Contract No:
HK/2009/05 Wanchai Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing Work
(Stage 1) Environmental
Permit no. EP-356/2009, Further Evironmental permit nos. fep-01/356/2009,
fep-02/356/2009 and FEP-03/356/2009 Quarterly
Environmental Monitoring
and Audit Report
- June
to August 2010 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai,
H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED
by: |
|
                         Raymond Dai Environmental Team Leader |
|
DATE: |
|
29 October 2010 |
1.1    Scope of the Report
2.   Project Background
2.1    Background
2.2    Scope of the Project and Site Description
2.3    Division of the Project Responsibility
2.4    Project Organization and Contact Personnel
2.5    Principle Work and Activities
3.   Monitoring Requirements
3.1.    Noise Monitoring
3.2.    Air Monitoring
3.3.    Water Quality Monitoring
4.   Monitoring Results
4.1.    Noise Monitoring Results
4.2.    Air Monitoring Results
4.3.    Water Monitoring Results
4.4.    Waste Monitoring Results
5.1.    Noise Monitoring
5.2.    Air Monitoring
5.3.    Water Quality Monitoring
5.4.    Site Audit
5.5.    Review of the Reasons for and the Implications of
Non-compliance
5.6.    Summary of action taken in the event of and follow-up
on non-compliance
6.   Complaints, Notification of Summons and Prosecution
7.   Cumulative Construction Impact due to the Concurrent Projects
lIST OF
TABLES
Table I      Principle Work Activities for Contract no. HY/2009/11
Table II     Principle Work Activities for Contract no.
HK/2009/01
Table III     Principle Work Activities for Contract no.
HK/2009/02
Table IV    Revised Action and Limit Levels for Water
Quality Monitoring
Table 2.1    Schedule 2 Designated Projects under this
Project
Table 2.2   Details of Individual Contracts under the
Project
Table 2.3   Contact Details of Key Personnel
Table 2.4    Principle Work Activities for Contract no.
HY/2009/11
Table 2.5    Principle Work Activities for Contract no.
HK/2009/01
Table 2.6    Principle Work Activities for Contract no.
HK/2009/02
Table 3.1   Noise Monitoring Stations
Table 3.2   Air Monitoring Stations
Table 3.3    Marine Water Quality Stations for Water
Quality Monitoring
Table 3.4   Marine Water Quality Monitoring Frequency
and Parameters
Table 4.1    Noise Monitoring Stations for Contract
no. HY/2009/11
Table 4.2
   Noise Monitoring Station for Contract nos.
HK/2009/01 and HK/2009/02
Table 4.3
  Air Monitoring
Stations for Contract no. HY/2009/11
Table 4.4
   Air Monitoring Stations for Contract no.
HK/2009/01
Table 4.5
   Air Monitoring Station for Contract no.
HK/2009/02
Table 4.6   Water Monitoring Stations for Contract
no. HY/2009/11
Table 4.7
   Water Monitoring Stations for Contract no.
HK/2009/01
Table 4.8
   Water Monitoring Stations for Contract no.
HK/2009/02
Table 4.9
   Summary of Water Quality Monitoring
Exceedances in Reporting Quarter
Table 4.10  Details of Waste Disposal for Contract no.
HY/2009/11
Table 4.11  Details of Waste Disposal for Contract no.
HK/2009/01
Table 4.12  Details of Waste Disposal for Contract no.
HK/2009/02
Table 5.1   Summary of Water Quality Exceedances in the
reporting Quarter
Table 5.2   Proposed Action and Limit Levels for Water
Quality Monitoring
Table 6.1   Cumulative Statistics on Complaints
Table 6.2   Cumulative Statistics on Successful
Prosecutions
lIST OF FIGUREs
Figure
2.1     Project
Layout
Figure
2.2     Project
Organization Chart
Figure 3.1      Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 2.1   Environmental Mitigation Implementation
Schedule
Appendix 3.1   Action
and Limit Level
Appendix 4.1   Noise Monitoring Graphical Presentations
Appendix
4.2   Air Quality Monitoring Graphical
Presentations
Appendix 4.3   Water Quality Monitoring Graphical Presentations
Appendix 5.1   Event
Action Plans
Appendix 5.2   Calculation
using the Marine Water Quality Data Obtained at the Closest EPD Routine Monitoring
Stations
Appendix
6.1   Complaint Log
Appendix 8.1   Construction
Programme of Individual Contracts
Construction Activities for the
Reported Period
Table I     Principle Work Activities for Contract no. HY/2009/11
June
2010 |
July
2010 |
August
2010 |
Installation of seawall blocks;
Construction of Caissons at Casting Yard in
Mainland China;
Dredging works; and
Construction of Rock Mound |
Construction of Rock Mound,
Floating Out of Caisson Seawall,
Installation of Caisson Seawall,
Dredging works, and
Laying of geo-textile |
Construction of Rock
Mound,
Floating Out of Caisson
Seawall,
Installation of Caisson
Seawall,
Dredging works,
Filling works;
Laying of geo-textile,
Drainage Works; and
Seawall Block
Installation |
Table II    Principle Work Activities for Contract no. HK/2009/01
June 2010 |
July 2010 |
August 2010 |
 -
Erection of interim Engineer’s Principal Office at Works areas WA2;  -
Pre-drilling works and fabrication of staging for trial pile  -
Transportation of materials to the designated pile
position by derrick barges.  -
Decorative panel installation;  -
Re-mobilization of flat top barge to carry
out Marine S.I. within fairway;  -
Marine ground investigation;  -
Fabrication of pipe pile wall staging at the existing promenade piled
deck;  -
Fabrication of special made flat top barge for dredging inside the
HKCEC water channel;  -
Production of pipe pile casing is underway, first batch of 30 nos. x
12 m mill steel pipeline arrived and stored at Yuen Long Yard;  -
Completion of silt screens installation for HKCEC
Phase 1, Government Buildings, China Resources, Great Eagle & Harbour
Centre, Telecom House, Shui On, HKAPA, Sheung Wan & Kowloon South Pumping
Station and HKCEC Extension (Pumping Station P6);  -
Erection of temporary platform for pipe pile installation; and  -
Fabrication of mud barges and crane barge for dredging within HKCEC
water channel |
 -
Erection of interim Engineer’s Principal Office at works area WA2  -
Hoarding erection at Wan Chai HKCEC VIP Drop-off Area and Tsim Sha
