Contract No: HK/2009/05

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 1)

 

Environmental Permit no. EP-356/2009,

Further Evironmental permit nos. fep-01/356/2009, fep-02/356/2009 and FEP-03/356/2009

 

Quarterly Environmental Monitoring
and Audit Report

 

- June to August 2010 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

CHECKED by:



 

 

 

 

 

                        

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

29 October 2010


Table of contents

 

EXECUTIVE SUMMARY.. iii

1.   Introduction.. 1

1.1    Scope of the Report 1

2.   Project Background.. 2

2.1    Background. 2

2.2    Scope of the Project and Site Description. 2

2.3    Division of the Project Responsibility. 3

2.4    Project Organization and Contact Personnel 4

2.5    Principle Work and Activities. 5

3.   Monitoring Requirements. 8

3.1.    Noise Monitoring. 8

3.2.    Air Monitoring. 8

3.3.    Water Quality Monitoring. 9

4.   Monitoring Results. 12

4.1.    Noise Monitoring Results. 12

4.2.    Air Monitoring Results. 13

4.3.    Water Monitoring Results. 14

4.4.    Waste Monitoring Results. 17

5.   Compliance Audit. 20

5.1.    Noise Monitoring. 20

5.2.    Air Monitoring. 20

5.3.    Water Quality Monitoring. 20

5.4.    Site Audit 22

5.5.    Review of the Reasons for and the Implications of Non-compliance. 22

5.6.    Summary of action taken in the event of and follow-up on non-compliance. 22

6.   Complaints, Notification of Summons and Prosecution.. 23

7.   Cumulative Construction Impact due to the Concurrent Projects. 24

8.   Conclusion.. 25


lIST OF TABLES

 

Table I      Principle Work Activities for Contract no. HY/2009/11

Table II     Principle Work Activities for Contract no. HK/2009/01

Table III     Principle Work Activities for Contract no. HK/2009/02

Table IV    Revised Action and Limit Levels for Water Quality Monitoring

Table 2.1    Schedule 2 Designated Projects under this Project

Table 2.2   Details of Individual Contracts under the Project

Table 2.3   Contact Details of Key Personnel

Table 2.4    Principle Work Activities for Contract no. HY/2009/11

Table 2.5    Principle Work Activities for Contract no. HK/2009/01

Table 2.6    Principle Work Activities for Contract no. HK/2009/02

Table 3.1   Noise Monitoring Stations

Table 3.2   Air Monitoring Stations

Table 3.3    Marine Water Quality Stations for Water Quality Monitoring

Table 3.4   Marine Water Quality Monitoring Frequency and Parameters

Table 4.1    Noise Monitoring Stations for Contract no. HY/2009/11

Table 4.2    Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02

Table 4.3   Air Monitoring Stations for Contract no. HY/2009/11

Table 4.4    Air Monitoring Stations for Contract no. HK/2009/01

Table 4.5    Air Monitoring Station for Contract no. HK/2009/02

Table 4.6   Water Monitoring Stations for Contract no. HY/2009/11

Table 4.7    Water Monitoring Stations for Contract no. HK/2009/01

Table 4.8    Water Monitoring Stations for Contract no. HK/2009/02

Table 4.9    Summary of Water Quality Monitoring Exceedances in Reporting Quarter

Table 4.10  Details of Waste Disposal for Contract no. HY/2009/11

Table 4.11  Details of Waste Disposal for Contract no. HK/2009/01

Table 4.12  Details of Waste Disposal for Contract no. HK/2009/02

Table 5.1   Summary of Water Quality Exceedances in the reporting Quarter

Table 5.2   Proposed Action and Limit Levels for Water Quality Monitoring

Table 6.1   Cumulative Statistics on Complaints

Table 6.2   Cumulative Statistics on Successful Prosecutions

 

lIST OF FIGUREs

 

Figure 2.1     Project Layout

Figure 2.2     Project Organization Chart

Figure 3.1      Locations of Environmental Monitoring Stations

 

lIST OF APPENDIces

 

Appendix 2.1   Environmental Mitigation Implementation Schedule

Appendix 3.1   Action and Limit Level

Appendix 4.1   Noise Monitoring Graphical Presentations

Appendix 4.2   Air Quality Monitoring Graphical Presentations

Appendix 4.3   Water Quality Monitoring Graphical Presentations

Appendix 5.1   Event Action Plans

Appendix 5.2   Calculation using the Marine Water Quality Data Obtained at the Closest EPD Routine Monitoring Stations

Appendix 6.1   Complaint Log

Appendix 8.1   Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

  1. This is the Quarterly Environmental Monitoring and Audit (EM&A) Report  /span> June to August 2010 prepared for the Project of Wan Chai Development Phase II and Central-Wanchai Bypass under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009 and FEP-03/356/2009. This report presents the environmental monitoring and audit findings and information during the period from 28th May 2010 to 27th August 2010. The cut-off date of reporting is at 27th of each reporting quarter.

 

Construction Activities for the Reported Period

  1. During this reporting period, the principle work activities for Contract no. HY/2009/11 are summarized as below:

Table I     Principle Work Activities for Contract no. HY/2009/11

June 2010

July 2010

August 2010

Ÿ              Installation of seawall blocks;

Ÿ              Construction of Caissons at Casting Yard in Mainland China;

Ÿ              Dredging works; and

Ÿ              Construction of Rock Mound

Ÿ              Construction of Rock Mound,

Ÿ              Floating Out of Caisson Seawall,

Ÿ              Installation of Caisson Seawall,

Ÿ              Dredging works, and

Ÿ              Laying of geo-textile

Ÿ              Construction of Rock Mound,

Ÿ              Floating Out of Caisson Seawall,

Ÿ              Installation of Caisson Seawall,

Ÿ              Dredging works,

Ÿ              Filling works;

Ÿ              Laying of geo-textile,

Ÿ              Drainage Works; and

Ÿ              Seawall Block Installation

 

  1. Major marine activities for Contract no. HK/2009/01 has been commenced on 23 July 2010. During this reporting period, the preparation works and principle work activities for it are summarized as below:

Table II    Principle Work Activities for Contract no. HK/2009/01

June 2010

July 2010

August 2010

 -           Erection of interim Engineer’s Principal Office at Works areas WA2;

 -           Pre-drilling works and fabrication of staging for trial pile

 -           Transportation of materials to the designated pile position by derrick barges.

