Contract No: HK/2009/05

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 1)

 

Environmental Permit no. EP-364/2009/A,

Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A and FEp-06/364/2009/a

 

Quarterly Environmental Monitoring
and Audit Report

 

- september to november 2010 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

CHECKED by:



 

 

 

 

 

                        

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

17 December 2010


Table of contents

 

1.   Introduction.. 1

1.1    Scope of the Report 1

1.2    Structure of the Report 1

2.   Project Background.. 2

2.1    Background. 2

2.2    Scope of the Project and Site Description. 2

2.3    Division of the Project Responsibility. 3

2.4    Project Organization and Contact Personnel 4

2.5    Principle Work and Activities. 6

3.   Monitoring Requirements. 8

3.1.    Noise Monitoring. 8

3.2.    Air Monitoring. 9

4.   Monitoring Results. 12

4.1.    Noise Monitoring Results. 12

4.2.    Real Time Noise Monitoring Results. 13

4.3.    Air Monitoring Results. 14

4.4.    Waste Monitoring Results. 15

5.   Compliance Audit.. 19

5.1.    Noise Monitoring. 19

5.2.    Air Monitoring. 19

5.3.    Site Audit 20

5.4.    Review of the Reasons for and the Implications of Non-compliance. 20

5.5.    Summary of action taken in the event of and follow-up on non-compliance. 20

6.   Complaints, Notification of Summons and Prosecution.. 21

7.   Cumulative Construction Impact due to the Concurrent Projects. 22

8.   Conclusion.. 23


lIST OF TABLES

 

Table I    Principle Work Activities for Contract no. HY/2009/17

Table II     Principle Work Activities for Contract no. 04/HY/2006

Table III     Principle Work Activities for Contract no. HY/2009/18

Table 2.1    Schedule 2 Designated Projects under this Project

Table 2.2   Details of Individual Contracts under the Project

Table 2.3   Contact Details of Key Personnel

Table 2.4    Principle Work Activities for Contract no. HY/2009/17

Table 2.5    Principle Work Activities for Contract no. 04/HY/2006

Table 2.6    Principle Work Activities for Contract no. HY/2009/18

Table 3.1   Noise Monitoring Station

Table 3.2   Real Time Noise Monitoring Station

Table 3.2   Air Monitoring Stations

Table 4.1    Noise Monitoring Stations for Contract no.  HY/2009/17

Table 4.2    Noise Monitoring Station for Contract nos. 04/HY/2006 and HY/2009/18

Table 4.3    Air Monitoring Stations for Contract nos. HK/2009/01 and HK/2009/02

Table 4.4    Noise Monitoring Station for Contract nos. HY/2009/15

Table 4.5   Real Time Noise Monitoring Station for Contract no. HY/2009/17

Table 4.6    Air Monitoring Stations for Contract no. HY/2009/17

Table 4.7    Air Monitoring Stations for Contract no. 04/HY/2006 and HY/2009/18

Table 4.8    Air Monitoring Stations for Contract no. HK/2009/01

Table 4.9    Air Monitoring Station for Contract no. HK/2009/02

Table 4.10   Air Monitoring Station for Contract no. HY/2009/15

Table 4.11  Details of Waste Disposal for Contract no. HY/2009/17

Table 4.12  Details of Waste Disposal for Contract no. 04/HY/2006

Table 4.13  Details of Waste Disposal for Contract no. HK/2009/01

Table 4.14  Details of Waste Disposal for Contract no. HK/2009/02

Table 4.15  Details of Waste Disposal for Contract no. HY/2009/18

Table 4.16  Details of Waste Disposal for Contract no. HY/2009/15

Table 6.1   Cumulative Statistics on Complaints

Table 6.2   Cumulative Statistics on Successful Prosecutions

 

lIST OF FIGUREs

 

Figure 2.1     Project Layout

Figure 2.2     Project Organization Chart

Figure 3.1      Locations of Environmental Monitoring Stations

 

lIST OF APPENDIces

 

Appendix 2.1   Environmental Mitigation Implementation Schedule

Appendix 3.1   Action and Limit Level

Appendix 4.1   Noise Monitoring Results and Graphical Presentations

Appendix 4.2   Real-time Noise Monitoring Results and Graphical Presentations

Appendix 4.3   Air Quality Monitoring Results and Graphical Presentations

Appendix 5.1   Event Action Plans

Appendix 6.1   Complaint Log

Appendix 8.1   Construction Programme of Individual Contracts

 

 

 

 

 

 

 

 

 

 

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Quarterly Report specific for Environmental Permit no. EP-364/2009/A, Further Environmental Permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-03-364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A and FEP-06/364/2009/A. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HK/2009/05 –Wanchai Development Phase II and Central Wanchai Bypass. This report presents the environmental monitoring and audit findings and information during the period from 28th September 2010 to 27th November 2010. The cut-off date of reporting is at 27th of each reporting quarter.