Tsui Salisbury Area;  -
The flat top barge is continued to carry out Marine S.I. within
fairway area  -
Marine S.I. at east side of HKCEC;  -
Fabrications of submarine pipelines;  -
Silt screens installation are completed for HKCEC Phase 1, Government
Buildings, China Resoureces, Great Eagle & Harbour Centre, Telecom House,
Shui On, HKAPA, Sheung Wan & Kowloon South Pumping Station and HKCEC
Extension (Pumping Station P6);  -
Routine maintenance and clearance works for silt screens;  -
Erection of temporary platform for pipe pile installation;  -
Fabrication of 3 nos. of mud barges for dredging within HKCEC water
channel and delivered on site. Application of respective license;  -
Fabrication of crane barges are in progress and expect to deliver to
site; and  -
Wheel washing facility will be provided at the north entrance to the
water channel |
 -
Erection of interim Engineer’s Principal Office at Works areas WA2  -
Modification of CATV combine service inspection chamber  -
Installation of staging piles for trial bored pile was completed and
bored pile construction  -
Marine site investigation  -
Dredging works for cross harbour watermains  -
Dismantling of existing sloping seawall and removal of armor rock at
north-west side of water channel is stopped and reinstating the rock slope at
seawall  -
Hoarding erection at Tsim Sha Tsui Salisbury Garden area  -
18m of artwork panel is installed as design for other location  -
Trial pits construction for determination of pipeline alignment at
Convention Avenue  -
Fabrication of straight sections of cross harbour submarine pipes and
land water pipes  -
Elbow sections of cross harbour submarine pipes are being fabricated.  -
Commenced assemble of 6 nos. of tailor made flat top barge. The
fabrication of dredging crane was completed and will be installed on the
tailor make flat top barge and ready for dredging. |
Table III    Principle Work Activities for Contract no. HK/2009/02
June
2010 |
July
2010 |
August
2010 |
Site Clearance;
Hoarding Erection;
Dismantle Existing Footbridge Staircase at Wan Shing
Road;
Pre-drilling Works at WSD Salt Water Pumping
Station;
Construction of Salt Water Intake Culvert at Pet
Garden;
Road Modification Works; and
Construction of
temporary seawall |
Site Clearance;
Hoarding Erection;
Breaking and Excavation at WSD Pumping Station;
Demolition Footbridge Staircase at WSD Pumping
Station;
Construction of Salt Water Intake Culvert at Pet
Garden;
Road Modification Works;
Construction of Cooling Mains Along Public Road;
Construction of Temporary Seawall;
Dredging for WCR 1; and
Equipments Procurement for TKO 137 |
Site Clearance;
Hoarding Erection;
Pre-bored H-piles, ELS
and excavation at WSD Pumping Station;
Construction of Salt
Water Intake Culvert at Pet Garden;
Road Modification Works;
Construction of Cooling
Mains Along Public Road;
Construction of Temporary
Seawall;
Dredging for WCR 1;
Tree Transplanting; and
Equipments Procurement
for TKO 137 |
Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
Table IV   Revised Action and Limit Levels for Water Quality Monitoring
|
Dry
Season (Existing AL & LL) |
Wet
Season |
||
Parameters |
Action |
Limit |
Action |
Limit |
WSD Salt Water Intakes |
|
|
|
|
SS in mg/L |
13.00 |
14.43 |
16.26 |
19.74 |
Turbidity in NTU |
8.04 |
9.49 |
10.01 |
11.54 |
DO in mg/L |
3.66 |
3.28 |
3.17 |
2.63 |
Cooling Water Intakes |
|
|
|
|
SS in mg/L |
15.00 |
22.13 |
18.42 |
27.54 |
Turbidity in NTU |
9.10 |
10.25 |
11.35 |
12.71 |
DO in mg/L |
3.36 |
2.73 |
3.02 |
2.44 |
Complaints, Notifications of
Summons and Successful Prosecutions
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009
and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009 and
FEP-03/356/2009 to implement the Environmental Monitoring and Audit (EM&A)
programme as stipulated in the EM&A Manual of the approved Environmental
Impact Assessment (EIA) Report for Wan Chai Development phase II and
Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring and
auditing work carried out in accordance to the Section
10.4 of EM&A Manual
and  /span>Environmental Monitoring and Audit
Requirements /span>
under Particular Specification Section 27.
1.1.3.
This
report documents the finding of EM&A works during the period from 28th
May 2010 to 27th August 2010.
Section 1     Introduction
 details the scope and structure of the report.
Section 2     Project
Background  summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3     Monitoring
Requirements
 summarizes all monitoring parameters, monitoring locations, monitoring
frequency, duration and action
plan.
Section 4     Monitoring
Results  summarizes the monitoring results
obtained in the reporting period.
Section 5     Compliance
Audit  summarizes the auditing of
monitoring results, all exceedances environmental parameters.
Section 6     Complaints, Notification of summons and Prosecution
 summarizes the cumulative statistics on complaints, notification
of summons and prosecution
Section 7     Cumulative Construction Impact due to the
Concurrent Projects  summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section 8     Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan Chai
Bypass and “Central-Wan Chai Bypass and Island Eastern Corridor Link 
(hereafter called “the Project  are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA)
Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register
No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and
11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to
provide relief to the very congested east-west Connaught Road Central/Harcourt
Road / Gloucester Road Corridor (the Corridor) which is currently operating
beyond its capacity. The CWB will provide relief to the existing congestion
along the Corridor and cater for the anticipated growth of traffic on Hong Kong
Island. Without the CWB and its access roads, there will not be sufficient
capacity to serve the heavy traffic demands at both strategic and local levels.
2.2.1.
