to 08 Mar 2017 |
Valid |
|
GW-RS0889-16 |
23 Aug 2016 |
11 Sep 2016
to 10 Mar 2017 |
Valid |
|
GW-RS1174-16 |
18 Nov 2016 |
24 Nov 2016
to 23 May 2017 |
Valid |
|
Registration
as a Chemical Waste Producer |
WPN:
5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Water
Discharge Licence (Discharge at TPCWAW) |
WT00020601-2014 |
18 Mar 2015 |
18 Mar 2015
to 31 Mar 2017 |
Valid |
Water Discharge
Licence (Discharge at TPCWAE) |
WT00024951-2016 |
8 Jul 2016 |
8 Jul 2016
to 31 Dec 2017 |
Expired |
Water
Discharge Licence( Discharge at TS1) |
WT00024874-2016 |
20 Jul 2016 |
20 Jul 2016
to 31 Mar 2021 |
Valid |
Table 3.9 Summary of submission status
under FEP-06/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition
2.6 |
Management
Organization of Main Construction Companies |
11 Mar 2011 |
Amendment
for Management Organization of Main Construction Companies |
16 May 2011 |
|
Condition
2.7 |
Works
Schedule |
15 Mar 2011 |
Condition
2.8 |
Location
Plan |
15 Mar 2011 |
Condition 2.9 |
Noise
Management Plan |
6 May 2011 |
Condition 2.10 |
Landscape Plan (Rev.3) |
30 Jan 2015 |
Contract no. HY/2009/19 –
Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor
Link under FEP-07/364/2009/D
3.1.10. The current status on licences and/or permits on
environmental protection pertinent and submission under FEP-07/364/2009/D for contract no. HY/2009/19 are shown in Table 3.10 and Table 3.11.
Table 3.10 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/19
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
25
Feb 2011 |
N/A |
Valid |
|
24
Nov 2015 |
N/A |
Valid |
||
Notification of Works Under APCO |
326160 |
24
Jan 2011 |
N/A |
Valid |
Registration as a Waste Producer |
7012306 |
10 Feb 2011 |
N/A |
Valid |
Registration as Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar 2011 |
N/A |
Valid |
Application for Vessel Disposal |
7012306 |
21 July 2011 |
N/A |
Valid |
Construction Noise Permits (CNP) for non-piling
equipment |
GW-RS0851-16 |
09 Aug 2016 |
09 Aug 2016 to 08 Feb 2017 |
Expired |
GW-RS1251-16 |
07 Dec 2016 |
18 Dec 2016 to 17 Jun 2017 |
Valid |
|
GW-RS1372-16 |
06 Jan 2017 |
11 Jan 2017 to 07 Apr 2017 |
Valid |
|
Water Discharge License |
WT00010865-2011 |
03 Nov 2011 |
30 Nov 2016 |
Cancelled |
Dumping
Permit (Approach Ramp) (Type 1 – Open Sea Disposal) |
EP/MD/17-078 |
01 Oct 2016 |
31 Mar 2017 |
Valid |
Table 3.11 Summary of
submission status under FEP-07/364/2009/D
EP Condition |
Submission |
Date of Submission |
Condition
2.13 |
Landscape
Plan (Rev.5) |
09 December 2016 |
Condition
2.9 |
Noise
Management Plan (Rev.4) |
15 February 2016 |
Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan
Chai Bypass at Wan Chai West
3.1.11.
The current status on licences and/or permits
on environmental protection pertinent and submission under FEP-12/364/2009/D
for contract no. HK/2012/08 showed in Table 3.12 and Table 3.13.
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2012/08
Permits
and/or Licences |
Reference
No. |
Issued Date
|
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-09/364/2009/B |
5 Mar 2013 |
N/A |
Valid |
FEP-12/364/2009/D |
1 Aug 2016 |
N/A |
Valid |
|
FEP-06/356/2009 |
5 March 2013 |
N/A |
Valid |
|
Notification
of Works Under APCO |
355439 |
4 Feb 2013 |
N/A |
Valid |
Registration
as a Chemical Waste Producer |
5213-134-C3790-01 |
30 Jun 2016 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance |
7016883 |
18 Feb 2013 |
18 Jul 2017 |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0902-16 |
24 Aug 2016 |
26 Aug 2016
to 25 Feb 2017 |
Expired |
GW-RS1336-16 |
29 Dec 2016 |
13 Jan 2017
to 12 Jul 2017 |
Valid |
|
GW-RS1371-16 |
5 Jan 2017 |
9 Jan 2017
to 8 Jul 2017 |
Valid |
|
GW-RS0098-17 |
1 Feb 2017 |
26 Feb 2017
to 25 Aug 2017 |
Valid |
|
Water
Discharge Licence |
WT00018223-2014 |
28 Jan 2014 |
31 Jan 2019 |
Cancelled |
WT00020594-2014 |
22 Dec 2014 |
31 Jan 2019 |
Valid |
Table 3.13 Summary of submission status under FEP-12/364/2009/D
Submission |
Date of Submission |
|
Condition 2.9 |
Noise Management
Plan (Rev.2) |
9 July 2013 |
Condition 2.14 |
Landscape Plan
(Rev.4) |
24 August 2015 |
Contract no. HY/2010/08 –Central – Wanchai Bypass Tunnel – Tunnel (Slip
Road 8)
3.1.12.
The current status on licences and/or permits
on environmental protection pertinent and submission under FEP-10/364/2009/B
for contract no. HK/2012/08 showed in Table 3.14 and Table 3.15.
Table 3.14 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2010/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental
Permit |
FEP-10/364/2009/B |
26 Jul 2013 |
NA |
Valid |
FEP-07/356/2009 |
26 Jul 2013 |
NA |
Valid |
|
Notification of Works
Under APCO |
357176 |
2013-04-02 |
NIL |
Valid |
Registration as a
Chemical Waste Producer |
WPN5213-147-C1169-44 |
2013-03-27 |
NIL |
Valid |
Billing Account under
Waste Disposal Ordinance |
7017170 |
2013-03-27 |
NIL |
Valid |
Water Discharge License |
WT0001651-2013 |
2013-07-09 |
2018-07-28 |
Cancelled |
WT00020468-2014 |
2014-12-03 |
2018-07-31 |
Valid |
|
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0888-16 |
23 Aug 2016 |
02 Sep 2016 to 28 Feb 2017 |
Cancelled |
GW-RS1232-16 |
08 Dec 2016 |
08 Dec 2016 to 01 June 2017 |
Cancelled |
|
GW-RS1194-16 |
30 Nov 2016 |
30 Nov 2016 to 24 May 2017 |
Cancelled |
|
GW-RS1129-16 |
24 Nov 2016 |
24 Nov 2016 to 22 May 2017 |
Cancelled |
|
GW-RS0977-16 |
21 Sep 2016 |
15 Nov 2016 to 14 May 2017 |
Cancelled |
|
GW-RS0969-16 |
19 Sep 2016 |
19 Sep 2016 to 18 Mar 2017 |
Valid |
|
GW-RS0971-16 |
19 Sep 2016 |
22 Oct 2016 to 20 Apr 2017 |
Valid |
|
GW-RS1182-16 |
29 Nov 2016 |
30 Nov 2016 to 24 May 2017 |
Valid |
|
GW-RS0930-16 |
17 Sep 2016 |
17 Sep 2016 to 17 Mar 2017 |
Cancelled |
|
GW-RS1254-16 |
10 Dec 2016 |
10 Dec 2016 to 07 Jun 2017 |
Valid |
|
GW-RS0029-17 |
19 Jan 2017 |
19 Jan 2017 to 02 Jul 2017 |
Valid |
|
GW-RS0086-17 |
31 Jan 2017 |
31 Jan 2017 to 30 Jul 2017 |
Valid |
|
GW-RS0092-17 |
31 Jan 2017 |
31 Jan 2017 to 31 Jul 2017 |
Valid |
Table 3.15 Summary of submission status under FEP-10/364/2009/B
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan (Rev.3) |
03 January 2014 |
Condition 2.14 |
Landscape Plan (Rev.2) |
19 May 2014 |
Condition 2.16 |
Additional Mitigation Plan (Rev.2) |
18 February 2015 |
Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009/E
3.1.13.
