Contract No:
HK/2015/01 Wanchai
Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing
Work (Stage 3) Environmental Permit no. EP-364/2009/E, Further
Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/D, FEP-09/364/2009/B,
FEP-10/364/2009/B and FEP-11/364/2009/E, FEP-12/364/2009/D Monthly Environmental Monitoring &
Audit Report
- MAy 2018 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
June 2018 |
2.2 Scope of the Project and Site
Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact
Personnel
3 status of regulatory
compliance
3.1 Status of Environmental Licensing and
Permitting under the Project
5.2 Real Time Noise Monitoring Results
5.3 Air Quality Monitoring Results
6.3 Review of the Reasons for and the
Implications of Non-compliance.
6.4 Summary of action taken in the event of
and follow-up on non-compliance.
7 Cumulative Construction
Impact due to the Concurrent Projects
9 Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details of Individual Contracts
under the Project
Table 2.3 Contact Details of Key
Personnel
Table 3.1 Summary of the current status
on licences and/or permits on environmental
protection pertinent to the Project
Table 3.2 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.3 Summary of submission status
under FEP-02/364/2009
Table 3.4 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.5 Summary of submission status
under FEP-01/364/2009
Table 3.6 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.7 Summary of submission status
under FEP-05/364/2009/A
Table 3.8 Cumulative Summary of Valid
Licences and Permits under Contract no.
Table 3.9 Summary of submission status
under FEP-06/364/2009/A
Table 3.10 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.11
Summary of submission status under FEP-07/364/2009/D
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.13 Summary
of submission status under FEP-12/364/2009/D
Table 3.14 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.15 Summary of submission status under
FEP-10/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HY/2011/08
Table 3.17 Summary of submission status under FEP-11/364/2009/E
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring
Stations
Table 4.3 Air Quality Monitoring Stations
Table 5.1 Noise Monitoring
Stations for Contract no. HY/2009/18 (NOT USED)
Table 5.2 Noise Monitoring
Station for Contract no HK/2009/01 and HK/2009/02
Table 5.3 Noise Monitoring
Stations for Contract no. HY/2009/15
Table 5.4 Noise Monitoring
Stations for Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table 5.6 Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Real Time Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.9 Air Quality Monitoring
Station for Contract no. HY/2009/18 (NOT USED)
Table 5.10 Air Quality Monitoring Station
for Contract no. HK/2009/01
Table 5.11 Air Quality Monitoring Station
for Contract no. HK/2009/02
Table 5.12 Air Quality Monitoring Stations
for Contract no. HY/2009/15
Table 5.13 Air Quality
Monitoring Station for Contract no. HY/2009/19
Table 5.14 Air Quality
Monitoring Station for Contract no. HK/2012/08
Table 5.15 Air Quality Monitoring Stations for Contract no. HY/2010/08
Table 5.16 Air Quality Monitoring
Stations for Contract no. HY/2011/08
Table 5.17 Details of Waste Disposal
for Contract no. HK/2009/01
Table 5.18 Details of Waste
Disposal for Contract no. HK/2009/02
Table 5.19 Details of Waste
Disposal for Contract no. HY/2009/18
Table 5.20 Details of Waste
Disposal for Contract no. HY/2009/15
Table 5.21 Details of Waste Disposal
for Contract no. HY/2009/19
Table 5.22 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.23 Details of Waste Disposal for
Contract no. HY/2010/08
Table 5.24 Details of Waste Disposal for Contract
no. HY/2011/08
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/15 (NOT USED)
Table 8.2 Summary
of Environmental Inspections for Contract no. HY/2009/18 (NOT USED)
Table 8.3 Summary of
Environmental Inspections for Contract no. HY/2009/19
Table 8.4 Summary of
Environmental Inspections for Contract no. HK/2009/01 (NOT USED)
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.6 Summary of
Environmental Inspections for Contract no. HK/2012/08