The Project is located mainly in Wan Chai North,
Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria
Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road
Interchange to the east, as shown in Figure 2.1.
2.2.2.
The study area encompasses existing developments
along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses
include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the
Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the
Royal Hong Kong Yacht Club (RHKYC), the Police Officers' Club, the Causeway Bay
Typhoon Shelter (CBTS) and commercial and residential developments.
2.2.3.
The
scope of the Project comprises:
 -
Land formation for key
transport infrastructure and facilities, including the Trunk Road (i.e.
CWB) and the associated slip roads for connection to the Trunk Road and for through
traffic from Central to Wan Chai and Causeway Bay. The land formed for the above
transport infrastructure will provide opportunities for the development of an
attractive waterfront promenade for the enjoyment of the public
 -
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
 -
Extension, modification,
reprovisioning or protection of existing storm water drainage outfalls,
sewerage outfalls and watermains affected by the revised land use and land
formation works mentioned above
 -
Upgrading of hinterland
storm water drainage system and sewerage system, which would be rendered
insufficient by the land formation works mentioned above
 -
Provision of the ground
level roads, flyovers, footbridges, necessary transport facilities and the
associated utility services
 -
Construction of the new
waterfront promenade, landscape works and the associated utility services
 -
The
Trunk Road (i.e. CWB) within the study area and the associated slip roads for
connection to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1 summarises the
five individual DPs under this Project. Figure 2.1
shows the locations of these Schedule 2 DPs.
Table 2.1   Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. 
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits (FEP) such that the impact monitoring
stations are sub-divided accordingly to facilitate the implementation of
EM&A programme and to streamline the EM&A reporting for individual FEP
holders correspondingly.
2.3.2.
In the reporting period, Contract no. HY/2009/11 -
Central  Wanchai Bypass, North Point Reclamation under the Project has been
commenced on 17 March 2010. Two Contracts under the Project has
been commenced in July 2010. The details of individual contracts are summarized
in Table2.2.
Table 2.2  Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II  Central –Wanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
Pending |
||
HK/2009/02 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
Pending |
||
HY/2009/11 |
Wan Chai Development Phase II and Central - Wan Chai Bypass - North
Point Reclamation |
DP3 |
17 March 2010 |
2.4.1.
Civil Engineering and
Development Department and Highways Department are the overall project
controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of
the Project, Project Engineer, Contractor(s), Environmental Team and
Independent Environmental Checker are appointed to manage and control
environmental issues.
2.4.2.
The proposed project organization and lines of communication
with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2607 0838 |
2687 2322 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1800 |
3529 2829 |
|
China Harbour- CRBC Joint Venture |
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo  Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Paul Yu |
9456 9819 |
2634 1626 |
Operation Manager |
Ho Wing Tai |
9306 1356 |
|||
Construction Manager |
David Wong |
9653 8635 |
|||
Construction Manager |
Wilson Lau |
5183 1270 |
|||
Construction Manager |
Alex Tsang |
9194 9383 |
|||
Environmental Officer
(Compliance Manager) |
Ho Wing Tai |
9306 1356 |
|||
Environmental Engineer |
Ken Yang |
9262 6791 |
|||
Chun Wo  CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Anthony Wu |
3658 3004 |
|||
Environmental Officer (Compliance Manager) |
Mr. Barry Leung |
3658 3031 |
|||
Environmental Engineer |
Ms. Flora Ng |
3658-3064 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
During this reporting period, the principle work
activities for Contract no. HY/2009/11 are summarized in Table2.4.
Table 2.4   Principle Work Activities for Contract no.
HY/2009/11
June 2010 |
July 2010 |
August 2010 |
Installation of seawall blocks;
Construction of Caissons at Casting Yard in
Mainland China;
Dredging works; and
Construction of Rock Mound |
Construction of Rock Mound,
Floating Out of Caisson Seawall,
Installation of Caisson Seawall,
Dredging works, and
Laying of geo-textile |
Construction of Rock Mound,
Floating Out of Caisson Seawall,
Installation of Caisson Seawall,
Dredging works,
Filling works;
Laying of geo-textile,
Drainage Works; and
Seawall Block Installation |
2.5.2.
Major marine activities
for Contract no. HK/2009/01 has been commenced on 23 July 2010. The preparation
works and major construction works in the reporting quarter are summarized in Table
2.5.
Table 2.5   Principle Work Activities for Contract no.
HK/2009/01
June 2010 |
July 2010 |
August 2010 |
 -
Erection of interim Engineer’s Principal Office at Works areas WA2;  -
Pre-drilling works and fabrication of staging for trial pile  -
Transportation of materials to the designated pile position by derrick
barges.  -
Decorative panel installation;  -
Re-mobilization of flat top barge to carry out Marine S.I. within
fairway;  -
Marine ground investigation;  -
Fabrication of pipe pile wall staging at the existing promenade piled
deck;  -
Fabrication of special made flat top barge for dredging inside the
HKCEC water channel;  -
Production of pipe pile casing is underway, first batch of 30 nos. x
12 m mill steel pipeline arrived and stored at Yuen Long Yard;  -
Completion of silt screens installation for HKCEC Phase 1, Government
Buildings, China Resources, Great Eagle & Harbour Centre, Telecom House,
Shui On, HKAPA, Sheung Wan & Kowloon South Pumping Station and HKCEC
Extension (Pumping Station P6);  -
Erection of temporary platform for pipe pile installation; and  -
Fabrication of mud barges and crane barge for dredging within HKCEC
water channel |
 -
Erection of interim Engineer’s Principal Office at works area WA2  -
Hoarding erection at Wan Chai HKCEC VIP Drop-off Area and Tsim Sha
Tsui Salisbury Area;  -
The flat top barge is continued to carry out Marine S.I. within
fairway area  -
Marine S.I. at east side of HKCEC;  -
Fabrications of submarine pipelines;  -
Silt screens installation are completed for HKCEC Phase 1, Government
Buildings, China Resoureces, Great Eagle & Harbour Centre, Telecom House,
Shui On, HKAPA, Sheung Wan & Kowloon South Pumping Station and HKCEC
Extension (Pumping Station P6);  -
Routine maintenance and clearance works for silt screens;  -
Erection of temporary platform for pipe pile installation;  -
Fabrication of 3 nos. of mud barges for dredging within HKCEC water
channel and delivered on site. Application of respective license;  -
Fabrication of crane barges are in progress and expect to deliver to site;
and  -
Wheel washing facility will be provided at the north entrance to the
water channel |
 -
Erection of interim Engineer’s Principal Office at Works areas WA2  -
Modification of CATV combine service inspection chamber  -
Installation of staging piles for trial bored pile was completed and
bored pile construction  -
Marine site investigation  -
Dredging works for cross harbour watermains  -
Dismantling of existing sloping seawall and removal of armor rock at
north-west side of water channel is stopped and reinstating the rock slope at
seawall  -
Hoarding erection at Tsim Sha Tsui Salisbury Garden area  -
18m of artwork panel is installed as design for other location  -
Trial pits construction for determination of pipeline alignment at
Convention Avenue  -
Fabrication of straight sections of cross harbour submarine pipes and
land water pipes  -
Elbow sections of cross harbour submarine pipes are being fabricated.  -
Commenced assemble of 6 nos. of tailor made flat top barge. The
fabrication of dredging crane was completed and will be installed on the
tailor make flat top barge and ready for dredging. |
2.5.3.
