Contract No:
HK/2009/05 Wanchai Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing Work
(Stage 1) Environmental
Permit no. EP-356/2009, Further Evironmental permit nos. fep-01/356/2009,
fep-02/356/2009 and FEP-03/356/2009 Monthly Environmental Monitoring
& Audit Report
- August
2010 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai,
H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED
by: |
|
                         Raymond Dai Environmental Team Leader |
|
DATE: |
|
9 September 2010 |
1.1    Scope
of the Report
1.2    Structure
of the Report
2.   Project Background
2.1    Background
2.2    Scope
of the Project and Site Description
2.3    Division
of the Project Responsibility
2.4    Project
Organization and Contact Personnel
3.   status of regulatory compliance
3.1    Status
of Environmental Licensing and Permitting under the Project
4.   Monitoring Requirements
4.1    Noise
Monitoring
4.2    Air
Monitoring
4.3    Water
Quality Monitoring
5.   Monitoring Results
5.1    Noise
Monitoring Results
5.2    Air
Monitoring Results
5.3    Water Monitoring
Results
5.4    Waste
Monitoring Results
6.1    Noise
Monitoring
6.2    Air
Monitoring
6.3    Water
Quality Monitoring
6.4    Review
of the Reasons for and the Implications of Non-compliance
6.5    Summary
of action taken in the event of and follow-up on non-compliance
7.   Cumulative Construction Impact due to the Concurrent Projects
9.   Complaints, Notification
of Summons and Prosecution
lIST OF
TABLES
Table I      Summary of Water Quality Monitoring
Exceedances in Reporting Month
Table 2.1    Schedule 2 Designated Projects under this
Project
Table 2.2   Details of Individual Contracts under the
Project
Table 2.3   Contact Details of Key Personnel
Table 3.3   Summary of submission status under
FEP-01/356/2009 Condition
Table 3.5   Summary of submission status under
FEP-02/356/2009 Condition
Table 3.7   Summary of submission status under
FEP-03/356/2009 Condition
Table 4.1   Noise Monitoring Station
Table 4.2   Air Monitoring Station
Table 4.3    Marine Water Quality Stations for Water
Quality Monitoring
Table 4.4   Marine Water Quality Monitoring Frequency
and Parameters
Table 5.1    Noise Monitoring Stations for Contract
no. HY/2009/11
Table 5.2    Noise Monitoring Station for Contract nos.
HK/2009/01 and HK/2009/02
Table 5.3    Air Monitoring Stations for Contract no.
HY/2009/11
Table 5.4    Air Monitoring Stations for Contract no.
HK/2009/01
Table 5.5    Air Monitoring Station for Contract no.
HK/2009/02
Table 5.6    Water Monitoring Stations for Contract
no. HY/2009/11
Table 5.7    Water Monitoring Stations for Contract no.
HK/2009/01
Table 5.8    Water Monitoring Stations for Contract no.
HK/2009/02
Table 5.9    Summary of Water Quality Monitoring
Exceedances in Reporting Month
Table 5.10  Details of Waste Disposal for Contract no.
HY/2009/11
Table 5.11  Details of Waste Disposal for Contract no.
HK/2009/01
Table 5.12  Details of Waste Disposal for Contract no.
HK/2009/02
Table 8.1   Summary of Environmental Inspections for
Contract no. HY/2009/11
Table 8.2    Summary of Environmental Inspections for
Contract no. HK/2009/01
Table 8.3    Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 9.1   Cumulative Statistics on Complaints
Table 9.2   Cumulative Statistics on Successful
Prosecutions
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table I ><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of Water Quality
Monitoring Exceedances in Reporting Month><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 2.1 ><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Schedule 2 Designated
Projects under this
Project><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 2.2><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Details of Individual
Contracts under the Project><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 2.3><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Contact Details of Key
Personnel><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 3.1><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of the current status
on licences and/or permits on environmental protection pertinent to the Project><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 3.2><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/11><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 3.3><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of submission status
under FEP-01/356/2009 Condition><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 3.4><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/01><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 3.5><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of submission status under
FEP-02/356/2009 Condition><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 3.6><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 3.7><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of submission status
under FEP-03/356/2009 Condition><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 4.1><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Noise Monitoring Station><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 4.2><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Air Monitoring Station><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 4.3 ><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Marine Water Quality Stations
for Water Quality Monitoring><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 4.4><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Marine Water Quality
Monitoring Frequency and Parameters><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.1 ><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Noise Monitoring Stations for
Contract no. HY/2009/11><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.2 ><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Noise Monitoring Station for Contract nos. HK/2009/01 and
HK/2009/02><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.3 ><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Air Monitoring Stations for
Contract no. HY/2009/11><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.4 ><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Air Monitoring Stations for
Contract no. HK/2009/01><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.5 ><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Air Monitoring Station for
Contract no. HK/2009/02><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.6 ><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Water Monitoring Stations for Contract
no. HY/2009/11><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.7 ><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Water Monitoring Stations for
Contract no. HK/2009/01><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.8 ><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Water Monitoring Stations for
Contract no. HK/2009/02><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.9 ><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of Water Quality
Monitoring Exceedances in Reporting Month><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.10><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Details of Waste Disposal for
Contract no. HY/2009/11><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.11><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Details of Waste Disposal for
Contract no. HK/2009/01><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 5.12><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Details of Waste Disposal for
Contract no. HK/2009/02><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 8.1><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of Environmental
Inspections for Contract no. HY/2009/11><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 8.2 ><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of Environmental
Inspections for Contract no. HK/2009/01><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 8.3 ><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of Environmental
Inspections for Contract no. HK/2009/02><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 9.1><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Cumulative Statistics on
Complaints><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 9.2><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Cumulative Statistics on
Successful Prosecutions><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 10.1><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Construction Activities and
Recommended Mitigation Measures in Coming Reporting Month><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Table 10.2><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">  >< cite="mailto:Lam20100204" datetime="2010-09-07T20:04">Summary of Key Construction
Activities of Individual Contract(s) to be commenced in Coming Reporting Month><
cite="mailto:Lam20100204" datetime="2010-09-07T20:04">
lIST OF FIGUREs
Figure
2.1     Project
Layout
Figure
2.2     Project
Organization Chart
Figure 4.1      Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1   Environmental Mitigation Implementation
Schedule
Appendix 4.1   Action
and Limit Level
Appendix
4.2   Copies of Calibration
Certificates
Appendix
5.1   Monitoring Schedule for
Reporting Month and Coming month
Appendix 5.2   Noise Monitoring Results and Graphical
Presentations
Appendix 5.3   Air Quality Monitoring Results and Graphical Presentations
Appendix
5.4   Water
Quality
Monitoring Results and Graphical Presentations
Appendix 6.1   Event
Action Plans
Appendix 6.2   Summary for Notification of Exceedance< cite="mailto:Lam20100204" datetime="2010-09-07T20:05"> >
Appendix
9.1   Complaint Log
Appendix 10.1  Construction
Programme of Individual Contracts
i.
