Contract No: HK/2015/01 Wanchai
Development Phase II and Central Wanchai Bypass Sampling,
Field Measurement and Testing Work (Stage 3) Environmental Permit no. EP-364/2009/E, Further
Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/D, FEP-09/364/2009/B,
FEP-10/364/2009/B and FEP-11/364/2009/E, FEP-12/364/2009/D Monthly Environmental Monitoring &
Audit Report
- July 2017 -
|
CLIENTS: |
|
Civil Engineering
and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
11 August 2017 |
2.2 Scope of the Project and Site
Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact
Personnel
3
status of regulatory compliance..
3.1 Status of Environmental Licensing and
Permitting under the Project
5.2 Real Time Noise Monitoring Results
5.3 Air Quality Monitoring Results
6.3 Review of the Reasons for and the
Implications of Non-compliance.
6.4 Summary of action taken in the event of
and follow-up on non-compliance.
7 Cumulative Construction
Impact due to the Concurrent Projects
9 Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table
2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.1 Summary
of the current status on licences and/or permits on environmental
protection pertinent to the Project
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.3 Summary
of submission status under FEP-02/364/2009
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.5 Summary
of submission status under FEP-01/364/2009
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.7 Summary
of submission status under FEP-05/364/2009/A
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.9 Summary
of submission status under FEP-06/364/2009/A
Table 3.10 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.11
Summary of submission status under FEP-07/364/2009/D
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.13 Summary of submission status under FEP-12/364/2009/D
Table 3.14 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.15 Summary of submission status under
FEP-10/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HY/2011/08
Table 3.17 Summary of submission status under FEP-11/364/2009/E
Table 4.1 Noise Monitoring
Stations
Table 4.2 Real
Time Noise Monitoring Stations
Table 4.3 Air
Quality Monitoring Stations
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/18
Table 5.2 Noise
Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Table 5.3 Noise
Monitoring Stations for Contract no. HY/2009/15
Table 5.4 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table 5.6 Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Real
Time Noise Monitoring Stations for Contract no. HY/2011/08
Table 5.9 Air
Quality Monitoring Station for Contract no. HY/2009/18
Table 5.10 Air Quality Monitoring
Station for Contract no. HK/2009/01
Table 5.11 Air Quality Monitoring
Station for Contract no. HK/2009/02
Table 5.12 Air Quality Monitoring
Stations for Contract no. HY/2009/15
Table 5.13 Air Quality
Monitoring Station for Contract no. HY/2009/19
Table 5.14 Air Quality
Monitoring Station for Contract no. HK/2012/08
Table 5.15 Air Quality Monitoring Stations for Contract no. HY/2010/08
Table 5.16 Air
Quality Monitoring Stations for Contract no. HY/2011/08
Table 5.17 Details
of Waste Disposal for Contract no. HK/2009/01
Table 5.18 Details
of Waste Disposal for Contract no. HK/2009/02
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/18
Table 5.20 Details
of Waste Disposal for Contract no. HY/2009/15
Table 5.21 Details of Waste Disposal
for Contract no. HY/2009/19
Table 5.22 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.23 Details of Waste Disposal
for Contract no. HY/2010/08
Table 5.24 Details of Waste Disposal for Contract
no. HY/2011/08
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/15 (NOT USED)
Table 8.2 Summary of Environmental
Inspections for Contract no. HY/2009/18 (NOT USED)
Table 8.3 Summary of
Environmental Inspections for Contract no. HY/2009/19
Table 8.4 Summary of
Environmental Inspections for Contract no. HK/2009/01 (NOT USED)
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.6 Summary of
Environmental Inspections for Contract no. HK/2012/08
Table
8.7 Summary of Environmental
Inspections for Contract no. HY/2010/08
Table 8.8 Summary of
Environmental Inspections for Contract no. HY/2011/08) (NOT USED)
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Table 10.1 Summary
of Key Construction Activities of Individual Contract(s) to be
commenced in Coming Reporting Month
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring
Results and Graphical Presentations
Appendix
