Contract No: HY/2019/18 Wanchai
Development Phase II and Central Wanchai Bypass Sampling, Field
Measurement and Testing Works (Stage 4) ENVIRONMENTAL PERMIT NO. EP-376/2009 and Further
Environmental Permit NO. FEP-01/376/2009 and FEP-02/376/2009 Final environmental monitoring & audit Review
report
FOR WDII project works for Road P2 under CEDD |
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 19/F, Remex Centre 42
Wong Chuk Hang Road, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond
Dai Environmental
Team Leader |
|
19 December 2023 |
|
|
|
|
2.2 Scope of the Project and Site Description
2.3 Project Organization and Contact Personnel
4.2 Air Quality Monitoring Results
6 Complaints,
Notification of Summons and Prosecution
7.1 Construction
of the Project
lIST OF FIGUREs
Figure 3.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
3.0 Layouts of Representative Noise and
Air Sensitive Receivers
Appendix
3.1 Action and Limit Level
Appendix
4.0 Event Action Plans
Appendix
4.1 Noise Monitoring Graphical
Presentations
Appendix
4.2 Air Quality Monitoring Graphical
Presentations
Appendix 5.1 Environmental Mitigation Implementation
Schedule
EXECUTIVE SUMMARY
i.
This
is the Final Environmental Monitoring and Audit (EM&A) Review Report
prepared by Lam Geotechnics Limited for Wan Chai Development Phase II and
Central-Wan Bypass ¡V Sampling, Field Measurement and Testing work under
EM&A manual for Environmental Permit no. EP-376/2009. This report presents the environmental monitoring
and audit findings during the period of May 2015 to November 2023.
Major construction works under taken during
construction phase monitoring programme
ii.
The
key purpose of the study area encompasses the Wan Chai harbourfront area. The
area starts at the boundary of Central Reclamation Phase III (CRIII) at the
west and connects to the existing Hung Hing Road at the east. The scope of the
project includes:
¡P
A dual 2-lane primary distributor
road, Road P2, approximately 0.6km in length; and
¡P
Other new primary and district
distributor roads connecting to the slip roads of the Central-Wan Chai Bypass
with a total length of approximately 0.7km.
iii.
The
project also contains Schedule 2 DP that, under the EIAO, require Environmental
Permits (EPs) to be granted by the DEP before they may be either constructed or
operated. Below table summarises the DP
under this Project.
Item |
Designated
Project |
EIAO
Reference |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
iv.
The
designated project work II (DP2) was awarded to China State ¡V Build King Joint
Venture HK/2012/08 (Contract Title: Wan Chai Development Phase II Central ¡V Wan
Chai Bypass at Wan Chai West) as part of the Project works by the Civil
Engineering and Development Department (CEDD). The construction work under
Contract no. HK/2012/08 was commenced on 13 May 2015.
Environmental Monitoring and Audit Works
v.
Summary table of the impact monitoring activities is listed below:
Noise Monitoring Station |
Commencement Date |
Suspension Date |
M1a ¡V Harbour Road Sports Centre / Footbridge for Harbour
Road Sports Centre |
19 May 2015 |
23 March 2019 |
Air Quality Monitoring Station |
Commencement Date |
Suspension Date |
CMA5a / CMA5b ¡V Children Playgrounds opposite to Pedestrian
Plaza / Pedestrian Plaza |
18 May 2015 |
26 March 2019 |
CMA 6a-WDII PRE Office |
18 May 2015 |
26 March 2019 |
Waste Management
vi.
No waste
generation were reported under EP-376/2009.
Complaints, Notifications of Summons and Successful
Prosecutions
vii.
No environmental
complaints were received in the reporting period. No notification of summons
and successful prosecutions were received in the reporting period.
Site
Inspections and Audit
viii.
The
weekly site inspections were conducted according to EM&A manual requirement
throughout the construction period. No non-compliance
from the site audits was recorded throughout the reporting period.
Conclusion
ix.