Table 8.7 Summary of Environmental
Inspections for Contract no. HY/2010/08
Table 8.8 Summary of
Environmental Inspections for Contract no. HY/2011/08)NOT USED)
Table 9.1 Cumulative Statistics on
Complaints
Table 9.2 Cumulative Statistics on
Successful Prosecutions
Table 10.1 Summary of Key
Construction Activities of Individual Contract(s) to be
commenced
in Coming Reporting period
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix
5.1 Monitoring Schedule for Reporting period and Coming month
Appendix
5.2 Noise Monitoring Results and Graphical Presentations
Appendix
5.3 Air Quality Monitoring Results and
Graphical Presentations
Appendix 5.4 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of
Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under
FEP-02/364/2009
·
Reinstatement
of amenity area
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
New PMMA
for the replacement of 8 nos. of damaged PMMA panels
·
Preparation
for raising the vent shaft, water meters chambers and multi-part covers of P7,
P8 and P9
·
Drainage
work
·
Remedial
works against water leakage and CCTV inside tunnel
·
Installation
of breakwater
·
Backfilling
behind seawall block
·
Pipe
piling work for ELS of Box Culvert O Bay 13, 14
·
Installation
of ELS for Box Culvert O Bay 14A and 17A
·
Backfilling
works for Box Culvert O Bay 15A and 16A
·
Demolition
of D-Wall for construction of Box Culvert O
·
Fabrication
of precast units for Box Culvert O
·
Remedial
works against water leakage inside OHVD cells
·
Temporary
drainage system for stock piling at Portion 5
·
Construction
of manhole no. MH4.17 for sewage works at Wan Shing Street
·
Backfilling
for sewage trench at Wan Shing Street
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/D
·
Approach ramp structure Construction.
·
Bridge superstructure, parapet & installation
of enclosure.
·
Retaining wall construction.
·
FEHD depot re-provision works.
·
FEHD metal roof construction.
·
Oil street drainage works.
·
Installation of skin parapet on TB bridge at
Pier 15-17.
·
Landscape deck, column & pile cap
foundation works.
·
Watson Road Watermains laying works.
·
EVA at EVB.
·
Hing Fat Street road and drainage works.
·
Demolition of TD bridge.
Contract no.
HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West under FEP-12/364/2009/D
·
Construction
of Slip Road 1
·
Construction
of drainage
·
Asphalt
paving
·
Construction
of roundabout
Contract no.
HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8) under
FEP-10/364/2009/B
·
Tree
replanting works in VP,
·
Drainage
improvement works,
·
Utility
diversion works,
·
Retaining
wall works
Contract no.
HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction
of Ventilation Buildings, inclusive of Administration Building, Central
Ventilation Building, East Ventilation Shaft/Building, West Ventilation
Building
·
Application
of Thermal Barrier inside the Tunnel, asphalt pavement
·
Installation
of Electricals and Mechanicals
·
Installation
of Tunnel Features
Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of Summons
and Successful Prosecutions
Site Inspections and Audit
Contract
no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009
·
Reinstatement
of amenity area
Contract
no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Rectification
work for the replacement of 8 nos. of damaged PMMA panels
·
Drainage
work
·
Remedial
works against water leakage and CCTV inside tunnel
·
Partial
removal of TWCR4 to -5.0mPD
·
Backfilling
works behind seawall blocks and adjacent Box Culvert O
·
Construction
of box culvert ‘O’
·
Temporary
works for construction of box culvert ‘O’
·
Demolition
of D-Wall for construction of Box Culvert O
·
Fabrication
of precast units for Box Culvert O
·
Installation
of tie-back
·
Remedial
works against water leakage inside tunnel
·
Stockpiling
and internal transfer of excavated materials from Portions 3&4
·
Monitoring
and maintain temporary drainage system for stockpiling
·
Rectification
works for damaged CMS cover under C1
·
Sewage
works at Wan Shing Street
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/D
·
Bridge
superstructure & installation of enclosure.