 -           Decorative panel installation;

 -           Re-mobilization of flat top barge to carry out Marine S.I. within fairway;

 -           Marine ground investigation;

 -           Fabrication of pipe pile wall staging at the existing promenade piled deck;

 -           Fabrication of special made flat top barge for dredging inside the HKCEC water channel;

 -           Production of pipe pile casing is underway, first batch of 30 nos. x 12 m mill steel pipeline arrived and stored at Yuen Long Yard;

 -           Completion of silt screens installation for HKCEC Phase 1, Government Buildings, China Resources, Great Eagle & Harbour Centre, Telecom House, Shui On, HKAPA, Sheung Wan & Kowloon South Pumping Station and HKCEC Extension (Pumping Station P6);

 -           Erection of temporary platform for pipe pile installation; and

 -           Fabrication of mud barges and crane barge for dredging within HKCEC water channel

 

 -           Erection of interim Engineer’s Principal Office at works area WA2

 -           Hoarding erection at Wan Chai HKCEC VIP Drop-off Area and Tsim Sha Tsui Salisbury Area;

 -           The flat top barge is continued to carry out Marine S.I. within fairway area

 -           Marine S.I. at east side of HKCEC;

 -           Fabrications of submarine pipelines;

 -           Silt screens installation are completed for HKCEC Phase 1, Government Buildings, China Resoureces, Great Eagle & Harbour Centre, Telecom House, Shui On, HKAPA, Sheung Wan & Kowloon South Pumping Station and HKCEC Extension (Pumping Station P6);

 -           Routine maintenance and clearance works for silt screens;

 -           Erection of temporary platform for pipe pile installation;

 -           Fabrication of 3 nos. of mud barges for dredging within HKCEC water channel and delivered on site. Application of respective license;

 -           Fabrication of crane barges are in progress and expect to deliver to site; and

 -           Wheel washing facility will be provided at the north entrance to the water channel

 -           Erection of interim Engineer’s Principal Office at Works areas WA2

 -           Modification of CATV combine service inspection chamber

 -           Installation of staging piles for trial bored pile was completed and bored pile construction

 -           Marine site investigation

 -           Dredging works for cross harbour watermains

 -           Dismantling of existing sloping seawall and removal of armor rock at north-west side of water channel is stopped and reinstating the rock slope at seawall

 -           Hoarding erection at Tsim Sha Tsui Salisbury Garden area

 -           18m of artwork panel is installed as design for other location

 -           Trial pits construction for determination of pipeline alignment at Convention Avenue

 -           Fabrication of straight sections of cross harbour submarine pipes and land water pipes

 -           Elbow sections of cross harbour submarine pipes are being fabricated.

 -           Commenced assemble of 6 nos. of tailor made flat top barge. The fabrication of dredging crane was completed and will be installed on the tailor make flat top barge and ready for dredging.

 

  1. The dredging works for Contract no. HK/2009/02 has been commenced on 5 July 2010. The preparation works and major construction activities for it in this reporting periods included:

Table III    Principle Work Activities for Contract no. HK/2009/02

June 2010

July 2010

August 2010

Ÿ              Site Clearance;

Ÿ              Hoarding Erection;

Ÿ              Dismantle Existing Footbridge Staircase at Wan Shing Road;

Ÿ              Pre-drilling Works at WSD Salt Water Pumping Station;

Ÿ              Construction of Salt Water Intake Culvert at Pet Garden;

Ÿ              Road Modification Works; and

Ÿ              Construction of temporary seawall

Ÿ              Site Clearance;

Ÿ              Hoarding Erection;

Ÿ              Breaking and Excavation at WSD Pumping Station;

Ÿ              Demolition Footbridge Staircase at WSD Pumping Station;

Ÿ              Construction of Salt Water Intake Culvert at Pet Garden;

Ÿ              Road Modification Works;

Ÿ              Construction of Cooling Mains Along Public Road;

Ÿ              Construction of Temporary Seawall;

Ÿ              Dredging for WCR 1; and

Ÿ              Equipments Procurement for TKO 137

Ÿ              Site Clearance;

Ÿ              Hoarding Erection;

Ÿ              Pre-bored H-piles, ELS and excavation at WSD Pumping Station;

Ÿ              Construction of Salt Water Intake Culvert at Pet Garden;

Ÿ              Road Modification Works;

Ÿ              Construction of Cooling Mains Along Public Road;

Ÿ              Construction of Temporary Seawall;

Ÿ              Dredging for WCR 1;

Ÿ              Tree Transplanting; and

Ÿ              Equipments Procurement for TKO 137

 

Noise Monitoring

  1. Two action level exceedances were recorded due to the noise complaints on 31 July and 12 August 2010 regarding noise nuisance from the dredging works in North Point district. The Contractor HY/2009/11 has implemented mitigation measures to reduce the construction work period during daytime and evening time. In addition, eleven limit level exceedances were recorded at stations M1a, M4a, M5b in reporting quarter. Investigation found that exceedances were not related to the Project. Reviewed the past monitoring results and observation at Station M4a, Victoria Centre (Station ID: M4b) was proposed as alternative noise monitoring station effective from August 2010.

 

Air Quality Monitoring

  1. One action level exceedance of 1 hour TSP was recorded at station CMA1b on 24 August 2010. Investigation found that the exceedance was not related to the Project work due to the burning joss paper activity near the Oil Street Community Centre between 23 and 25 August 2010 morning.

 

Water Quality Monitoring

  1. Water quality monitoring was conducted at 17 monitoring stations namely WSD7, WSD9, WSD10, WSD15, WSD17, WSD19, WSD20, WSD 21, C1, C2, C3, C4e, C4w, C5e, C5w, C8 and C9 on 74 tidal monitoring events during the reporting period.  /span>Total 49 exceedances of DO, 43 exceedances of SS and 4 exceedances of turbidity were recorded during mid-flood while 83 exceedances of DO, 36 exceedances of SS and 8 exceedances of turbidity were recorded during mid-ebb in the reporting period. Investigation found that the exceedances were not due to the Project works.

 

  1. Owing to the frequent non-project related exceedances caused by fluctuation in coastal water quality due to localized effect, it is considered the existing Action and Limit Levels values were underestimated to the natural variation of water quality around the baseline range.  It is recommended to review the existing Action and Limit Levels on water quality in order to take into the account of the coastal activities and potential variation of coastal water qualities during wet season (i.e. Apr  Sep period).

 

  1. While the existing Action and Limit levels will continue to be used for impact monitoring for dry season (Oct  Mar period), an additional set of Action and Limit levels are proposed for use in the coming wet season and are summarized in the table below.