5.4 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of
Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
·
Drainage works
·
Road works
·
Landscaping works
·
Maintenance works
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
Reinstatement of amenity area
·
Road and Drain works
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
·
Rectification works for the defects recorded in the inspection for the
end of maintenance period of Observation Deck and Staircase ST-01
·
Rectification works for cracks/joints with water leakage inside OHVD
cells
·
Concreting of Hung Hing Road Flyover approach ramp bay 3 base slab
·
Rebar fixing and formwork at Hung Hing Road Flyover approach ramp bay 1
base slab
·
Rebar fixing and formwork at Hung Hing Road Flyover approach ramp bay 2
wall
·
Backfilling works up to +4.0mPD inside cofferdam
·
Remedial work for cross road duct
·
Rectification works against water leakage and remedial works against
concrete defects of the tunnel structure
·
Outstanding works inside tunnel
·
Concreting for roadside barrier
·
Removal of scaffolding and formwork inside tunnel
·
Removal of silo tank
·
Waterproofing and screeding works on top of tunnel
·
Removal of strut and removal of waling
·
Reinstatement of temporary access opening at Bay 7
·
Breaking of D-Wall panel
·
Backfilling work for the area to be handed over to MTR SCL 1123
·
Sewage works at Wan Shing Street
·
Rectification works for uneven road surface at Hung Hing Road
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and
TPCWAW
·
Reinstatement work at the PRE Office car park area
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored piling and top soil removal works
·
Approach ramp structure Construction.
·
Bridge Construction
·
Pier 30-32 Cap Construction
·
Excavation / Construction of retaining wall
·
FEHD Metal Roof Construction
·
Pre-bored H-piles for Approach Ramp Phase 2 Construction
·
Hing Fat Street road and drainage works
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-12/364/2009/D
·
Construction of Slip Road 1
·
Construction of drainage
·
Asphalt paving of A2 Road
Contract
no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009/B
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction of Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
Noise Monitoring
Air Quality Monitoring
The 24hr TSP monitoring at CMA1b was
rescheduled from 17 July 2017 and 22 July 2017 to 18 July 2017 and 24 July 2017
respectively.
The 24hr TSP monitoring at CMA5b was
rescheduled from 29 June 2017 to 03 July 2017.
The 1hr TSP monitoring at CMA5b was
rescheduled from 30 June 2017 to 03 July 2017.
Complaints, Notifications of Summons
and Successful Prosecutions
ET confirmed with the Resident Site
Staff that Manual re-bar fixing works was carried out under Contract HK/2009/02
from 2300hrs to 2330hrs on 26 June 2017 at Portion 5 Bay 15 (Non - Designated
Area) top slab area adjacent to the covered walkway of the Wan Chai Ferry Pier.
1 no. of generator was operated at ground level and 2 nos. of generators were
operated below ground level from 2300hrs to 2400hrs on 26 June 2017. In
addition 16 electric water pump were operated below ground level from 2300hrs
to 2400hrs on 26 June 2017.
Notwithstanding the information stated
in above item 1), according to relevant Resident Site Staff site record, it was
recorded that 1 no. of mobile crane and 1 no. of bar bender were deployed and
operated at Portion 5 area (West of Wan Chai Ferry Pier) under Contract
HK/2009/02 after 2300hrs on 26 July 2017. Upon warning given by WDII Resident
Site staff to the Contractor of HK/2009/02, the operation of crawler crane for
lifting rebar and operation of bar bender machine were suspended at around
2315hrs on 26 June 2017.
No construction activity and site
operation was carried out under Contract HK/2009/01 from 2300hrs to 2400hrs on
26 June 2017.
According to the RSS site information,
manual re-bar fixing works was carried out under Contract HK/2009/02 from
2300hrs to 2330hrs on 26 June 2017 at Portion 5 Bay 15 (Non - Designated Area)
top slab area adjacent to the covered walkway of the Wan Chai Ferry Pier. 1 no.
of generator was operated at ground level and 2 nos. of generators were
operated below ground level from 2300hrs to 2400hrs on 26 June 2017 while 16
electric water pump were operated below ground level at Portion 5 Bay from
2300hrs to 2400hrs on 26 June 2017 and the relevant Construction Noise Permit
GW-RS0527-17 for the above operation was in place. However, site record on the
model of generators deployed on the concerned night was not available.