·
Retaining
wall construction.
·
FEHD
re-provision works.
·
Oil
Street drainage works.
·
Installation
of skin parapet on TB bridge at Pier 15-17.
·
Landscape
deck soft landscaping works.
·
Watson
Road Watermains laying works.
·
EVA at EVB.
·
Hing Fat
Street road and drainage works.
·
Demolition
of TD bridge
Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan
Chai Bypass at Wan Chai West under FEP-12/364/2009/D
·
Construction
of Slip Road 1
·
Construction
of drainage
·
Asphalt paving
·
Construction
of roundabout
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009
·
Tree
replanting works in VP,
·
Drainage
improvement works,
·
Utility
diversion works,
·
Retaining
wall works
Contract no. HY/2011/08 – Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction
of Ventilation Buildings, inclusive of Administration Building, Central
Ventilation Building, East Ventilation Shaft/Building, West Ventilation
Building
·
Application
of Thermal Barrier inside the Tunnel, asphalt pavement
·
Installation
of Electricals and Mechanicals
·
Installation
of Tunnel Features
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/E and
Further Environmental permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B,
FEP-11/364/2009/E and FEP-12/364/2009/D to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and “Environmental Monitoring and Audit
Requirements” under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/E, Further Environmental
Permit (FEP) nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B,
FEP-11/364/2009/E and FEP-12/364/2009/D during the
period 27 April 2018 to 26 May 2018.
Section 1 Introduction – details the scope
and structure of the report.
Section 2 Project
Background
– summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance – summarizes the
status of valid Environmental Permits / Licenses during the reporting period.
Section 4 Monitoring
Requirements
– summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section 5 Monitoring
Results
– summarizes the monitoring results obtained in the reporting period.
Section 6 Compliance
Audit
– summarizes the auditing of monitoring results, all
exceedances
environmental parameters.
Section 7 Cumulative Construction Impact due to the
Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Environmental Site Audit – summarizes the
findings of weekly site inspections undertaken within the reporting period,
with a review of any relevant
follow-up actions within the reporting period.
Section 9 Complaints, Notification of summons and Prosecution
–
summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 10 Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan Chai Bypass” and
“Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called
“the Project”) are Designated Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental
Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern
Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved
on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested east-west Connaught Road Central/Harcourt Road / Gloucester
Road Corridor (the Corridor) which is currently operating beyond its capacity.
The CWB will provide relief to the existing congestion along the Corridor and
cater for the anticipated growth of traffic on Hong Kong Island. Without the
CWB and its access roads, there will not be sufficient capacity to serve the
heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
·
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
·
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
·
Tunnel
control buildings and ventilation buildings;
·
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
Causeway Bay area;
·
Associated
road lighting, road signing, traffic control and surveillance system; and
·
Other
associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further
Environmental Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 April 2011 (Completed) |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre – Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1,DP3 |
13 July 2011 (Completed) |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai Bypass at Wan Chai
West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel – Tunnel (Slip Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Ms. Gloria Tang |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3328 |