Table IV   Revised Action and Limit Levels for Water Quality Monitoring

 

Dry Season (Existing AL & LL)

Wet Season

Parameters

Action

Limit

Action

Limit

WSD Salt Water Intakes

 

 

 

 

SS in mg/L

13.00

14.43

16.26

19.74

Turbidity in NTU

8.04

9.49

10.01

11.54

DO in mg/L

3.66

3.28

3.17

2.63

Cooling Water Intakes

 

 

 

 

SS in mg/L

15.00

22.13

18.42

27.54

Turbidity in NTU

9.10

10.25

11.35

12.71

DO in mg/L

3.36

2.73

3.02

2.44

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. Two noise complaints were recorded on 31 July and 12 August 2010 regarding noise nuisance from the dredging works in North Point district. Investigation found that the complaints were considered not valid from the Environmental Permit and Construction Noise Permit point of view.

 

 

 


1.     Introduction

1.1               Scope of the Report

1.1.1.        Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009 and FEP-03/356/2009 to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.        This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.4 of EM&A Manual and  /span>Environmental Monitoring and Audit Requirements /span> under Particular Specification Section 27.

1.1.3.        This report documents the finding of EM&A works during the period from 28th May 2010 to 27th August 2010.

1.2               Structure of the Report

 

Section 1     Introduction  details the scope and structure of the report.

 

Section 2     Project Background  summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3     Monitoring Requirements  summarizes all monitoring parameters, monitoring locations, monitoring frequency, duration and action plan.

 

Section 4     Monitoring Results  summarizes the monitoring results obtained in the reporting period.

 

Section 5     Compliance Audit  summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 6     Complaints, Notification of summons and Prosecution  summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 7     Cumulative Construction Impact due to the Concurrent Projects  summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8     Conclusion

2.     Project Background

2.1               Background

2.1.1.        “Wan Chai Development phase II and Central-Wan Chai Bypass and “Central-Wan Chai Bypass and Island Eastern Corridor Link  (hereafter called “the Project  are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.        The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.        There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2               Scope of the Project and Site Description

2.2.1.        The Project is located mainly in Wan Chai North, Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road Interchange to the east, as shown in Figure 2.1.

2.2.2.        The study area encompasses existing developments along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police Officers' Club, the Causeway Bay Typhoon Shelter (CBTS) and commercial and residential developments.

2.2.3.        The scope of the Project comprises:

 -           Land formation for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for connection to the Trunk Road and for through traffic from Central to Wan Chai and Causeway Bay. The land formed for the above transport infrastructure will provide opportunities for the development of an attractive waterfront promenade for the enjoyment of the public

 -           Reprovisioning / protection of the existing facilities and structures affected by the land formation works mentioned above

 -           Extension, modification, reprovisioning or protection of existing storm water drainage outfalls, sewerage outfalls and watermains affected by the revised land use and land formation works mentioned above

 -           Upgrading of hinterland storm water drainage system and sewerage system, which would be rendered insufficient by the land formation works mentioned above

 -           Provision of the ground level roads, flyovers, footbridges, necessary transport facilities and the associated utility services

 -           Construction of the new waterfront promenade, landscape works and the associated utility services

 -           The Trunk Road (i.e. CWB) within the study area and the associated slip roads for connection to the Trunk Road.

 

2.2.4.        The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1   Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

 

2.3               Division of the Project Responsibility

2.3.1.        Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits (FEP) such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.        In the reporting period, Contract no. HY/2009/11 - Central  Wanchai Bypass, North Point Reclamation under the Project has been commenced on 17 March 2010. Two Contracts under the Project has been commenced in July 2010. The details of individual contracts are summarized in Table2.2.

Table 2.2  Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HK/2009/01

Wan Chai Development Phase II  Central –Wanchai Bypass at Hong Kong Convention and Exhibition Centre

DP3, DP6

23 July 2010

DP1, DP2

Pending

HK/2009/02

Wan Chai Development Phase II  Central  Wan Chai Bypass at WanChai East

DP3, DP5

5 July 2010

DP1

Pending

HY/2009/11

Wan Chai Development Phase II and Central - Wan Chai Bypass - North Point Reclamation

DP3

17 March 2010

 

2.4               Project Organization and Contact Personnel

2.4.1.        Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.        The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3  Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer for WDII

Principal Resident Engineer

Mr. Frankie Fan

2607 0838

2687 2322

Engineer for CWB

Principal Resident Engineer

Mr. Peter Poon

3916 1800

3529 2829

China Harbour- CRBC Joint Venture

Contractor under Contract no. HY/2009/11

Project Director

Mr. Cho Yu Fun

3157 1086

3157 1085

Project Manager

Mr. Gregory Wong

3157 1086

Site Agent

Mr. Daniel Cheung

3157 1086

Environmental Officer

Mr. C. M. Wong

3157 1086

Chun Wo  Leader Joint Venture

Contractor under Contract no. HK/2009/01

Site Agent

Paul Yu

9456 9819

2634 1626

Operation Manager

Ho Wing Tai

9306 1356

Construction Manager

David Wong

9653 8635

Construction Manager

Wilson Lau

5183 1270

Construction Manager

Alex Tsang

9194 9383

Environmental Officer (Compliance Manager)

Ho Wing Tai

9306 1356

Environmental Engineer

Ken Yang

9262 6791

Chun Wo  CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Project Manager

Mr. Chan Sing Cho

3658 3002

2827 9996

Site Agent

Mr. Anthony Wu

3658 3004

Environmental Officer (Compliance Manager)

Mr. Barry Leung

3658 3031

Environmental Engineer

Ms. Flora Ng

3658-3064

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3743 0788

3548 6988

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

2.5               Principle Work and Activities

2.5.1.        During this reporting period, the principle work activities for Contract no. HY/2009/11 are summarized in Table2.4.

Table 2.4   Principle Work Activities for Contract no. HY/2009/11

June 2010

July 2010

August 2010

Ÿ              Installation of seawall blocks;

Ÿ              Construction of Caissons at Casting Yard in Mainland China;

Ÿ              Dredging works; and

Ÿ              Construction of Rock Mound

Ÿ              Construction of Rock Mound,

Ÿ              Floating Out of Caisson Seawall,

Ÿ              Installation of Caisson Seawall,

Ÿ              Dredging works, and

Ÿ              Laying of geo-textile

Ÿ              Construction of Rock Mound,

Ÿ              Floating Out of Caisson Seawall,

Ÿ              Installation of Caisson Seawall,

Ÿ              Dredging works,

Ÿ              Filling works;

Ÿ              Laying of geo-textile,

Ÿ              Drainage Works; and

Ÿ              Seawall Block Installation

 

2.5.2.        Major marine activities for Contract no. HK/2009/01 has been commenced on 23 July 2010. The preparation works and major construction works in the reporting quarter are summarized in Table 2.5.