Notwithstanding the above, according to
relevant Resident Site Staff site record, it was recorded that 1 no. of mobile
crane and 1 no. of bar bender machine were deployed and operated at Portion 5
area (West of Wan Chai Ferry Pier) under Contract HK/2009/02 after 2300hrs on
26 July 2017 without a valid Construction Noise Permit. Upon warning given by
WDII Resident Site staff to the Contractor of HK/2009/02, the operation of
crawler crane for lifting rebar and operation of bar bender machine were
suspended at around 2315hrs on 26 June 2017. According to Contractor of
HK/2009/02, the operation bar bender machine was suspended upon warning by RSS
team and the operation of crawler crane was suspended upon moving to a proper
location to avoid obstruction for next day work.
Meanwhile, no construction activity and
site operation was carried out under Contract HK/2009/01 from 2300hrs to
2400hrs on 26 June 2017. In view of the above operation of powered mechanical
equipment under Contract HK/2009/02 beyond 2300hrs, the Contractor of
HK/2009/02 was required and urged to implement the following remedial measures
to ensure the strict construction noise permit compliance including:-
Fully review the site control system for
construction works carried out during restricted hours, in particular to ensure
the frontline supervisors responsible for restricted hours construction
operations are trained with comprehensive understanding on the requirement of
the Construction Noise Permit in force to ensure the PMEs deployed are in
compliance with relevant Construction Noise Permit.
To assign delegated and competent
personnel on-site to conduct checking on the deployment of PMEs on-site prior
and during restricted hours to ensure only PMEs allowed under relevant
Construction Noise Permit would be operated.
In addition, the following preventive
measures are also recommended including the Contractor of HK/2009/02 is
recommended to provide regular briefing and training section to site staffs and
frontline workers to enhance the workers awareness and understanding on
relevant Construction Noise Permit(s) requirement during restricted hours.
The Contractor of HK/2009/02 is
recommended to review the construction operation planning procedures to ensure
relevant PME(s) required for conducting the planned operation to ensure
required PME are adequate considered and covered by relevant Construction Noise
Permit.
In view of the recent concern over
restricted hours construction operations, a meeting was held amongst the CEDD,
the RSS team, the Contractor of HK/2009/02 and the Environmental Team on 21
July 2017 to review the site control measures and enhancement measures to be
adopted for restricted hours construction operations control for Construction Noise
Permit Compliance. A detailed implementation plan would be prepared by the
Contractor of HK/2009/02 and further supplemented.
An ICC complaint case (Ref:
2-4122021589) was Referred to the ET on 25 July 2017. The complainant reported
that the workers are now doing extremely noisy works at the Island Eastern
Corridor near Provident Centre affecting the nearby residents. As the ICC
complaint case refers to the noise concern at the same location at the same
hours on the same date, hence the ICC case is considered as the same complaint
case under the EPD complaint for investigation purpose.
ET confirmed with the Resident Site
Staff that emergency road repairing work including the repairing of movement
joint at Pier 46 and three potholes along IEC Westbound was carried out under
Contract HY/2009/19 around the concerned location from 0000hrs to 0600hrs on 14
July 2017. Total 1 no. of hand held breaker and 1 no. of hand held drill for
grout mixing were operated.
According to the RSS site information,
emergency road repairing work including the repairing of movement joint at Pier
46 and three potholes along IEC Westbound was carried out under Contract
HY/2009/19 around the concerned location from 0000hrs to 0600hrs on 14 July
2017. Total 1 no. of hand held breaker and 1 no. of hand held drill for grout
mixing were operated. A written advance notification was issued to the EPD on
13 July 2017 regarding the aforesaid emergency road repairing works. In view of
the public concern, the Contractor of HY/2009/19 is recommended to adopt
additional noise mitigation measure for future emergency road repairing works,
if any, at night time hours around the concerned location. In response to the
public concern, the Contractor of HY/2009/19 would adopt the following
additional measures for future emergency road repairing works including: i) For
any emergency works requiring, for example, breaking or any other noisy
activities, wherever possible, temporary noise barrier or acoustic mat will be
use to fence of the line of sight between the noise emanating source and the
NSR, ii) Covering breaking head with acoustic mat to minimize noise if breaking
would be conducted and iii) complete noisy work as soon as possible to minimize
disturbance to the nearby residents.
