Contract No: HK/2015/01 Wanchai
Development Phase II and Central Wanchai Bypass Sampling,
Field Measurement and Testing Work (Stage 3) Environmental Permit no. EP-364/2009/E, Further
Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/D, FEP-09/364/2009/B,
FEP-10/364/2009/B and FEP-11/364/2009/E, FEP-12/364/2009/D Monthly Environmental Monitoring &
Audit Report
- December
2018 -
|
CLIENTS: |
|
Civil Engineering
and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
10 January
2019 |
2.2 Scope of the Project and Site
Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact
Personnel
3
status of regulatory compliance..
3.1 Status of Environmental Licensing and
Permitting under the Project
5.2 Real Time Noise Monitoring Results
5.3 Air Quality Monitoring Results
6.3 Review of the Reasons for and the
Implications of Non-compliance.
6.4 Summary of action taken in the event of
and follow-up on non-compliance.
7 Cumulative Construction
Impact due to the Concurrent Projects
9 Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table
2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.1 Summary
of the current status on licences and/or permits on environmental
protection pertinent to the Project
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.3 Summary
of submission status under FEP-02/364/2009
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.5 Summary
of submission status under FEP-01/364/2009
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.7 Summary
of submission status under FEP-05/364/2009/A
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.9 Summary
of submission status under FEP-06/364/2009/A
Table 3.10 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.11
Summary of submission status under FEP-07/364/2009/D
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.13 Summary of submission status under FEP-12/364/2009/D
Table 3.14 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.15 Summary of submission status under
FEP-10/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HY/2011/08
Table 3.17 Summary of submission status under FEP-11/364/2009/E
Table 4.1 Noise Monitoring
Stations
Table 4.2 Real
Time Noise Monitoring Stations
Table 4.3 Air
Quality Monitoring Stations
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/18 (NOT USED)
Table 5.2 Noise
Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Table 5.3 Noise
Monitoring Stations for Contract no. HY/2009/15
Table 5.4 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table 5.6 Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Real
Time Noise Monitoring Stations for Contract no. HY/2011/08
Table 5.9 Air
Quality Monitoring Station for Contract no. HY/2009/18 (NOT USED)
Table 5.10 Air Quality Monitoring
Station for Contract no. HK/2009/01(NOT USED)
Table 5.11 Air Quality Monitoring
Station for Contract no. HK/2009/02
Table 5.12 Air Quality Monitoring
Stations for Contract no. HY/2009/15(NOT USED)
Table 5.13 Air Quality
Monitoring Station for Contract no. HY/2009/19
Table 5.14 Air Quality
Monitoring Station for Contract no. HK/2012/08
Table 5.15 Air Quality Monitoring Stations for Contract no. HY/2010/08
Table 5.16 Air
Quality Monitoring Stations for Contract no. HY/2011/08
Table 5.17 Details
of Waste Disposal for Contract no. HK/2009/01(NOT USED)
Table 5.18 Details
of Waste Disposal for Contract no. HK/2009/02
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/18
Table 5.20 Details
of Waste Disposal for Contract no. HY/2009/15
Table 5.21 Details of Waste Disposal
for Contract no. HY/2009/19
Table 5.22 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.23 Details of Waste Disposal
for Contract no. HY/2010/08
Table 5.24 Details of Waste Disposal for Contract
no. HY/2011/08
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/15 (NOT USED)
Table 8.2 Summary of Environmental
Inspections for Contract no. HY/2009/18 (NOT USED)
Table 8.3 Summary of
Environmental Inspections for Contract no. HY/2009/19
Table 8.4 Summary of
Environmental Inspections for Contract no. HK/2009/01 (NOT USED)
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.6 Summary of
Environmental Inspections for Contract no. HK/2012/08
Table
8.7 Summary of Environmental
Inspections for Contract no. HY/2010/08
Table 8.8 Summary of
Environmental Inspections for Contract no. HY/2011/08)NOT USED)
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Table 10.1 Summary
of Key Construction Activities of Individual Contract(s) to be
commenced in Coming Reporting period