 

  1. In the reporting period, the principal work activities of individual contracts are included as follows:

 

Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

 

Major construction activities for Contract no. HK/2009/17 have been commenced on 5 October 2010. During this reporting period, the principle work activities for Contract no. HY/2009/17 are summarized as below:

Table I     Principle Work Activities for Contract no. HY/2009/17

September 2010

October 2010

November 2010

Ÿ             Only preparation works was commenced.

Ÿ             Mobilization and plant setup for site preparation work.

Ÿ             Piling Works.

Ÿ             Piling Works.

 

Contract no. 04/HY/2006  /span> Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

 

Major construction activities for Contract no. 04/HY/2006 have been conducted on September 2010. During this reporting period, the preparation works and principle work activities for it are summarized as below:

Table II    Principle Work Activities for Contract no. 04/HY/2006

September 2010

October 2010

November 2010

Ÿ             Modification of bus bays at the bus terminus;

Ÿ             Widening of carriageway at the bus terminus; and

Ÿ             Relocation of existing lay-bay at Man Kwong Street

Ÿ             Modification of bus bays at the bus terminus; and

Ÿ             Relocation of existing lay-bay at Man Kwong Street

 

Ÿ             Modification of bus bays at the bus terminus

 

 

 

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A

 

The major construction activities for Contract no. HY/2009/18 anticipated commencing by early January 2011. The preparation works for it in this reporting periods included:

Table III    Principle Work Activities for Contract no. HY/2009/18

September 2010

October 2010

November 2010

Ÿ             No major construction activity was undertaken in reporting period.

Ÿ             Only preparation works was commenced.

Ÿ             Site preparation of Community Liaison Centre (CLC) and Engineer’s sub office;

Ÿ             Installation of trial pits for utilities identification; and

Ÿ             Tree survey

Ÿ             Only preparation works was commenced.

Ÿ              /span>Refurbishment of existing site office next to Star Ferry Central Pier;

Ÿ             Initial record survey; and

Ÿ             Condition survey

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

 -           No major construction activity was undertaken in reporting period.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

 -           No major construction activity was undertaken in reporting period.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

 -           No major construction activity was undertaken in reporting period.

 

Noise Monitoring

  1. Noise monitoring during daytime was commenced on 30 August 2010 at the International Finance Centre (eastern and western podium) on a weekly basis. No action and limit exceedances were recorded in the reporting period.

 

  1. Noise monitoring during daytime was commenced on 5 October 2010 at Victoria Center on a weekly basis. No action and limit exceedances were recorded in the reporting period.

 

  1. 24-hour real time noise monitoring was commenced at FEHD Hong Kong Transport Section Whitefield Depot by 5 October 2010 for the pilling works in FEHD Whitfield Depot. No action and limit level exceedances were recorded in the reporting period during normal hour monitoring. In contrast, exceedances were recorded through out in October and scrappy in November during restricted hour and nighttime monitoring. The details of exceedances can be referred to section 4.1.

 

Air Quality Monitoring

  1. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring was commenced on 9 September 2010 at International Finance Centre (eastern and western podium) on every six days basis. No action and limit level exceedance were recorded in the reporting period.

 

  1. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring was commenced 8 October 2010 at Causeway Bay Community Center on every six days basis. No action and limit level exceedance were recorded in the reporting period.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. No complaint was recorded in the reporting period.

 

 

 


1.     Introduction

1.1               Scope of the Report

1.1.1.        Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A and FEP-06/364/2009/A to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.        This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and  /span>Environmental Monitoring and Audit Requirements  under Particular Specification Section 27.

1.1.3.        This report documents the finding of EM&A works during the period from 28th September 2010 to 27th November 2010.

1.2               Structure of the Report

 

Section 1     Introduction  details the scope and structure of the report.

 

Section 2     Project Background  summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3     Monitoring Requirements   summarizes all monitoring parameters, monitoring locations, monitoring frequency, duration and action plan.