This is the Environmental
Monitoring and Audit (EM&A) Monthly Report  /span> August 2010 for
Contract No. HK/2009/05 –Wanchai Development Phase II and Central Wanchai
Bypass - Sampling,
Field Measurement and Testing Work (Stage 1). 
This report presents the environmental monitoring findings and
information recorded during the period 28th July 2010 to 27th
August 2010. The cut-off date of reporting is at 27th of
each reporting month.
Construction Activities for the
Reported Period
ii.
During this reporting period,
the major work activities for Contract no. HY/2009/11 included:
< cite="mailto:Lam20100204" datetime="2010-09-03T15:01"> -
><
cite="mailto:Lam20100204" datetime="2010-09-03T15:01"> >< cite="mailto:Lam20100204" datetime="2010-09-03T15:01">
 -
Construction of Rock
Mound,
 -
Floating Out of Caisson
Seawall,
 -
Installation of Caisson
Seawall,
 -
Dredging works,
 -
Filling works;
 -
Laying of geo-textile,
 -
Drainage Works; and
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:14"> -
>Seawall Block Installation<
cite="mailto:Lam20100204" datetime="2010-09-07T14:14">
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:14">Construction of Rock
Mound,
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:14"> -
><
cite="mailto:mansonyeung" datetime="2010-09-04T12:14">Floating Out of Caisson
Seawall,
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:14"> -
><
cite="mailto:mansonyeung" datetime="2010-09-04T12:14">Installation of Caisson
Seawall,
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:14"> -
><
cite="mailto:mansonyeung" datetime="2010-09-04T12:14">Dredging works,>< cite="mailto:mansonyeung"
datetime="2010-09-04T12:14">
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:14"> -
><
cite="mailto:mansonyeung" datetime="2010-09-04T12:14">Filling works><
cite="mailto:mansonyeung" datetime="2010-09-04T12:14">
< cite="mailto:mansonyeung"
datetime="2010-09-04T12:14"> -
><
cite="mailto:mansonyeung" datetime="2010-09-04T12:14">Laying of geo-textile,
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:14"> -
><
cite="mailto:mansonyeung" datetime="2010-09-04T12:14">Drainage Works and
 -
< cite="mailto:mansonyeung"
datetime="2010-09-04T12:14">Seawall Block Installation>
iii.
During this reporting
period, the major work activities for Contract no. HK/2009/01 included:
< cite="mailto:Lam20100204" datetime="2010-09-03T14:58"> -
>< cite="mailto:Lam20100204" datetime="2010-09-03T14:58"> >< cite="mailto:Lam20100204" datetime="2010-09-03T14:58">
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:18"> -
><
cite="mailto:Lam20100204" datetime="2010-09-07T14:18">Erection of interim
Engineer’s Principal Office at Works areas WA2 was completed for moving-in on 5
Aug 10.
 -
Erection of interim
Engineer’s Principal Office at Works areas WA2
 -
Modification of CATV
combine service inspection chamber
 -
Installation of staging
piles for trial bored pile was completed and bored pile construction
 -
Marine site investigation
 -
Dredging works for cross
harbour watermains
 -
Dismantling of existing
sloping seawall and removal of armor rock at north-west side of water channel
is stopped and reinstating the rock slope at seawall
 -
Hoarding erection at Tsim
Sha Tsui Salisbury Garden area
 -
18m of artwork panel is
installed as design for other location
 -
Trial pits construction
for determination of pipeline alignment at Convention Avenue
 -
Fabrication of straight
sections of cross harbour submarine pipes and land water pipes
 -
Elbow sections of cross
harbour submarine pipes are being fabricated.
 -
The assemble of 6 nos. of
tailor made flat top barge was commenced on 14 Aug 10. The fabrication of
dredging crane was completed and will be installed on the tailor make flat top
barge on 21 Aug 10 and ready for dredging by 15 Sept 10 tentatively.
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:17">Modification of CATV combine service inspection
chamber is ongoing.
iv. >>>>>>>
>>>>>>>>>>>>>
>During this reporting
period, the major work activities for Contract no. HK/2009/02 included:
 -
Hoarding Erection;
 -
Pre-bored H-piles, ELS
and excavation at WSD Pumping Station;
 -
Construction of Salt
Water Intake Culvert at Pet Garden;
 -
Road Modification Works;
 -
Construction of Cooling Mains
Along Public Road;
 -
Construction of Temporary
Seawall;
 -
Dredging for WCR 1;
 -
Tree Transplanting; and
 -
Equipments Procurement
for TKO 137
< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">S><
cite="mailto:mansonyeung" datetime="2010-09-04T12:20">ite >< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">C><
cite="mailto:mansonyeung" datetime="2010-09-04T12:20">learance>< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">
< cite="mailto:mansonyeung"
datetime="2010-09-04T12:20"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Hoarding >< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">E><
cite="mailto:mansonyeung" datetime="2010-09-04T12:20">rection>< cite="mailto:mansonyeung"
datetime="2010-09-04T12:20">
< cite="mailto:mansonyeung"
datetime="2010-09-04T12:20"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Pre-bored H-piles, ELS
and excavation at WSD Pumping Station><
cite="mailto:mansonyeung" datetime="2010-09-04T12:20">
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:20"> />< cite="mailto:mansonyeung"
datetime="2010-09-04T12:20">Construction of >< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Salt
Water Intake Culvert at Pet Garden>< cite="mailto:mansonyeung"
datetime="2010-09-04T12:20">
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:20"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Road >< cite="mailto:mansonyeung"
datetime="2010-09-04T12:20">M><
cite="mailto:mansonyeung" datetime="2010-09-04T12:20">odification Works>< cite="mailto:mansonyeung"
datetime="2010-09-04T12:20">
< cite="mailto:mansonyeung"
datetime="2010-09-04T12:20"> />< cite="mailto:mansonyeung"
datetime="2010-09-04T12:20">Construction of Cooling Mains Along Public Road><
cite="mailto:mansonyeung" datetime="2010-09-04T12:20">
< cite="mailto:mansonyeung"
datetime="2010-09-04T12:20"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Construction of >< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">T><
cite="mailto:mansonyeung" datetime="2010-09-04T12:20">emporary >< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">S><
cite="mailto:mansonyeung" datetime="2010-09-04T12:20">eawall>< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">
< cite="mailto:mansonyeung"
datetime="2010-09-04T12:20"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">D><
cite="mailto:mansonyeung" datetime="2010-09-04T12:20">redging>< cite="mailto:mansonyeung" datetime="2010-09-04T12:20"> for
WCR 1>< cite="mailto:mansonyeung"
datetime="2010-09-04T12:20">
< cite="mailto:mansonyeung"
datetime="2010-09-04T12:20"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Tree
Transplanting>< cite="mailto:mansonyeung"
datetime="2010-09-04T12:20">
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:19"> />< cite="mailto:mansonyeung" datetime="2010-09-04T12:20">Equipments
>< cite="mailto:mansonyeung"
datetime="2010-09-04T12:20">Procurement><
cite="mailto:mansonyeung" datetime="2010-09-04T12:20"> for TKO 137>< cite="mailto:Lam20100204"
datetime="2010-09-07T14:19">
Noise Monitoring
v.