|
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Manager |
Mr. Simon Liu |
9304 8355 |
2587 1878 |
Environmental
Officer |
Mr. Terry
Tsang |
6683 9394 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Paul Yu |
3658 3085 |
2827 9996 |
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570 8013 |
Site Agent |
Mr. William Luk |
9456 9819 |
|||
Deputy Site Agent |
Mr. Andy Chan |
3758 8879 |
|||
Environmental Officer |
Mr. M.H. Isa |
3757 8218 |
|||
Assistant Environmental Officer |
Mr. James Chan |
3757 8217 |
|||
Construction Manager (Marine) |
Mr. Wingo Wong |
9300 2625 |
|||
Construction Manager (Land) |
Mr. Ray Ho |
9608 6366 |
|||
Construction Manager (Land) |
Mr. Yung Kwok Wah |
9834 1010 |
|||
Construction Manager (Ext. Works) |
Mr. Paul Wan |
6629 4652 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
3973 0803 |
|
Construction Manager |
Mr. Darren Grant |
3971 1460 |
|||
Environmental
Supervisor |
Ms. Penny Yiu |
3973 1065 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2865 5229 |
Site Agent |
Mr. Patrick Ho |
3557 6405 |
2566 2192 |
||
Environmental Officer |
Mr. Desmond Ho |
3557 6347 |
|||
China State- Build King JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N. Lai |
9137 1811 |
2877 1522 |
Site Agent |
Mr. George
Cheung |
9268 1918 |
|||
Environmental
Officer |
Mr. James MA |
9130 9549 |
|||
Environmental
Supervisor |
Mr. Y. L. Ho |
9856 5669 |
|||
China State |
Contractor under Contract no. HY/2010/08 |
Project
Director |
Chris
Leung |
9210 7116 |
2566 8061 |
Site Agent |
Mr. Thomas Lui |
3557 6407 |
|||
Environmental
Officer |
Mr. Gabriel
Wong |
3557 6466 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Site Agent |
Mr. Colman Wong |
2823 1410 |
21406799 |
Environmental
Officer |
Ms. Penny Yiu |
3973 1065 |
|||
Ramboll Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting period, the principal work
activities of individual contracts are included as follows:
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
Reinstatement
of amenity area
Contract
no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai
East (CWB Tunnel) under FEP-01/364/2009
·
New PMMA
for the replacement of 8 nos. of damaged PMMA panels
·
Preparation
for raising the vent shaft, water meters chambers and multi-part covers of P7,
P8 and P9
·
Drainage
work
·
Remedial
works against water leakage and CCTV inside tunnel
·
Installation
of breakwater
·
Backfilling
behind seawall block
·
Pipe
piling work for ELS of Box Culvert O Bay 13, 14
·
Installation
of ELS for Box Culvert O Bay 14A and 17A
·
Backfilling
works for Box Culvert O Bay 15A and 16A
·
Demolition
of D-Wall for construction of Box Culvert O
·
Fabrication
of precast units for Box Culvert O
·
Remedial
works against water leakage inside OHVD cells
·
Temporary
drainage system for stock piling at Portion 5
·
Construction
of manhole no. MH4.17 for sewage works at Wan Shing Street
·
Backfilling
for sewage trench at Wan Shing Street
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
·
Approach
ramp structure Construction.
·
Bridge
superstructure, parapet & installation of enclosure.
·
Retaining
wall construction.
·
FEHD
depot re-provision works.
·
FEHD
metal roof construction.
·
Oil
street drainage works.
·
Installation
of skin parapet on TB bridge at Pier 15-17.
·
Landscape
deck, column & pile cap foundation works.
·
Watson
Road Watermains laying works.
·
EVA at
EVB.
·
Hing Fat
Street road and drainage works.
·
Demolition
of TD bridge
Contract no. HK/2012/08 – Wan Chai
Development Phase II – Central- Wan Chai Bypass at Wan Chai West under
FEP-12/364/2009/D
·
Construction
of Slip Road 1
·
Construction
of drainage
·
Asphalt
paving
·
Construction
of roundabout
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009/B
·
Tree
replanting works in VP,
·
Drainage
improvement works,
·
Utility
diversion works,
·
Retaining
wall works
Contract no. HY/2011/08 –Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction
of Ventilation Buildings, inclusive of Administration Building, Central
Ventilation Building, East Ventilation Shaft/Building, West Ventilation
Building
·
Application
of Thermal Barrier inside the Tunnel, asphalt pavement
·
Installation
of Electricals and Mechanicals
·
Installation
of Tunnel Features
2.4.4.