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting period and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring
Results and Graphical Presentations
Appendix
5.4 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of
Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P
Rectification work for the replacement of 8 nos. of damaged PMMA panels
¡P
Drainage work
¡P
Removal of TWCR4
¡P
Construction of seawall at Portion 3&4
¡P
Backfilling work behind seawall
¡P
Construction of drainage system for Box Culvert O and Hung Hing Road
at-grade Road
¡P
Laying pavement of Hung Hing Road
¡P
Fabrication of seawall block in China
¡P
Placing bedding and precast units of Box Culvert O Bay 12
¡P
Stockpiling and internal transfer of excavated materials from Portions
3&4
¡P
Monitoring and maintain temporary drainage system for stockpiling
¡P
Rectification works for damaged CMS cover under C1
¡P
Rectification of CMS termination box cover
¡P
DN600 sewerage works across Hung Hing Road
¡P
Remedial works for covered walkway at Expo Drive East
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
¡P
Approach ramp road works
¡P
Bridge noise enclosure installation works
¡P
FEHD depot re-provision works
¡P
Oil street road works
¡P
Hing Fat Street road and drainage works
¡P
Trough B & C construction
¡P
SR13 road works
¡P
Seawall block reinstatement near box culvert T1
¡P
Soft Landscaping works
¡P
SR13 to Box Culvert T1 drainage works
¡P
EVB open area drainage & hard paving works
¡P
D9 to D12 drainage works
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West under FEP-12/364/2009/D
¡P
Construction of Lung King Street
¡P
Construction of drainage
¡P
Construction of roundabout
Contract
no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under
FEP-10/364/2009/B
¡P
Tree replanting works in VP
¡P
Drainage improvement works
¡P
Utility diversion works
¡P
Retaining wall works
¡P
Junction modification
Contract
no. HY/2011/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
¡P
ABWF works at Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
¡P
Construction works at SCB and SCP area
¡P
Defects redefection works inside Tunnel
¡P
Road resurfacing works in Portion 1a
¡P
Installation and testing of Electricals and Mechanicals
¡P
Installation of Tunnel Features
¡P
Man Po Street widening works
¡P
Traffic sign installation and modification of directional sign
¡P
Installation of glass canopy at ADB
Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of Summons
and Successful Prosecutions
An ICC complaint (Case Ref:
2-4915837866, lodged at 0944hrs on 4 December 2018) was referred to the ET on 4
December 2018. The ICC hotline operator reported that Construction noise was
generated from Man Po Street starting from midnight for two consecutive night.
ET confirmed with the Resident Site
Staff that
1.
No construction works was conducted under HY/2010/08 at Man Po Street
after midnight on 2 and 3 December 2018.
2.
Resurfacing and road marking was conducted under HY/2011/08 at Man Po
Street after midnight on 2 and 3 December 2018. The PME operation was listed as
follow:
03 December 2018
1:00 am: Hand-held Breaker (electric) x
1, Road Miller x 1, Dump truck x1, Portable generator x 1; 2:00 am: Road
sweeper x 1, Tack coat sprayer x 1, Asphalt Paver x 1, Dump truck x 1,Road
Roller x 1; 3:00 am: Cleaning up & off work before 6:00am
04 December 2018
1:00 am: Hand-held Breaker (electric) x
1, Road Miller x 1, Dump truck x1, Portable generator x 1; 2:00 am: Road
sweeper x 1, Tack coat sprayer x 1, Asphalt Paver x 1, Dump truck x 1, Road
Roller x 1; 3:00 am: Cleaning up & off work before 6:00am
Relevant Construction Noise Permit
GW-RS0969-18 was in place for the construction works conducted during the above
concerned period and the PME operated during the concerned period was included
in Construction Noise Permit GW-RS0969-18 Condition 3.a. Group A. Based on RSS
information, the noise control measures listed in Construction Noise Permit
GW-RS0969-18 Condition 3.d.5., including the use of acoustic enclosure for
operation of Hand-held Breaker (electric) with Noise Emission Label showing a
sound power level of <=104dB(A) and portable generator was generally in
place. Noise control measures listed in Construction Noise Permit GW-RS0969-18
Condition 3.d.6 including sound absorbing lining and sound baffles for engine
compartment and engine exhaust silencers for road miller, asphalt paver and
road roller (with QPME label) was generally in place.