ET confirmed with the Resident Site
Staff that unloading of fill material was conducted under Contract HK/2009/02
at WCR3 area (West of Wan Chai Ferry Pier) from 2300hrs on 19 July 2017 to
0540hrs on 20 July 2017. 1 no. of grab dredger was operated for the above
construction works. No construction activities or site operation was conducted
under Contract HK/2009/01 from 2300hrs on 19 July 2019 to 0700hrs on 20 July
2017.
According to the RSS site information,
unloading of fill material was conducted under Contract HK/2009/02 at WCR3 area
(West of Wan Chai Ferry Pier) from 2300hrs on 19 July 2017 to 0540hrs on 20
July 2017. 1 no. of grab dredger was operated for the above construction works
and relevant Construction Noise Permit GW-RS0348-17 was in place and noise
barrier with surface mass density of not less than 5kg/m2 was provided to the
power generating part of the grab dredger operated from 2300hrs on 19 July 2017
to 0540hrs on 20 July 2017. Meanwhile, no construction activities or site
operation was conducted under Contract HK/2009/01 from 2300hrs on 19 July 2019
to 0700hrs on 20 July 2017.
In view of the public concern, the
Contractor of HK/2009/02 was reminded to upkeep the site control system for
construction works carried out during restricted hours and night time for
Construction Noise Permit compliance and maintain regular maintenance of the
plant and equipment deployed to avoid potential nuisance to the nearby public.
ET confirmed with the Resident Site
Staff that breaking works and backfilling works were conducted under Contract
HK/2009/02 at the concerned location on 25 July 2017 afternoon.
Dust mitigation measures including water
spraying was implemented for the above construction activities on 25 July 2017
at the concerned location.
According to the RSS site information,
breaking works and backfilling works were conducted under Contract HK/2009/02
at the concerned location on 25 July 2017 afternoon while dust mitigation
measures including water spraying was implemented for the above construction
activities on 25 July 2017 at the concerned location. During Environmental Team
ad hoc inspection conducted on 26 July 2017, water spraying was found
insufficient to mitigate the extended area of breaking operation and
construction dust impact to surroundings public area was observed.
Subsequently, Contractor of HK/2009/02 was reminded to enhance the dust
suppression measure for the dust generating works.
In response to the observed
environmental concern, the Contractor of HK/2009/02 has strengthened the water
spraying coverage to all breaking operation area and haul road to minimize the
potential dust impact. Follow up inspection was conducted by Environmental Team
on 27 July 2017 and no further dust impact was observed.
Site Inspections and Audit
Contract no. HY/2009/18 – Central – Wan
Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Drainage works
·
Road works
·
Landscaping works
·
Maintenance works
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under
FEP-02/364/2009
·
Reinstatement of amenity area
·
Road and Drain works
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Rectification works for the defects for the end of maintenance period of
Observation Deck and Staircase ST-01.
·
Formwork, rebar fixing and concreting of HHR Flyover Approach Ramp.
·
Ground investigation works for Box Culvert O re-provision.
·
Advance works for removal of D-Wall panel adjacent to temporary
reclamation area
·
Remedial works for cross road ducts inside tunnel.
·
Partial lowering of temporary reclamation and removal of Strut S1 (West
corner) - TBC
·
Concreting of roadside barrier.
·
Dismantling of scaffolding inside tunnel.
·
Reinstatement of temporary access opening.
·
Breaking of D-Wall panel.
·
Backfilling.
·
Remedial works of tunnel wall, base slab and OHVD inside tunnel.
·
Sewage works at Wan Shing Street.
·
Repair of clay pipe inside WSD Pumping Station
·
Synthetic wood completion inside Works Area B
Contract no. HY/2009/15 – Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and
TPCWAW
·
Reinstatement work at the PRE Office car park area
·
Re-surfacing work at Hung Hing Road
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored piling and top soil removal works
·
Approach ramp structure Construction.