In coming reporting period, the principal
work activities of individual contracts are anticipated as follows:
·
Reinstatement
of amenity area
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
·
Rectification
work for the replacement of 8 nos. of damaged PMMA panels
·
Drainage
work
·
Remedial
works against water leakage and CCTV inside tunnel
·
Partial
removal of TWCR4 to -5.0mPD
·
Backfilling
works behind seawall blocks and adjacent Box Culvert O
·
Construction
of box culvert ‘O’
·
Temporary
works for construction of box culvert ‘O’
·
Demolition
of D-Wall for construction of Box Culvert O
·
Fabrication
of precast units for Box Culvert O
·
Installation
of tie-back
·
Remedial
works against water leakage inside tunnel
·
Stockpiling
and internal transfer of excavated materials from Portions 3&4
·
Monitoring
and maintain temporary drainage system for stockpiling
·
Rectification
works for damaged CMS cover under C1
·
Sewage
works at Wan Shing Street
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
·
Bridge
superstructure & installation of enclosure.
·
Retaining
wall construction.
·
FEHD
re-provision works.
·
Oil
Street drainage works.
·
Installation
of skin parapet on TB bridge at Pier 15-17.
·
Landscape
deck soft landscaping works.
·
Watson
Road Watermains laying works.
·
EVA at
EVB.
·
Hing Fat
Street road and drainage works.
·
Demolition
of TD bridge
Contract no. HK/2012/08 – Wan Chai
Development Phase II – Central- Wan Chai Bypass at Wan Chai West under
FEP-12/364/2009/D
·
Construction
of Slip Road 1
·
Construction
of drainage
·
Asphalt
paving
·
Construction
of roundabout
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009
·
Tree
replanting works in VP,
·
Drainage
improvement works,
·
Utility
diversion works,
·
Retaining
wall works
Contract no. HY/2011/08 – Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction
of Ventilation Buildings, inclusive of Administration Building, Central Ventilation
Building, East Ventilation Shaft/Building, West Ventilation Building
·
Application
of Thermal Barrier inside the Tunnel, asphalt pavement
·
Installation
of Electricals and Mechanicals
·
Installation
of Tunnel Features
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of the current status
on licences and/or permits on environmental protection pertinent to the Project
Permits and/or Licenses |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009/E |
22 Dec
2016 |
Valid |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Surrendered |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Surrendered |
Further Environmental Permit |
FEP-06/356/2009 |
5
March 2013 |
Valid |
Further Environmental Permit |
FEP-07/356/2009 |
26
July 2013 |
Valid |
Further
Environmental Permit |
24 Mar
2010 |
Valid |
|
Further
Environmental Permit |
21 Apr 2010 |
Valid |
|
Further
Environmental Permit |
12 July 2010 |
Surrendered
|
|
Further
Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further
Environmental Permit |
15 Nov 2010 |
Valid |
|
Further
Environmental Permit |
22 Nov 2010 |
Valid |
|
Further
Environmental Permit |
24 Nov 2015 |
Valid |
|
Further
Environmental Permit |
15 June 2012 |
Surrendered |
|
Further
Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further
Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further
Environmental Permit |
FEP-11/364/2009/E |
22 Dec
2016 |
Valid |
Further
Environmental Permit |
FEP-12/364/2009/D |
01
Aug 2016 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 – Central – Wan Chai
Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.
Contract no. 04/HY/2006 – Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP-04/HY/2006 was
surrendered by the Contractor on 11 February 2011.
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
3.1.5. The construction works was completed, and the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
Contract no. HY/2009/15 – Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
3.1.6. The Construction works under HY/2009/15 was confirm completed by the RSS
from 27 October 2017 onwards. The weekly site audit inspection and the
associated monitoring station for HY/2009/15 were temporary suspended from 27
October 2017 onwards.
Contract no.
HY/2009/18 –
Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
3.1.7. The Construction works under HY/2009/18 was confirm completed by the RSS
from 25 April 2018 onwards. The weekly site audit inspection and the associated
monitoring station for HY/2009/18 were temporary suspended from 27 April 2018
onwards.
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009
3.1.8.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.2 and Table 3.3.