In view of the above, the Contractor of
HY/2011/08 was reminded to upkeep the site control system for construction
works carried out during restricted hours and night time for Construction Noise
Compliance and maintain regular maintenance of the plant and equipment deployed
to avoid potential nuisance to nearby public.
Site Inspections and Audit
i.
In the coming reporting period, the principal work activities of
individual contracts are anticipated as follows:
Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Drainage works
¡P
Construction of seawall at Portion 3&4
¡P
Backfilling works behind seawall blocks and adjacent Box Culvert O
¡P
Construction of drainage system for Box Culvert O and Hung Hing Road
at-grade Road
¡P
Laying pavement of Hung Hing Road
¡P
Fabrication of seawall block in China
¡P
Placing bedding and precast units of Box Culvert O Bay 12
¡P
Stockpiling and internal transfer of excavated materials from Portions
3&4
¡P
Monitoring and maintain temporary drainage system for stockpiling.
¡P
Rectification works for damaged CMS cover under C1.
¡P
Rectification of CMS termination box cover
¡P
DN600 sewerage works across Hung Hing Road.
¡P
Remedial works for covered walkway at Expo Drive East
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
¡P
Bridge noise enclosure installation works
¡P
FEHD depot re-provision works
¡P
Oil Street road works
¡P
Hing Fat Street road and drainage works
¡P
Trough B & C construction
¡P
SR13 road works
¡P
Seawall block reinstatement near box culvert T1
¡P
Soft landscaping works
¡P
EVB open area hard paving works
¡P
D9 to D12 drainage works
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D
¡P
Construction of Lung King Street
¡P
Construction of drainage
¡P
Construction of roundabout
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009
¡P
Tree replanting works in VP
¡P
Drainage improvement works
¡P
Utility diversion works
¡P
Retaining wall works
¡P
Junction modification
Contract no. HY/2011/08 ¡V Central - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
¡P
ABWF works at Ventilation Buildings, inclusive of Administration Building,
Central Ventilation Building, East Ventilation Shaft/Building, West Ventilation
Building
¡P
Construction works at SCB and SCP area
¡P
Defects redefection works inside Tunnel
¡P
Road resurfacing works in Portion 1a
¡P
Installation and testing of Electricals and Mechanicals
¡P
Installation of Tunnel Features
¡P
Man Po Street widening works
¡P
Traffic sign installation and modification of directional sign at
various locations
¡P
Installation of glass canopy at ADB
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/E and
Further Environmental permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/B,
FEP-10/364/2009/B, FEP-11/364/2009/E and FEP-12/364/2009/D to implement the Environmental Monitoring and Audit (EM&A)
programme as stipulated in the EM&A Manual of the approved Environmental
Impact Assessment (EIA) Report for Wan Chai Development phase II and
Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit
Requirements¡¨ under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/E, Further Environmental
Permit (FEP) nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/B,
FEP-10/364/2009/B, FEP-11/364/2009/E and FEP-12/364/2009/D during the period 27 November 2018 to 26 December 2018.
Section
1 Introduction ¡V
details the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results obtained
in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all
exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Environmental Site Audit ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and
¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called
¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested east-west Connaught Road Central/Harcourt Road / Gloucester
Road Corridor (the Corridor) which is currently operating beyond its capacity.