 

Section 4     Monitoring Results  summarizes the monitoring results obtained in the reporting period.

 

Section 5     Compliance Audit  summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 6     Complaints, Notification of summons and Prosecution  summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 7     Cumulative Construction Impact due to the Concurrent Projects  summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8     Conclusion

2.     Project Background

2.1               Background

2.1.1.        “Wan Chai Development phase II and Central-Wan Chai Bypass and “Central-Wan Chai Bypass and Island Eastern Corridor Link  (hereafter called “the Project  are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.        The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.        There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2               Scope of the Project and Site Description

2.2.1.        Design and Construction of Central  Wan Chai Bypass and Island Eastern Corridor Link under the Project involves the construction and operation of a trunk road and its road tunnel more than 800m in length between portals that is shown at Figure 2.1.

2.2.2.         The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:

 -           A dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);

 -           The Central Interchange near the Rumsey Street Flyover to provide road connections to the Central area;

 -           Tunnel control buildings and ventilation buildings;

 -           Slip roads to connect the CWB to the local road system in the Wan Chai North and Causeway Bay area;

 -           Associated road lighting, road signing, traffic control and surveillance system; and

 -           Other associated works.

 

2.2.3.        The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1   Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3               Division of the Project Responsibility

2.3.1.        Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.        In the reporting period, Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under Contract no. 04/HY/2006 was commenced on September 2010 and advance piling work at FEHD Whitfield Depot under Contract no. HY/2009/17 was commenced on 5 October 2010. The details of individual contracts are summarized in Table2.2.

Table 2.2  Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HY/2009/17

Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works.

DP1

5 October 2010

HY/2009/18

Central - Wan Chai Bypass (CWB)  Central Interchange

DP1

Anticipated to be commenced in January 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

HK/2009/01

Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works

DP1, DP2

Pending

HK/2009/02

Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East(CWB Tunnel) (CWB Tunnel)

DP1

Pending

HY/2009/15

Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section)

DP1

Pending

 

 

2.4               Project Organization and Contact Personnel

2.4.1.        Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.        The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3  Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer for WDII

Principle Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer for CWB

Principle Resident Engineer

Mr. Peter Poon

3916 1818

3529 2829

Lam Woo & CO., LTD.

Contractor under Contract no. HY/2009/17

Project Manager

Mr. K. S. Law

9090 1378

2566 7522

Construction Manager / Sub Agent

Mr. Joe Tsang

9725-5874

Site Agent

Mr. Daniel Chan

9372 0495

Environmental Officer

Mr. Andy Mak

6461 3065

Chiu Hing Construction & Transportation Co. Ltd.

Contractor under Contract no. 04/HY/2006

Contract Manager

Mr. Frederick Tsui

2967 6363

2967 6366

Senior Site Agent

Mr. Alvin Ma

2967 6363

2967 6366

Environmental Consultant

Mr. Jimmy Cheng

2965 0898

2556 9172

Chun Wo   Leader Joint Venture

Contractor under Contract no. HK/2009/01

Site Agent

Mr. Paul Yu

9456 9819

2634 1626

Operation Manager

Mr. Ho Wing Tai

9306 1356

Construction Manager

Mr. David Wong

9653 8635

Construction Manager

Mr. Wilson Lau

5183 1270

Construction Manager

Mr. Alex Tsang

9194 9383

Environmental Officer (Compliance Manager)

Mr.Ho Wing Tai

9306 1356

Environmental Engineer

Mr. Ken Yang

9262 6791

Chun Wo   CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Project Manager

Mr. Chan Sing Cho

3658 3002

2827 9996

Site Agent

Mr. Eric Lam

3658-3048

Deputy Site Agent

Mr. Anthony Wu

3658-3004

Environmental Officer (Compliance Manager)

Mr. Barry Leung

3658 3031

Environmental Engineer

Ms. Flora Ng

3658-3064

Leighton Contractors (Asia) Limited

Contractor under Contract no. HY/2009/18

Site Agent

Mr. Brian Gillon

2214 7700

2140 6799

Deputy Site Agent

Mr. Desmond Sze

2214 7703

Quality & Env. Manager

Mr. Stephen Moc

2214 7720

Environmental Officer

Mr. Anfernee Chow

2214 7721

Environmental Supervisor

Mr. Kelven Yip

2214 7722

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Manager

Mr. M Y Wong

2823 7879

2566 2192

Site Agent

Mr. Leung Kwok Yiu

9026 8808

Head of construction

Mr. Simon Tang

9022 6060

Construction Manager

Mr. C K Kwok

9779 2162

Assistant Construction Manager (East)