Major construction activities
for Contract no. HK/2009/02 has been commenced on 5 July 2010. The preparation
works and major construction works in the reporting quarter are summarized in Table
2.6.
Table 2.6   Principle Work Activities for Contract no.
HK/2009/02
June 2010 |
July 2010 |
August 2010 |
Site Clearance;
Hoarding Erection;
Dismantle Existing Footbridge Staircase at Wan Shing
Road;
Pre-drilling Works at WSD Salt Water Pumping
Station;
Construction of Salt Water Intake Culvert at Pet
Garden;
Road Modification Works; and
Construction of
temporary seawall |
Site Clearance;
Hoarding Erection;
Breaking and Excavation at WSD Pumping Station;
Demolition Footbridge Staircase at WSD Pumping
Station;
Construction of Salt Water Intake Culvert at Pet
Garden;
Road Modification Works;
Construction of Cooling Mains Along Public Road;
Construction of Temporary Seawall;
Dredging for WCR 1; and
Equipments Procurement for TKO 137 |
Site Clearance;
Hoarding Erection;
Pre-bored H-piles, ELS
and excavation at WSD Pumping Station;
Construction of Salt
Water Intake Culvert at Pet Garden;
Road Modification Works;
Construction of Cooling
Mains Along Public Road;
Construction of Temporary
Seawall;
Dredging for WCR 1;
Tree Transplanting; and
Equipments Procurement
for TKO 137 |
2.5.4.
Implementation status of the recommended mitigation
measures during this reporting period is presented in Appendix 2.1.
Noise Monitoring Stations
3.1.1.
The noise monitoring stations for the Project are
listed and shown in Table 3.1
and Figure 3.1.  /span>Appendix 3.1 shows the established Action/Limit
Levels for the monitoring works.
Table
3.1  Noise
Monitoring Stations
Station |
Description |
M1a |
Harbour
Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4a |
Causeway
Bay Community Centre |
M5b |
City
Garden |
M6 |
HK Baptist Church Henrietta
Secondary School |
M7e |
International
Finance Centre (Eastern End of Podium) |
M7w |
International
Finance Centre (Western End of Podium) |
Noise Monitoring Parameters, Frequency
and Duration
3.1.2.
The construction noise level shall
be measured in terms of the A-weighted equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700
and 1900 hours on normal weekdays. For all other time periods, Leq (5
minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria. Supplementary information for
data auditing, statistical results such as L10 and L90 shall also be obtained
for reference.
3.1.3.
Noise monitoring shall be carried
out at all the designated monitoring stations. The monitoring frequency shall
depend on the scale of the construction activities. The following is an initial
guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
 -
one set of measurements between 0700 and 1900
hours on normal weekdays.
3.1.4.
If
construction works are extended to include works during the hours of 1900  
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Air Quality Monitoring Stations
3.2.1.
The air monitoring stations for the Project
are listed and shown in Table 3.2 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table 3.2  Air
Monitoring Stations
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North
Point |
CMA2a |
Causeway Bay Community Centre |
Causeway
Bay |
CMA3a |
Future CWB site office at Wanchai
Waterfront Promenade |
Causeway
Bay |
CMA4a |
Society for the Prevention of
Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds opposite to
Pedestrian Plaza |
Wan Chai |
CMA6a |
Future AECOM site office at Work
Area |
Wan Chai |
MA1e |
International
Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International
Finance Centre (Western End of Podium) |
Central |
Air Monitoring Parameters, Frequency and
Duration
3.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
3.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
3.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
3.3.1.
The EIA Report has identified that the key
water quality impact would be associated with the dredging works during the
construction phase. Marine water
quality monitoring for dissolved oxygen (DO), suspended solid (SS) and
turbidity is therefore recommended to be carried out at selected WSD flushing
water intakes. The impact monitoring
should be carried out during the proposed dredging works to ensure the
compliance with the water quality standards.
Water Quality Monitoring Stations
3.3.2.
It is proposed to monitor the water quality
at 9 WSD salt water intakes and 14 cooling water intakes along the seafront of
the Victoria Harbour. The proposed water quality monitoring stations of the
Project are shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table
3.3   Marine
Water Quality Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt
Water Intake |
|||
WSD7 |
Kowloon South |
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
Kennedy Town |
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW1 |
Wan Chai (Reprovision) |
836188.8 |
815911.1 |
Cooling
Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Wan Chai Tower and Great Eagle
Centre (Eastern) |
835932.8 |
815888.2 |
C4w |
Wan Chai Tower and Great Eagle
Centre (Western) |
835629.8 |
815889.2 |
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
C6 |
World Trade Centre |
837009.6 |
815999.3 |
C7 |
Windsor House |
837193.7 |
816150.0 |
C8 |
City Garden |
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
RC1 |
Proposed
HKAPA Extension |
835487.7 |
815987.7 |
RC5 |
Sun Hung
Kai Centre (Reprovision) |
836291.4 |
816029.7 |
RC7 |
Windsor House (Temporary Dilution) |
837245.2 |
816156.6 |
Water Quality Parameters and frequency
3.3.3.
