Contract No:
HK/2015/01 Wanchai
Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing
Work (Stage 3) Environmental Permit no. EP-364/2009/E, Further
Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/D, FEP-09/364/2009/B,
FEP-10/364/2009/B and FEP-11/364/2009/E, FEP-12/364/2009/D Monthly Environmental Monitoring &
Audit Report
- March 2018 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
April 2018 |
2.2 Scope of the Project and Site
Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact
Personnel
3 status of regulatory
compliance
3.1 Status of Environmental Licensing and
Permitting under the Project
5.2 Real Time Noise Monitoring Results
5.3 Air Quality Monitoring Results
6.3 Review of the Reasons for and the
Implications of Non-compliance.
6.4 Summary of action taken in the event of
and follow-up on non-compliance.
7 Cumulative Construction
Impact due to the Concurrent Projects
9 Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details of Individual Contracts
under the Project
Table 2.3 Contact Details of Key
Personnel
Table 3.1 Summary of the current status
on licences and/or permits on environmental
protection pertinent to the Project
Table 3.2 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.3 Summary of submission status
under FEP-02/364/2009
Table 3.4 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.5 Summary of submission status
under FEP-01/364/2009
Table 3.6 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.7 Summary of submission status
under FEP-05/364/2009/A
Table 3.8 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.9 Summary of submission status
under FEP-06/364/2009/A
Table 3.10 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.11
Summary of submission status under FEP-07/364/2009/D
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.13 Summary
of submission status under FEP-12/364/2009/D
Table 3.14 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.15 Summary of submission status under
FEP-10/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HY/2011/08
Table 3.17 Summary of submission status under FEP-11/364/2009/E
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring
Stations
Table 4.3 Air Quality Monitoring Stations
Table 5.1 Noise Monitoring
Stations for Contract no. HY/2009/18
Table 5.2 Noise Monitoring
Station for Contract no HK/2009/01 and HK/2009/02
Table 5.3 Noise Monitoring
Stations for Contract no. HY/2009/15
Table 5.4 Noise Monitoring
Stations for Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table 5.6 Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Real Time Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.9 Air Quality Monitoring
Station for Contract no. HY/2009/18
Table 5.10 Air Quality Monitoring Station
for Contract no. HK/2009/01
Table 5.11 Air Quality Monitoring Station
for Contract no. HK/2009/02
Table 5.12 Air Quality Monitoring Stations
for Contract no. HY/2009/15
Table 5.13 Air Quality
Monitoring Station for Contract no. HY/2009/19
Table 5.14 Air Quality
Monitoring Station for Contract no. HK/2012/08
Table 5.15 Air Quality Monitoring Stations for Contract no. HY/2010/08
Table 5.16 Air Quality Monitoring
Stations for Contract no. HY/2011/08
Table 5.17 Details of Waste Disposal
for Contract no. HK/2009/01
Table 5.18 Details of Waste
Disposal for Contract no. HK/2009/02
Table 5.19 Details of Waste
Disposal for Contract no. HY/2009/18
Table 5.20 Details of Waste
Disposal for Contract no. HY/2009/15
Table 5.21 Details of Waste Disposal
for Contract no. HY/2009/19
Table 5.22 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.23 Details of Waste Disposal
for Contract no. HY/2010/08
Table 5.24 Details of Waste Disposal for Contract
no. HY/2011/08
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/15 (NOT USED)
Table 8.2 Summary
of Environmental Inspections for Contract no. HY/2009/18 (NOT USED)
Table 8.3 Summary of
Environmental Inspections for Contract no. HY/2009/19
Table 8.4 Summary of
Environmental Inspections for Contract no. HK/2009/01 (NOT USED)
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02 (NOT USED)
Table 8.6 Summary of
Environmental Inspections for Contract no. HK/2012/08
Table 8.7 Summary of Environmental
Inspections for Contract no. HY/2010/08
Table 8.8 Summary of
Environmental Inspections for Contract no. HY/2011/08) (NOT USED)
Table 9.1 Cumulative Statistics on
Complaints
Table 9.2 Cumulative Statistics on
Successful Prosecutions
Table 10.1 Summary of Key
Construction Activities of Individual Contract(s) to be
commenced in Coming Reporting period