Noise monitoring during
day time and evening time were conducted at the City Garden, Victoria Centre and
Harbour Road Sports Center on a weekly basis in the reporting month. Two action level
exceedances were recorded due to the receipt of two noise complaints dated 31 July and 12 August
2010 regarding
the noise nuisance generated from the dredging works at North Point. Three limit level exceedances were recorded at Harbour Road Sports
Centre on 3,
10 and 17 August 2010 during the evening time period.  /span>Investigation found that exceedances were not related to the Project. < cite="mailto:mansonyeung" datetime="2010-09-02T19:18">Noise
monitoring during >< cite="mailto:mansonyeung"
datetime="2010-09-02T19:18">day time and evening time>< cite="mailto:mansonyeung" datetime="2010-09-02T19:18"> were
conducted at the City Garden on a weekly basis in the reporting period. >< cite="mailto:mansonyeung" datetime="2010-09-02T19:18">Two
limit level exceedances were recorded at M4a on 20 and 27 July 2010 during
restricted hours. Investigation found that is not project related exceedances. >< cite="mailto:mansonyeung"
datetime="2010-09-02T19:18">Reviewed the past monitoring results and
observation at Station M4a, Victoria Centre (Station ID: M4b) is proposed as
alternative noise monitoring ><
cite="mailto:mansonyeung" datetime="2010-09-02T19:18">station>< cite="mailto:mansonyeung" datetime="2010-09-02T19:18"> from
August 2010.>
< cite="mailto:Lam20100204"
datetime="2010-09-07T20:10"> >< cite="mailto:Lam20100204" datetime="2010-09-07T20:10">
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:23">Noise monitoring during
daytime>< cite="mailto:Lam20100204"
datetime="2010-09-07T14:23"> ><
cite="mailto:Lam20100204" datetime="2010-09-07T14:23">w>< cite="mailto:Lam20100204" datetime="2010-09-07T14:23">as>< cite="mailto:Lam20100204" datetime="2010-09-07T14:23">
conducted at the >< cite="mailto:Lam20100204"
datetime="2010-09-07T14:23">M1a ><
cite="mailto:Lam20100204" datetime="2010-09-07T14:23"> />< cite="mailto:Lam20100204" datetime="2010-09-07T14:23">
Harbour Road Sports Centre in this reporting month. >< cite="mailto:mansonyeung" datetime="2010-09-02T19:21">Due to
the marine works undertaken in evening time from 12 July 2010, noise monitoring
during evening time was conducted from 13 July 2010. >< cite="mailto:Lam20100204" datetime="2010-09-07T14:23">Three
limit level exceedances were recorded ><
cite="mailto:Lam20100204" datetime="2010-09-07T14:23">at 3, 10 and 17 during
restricted hour><
cite="mailto:mansonyeung" datetime="2010-09-02T19:22">in reporting month. It is
concluded as not related to the Project works. However, baseline noise level at
M1 needs to be reviewed in next ><
cite="mailto:mansonyeung" datetime="2010-09-02T19:22">reporting>< cite="mailto:mansonyeung" datetime="2010-09-02T19:22"> month.><
cite="mailto:Lam20100204" datetime="2010-09-07T14:23">Investigation found that
is not project related exceedances. ><
cite="mailto:Lam20100204" datetime="2010-09-07T14:23">
Air Quality Monitoring
vi.
As <
cite="mailto:Lam20100204" datetime="2010-09-07T14:25">no >filling
works for Contract
no. HY/2009/11
was < cite="mailto:Lam20100204"
datetime="2010-09-07T14:40">carried>commenced <
cite="mailto:Lam20100204" datetime="2010-09-07T14:40"> /span>><
cite="mailto:Lam20100204" datetime="2010-09-07T14:41">out >in mid-< cite="mailto:Lam20100204" datetime="2010-09-07T14:41">reporting
month>August
2010, < cite="mailto:Lam20100204"
datetime="2010-09-07T14:41">n><
cite="mailto:Lam20100204" datetime="2010-09-07T14:41">o >air
quality monitoring at
stations CMA1b  /ins> Oil Street Community Liaison
Centre and
CMA2a  Causeway Bay Community Centre <
cite="mailto:Lam20100204" datetime="2010-09-07T14:42">was >were < cite="mailto:Lam20100204" datetime="2010-09-08T11:02">undertaken>commenced < cite="mailto:Lam20100204" datetime="2010-09-07T14:42">during >on 11 August 2010< cite="mailto:Lam20100204" datetime="2010-09-08T11:02">the
reporting month>. One action level exceedance of 1hour TSP was
recorded at CMA1b on 24 August 2010. Investigation found that exceedance was not related to the
Project.
Water Quality Monitoring
vii.
Water quality monitoring
at 17 monitoring stations < cite="mailto:Lam20100204"
datetime="2010-09-07T14:44">were>was conducted three days per week during the
reporting period.  /span>The action and limit
level exceedances of water quality monitoring are summarized in Table I.
Investigations were found that the exceedances are not related to the Project
works. The details of the exceedances can be referred to Section 5.3 and 6.3 of
the report.