Monitoring of dissolved oxygen (DO),
turbidity and suspended solids (SS) shall be carried out at WSD flushing water
intakes and cooling water intakes. DO and Turbidity are measured in-situ while
SS is determined in laboratory. 
3.3.4.
In association with the water quality
parameters, other relevant data shall also be measured, such as monitoring
location/position, time, sampling depth, water temperature, pH, salinity,
dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal
stage, and any special phenomena and work underway at the construction site
etc.
3.3.5.
The interval between two sets of monitoring
should not be less than 36 hours except where there are exceedances of Action
and/or Limit Levels, in which case the monitoring frequency will be
increased. Table 3.4 shows the
proposed monitoring frequency and water quality parameters. Duplicate in-situ measurements and water
sampling should be carried out in each sampling event. For selection of tides for in-situ
measurement and water sampling, tidal range of individual flood and ebb tides
should be not less than 0.5m.
Table
3.4  Marine
Water Quality Monitoring Frequency and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week baseline
monitoring period |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine
construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
After
completion of marine construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1. For
selection of tides for in-situ measurement and water sampling, tidal range of
individual flood and ebb tides should be not less than 0.5m.
2. Turbidity
should be measured in situ whereas SS should be determined by laboratory.
4.0.1.
The environmental monitoring will be
implemented based on the division of works areas of each designed project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure
2.1 and Figure 3.1. The monitoring results
are presented in according to the Individual Contract(s).
Contract
no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation
4.1.1.
The proposed division of noise monitoring
stations for Contract no. HY/2009/11 are summarized in Table 4.1 below:
Table 4.1
  Noise Monitoring Stations for Contract no.  /span>HY/2009/11
Station |
Description |
M4a |
Causeway Bay Community Centre |
M4b |
Victoria Centre |
M5b |
City Garden |
4.1.2.
Reviewed the past monitoring results and
observation at Station M4a, the monitoring location at Causeway Bay Community
Centre is facing and closed to the Island Eastern Corridor. Traffic noise is
the major noise source obtained in the monitoring that cannot reflect the
construction noise from the construction site. Victoria Centre (Station ID:
M4b) was proposed as alternative noise monitoring station effective from August
2010.
4.1.3.
Two action level exceedances
were recorded due to the noise complaints on 31 July and 12 August 2010. There
were complained on the construction noise nuisance from the dredging work
activities at North Point District. Contractor’s site practical and measurement
results were reviewed. The details of the complaints can be referred to Section
6 and Appendix 6.1.
4.1.4.
Five limit level
exceedances were recorded at M4a on 8 and 22 June 2010 and 20 and 27 July 2010
and at M5b on 16 June 2010 August 2010. All exceedances were investigated and
found not attributed to the project works as major
noise source was obtained from the Island Eastern Corridor. It was
concluded that the exceedances were not due to the project.
4.1.5.
Noise monitoring results measured in this
reporting period are reviewed and summarized. 
Details of graphical presentation can be referred in Appendix 4.1. 
Contract
no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at
HKCEC and Contract no. HK/2009/02 - Wan Chai Development Phase II  Central  
Wan Chai Bypass at WanChai East
4.1.6.
The commencement of marine
construction works for Contract nos. HK/2009/01 and HK/2009/02 have been
commenced in July 2010. The proposed division of noise monitoring stations are
summarized in Table 4.2 below.
Table 4.2
  Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
4.1.7.
Six limit level
exceedances were recorded at station M1a on 13, 20 and 27 July 2010 and 3, 10
and 17 August 2010 during construction works at evening time for Contract no.
HK/2009/02 in reporting quarter. Major noise source was contributed from
Tonnochy Road and water sport competition at Wan Chai Training Swimming Pool. The
dredging work was complied with the conditions under valid Construction Noise
Permit no. GW-RS0132-10 during the measurement.
Contract
no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation
4.2.1.
Since the filling
work of Contract no. HY/2009/11 were commenced in the mid-August 2010, air
monitoring had been commenced on 11 August 2010. The proposed division of air
monitoring stations is summarized in Table 4.3 below.
Table
4.3
  Air
Monitoring Stations for Contract no. HY/2009/11
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
Causeway Bay Community Centre |
4.2.2.
Due to no 24-hour electricity supply in CMA1b
 Oil Street Community Liaison Centre, only 1-hour TSP monitoring can be
conducted in the reporting quater. Details of noise monitoring results and
graphical presentation can be referred in Appendix 4.2.
4.2.3.
One action level exceedance was recorded at
CMA1b on 24 August 2010. Investigation found that the exceedance was not
related to the Project work but due to the burning joss paper activity near the
Oil Street Community Centre between 23 and 25 August 2010 morning.
Contract
no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at
HKCEC
4.2.4.
Air monitoring will be commenced from the
filling work for Contract no. HK/2009/01. The proposed division of air
monitoring stations are summarized in Table 4.4 below.
Table 4.4
  Air
Monitoring Stations
for Contract
no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
CMA6a |
Future AECOM site office at Work Area 1 |
Contract
no. HK/2009/02 - Wan Chai Development Phase II  Central  Wan Chai Bypass at
WanChai East
4.2.5.
Air monitoring will be commenced from the
filling work for Contract no. HK/2009/02. The proposed division of air
monitoring stations are summarized in Table 4.5 below.
Table 4.5
  Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
4.2.6.
No major dust impact is anticipated to be
caused by the site preparation works and dredging works during the reporting
quarter. Air monitoring will be commenced from the filling works for Contract
no. HK/2009/01 and HK/2009/02. Therefore, no air monitoring was conducted in
the reporting period.
Contract
no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation
4.3.1.