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix
5.1 Monitoring Schedule for Reporting period and Coming month
Appendix
5.2 Noise Monitoring Results and Graphical Presentations
Appendix
5.3 Air Quality Monitoring Results and
Graphical Presentations
Appendix 5.4 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of
Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under
FEP-05/364/2009/A
¡P
Maintenance
works
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under
FEP-02/364/2009
¡P
Reinstatement
of amenity area
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Joint
Inspection with ASD, AECOM and JV for completion of rectification work within
the rooms under Staircases
¡P
Water
test to the Types 3 and 4 Covered Walkway at West Wing
¡P
New PMMA
for the replacement of 8 nos. of damaged PMMA panels
¡P
Preparation
for raising the vent shaft, water meters chambers and multi-part covers of P7,
P8 and P9
¡P
Drainage
work
¡P
Excavation
for relocation of temporary fire hydrant PH2582
¡P
Jointed
inspection with HKE, AECOM and JV on the new pillar box work
¡P
Remedial
works against water leakage inside OHVD cells
¡P
Backfilling
behind seawall block
¡P
Steel
fixing of Culvert O bay 15A top slab and wall
¡P
Base slab
of Culvert O Bay 16A
¡P
Pipe
piling work for ELS of Culvert O
¡P
Remedial
works against water leakage inside OHVD cells
¡P
Raising
of CMS draw pits and caisson wall units access opening covers
¡P
Installation
of surface drain cover
¡P
All
backfilling works at surface drain trench
¡P
Remedial
works for 0.5T rock armor
¡P
Sewage
works at Wan Shing Street
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/D
¡P
Approach
ramp structure Construction.
¡P
Bridge
Construction & installation of enclosure.
¡P
Retaining
wall construction.
¡P
FEHD depot
re-provision works.
¡P
Oil
street drainage works.
¡P
Installation
of skin parapet on TB bridge at Pier 15-17.
¡P
Landscape
deck, column & pile cap foundation works.
¡P
Watson
Road Water mains laying works.
¡P
Hing Fat
Street road and drainage works.
¡P
IEC TD
bridge parapet installation.
Contract no.
HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan
Chai West under FEP-12/364/2009/D
¡P
Construction
of Slip Road 1
¡P
Construction
of drainage
¡P
Asphalt
paving
¡P
Construction
of roundabout
Contract no.
HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under
FEP-10/364/2009/B
¡P
Tree
protection works next to existing BGO,
¡P
Drainage improvement
works,
¡P
Utility
diversion works,
¡P
Retaining
wall works
¡P
ELS
works,
¡P
Construction
works for subway extension
Contract no.
HY/2011/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
¡P
Construction
of Ventilation Buildings, inclusive of Administration Building, Central
Ventilation Building, East Ventilation Shaft/Building, West Ventilation
Building
¡P
Application
of Thermal Barrier inside the Tunnel, asphalt pavement
¡P
Construction
of Tunnel Thermal Barrier
¡P
Installation
of Electricals and Mechanicals
¡P
Installation
of Tunnel Features
Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of Summons
and Successful Prosecutions
An ICC complaint (Case Ref:
2-4495970766, lodged at 0955hrs on 12 March 2018) was referred to the ET on 27
March 2018. The ICC hotline operator reported that a public complaint was
referred by the Police Force regarding noise emanation from road construction
works at North Point section Island East Corridor (IEC) near 19 Wharf Road at
around 0920hrs on 12 March 2018. Further information regarding the same event
was received via ICC hotline (Case ref: 2-449606553, lodged at 1004hrs on 12
March 2018) was referred to the ET on 27 March 2018. The complainant further
reported that noise was emanated from road construction works on Island Eastern
Corridor (IEC) near Yu Lee Mo Fan Memorial School. Temporary noise barrier
observed to be transparent in nature was speculated to be ineffective; and it
was observed that only 3 out of the 6 units of temporary noise barrier are
installed. The complainant suggested that additional 6 sections of noise
barrier shall be installed. The noise emanation was started from 0800hrs and he
is a resident at 18 Wharf Road and his rest was adversely affected by the concerned
noise emanation. He has contacted the Environmental Protection Department and
the Police Force regarding the noise emanation. The Environmental Protection
Department has replied that construction works conducted after 0700hrs does not
violate statutory requirement while the Police Force has created an ICC
complaint case file (2-4495970766) for follow up.