Mr. Gene Cheung

6105 4880

Assistant Construction Manager (West)

Mr. Tony Chiu

9090 0606

Section Agent (East)

Mr. Jason Chan

9254 1635

Section Agent (West)

Mr. Tang Ka Tung

9473 4771

Environmental Manager

Ms. Anna Yu

9473 1945

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3743 0788

3548 6988

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

2.5               Principle Work and Activities

2.5.1.        Major construction activities for Contract no. HK/2009/17 have been commenced on 5 October 2010. During this reporting period, the principle work activities for Contract no. HY/2009/17 are summarized in Table2.4.

Table 2.4   Principle Work Activities for Contract no. HY/2009/17

September 2010

October 2010

November 2010

Ÿ             Only preparation works was commenced.

Ÿ             Mobilization and plant setup for site preparation work.

Ÿ             Piling Works.

Ÿ             Piling Works.

 

2.5.2.        Major construction activities for Contract no. 04/HY/2006 have been commenced on September 2010. The major construction works in the reporting quarter are summarized in Table 2.5.

Table 2.5   Principle Work Activities for Contract no. 04/HY/2006

September 2010

October 2010

November 2010

Ÿ             Modification of bus bays at the bus terminus;

Ÿ             Widening of carriageway at the bus terminus; and

Ÿ             Relocation of existing lay-bay at Man Kwong Street

Ÿ             Modification of bus bays at the bus terminus; and

Ÿ             Relocation of existing lay-bay at Man Kwong Street

 

Ÿ             Modification of bus bays at the bus terminus

 

2.5.3.        The major construction activities for Contract no. HY/2009/18 anticipated commencing by early January 2011. The preparation works in the reporting quarter are summarized in Table 2.6.

Table 2.6   Principle Work Activities for Contract no. HY/2009/18

September 2010

October 2010

November 2010

Ÿ             No major construction activity was undertaken in reporting period.

Ÿ             Only preparation works was commenced.

Ÿ             Site preparation of Community Liaison Centre (CLC) and Engineer’s sub office;

Ÿ             Installation of trial pits for utilities identification; and

Ÿ             Tree survey

Ÿ             Only preparation works was commenced.

Ÿ              /span>Refurbishment of existing site office next to Star Ferry Central Pier;

Ÿ             Initial record survey; and

Ÿ             Condition survey

 

2.5.4.        Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

 -           No major construction activity is anticipated in coming reporting period.

 

2.5.5.        Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

 -           No major construction activity is anticipated in coming reporting period.

 

2.5.6.        Contract no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

 -           No major construction activity was undertaken in reporting period.

2.5.7.        Implementation status of the recommended mitigation measures during this reporting period is presented in Appendix 2.1.

 

3.     Monitoring Requirements

3.1.               Noise Monitoring

Noise Monitoring Stations

3.1.1.        The noise monitoring stations for the Project are listed and shown in Table 3.1 and Figure 3.1.  /span>Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.1  Noise Monitoring Station

Station

Description

M1a

Harbour Road Sports Centre

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

 

Real time Noise Monitoring Stations

3.1.2.        The noise monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.2  Real Time Noise Monitoring Station

District

Station

Description

Tin Hau

RTN1

FEHD Hong Kong Transport Section Whitefield Depot

North Point

RTN2

Oil Street Community Liaison Centre

 

Noise Monitoring Parameters, Frequency and Duration

3.1.3.        The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

3.1.4.        Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

 -           One set of measurements between 0700 and 1900 hours on normal weekdays.

3.1.5.        Real time noise shall be carried out at the designated monitoring stations. The following is an initial guide on the regular monitoring frequency for each station on a 24 hours daily basis when noise generating activities are underway:

 -           One set of measurements between 0700 and 1900 hours on normal weekdays.

 -           One set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.

 -           One set of measurements between 2300 and 0700 hours on next day on everyday.