Table 2.5   Principle Work Activities for Contract no. HK/2009/01

June 2010

July 2010

August 2010

 -           Erection of interim Engineer’s Principal Office at Works areas WA2;

 -           Pre-drilling works and fabrication of staging for trial pile

 -           Transportation of materials to the designated pile position by derrick barges.

 -           Decorative panel installation;

 -           Re-mobilization of flat top barge to carry out Marine S.I. within fairway;

 -           Marine ground investigation;

 -           Fabrication of pipe pile wall staging at the existing promenade piled deck;

 -           Fabrication of special made flat top barge for dredging inside the HKCEC water channel;

 -           Production of pipe pile casing is underway, first batch of 30 nos. x 12 m mill steel pipeline arrived and stored at Yuen Long Yard;

 -           Completion of silt screens installation for HKCEC Phase 1, Government Buildings, China Resources, Great Eagle & Harbour Centre, Telecom House, Shui On, HKAPA, Sheung Wan & Kowloon South Pumping Station and HKCEC Extension (Pumping Station P6);

 -           Erection of temporary platform for pipe pile installation; and

 -           Fabrication of mud barges and crane barge for dredging within HKCEC water channel

 -           Erection of interim Engineer’s Principal Office at works area WA2

 -           Hoarding erection at Wan Chai HKCEC VIP Drop-off Area and Tsim Sha Tsui Salisbury Area;

 -           The flat top barge is continued to carry out Marine S.I. within fairway area

 -           Marine S.I. at east side of HKCEC;

 -           Fabrications of submarine pipelines;

 -           Silt screens installation are completed for HKCEC Phase 1, Government Buildings, China Resoureces, Great Eagle & Harbour Centre, Telecom House, Shui On, HKAPA, Sheung Wan & Kowloon South Pumping Station and HKCEC Extension (Pumping Station P6);

 -           Routine maintenance and clearance works for silt screens;

 -           Erection of temporary platform for pipe pile installation;

 -           Fabrication of 3 nos. of mud barges for dredging within HKCEC water channel and delivered on site. Application of respective license;

 -           Fabrication of crane barges are in progress and expect to deliver to site; and

 -           Wheel washing facility will be provided at the north entrance to the water channel

 -           Erection of interim Engineer’s Principal Office at Works areas WA2

 -           Modification of CATV combine service inspection chamber

 -           Installation of staging piles for trial bored pile was completed and bored pile construction

 -           Marine site investigation

 -           Dredging works for cross harbour watermains

 -           Dismantling of existing sloping seawall and removal of armor rock at north-west side of water channel is stopped and reinstating the rock slope at seawall

 -           Hoarding erection at Tsim Sha Tsui Salisbury Garden area

 -           18m of artwork panel is installed as design for other location

 -           Trial pits construction for determination of pipeline alignment at Convention Avenue

 -           Fabrication of straight sections of cross harbour submarine pipes and land water pipes

 -           Elbow sections of cross harbour submarine pipes are being fabricated.

 -           Commenced assemble of 6 nos. of tailor made flat top barge. The fabrication of dredging crane was completed and will be installed on the tailor make flat top barge and ready for dredging.

 

2.5.3.        Major construction activities for Contract no. HK/2009/02 has been commenced on 5 July 2010. The preparation works and major construction works in the reporting quarter are summarized in Table 2.6.

Table 2.6   Principle Work Activities for Contract no. HK/2009/02

June 2010

July 2010

August 2010

Ÿ              Site Clearance;

Ÿ              Hoarding Erection;

Ÿ              Dismantle Existing Footbridge Staircase at Wan Shing Road;

Ÿ              Pre-drilling Works at WSD Salt Water Pumping Station;

Ÿ              Construction of Salt Water Intake Culvert at Pet Garden;

Ÿ              Road Modification Works; and

Ÿ              Construction of temporary seawall

Ÿ              Site Clearance;

Ÿ              Hoarding Erection;

Ÿ              Breaking and Excavation at WSD Pumping Station;

Ÿ              Demolition Footbridge Staircase at WSD Pumping Station;

Ÿ              Construction of Salt Water Intake Culvert at Pet Garden;

Ÿ              Road Modification Works;

Ÿ              Construction of Cooling Mains Along Public Road;

Ÿ              Construction of Temporary Seawall;

Ÿ              Dredging for WCR 1; and

Ÿ              Equipments Procurement for TKO 137

Ÿ              Site Clearance;

Ÿ              Hoarding Erection;

Ÿ              Pre-bored H-piles, ELS and excavation at WSD Pumping Station;

Ÿ              Construction of Salt Water Intake Culvert at Pet Garden;

Ÿ              Road Modification Works;

Ÿ              Construction of Cooling Mains Along Public Road;

Ÿ              Construction of Temporary Seawall;

Ÿ              Dredging for WCR 1;

Ÿ              Tree Transplanting; and

Ÿ              Equipments Procurement for TKO 137

 

2.5.4.        Implementation status of the recommended mitigation measures during this reporting period is presented in Appendix 2.1.

 

3.     Monitoring Requirements

3.1.               Noise Monitoring

Noise Monitoring Stations

3.1.1.        The noise monitoring stations for the Project are listed and shown in Table 3.1 and Figure 3.1.  /span>Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.1  Noise Monitoring Stations

Station

Description

M1a

Harbour Road Sports Centre

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

M4a

Causeway Bay Community Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

 

Noise Monitoring Parameters, Frequency and Duration

3.1.2.        The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

3.1.3.        Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

 -           one set of measurements between 0700 and 1900 hours on normal weekdays.