ET confirmed with the Resident Site
Staff that Concrete breaking works on IEC Eastbound near Pier F8 and Pier F9
was conducted under Contract HY/2009/19 from 0900hrs to 1000hrs on 12 March
2018. Noise mitigation measure including wrapping of breaking head with
acoustic material was implemented. Enhancement measures including provision of
2.5m high temporary noise barrier were subsequent implemented on 12 March 2018.
According to RSS confirmed information,
concrete breaking works on IEC Eastbound near Pier F8 and Pier F9 was conducted
under Contract HY/2009/19 from 0900hrs to 1000hrs on 12 March 2018. Noise
mitigation measure including wrapping of breaking head with acoustic material
was implemented. Enhancement measures including provision of 2.5m high
temporary noise barrier were subsequent implemented on 12 March 2018.
Based on review on relevant site record,
noise impact associated with the breaking works on IECL opposite to the
concerned location was observed across March 2018 and project related
exceedances were recorded at nearby noise monitoring station at YLMF Memorial
School across March 2018. Upon identificaion of the project related exceedance
at YLMF memorial school noise monitoring station, the Contractor is requested
to adopt remedial and enhancement measures to minimize the noise emanation and
avoid noise impact to the nearby sensitive receivers.
According to ET follow up checking, the
following enahncement measures were proposed and implemented by the Contractor
by 16 March 2018 including provide additional temporary noise barrier and
repair damaged or incomplete temporary noise barrier installed for the breaking
works, provide additional acoustics screen to the breaking tip in addition to
temporary noise barrier installed, provide covering of breaker tip with
acoustic material for noise reduction and conduct breaking works intermittently.
Nevertheless, subsequent to 16 March
2018, it was observed at times that the above mitigation measures were not
fully implemented by the Contractor throughout the remaining breaking works
period. Upon identification of deficiency in mitigation measures, the
Contractor has been requested to rectify any deficiency obserbed and ensure
relevant noise mitigation measures are implemented and the observed
deficiencies are rectified prior to resumption of the concerned impact
associated works. According to Contractor information, the concerned breaking
works have been completed by 26 March 2018.
In view of the public concern and the
identified noise concern, the Contractor of HY/2009/19 was reminded that, shall
future breaking works be required to be conducted on IECL (at works area
located at the East of the noise enclosure), noise mitigation measure including
but not limit to provision of temporary noise barrier with adequate height and
extend and additional noise screen shall be proposed for ET/IEC review and
confirmation prior to conducting the corresponding works to minimize the
potential impact to the surroundings. The Contractor is also advised to review
the adopt construction method with consideration on alterative PME with reduced
noise emanation to minimize the potential noise impact to the surroundings.
Site Inspections and Audit
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Maintenance
works
Contract
no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
¡P
Reinstatement
of amenity area
Contract
no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Reprovisioned
Wan Chai Ferry Pier
¡P
Rectification
work for the leakage of covered walkway at Expo Drive East
¡P
Remedial
works against water leakage inside OHVD cells.
¡P
Partial
removal of TWCR4 to +2.5mPD
¡P
Backfilling
works
¡P
Construction
of box culvert ¡¥O¡¦
¡P
Temporary
works for construction of box culvert ¡¥O¡¦
¡P
Remedial
works against water leakage inside OHVD cells.
¡P
Remedial
and Outstanding Works inside Tunnel
¡P
Remedial
works for damaged caisson seawall under C2
¡P
Remedial works
for damaged caisson seawall and CMS under C1
¡P
Modification
of levels of caisson seawall access, manhole covers and CMS draw pit covers.
¡P
Construction
of surface channel at potion 5
¡P
Remedial
work for 0.5 ton armour at WCR3
¡P
Sewage
works at Wan Shing Street.