The proposed division of water monitoring
stations for Contract no. HY/2009/11 are summarized in Table 4.6 below:
Table 4.6  Water Monitoring Stations for Contract no.  /span>HY/2009/11
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
Cooling Water Intake |
|||
C8 |
City Garden |
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
Contract
no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai Bypass at
HKCEC
4.3.2.
Water monitoring stations for Contract
no. HK/2009/01 were commenced on 8 July 2010. The proposed division of water
monitoring stations are summarized in Table 4.7 below.
Table 4.7
  Water Monitoring Stations for Contract no. HK/2009/01
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
Kowloon South |
834150.0 |
818300.3 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
Kennedy Town |
830750.6 |
816030.3 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Wan Chai Tower and Great
Eagle Centre (Eastern) |
835932.8 |
815888.2 |
C4w |
Wan Chai Tower and Great
Eagle Centre (Western) |
835629.8 |
815889.2 |
Contract
no. HK/2009/02 - Wan Chai Development Wan Chai Development Phase II  Central  
Wan Chai Bypass at WanChai East
4.3.3.
Water monitoring for Contract no. HK/2009/02
was commenced on 8 July 2010. The proposed division of water monitoring
stations are summarized in Table 4.8 below.
Table 4.8
  Water Monitoring Stations for Contract no. HK/2009/02
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
Cooling Water Intake |
|||
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
4.3.4.
Water quality monitoring
at the stations for Contract nos. HK/2009/01 and HK/2009/02 were commenced on 8
July 2010. Water quality monitoring was conducted at total 17 monitoring
stations namely WSD7, WSD9, WSD10, WSD15, WSD17, WSD19, WSD20, WSD 21, C1, C2,
C3, C4e, C4w, C5e, C5w, C8 and C9 during the reporting period.
4.3.5.
The access to WSD7 is needed to via the gates
that are locked and under the control of LCSD between 1800hrs and 0800hrs from
10 July 2010. Due to no access permission obtained from LCSD in this reporting
quarter, water monitoring cannot be conducted at WSD7 on 10 July 2010 at mid-flood,
14 July 2010 at mid-flood and mid-ebb, 18 July 2010 at mid-flood and 19 July
2010 at mid-ebb. The approval of access permission had been obtained from LCSD
for the access to WSD7 in Mid-August 2010. However, due to the wrong locking
order of the series pad locks at the gate, water quality monitoring could not
be conducted on 30 July 2010, 18 and 25 August 2010.
4.3.6.
The construction and maintenance works of the
silt screen cover at C4e and C4w was conducted by Chun Wo & Leader JV on 14
July 2010, no water monitoring was conducted at these stations during the
mid-ebb.
4.3.7.
Concerning the safety
works and the unrepresentative water quality being substantially affected by
urban runoff under adverse weather, the following water quality monitoring were
cancelled:
-
28 June 2010 at mid-ebb for all stations; 28
July 2010 at mid-ebb tide for C1 to C4 due to amber rainstorm warning in force;
-
5 August 2010 at mid-flood for all stations
due to red rainstorm warning in force;
-
28 July 2010 at mid-flood for all stations
due to black rainstorm warning in force;
-
21 July 2010 at mid-flood for all stations
due to Strong Wind Signal No. 3 announced.
4.3.8.
Water monitoring results measured in this
reporting period are reviewed and summarized in Table 4.9. Details of water quality monitoring results
and graphical presentation can be referred in Appendix 4.3.
Table 4.9
  Summary of Water Quality Monitoring Exceedances in Reporting Quarter
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
HY/2009/11 |
WSD9 |
2 |
2 |
0 |
0 |
0 |
1 |
2 |
4 |
0 |
0 |
0 |
1 |
|
WSD10 |
3 |
3 |
0 |
0 |
3 |
2 |
2 |
7 |
0 |
0 |
1 |
0 |
|
WSD15 |
3 |
4 |
0 |
0 |
1 |
3 |
4 |
8 |
0 |
0 |
1 |
0 |
|
WSD17 |
3 |
3 |
0 |
0 |
0 |
1 |
4 |
10 |
1 |
0 |
0 |
3 |
|
C8 |
5 |
2 |
2 |
0 |
7 |
2 |
3 |
2 |
0 |
4 |
7 |
4 |
|
C9 |
4 |
1 |
0 |
1 |
8 |
1 |
6 |
0 |
2 |
1 |
6 |
3 |
HK/2009/01 |
WSD19 |
1 |
1 |
1 |
0 |
0 |
2 |
2 |
3 |
0 |
0 |
0 |
0 |
|
WSD20 |
1 |
1 |
0 |
0 |
0 |
2 |
2 |
2 |
0 |
0 |
1 |
2 |
|
WSD7 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
4 |
0 |
0 |
0 |
0 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C2 |
1 |
1 |
0 |
0 |
1 |
0 |
3 |
0 |
0 |
0 |
0 |
1 |
|
C3 |
1 |
0 |
0 |
0 |
1 |
0 |
3 |
0 |
0 |
0 |
1 |
1 |
|
C4e |
1 |
0 |
0 |
0 |
1 |
0 |
4 |
0 |
0 |
0 |
0 |
0 |
|
C4w |
1 |
0 |
0 |
0 |
0 |
0 |
2 |
0 |
0 |
0 |
1 |
0 |
HK/2009/02 |
C5e |
1 |
0 |
0 |
0 |
2 |
1 |
2 |
0 |
0 |
0 |
1 |
0 |
|
C5w |
1 |
1 |
0 |
0 |
2 |
1 |
0 |
0 |
0 |
0 |
1 |
0 |
|
WSD21 |
0 |
1 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
1 |
Total |
28 |
21 |
3 |
1 |
26 |
17 |
40 |
43 |
3 |
5 |
20 |
16 |
4.3.9.
The exceedances have been investigated and were considered unlikely to
be related to project works. Water
monitoring results measured in this reporting period are reviewed and
summarized. Details of graphical
presentation can be referred in Appendix 4.2.
Contract
no. HY/2009/11  Central  Wanchai Bypass, North Point Reclamation
4.4.1.