The
EM&A programme were found to be effective in monitoring impacts arising
from the Project. The findings of the environmental monitoring program suggest
that no adverse impacts on sensitive receivers at the designated monitoring
locations were brought about the Project.
x.
In
conclusion the Project was environmentally acceptable in terms of air quality
and noise impact.
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed under
Contract HY/2019/18 ¡V Wan Chai Development Phase II and Central Wan Chai Bypass
¡V Sampling, Field Measurement and Testing works (Stage 4) to work as the Environmental Team (ET) under Environmental Permit nos. FEP-01/376/2009
and FEP-02/376/2009 of Environmental Permit no. EP-376/2009 to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2.
SCL Contractor has been granted a further environmental permit
(FEP-03/376/2009) on 02 June 2020 to undertake the construction of part of other
part of the Road P2 and other roads which are classified as primary/district
distributor roads which are implemented and reported by a separate ET/IEC of
SCL Contractor.
1.1.3.
This report presents the environmental monitoring and audit findings during
the period of May 2015 to November 2023 covers the work areas FEP-01/376/2009 and
FEP-02/376/2009 of EP-376/2009, as listed in Section 1.1.1.
Section 1 Introduction ¡V details the scope and structure of the report.
Section 2 Project Background ¡V summarizes background and scope of the project, site
description, project organization and contact details of key personnel during
the reporting period.
Section 3 Monitoring Requirements ¡V summarizes all monitoring parameters, monitoring
methodology and equipment, monitoring locations, monitoring frequency, criteria
and respective event and action plan and monitoring programmes.
Section 4 Monitoring Results ¡V summarizes the monitoring results and exceedances recorded
throughout the monitoring programme.
Section 5 Environmental Site Audit ¡V summarizes the findings of site inspections undertaken during
the construction period, with a review of any relevant follow-up actions during the construction period.
Section 6 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on
complaints, notification of summons and prosecution.
Section 7 Conclusion
2.1.1.
Wan Chai Development phase II and Central-Wan Chai Bypass (hereafter
called ¡§the Project¡¨) are Designated Project (DP) under the Environmental
Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) has been approved on 11 December 2008.
2.2.1.
The design and construction of Wan Chai Development Phase II and Central
Wanchai Bypass involves the construction and operation of primary and district
distributor roads is shown in Figure 2.1.
2.2.2.
The key purpose of the study area encompasses the Wan Chai harbourfront
area. The area starts at the boundary of Central Reclamation Phase III (CRIII)
at the west and connects to the existing Hung Hing Road at the east. The scope
of the project includes:
¡P
A dual 2-lane primary distributor
road, Road P2, approximately 0.6km in length; and
¡P
Other new primary and district
distributor roads connecting to the slip roads of the Central-Wan Chai Bypass
with a total length of approximately 0.7km.
2.2.3.
The project also contains Schedule 2 DP that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the DP under this
Project. Figure 2.1 shows the locations of this Schedule 2 DP.
Table 2.1 Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
2.2.4.
The designated project work II (DP2) was awarded to China State ¡V Build
King Joint Venture HK/2012/08 (Contract Title: Wan Chai Development Phase II
Central ¡V Wan Chai Bypass at Wan Chai West) as part of the Project works by the
Civil Engineering and Development Department (CEDD). The construction work
under Contract no. HK/2012/08 was commenced on 13 May 2015.
2.3.1.
Civil Engineering and Development Department and Highway Department are
the overall project controllers for the Wan Chai Development Phase II and
Central-Wan Chai Bypass respectively. For the construction phase of the
Project, Project Engineer, Contractor(s), Environmental Team and Independent
Environmental Checker are appointed to manage and control environmental issues.
2.3.2.