Contract
no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/D
¡P
Approach
ramp structure Construction.
¡P
Bridge
Construction & installation of enclosure.
¡P
Retaining
wall construction.
¡P
FEHD
re-provision works.
¡P
Oil
Street drainage works.
¡P
Installation
of skin parapet on TB bridge at Pier 15-17.
¡P
Landscape
deck, column & pile cap foundation works.
¡P
Watson
Road Water mains laying works.
¡P
EVA at
EVB.
¡P
Hing Fat
Street road and drainage works.
¡P
IEC TD
bridge parapet installation.
¡P
Watson
Road Cul-de-sac construction.
Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan
Chai Bypass at Wan Chai West under FEP-12/364/2009/D
¡P
Construction
of Slip Road 1
¡P
Construction
of drainage
¡P
Asphalt
paving
¡P
Construction
of roundabout
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009
¡P
Tree
protection works next to existing BGO,
¡P
Drainage
improvement works,
¡P
Utility
diversion works,
¡P
Retaining
wall works
¡P
ELS
works,
¡P
Construction
works for subway extension
Contract no. HY/2011/08 ¡V Central - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
¡P
Construction
of Ventilation Buildings, inclusive of Administration Building, Central
Ventilation Building, East Ventilation Shaft/Building, West Ventilation
Building
¡P
Application
of Thermal Barrier inside the Tunnel, asphalt pavement
¡P
Installation
of Electricals and Mechanicals
¡P
Installation
of Tunnel Features
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/E and
Further Environmental permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B,
FEP-11/364/2009/E and FEP-12/364/2009/D to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit
Requirements¡¨ under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/E, Further Environmental
Permit (FEP) nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B,
FEP-11/364/2009/E and FEP-12/364/2009/D during the
period 27 February 2018 to 26 March 2018.
Section 1 Introduction ¡V details the scope
and structure of the report.
Section 2 Project
Background
¡V summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance ¡V summarizes the
status of valid Environmental Permits / Licenses during the reporting period.
Section 4 Monitoring
Requirements
¡V summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section 5 Monitoring
Results
¡V summarizes the monitoring results obtained in the reporting period.
Section 6 Compliance
Audit
¡V summarizes the auditing of monitoring results, all
exceedances
environmental parameters.
Section 7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Environmental Site Audit ¡V summarizes the
findings of weekly site inspections undertaken within the reporting period,
with a review of any
relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of summons and Prosecution
¡V
summarizes the cumulative statistics on complaints, notification
of summons and prosecution
Section 10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and
¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called
¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested east-west Connaught Road Central/Harcourt Road / Gloucester
Road Corridor (the Corridor) which is currently operating beyond its capacity.
The CWB will provide relief to the existing congestion along the Corridor and
cater for the anticipated growth of traffic on Hong Kong Island. Without the
CWB and its access roads, there will not be sufficient capacity to serve the
heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central ¡V Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
¡P
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
¡P
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
¡P
Tunnel
control buildings and ventilation buildings;
¡P
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
Causeway Bay area;
¡P
Associated
road lighting, road signing, traffic control and surveillance system; and
¡P
Other
associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further
Environmental Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling
works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre ¡V Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1,DP3 |
13 July 2011 (Completed) |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai Bypass at Wan Chai
West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel ¡V Tunnel (Slip Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3328 |
|