No inert and non-inert
C&D waste was disposed in this reporting period. Details of the waste flow table are summarized in Table
4.10
Table 4.10 Details
of Waste Disposal for Contract no. HY/2009/11
Waste
Type |
Quantity this quarter, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Marine Sediment (Type 1  Open Sea Disposal) |
 /span>35,500 (Bulk Volume) |
71,500 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) |
35,000 (Bulk Volume) |
81,000 (Bulk Volume) |
East of Sha Chau |
4.4.2.
There were marine sediments Type 1  Open Sea
Disposal and Type 1  Open Sea Disposal (Dedicate Sites) & Type 2  
Confined Marine Disposal marine sediment disposed in the reporting period. The
maximum dredging rate in North Point Shoreline Zone is 3,000m3 per
day in the reporting quarter, which is complied with the criteria listed in
Table 5.10 of EIA Report Register No. AEIAR-125/2008.
Contract no. HK/2009/01 - Wan Chai Development Phase II  Central –Wanchai
Bypass at HKCEC
4.4.3.
Inert and non-inert
C&D waste was disposed of for the site preparation works in this reporting
period. Details of the waste flow table are summarized in Table 4.11.
Table 4.11 Details
of Waste Disposal for Contract no. HK/2009/01
Waste
Type |
Quantity this quarter, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
201.54 |
201.54 |
TKO134 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
        33.91 |
43.68 |
SENT Landfill |
Non-inert C&D materials recycled |
2.89 |
2.89 |
N/A |
Chemical waste disposed |
0.29 |
0.29 |
N/A |
Marine Sediment (Type 1  Open Sea Disposal) |
23,987 (Bulk Volume) |
23,987 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) |
NIL |
NIL |
N/A |
4.4.4.
There were marine sediments Type 1  Open Sea
Disposal disposed in the reporting period. The maximum dredging rate in Cross
Harbour Water Main is 845m3 per day in the reporting quarter, which
is complied with the criteria listed in Table 5.10 of EIA Report Register No. AEIAR-125/2008.
Contract no. HK/2009/02 - Wan Chai Development Phase II  Central  Wan
Chai Bypass at WanChai East
4.4.5.
Inert and non-inert
C&D waste was disposed of for the site preparation works in this reporting
period. Details of the waste flow table are summarized in Table 4.12.
Table 4.12 Details
of Waste Disposal for Contract no. HK/2009/02
Waste
Type |
Quantity this quarter, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
1550.5 |
1550.5 |
TKO137 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
5.5 |
27.5 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Marine Sediment (Type 1  Open Sea Disposal) |
NIL |
NIL |
N/A |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) |
51210 (Bulk Volume) |
51210 (Bulk Volume) |
East of Sha Chau |
4.4.6.
There was marine sediment (Type 1  Open Sea Disposal (Dedicate Sites) &
Type 2  Confined Marine Disposal) disposed in reporting
quarter at a maximum dredging rate 1,590m3 per day. On-going ET site
inspections observed that the temporary western seawall has been partially
constructed since early August 2010 with no apparent water quality impact
reported for the stations WSD21, C5e and C5w, it is considered the maximum
dredging rate at WCR can be stepped up to 6,000m3 as per the
criteria under Table 5.10 of EIA Report Register No. AEIAR-125/2008 for
dredging with WCR area.
5.0.1.
The Event Action Plan for construction noise,
air quality and water quality are presented in Appendix 5.1.
5.1.1.
Two action level exceedances
were recorded due to the noise complaints on 31 July and 12 August 2010. There
were complained on the construction noise nuisance from the dredging work
activities at North Point District. Contractor’s site practical and noise
monitoring results were reviewed. Investigation found that the complaints were
considered not valid from the Environmental Permit and Construction Noise
Permit point of view. The details of the complaints can be referred to Section
6 and Appendix 5.1.
5.1.2.
Eleven limit level
exceedances were recorded in the reporting quarter. All exceedances
were investigated and found not attributed to the project works as major noise source was obtained from the traffic
noise. Besides, crowd noise from the Wan Chai Training Pool was also
contributed during evening noise monitoring at M1a  Harbour Road Sports Centre. It was concluded that the exceedances were not due
to the project.
5.2.1.
One action level exceedance was recorded at
CMA1b on 24 August 2010. Investigation found that the exceedance was due to the
burning joss paper activities near CMA1b.
5.3.1.
The summary of water quality exceedances
recorded in reporting quarter is presented in the Table 5.1.
Table 5.1  Summary of Water Quality Exceedances in the
reporting Quarter
Contract
no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
HY/2009/11 |
WSD9 |
2 |
2 |
0 |
0 |
0 |
1 |
2 |
4 |
0 |
0 |
0 |
1 |
|
WSD10 |
3 |
3 |
0 |
0 |
3 |
2 |
2 |
7 |
0 |
0 |
1 |
0 |
|
WSD15 |
3 |
4 |
0 |
0 |
1 |
3 |
4 |
8 |
0 |
0 |
1 |
0 |
|
WSD17 |
3 |
3 |
0 |
0 |
0 |
1 |
4 |
10 |
1 |
0 |
0 |
3 |
|
C8 |
5 |
2 |
2 |
0 |
7 |
2 |
3 |
2 |
0 |
4 |
7 |
4 |
|
C9 |
4 |
1 |
0 |
1 |
8 |
1 |
6 |
0 |
2 |
1 |
6 |
3 |
HK/2009/01 |
WSD19 |
1 |
1 |
1 |
0 |
0 |
2 |
2 |
3 |
0 |
0 |
0 |
0 |
|
WSD20 |
1 |
1 |
0 |
0 |
0 |
2 |
2 |
2 |
0 |
0 |
1 |
2 |
|
WSD7 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
4 |
0 |
0 |
0 |
0 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C2 |
1 |
1 |
0 |
0 |
1 |
0 |
3 |
0 |
0 |
0 |
0 |
1 |
|
C3 |
1 |
0 |
0 |
0 |
1 |
0 |
3 |
0 |
0 |
0 |
1 |
1 |
|
C4e |
1 |
0 |
0 |
0 |
1 |
0 |
4 |
0 |
0 |
0 |
0 |
0 |
|
C4w |
1 |
0 |
0 |
0 |
0 |
0 |
2 |
0 |
0 |
0 |
1 |
0 |
HK/2009/02 |
C5e |
1 |
0 |
0 |
0 |
2 |
1 |
2 |
0 |
0 |
0 |
1 |
0 |
|
C5w |
1 |
1 |
0 |
0 |
2 |
1 |
0 |
0 |
0 |
0 |
1 |
0 |
|
WSD21 |
0 |
1 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
1 |
Total |
28 |
21 |
3 |
1 |
26 |
17 |
40 |
43 |
3
|
5 |
20 |
16 |
5.3.2.