3.1.4.        If construction works are extended to include works during the hours of 1900   0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

3.2.                        Air Monitoring

Air Quality Monitoring Stations

3.2.1.        The air monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.2  Air Monitoring Stations

Station ID

Monitoring Location

Description

CMA1b

Oil Street Community Liaison Centre

North Point

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

Future CWB site office at Wanchai Waterfront Promenade

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5a

Children Playgrounds opposite to Pedestrian Plaza

Wan Chai

CMA6a

Future AECOM site office at Work Area

Wan Chai

MA1e

International Finance Centre (Eastern End of Podium)

Central

MA1w

International Finance Centre (Western End of Podium)

Central

 

Air Monitoring Parameters, Frequency and Duration

3.2.2.        One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

3.2.3.        All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

3.2.4.        For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.

3.3.               Water Quality Monitoring

3.3.1.        The EIA Report has identified that the key water quality impact would be associated with the dredging works during the construction phase. Marine water quality monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is therefore recommended to be carried out at selected WSD flushing water intakes. The impact monitoring should be carried out during the proposed dredging works to ensure the compliance with the water quality standards.

Water Quality Monitoring Stations

3.3.2.        It is proposed to monitor the water quality at 9 WSD salt water intakes and 14 cooling water intakes along the seafront of the Victoria Harbour. The proposed water quality monitoring stations of the Project are shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.3   Marine Water Quality Stations for Water Quality Monitoring

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD7

Kowloon South

834150.0

818300.3

WSD9

Tai Wan

837921.0

818330.0

WSD10

Cha Kwo Ling

841900.9

817700.1

WSD15

Sai Wan Ho

841110.4

816450.1

WSD17

Quarry Bay

839790.3

817032.2

WSD19

Sheung Wan

833415.0

816771.0

WSD20

Kennedy Town

830750.6

816030.3

WSD21

Wan Chai

836220.8

815940.1

RW1

Wan Chai (Reprovision)

836188.8

815911.1

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

C2

Telecom House

835647.9

815864.4

C3

HKCEC Phase I

835836.2

815910.0

C4e

Wan Chai Tower and Great Eagle Centre (Eastern)

835932.8

815888.2

C4w

Wan Chai Tower and Great Eagle Centre (Western)

835629.8

815889.2

C5e

Sun Hung Kai Centre (Eastern)

836250.1

815932.2

C5w

Sun Hung Kai Centre (Western)

836248.1

815933.2

C6

World Trade Centre

837009.6

815999.3

C7

Windsor House

837193.7

816150.0

C8

City Garden

837970.6

816957.3

C9

Provident Garden

838355.0

817116.6

RC1

Proposed HKAPA Extension

835487.7

815987.7

RC5

Sun Hung Kai Centre (Reprovision)

836291.4

816029.7

RC7

Windsor House (Temporary Dilution)

837245.2

816156.6

 

Water Quality Parameters and frequency

3.3.3.        Monitoring of dissolved oxygen (DO), turbidity and suspended solids (SS) shall be carried out at WSD flushing water intakes and cooling water intakes. DO and Turbidity are measured in-situ while SS is determined in laboratory. 

3.3.4.        In association with the water quality parameters, other relevant data shall also be measured, such as monitoring location/position, time, sampling depth, water temperature, pH, salinity, dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal stage, and any special phenomena and work underway at the construction site etc.

3.3.5.        The interval between two sets of monitoring should not be less than 36 hours except where there are exceedances of Action and/or Limit Levels, in which case the monitoring frequency will be increased. Table 3.4 shows the proposed monitoring frequency and water quality parameters. Duplicate in-situ measurements and water sampling should be carried out in each sampling event. For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5m.

Table 3.4  Marine Water Quality Monitoring Frequency and Parameters

Activities

Monitoring Frequency1

Parameters2

During the 4-week baseline monitoring period

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

During marine construction works

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

After completion of marine construction works

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

Notes:

1.       For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5m.

2.       Turbidity should be measured in situ whereas SS should be determined by laboratory.

 

 

4.     Monitoring Results

4.0.1.        The environmental monitoring will be implemented based on the division of works areas of each designed project managed under different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 3.1. The monitoring results are presented in according to the Individual Contract(s).

 

   4.1.          Noise Monitoring Results

Contract no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation

4.1.1.        The proposed division of noise monitoring stations for Contract no. HY/2009/11 are summarized in Table 4.1 below:

Table 4.1   Noise Monitoring Stations for Contract no.  /span>HY/2009/11

Station

Description

M4a

Causeway Bay Community Centre

M4b

Victoria Centre

M5b

City Garden

 

4.1.2.        Reviewed the past monitoring results and observation at Station M4a, the monitoring location at Causeway Bay Community Centre is facing and closed to the Island Eastern Corridor. Traffic noise is the major noise source obtained in the monitoring that cannot reflect the construction noise from the construction site. Victoria Centre (Station ID: M4b) was proposed as alternative noise monitoring station effective from August 2010.

4.1.3.        Two action level exceedances were recorded due to the noise complaints on 31 July and 12 August 2010. There were complained on the construction noise nuisance from the dredging work activities at North Point District. Contractor’s site practical and measurement results were reviewed. The details of the complaints can be referred to Section 6 and Appendix 6.1.

4.1.4.        Five limit level exceedances were recorded at M4a on 8 and 22 June 2010 and 20 and 27 July 2010 and at M5b on 16 June 2010 August 2010. All exceedances were investigated and found not attributed to the project works as major noise source was obtained from the Island Eastern Corridor. It was concluded that the exceedances were not due to the project.

4.1.5.        Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of graphical presentation can be referred in Appendix 4.1. 

 

Contract no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at HKCEC and Contract no. HK/2009/02 - Wan Chai Development Phase II  Central   Wan Chai Bypass at WanChai East

4.1.6.        The commencement of marine construction works for Contract nos. HK/2009/01 and HK/2009/02 have been commenced in July 2010. The proposed division of noise monitoring stations are summarized in Table 4.2 below.

Table 4.2   Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02

Station

Description

M1a

Harbour Road Sports Centre

4.1.7.        Six limit level exceedances were recorded at station M1a on 13, 20 and 27 July 2010 and 3, 10 and 17 August 2010 during construction works at evening time for Contract no. HK/2009/02 in reporting quarter. Major noise source was contributed from Tonnochy Road and water sport competition at Wan Chai Training Swimming Pool. The dredging work was complied with the conditions under valid Construction Noise Permit no. GW-RS0132-10 during the measurement.

   4.2.          Air Monitoring Results

Contract no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation

4.2.1.        Since the filling work of Contract no. HY/2009/11 were commenced in the mid-August 2010, air monitoring had been commenced on 11 August 2010. The proposed division of air monitoring stations is summarized in Table 4.3 below.

Table 4.3   Air Monitoring Stations for Contract no. HY/2009/11

Station

Description

CMA1b

Oil Street Community Liaison Centre

CMA2a

Causeway Bay Community Centre

 

4.2.2.        Due to no 24-hour electricity supply in CMA1b  Oil Street Community Liaison Centre, only 1-hour TSP monitoring can be conducted in the reporting quater. Details of noise monitoring results and graphical presentation can be referred in Appendix 4.2.