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits
and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification
of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Discharge License |
WT00024952-2016 |
06 Jul 2016 |
31 Jul 2021 |
Valid |
WT00024844-2016 |
29 Jun 2016 |
31 Mar 2020 |
Valid |
|
Billing account under
Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table
3.3 Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May 2011 |
Condition 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Condition 1.12 |
Commencement Date of Works |
20 Jun 2011 |
Condition 2.9 |
Noise Management Plan |
10 Jun 2011 |
Condition 2.11 |
Landscape Plan (Rev.5) |
25 January 2018 |
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.9.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.4 and Table 3.5.
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02
Permits and/or Licenses |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of
Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling equipment |
GW-RS0296-18 |
10 Apr 2018 |
23 Apr 2018 to 22
Oct 2018 |
Valid |
GW-RS0333-18 |
25 Apr 2018 |
27 Apr 2018 to 25
Oct 2018 |
Valid |
|
GW-RS0334-18 |
25 Apr 2018 |
27 Apr 2018 to 25
Oct 2018 |
Valid |
|
Water Discharge
License |
WT00022295-2015 |
12 Aug 2015 |
31 July 2020 |
Valid |
WT00025276-2016 |
19 Sep 2016 |
31 July 2021 |
Valid |
|
Billing Account
under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Billing Account
under Waste Disposal Ordinance (Marine) |
7011496 |
6 Oct 2010 |
N/A |
Valid |
Registration as
Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as
Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table
3.5 Summary of submission status
under FEP-01/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.7 and 2.8 |
Works
Schedule and Location Plan |
14 Jun 2011 |
Condition 2.6 |
Environmental
Management Organization Chart |
14 Jun 2011 |
Condition 1.12 |
Commencement
Date of Works |
21 Jun 2011 |
Condition
2.11 |
Landscape Plan (Revision B) |
20 Nov 2012 |
Condition 2.9 |
Noise Management Plan (Revision B) |
13 Jan 2012 |
Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
3.1.10.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.6 and Table
3.7.
Table
3.6 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/18
Permit /
License / Notification / Approval |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
N/A |
Valid |
Notification
of Works Under APCO |
322293 |
07 Oct 2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0032-18 |
15 Jun 2018 |
24 Jan 2018
to 21 Jul 2018 |
Valid |
Discharge
Licenses |
WT00024255-2016 |
18 May 2016 |
31 Jan 2021 |
Valid |
Registration
as a Chemical Waste Producer |
WPN: 8335-121-L1048-04 |
17 Dec 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance (Land) |
Account No.: 7011587 |
11 Oct 2010 |
N/A |
Valid |
Table 3.7 Summary of submission status
under FEP-05/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan (Rev. 6) |
19 May 2014 |
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
3.1.11.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.8 and Table 3.9.
Table
3.8 Cumulative Summary
of Valid Licences and Permits under Contract no. HY/2009/15
Permits
and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Construction Noise Permit |
N/A |
N/A |
N/A |
N/A |
Water Discharge License (Discharge at TS1) |
WT00024874-2016 |
20 Jul 2016 |
20 Jul 2016 to 31 Mar 2021 |
Valid |
Table
3.9 Summary of
submission status under FEP-06/364/2009/A
EP
Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction
Companies |
11 Mar 2011 |
Amendment for Management Organization of Main
Construction Companies |
16 May 2011 |
|
Condition 2.7 |
Works Schedule |
15 Mar 2011 |
Condition 2.8 |
Location Plan |
15 Mar 2011 |
Condition 2.9 |
Noise Management Plan |
6 May 2011 |
Condition 2.10 |
Landscape Plan
(Rev.5) |
25 Jan 2018 |
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
3.1.12.
The current status on licences and/or permits
on environmental protection pertinent and submission
under FEP-07/364/2009/D for contract no. HY/2009/19 are shown in Table 3.10 and Table
3.11.
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
24 Nov 2015 |