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Manager |
Mr. Simon Liu |
9304 8355 |
2587 1878 |
Environmental
Officer |
Mr. Terry
Tsang |
6683 9394 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827 9996 |
Project Manager |
Mr. Paul Yu |
3658 3085 |
|||
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570 8013 |
Site Agent |
Mr. William Luk |
9456 9819 |
|||
Deputy Site Agent |
Mr. Andy Chan |
3758 8879 |
|||
Environmental Officer |
Mr. M.H. Isa |
3757 8218 |
|||
Assistant Environmental Officer |
Mr. James Chan |
3757 8217 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
3973 0803 |
|
Construction Manager |
Mr. Darren Grant |
3971 1460 |
|||
Environmental
Supervisor |
Ms. Penny Yiu |
3973 1065 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2865 5229 |
Site Agent |
Mr. Patrick Ho |
3557 6405 |
2566 2192 |
||
Environmental Officer |
Mr. Desmond Ho |
3557 6347 |
|||
China State- Build King JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N. Lai |
9137 1811 |
2877 1522 |
Site Agent |
Mr. George
Cheung |
9268 1918 |
|||
Environmental
Officer |
Mr. James MA |
9130 9549 |
|||
China State |
Contractor under Contract no. HY/2010/08 |
Project
Director |
Chris
Leung |
9210 7116 |
2566 8061 |
Site Agent |
Mr. Thomas Lui |
3557 6407 |
|||
Environmental
Officer |
Mr. Gabriel
Wong |
3557 6466 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Site Agent |
Mr. Colman Wong |
2823
1410 |
21406799 |
Environmental
Officer |
Mr. Chris
Chan |
3973 0850 |
|||
Environmental
Supervisor |
Ms. Penny Yiu |
3973 1065 |
|||
Ramboll Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting period, the principal work
activities of individual contracts are included as follows:
Contract no. HY/2009/18 - Central - Wan
Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
¡P
Maintenance
works
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre - Tunnel Works under FEP-02/364/2009
¡P
Reinstatement
of amenity area
Contract
no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai
East (CWB Tunnel) under FEP-01/364/2009
¡P
Joint
Inspection with ASD, AECOM and JV for completion of rectification work within
the rooms under Staircases
¡P
Water
test to the Types 3 and 4 Covered Walkway at West Wing
¡P
New PMMA
for the replacement of 8 nos. of damaged PMMA panels
¡P
Preparation
for raising the vent shaft, water meters chambers and multi-part covers of P7,
P8 and P9
¡P
Drainage
work
¡P
Excavation
for relocation of temporary fire hydrant PH2582
¡P
Jointed
inspection with HKE, AECOM and JV on the new pillar box work
¡P
Remedial
works against water leakage inside OHVD cells
¡P
Backfilling
behind seawall block
¡P
Steel
fixing of Culvert O bay 15A top slab and wall
¡P
Base slab
of Culvert O Bay 16A
¡P
Pipe
piling work for ELS of Culvert O
¡P
Remedial
works against water leakage inside OHVD cells
¡P
Raising
of CMS draw pits and caisson wall units access opening covers
¡P
Installation
of surface drain cover
¡P
All
backfilling works at surface drain trench
¡P
Remedial
works for 0.5T rock armor
¡P
Sewage
works at Wan Shing Street
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
¡P
Approach
ramp structure Construction.
¡P
Bridge
Construction & installation of enclosure.
¡P
Retaining
wall construction.
¡P
FEHD depot
re-provision works.
¡P
Oil
street drainage works.
¡P
Installation
of skin parapet on TB bridge at Pier 15-17.
¡P
Landscape
deck, column & pile cap foundation works.
¡P
Watson
Road Water mains laying works.
¡P
EVA at
EVB.
¡P
Hing Fat
Street road and drainage works.
¡P
IEC TD
bridge parapet installation.
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-12/364/2009/D
¡P
Construction
of Slip Road 1
¡P
Construction
of drainage
¡P
Asphalt
paving
¡P
Construction
of roundabout
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009/B
¡P
Tree
protection works next to existing BGO,
¡P
Drainage
improvement works,
¡P
Utility
diversion works,
¡P
Retaining
wall works
¡P
ELS
works,
¡P
Construction
works for subway extension
Contract no. HY/2011/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
¡P
Construction
of Ventilation Buildings, inclusive of Administration Building, Central
Ventilation Building, East Ventilation Shaft/Building, West Ventilation
Building
¡P
Application
of Thermal Barrier inside the Tunnel, asphalt pavement
¡P
Construction
of Tunnel Thermal Barrier
¡P
Installation
of Electricals and Mechanicals
¡P
Installation
of Tunnel Features
2.4.4.