The proposed project organization, key parties and roles are summarized
in Table 2.2:
Table 2.2 Contact Details of Key Parties and Roles
Party |
Role |
CEDD |
Project Proponent / Permit Holder |
AECOM |
Engineer¡¦s Representative for WDII |
China State - Build King JV |
Contractor of Contract no. HK/2012/08 (the permit holder of FEP-01/376/2009 and |
Ramboll Hong Kong Limited |
Independent Environmental Checker |
Lam Geotechnics Limited |
Environmental Team |
2.3.3 Contract HK/2012/08 under CEDD is the
main works contract to construct part of the Road P2 and other roads as
indicated in Figure 2.1, has been granted FEP-01/376/2009 and FEP-02/376/2009
on 31 March 2015 and 01 August 2016 respectively. The construction works were
commenced on 13 May 2015.
2.3.4 As confirmed by Engineer¡¦s
Representative, Contract HK/2012/08 had completed construction works on 31
March 2020 and the corresponding FEP-01/376/2009 and FEP-02/376/2009 were
surrendered on 06 April 2020.
Noise Monitoring Stations
3.1.1
The noise monitoring stations for the Project are listed in Table 3.1
and shown in Figure 3.1. Corresponding
noise sensitive receivers as identified in EIA can be referred to Appendix
3.0. Appendix 3.1
shows the established Action/Limit Levels for the monitoring works.
Table 3.1 Noise Monitoring Station
Station |
Description |
M1a* |
Harbour
Road Sports Centre / Footbridge for Harbour Road Sports Centre (M1a)* Rooftop
of Wan Chai Ferry Pier (M1b, alternative to M1a due to Shatin Central Link
construction)** |
Remark*: With respect to the demolition of
Ex-Harbour Road Sports Centre, the respective noise monitoring station M1a ¡V
Harbour Road Sports Centre were finely adjusted to the Footbridge for Harbour
Road Sports after May 2017.
Remark**: The monitoring station M1a was relocated
as M1b ¡V Rooftop of Wan Chai Ferry Pier on 2 November 2020.
Noise Monitoring Parameters, Frequency and Duration
3.1.2
The construction noise level was
measured in terms of the A-weighted equivalent continuous sound pressure level
(Leq). Leq (30 minutes) was used as the monitoring
parameter for the time period between 0700 and 1900 hours on normal weekdays.
For all other time periods, Leq (5 minutes) was employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for
data auditing, statistical results such as L10 and L90 were also obtained for
reference.
3.1.3
Noise monitoring was carried out at all the designated monitoring
stations. The monitoring frequency depended on the scale of the construction
activities. The following is an initial guide on the regular monitoring
frequency for each station on a weekly basis when noise generating activities
were underway:
¡P
One
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.4
If construction works were extended to include works during the hours of
1900 ¡V 0700 as well as public holidays and Sundays, additional weekly impact
monitoring was carried out during respective restricted hour¡¦s periods.
Monitoring Equipment
3.1.5
As referred to the Technical Memorandum ? issued under the NCO, sound
level meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications were used
for carrying out the noise monitoring. Immediately prior to and following each
noise measurement the accuracy of the sound level meter was checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements were accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.6
Noise measurements was not carried out in fog, rain, wind with a steady
speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed was
checked with a portable wind speed meter capable of measuring the wind speed in
m/s.
Air Quality Monitoring Stations
3.2.1
The air monitoring stations for the Project are listed in Table 3.2 and shown in Figure 3.1. Corresponding air sensitive receivers as
identified in EIA can be referred to Appendix
3.0. Appendix 3.1
shows the established Action/Limit Levels for the monitoring works.
Table 3.2 Air
Monitoring Station
Station ID |
Monitoring
Location |
Description |
CMA5b |
Pedestrian Plaza |
Wan Chai |
CMA6a |
WDII PRE Office |
Wan Chai |
Air Monitoring Parameters, Frequency and Duration
3.2.2
One-hour and 24-hour TSP levels were measured to indicate the impacts of
construction dust on air quality. The 24-hour TSP level was measured by
following the standard high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
3.2.3
All relevant data including temperature, pressure, weather conditions,
elapsed-time meter reading for the start and stop of the sampler,
identification and weight of the filter paper, and any other local atmospheric
factors affecting or affected by site conditions, etc., were recorded down in
detail.