Since all exceedances recorded were not
project-related, follow-up mitigation measures were therefore not required.
5.4.1
Existing Action and
Limit Levels were derived based on the 4-weeks baseline water quality monitoring
data obtained during the dry season in October and November 2009 prior to the
commencement of construction. The Action
and Limit Levels are applied the water monitoring for all seasons.
5.4.2
Owing to the frequent
non-project related exceedances caused by fluctuation in coastal water quality
due to localized effect, it is considered the existing Action and Limit Levels
values were underestimated to the natural variation of water quality around the
baseline range.  It is recommended to
review the existing Action and Limit Levels on water quality in order to take
into the account of the coastal activities and potential variation of coastal
water qualities during wet season (i.e. Apr  Sep period). Action and Limit
levels for wet season were devised based on a projected scenario calculated
using the marine water quality data obtained at the closest EPD routine
monitoring stations as per EM&A Manual Section 4.10.4 which states,
“Where necessary, EPD routine water quality monitoring data at the relevant station(s), dry and wet seasons inclusive, could also be used to established the baseline water quality. o:p>
5.4.3
While the existing
Action and Limit levels will continue to be used for impact monitoring for dry
season (Oct  Mar period), an additional set of Action and Limit levels are
proposed for use in the coming wet season and are summarized in Table
5.2. The details of calculation
using the marine water quality data obtained at the closest EPD routine
monitoring stations can be referred to Appendix 5.2.
Table 5.2  Proposed
Action and Limit Levels for Water Quality Monitoring
|
Dry
Season (Existing AL & LL) |
Wet
Season |
||
Parameters |
Action |
Limit |
Action |
Limit |
WSD Salt Water Intakes |
|
|
|
|
SS in mg/L |
13.00 |
14.43 |
16.26 |
19.74 |
Turbidity in NTU |
8.04 |
9.49 |
10.01 |
11.54 |
DO in mg/L |
3.66 |
3.28 |
3.17 |
2.63 |
Cooling Water Intakes |
|
|
|
|
SS in mg/L |
15.00 |
22.13 |
18.42 |
27.54 |
Turbidity in NTU |
9.10 |
10.25 |
11.35 |
12.71 |
DO in mg/L |
3.36 |
2.73 |
3.02 |
2.44 |
5.5.1.
There was no non-compliance from the site
audits in the reporting period. During environmental site inspections conducted
during the reporting quarter, minor deficiencies were noted. However, the Contractor rectified all
deficiencies after receipt of notification.
5.6.1.
No project-related non-compliance from
monitoring was recorded in the reporting period.
5.7.1.
There was no particular action taken since no project-related
non-compliance was recorded from the site audits and environmental monitoring
in the reporting period.
6.0.1.
Two noise complaints were
recorded on 31 July and 12 August 2010 regarding noise nuisance from the dredging
works in North Point district. Investigation found that the complaints were
considered not valid from the Environmental Permit and Construction Noise
Permit point of view. 
The details of cumulative complaint log and summary of complaints are
presented in Appendix 6.1.
6.0.2.
No notification
of summons or prosecution was received in the reporting period. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
6.1 and Table 6.2 respectively.
Table 6.1  Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Jun - Aug 2010 |
2 |
Project-to-Date |
5 |
Table 6.2  Cumulative Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1.
According to Condition 3.4 of the EP-356/2009, this
section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation,
Central-WanChai Bypass and Island Eastern Corridor Link projects.
7.0.2.
According to the construction programme of Central-Wan
Chai Bypass and Island Eastern Corridor Link projects, the major construction activity
under Wan Chai Development Phase II was the dredging works at North Point Reclamation
Stage 1(NPR1), Wan Chai Reclamation Stage 1(WCR1) and Cross Harbour Water Mains
in the reporting quater. The major environmental impact was water quality
impact at North Point and Wan Chai. No major construction activities were
undertaken in the Central-Wan Chai Bypass and Island Eastern Corridor Link
projects.
7.0.3.
The major environmental impacts generated from
the Central Reclamation Phase III were located along the coastline of Central
and Admiralty while dredging works at NPR1, WCR1 and Cross Harbour Water Mains were
in operation in this reporting quarter. The dredging works was just commenced
at WCR1 and Cross Harbour Water Mains in this reporting quarter.  /span>Beside, water quality mitigation measures
were properly in place for the dredging works in this reporting quarter. No
project related exceedance was recorded. Thus, it is evaluated that the cumulative
construction impact from the concurrent projects including Wan Chai Development
Phase II and Central Reclamation Phase III was insignificant.
8.0.1.
The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
8.0.2.
No project-related exceedance,
non-compliances were noted and no prosecutions were received during the
reporting quarter.
8.0.3.
Owing to the frequent non-project related
exceedances caused by fluctuation in coastal water quality due to localized
effect, it is considered the existing Action and Limit Levels values were
underestimated to the natural variation of water quality around the baseline
range.  It is recommended to review
the existing Action and Limit Levels on water quality in order to take into the
account of the coastal activities and potential variation of coastal water
qualities during wet season (i.e. Apr  Sep period). While the existing Action and Limit levels will continue to be used for impact monitoring for
dry season (Oct  Mar period), an additional set of Action and Limit
levels are proposed for use in the coming wet season.
8.0.4.
The construction programmes of individual contracts
are provided in Appendix 8.1.