The current status on licenses and/or permits
on environmental protection pertinent and submission under FEP-11/364/2009/E
for contract no. HY/2011/08 showed in Table 3.16 and Table 3.17.
Table 3.16 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2011/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental
Permit |
FEP-11/364/2009/B |
2 May 2014 |
N/A |
Valid |
|
FEP-11/364/2009/E |
22 Dec 2014 |
N/A |
Valid |
Notification of Works
Under APCO |
LCAC-EN-LE-00017 |
7 Mar 2014 |
N/A |
Valid |
Registration as a
Chemical Waste Producer |
5213-121-L2837-01 |
19 Apr 2016 |
N/A |
Registered |
5213-151-L2837-02 |
24 May 2016 |
N/A |
Registered |
|
5213-134-L2898-01 |
16 Nov 2015 |
N/A |
Registered |
|
Billing Account under
Waste Disposal Ordinance |
7019640 |
27 Mar 2014 |
N/A |
Valid |
Construction Noise Permit
(CNP) for non-piling equipment |
GW-RS0811-16 |
28 Jul 2016 |
1 Aug 2016 to |
Cancelled |
GW-RS0892-16 |
25 Aug 2016 |
1 Sep 2016 to |
Cancelled |
|
GW-RS0801-16 |
29 Jul 2016 |
1 Aug 2016 to |
Expired |
|
GW-RS0891-16 |
25 Aug 2016 |
1 Sep 2016 to |
Valid |
|
GW-RS1089-16 |
28 Oct 2016 |
01 Nov 2016 to |
Valid |
|
GW-RS1151-16 |
17 Nov 2016 |
01 Dec 2016 to 31 May 2017 |
Valid |
|
GW-RS1168-16 |
17 Nov 2016 |
01 Dec 2016 to 31 May 2017 |
Valid |
|
GW-RS1169-16 |
18 Nov 2016 |
18 Nov 2016 to |
Valid |
|
GW-RS1178-16 |
17 Nov 2016 |
01 Dec 2016 to 31 May 2017 |
Valid |
|
GW-RS1134-16 |
28 Dec 2016 |
01 Jan 2017 to |
Valid |
|
GW-RS1137-16 |
28 Dec 2016 |
01 Jan 2017 to |
Valid |
|
GW-RS0068-17 |
24 Jan 2017 |
01 Feb 2017 to |
Valid |
|
GW-RS0100-17 |
1 Feb 2017 |
03 Feb 2017 to 31 Jul 2017 |
Valid |
|
GW-RS0139-17 |
23 Feb 2017 |
01 Mar 2017 to 31 Aug 2017 |
Valid |
|
GW-RS0146-17 |
23 Feb 2017 |
01 Mar 2017 to 31 Aug 2017 |
Valid |
|
Water Discharge Licence |
WT00020242-2014 |
04 Nov 2014 |
30 Nov 2019 |
Cancelled |
WT00022046-2015 |
15 Jul 2015 |
31 Jul 2019 |
Valid |
|
WT00022753-2015 |
3 May 2016 |
30 Apr 2021 |
Valid |
|
WT00024561-2016 |
30 May 2016 |
31 May 2021 |
Valid |
|
WT00022046-2015 |
15 Jul 2015 |
31 Jul 2019 |
Valid |
Table 3.17 Summary of submission status under FEP-11/364/2009/E
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan (Rev.4) |
08 November 2016 |
Condition 2.14 |
Landscape Plan (Rev.2) |
18 Feb 2015 |
Condition 2.13 a) |
Operational Air Quality Management Plan for
West Ventilation Building (Rev.0) |
25 Nov 2014 |
Condition 2.13 c) |
Operational Air Quality Management Plan for
East Ventilation Building and East Vent Shaft (Rev.0) |
18 Feb 2015 |
Condition 2.13 e) |
Operational Air Quality Management Plan for
ventilation system of Eastern Portal of the CWB Tunnel |
23 October 2016 |
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the Project
are listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.
Table 4.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon-day Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
*M7e |
International Finance Centre (Eastern End
of Podium) |
M7w |
International Finance Centre (Western End
of Podium) |
*M8 |
City Hall |
* Remark 1: Location ID has
been updated from M7 to M8 for City Hall
* Remark 2: M7e has become a
reference station starting from 7 Aug 2012
Real time Noise Monitoring Stations
4.1.2. The noise monitoring
stations for the Project are listed and shown in Table 4.2 and Figure 4.1. Appendix 4.1 shows the
established Action/Limit Levels for the monitoring works.
Table 4.2 Real Time Noise Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section
Whitfield Depot |
North Point |
RTN2a |
Hong
Kong Electric Centre |
North Point |
RTN3 |
Po
Leung Kuk Yu Lee Mo Fan Memorial School |
Tin Hau |
RTN4 |
Causeway
Bay Community Centre |
Noise Monitoring Parameters, Frequency and Duration
4.1.3. The construction noise level shall be measured in terms of the
A-weighted equivalent continuous sound pressure level (Leq). Leq
(30 minutes) shall be used as the monitoring parameter for the time period between 0700
and 1900 hours on normal weekdays. For all other time periods, Leq (5
minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria. Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
4.1.4. Noise monitoring shall be carried out at all the designated monitoring
stations. The monitoring frequency shall depend on the scale of the
construction activities. The following is an initial guide on the regular
monitoring frequency for each station on a weekly basis when noise generating
activities are underway:
· One set of
measurements between 0700 and 1900 hours on normal weekdays.
4.1.5. Real time noise shall be carried out at the designated monitoring
stations. The following is an initial guide on the regular monitoring frequency
for each station on a 24 - hours basis when noise generating activities are
underway:
· One set of
measurements between 0700 and 1900 hours on normal weekdays.
· One set of
measurements between 1900 and 2300 hours on normal weekdays and 0700 and 2300
hours on public holidays.
· One set of
measurements between 2300 and 0700 hours on next day on everyday.
4.1.6. If construction works are extended to include works during the hours of
1900 – 0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
4.1.7. As referred to in the Technical Memorandum ™ issued under the NCO, sound
level meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
4.1.8. Noise measurements shall not be made in fog, rain, wind with a steady
speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall
be checked with a portable wind speed meter capable of measuring the wind speed
in m/s.
4.1.9. The sound level meter shall be checked using an acoustic calibrator
generating a known sound pressure level at a known frequency before deployment
to the site and during each site visit. Measurements will be accepted as valid
only if the calibration level from before and after the noise measurement agree
to within 1.0 dB.
Air Quality Monitoring Stations
4.2.1. The air quality monitoring stations for the Project are listed and shown
in Table 4.3 and Figure 4.1. Appendix 4.1
shows the established Action/Limit Levels for the monitoring works.
Table 4.3 Air Quality Monitoring
Stations
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Site Office** |
North Point (Re-commenced on 14 November
2011) |
CMA2a |
Causeway Bay Community Centre |
Causeway Bay |
CMA3a |
CWB PRE Site Office * |
Causeway Bay |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5b |
Pedestrian Plaza*** |
Wan Chai |
MA1e |
International Finance Centre (Eastern End
of Podium) |
Central |
MA1w |
International Finance Centre (Western End
of Podium) |
Central |
Remarks*: As per the ENPC meeting in March 2011, the monitoring stations
CMA3a – Future CWB site office at Wanchai Waterfront Promenade was renamed as
remark.
Remarks**: The location ID of monitoring station CMA1b was updated as “Oil
Street Site Office” in April 2013.
Remarks***: The station ID and monitoring location was updated in
December 2014 with respect to monitoring station relocation.
Air QUALITY Monitoring Parameters, Frequency and Duration
4.2.2. One-hour and 24-hour TSP levels should be measured to indicate the
impacts of construction dust on air quality. The 24-hour TSP levels shall be
measured by following the standard high volume sampling method as set out in
the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix
B.
4.2.3. All relevant data including temperature, pressure, weather conditions,
elapsed-time meter reading for the start and stop of the sampler,
identification and weight of the filter paper, and any other local atmospheric
factors affecting or affected by site conditions, etc., shall be recorded down
in detail.
4.2.4. For regular impact monitoring, the sampling frequency of at least once
in every six days, shall be strictly observed at all the monitoring stations
for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency
of at least three times in every six days should be undertaken when the highest
dust impact occurs.