3.2.4
For regular impact monitoring, the sampling frequency of at least once
in every six-days, was strictly observed at all the monitoring stations for
24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at
least three times in every six-days was undertaken when the highest dust impact
occurred.
Sampling Procedure and Monitoring Equipment
3.2.5
High volume samplers (HVSs) in compliance with the following
specifications were used for carrying out the 1-hour and 24-hour TSP
monitoring:
¡P
0.6
¡V 1.7 m3 per minute adjustable flow range;
¡P
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
¡P
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
¡P
capable
of providing a minimum exposed area of 406 cm2;
¡P
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
¡P
equipped
with a shelter to protect the filter and sampler;
¡P
incorporated
with an electronic mass flow rate controller or other equivalent devices;
¡P
equipped
with a flow recorder for continuous monitoring;
¡P
provided
with a peaked roof inlet;
¡P
incorporated
with a manometer;
¡P
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
¡P
easily
changeable filter; and
¡P
capable
of operating continuously for a 24-hour period.
3.2.6
Initial calibration of dust monitoring equipment was conducted upon
installation and thereafter at bi-monthly intervals. The transfer standard was
traceable to the internationally recognized primary standard and be calibrated
annually. The concern parties such as IEC was properly document the calibration
data for future reference. All the data was converted into standard temperature
and pressure condition.
Laboratory Measurement / Analysis
3.2.7
A clean laboratory with constant temperature and humidity control, and
equipped with necessary measuring and conditioning instruments to handle the
dust samples collected, was available for sample analysis, and equipment
calibration and maintenance. The laboratory was HOKLAS accredited.
3.2.8
An alternative non-HOKLAS accredited
laboratory was set-up for carrying out the laboratory analysis,
the laboratory equipment was approved by the ER on
8 February 2011 and
the measurement procedures were witnessed by the IEC. Any measurement
performed by the laboratory was demonstrated to the satisfaction of the
ER and IEC. IEC was regularly audit to the measurement performed by the
laboratory to ensure the accuracy of measurement results.
3.2.9
Filter paper of size 8¡¨ x 10¡¨ was labelled before sampling. It was a
clean filter paper with no pinholes, and conditioned in a humidity-controlled
chamber for over 24-hours and pre-weighed before used for the sampling.
3.2.10
After sampling, the filter paper loaded with dust was kept in a clean
and tightly sealed plastic bag. The filter paper was then returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance was regularly calibrated against a traceable standard.
3.2.11
All the collected samples were kept in a good condition for 6 months
before disposal.
4.0.1 The Event Action Plan for
construction noise, air quality and water quality are presented in Appendix 4.0.
Table 4.1 Summary of noise limit level
exceedances
Year |
Limit level |
M1a |
Total |
2015 |
Non-Project
related |
5 |
5 |
Project
related |
0 |
||
2016 |
Non-Project
related |
17 |
17 |
Project
related |
0 |
||
2017 |
Non-Project
related |
17 |
17 |
Project
related |
0 |
||
2018 |
Non-Project
related |
5 |
5 |
Project
related |
0 |
||
2019 |
Non-Project
related |
0 |
0 |
Project
related |
0 |
4.1.2
The major construction activities involved site preparation works,
excavation, utilities and drainage works in 2015 (since May 2015). Total 5
limit level exceedance was recorded in the reporting period. After the
investigation, the exceedances were concluded as non-project related. No action level exceedance were confirmed
from noise complaints received in 2015.
4.1.3
The major construction activities involved utilities and drainage works in
2016. Total 17 limit level exceedance was recorded in the reporting period. After
the investigation, the exceedances were concluded as non-project related. No action level exceedance were confirmed
from noise complaints received in 2016.
4.1.4
The major construction activities involved drainage and road works in
2017. Total 17 limit level exceedances were recorded in the reporting period.
After the investigation, the exceedances were concluded as non-project related.
No action level exceedance related to
noise complaint was recorded in 2017.
4.1.5
The major construction activities involved drainage, road and asphalt
paving works in 2018. Total 5 limit level exceedances were recorded in the
reporting period. After the investigation, the exceedances were concluded as
non-project related. No action level
exceedance related to noise complaint was recorded in 2018.