3.1.6.        If construction works are extended to include works during the hours of 1900  0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

Monitoring Equipment

3.1.7.        As referred to in the Technical Memorandum   issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

3.1.8.        Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

3.1.9.        The sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency before deployment to the site and during each site visit. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

3.2.                        Air Monitoring

Air Quality Monitoring Stations

3.2.1.        The air monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.2  Air Monitoring Stations

Station ID

Monitoring Location

Description

CMA1b

Oil Street Community Liaison Centre

North Point

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

Future CWB site office at Wanchai Waterfront Promenade

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5a

Children Playgrounds opposite to Pedestrian Plaza

Wan Chai

CMA6a

Future AECOM site office at Work Area

Wan Chai

MA1e

International Finance Centre (Eastern End of Podium)

Central

MA1w

International Finance Centre (Western End of Podium)

Central

 

Air Monitoring Parameters, Frequency and Duration

3.2.2.        One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

3.2.3.        All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

3.2.4.        For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.

Sampling Procedure and Monitoring Equipment

3.2.5.        High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

 -           0.6 - 1.7 m3 per minute adjustable flow range;

 -           Equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

 -           Installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

 -           Capable of providing a minimum exposed area of 406 cm2;

 -           Flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

 -           Equipped with a shelter to protect the filter and sampler;

 -           Incorporated with an electronic mass flow rate controller or other equivalent devices;

 -           Equipped with a flow recorder for continuous monitoring;

 -           Provided with a peaked roof inlet;

 -           Incorporated with a manometer;

 -           Able to hold and seal the filter paper to the sampler housing at horizontal position;

 -           Easily changeable filter; and

 -           Capable of operating continuously for a 24-hour period.

 

3.2.6.        Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

3.2.7.        Laboratory Measurement / Analysis

3.2.8.        A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

3.2.9.        Filter paper of size 8" x 10" shall be labeled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

3.2.10.    After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

3.2.11.    All the collected samples shall be kept in a good condition for 6 months before disposal.

 

 

4.     Monitoring Results

4.0.1.        The environmental monitoring will be implemented based on the division of works areas of each designed project managed under different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 3.1. The monitoring results are presented in according to the Individual Contract(s).

4.0.2.        In the reporting period, the concurrent contracts are as follows:

Ÿ         Contract no. 04/HY/2006 –Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A.

Ÿ         Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

   4.1.          Noise Monitoring Results

Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

4.1.1.        The proposed division of noise monitoring stations for Contract no. HY/2009/17 is summarized in Table 4.1 below:

Table 4.1   Noise Monitoring Stations for Contract no.  /span>HY/2009/17

Station

Description

M4b

Victoria Centre

 

4.1.2.        No action and limit exceedance was recorded during day time and restricted hour period in the reporting period. Noise monitoring results measured in this reporting period are reviewed and summarized. Noise monitoring results measured in this reporting period are reviewed and summarized. Details of graphical presentation can be referred in Appendix 4.1. 

 

Contract no. 04/HY/2006  /span> Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A

4.1.3.        The commencement of major construction works for Contract no. 04/HY/2006 by September 2010 and no major construction work was commenced by Contract no. HY/2009/18 in the reporting period. The proposed division of noise monitoring stations are summarized in Table 4.2 below.

Table 4.2   Noise Monitoring Station for Contract nos. 04/HY/2006 and HY/2009/18

Station

Description

M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

 

4.1.4.        No exceedance was recorded in the reporting period. Noise monitoring results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and graphical presentation can be referred in Appendix 4.1. 

4.1.5.        The commencement of major construction works for Contract no. HY/2009/18 under FEP-05/364/2009A is pending. Only preparation works was commenced in the reporting period.

4.1.6.        Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

4.1.7.        The commencement of construction works for Contract no. HK/2009/01 and HK/2009/02 under FEP-02/364/2009 and FEP-01/364/2009 respectively are pending. The proposed division of air monitoring stations are summarized in Table 4.3 below.

Table 4.3   Noise Monitoring Stations for Contract nos. HK/2009/01 and HK/2009/02

 

Station

Description

M1a

Harbour Road Sports Centre

 

Contract no. HY/2009/15 - Central-Wanchai Bypass   Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

4.1.8.        The commencement of construction works for Contract no. under FEP-06/364/2009/A is pending. The proposed division of noise monitoring stations are summarized in in Table 4.4 below.

Table 4.4   Noise Monitoring Station for Contract nos. HY/2009/15

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

 

   4.2.          Real Time Noise Monitoring Results

Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

4.2.1.        The proposed division of real time noise monitoring stations are summarized in Table 4.5 below. Real time noise monitoring for the piling works under contract no. HY/2009/17 was commenced on 5 October 2010.