4.2.3.        One action level exceedance was recorded at CMA1b on 24 August 2010. Investigation found that the exceedance was not related to the Project work but due to the burning joss paper activity near the Oil Street Community Centre between 23 and 25 August 2010 morning.

Contract no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at HKCEC

4.2.4.        Air monitoring will be commenced from the filling work for Contract no. HK/2009/01. The proposed division of air monitoring stations are summarized in Table 4.4 below.

Table 4.4   Air Monitoring Stations for Contract no. HK/2009/01

Station

Description

CMA5a

Children Playgrounds opposite to Pedestrian Plaza

CMA6a

Future AECOM site office at Work Area 1

 

Contract no. HK/2009/02 - Wan Chai Development Phase II  Central  Wan Chai Bypass at WanChai East

4.2.5.        Air monitoring will be commenced from the filling work for Contract no. HK/2009/02. The proposed division of air monitoring stations are summarized in Table 4.5 below.

Table 4.5   Air Monitoring Station for Contract no. HK/2009/02

Station

Description

CMA4a

Society for the Prevention of Cruelty to Animals

 

4.2.6.        No major dust impact is anticipated to be caused by the site preparation works and dredging works during the reporting quarter. Air monitoring will be commenced from the filling works for Contract no. HK/2009/01 and HK/2009/02. Therefore, no air monitoring was conducted in the reporting period.

   4.3.          Water Monitoring Results

Contract no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation

4.3.1.        The proposed division of water monitoring stations for Contract no. HY/2009/11 are summarized in Table 4.6 below:

Table 4.6  Water Monitoring Stations for Contract no.  /span>HY/2009/11

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD9

Tai Wan

837921.0

818330.0

WSD10

Cha Kwo Ling

841900.9

817700.1

WSD15

Sai Wan Ho

841110.4

816450.1

WSD17

Quarry Bay

839790.3

817032.2

Cooling Water Intake

C8

City Garden

837970.6

816957.3

C9

Provident Garden

838355.0

817116.6

 

Contract no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at HKCEC

4.3.2.        Water monitoring stations for Contract no. HK/2009/01 were commenced on 8 July 2010. The proposed division of water monitoring stations are summarized in Table 4.7 below.

Table 4.7   Water Monitoring Stations for Contract no. HK/2009/01

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD7

Kowloon South

834150.0

818300.3

WSD19

Sheung Wan

833415.0

816771.0

WSD20

Kennedy Town

830750.6

816030.3

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

C2

Telecom House

835647.9

815864.4

C3

HKCEC Phase I

835836.2

815910.0

C4e

Wan Chai Tower and Great Eagle Centre (Eastern)

835932.8

815888.2

C4w

Wan Chai Tower and Great Eagle Centre (Western)

835629.8

815889.2

 

Contract no. HK/2009/02 - Wan Chai Development Wan Chai Development Phase II  Central   Wan Chai Bypass at WanChai East

4.3.3.        Water monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010. The proposed division of water monitoring stations are summarized in Table 4.8 below.

Table 4.8   Water Monitoring Stations for Contract no. HK/2009/02

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD21

Wan Chai

836220.8

815940.1

Cooling Water Intake

C5e

Sun Hung Kai Centre (Eastern)

836250.1

815932.2

C5w

Sun Hung Kai Centre (Western)

836248.1

815933.2

 

4.3.4.        Water quality monitoring at the stations for Contract nos. HK/2009/01 and HK/2009/02 were commenced on 8 July 2010. Water quality monitoring was conducted at total 17 monitoring stations namely WSD7, WSD9, WSD10, WSD15, WSD17, WSD19, WSD20, WSD 21, C1, C2, C3, C4e, C4w, C5e, C5w, C8 and C9 during the reporting period.

4.3.5.        The access to WSD7 is needed to via the gates that are locked and under the control of LCSD between 1800hrs and 0800hrs from 10 July 2010. Due to no access permission obtained from LCSD in this reporting quarter, water monitoring cannot be conducted at WSD7 on 10 July 2010 at mid-flood, 14 July 2010 at mid-flood and mid-ebb, 18 July 2010 at mid-flood and 19 July 2010 at mid-ebb. The approval of access permission had been obtained from LCSD for the access to WSD7 in Mid-August 2010. However, due to the wrong locking order of the series pad locks at the gate, water quality monitoring could not be conducted on 30 July 2010, 18 and 25 August 2010.

4.3.6.        The construction and maintenance works of the silt screen cover at C4e and C4w was conducted by Chun Wo & Leader JV on 14 July 2010, no water monitoring was conducted at these stations during the mid-ebb.

4.3.7.        Concerning the safety works and the unrepresentative water quality being substantially affected by urban runoff under adverse weather, the following water quality monitoring were cancelled:

-          28 June 2010 at mid-ebb for all stations; 28 July 2010 at mid-ebb tide for C1 to C4 due to amber rainstorm warning in force;

-          5 August 2010 at mid-flood for all stations due to red rainstorm warning in force;

-          28 July 2010 at mid-flood for all stations due to black rainstorm warning in force;

-          21 July 2010 at mid-flood for all stations due to Strong Wind Signal No. 3 announced.

4.3.8.        Water monitoring results measured in this reporting period are reviewed and summarized in Table 4.9. Details of water quality monitoring results and graphical presentation can be referred in Appendix 4.3.

Table 4.9   Summary of Water Quality Monitoring Exceedances in Reporting Quarter

Contract no.

Water Monitoring Station

Mid-flood 

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HY/2009/11

WSD9

2

2

0

0

0

1

2

4

0

0

0

1

 

WSD10

3

3

0

0

3

2

2

7

0

0

1

0

 

WSD15

3

4

0

0

1

3

4

8

0

0

1

0

 

WSD17

3

3

0

0

0

1

4

10

1

0

0

3

 

C8

5

2

2

0

7

2

3

2

0

4

7

4

 

C9

4

1

0

1

8

1

6

0

2

1

6

3

HK/2009/01

WSD19

1

1

1

0

0

2

2

3

0

0

0

0

 

WSD20

1

1

0

0

0

2

2

2

0

0

1

2

 

WSD7

0

1

0

0

0

0

0

4

0

0

0

0

 

C1

0

0

0

0

0

0

0

0

0

0

0

0

 

C2

1

1

0

0

1

0

3

0

0

0

0

1

 

C3

1

0

0

0

1

0

3

0

0

0

1

1

 

C4e

1

0

0

0

1

0

4

0

0

0

0

0

 

C4w

1

0

0

0

0

0

2

0

0

0

1

0

HK/2009/02

C5e

1

0

0

0

2

1

2

0

0

0

1

0

 

C5w

1

1

0

0

2

1

0

0

0

0

1

0

 

WSD21

0

1

0

0

0

1

1

0

0

0

0

1

 Total

28

21

3

1

26

17

40

43

3

5

20

16

 

4.3.9.        The exceedances have been investigated and were considered unlikely to be related to project works. Water monitoring results measured in this reporting period are reviewed and summarized. Details of graphical presentation can be referred in Appendix 4.2.