4.1.6
The major construction activities involved drainage, road and
landscaping works in 2019. No limit level exceedance was recorded in scheduled
noise monitoring in the reporting period. No action level exceedance were
confirmed from noise complaints received in 2019.
4.1.7
Details of graphical presentation of noise monitoring result can refer
to Appendix
4.1. The complaint investigation shall refer to Appendix
4.1.
4.2.1
The air quality monitoring exceedances in reporting period is summarized
in Table
4.2.
Table 4.2 Summary of air quality exceedances
Year |
Parameter |
CMA 5b |
CMA 6a |
Total |
2015 |
24hr TSP |
0 |
0 |
0 |
1hr TSP |
0 |
0 |
||
2016 |
24hr TSP |
1LL |
0 |
6 |
1hr TSP |
5AL |
0 |
||
2017 |
24hr TSP |
3AL / 1LL |
0 |
22 |
1hr TSP |
14AL / 4LL |
0 |
||
2018 |
24hr TSP |
0 |
0 |
1 |
1hr TSP |
1AL |
0 |
||
2019 |
24hr TSP |
0 |
0 |
1 |
1hr TSP |
1AL |
0 |
4.2.2
The major construction activities involved site preparation works,
excavation, utilities and drainage works in 2015 (since May 2015). No exceedance
was recorded in the reporting period.
4.2.3
The major construction activities involved utilities and drainage works in
2016. Total 1 limit level of 24hr TSP
and 5 action level of 1hr TSP exceedances were recorded in the reporting
period. After the investigation, the
exceedances were concluded as non-project related.
4.2.4
The major construction activities involved drainage and road works in
2017. Total 3 action level and 1 limit level of 24hr TSP whereas 14 action
level and 4 limit level of 1hr TSP exceedances were recorded in the reporting
period. After the investigation, the
exceedances were concluded as non-project related.
4.2.5
The major construction activities involved drainage, road and asphalt
paving works in 2018. Total 1 action and no limit level of 1hr TSP was recorded
in the reporting period. After the investigation, the exceedances were
concluded as non-project related.
4.2.6
The major construction activities involved drainage, road and
landscaping works in 2019. Total 1 action level and no limit level of 1hr TSP
exceedances was recorded in the reporting period. After the investigation, the
exceedances were concluded as non-project related.
4.2.7
Details of graphical presentation of air monitoring result can referred
to Appendix 4.2.
4.3.1
No waste generation were reported for FEP-01/376/2009
and FEP-02/376/2009 under EP-376/2009.
5.0.1
Site audit was carried out by
representatives of the Contractor, Engineer and ET on weekly basis to monitor
the timely implementation of proper environmental management practices and
mitigation measures in the Project site. The representative of the IEC joined
the site inspections once per month.
5.0.2
No non-compliance was recorded
during the site inspections throughout the construction period. Observations
and recommendations recorded during the site inspections were summarized in
each of the EM&A reports.
5.0.3
According to EIA Study Report,
Environmental Permit and EM&A Manual of the Project, the mitigation
measures detailed in the documents were recommended to be implemented during
the construction phase. A summary of the Environmental Mitigation
Implementation Schedule (EMIS) is provided in Appendix 5.1.
5.1.1
As confirmed by ER, all landscape
works for FEP-01/376/2009
and FEP-02/376/2009 under
EP-376/2009 were completed during constructions phase; 12-month Landscape
Establishment Monitoring on planting works by ET in quarterly basis as per
requirement under the EM&A manual has been completed.
5.1.2
The planting works for FEP-01/376/2009 and FEP-02/376/2009
associated with
EP-376/2009 were monitored during the 12-month Establishment Landscape
Monitoring period to ensure the compliance with the intended aims of the
measures.
5.1.3
Shrubs planting, new trees,
transplanted trees and compensatory trees planted were provided as per the
design in the operation landscape plan submitted under EP-376/2009.