Table 4.5  Real Time Noise Monitoring Station for Contract no. HY/2009/17

District

Description

Tin Hau

FEHD Hong Kong Transport Section Whitefield Depot

4.2.2.        No exceedance was recorded between 0700 and 1900 hours. In contrast, fragmentary exceedances were recorded between 1900 and 2300 hours though out the reporting period and between 2300 and 0700 on the next day. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 4.2

   4.3.          Air Monitoring Results

Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

4.3.1.        The proposed division of air monitoring stations are summarized in Table 4.6 below. Air monitoring for the piling works under contract no. HY/2009/17 was commenced on 8 October 2010.

Table 4.6   Air Monitoring Stations for Contract no. HY/2009/17

Station

Description

CMA2a

Causeway Bay Community Centre

4.3.2.        No exceedance was recorded in the reporting period. Air quality monitoring results measured in this reporting period are reviewed and summarized. Details of air monitoring results and graphical presentation can be referred in Appendix 4.2.. 

Contract no. 04/HY/2006  /span> Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A

4.3.3.        The proposed division of air monitoring stations are summarized in Table 4.7 below.

Table 4.7   Air Monitoring Stations for Contract no. 04/HY/2006 and HY/2009/18

Station

Description

MA1e

International Finance Centre (Eastern End of Podium)

MA1w

International Finance Centre (Western End of Podium)

 

4.3.4.        Due to lack of electricity at station MA1w on 18 November 2010. 24 hours air quality monitoring was rescheduled by 19 November 2010.

4.3.5.        No exceedance was recorded in the reporting period. Air quality monitoring results measured in this reporting period are reviewed and summarized. Details of air monitoring results and graphical presentation can be referred in Appendix 4.3. 

4.3.6.        The commencement of major construction works for Contract no. HY/2009/18 under FEP-05/364/2009A is pending. Only preparation works was commenced in the reporting period.

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

4.3.7.        Air quality monitoring will be commenced depending on the commencement of work for Contract no. HK/2009/01 under FEP-02/364/2009. The proposed division of air monitoring stations are summarized in Table 4.8 below.

Table 4.8   Air Monitoring Stations for Contract no. HK/2009/01

Station

Description

CMA5a

Children Playgrounds opposite to Pedestrian Plaza

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

4.3.8.        Air quality monitoring will be commenced depending on the commencement of work for Contract no. HK/2009/02 under FEP-01/364/2009. The proposed division of air monitoring stations are summarized in Table 4.9 below.

Table 4.9   Air Monitoring Station for Contract no. HK/2009/02

Station

Description

CMA4a

Society for the Prevention of Cruelty to Animals

 

Contract no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

4.3.9.        Air quality monitoring will be commenced depending on the commencement of work for Contract no. HY/2009/15 under FEP-06/364/2009/A. The proposed division of air monitoring stations are summarized in Table 4.10 below.

Table 4.10 Air Monitoring Station for Contract no. HY/2009/15

Station

Description

CMA3a

CWB site office at Wanchai Waterfront Promenade

 

   4.4.          Waste Monitoring Results

Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

 

4.4.1.        Inert C&D waste was recycled in the reporting period. Details of the waste flow table are summarized in Table 4.11

Table 4.11 Details of Waste Disposal for Contract no. HY/2009/17

Waste Type

Quantity this quarter, m3

Cumulative Quantity-to-Date, m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

NIL

N/A

Inert C&D materials recycled

730.24

730.24

N/A

Non-inert C&D materials disposed

NIL

NIL

N/A

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

N/A

N/A

N/A

 

Contract no. 04/HY/2006  /span> Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

4.4.2.        Inert C&D waste was disposed of in this reporting period. Details of the waste flow table are summarized in Table 4.12.

Table 4.12 Details of Waste Disposal for Contract no. 04/HY/2006

Waste Type*

Quantity this quarter,  m3

Cumulative-to-Date.  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

1135.9

1135.9

Chai Wan and

T.K.O. 137

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

NIL

NIL

N/A

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

NIL

NIL

N/A

 

Contract nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

4.4.3.        No inert and non-inert C&D waste was disposed of in this reporting period. Details of the waste flow table are summarized in Table 4.13.

Table 4.13 Details of Waste Disposal for Contract no. HK/2009/01

Waste Type*

Quantity this quarter, m3

Cumulative-to-Date. m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

NIL

N/A

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

NIL

NIL

N/A

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

NIL

NIL

N/A

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

4.4.4.        No inert and no-inert C&D waste was disposed of in this reporting period. Details of the waste flow table are summarized in Table 4.14.