 

   4.4.          Waste Monitoring Results

Contract no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation

4.4.1.        No inert and non-inert C&D waste was disposed in this reporting period. Details of the waste flow table are summarized in Table 4.10

Table 4.10 Details of Waste Disposal for Contract no. HY/2009/11

Waste Type

Quantity this quarter, m3

Cumulative Quantity-to-Date, m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

NIL

N/A

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

NIL

NIL

SENT Landfill

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

N/A

N/A

N/A

Marine Sediment (Type 1  Open Sea Disposal)

 /span>35,500

(Bulk Volume)

71,500

(Bulk Volume)

South of Cheung Chau

Marine Sediment (Type 1  Open Sea Disposal (Dedicate Sites) & Type 2  Confined Marine Disposal)

35,000

(Bulk Volume)

81,000

(Bulk Volume)

East of Sha Chau

 

4.4.2.        There were marine sediments Type 1  Open Sea Disposal and Type 1  Open Sea Disposal (Dedicate Sites) & Type 2   Confined Marine Disposal marine sediment disposed in the reporting period. The maximum dredging rate in North Point Shoreline Zone is 3,000m3 per day in the reporting quarter, which is complied with the criteria listed in Table 5.10 of EIA Report Register No. AEIAR-125/2008.

 

Contract no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at HKCEC

4.4.3.        Inert and non-inert C&D waste was disposed of for the site preparation works in this reporting period. Details of the waste flow table are summarized in Table 4.11.

Table 4.11 Details of Waste Disposal for Contract no. HK/2009/01

Waste Type

Quantity this quarter, m3

Cumulative Quantity-to-Date, m3

Disposal / Dumping Grounds

Inert C&D materials disposed

201.54

201.54

TKO134

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

        33.91

43.68

SENT Landfill

Non-inert C&D materials recycled

2.89

2.89

N/A

Chemical waste disposed

0.29

0.29

N/A

Marine Sediment (Type 1  Open Sea Disposal)

23,987

(Bulk Volume)

23,987

(Bulk Volume)

South of Cheung Chau

Marine Sediment (Type 1  Open Sea Disposal (Dedicate Sites) & Type 2  Confined Marine Disposal)

NIL

NIL

N/A

 

4.4.4.        There were marine sediments Type 1  Open Sea Disposal disposed in the reporting period. The maximum dredging rate in Cross Harbour Water Main is 845m3 per day in the reporting quarter, which is complied with the criteria listed in Table 5.10 of EIA Report Register No. AEIAR-125/2008.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II  Central  Wan Chai Bypass at WanChai East

4.4.5.        Inert and non-inert C&D waste was disposed of for the site preparation works in this reporting period. Details of the waste flow table are summarized in Table 4.12.

Table 4.12 Details of Waste Disposal for Contract no. HK/2009/02

Waste Type

Quantity this quarter, m3

Cumulative Quantity-to-Date, m3

Disposal / Dumping Grounds

Inert C&D materials disposed

1550.5

1550.5

TKO137

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

5.5

27.5

SENT Landfill

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

NIL

NIL

N/A

Marine Sediment (Type 1  Open Sea Disposal)

NIL

NIL

N/A

Marine Sediment (Type 1  Open Sea Disposal (Dedicate Sites) & Type 2  Confined Marine Disposal)

51210

(Bulk Volume)

51210

(Bulk Volume)

East of Sha Chau

 

4.4.6.        There was marine sediment (Type 1  Open Sea Disposal (Dedicate Sites) & Type 2  Confined Marine Disposal) disposed in reporting quarter at a maximum dredging rate 1,590m3 per day. On-going ET site inspections observed that the temporary western seawall has been partially constructed since early August 2010 with no apparent water quality impact reported for the stations WSD21, C5e and C5w, it is considered the maximum dredging rate at WCR can be stepped up to 6,000m3 as per the criteria under Table 5.10 of EIA Report Register No. AEIAR-125/2008 for dredging with WCR area.

5.     Compliance Audit

5.0.1.        The Event Action Plan for construction noise, air quality and water quality are presented in Appendix 5.1.

5.1.               Noise Monitoring

5.1.1.        Two action level exceedances were recorded due to the noise complaints on 31 July and 12 August 2010. There were complained on the construction noise nuisance from the dredging work activities at North Point District. Contractor’s site practical and noise monitoring results were reviewed. Investigation found that the complaints were considered not valid from the Environmental Permit and Construction Noise Permit point of view. The details of the complaints can be referred to Section 6 and Appendix 5.1.

5.1.2.        Eleven limit level exceedances were recorded in the reporting quarter. All exceedances were investigated and found not attributed to the project works as major noise source was obtained from the traffic noise. Besides, crowd noise from the Wan Chai Training Pool was also contributed during evening noise monitoring at M1a  Harbour Road Sports Centre. It was concluded that the exceedances were not due to the project.

5.2.               Air Monitoring

5.2.1.        One action level exceedance was recorded at CMA1b on 24 August 2010. Investigation found that the exceedance was due to the burning joss paper activities near CMA1b.

5.3.               Water Quality Monitoring

5.3.1.        The summary of water quality exceedances recorded in reporting quarter is presented in the Table 5.1.

Table 5.1  Summary of Water Quality Exceedances in the reporting Quarter

Contract no.