5.1.4
5-year Long-term Operation
Landscape Monitoring for the part of project under WDII project works associated
with EP-376/2009 has been carried out and the implementation are summarized in Table
5.1.
Table 5.1 Summary
Table of Landscape Monitoring Implementation
FEP
No. |
Contract
No. & Title |
Landscape
Establishment Monitoring implementation |
Long-term
Landscape Operation Monitoring implementation1 |
FEP-01/376/2009,
FEP-02/376/2009 |
Contract
No. HK/2012/08: Wan Chai Development Phase II- Central-Wan Chai Bypass at Wan
Chai West |
January
2020 ¡V January 2021 (completed by ET) |
January
2020 ¡V January 2024 (completed by ET) February
2024 (to be
completed by LCSD) |
6.0.1
No complaints were recorded with
respect to construction of Road P2 in the reporting period.
6.0.2
No summons nor successful
prosecutions were recorded in the reporting period.
6.0.3
The details of cumulative
complaint log and updated summary of complaints are presented in Appendix
6.1.
6.0.4
Cumulative statistic on
complaints and successful prosecutions are summarized in Table 6.1
and Table 6.2 respectively.
Table 6.1 Cumulative
Statistics on Complaints
Reporting
Period |
No.
of Complaints |
May 2015 (construction commencement) to Nov 2023 |
0 |
Total |
0 |
Table 6.2 Cumulative Statistics on
Successful Prosecutions
Environmental
Parameters |
Cumulative
No. Brought Forward |
No.
of Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
Air |
0 |
0 |
0 |
Noise |
0 |
0 |
0 |
Water |
0 |
0 |
0 |
Waste |
0 |
0 |
0 |
Total |
0 |
0 |
0 |
7.0.1
The Project was implemented in
accordance with the conditions stipulated in the Environmental Permits.
7.0.2
Construction works of all the
contracts under the Project were completed with FEP surrender application
submitted. The details are summarized in Table 7.1.
Table 7.1 Details of
Individual Contracts under the Project
Contract
No. |
Associated
DP(s) |
Date
of Work Completion
Date (with FEP surrender) / Substantial Completion
Date |
HK/2012/08 |
DP2 |
Construction works was completed with FEP-01/376/2009 & FEP-02/376/2009
surrendered by contractor and found in order by EPD on 06 April 2020. |
Remarks: SCL Contractor has granted FEP-03/376/2009 on 2 June 2020 to
undertake the construction of part of the Road P2 under EP376/2009. EM&A
works associated with FEP-03/376/2009 shall be implemented and reported by a
separate ET/IEC of SCL Contractor.
Validity
of EIA Predictions
7.2.1
It is predicted in the EIA reports that with the implementation of the
recommended mitigation measures, there would be no unacceptable nor residual noise,
air and water quality impacts arising from the Project-related construction
works.
Comments
on Overall EM&A programme
7.2.2
The mitigation measures detailed in the Environmental Permit, the
EM&A Manual and the EIA report were implemented throughout the whole
project period. With the environmental monitoring and site inspection to
directly ensure the timely implementation of mitigation measures during the
Project, the environmental performance of the Project was acceptable. Analysis
of all EM&A data collected throughout the construction periods also
demonstrated the environmental acceptability of the Project.
7.2.3
The overall performance of the monitoring methodology adopted and
environmental management system in this Project was effective.
Overall
EM&A Data
7.2.4
Baseline and impact air and noise monitoring were carried out according
to the requirements in the EM&A Manual. The monitoring data analysis shown
that the environmental conditions generally return to baseline condition.
Conclusions
7.2.5
The EM&A programme was found to be effective in monitoring impacts
arising from the Project. The findings of the environmental monitoring
programme suggest that no adverse impacts on sensitive receivers were brought
about by the Project. In conclusion, the Project was environmentally acceptable
in terms of noise, air quality and water discharge and waste disposal.
7.2.6
With the success of the overall EM&A programme, the deterioration of
the environment caused by the Project was cost-effectively identified and
necessary prompt effective mitigation measures were implemented to avoid any
unacceptable impacts.