Table I     Summary of Water Quality Monitoring Exceedances in Reporting
Month
Contract
no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
HY/2009/11 |
WSD9 |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">3> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
|
WSD10 |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">5> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
|
WSD15 |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">3> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">4> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
|
WSD17 |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">5> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
|
C8 |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">4> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
2 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">5> |
1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">3> |
|
C9 |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
3 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">4> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">3> |
1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
HK/2009/01 |
WSD19 |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
|
WSD20 |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
2 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
|
WSD7 |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">3> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
|
C1 |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
|
C2 |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">3> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
|
C3 |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">3> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
|
C4e |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
2 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
|
C4w |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
HK/2009/02 |
C5e |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
|
C5w |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
|
WSD21 |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
1 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 <
cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">1> |
Total |
1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">11> |
2 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">11> |
0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">0> |
5 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">18> |
0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">16> |
7 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">22> |
6 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">24> |
0 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">3> |
2 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2> |
1 < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">15> |
6 < cite="mailto:Lam20100204"
datetime="2010-09-07T14:45">8> |
Complaints, Notifications of
Summons and Successful Prosecutions
viii.
< cite="mailto:mansonyeung" datetime="2010-09-02T19:30">No
complaint>< cite="mailto:Lam20100204" datetime="2010-09-07T14:45">2>Two noise complaints were
recorded on 3< cite="mailto:Lam20100204"
datetime="2010-09-08T20:15">0>1 July and 12 August 2010 regarding noise nuisance
generated from the dredging works < cite="mailto:Lam20100204" datetime="2010-09-07T14:45">between 1900 and 0800 >in North
Point district.
Investigation found that the complaints were considered not valid
from the Environmental
Permit and Construction Noise Permit point of view.
< cite="mailto:Lam20100204" datetime="2010-09-07T14:47">i.><
cite="mailto:Lam20100204" datetime="2010-09-07T14:46">,>< cite="mailto:Lam20100204"
datetime="2010-09-07T14:46"> ><
cite="mailto:mansonyeung" datetime="2010-09-02T19:31">notification of summons
and prosecution was recorded in ><
cite="mailto:mansonyeung" datetime="2010-09-02T19:31">reporting>< cite="mailto:mansonyeung" datetime="2010-09-02T19:31"> month.>< cite="mailto:Lam20100204" datetime="2010-09-07T14:47">
Site Inspections and Audit
ix.
The Environmental Team
(ET) conducted weekly site inspections for Contract nos. HY/2009/11, HK/2009/01
and HK/2009/02 in this reporting period. Major observations and recommendations
made during the audit sessions were rectified by the Contractors. No non-conformance
was identified during the site inspections.
x.
In coming reporting month,
the principal work activities of individual contracts are anticipated as follows:
Contract no. HY/2009/11- North Point Reclamation
 -
Floating Out of Caisson
Seawall,
 -
Installation of Caisson
Seawall,
 -
Dredging works,
 -
Filling works;
 -
Construction of Seawall
Block,
 -
Works for Fenders and
rubber steps and Drainage works
< cite="mailto:mansonyeung" datetime="2010-09-04T12:23">Floating>< cite="mailto:mansonyeung"
datetime="2010-09-04T12:23"> Out of Caisson Seawall,
< cite="mailto:mansonyeung"
datetime="2010-09-04T12:23"> />< cite="mailto:mansonyeung"
datetime="2010-09-04T12:23">Installation of Caisson Seawall,
< cite="mailto:mansonyeung"
datetime="2010-09-04T12:23"> />< cite="mailto:mansonyeung"
datetime="2010-09-04T12:23">Dredging works,>< cite="mailto:mansonyeung"
datetime="2010-09-04T12:23">
< cite="mailto:mansonyeung"
datetime="2010-09-04T12:23"> />< cite="mailto:mansonyeung"
datetime="2010-09-04T12:23">Filling works>< cite="mailto:mansonyeung"
datetime="2010-09-04T12:23">
< cite="mailto:mansonyeung"
datetime="2010-09-04T12:23"> />< cite="mailto:mansonyeung"
datetime="2010-09-04T12:23">Construction of Seawall Block,
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:23"> />< cite="mailto:mansonyeung"
datetime="2010-09-04T12:23">Works for Fenders and rubber steps and
<
cite="mailto:Lam20100204" datetime="2010-09-03T15:02"> />< cite="mailto:mansonyeung"
datetime="2010-09-04T12:23">Drainage works>< cite="mailto:Lam20100204" datetime="2010-09-03T15:02">
<
cite="mailto:Lam20100204" datetime="2010-09-03T15:02"> />< cite="mailto:Lam20100204"
datetime="2010-09-03T15:02"> >< cite="mailto:Lam20100204" datetime="2010-09-03T15:02">
Contract no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai
Bypass at HKCEC
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49"> -
><
cite="mailto:Lam20100204" datetime="2010-09-07T14:49">Installation of pipe pile
wall at West Bridge
 -
Installation of pipe pile
wall at West Bridge
 -
Installation of trial
bored pile
 -
Assembly of crane to the
custom made dredger
 -
Dredging works for cross
harbour watermains
 -
Construction of wheel
washing facilities
 -
Commencement of temporary
jetty construction
 -
Implementation of TTM
scheme for trial pit at Convention Avenue (Area A1) and Harbour Road (Area A5)
 -
Implementation of TTM
scheme for Stage 1 pipe laying for cooling mains and cross harbour water main
at Convention Avenue (Area A1)
 -
Implementation of TTM
scheme for Stage 1 pipe laying for salt water main and optic fibre at Harbour
Road (Area A5)
 -
Implementation of TTM
scheme for Stage 1 pipe laying for cooling mains and cross harbour water main
at Expo Drive near HKCEC (Area B1)
 -
Tree transplantation at
Wan Chai and Tsim Sha Tsui
 -
Builder’s work and
structural modification for Sea water pump houses / Transformer room of HKCEC
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49">Installation of trial bored pile
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49">Assembly of crane to the custom made dredger
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49">Dredging works for cross harbour watermains
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49">Construction of wheel washing facilities
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49">Commencement of temporary jetty construction
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49">Implementation of TTM scheme for trial pit at
Convention Avenue (Area A1) and Harbour Road (Area A5)
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49">Implementation of TTM scheme for Stage 1 pipe
laying for cooling mains and cross harbour water main at Convention Avenue
(Area A1)
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49">Implementation of TTM scheme for Stage 1 pipe
laying for salt water main and optic fibre at Harbour Road (Area A5)