Sampling Procedure and Monitoring Equipment
4.2.5. High volume samplers (HVSs) in compliance with the following
specifications shall be used for carrying out the 1-hour and 24-hour TSP
monitoring:
· 0.6 – 1.7 m3
per minute adjustable flow range;
· Equipped with a
timing / control device with +/- 5 minutes accuracy for 24 hours operation;
· Installed with
elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
· Capable of
providing a minimum exposed area of 406 cm2;
· Flow control
accuracy: +/- 2.5% deviation over 24-hour sampling period;
· Equipped with a shelter
to protect the filter and sampler;
· Incorporated with
an electronic mass flow rate controller or other equivalent devices;
· Equipped with a
flow recorder for continuous monitoring;
· Provided with a
peaked roof inlet;
· Incorporated with
a manometer;
· Able to hold and
seal the filter paper to the sampler housing at horizontal position;
· Easily changeable
filter; and
· Capable of
operating continuously for a 24-hour period.
4.2.6. Initial calibration of dust monitoring equipment shall be conducted upon
installation and thereafter at bi-monthly intervals. The transfer standard
shall be traceable to the internationally recognized primary standard and be
calibrated annually. The concern parties such as IEC shall properly document
the calibration data for future reference. All the data should be converted
into standard temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7. A clean laboratory with constant temperature and humidity control, and
equipped with necessary measuring and conditioning instruments to handle the
dust samples collected, shall be available for sample analysis, and equipment
calibration and maintenance. The laboratory should be HOKLAS accredited.
4.2.8. Filter paper of size 8” x 10” shall be labelled before sampling. It
shall be a clean filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24 hours and be pre-weighed before use for
the sampling.
4.2.9. After sampling, the filter paper loaded with dust shall be kept in a
clean and tightly sealed plastic bag. The filter paper shall then be returned
to the laboratory for reconditioning in the humidity controlled chamber
followed by accurate weighing by an electronic balance with readout down to 0.1
mg. The balance shall be regularly calibrated against a traceable standard.
4.2.10. All the collected samples shall be kept in a good condition for 6 months
before disposal.
4.2.11. Current calibration certificates of equipments are presented in Appendix 4.2.
5.0.1. The environmental monitoring will be implemented based on the division
of works areas of each designated project managed under different contracts
with separate FEP applied by individual contractors. Overall layout showing work areas of
various contracts, latest status of work commencement and monitoring stations
is shown in Figure 2.1 and Figure 4.1. The
monitoring results are presented in according to the Individual Contract(s).
5.0.2. In the reporting month, the concurrent contracts are as follows:
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section)
Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central
Interchange
Contract no. HY/2009/19 – Central – Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
Contract no. HY/2010/08 – Central- Wanchai Bypass Tunnel (Slip Road 8
Section)
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre
Contract no. HK/2009/02 - Wan Chai Development Phase II – Central - Wan
Chai Bypass at Wan Chai East
Contract no. HK/2012/08 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai West
Contract no. HY/2011/08 – Central - Wan Chai Bypass (CWB)– Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
5.0.3. The environment monitoring schedules for reporting month and coming
month are presented in Appendix 5.1.
5.1.1
Monitoring for report
of review baseline noise level was performed from 11 April 2011 to 8 June
2011. Then the report was submitted
on the 20 June 2011, verified by IEC on 18 July 2011 and was approved by ER by
January 2012. The new baseline is
used for the noise calculation starting from January 2012.
Contract no.
HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
5.1.2 Noise monitoring for the Central Interchange works under contract no.
HY/2009/18 was commenced on 22 April 2011.The proposed division of noise
monitoring stations for Contract no. HY/2009/18 are summarized in Table
5.1 below:
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre
(Eastern End of Podium) |
M7w |
International Finance Centre
(Western End of Podium) |
M8 |
City Hall |
* Remark: M7e has become a reference station starting from 7 Aug 2012
5.1.3
No action or limit
level exceedance was recorded in this reporting month.
5.1.4
Noise monitoring
results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009 and
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai
Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.1.5
The commencement of
construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25
August 2011 and HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The
proposed division of noise monitoring stations are summarized in Table 5.2
below.
Table 5.2 Noise
Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.6
No action or limit
level exceedance was recorded in this reporting month.
5.1.7
Noise monitoring
results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no.
HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
5.1.8 The commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July
2011. Noise monitoring was commenced on 13 July 2011. The
proposed divisions of noise monitoring stations are summarized in Table
5.3 below.
Table 5.3 Noise
Monitoring Stations for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.9
No action or limit
level exceedance was recorded in this reporting month.
5.1.10
Noise monitoring
results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no.
HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/D
5.1.11 Noise
monitoring for the tunnel works under contract no. HY/2009/19 was commenced on
24 April 2011. The proposed division of noise monitoring stations are
summarized in Table 5.4 below.
Table 5.4 Noise
Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta
Secondary School |
5.1.12
Three limit level exceedances were recorded at M6-
HK Baptist Church Henrietta Secondary School on 07, 13 and 21 February 2017 in
this reporting month.
5.1.13
Traffic noise was
observed during monitoring 07, 13 and 21 February 2017 and were considered as
the major noise contribution. As such, the limit level exceedance was concluded
as non-project related.
5.1.14
Noise monitoring
results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2. Details of the Notification of Exceedance
can be referred in Appendix 6.2.
Contract no. HY/2010/08
– Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-12/364/2009/D
5.1.15 The commencement of construction works for Contract no. HY/2010/08 under
FEP-10/364/2009/B was on 02
September 2013. Noise monitoring was commenced on 02 September 2013. The
proposed divisions of noise monitoring stations are summarized in Table
5.5 below.
Table 5.5 Noise Monitoring Stations for Contract no. HY/2010/08
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
5.1.16
No action or limit
level exceedance was recorded in this reporting month.
5.1.17
Noise monitoring
results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
5.1.18 Noise monitoring for the Central Interchange works under contract no.
HY/2009/18 was commenced on 22 April 2011.The proposed division of noise
monitoring stations for Contract no. HY/2011/08 are summarized in Table
5.6 below:
Table 5.6 Noise Monitoring Stations for Contract no. HY/2011/08
Station |
Description |
M4b |
Victoria Centre |
*M7e |
International Finance Centre
(Eastern End of Podium) |
M7w |
International Finance Centre
(Western End of Podium) |
M8 |
City Hall |
* Remark: M7e has become a
reference station starting from 7 Aug 2012
5.1.19
No action or limit
level exceedance was recorded in this reporting month.
5.1.20
Noise monitoring
results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
5.2.1.
Real time noise monitoring at RTN4-Causeway
Bay Community Centre was commenced on 13 Jan 2013. The baseline noise level of
RTN4- Causeway Bay Community Centre has adopted the results from the baseline
noise monitoring report for EP/364/2009 in 22 April 2010 in which approved by
EPD.
5.2.2.
Po Leung Kuk Yu Lee Mo Fan Memorial School
granted permission for set up on 4 Sep 2012 and real time noise monitoring station
RTN3 set up was performed on 14 Sep 2012. Real time noise baseline capturing
was conducted during time period without construction work from 21 Sep 2012 to
04 Oct 2012. Real time noise monitoring at RTN3
– Po Leung Kuk Yu Lee Mo Fan Memorial School was commenced since 06 Oct 2012.
5.2.3.
Real-time noise monitoring station RTN2 previously
located at oil Street Community Liaison Centre was relocated to Hong Kong
Electric Centre on 5 Oct 2012, which is a representative of the noise sensitive
receiver City Garden. The baseline noise level of RTN2a will adopt the results
derived from the baseline noise monitoring conducted at Hong Kong Electric
Centre from 4 December 2009 to 17 December 2009.
5.2.4.
Real-time noise monitoring station RTN1-FEHD
Whitfield Depot was finely adjusted from 2/F to roof-top at FEHD Whitfield
Depot on 24 June 2013 with respect to the commencement of advance works for IEC
parapet demolition.
Contract no.
HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/D
5.2.5.
The proposed division
of noise monitoring stations are summarized in Table 5.7 below.
Real time noise monitoring for major construction works under contract no.
HY/2009/19 was commenced on 24 April 2011.