The CWB will provide relief to the existing congestion along the Corridor and
cater for the anticipated growth of traffic on Hong Kong Island. Without the
CWB and its access roads, there will not be sufficient capacity to serve the
heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central ¡V Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
¡P
A dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
¡P
The Central Interchange near the Rumsey Street Flyover to provide road
connections to the Central area;
¡P
Tunnel control buildings and ventilation buildings;
¡P
Slip roads to connect the CWB to the local road system in the Wan Chai
North and Causeway Bay area;
¡P
Associated road lighting, road signing, traffic control and surveillance
system; and
¡P
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason
for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in
length |
DP2 |
Road P2 and other roads which are classified as
primary/district distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging
works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging
operation less than 100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter
more than 1,200 mm and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from
Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a
seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further Environmental
Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield
Depot ¡V Advanced piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange |
DP1 |
21 April 2011 (Completed) |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu
Street and Man Kwong Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai
Bypass at Hong Kong Convention and Exhibition Centre ¡V Tunnel Works |
DP1,
DP2 |
25
August 2011 (Completed) |
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East(CWB Tunnel) |
DP1 |
26
April 2011 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) |
DP1,DP3 |
13
July 2011 (Completed) |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link |
DP1 |
24
March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai
Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel ¡V Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) ¡VTunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Chief Resident Engineer |
Ms. Gloria Tang |
2587 1778 |
2587
1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912
3328 |
|
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Paul Yu |
3658 3085 |
2827
9996 |
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint
Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570
8013 |
Site Agent |
Mr. William Luk |
9456 9819 |
|||
Deputy Site Agent |
Mr. Andy Chan |
3758 8879 |
|||
Environmental Officer |
Mr. M.H. Isa |
3757 8218 |
|||
Assistant Environmental Officer |
Mr. James Chan |
3757 8217 |
|||
Construction Manager (Marine) |
Mr. Wingo Wong |
9300 2625 |
|||
Construction Manager (Land) |
Mr. Mark Mak |
9356 4421 |
|||
Construction Manager (Ext. Works) |
Mr. Paul Wan |
6629 4652 |
|||
Construction Manager (Land) |
Mr. Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
3973
0803 |
|
Construction Manager |
Mr. Darren Grant |
3971
1460 |
|||
Environmental
Supervisor |
Ms. Penny Yiu |
3973
1065 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2865 5229 |
Site Agent |
Mr. Patrick Ho |
3557 6405 |
2566 2192 |
||
Environmental Officer |
Mr. Gabriel
Wong |
6114
9590 |
|||
China State- Build King JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N.
Lai |
9137
1811 |
2877
1522 |
Site
Agent |
Mr. George
Cheung |
9268
1918 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Y. L. Ho |
9856
5669 |
|||
China State |
Contractor under Contract no. HY/2010/08 |
Project
Director |
Chris
Leung |
9210
7116 |
2566
8061 |
Site
Agent |
Mr. Thomas
Lui |
3557
6407 |
|||
Environmental
Officer |
Mr. Gabriel
Wong |
3557
6466 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Site Agent |
Mr. Colman Wong |
2823 1410 |
21406799 |
Environmental
Officer |
Ms. Penny Yiu |
3973
1065 |
|||
Ramboll Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics
Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882
3939 |
2882 3331 |
2.4.3.
In this reporting period, the principal work
activities of individual contracts are included as follows:
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Rectification work for the replacement of 8 nos. of damaged PMMA panels
¡P
Drainage work
¡P
Removal of TWCR4
¡P
Construction of seawall at Portion 3&4
¡P
Backfilling work behind seawall
¡P
Construction of drainage system for Box Culvert O and Hung Hing Road
at-grade Road
¡P
Laying pavement of Hung Hing Road
¡P
Fabrication of seawall block in China
¡P
Placing bedding and precast units of Box Culvert O Bay 12
¡P
Stockpiling and internal transfer of excavated materials from Portions
3&4
¡P
Monitoring and maintain temporary drainage system for stockpiling
¡P
Rectification works for damaged CMS cover under C1
¡P
Rectification of CMS termination box cover
¡P
DN600 sewerage works across Hung Hing Road
¡P
Remedial works for covered walkway at Expo Drive East
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
¡P
Approach ramp road works
¡P
Bridge noise enclosure installation works
¡P
FEHD depot re-provision works
¡P
Oil street road works
¡P
Hing Fat Street road and drainage works
¡P
Trough B & C construction
¡P
SR13 road works
¡P
Seawall block reinstatement near box culvert T1
¡P
Soft Landscaping works
¡P
SR13 to Box Culvert T1 drainage works
¡P
EVB open area drainage & hard paving works
¡P
D9 to D12 drainage works
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-12/364/2009/D
¡P
Construction of Lung King Street
¡P
Construction of drainage
¡P
Construction of roundabout
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009/B
¡P
Tree replanting works in VP
¡P
Drainage improvement works
¡P
Utility diversion works
¡P
Retaining wall works
¡P
Junction modification
Contract no. HY/2011/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
¡P
ABWF works at Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
¡P
Construction works at SCB and SCP area
¡P
Defects redefection works inside Tunnel
¡P
Road resurfacing works in Portion 1a
¡P
Installation and testing of Electricals and Mechanicals
¡P
Installation of Tunnel Features
¡P
Man Po Street widening works
¡P
Traffic sign installation and modification of directional sign
¡P
Installation of glass canopy at ADB
2.4.4.