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49">Implementation of TTM scheme for Stage 1 pipe
laying for cooling mains and cross harbour water main at Expo Drive near HKCEC
(Area B1)
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49">Tree transplantation at Wan Chai and Tsim Sha Tsui
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49"> />< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49">Builder’s work and structural modification for Sea water 
pump houses / Transformer room of HKCEC
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:49">
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:49">
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:49">
< cite="mailto:Lam20100204" datetime="2010-09-07T14:49"> >< cite="mailto:Lam20100204" datetime="2010-09-07T14:49">
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Installation of pipe pile
wall at West Bridge
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Installation of trial
bored pile
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Assembly of crane to the
custom made dredger
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Dredging works for cross
harbour watermains
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Construction of wheel
washing facilities
< cite="mailto:mansonyeung"
datetime="2010-09-04T12:24"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Commencement of temporary
jetty construction
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Implementation of TTM
scheme for trial pit at Convention Avenue (Area A1) and Harbour Road (Area A5)
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Implementation of TTM
scheme for Stage 1 pipe laying for cooling mains and cross harbour water main
at Convention Avenue (Area A1)
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Implementation of TTM
scheme for Stage 1 pipe laying for salt water main and optic fibre at Harbour
Road (Area A5)
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Implementation of TTM
scheme for Stage 1 pipe laying for cooling mains and cross harbour water main
at Expo Drive near HKCEC (Area B1)
<
cite="mailto:mansonyeung" datetime="2010-09-04T12:24"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T12:24">Tree transplantation at
Wan Chai and Tsim Sha Tsui
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:49"> />< cite="mailto:mansonyeung"
datetime="2010-09-04T12:24">Builder’s work and structural modification for Sea
water pump houses / Transformer room of HKC>< cite="mailto:Lam20100204" datetime="2010-09-07T14:49">
Contract no. HK/2009/02 - Wan Chai Development Phase II  Central  Wan
Chai Bypass at WanChai East
 -
Site Clearance;
 -
Hoarding Erection;
 -
Pre-bored H-piles, ELS
and excavation at WSD Pumping Station;
 -
Construction of Salt
Water Intake Culvert at Pet Garden;
 -
Road Modification Works;
 -
Construction of Cooling
Mains Along Public Road;
 -
Construction of Temporary
Seawall;
 -
Dredging for WCR 1;
 -
Tree Transplanting; and
 -
Equipments Procurement
for TKO 137
1.1.1.
Lam Geotechnics Limited (LGL) has
been appointed to work as the
Environmental Team (ET) for Contractor No. HK/2009/05
Wan Chai Development Phase II and Central –Wan Chai Bypass  Sampling, Field
Measurement and Testing Work (Stage 1) to implement the Environmental Monitoring and Audit
(EM&A) programme as stipulated in the EM&A Manual of the
approved Environmental Impact Assessment (EIA) Report for Wan Chai Development
phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the
EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring and
auditing work carried out in accordance to the Section
10.3 of EM&A Manual
and  /span>Environmental Monitoring and Audit
Requirements /span>
under Particular Specification Section 27.
1.1.3.
This report documents the
finding of EM&A works for Environmental Permit no. EP-356/2009, Further
Environmental Permit no. FEP-01/2009, FEP-02/2009 and FEP-03/2009 during the period 28th July to 27th August 2010. The
cut-off date of reporting is at 27th of each reporting month.
Section 1     Introduction
 details the scope and structure of the report.
Section 2     Project
Background  summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3     Status of Regulatory Compliance
 summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section 4     Monitoring
Requirements
 summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section 5     Monitoring
Results  summarizes the monitoring results
obtained in the reporting period.
Section 6     Compliance
Audit  summarizes the auditing of
monitoring results, all exceedances environmental parameters.
Section 7     Cumulative Construction Impact due to the
Concurrent Projects  summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section 8     Site Inspection  
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a
review of any relevant follow-up actions within the
reporting period.
Section 9     Complaints, Notification of summons and Prosecution
 summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 10    Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan Chai
Bypass and “Central-Wan Chai Bypass and Island Eastern Corridor Link 
(hereafter called “the Project  are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA)
Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass
(Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11
December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to
provide relief to the very congested east-west Connaught Road Central/Harcourt
Road / Gloucester Road Corridor (the Corridor) which is currently operating
beyond its capacity. The CWB will provide relief to the existing congestion
along the Corridor and cater for the anticipated growth of traffic on Hong Kong
Island. Without the CWB and its access roads, there will not be sufficient
capacity to serve the heavy traffic demands at both strategic and local levels.
2.2.1.
The Project is located mainly in Wan Chai North,
Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria
Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road
Interchange to the east, as shown in Figure 2.1.
2.2.2.
The study area encompasses existing developments
along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses include
the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the Wan
Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the Royal
Hong Kong Yacht Club (RHKYC), the Police Officers' Club, the Causeway Bay
Typhoon Shelter (CBTS) and commercial and residential developments.
2.2.3.
The
scope of the Project comprises:
 -
Land formation for key
transport infrastructure and facilities, including the Trunk Road (i.e.
CWB) and the associated slip roads for connection to the Trunk Road and for through
traffic from Central to Wan Chai and Causeway Bay. The land formed for the above
transport infrastructure will provide opportunities for the development of an
attractive waterfront promenade for the enjoyment of the public
 -
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
 -
Extension, modification,
reprovisioning or protection of existing storm water drainage outfalls,
sewerage outfalls and watermains affected by the revised land use and land
formation works mentioned above
 -
Upgrading of hinterland
storm water drainage system and sewerage system, which would be rendered
insufficient by the land formation works mentioned above
 -
Provision of the ground
level roads, flyovers, footbridges, necessary transport facilities and the
associated utility services
 -
Construction of the new
waterfront promenade, landscape works and the associated utility services
 -
The
Trunk Road (i.e. CWB) within the study area and the associated slip roads for
connection to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1 summarises the
five individual DPs under this Project. Figure 2.1
shows the locations of these Schedule 2 DPs.
Table 2.1   Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. 
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits (FEP) such that the impact monitoring
stations are sub-divided accordingly to facilitate the implementation of
EM&A programme and to streamline the EM&A reporting for individual FEP
holders correspondingly.
2.3.2.