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin
Hau |
FEHD Hong Kong Transport Section Whitfield Depot |
RTN2a |
North Point |
Hong Kong Electric Centre |
RTN3 |
North Point |
Po Leung Kuk Yu Lee Mo Fan
Memorial School |
RTN4 |
Tin Hau |
Causeway Bay Community
Centre |
* Real
time noise monitoring results and graphical presentation during restrict hours
and night time period are for information only and noise during CNP period
shall be controlled under NCO.
5.2.6.
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section
Whitfield Depot was recorded in the reporting month.
5.2.7.
Limit level exceedances
were recorded at RTN2a- Hong Kong Electric Centre on 03, 04, 07, 09, 11, 13 to
17, and 21 to 25 February 2017 during daytime in the reporting month. After
checking with Contractor of HY/2009/19, on 03 and 04 February 2017, no works
was conducted around the monitoring station under Contract HY/2009/19.
On 07 and 09 February
2017, Re-boring, sheet piling and sheet pile extraction were conducted under
Contract HY/2009/19 and temporary noise barrier was provided along the site
boundary by the Contractor of HY/2009/19.
On 11 and 13 February
2017, no works was conducted around the monitoring station under Contract
HY/2009/19.
On 14 and 15 February
2017, Re-boring, sheet piling and sheet pile extraction were conducted under
Contract HY/2009/19 and temporary noise barrier was provided along the site
boundary by the Contractor of HY/2009/19.
On 16 and 17 February
2017, Pre-boring and sheet piling were conducted under Contract HY/2009/19 and
temporary noise barrier was provided along the site boundary by the Contractor
of HY/2009/19.
On 21, 22, 23
February 2017, Pre-boring and sheet piling and administration building concrete
junction trimming works were conducted under Contract HY/2009/19 and temporary
noise barrier was provided along the site boundary by the Contractor of
HY/2009/19.
On 24, 25 February
2017, Pre-boring and sheet piling installation/ extraction and administration
building concrete junction trimming works were conducted under Contract
HY/2009/19 and temporary noise barrier was provided along the site boundary by
the Contractor of HY/2009/19.
Nevertheless,
building construction works with breaking and hammering works under non-CWB
private development site at Oil Street was conducted at the building level
adjacent to the noise monitoring station and were considered as the major noise
contribution across the monitoring period in February. As such, the exceedances
were considered as non-Project related.
5.2.8.
No limit level
exceedances were recorded at RTN3- Yu Lee Mo Fan Memorial School in the
reporting month.
5.2.9.
No limit level exceedance was recorded at RTN4- Causeway Bay Community Centre in
the reporting month.
5.2.10.
Real time noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix 5.4.
Contract no. HY/2011/08
– Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and
Works Associated with Tunnel Commissioning
5.2.11.
The proposed division
of noise monitoring stations are summarized in Table 5.8 below.
Real time noise monitoring for major construction works under contract no.
HY/2011/08 was commenced on 19 March 2015.
Table 5.8 Real Time Noise Monitoring Stations for Contract no. HY/2011/08
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section
Whitfield Depot |
RTN2a |
North Point |
Hong
Kong Electric Centre |
RTN4 |
Tin Hau |
Causeway Bay Community Centre |
* Real
time noise monitoring results and graphical presentation during restrict hours
and night time period are for information only and noise during CNP period
shall be controlled under NCO.
5.2.12.
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section
Whitfield Depot was recorded in the reporting month.
5.2.13.
Limit level
exceedances were recorded at RTN2a- Hong Kong Electric Centre on 03, 04, 07,
09, 11, 13 to 17, and 21 to 25 February 2017 during daytime in the reporting
month. After checking with Contractor of HY/2011/08, formwork and bar fixing works
were conducted at the Administration Building Area on 03, 04, 07, 09, 11, 13 to
15 February 2017 and formwork and bar fixing works and concreting works were
conducted on 16, 17, 21 to 25 February 2017 at the Administration Building Area
and no major noise emanation were considered.
Nevertheless, Non CWB Project building construction works with drilling
and breaking works opposite to the monitoring station at Oil Street were
observed across February 2017 and observed as the major noise contribution
throughout the monitoring period. In view of the above, the exceedances were
considered as non-Project related.
5.2.14.
No limit level exceedance was
recorded at RTN4- Causeway Bay Community Centre Hong Kong Transport Section
Whitfield Depot was recorded in the reporting month.
Contract no.
HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange
under FEP-05/364/2009/A
5.3.1
Air quality monitoring
for the Central Interchange works under contract no. HY/2009/18 was commenced
on 21 April 2011. The proposed division of air quality monitoring stations are
summarized in Table 5.9 below.
Table 5.9 Air Quality Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre
(Eastern End of Podium) |
MA1w |
International Finance Centre
(Western End of Podium) |
5.3.2
No exceedance was
recorded in the reporting month.
5.3.3
Air quality
monitoring results measured in this reporting period are reviewed and
summarized. Details of air quality monitoring results and graphical
presentation can be referred in Appendix 5.3.
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009
5.3.4
The commencement of
construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25
August 2011. Air quality monitoring was commenced on 25 August 2011. The
proposed division of air quality monitoring stations are summarized in Table
5.10 below.
Table 5.10 Air Quality Monitoring Station for Contract no. HK/2009/01
Station |
Description |
CMA5b |
Pedestrian Plaza |
5.3.5
One 1hr TSP action
level exceedance was recorded at CMA5b on 02 February 2017.
5.3.6
No construction works
was undertaken on 02 February 2017 around Pedestrian Plaza under Contract
HK/2009/01, no particular observation regarding air quality impact was observed
during sampling. In view of the above, the action level exceedance was
considered to be non-project related and potentially contributed by local
ambient condition.
5.3.7
One 24hr TSP action
level exceedance was recorded at CMA5b on 18 February 2017.
5.3.8
No construction works
was undertaken on 18 February 2017 around Pedestrian Plaza under Contract
HK/2009/01, no particular observation regarding air quality impact was observed
during sampling. In view of the above, the action level exceedance was
considered to be non-project related and potentially contributed by local
ambient condition such as road traffic next to the monitoring station.
5.3.9
Air quality
monitoring results measured in this reporting period are reviewed and
summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
5.3.10
The commencement of
construction works for HK/2009/02 under FEP-01/364/2009 is on 26 April 2011.
The proposed division of air quality monitoring stations are summarized in Table
5.11 below.
Table 5.11 Air Quality Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention
of Cruelty to Animals |
5.3.11
No exceedance was
recorded in the reporting month.
5.3.12
Air quality
monitoring results measured in this reporting period are reviewed and
summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no.
HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
5.3.13
The commencement of
construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on
13 July 2011. Air quality monitoring was commenced on 14 July 2011. The proposed division of air quality monitoring
stations are summarized in Table 5.12 below.
Table 5.12 Air Quality Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.14
No exceedance was
recorded in the reporting month.
5.3.15
Air quality
monitoring results measured in this reporting period are reviewed and
summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no.
HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/D
5.3.16
The proposed division
of air quality monitoring stations are summarized in Table 5.13
below. Air quality monitoring for the tunnel works under contract no.
HY/2009/19 was commenced on 26 April 2011.
Table 5.13 Air Quality Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Site Office |
CMA2a |
Causeway Bay Community
Centre |
5.3.17
No exceedance was
recorded in the reporting month.
5.3.18
Air quality
monitoring results measured in this reporting period are reviewed and
summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2012/08-
Wan Chai Development Phase II – Central-Wan Chai Bypass at Wan Chai West
5.3.19
The commencement of
construction works for Contract no. HK/2012/08 under FEP-09/364/2009/B was on May
2014. Air quality monitoring was commenced on 25 August 2011. The proposed division of air quality monitoring
stations are summarized in Table 5.14 below.
Table 5.14 Air Quality Monitoring Station for Contract no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian Plaza |
5.3.20
One 1hr TSP action
level exceedance was recorded at CMA5b on 02 February 2017.
5.3.21
Despite formwork
erection and rebar fixing was undertaken on 02 February 2017 around Pedestrian
Plaza under Contract HK/2012/08, no particular observation regarding air
quality impact was observed during sampling. In view of the above, the action
level exceedance was considered to be non-project related and potentially
contributed by local ambient condition.