·
Bridge Construction
·
Pier 30-32 Cap Construction
·
Excavation / Construction of retaining wall
·
FEHD Metal Roof Construction and drainage works
·
Pre-bored H-piles for Approach Ramp Phase 2 Construction
·
Hing Fat Street road and drainage works
·
Oil Street drainage works
·
Installation of skin parapet on TB bridge
Contract no. HK/2012/08 – Wan Chai
Development Phase II – Central- Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D
·
Construction of Slip Road 1
·
Construction of drainage
·
Asphalt paving of A2 Road
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009
·
Tree protection works next to existing BGO
·
Drainage improvement works
·
Utility diversion works
·
Retaining wall works
·
ELS works
·
Construction works for subway extension
Contract no. HY/2011/08 – Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction of Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/E and Further
Environmental permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/B,
FEP-10/364/2009/B, FEP-11/364/2009/E and FEP-12/364/2009/D to implement the Environmental Monitoring and Audit (EM&A)
programme as stipulated in the EM&A Manual of the approved Environmental
Impact Assessment (EIA) Report for Wan Chai Development phase II and
Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and “Environmental Monitoring and Audit Requirements” under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/E, Further Environmental
Permit (FEP) nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/B,
FEP-10/364/2009/B, FEP-11/364/2009/E and FEP-12/364/2009/D during the period 27 June 2017 to 26 July 2017.
Section
1 Introduction –
details the scope and structure of the report.
Section
2 Project
Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance –
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements – summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results – summarizes the monitoring results obtained
in the reporting period.
Section
6 Compliance
Audit – summarizes the auditing of monitoring
results, all
exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects – summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Environmental Site Audit –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
– summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan Chai Bypass” and
“Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called
“the Project”) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide land
at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested east-west Connaught Road Central/Harcourt Road / Gloucester
Road Corridor (the Corridor) which is currently operating beyond its capacity.
The CWB will provide relief to the existing congestion along the Corridor and
cater for the anticipated growth of traffic on Hong Kong Island. Without the
CWB and its access roads, there will not be sufficient capacity to serve the
heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street Flyover to provide road
connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road system in the Wan Chai
North and Causeway Bay area;
·
Associated road lighting, road signing, traffic control and surveillance
system; and
·
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason
for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in
length |
DP2 |
Road P2 and other roads which are classified as
primary/district distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging
works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging
operation less than 100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter
more than 1,200 mm and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from
Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater
intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further
Environmental Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield
Depot – Advanced piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central
Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu
Street and Man Kwong Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works |
DP1,
DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East(CWB Tunnel) |
DP1 |
26
April 2011 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) |
DP1,DP3 |
13
July 2011 |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link |
DP1 |
24
March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai
Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel – Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587
1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912
3328 |
|
Chun Wo – Leader
Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Manager |
Mr. Simon Liu |
2162 9909 |
2587
1878 |
Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Environmental
Officer |
Mr.
Terry Tsang |
6683
9394 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827
9996 |
Project Manager |
Mr. Paul Yu |
3658 3085 |
|||
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint
Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570
8013 |
Deputy Project Manager |
Mr. William Luk |
9456 9819 |
|||
Site Agent |
Mr. David Lau |
3758 8879 |
|||
Deputy Site Agent |
Mr. Eric Fong |
6191 9337 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
3757 8218 |
|||
Assistant Environmental Officer |
Mr. James Chan |
3757 8217 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
3973
0803 |
|
Environmental Officer |
Mr. Chris Chan |
3973
0885 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2865 5229 |
Site Manager |
Mr. Y. Huo |
3557 6368 |
2566 2192 |
||
Contractor’s
Representative |
Mr. Rex Lau |
3557
6405 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6347 |
|||
China State- Build King JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N.
Lai |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Eddie
Chung |
9193
8871 |
|||
Site
Agent |
Mr. Keith
Tse |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Y.L.
Ho |
6050
4919 |
|||
China State |
Contractor under Contract no.HY/2010/08 |
Project
Director |
Chris
Leung |
9210
7116 |
2566
8061 |
Site
Agent |
Mr. Thomas
Lui |
3557
6407 |
|||
Environmental
Officer |
Mr. Gabriel
Wong |
3557
6466 |
|||
Environmental
Supervisor |
Mr. Desmond
Ho |
3557
6465 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Site Agent |
Mr. Colman Wong |
2823 1410 |
21406799 |
Environmental
Officer |
Mr.