In coming reporting period, the principal
work activities of individual contracts are anticipated as follows:
¡P
Drainage works
¡P
Construction of seawall at Portion 3&4
¡P
Backfilling works behind seawall blocks and adjacent Box Culvert O
¡P
Construction of drainage system for Box Culvert O and Hung Hing Road
at-grade Road
¡P
Laying pavement of Hung Hing Road
¡P
Fabrication of seawall block in China
¡P
Placing bedding and precast units of Box Culvert O Bay 12
¡P
Stockpiling and internal transfer of excavated materials from Portions
3&4
¡P
Monitoring and maintain temporary drainage system for stockpiling.
¡P
Rectification works for damaged CMS cover under C1.
¡P
Rectification of CMS termination box cover
¡P
DN600 sewerage works across Hung Hing Road.
¡P
Remedial works for covered walkway at Expo Drive East
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
¡P
Approach ramp road works
¡P
Bridge noise enclosure installation works
¡P
FEHD depot re-provision works
¡P
Oil Street road works
¡P
Hing Fat Street road and drainage works
¡P
Trough B & C construction
¡P
SR13 road works
¡P
Seawall block reinstatement near box culvert T1
¡P
Soft landscaping works
¡P
EVB open area hard paving works
¡P
D9 to D12 drainage works
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-12/364/2009/D
¡P
Construction of Lung King Street
¡P
Construction of drainage
¡P
Construction of roundabout
Contract no. HY/2010/08 ¡VCentral - Wan
Chai Bypass (CWB) ¡VTunnel (Slip Road 8) under FEP-10/364/2009
¡P
Tree replanting works in VP
¡P
Drainage improvement works
¡P
Utility diversion works
¡P
Retaining wall works
¡P
Junction modification
Contract no. HY/2011/08 ¡V Central - Wan
Chai Bypass (CWB) ¡VTunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
¡P
ABWF works at Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
¡P
Construction works at SCB and SCP area
¡P
Defects redefection works inside Tunnel
¡P
Road resurfacing works in Portion 1a
¡P
Installation and testing of Electricals and Mechanicals
¡P
Installation of Tunnel Features
¡P
Man Po Street widening works
¡P
Traffic sign installation and modification of directional sign at
various locations
¡P
Installation of glass canopy at ADB
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of the current status
on licences and/or permits on environmental protection pertinent to the Project
Permits
and/or Licenses |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009/E |
22 Dec 2016 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Surrendered |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Surrendered |
Further
Environmental Permit |
FEP-06/356/2009 |
5 March 2013 |
Valid |
Further
Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Surrendered |
|
Further Environmental Permit |
12 July 2010 |
Surrendered |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
24 Nov 2015 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Surrendered |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/E |
22 Dec 2016 |
Valid |
Further Environmental Permit |
FEP-12/364/2009/D |
01 Aug 2016 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai
Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.
Contract no. 04/HY/2006 ¡V Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP-04/HY/2006 was
surrendered by the Contractor on 11 February 2011.
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
3.1.5. The construction works was completed, and the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
Contract no. HY/2009/15 ¡V Central-Wanchai
Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
3.1.6. The Construction works under HY/2009/15 was confirm completed by the RSS
from 27 October 2017 onwards. The weekly site audit inspection and the
associated monitoring station for HY/2009/15 were temporary suspended from 27
October 2017 onwards.
Contract no.
HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under
FEP-05/364/2009/A
3.1.7. The Construction works under HY/2009/18 was confirm completed by the RSS
from 25 April 2018 onwards. The weekly site audit inspection and the associated
monitoring station for HY/2009/18 were temporary suspended from 27 April 2018
onwards.