5.3.22
One 24hr TSP action
level exceedance was recorded at CMA5b on 18 February 2017.
5.3.23
Despite formwork
erection and rebar fixing was undertaken on 18 February 2017 around Pedestrian
Plaza under Contract HK/2012/08, no particular observation regarding air
quality impact was observed during sampling. In view of the above, the action
level exceedance was considered to be non-project related and potentially
contributed by local ambient condition such as road traffic next to the
monitoring station.
5.3.24
Air quality
monitoring results measured in this reporting period are reviewed and
summarized. Details of air quality monitoring results and graphical
presentation can be referred in Appendix 5.3.
Contract no. HY/2010/08
– Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-12/364/2009/D
5.3.25
The commencement of
construction works for Contract no. HY/2010/08 under FEP-12/364/2009/D was on
July 2014. Air quality monitoring was commenced on 14 July 2011. The proposed division of air quality monitoring
stations are summarized in Table 5.15 below.
Table 5.15 Air Quality Monitoring Station for Contract no. HY/2010/08
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.26
No exceedance was
recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
5.3.27
Air quality monitoring
for the Central Interchange works under contract no. HY/2011/08 was commenced
on 21 April 2011. The proposed division of air quality monitoring stations are
summarized in Table 5.16 below.
Table 5.16 Air Quality Monitoring Stations for Contract no. HY/2011/08
Station |
Description |
MA1e |
International Finance Centre
(Eastern End of Podium) |
MA1w |
International Finance Centre
(Western End of Podium) |
CMA1b |
Oil Street Site Office |
CMA2a |
Causeway Bay Community
Centre |
5.3.28
No exceedance was
recorded in the reporting month.
5.3.29
Air quality
monitoring results measured in this reporting period are reviewed and
summarized. Details of air quality monitoring results and graphical
presentation can be referred in Appendix 5.3.
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009
5.4.1. Inert C&D
wastes and non-inert C&D wastes were disposed in this reporting month. Details of the waste flow table are summarized in Table 5.17.
Table 5.17 Details of
Waste Disposal for Contract no. HK/2009/01
Waste Type |
|||
Inert C&D materials disposed, m3 |
Nil |
107926.02 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
Nil |
98512.03 |
N/A |
Non-inert C&D materials disposed, m3 |
14.94 |
5230.98 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
Nil |
1285746 |
N/A |
Chemical waste disposed, kg |
Nil |
10400 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal) , m3 |
Nil |
11527 |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
Nil |
16261 |
East of Cha Chau South Brothers |
Contract no. HK/2009/02
– Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East
(CWB Tunnel) under FEP-01/364/2009
5.4.2. Inert C&D & non-inert C&D wastes were disposed of in this
reporting month. Details of the waste flow table are summarized in Table
5.18.
Table 5.18 Details of Waste Disposal for
Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D
materials disposed, m3 |
335 |
521603.412 |
TKO137
/ TM 38 |
Inert C&D
materials recycled, m3 |
Nil |
46520 |
N/A |
Non-inert C&D
materials disposed, m3 |
72 |
4079.317 |
SENT
Landfill |
Non-inert C&D
materials recycled, m3 |
Nil |
N/A |
N/A |
Chemical waste
disposed, kg |
Nil |
17718 |
N/A |
Marine Sediment
(Type 1 – Open Sea Disposal) , m3 |
Nil |
65663 |
South
Cheung Chau |
Contract
no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
5.4.3. Inert C&D and non-inert C&D waste was disposed of in this
reporting month. Details of the waste flow table are summarized in Table
5.19.
Table 5.19 Details of Waste Disposal for Contract
no. HY/2009/18
74.86 |
1414855.85 |
||
Nil |
58787.05 |
||
5.87 |
4349.5 |
||
Nil |
878.37 |
||
Nil |
6772 |
Contract no. HY/2009/15 – Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
5.4.4. Inert & Non-inert
C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.20.
Table 5.20 Details of
Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
165.12 Nil |
625200.92 245453.3 |
Tuen
Mun Area 38 TKO137
FB |
Inert
C&D materials recycled, m3 |
Nil |
358660.77 |
HY/2009/11 ex-PCWA TS4
/TS2 WDII Lun
Ku Tan WENT HY/2010/08 |
Non-inert
C&D materials disposed, m3 |
0.71 Nil |
4673.1 1.58 |
SENT
Landfill WENT
Landfill |
Non-inert
C&D materials recycled, m3 |
Nil |
5496446.2 |
Xun
Xiang Metalware Skylight Recycle (paper) |
Chemical
waste disposed, kg |
Nil |
22755 |
Dunwell
Group |
Marine
Sediment (Type1-Open Sea Disposal (Dedicate Sites) &Type 2 – Confined
Marine Disposal), m3 |
Nil |
5684 |
South
of the Brothers |
Contract no. HY/2009/19 – Central – Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
5.4.5. Inert and Non-inert C&D wastes were disposed of in this reporting
month. Details of the waste flow table are summarized in Table 5.21.
Table 5.21 Details of Waste Disposal for Contract no. HY/2009/19
Inert C&D materials disposed, ton |
2425.87 |
673804.84 |
TM38 |
Inert C&D materials recycled, ton |
Nil |
82349.7 |
N/A |
Non-inert C&D materials disposed, ton |
46.3 |
5541.32 |
SENT Landfill |
Non-inert C&D materials recycled, ton |
0.5 |
565.63 |
N/A |
Chemical waste disposed, kg |
0.13 |
10.15 |
N/A |
Marine Sediment (Tunnel) (Type-1 Open Sea Disposal), m3 |
Nil |
20556 |
South of Cheung Chau |
Marine Sediment (Tunnel) (Type 1- Open Sea Disposal (Dedicated Sites)
& Type 2 – Confined Marine Disposal),
m3 |
Nil |
30751 |
East of Sha Chau |
Contract no.
HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai
West under FEP-12/364/2009/D
5.4.6. No inert and Non-inert C&D wastes were disposed of in this reporting
month. Details of the waste flow table are summarized in Table 5.22.
Table 5.22 Details of Waste Disposal for Contract
no. HK/2012/08
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
154 Nil |
181965 116668 |
TKO 137 TM38 |
Inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Non-inert C&D materials disposed, m3 |
525 |
5802 |
SENT |
Non-inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Chemical waste disposed, kg |
Nil |
Nil |
N/A |
Marine sediment (Type 1) disposal, m3 |
Nil |
3145 |
South of Cheung Chau / East
of Sha Chau / South of The Brothers |
RRemarks: The quantity of inert C&D
material disposed, recycled, non-inert C&D material disposed, recycled are
reported up to calendar month on 28 February 2017.
Contract no. HY/2010/08 Central – Wan Chai Bypass (CWB) – Tunnel
(Slip Road 8) under FEP-10/364/2009/B
5.4.7. No inert and Non-inert C&D wastes were disposed of in this reporting
month. Details of the waste flow table are summarized in Table 5.23.
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials
disposed, m3 |
104.2 Nil Nil 16.1 |
578139.47 262656.6 82911.8 72497.69 |
TM
38 WENT SENT TKO
area 137 |
Inert C&D materials
recycled, m3 |
Nil |
Nil |
N/A |
Non-inert C&D materials disposed, m3 |
128 |
3639.53 |
SENT |
Non-inert C&D materials
recycled, m3 |
Nil |
Nil |
N/A |
Chemical waste disposed, kg |
Nil |
979 |
N/A |
Type 1 – Open Sea Disposal, m3 |
Nil |
16368.4 |
East Sha Chau/ South Brothers Island |
Type 2 – Confined Marine disposal, m3 |
Nil |
549.2 |
East Sha Chau |
Table 5.23 Details of
Waste Disposal for Contract no. HY/2010/08
Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
5.4.8. No inert and Non-inert C&D wastes were disposed of in this reporting
month. Details of the waste flow table are summarized in Table 5.24.
Table 5.24 Details of
Waste Disposal for Contract no. HY/2011/08
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials
disposed, m3 |
46.37 |
645.33 |
CWPF & TKO137 |
Inert C&D materials
recycled, m3 |
Nil |
Nil |
N/A |
Non-inert C&D materials
disposed, m3 |
110.72 |
1948.89 |
SENT |
Non-inert C&D materials
recycled, ton |
Nil |
31.72 |
N/A |
Chemical waste disposed, kg |
Nil |
3800 |
N/A |
6.0.1. The Event Action Plan for construction noise, air qualities are
presented in Appendix 6.1.