Water Monitoring Station

Mid-flood 

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HY/2009/11

WSD9

2

2

0

0

0

1

2

4

0

0

0

1

 

WSD10

3

3

0

0

3

2

2

7

0

0

1

0

 

WSD15

3

4

0

0

1

3

4

8

0

0

1

0

 

WSD17

3

3

0

0

0

1

4

10

1

0

0

3

 

C8

5

2

2

0

7

2

3

2

0

4

7

4

 

C9

4

1

0

1

8

1

6

0

2

1

6

3

HK/2009/01

WSD19

1

1

1

0

0

2

2

3

0

0

0

0

 

WSD20

1

1

0

0

0

2

2

2

0

0

1

2

 

WSD7

0

1

0

0

0

0

0

4

0

0

0

0

 

C1

0

0

0

0

0

0

0

0

0

0

0

0

 

C2

1

1

0

0

1

0

3

0

0

0

0

1

 

C3

1

0

0

0

1

0

3

0

0

0

1

1

 

C4e

1

0

0

0

1

0

4

0

0

0

0

0

 

C4w

1

0

0

0

0

0

2

0

0

0

1

0

HK/2009/02

C5e

1

0

0

0

2

1

2

0

0

0

1

0

 

C5w

1

1

0

0

2

1

0

0

0

0

1

0

 

WSD21

0

1

0

0

0

1

1

0

0

0

0

1

 Total

28

21

3

1

26

17

40

43

3

5

20

16

 

5.3.2.        Since all exceedances recorded were not project-related, follow-up mitigation measures were therefore not required.

5.4.               Review of Action and Limit Level for Water Quality Monitoring

5.4.1          Existing Action and Limit Levels were derived based on the 4-weeks baseline water quality monitoring data obtained during the dry season in October and November 2009 prior to the commencement of construction. The Action and Limit Levels are applied the water monitoring for all seasons.

5.4.2          Owing to the frequent non-project related exceedances caused by fluctuation in coastal water quality due to localized effect, it is considered the existing Action and Limit Levels values were underestimated to the natural variation of water quality around the baseline range.  It is recommended to review the existing Action and Limit Levels on water quality in order to take into the account of the coastal activities and potential variation of coastal water qualities during wet season (i.e. Apr  Sep period). Action and Limit levels for wet season were devised based on a projected scenario calculated using the marine water quality data obtained at the closest EPD routine monitoring stations as per EM&A Manual Section 4.10.4 which states,

“Where necessary, EPD routine water quality monitoring data at the relevant station(s), dry and wet seasons inclusive, could also be used to established the baseline water quality. o:p>

 

5.4.3          While the existing Action and Limit levels will continue to be used for impact monitoring for dry season (Oct  Mar period), an additional set of Action and Limit levels are proposed for use in the coming wet season and are summarized in Table 5.2. The details of calculation using the marine water quality data obtained at the closest EPD routine monitoring stations can be referred to Appendix 5.2.


Table 5.2  Proposed Action and Limit Levels for Water Quality Monitoring

 

Dry Season (Existing AL & LL)

Wet Season

Parameters

Action

Limit

Action

Limit

WSD Salt Water Intakes

 

 

 

 

SS in mg/L

13.00

14.43

16.26

19.74

Turbidity in NTU

8.04

9.49

10.01

11.54

DO in mg/L

3.66

3.28

3.17

2.63

Cooling Water Intakes

 

 

 

 

SS in mg/L

15.00

22.13

18.42

27.54

Turbidity in NTU

9.10

10.25

11.35

12.71

DO in mg/L

3.36

2.73

3.02

2.44

 

5.5.               Site Audit

5.5.1.        There was no non-compliance from the site audits in the reporting period. During environmental site inspections conducted during the reporting quarter, minor deficiencies were noted. However, the Contractor rectified all deficiencies after receipt of notification.

5.6.               Review of the Reasons for and the Implications of Non-compliance

5.6.1.        No project-related non-compliance from monitoring was recorded in the reporting period.

5.7.               Summary of action taken in the event of and follow-up on non-compliance

5.7.1.        There was no particular action taken since no project-related non-compliance was recorded from the site audits and environmental monitoring in the reporting period.

 

6.     Complaints, Notification of Summons and Prosecution

6.0.1.        Two noise complaints were recorded on 31 July and 12 August 2010 regarding noise nuisance from the dredging works in North Point district. Investigation found that the complaints were considered not valid from the Environmental Permit and Construction Noise Permit point of view.  The details of cumulative complaint log and summary of complaints are presented in Appendix 6.1.

6.0.2.        No notification of summons or prosecution was received in the reporting period. Cumulative statistic on complaints and successful prosecutions are summarized in Table 6.1 and Table 6.2 respectively.

Table 6.1  Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

Jun - Aug 2010

2

Project-to-Date

5

 

Table 6.2  Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this quarter (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Water

-

0

0

Waste

-

0

0

Total

-

0

0

 

 

7.     Cumulative Construction Impact due to the Concurrent Projects

7.0.1.        According to Condition 3.4 of the EP-356/2009, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation, Central-WanChai Bypass and Island Eastern Corridor Link projects.

7.0.2.        According to the construction programme of Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activity under Wan Chai Development Phase II was the dredging works at North Point Reclamation Stage 1(NPR1), Wan Chai Reclamation Stage 1(WCR1) and Cross Harbour Water Mains in the reporting quater. The major environmental impact was water quality impact at North Point and Wan Chai. No major construction activities were undertaken in the Central-Wan Chai Bypass and Island Eastern Corridor Link projects.

7.0.3.        The major environmental impacts generated from the Central Reclamation Phase III were located along the coastline of Central and Admiralty while dredging works at NPR1, WCR1 and Cross Harbour Water Mains were in operation in this reporting quarter. The dredging works was just commenced at WCR1 and Cross Harbour Water Mains in this reporting quarter.  /span>Beside, water quality mitigation measures were properly in place for the dredging works in this reporting quarter. No project related exceedance was recorded. Thus, it is evaluated that the cumulative construction impact from the concurrent projects including Wan Chai Development Phase II and Central Reclamation Phase III was insignificant.

8.     Conclusion

8.0.1.        The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

8.0.2.        No project-related exceedance, non-compliances were noted and no prosecutions were received during the reporting quarter.

8.0.3.        Owing to the frequent non-project related exceedances caused by fluctuation in coastal water quality due to localized effect, it is considered the existing Action and Limit Levels values were underestimated to the natural variation of water quality around the baseline range.  It is recommended to review the existing Action and Limit Levels on water quality in order to take into the account of the coastal activities and potential variation of coastal water qualities during wet season (i.e. Apr  Sep period). While the existing Action and Limit levels will continue to be used for impact monitoring for dry season (Oct  Mar period), an additional set of Action and Limit levels are proposed for use in the coming wet season.

8.0.4.        The construction programmes of individual contracts are provided in Appendix 8.1.