Contract no.
HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009
3.1.8. As confirmed with WDII RSS and with
respect to the joint inspection conducted with IEC on 25 May 2018, RSS, ET and
IEC share the view that there is no adverse environmental impact of remaining
works under Contract HK/2009/01 and the respective environmental site
inspection and associated monitoring station were temporary suspended from 26
May 2018 onwards. FEP-02/364/2009 was surrendered by the Contractor on 3
September 2018.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.9.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.4 and Table 3.5.
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02
Permits and/or Licenses |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar
2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb
2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling
equipment |
GW-RS0674-18 |
31 Jul
2018 |
2 Aug
2018 to 31 Jan 2019 |
Valid |
GW-RS0713-18 |
14 Aug 2018 |
16 Aug
2018 to 14 Feb 2019 |
Valid |
|
GW-RS0880-18 |
24 Sep
2018 |
26 Sep
2018 to 24 Mar 2019 |
Valid |
|
GW-RS0931-18 |
16 Oct
2018 |
22 Oct
2018 to 18 Apr 2019 |
Valid |
|
Water
Discharge License |
WT00022295-2015 |
12 Aug 2015 |
31 July 2020 |
Valid |
WT00025276-2016 |
19 Sep 2016 |
31 July 2021 |
Valid |
|
Billing
Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance (Marine) |
7011496 |
6 Oct 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table
3.5 Summary of submission status
under FEP-01/364/2009
EP Condition |
Submission |
Date
of
Submission |
Condition 2.7
and 2.8 |
Works
Schedule and Location Plan |
14 Jun 2011 |
Condition 2.6 |
Environmental
Management Organization Chart |
14 Jun 2011 |
Condition 1.12 |
Commencement
Date of Works |
21 Jun 2011 |
Condition
2.11 |
Landscape Plan (Revision B) |
20 Nov
2012 |
Condition 2.9 |
Noise Management Plan (Revision B) |
13 Jan
2012 |
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass
(CWB) ¡V Central Interchange under FEP-05/364/2009/A
3.1.10.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.6 and Table
3.7.
Table
3.6 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/18
Permit / License / Notification / Approval |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-05/364/2009/A |
15
Nov 2010 |
N/A |
Valid |
Notification
of Works Under APCO |
322293 |
07
Oct 2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
- |
- |
- |
- |
Discharge
Licenses |
WT00024255-2016 |
18
May 2016 |
31
Jan 2021 |
Valid |
Registration
as a Chemical Waste Producer |
WPN: 8335-121-L1048-04 |
17
Dec 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance
(Land) |
Account No.: 7011587 |
11
Oct 2010 |
N/A |
Valid |
Table 3.7 Summary of submission status
under FEP-05/364/2009/A
EP Condition |
Submission |
Date
of
Submission |
Condition 2.9 |
Noise Management Plan |
01 March 2011 |
Condition 2.10 |
Final Landscape Plan (Rev. D2) |
7 August 2018 |
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
3.1.11.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.8 and Table 3.9.
Table
3.8 Cumulative Summary
of Valid Licences and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference
No. |
Issued
Date |
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Registration as a Chemical Waste
Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Construction Noise Permit |
N/A |
N/A |
N/A |
N/A |
Water Discharge License (Discharge
at TS1) |
WT00024874-2016 |
20 Jul 2016 |
20 Jul 2016 to 31 Mar 2021 |
Valid |
Table
3.9 Summary of
submission status under FEP-06/364/2009/A
EP
Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
11 Mar
2011 |
Amendment for Management
Organization of Main Construction Companies |
16 May
2011 |
|
Condition 2.7 |
Works Schedule |
15 Mar
2011 |
Condition 2.8 |
Location Plan |
15 Mar
2011 |
Condition 2.9 |
Noise Management Plan |
6 May
2011 |
Condition
2.10 |
Landscape
Plan (Rev.5) |
25 Jan 2018 |
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
3.1.12.
The current status on licences and/or permits
on environmental protection pertinent and submission
under FEP-07/364/2009/D for contract no. HY/2009/19 are shown in Table 3.10 and Table
3.11.
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19