Contract no.
HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
6.1.1.
No exceedance was
recorded in the reporting month.
Contract no. HK/2009/01
– Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong
Convention Exhibition Centre – Tunnel Works under FEP-02/364/2009
6.1.2.
No exceedance was
recorded in the reporting month.
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
6.1.3.
No exceedance was
recorded in the reporting month.
Contract no. HY/2009/15 –
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
6.1.4.
No exceedance was
recorded in the reporting month.
Contract no.
HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/D
6.1.5.
Three limit level
exceedances were recorded at M6- HK Baptist Church Henrietta Secondary School
on 07, 13 and 21 February 2017 in this reporting month.
6.1.6.
Traffic noise was
observed during monitoring 07, 13 and 21 February 2017 and were considered as
the major noise contribution. As such, the limit level exceedance was concluded
as non-project related.
Contract no. HY/2010/08 –
Central-Wanchai Bypass – Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
6.1.7.
No exceedance was
recorded in the reporting month.
Contract no. HY/2011/08
Central –Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009/E
6.1.8.
No exceedance was
recorded in the reporting month.
Real Time Noise Monitoring
Contract no. HY/2009/19 – Central – Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
6.1.9.
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section
Whitfield Depot was recorded in the reporting month.
6.1.10.
Limit level
exceedances were recorded at RTN2a- Hong Kong Electric Centre on 03, 04, 07,
09, 11, 13 to 17, and 21 to 25 February 2017 during daytime in the reporting
month. After checking with Contractor of HY/2009/19, on 03 and 04 February
2017, no works was conducted around the monitoring station under Contract
HY/2009/19.
On 07 and 09 February
2017, Re-boring, sheet piling and sheet pile extraction were conducted under
Contract HY/2009/19 and temporary noise barrier was provided along the site
boundary by the Contractor of HY/2009/19.
On 11 and 13 February
2017, no works was conducted around the monitoring station under Contract
HY/2009/19.
On 14 and 15 February
2017, Re-boring, sheet piling and sheet pile extraction were conducted under
Contract HY/2009/19 and temporary noise barrier was provided along the site
boundary by the Contractor of HY/2009/19.
On 16 and 17 February
2017, Pre-boring and sheet piling were conducted under Contract HY/2009/19 and
temporary noise barrier was provided along the site boundary by the Contractor
of HY/2009/19.
On 21, 22, 23
February 2017, Pre-boring and sheet piling and administration building concrete
junction trimming works were conducted under Contract HY/2009/19 and temporary
noise barrier was provided along the site boundary by the Contractor of
HY/2009/19.
On 24, 25 February
2017, Pre-boring and sheet piling installation/ extraction and administration
building concrete junction trimming works were conducted under Contract
HY/2009/19 and temporary noise barrier was provided along the site boundary by
the Contractor of HY/2009/19.
Nevertheless,
building construction works with breaking and hammering works under non-CWB
private development site at Oil Street was conducted at the building level
adjacent to the noise monitoring station and were considered as the major noise
contribution across the monitoring period in February. As such, the exceedances
were considered as non-Project related.
6.1.11.
No limit level
exceedances were recorded at RTN3- Yu Lee Mo Fan Memorial School in the
reporting month.
6.1.12.
No limit level exceedance was recorded at RTN4- Causeway Bay Community Centre in
the reporting month.
Contract no. HY/2011/08
Central –Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009/EF
6.1.13.
No limit level exceedance was
recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot was recorded in
the reporting month.
6.1.14.
Limit level
exceedances were recorded at RTN2a- Hong Kong Electric Centre on 03, 04, 07,
09, 11, 13 to 17, and 21 to 25 February 2017 during daytime in the reporting
month. After checking with Contractor of HY/2011/08, formwork and bar fixing
works were conducted at the Administration Building Area on 03, 04, 07, 09, 11,
13 to 15 February 2017 and formwork and bar fixing works and concreting works
were conducted on 16, 17, 21 to 25 February 2017 at the Administration Building
Area and no major noise emanation were considered.
Nevertheless, Non CWB
Project building construction works with drilling and breaking works opposite
to the monitoring station at Oil Street were observed across February 2017 and
observed as the major noise contribution throughout the monitoring period. In
view of the above, the exceedances were considered as non-Project related.
6.1.15.
No limit level exceedance was
recorded at RTN4- Causeway Bay Community Centre Hong Kong Transport Section
Whitfield Depot was recorded in the reporting month
Contract no. HY/2009/18 –
Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
6.2.1. No exceedance was recorded in the reporting month.
Contract no. HK/2009/01 – Wan
Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre – Tunnel Works under FEP-02/364/2009
6.2.2. One 1hr TSP action level exceedance was recorded at CMA5b on 02 February
2017.
6.2.3. No construction works was undertaken on 02 February 2017 around
Pedestrian Plaza under Contract HK/2009/01, no particular observation regarding
air quality impact was observed during sampling. In view of the above, the
action level exceedance was considered to be non-project related and
potentially contributed by local ambient condition.
6.2.4. One 24hr TSP action level exceedance was recorded at CMA5b on 18
February 2017.
6.2.5. No construction works was undertaken on 18 February 2017 around
Pedestrian Plaza under Contract HK/2009/01, no particular observation regarding
air quality impact was observed during sampling. In view of the above, the
action level exceedance was considered to be non-project related and
potentially contributed by local ambient condition such as road traffic next to
the monitoring station.
Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
6.2.6. No exceedance was recorded in the reporting month.
Contract no. HY/2009/15 –
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)
FEP-06/364/2009/A
6.2.7. No exceedance was recorded in the reporting month.
Contract no. HY/2009/19 – Central – Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
6.2.8. No exceedance was recorded in the reporting month.
Contract no. HK/2012/08 Wan
Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D
6.2.9. One 1hr TSP action level exceedance was recorded at CMA5b on 02 February
2017.
6.2.10. Despite formwork erection and rebar fixing was undertaken on 02 February
2017 around Pedestrian Plaza under Contract HK/2012/08, no particular
observation regarding air quality impact was observed during sampling. In view
of the above, the action level exceedance was considered to be non-project
related and potentially contributed by local ambient condition.
6.2.11. One 24hr TSP action level exceedance was recorded at CMA5b on 18
February 2017.
6.2.12. Despite formwork erection and rebar fixing was undertaken on 18 February
2017 around Pedestrian Plaza under Contract HK/2012/08, no particular
observation regarding air quality impact was observed during sampling. In view
of the above, the action level exceedance was considered to be non-project
related and potentially contributed by local ambient condition such as road
traffic next to the monitoring station.
Contract no. HY/2010/08 –
Central-Wanchai Bypass – Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
6.2.13. No exceedance was recorded in the reporting month.
Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009/E
6.2.14. No exceedance was recorded in the reporting month.
6.3.1. There was no non-compliance from the site audits and monitoring in the
reporting period. The observations and recommendations made in each individual
site audit session were presented in Section 8.
6.4.1 There was no particular action taken since no non-compliance was
recorded from the site audits and monitoring in the reporting period.
7.0.1.
According to Condition
3.4 of the EP-364/2009/E, this section addresses the relevant cumulative
construction impact due to the concurrent activities of the current projects
including the Central Reclamation Phase III (CRIII), Wan Chai Development Phase
II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects
(IECL) and Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai East (CWB Tunnel).
7.0.2.
According to the
Final EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK
12/02, the major construction activities were completed by end of January 2014
and no construction activities were undertaken thereafter and the water quality
monitoring was completed in October 2011.
As such, it is considered that there were no cumulative construction
impact due to the concurrent activities of the current projects with the
Central Reclamation Phase III (CRIII) undertaken by contractor HK12/02 in the
reporting month.
7.0.3.
According to the
construction programme of Central-Wanchai Bypass at Wanchai West at the Central
Reclamation Phase III area include road works, backfilling works and
reinstatement of Culvert and Cooling main were performed in February 2017
reporting month. As no project related exceedance were recorded during the
reporting period, cumulative construction impact due to the concurrent
activities of the current projects with the Central Reclamation Phase III
(CRIII) was considered as insignificant.