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:52">In the reporting month, >< cite="mailto:Lam20100204" datetime="2010-09-07T14:52">the
dredging works for Contracts no. HK/2009/01 and HK/2009/02 were commenced on 23
July and 5 July 2010 respectively><
cite="mailto:Lam20100204" datetime="2010-09-07T14:52">. >The details of individual
contracts are summarized in Table 2.2.
Table 2.2  Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II  Central –Wanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
Pending |
||
HK/2009/02 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
Pending |
||
HY/2009/11 |
Wan Chai Development Phase II and Central - Wan Chai Bypass - North
Point Reclamation |
DP3 |
17 March 2010 |
2.4.1.
Civil Engineering and
Development Department and Highways Department are the overall project
controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass
respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principle Resident Engineer |
Mr. Frankie Fan |
2607 7801 |
2687 2322 |
Engineer for CWB |
Chief Resident Engineer |
Mr. David Kwan |
3916 1818 |
3529 2829 |
|
China Harbour- CRBC Joint Venture |
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr.
Daniel Cheung |
3157 1086 |
|||
Environmental Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo  Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Paul Yu |
9456 9819 |
2634 1626 |
Operation Manager |
Lau Yee Ching< cite="mailto:mansonyeung"
datetime="2010-09-04T13:03">Ho Wing Tai> |
9466 3918< cite="mailto:mansonyeung"
datetime="2010-09-04T13:03">9306 1356> |
|||
Construction Manager |
David Wong |
9653 8635 |
|||
Construction Manager |
Wilson Lau |
5183 1270 |
|||
Construction Manager |
Chan Mui Sang< cite="mailto:mansonyeung"
datetime="2010-09-04T13:03">Alex Tsang> |
9864 8615< cite="mailto:mansonyeung"
datetime="2010-09-04T13:03">9194 9383> |
|||
Environmental Officer
(Compliance Manager) |
Brian Wan< cite="mailto:mansonyeung"
datetime="2010-09-04T13:04">Ho Wing Tai> |
9312 2827< cite="mailto:mansonyeung"
datetime="2010-09-04T13:04">9306 1356> |
|||
Environmental Engineer |
Shelton Chan< cite="mailto:mansonyeung"
datetime="2010-09-04T13:04">Ken Yang> |
5395 5470<
cite="mailto:mansonyeung" datetime="2010-09-04T13:04">9262 6791> |
|||
Chun Wo  CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Eric Lam<
cite="mailto:mansonyeung" datetime="2010-09-04T13:04">Mr. Anthony Wu> |
3658-3048<
cite="mailto:mansonyeung" datetime="2010-09-04T13:04">3658 3004> |
|||
Environmental Officer (Compliance Manager) |
Mr. Barry Leung |
3658 3031 |
|||
Environmental Engineer |
Ms. Flora Ng |
3658-3064 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HY/2009/11, the principal work activities in this
reporting month included:
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:54"> -
><
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Construction of Rock
Mound,
 -
Construction of Rock
Mound,
 -
Floating Out of Caisson
Seawall,
 -
Installation of Caisson
Seawall,
 -
Dredging works,
 -
Filling works;
 -
Laying of geo-textile,
 -
Drainage Works and
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:54"> -
>Seawall Block
Installation< cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Floating
Out of Caisson Seawall,
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:54"> -
><
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Installation of Caisson
Seawall,
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:54"> -
><
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Dredging works,
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:54"> -
><
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Laying of geo-textile,
 -
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Drainage Works and Seawall
Block Installation>
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Construction of Rock
Mound,
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Floating Out of Caisson
Seawall,
< cite="mailto:mansonyeung" datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Installation of Caisson
Seawall,
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Dredging works,
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Filling works;
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Laying of geo-textile,
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Drainage Works and
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:53"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Seawall Block
Installation>< cite="mailto:Lam20100204"
datetime="2010-09-07T14:53">
< cite="mailto:Lam20100204" datetime="2010-09-03T16:56"> >< cite="mailto:Lam20100204" datetime="2010-09-03T16:56">
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:53"> >< cite="mailto:Lam20100204" datetime="2010-09-07T14:53">
2.4.4.
For Contract no. HK/2009/01, the principal work activities in
this reporting month included:
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:54"> -
>< cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> >< cite="mailto:Lam20100204" datetime="2010-09-07T14:54">
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:54"> -
><
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Erection of interim
Engineer’s Principal Office at Works areas WA2 was completed for moving-in on 5
Aug 10.
 -
Erection of interim
Engineer’s Principal Office at Works areas WA2
 -
Modification of CATV
combine service inspection chamber
 -
Installation of staging
piles for trial bored pile was completed and bored pile construction
 -
Marine site investigation
 -
Dredging works for cross
harbour watermains
 -
Dismantling of existing
sloping seawall and removal of armor rock at north-west side of water channel
is stopped and reinstating the rock slope at seawall
 -
Hoarding erection at Tsim
Sha Tsui Salisbury Garden area
 -
18m of artwork panel is
installed as design for other location
 -
Trial pits construction
for determination of pipeline alignment at Convention Avenue
 -
Fabrication of straight
sections of cross harbour submarine pipes and land water pipes
 -
Elbow sections of cross
harbour submarine pipes are being fabricated.
 -
The assemble of 6 nos. of
tailor made flat top barge was commenced on 14 Aug 10. The fabrication of
dredging crane was completed and will be installed on the tailor make flat top
barge on 21 Aug 10 and ready for dredging by 15 Sept 10 tentatively.
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Modification of CATV
combine service inspection chamber is ongoing.
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:54"> /><
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Installation of staging
piles for trial bored pile was completed and bored pile construction is in
progress.
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> /><
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Marine site investigation
was completed.
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> /><
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Dredging works for cross
harbour watermains is on going.
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> /><
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Dismantling of existing
sloping seawall and removal of armor rock at north-west side of water channel
is stopped and reinstating the rock slope at seawall is in progress.
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> /><
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Hoarding erection at Tsim
Sha Tsui Salisbury Garden area is completed on 18/08/10. However, only 18m of
artwork panel is installed as design for other location has yet been finalized
from the Engineer.
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> /><
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Trial pits construction
for determination of pipeline alignment at Convention Avenue is ongoing.
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> /><
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Fabrication of straight
sections of cross harbour submarine pipes and land water pipes was completed.
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> /><
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">Elbow sections of cross
harbour submarine pipes are being fabricated.