In coming reporting period, the principal
work activities of individual contracts are anticipated as follows:
¡P
Maintenance
works
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
¡P
Reinstatement
of amenity area
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P
Provisioned
Wan Chai Ferry Pier
¡P
Rectification
work for the leakage of covered walkway at Expo Drive East
¡P
Remedial
works against water leakage inside OHVD cells.
¡P
Partial
removal of TWCR4 to +2.5mPD
¡P
Backfilling
works
¡P
Construction
of box culvert ¡¥O¡¦
¡P
Temporary
works for construction of box culvert ¡¥O¡¦
¡P
Remedial
works against water leakage inside OHVD cells.
¡P
Remedial
and Outstanding Works inside Tunnel
¡P
Remedial
works for damaged caisson seawall under C2
¡P
Remedial
works for damaged caisson seawall and CMS under C1
¡P
Modification
of levels of caisson seawall access, manhole covers and CMS draw pit covers.
¡P
Construction
of surface channel at potion 5
¡P
Remedial
work for 0.5 ton armour at WCR3
¡P
Sewage
works at Wan Shing Street.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/D
¡P
Approach
ramp structure Construction.
¡P
Bridge
Construction & installation of enclosure.
¡P
Retaining
wall construction.
¡P
FEHD
re-provision works.
¡P
Oil
Street drainage works.
¡P
Installation
of skin parapet on TB bridge at Pier 15-17.
¡P
Landscape
deck, column & pile cap foundation works.
¡P
Watson
Road Water mains laying works.
¡P
EVA at
EVB.
¡P
Hing Fat
Street road and drainage works.
¡P
IEC TD
bridge parapet installation.
¡P
Watson Road
Cul-de-sac construction.
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-12/364/2009/D
¡P
Construction
of Slip Road 1
¡P
Construction
of drainage
¡P
Asphalt
paving
¡P
Construction
of roundabout
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009
¡P
Tree
protection works next to existing BGO,
¡P
Drainage
improvement works,
¡P
Utility
diversion works,
¡P
Retaining
wall works
¡P
ELS
works,
¡P
Construction
works for subway extension
Contract no. HY/2011/08 ¡V Central - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
¡P
Construction
of Ventilation Buildings, inclusive of Administration Building, Central
Ventilation Building, East Ventilation Shaft/Building, West Ventilation
Building
¡P
Application
of Thermal Barrier inside the Tunnel, asphalt pavement
¡P
Installation
of Electricals and Mechanicals
¡P
Installation
of Tunnel Features
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of the current status
on licences and/or permits on environmental protection pertinent to the Project
Permits and/or Licenses |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009/E |
22 Dec
2016 |
Valid |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Surrendered |
Further Environmental Permit |
FEP-06/356/2009 |
5
March 2013 |
Valid |
Further Environmental Permit |
FEP-07/356/2009 |
26
July 2013 |
Valid |
Further
Environmental Permit |
24 Mar
2010 |
Valid |
|
Further
Environmental Permit |
21 Apr 2010 |
Valid |
|
Further
Environmental Permit |
12 July 2010 |
Surrendered
|
|
Further
Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further
Environmental Permit |
15 Nov 2010 |
Valid |
|
Further
Environmental Permit |
22 Nov 2010 |
Valid |
|
Further
Environmental Permit |
24 Nov 2015 |
Valid |
|
Further
Environmental Permit |
15 June 2012 |
Surrendered |
|
Further
Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further
Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further
Environmental Permit |
FEP-11/364/2009/E |
22 Dec
2016 |
Valid |
Further
Environmental Permit |
FEP-12/364/2009/D |
01
Aug 2016 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai
Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.
Contract no. 04/HY/2006 ¡V Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP-04/HY/2006 was
surrendered by the Contractor on 11 February 2011.
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
3.1.5. The construction works was completed, and the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
Contract no. HY/2009/15 ¡V Central-Wanchai
Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
3.1.6. The Construction works under HY/2009/15 was confirm completed by the RSS
from 27 October 2017 onwards. The weekly site audit inspection and the
associated monitoring station for HY/2009/15 were temporally suspended from 27
October 2017 onwards.
Contract no.
HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
3.1.7.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.2 and Table 3.3.
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits
and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Discharge License |
WT00024952-2016 |
06 Jul 2016 |
31 Jul 2021 |
Valid |
WT00021138-2015 |
17 Mar 2014 |
31 Mar 2020 |
Valid |
|
Billing account under
Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table
3.3 Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May 2011 |
Condition 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Condition 1.12 |
Commencement Date of Works |
20 Jun 2011 |
Condition 2.9 |
Noise Management Plan |
10 Jun 2011 |
Condition 2.11 |
Landscape Plan (Rev.5) |
25 January 2018 |
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.8.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.4 and Table 3.5.
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02
Permits and/or Licenses |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of
Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling equipment |
GW-RS0756-17 |
04 Sep 2017 |
07 Sep 2017 to 28 Feb 2018 |
Expired |
GW-RS0843-17 |
28 Sep 2017 |
07 Oct 2017 to 25 Mar 2018 |
Expired |
|
GW-RS0869-17 |
10 Oct 2017 |
15 Oct 2017 to 11 Mar 2018 |
Expired |
|
GW-RS0884-17 |
12 Oct 2017 |
24 Oct 2017 to 23 Apr 2018 |
Valid |
|
GW-RS0885-17 |
12 Oct 2017 |
14 Oct 2017 to 12 Apr 2018 |
Cancelled |
|
GW-RS0159-18 |
22 Feb 2018 |
1 Mar 2018 to 31 Aug 2018 |
Valid |
|
GW-RS0209-18 |
22 Feb 2018 |
16 Mar 2018 to 14 Sep 2018 |
Valid |
|
Water Discharge
License |
WT00022295-2015 |
12 Aug 2015 |
31 July 2020 |
Valid |
WT00025276-2016 |
19 Sep 2016 |
31 July 2021 |
Valid |
|
Billing Account
under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Billing Account
under Waste Disposal Ordinance (Marine) |
7011496 |
6 Oct 2010 |
N/A |
Valid |
Registration as
Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as
Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table
3.5 Summary of submission status
under FEP-01/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.7 and 2.8 |
Works
Schedule and Location Plan |
14 Jun 2011 |
Condition 2.6 |
Environmental
Management Organization Chart |
14 Jun 2011 |
Condition 1.12 |
Commencement
Date of Works |
21 Jun 2011 |
Condition
2.11 |
Landscape Plan (Revision B) |
20 Nov 2012 |
Condition 2.9 |
Noise Management Plan (Revision B) |
13 Jan 2012 |
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange under FEP-05/364/2009/A
3.1.9.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.6 and Table
3.7.
Table
3.6 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/18
Permit /
License / Notification / Approval |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
N/A |
Valid |
Notification
of Works Under APCO |
322293 |
07 Oct 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling
equipment |
GW-RS0241-18 |
27 Mar 2018 |
29 Mar 2018
to 27 Sep 2018 |
Valid |
¡¥Discharge
Licenses |
WT00024255-2016 |
18 May 2016 |
31 Jan 2021 |
Valid |
Registration
as a Chemical Waste Producer |
WPN: 8335-121-L1048-04 |
17 Dec 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance (Land) |
Account No.: 7011587 |
11 Oct 2010 |
N/A |
Valid |
Table 3.7 Summary of submission status
under FEP-05/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan (Rev. 6) |
19 May 2014 |
Contract
no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
3.1.10.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.8 and Table 3.9.
Table
3.8 Cumulative Summary
of Valid Licences and Permits under Contract no. HY/2009/15
Permits
and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Construction Noise Permit |
N/A |
N/A |
N/A |
N/A |
Water Discharge License (Discharge at TS1) |
WT00024874-2016 |
20 Jul 2016 |
20 Jul 2016 to 31 Mar 2021 |
Valid |
Table
3.9 Summary of
submission status under FEP-06/364/2009/A
EP
Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction
Companies |
11 Mar 2011 |
Amendment for Management Organization of Main
Construction Companies |
16 May 2011 |
|
Condition 2.7 |
Works Schedule |
15 Mar 2011 |