7.0.4.
According to the construction programme of Wan Chai Development Phase
II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the
major construction activities under Wan Chai Development Phase II were, road
and drains, building demolition and tunnel works at Wan Chai East, tunnel
construction and backfilling works and ELS works at Wan Chai West. The major
construction activities under Central-Wan Chai Bypass and Island Eastern
Corridor Link Projects were road works and ventilation building construction at
Central Interchange, reinstatement of Eastern Breakwater, ELS works and
retaining wall construction at Victoria Park, ELS works and tunnel works at
TS3, bridge construction, piling and tunnel works at North Point area in the
reporting month. In addition, other non-Wan Chai Development Phase II,
Central-Wan Chai Bypass and Island Eastern Corridor Link projects was
observed undertaken at Wan Chai North and North Point area.
7.0.5.
No significant air quality
impact from construction activities was anticipated in the reporting month.
Besides, no project related exceedance was recorded during the air quality and
noise environmental monitoring events in the reporting month. Thus, it is
evaluated that the cumulative construction impact from the concurrent projects
including Central Reclamation Phase III (CRIII), Wan Chai Development Phase II
(WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects
(IECL) was insignificant.
8.0.1.
During this reporting
month, weekly environmental site audits were conducted for Contracts no.
HY/2009/15, HY/2009/18, HY/2009/19, HK/2012/08, HK/2009/01, HK/2009/02,
HY/2010/08 and HY/2011/08. No non-conformance was identified during the site
audits. The Contractors rectified major observations and recommendations made
during the audit sessions. No non-conformance was identified during the site
inspections.
8.0.2.
Site inspections for
Contract no. HY/2009/15 were carried out during this reporting period. The results of these inspections and outcomes are summarized in Table
8.1.
Table 8.1 Summary of Environmental Inspections for Contract no. HY/2009/15
Item |
Date |
Observations |
Action taken by Contractor |
Completion date |
170214_1 |
14 Feb 2017 |
Refuse sitting on the edge of breakwater shall be
cleaned regularly (Eastern Breakwater) |
Refuses sitting on the edge of breakwater was cleaned |
Completion as observed on 21 Feb 2017 |
Table 8.5 Summary of Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by Contractor |
Completion date |
170216_1 |
16 Feb 2017 |
Proper NRMM Label with correct information shall be
provided to powered mechanical equipment (Portion 3 & 4) |
Proper NRMM label was provided at the captioned
mechanical machine at Portion 3 & 4. |
Completion as observed on 21 February 2017. |
Table 8.6 Summary of Environmental Inspections for Contract no. HK/2012/08
Item |
Date |
Observations |
Action taken by Contractor |
Completion date |
170201_01 |
1-Feb-17 |
Contractor is needed to review the operation process of
the concerned concrete machine near MVB area and provide necessary action to
prevent dust emission to nearby sensitive receiver. |
The concerned machinery has been reviewed by the
contractor and it is operating at a controlled manner. No related dust
emission was further observed. |
Completion as observed on 7 Feb 2017. |
8.0.8.
Site inspections for
Contract no. HY/2010/08 were carried out during this reporting period. The
results of these inspections and outcomes are summarized in Table 8.7.
Table 8.7 Summary of Environmental Inspections for Contract no. HY/2010/08
Item |
Date |
Observations |
Action taken by Contractor |
Completion date |
170210_1 |
10 Feb 2017 |
Dust mitigation shall be provided to breaking works to
avoid dust emission (Victoria
Park) |
No further breaking works was observed |
Completion as observed on 15 Feb 2017 |
170210_2 |
10 Feb 2017 |
Proper drip tray with sides shall be provided for
chemical containers (TS3) |
Drip tray was provided to chemical container |
Completion as observed on 15 Feb 2017 |
170215_1 |
15 Feb 2017 |
Embankment and protection along site boundary shall be
reinforce to avoid surface runoff to public area (TS3) |
No further surface runoff was observed |
Completion as observed on 22 Feb 2017 |
170215_2 |
15 Feb 2017 |
Proper covering shall be provided to stockpile and dust
suppression measure shall be provided during operation (Victoria Park) |
Covering was provided to stockpile stored on-site |
Completion as observed on 22 Feb 2017 |
170222_1 |
22 Feb 2017 |
NRMM Label shall be provided to powered mechanical
equipment (TS3) |
NRMM Label was provided to the concerned PME |
Completion as observed on 2 Mar 2017 |
8.0.9.
Site inspections for
Contract no. HY/2011/08 were carried out during this reporting period. The
results of these inspections and outcomes are summarized in Table 8.8.
Table 8.8 Summary of
Environmental Inspections for Contract no. HY/2010/08
Item |
Date |
Observations |
Action taken by Contractor |
Completion date |
170210_1 |
10 Feb 2017 |
Dust mitigation shall be
provided to breaking works to avoid dust emission (Victoria Park) |
No further breaking
works was observed |
Completion as observed
on 15 Feb 2017 |
9.0.1.
Two environmental complaints were received in
the reporting month.
9.0.2.
First ICC public complaint referred by RSS
was received by ET on 24 February 2017 (Case Ref.: H08/RS/00001175-17). The complainant
reported that noise was emanated from the construction site near Victoria Park
Swimming Pool between 2300hrs to 2400hrs in the past months and caused
nuisance. ET confirmed with the Resident Site Staff that no works was conducted
under Contract HY/2010/08 near Victoria Park Swimming Pool (Hing Fat Street)
during the restricted hours (from 1900hrs to 0700hrs on the following day) from
21 December 2016 to 20 February 2017.
No works was
conducted under Contract HY/2010/08near Victoria Park Swimming Pool (Hing Fat
Street) during the restricted hours (from 1900hrs to 0700hrs on the following
day) from 21 December 2016 to 20 February 2017.
Nevertheless, in
view of the public concern, the Contractor of HY/2010/08 was reminded to
maintain the site control system for construction works carried out during
restricted hours to ensure the PMEs deployed are in compliance with relevant
Construction Noise Permit. The Contractor of HY/2010/08 was also reminded to
maintain regular maintenance of the plant and equipment deployed to avoid
potential nuisance to the nearby public
9.0.3.
Second ICC complaint referred by RSS was
received by ET on 24 February 2017 (CASE#2-3515474831). The complainant
reported that noise was emanated from the construction site near Victoria Park Swimming
Pool and Causeway Bay Typhoon Shelter between 1900hrs to 2400hrs in the past
months and caused nuisance.
ET confirmed with
the Resident Site Staff that concreting of tunnel structure at Temporary
Reclamation Area TS3 were conducted under Contract HY/2010/08 between 1900hrs
and 2300hrs on 13, 14, 15, 16 and 18 February 2017. Total 3 nos. of concrete
pump and 6 nos. of concrete lorry mixers were operated. Concreting of tunnel
structure at Temporary Reclamation Area TS3 were conducted under Contract
HY/2010/08 between 1900hrs and 2100hrs on 21 February 2017. Total 3 nos. of
concrete pump and 6 nos. of concrete lorry mixers were operated. Concreting of
tunnel structure at Zone C was conducted under Contract HY/2010/08 between
1900hrs to 2300hrs on 17 and 20 February 2017. Total 1 no. of concrete pump and
2 nos. of concrete mixers were operated. Bar bending at Zone C was conducted
under Contract HY/2010/08 between 1900hrs to 2300hrs on 13, 14, 15, 16, 18 and
19 February 2017. Total 1 no. bar bender and cutter was operated. No works was
conducted under Contract HY/2010/08 near Victoria Park Swimming Pool (Hing Fat
Street) during the restricted hours (from 1900hrs to 0700hrs on the following
day) across the period from 13 February 2017 to 21 February 2017.