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:54"> /><
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">The assemble of 6 nos. of
tailor made flat top barge was commenced on 14 Aug 10. The fabrication of
dredging crane was completed and will be installed on the tailor make flat top
barge on 21 Aug 10 and ready for dredging by 15 Sept 10 tentatively. >< cite="mailto:Lam20100204"
datetime="2010-09-07T14:54">
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:54"> /><
cite="mailto:Lam20100204" datetime="2010-09-07T14:54">The registration of 3 mud
barges had been fully licensed. Demonstration to EPD for operation is on going.>< cite="mailto:Lam20100204"
datetime="2010-09-07T14:54">
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06">Erection of interim Engineer’s Principal Office at
Works areas WA2
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Modification of CATV combine
service inspection chamber
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Installation of staging
piles for trial bored pile was completed and bored pile construction
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Marine site investigation
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Dredging works for cross
harbour watermains
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Dismantling of existing
sloping seawall and removal of armor rock at north-west side of water channel
is stopped and reinstating the rock slope at seawall
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Hoarding erection at Tsim
Sha Tsui Salisbury Garden area
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">18m of artwork panel is
installed as design for other location
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Trial pits construction
for determination of pipeline alignment at Convention Avenue
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Fabrication of straight
sections of cross harbour submarine pipes and land water pipes
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">Elbow sections of cross
harbour submarine pipes are being fabricated.
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:06"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:06">The assemble of 6 nos. of
tailor made flat top barge was commenced on 14 Aug 10. The fabrication of
dredging crane was completed and will be installed on the tailor make flat top
barge on 21 Aug 10 and ready for dredging by 15 Sept 10 tentatively.>< cite="mailto:mansonyeung" datetime="2010-09-04T13:06">
<
cite="mailto:Lam20100204" datetime="2010-09-07T14:54"> >< cite="mailto:Lam20100204" datetime="2010-09-07T14:54">
2.4.5.
For Contract no. HK/2009/02, the principal work activities in
this reporting month included:
 -
Site Clearance
 -
Hoarding Erection
 -
Pre-bored H-piles, ELS
and excavation at WSD Pumping Station
 -
Construction of Salt
Water Intake Culvert at Pet Garden
 -
Road Modification Works
 -
Construction of Cooling
Mains Along Public Road
 -
Construction of Temporary
Seawall
 -
Dredging for WCR 1
 -
Tree Transplanting
 -
Equipments Procurement
for TKO 137
< cite="mailto:Lam20100204" datetime="2010-09-07T14:55"> >< cite="mailto:Lam20100204" datetime="2010-09-07T14:55">
2.4.6.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract
no. HY/2009/11- North Point Reclamation
 -
Floating Out of Caisson
Seawall,
 -
Installation of Caisson
Seawall,
 -
Dredging works,
 -
Filling works;
 -
Construction of Seawall
Block,
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:55"> -
>Works for Fenders and
rubber steps and Drainage works<
cite="mailto:Lam20100204" datetime="2010-09-07T14:55">
< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Floating
Out of Caisson Seawall,
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07"> -
>< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07">Installation of Caisson Seawall,
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07"> -
>< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07">Dredging works,
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07"> -
>< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07">Filling works
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07"> -
>< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07">Construction of Seawall Block,
< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> -
>< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07">Works for Fenders and rubber steps and
< cite="mailto:Lam20100204"
datetime="2010-09-07T14:55"> -
>< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Drainage
works>< cite="mailto:Lam20100204" datetime="2010-09-07T14:55">
<
cite="mailto:Lam20100204" datetime="2010-09-03T16:56"> >< cite="mailto:Lam20100204" datetime="2010-09-03T16:56">
 -
Contract
no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at
HKCEC
 -
Installation of pipe pile
wall at West Bridge
 -
Installation of trial
bored pile
 -
Assembly of crane to the
custom made dredger
 -
Dredging works for cross
harbour watermains
 -
Construction of wheel
washing facilities
 -
Commencement of temporary
jetty construction
 -
Implementation of TTM
scheme for trial pit at Convention Avenue (Area A1) and Harbour Road (Area A5)
 -
Implementation of TTM
scheme for Stage 1 pipe laying for cooling mains and cross harbour water main
at Convention Avenue (Area A1)
 -
Implementation of TTM
scheme for Stage 1 pipe laying for salt water main and optic fibre at Harbour
Road (Area A5)
 -
Implementation of TTM
scheme for Stage 1 pipe laying for cooling mains and cross harbour water main
at Expo Drive near HKCEC (Area B1)
 -
Tree transplantation at
Wan Chai and Tsim Sha Tsui
 -
Builder’s work and
structural modification < cite="mailto:Lam20100204"
datetime="2010-09-07T14:56">for Sea>for Sea <
cite="mailto:Lam20100204" datetime="2010-09-07T14:56">water pump>water pump houses / Transformer
room of HKCEC
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Installation of pipe pile
wall at West Bridge
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Installation of trial
bored pile
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Assembly of crane to the
custom made dredger
< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Dredging works for cross
harbour watermains
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Construction of wheel
washing facilities
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Commencement of temporary
jetty construction
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Implementation of TTM
scheme for trial pit at Convention Avenue (Area A1) and Harbour Road (Area A5)
< cite="mailto:mansonyeung" datetime="2010-09-04T13:07"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Implementation of TTM
scheme for Stage 1 pipe laying for cooling mains and cross harbour water main
at Convention Avenue (Area A1)
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Implementation of TTM
scheme for Stage 1 pipe laying for salt water main and optic fibre at Harbour
Road (Area A5)
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Implementation of TTM
scheme for Stage 1 pipe laying for cooling mains and cross harbour water main
at Expo Drive near HKCEC (Area B1)
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Tree transplantation at
Wan Chai and Tsim Sha Tsui
< cite="mailto:mansonyeung"
datetime="2010-09-04T13:07"> /><
cite="mailto:mansonyeung" datetime="2010-09-04T13:07">Builder’s work and
structural modification for Sea water pump houses / Transformer room of HKCEC>< cite="mailto:mansonyeung" datetime="2010-09-04T13:07">
< cite="mailto:Lam20100204"
datetime="2010-09-03T16:56"> />< cite="mailto:Lam20100204" datetime="2010-09-03T16:56"> >< cite="mailto:Lam20100204" datetime="2010-09-03T16:56">
< cite="mailto:Lam20100204"
datetime="2010-09-03T16:56"> />< cite="mailto:Lam20100204" datetime="2010-09-03T16:56"> >< cite="mailto:Lam20100204" datetime="2010-09-03T16:56">
< cite="mailto:Lam20100204"
datetime="2010-09-03T16:56"> />< cite="mailto:Lam20100204" datetime="2010-09-03T16:56"> >< cite="mailto:Lam20100204" datetime="2010-09-03T16:56">
Contract
no. HK/2009/02 - Wan Chai Development Phase II  Central  Wan Chai Bypass at
WanChai East
 -
Site Clearance;
 -
Hoarding Erection;
 -
Pre-bored H-piles, ELS
and excavation at WSD Pumping Station;
 -
Construction of Salt
Water Intake Culvert at Pet Garden;
 -
Road Modification Works;
 -
Construction of Cooling
Mains Along Public Road;
 -
Construction of Temporary
Seawall;
 -
Dredging for WCR 1;
 -
Tree Transplanting; and
 -
Equipments Procurement
for TKO 137
<
cite="mailto:mansonyeung" datetime="2010-09-02T19:34"> >< cite="mailto:mansonyeung" datetime="2010-09-02T19:34">
< cite="mailto:mansonyeung"
datetime="2010-09-02T19:34"> />< cite="mailto:mansonyeung" datetime="2010-09-02T19:34"> >< cite="mailto:mansonyeung" datetime="2010-09-02T19:34">
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009/A |
4 Aug < cite="mailto:Lam20100204" datetime="2010-09-08T19:03">17
Aug 2009>2010 |
Valid |
Environmental Permit |
EP-364/2009/ |
17 Aug 2009 |
Susperseded |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb
2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
24 Mar
2010 |
Valid |
|
Further
Environmental Permit |
21 Apr 2010 |
Valid |
|
Further
Environmental Permit |
12 July 2010 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the
status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HY/2009/11  Central  Wanchai
Bypass, North Point Reclamation
3.1.3.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-01/356/2009 for
contract no. HY/2009/11
are shown in Table 3.2 and
Table 3.3.