Malcolm Leung |
3973 0850 |
|||
Environmental
Supervisor |
Ms. Christy So |
3973 1065 |
|||
Ramboll Environ Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics
Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882
3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. HY/2009/18 - Central - Wan
Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
·
Drainage works
·
Road works
·
Landscaping works
·
Maintenance works
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
Reinstatement of amenity area
·
Road and Drain works
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Rectification works for the defects recorded in the inspection for the
end of maintenance period of Observation Deck and Staircase ST-01
·
Rectification works for cracks/joints with water leakage inside OHVD
cells
·
Concreting of Hung Hing Road Flyover approach ramp bay 3 base slab
·
Rebar fixing and formwork at Hung Hing Road Flyover approach ramp bay 1
base slab
·
Rebar fixing and formwork at Hung Hing Road Flyover approach ramp bay 2
wall
·
Backfilling works up to +4.0mPD inside cofferdam
·
Remedial work for cross road duct
·
Rectification works against water leakage and remedial works against
concrete defects of the tunnel structure
·
Outstanding works inside tunnel
·
Concreting for roadside barrier
·
Removal of scaffolding and formwork inside tunnel
·
Removal of silo tank
·
Waterproofing and screeding works on top of tunnel
·
Removal of strut and removal of waling
·
Reinstatement of temporary access opening at Bay 7
·
Breaking of D-Wall panel
·
Backfilling work for the area to be handed over to MTR SCL 1123
·
Sewage works at Wan Shing Street
·
Rectification works for uneven road surface at Hung Hing Road
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and
TPCWAW
·
Reinstatement work at the PRE Office car park area
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored piling and top soil removal works
·
Approach ramp structure Construction.
·
Bridge Construction
·
Pier 30-32 Cap Construction
·
Excavation / Construction of retaining wall
·
FEHD Metal Roof Construction
·
Pre-bored H-piles for Approach Ramp Phase 2 Construction
·
Hing Fat Street road and drainage works
Contract no. HK/2012/08 – Wan Chai
Development Phase II – Central- Wan Chai Bypass at Wan Chai West under
FEP-12/364/2009/D
·
Construction of Slip Road 1
·
Construction of drainage
·
Asphalt paving of A2 Road
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009/B
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract no. HY/2011/08 –Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction of Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
2.4.4.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
·
Drainage works
·
Road works
·
Landscaping works
·
Maintenance works
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre – Tunnel Works under FEP-02/364/2009
·
Reinstatement of amenity area
·
Road and Drain works
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
·
Rectification works for the defects for the end of maintenance period of
Observation Deck and Staircase ST-01.
·
Formwork, rebar fixing and concreting of HHR Flyover Approach Ramp.
·
Ground investigation works for Box Culvert O re-provision.
·
Advance works for removal of D-Wall panel adjacent to temporary
reclamation area
·
Remedial works for cross road ducts inside tunnel.
·
Partial lowering of temporary reclamation and removal of Strut S1 (West
corner) - TBC
·
Concreting of roadside barrier.
·
Dismantling of scaffolding inside tunnel.
·
Reinstatement of temporary access opening.
·
Breaking of D-Wall panel.
·
Backfilling.
·
Remedial works of tunnel wall, base slab and OHVD inside tunnel.
·
Sewage works at Wan Shing Street.
·
Repair of clay pipe inside WSD Pumping Station
·
Synthetic wood completion inside Works Area B
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and
TPCWAW
·
Reinstatement work at the PRE Office car park area
·
Re-surfacing work at Hung Hing Road
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored piling and top soil removal works
·
Approach ramp structure Construction.