Based on the site
records confirmed by RSS, no works was conducted under Contract HY/2010/08 near
Victoria Park Swimming Pool (Hing Fat Street) during the restricted hours (from
1900hrs to 0700hrs on the following day) from 13 February 2017 to 20 February
2017. Concreting of tunnel structure at Temporary Reclamation Area TS3 was
conducted under Contract HY/2010/08 between 1900hrs and 2300hrs on 13, 14, 15,
16 and 18 February 2017 and total 3 nos. of concrete pumps and 6 nos. of
concrete lorry mixers were operated. Concreting of tunnel structure at
Temporary Reclamation Area TS3 were conducted under Contract HY/2010/08 between
1900hrs and 2100hrs on 21 February 2017 and total 3 nos. of concrete pump and 6
nos. of concrete lorry mixers were operated. Relevant Construction Noise Permit
GW-RS0029-17 was in place while it is considered that there is no sufficient
information to indicate whether the Powered Mechanical Equipment were deployed
at the designed location stipulated under the relevant Construction Noise
Permit with noise mitigation measures required.
Concreting of
tunnel structure at Zone C was conducted under Contract HY/2010/08 between
1900hrs to 2300hrs on 17 and 20 February 2017. Total 1 no. of concrete pump and
2 nos. concrete mixers were operated. Bar bending at Zone C was conducted under
Contract HY/2010/08 between 1900hrs to 2300hrs on 13, 14, 15, 16, 18 and 19
February 2017 and total 1 no. bar bender and cutter was operated. Relevant
Construction Noise Permit GW-RS1366-13 was in place while it is considered that
there is no sufficient information to indicate whether the Powered Mechanical
Equipment were deployed at the designed location stipulated under the relevant
Construction Noise Permit with noise mitigation measures required.
Nevertheless,
further to the joint ad-hoc inspection conducted by the ET/IEC on 13 February
2017 during restricted hours (between 1900hrs to 2200hrs), concurrent
operations of 4 nos. of concrete lorry trucks at the Southern Side of TS3 near
Construction Site Entrance and concurrent operations of 2 nos. of concrete
lorry pumps and 2 nos. of concrete lorry truck at Western and Northern Side of
TS3 were observed while the temporary noise barrier provided for the concrete
lorry pump and concrete lorry truck at the Northern Side of TS3 could not
screen entirely the concrete lorry truck and concrete lorry pump (Located at
Northern Side of TS3) from nearby sensitive receivers. Therefore, it is
considered that the above operations observed could not follow the PME grouping
requirement and the specific condition 3.d.4 under the relevant Construction
Noise Permit.
In view of the
above, the Contractor of HY/2010/08 was advised to enhance the site supervision
and strictly implement the site control system for construction works carried
out during restricted hours to ensure the PMEs deployed strictly comply with
relevant Construction Noise Permit. The Contractor of HY/2010/08 was also
reminded to maintain regular maintenance of the plant and equipment deployed to
avoid potential nuisance to the nearby public.
9.0.4.
The details of cumulative complaint log and
updated summary of complaints are presented in Appendix 9.1
9.0.5. Cumulative statistic on complaints and successful prosecutions are
summarized in Table 9.1 and Table 9.2 respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
February
2017 |
2 |
September 2010 – January 2017 |
73 |
Total |
75 |
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought
Forward |
No. of Successful
Prosecutions this month (Offence Date) |
Cumulative No.
Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The EM&A programme was carried out in accordance with the EM&A
Manual requirements, minor alterations to the programme proposed were made in
response to changing circumstances.
10.0.2. The scheduled construction activities and the recommended mitigation
measures for the coming month are listed in Table 10.1. The
construction programmes of individual contracts are provided in Appendix 10.1.
Table 10.1 Summary of Key Construction Activities of Individual
Contract(s) to be commenced in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation
Measures |
HY/2009/15 |
·
Remedial works inside tunnel structure at
Mined Tunnel, TS4, TPCWAE and TPCWAW ·
Reinstatement of drainage pipes and
manhole at TPCWAE |
·
Dust control during dust generating activities
and covering for stockpile stored on site. ·
Provide protection works and adequate
drainage system to ensure no direct discharge into public drainage system or
the nearby water. ·
Maintain regular cleaning of floating
refuses within construction area. |
HY/2009/18 |
·
Drainage works ·
Road works ·
Landscaping works ·
Maintenance works |
·
Dust control during dust generating activities ·
Provide protection works to ensure no
runoff out of site area or direct discharge into public drainage system. |
HY/2009/19 |
·
Approach ramp sheet piling, pre-bored
piling and top soil removal
works ·
Hing Fat Street modification works ·
Bridge Demolition / Construction ·
Hotel Carpark Reinstatement ·
Oil Street drainage works ·
Bridge E noise barrier installation ·
IEC noise enclosure/barrier installation ·
Excavation / Construction of retaining
wall |
·
Noise level shall be controlled by
reducing the breaking operation rate. ·
Noise barrier shall be implemented ·
Dust control during dust generating works ·
Provide protection works and adequate
drainage system to ensure no direct discharge into public drainage system or
the sea. |
HK/2009/01 |
·
Reinstatement of amenity area ·
Road and Drain works |
·
Provide protection works and adequate
drainage system to ensure no direct discharge into public drainage system or
the sea. ·
Dust control during dust generating works ·
Noise mitigation measures during breaking
works |
HK/2009/02 |
·
Rectification works for cross road ducts ·
Rectification works for cracks/joints with
water leakage inside OHVD cells ·
Rectification works for out of tolerance
cross passage CP22 ·
Removal works for ELS S1 layer. ·
Concreting of mass concrete underneath HHR
flyover. ·
Tunnel backfilling & construction of
seawall foundation with Grade 400 rock fill. ·
Construction of temporary wall for Hung
Hing Road Flyover. ·
Demolition works for HHR flyover abutment. ·
Concreting blinding layer for HHR flyer. ·
Rebar fixing for HHR flyover. ·
Demolition of D-Wall ·
Remedial works of tunnel wall, base slab
and OHVD. ·
General cleaning and rectification works
of OHVD, tunnel base slab, carrier drain, cross road duct and manhole gully.
·
Rectification works for out of tolerance
cross passage CP23 ·
Rebar fixing and concreting of base slab
and walls. ·
Waterproofing membrane laying works for
side walls. |
·
Dust control during dust generating works ·
Proper maintenance boundary surface runoff
protection and water treatment facilities to avoid potential runoff related
impact. ·
Provision of protection measures to ensure
no runoff out of site area or direct discharge into public drainage system. |
HK/2009/02 |
·
Removal works for ELS S2 & S3 layer. ·
Rebar fixing and concreting of roadside
barrier. ·
Erect scaffolding for OHVD slab. ·
Rebar fixing and concreting of OHVD slab. ·
Relocation of the pillar. ·
Excavation works for trial pit for the
132kV HK Electric cables. |
|
HK/2012/08 |
·
Grouting ·
Construction of MVB and CWB Tunnel and
Slip Road 1 ·
Construction of concrete plug ·
Lateral support installation for CWB
tunnel, Slip Road 1, Plant Room and Exhaust Duct ·
Bulkhead removal ·
Back-filling at CWB tunnel |
·
Dust control during dust generating works ·
Provide protection works and adequate
drainage system to ensure no direct discharge into public drainage system. |
HY/2010/08 |
·
Tree protection works next to existing
BGO, ·
Drainage improvement works, ·
Excavation and Lateral Support for
U-structure, ·
Utility diversion works, ·
Retaining wall works ·
ELS works, ·
Construction works for subway extension |
·
Dust control during dust generating works
and stockpile stored on site. ·
Appropriate measures should be taken to
ensure adequate protections are provided for trees being transplanted and
retained on site. ·
Provision of protection to ensure no
runoff out of site area or direct discharge into public drainage system. |
HY/2011/08 |
·
Construction of Ventilation Buildings,
inclusive of Administration Building, East Ventilation Shaft/Building, West
Ventilation Building ·
Construction of Tunnel Thermal Barrier ·
Installation of Electricals and
Mechanicals ·
Installation of Tunnel Features |
·
Dust control during dust generating works |
10.0.3. The construction works of Contract no. 04/HY/2006 – Reconstruction of
Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
was completed, and the FEP was surrendered by the Contractor on 11 February
2011.
10.0.4. The construction works of Contract no. HY/2009/17 - Advance piling works
at Whitfield Depot under FEP-03/264/2009 was completed, and the FEP was
surrendered by the Contractor and found in order by EPD on 25 April 2013.
10.0.5. The construction works of Contract HK/2010/06 was completed, and the
FEP-08/364/2009/A was surrendered by the Contractor on 3 October 2014.