Table
3.2  Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/11
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
N/A |
Valid |
Notification of Works Under APCO |
314911 |
9 Mar 2010 |
N/A |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0371-10<
cite="mailto:Lam20100204" datetime="2010-09-07T15:01">GW-RS0119-10> |
7 May 2010<
cite="mailto:Lam20100204" datetime="2010-09-07T15:01">17 Feb 2010> |
10 May 2010 to 31 Oct 2010< cite="mailto:Lam20100204" datetime="2010-09-07T15:01">22>< cite="mailto:Lam20100204" datetime="2010-09-07T15:01"> Feb >< cite="mailto:Lam20100204" datetime="2010-09-07T15:01">2010>< cite="mailto:Lam20100204" datetime="2010-09-07T15:01"> to><
cite="mailto:Lam20100204" datetime="2010-09-07T15:01"> >< cite="mailto:Lam20100204"
datetime="2010-09-07T15:01">22 Aug 2010> |
Valid <
cite="mailto:Lam20100204" datetime="2010-09-07T15:01">Superseded> |
GW-RS0534-10 |
22 Jun 2010 |
29 Jun 2010 to 28 Dec 2010 |
Valid <
cite="mailto:Lam20100204" datetime="2010-09-07T15:01">(Replaced CNP no.
GW-RS0437-10)> |
|
Billing Account
under Waste Disposal Ordinance |
7010037 |
13 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1  Open
Sea Disposal) |
EP/MD/10-067 |
10 Mar 2010 |
10 Mar 2010 to 9 Sep 2010 |
Valid |
Dumping Permit (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) |
EP/MD/11-033 |
9 Jul 2010 |
10
Jul to 9 Aug 2010 |
Expired |
EP/MD/11-044 |
2 Aug 2010 |
10
Aug to 9 Sep 2010 |
Valid |
Table 3.3  Summary
of submission status under FEP-01/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
18 Dec 2009 |
Condition 2.7 |
Submission of works schedule and location plan |
8 Feb 2010 |
Condition
2.8 |
Silt
Curtain Deployment Plan |
25 Feb 2010 |
Condition
2.9 |
Silt
Screen Deployment Plan |
25 Feb 2010 |
Condition
2.10 |
Coral
Translocation Plan |
20 Nov 2009 |
Condition
2.16 |
Noise
Management Plan |
1 Mar 2010 |
Condition
2.17 |
Landscape
Plan |
12
May 2010 |
|
Submission of
Supplementary Information - Revised Management & Maintenance Schedule for
Submitted Revised Landscape Plan |
25 Aug 2010 |
Contract no. HK/2009/01 - Wan
Chai Development Phase II  Central –Wanchai Bypass at HKCEC
3.1.4.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and
submission under FEP-02/356/2009 for
contract no.
HK/2009/01 are shown in Table 3.4 and
Table 3.5.
Table 3.4  Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0313-10 |
16 Apr 2010 |
16 Apr 2010 to 14 Sep 2010 |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0328-10 |
22 Apr 2010 |
22 Apr 2010 to 15 Oct 2010 |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0333-10 |
21 Apr 2010 |
21 Apr 2010 to 14 Sep 2010 |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0336-10 |
21 Apr 2010 |
21 Apr 2010 to 14 Sep 2010 |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0554-10 |
25 Jun 2010 |
28 Jun 2010 to 30 Sep 2010 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar <
cite="mailto:mansonyeung" datetime="2010-09-06T17:41">31 Mar 2015><
cite="mailto:Lam20100204" datetime="2010-09-07T15:17">N/A>2015 |
Valid |
Registration as a Waste Producer |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1  Open
Sea Disposal) |
EP/MD/10-060 |
30 Apr 2010 |
4 May to 3 Nov 2010 |
Valid |
Dumping Permit (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) |
EP/MD/11-027 |
29 Jun 2010 |
1 Jul to 31 Jul 2010 |
Expired |
EP/MD/11-041 |
31 Aug 2010 |
1 Sep to 30 Sep 2010 |
Valid |
Table 3.5  Summary
of submission status under FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
13 Apr 2010 |
Condition 2.7 |
Works Schedule and Location
Plan |
8 Apr 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
19 Apr 2010 |
Condition 2.9 |
Silt Screen Deployment Plan |
19 Apr 2010 |
Conditions 2.8 and 2.9 |
Supplementary Document on Silt Curtain and Silt
Screen Deployment Plan |
19 Jul 2010 |
Report on Field Testing for Silt Curtain |
26 Aug 2010 |
|
Condition 2.17 |
Noise Management Plan |