·
Bridge Construction
·
Pier 30-32 Cap Construction
·
Excavation / Construction of retaining wall
·
FEHD Metal Roof Construction and drainage works
·
Pre-bored H-piles for Approach Ramp Phase 2 Construction
·
Hing Fat Street road and drainage works
·
Oil Street drainage works
·
Installation of skin parapet on TB bridge
Contract no. HK/2012/08 – Wan Chai
Development Phase II – Central- Wan Chai Bypass at Wan Chai West under
FEP-12/364/2009/D
·
Construction of Slip Road 1
·
Construction of drainage
·
Asphalt paving of A2 Road
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009
·
Tree protection works next to existing BGO
·
Drainage improvement works
·
Utility diversion works
·
Retaining wall works
·
ELS works
·
Construction works for subway extension
Contract no. HY/2011/08 – Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction of Ventilation Buildings, inclusive of Administration Building,
Central Ventilation Building, East Ventilation Shaft/Building, West Ventilation
Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of the current status
on licences and/or permits on environmental protection pertinent to the Project
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Superseded |
Environmental Permit |
EP-364/2009/C |
11 Jul 2014 |
Superseded |
Environmental Permit |
EP-364/2009/D |
24 Nov 2015 |
Superseded |
Environmental Permit |
EP-364/2009/E |
22 Dec 2016 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Surrendered |
Further
Environmental Permit |
FEP-06/356/2009 |
5 March 2013 |
Valid |
Further
Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Surrendered |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Superseded |
|
Further Environmental Permit |
24 Nov 2015 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Surrendered |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
Superseded |
Further Environmental Permit |
FEP-11/364/2009/E |
22 Dec 2016 |
Valid |
Further Environmental Permit |
FEP-12/364/2009/D |
01 Aug 2016 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 – Central – Wan Chai
Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.
Contract no. 04/HY/2006 – Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP-04/HY/2006 was
surrendered by the Contractor on 11 February 2011.
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
3.1.5. The construction works was completed, and the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.2 and Table 3.3.
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Discharge License |
WT00024952-2016 |
06 Jul 2016 |
31 Jul 2021 |
Valid |
WT00021138-2015 |
17 Mar 2014 |
31 Mar 2020 |
Valid |
|
Billing account under
Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table
3.3 Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of
Submission |
Condition 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May
2011 |
Condition 2.6 |
Environmental Management Organization Chart |
18 May
2011 |
Condition 1.12 |
Commencement Date of Works |
20 Jun
2011 |
Condition 2.9 |
Noise Management Plan |
10 Jun 2011 |
Condition 2.11 |
Landscape Plan (Rev.4) |
8 July 2015 |
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.7.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.4 and Table 3.5.
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02
Permits and/or Licenses |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar
2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb
2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling
equipment |
GW-RS0289-17 |
31 Mar 2017 |
02 Apr 2017 to 02 Jul /2017 |
Expired |
GW-RS0314-17 |
07 Apr 2017 |
11 Apr 2017 to 04 Oct 2017 |
Valid |
|
GW-RS0338-17 |
13 Apr 2017 |
28 May 2017 to 27 Aug 2017 |
Valid |
|
GW-RS0334-17 |
18 Apr 2017 |
21 Apr 2017 to 06 Oct 2017 |
Cancelled |
|
GW-RS0348-17 |
18 Apr 2017 |
25 Apr 2017 to 24 Oct 2017 |
Valid |
|
GW-RS0527-17 |
16 Jun 2017 |
17 Jun 2017 to 20 Sep 2017 |
Valid |
|
GW-RS0535-17 |
16 Jun 2017 |
17 Jun 2017 to 20 Sep 2017 |
Valid |
|
GW-RS0584-17 |
19Jul 2017 |
20 Jul 2017 to 19 Oct 2017 |
Valid |
|
Water
Discharge License |
WT00022295-2015 |
12 Aug 2015 |
31 July 2020 |
Valid |
WT00025276-2016 |
19 Sep 2016 |
31 July 2021 |
Valid |
|
Billing
Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table
3.5 Summary of submission status
under FEP-01/364/2009
EP Condition |
Submission |
Date
of
Submission |
Condition 2.7
and 2.8 |
Works
Schedule and Location Plan |
14 Jun 2011 |
Condition 2.6 |
Environmental
Management Organization Chart |
14 Jun 2011 |
Condition 1.12 |
Commencement
Date of Works |
21 Jun 2011 |
Condition
2.11 |
Landscape Plan (Revision B) |
20 Nov
2012 |
Condition 2.9 |
Noise Management Plan (Revision B) |
13 Jan
2012 |
Contract no. HY/2009/18 – Central – Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
3.1.8.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.6 and Table
3.7.
Table
3.6 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/18
Permit / Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-05/364/2009/A |
|