Table 4.14 Details of Waste Disposal for Contract no. HK/2009/02

Waste Type*

Quantity this quarter,  m3

Cumulative-to-Date.  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

NIL

N/A

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

NIL

NIL

N/A

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

NIL

NIL

N/A

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A

 

4.4.5.        Non-Inert C&D waste was disposed of in this reporting period. Details of the waste flow table are summarized in Table 4.15.

Table 4.15 Details of Waste Disposal for Contract no. HY/2009/18

Waste Type*

Quantity this quarter,  m3

Cumulative-to-Date.  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

NIL

N/A

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

3.04

3.04

SENT, TKO137

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

NIL

NIL

N/A

 

Contract no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

4.4.6.        No inert and no-inert C&D waste was disposed of in this reporting period. Details of the waste flow table are summarized in Table 4.16.

Table 4.16 Details of Waste Disposal for Contract no. HY/2009/15

Waste Type*

Quantity this month,  m3

Cumulative-to-Date.  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

NIL

N/A

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

NIL

NIL

N/A

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

NIL

NIL

N/A

5.     Compliance Audit

5.0.1.        The Event Action Plan for construction noise, air quality and water quality are presented in Appendix 5.1.

5.1.               Noise Monitoring

Contract no. HY/2009/17  Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

5.1.1.        No exceedance was recorded in the reporting period.

Contract no. 04/HY/2006  /span> Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

5.1.2.        No exceedance was recorded in the reporting period.

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A

5.1.3.        No noise monitoring was undertaken in the reporting period.

Contract nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works and HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East(CWB Tunnel)

5.1.4.        No noise monitoring was undertaken in the reporting period.

Contract no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A

5.1.5.        No noise monitoring was undertaken in the reporting period.

5.2.               Air Monitoring

Contract no. HY/2009/17  Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

5.2.1.        No exceedance was recorded in the reporting period.

 

Contract no. 04/HY/2006  /span> Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

5.2.2.        No exceedance was recorded in the reporting period.

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A

5.2.3.        No air quality monitoring was undertaken in the reporting period.

Contract nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works and HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East(CWB Tunnel)

5.2.4.        No air quality monitoring was undertaken in the reporting period.

Contract no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A

5.2.5.        No air quality monitoring was undertaken in the reporting period.

5.3.               Site Audit

5.3.1.        There was no non-compliance from the site audits in the reporting period. During environmental site inspections conducted during the reporting quarter, minor deficiencies were noted. However, the Contractor rectified all deficiencies after receipt of notification.

5.4.               Review of the Reasons for and the Implications of Non-compliance

5.4.1.        No project-related non-compliance from monitoring was recorded in the reporting period.

5.5.               Summary of action taken in the event of and follow-up on non-compliance

5.5.1.        There was no particular action taken since no project-related non-compliance was recorded from the site audits and environmental monitoring in the reporting period.

 

6.     Complaints, Notification of Summons and Prosecution

6.0.1.        No complaint was recorded in the reporting period.  The details of cumulative complaint log and summary of complaints are presented in Appendix 6.1.

6.0.2.        No notification of summons or prosecution was received in the reporting period. Cumulative statistic on complaints and successful prosecutions are summarized in Table 6.1 and Table 6.2 respectively.

Table 6.1  Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

Sep - Nov 2010

0

Project-to-Date

0

 

Table 6.2  Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this quarter (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Waste

-

0

0

Total

-

0

0

 

 

7.     Cumulative Construction Impact due to the Concurrent Projects

7.0.1.        According to Condition 3.4 of the EP-364/2009/A, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WWDII), Central-WanChai Bypass (CWB) and Island Eastern Corridor Link projects (IECL).

7.0.2.        According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activity under Wan Chai Development Phase II was the filling works at North Point Reclamation Stage 1(NPR1), dredging works at Wan Chai Reclamation Stage 1(WCR1), Advanced piling works at FEHD Whitfield Depot and cross-harbour water mains in the reporting period. The major environmental impact was water quality impact at North Point and Wan Chai. Land-based construction activity was only the modification works of bus terminus near Man Yiu Street and Man Kwong Street under CWB and advance piling works at FEHD Whitfield Depot in the reporting period.

7.0.3.        The major environmental impacts generated from the Central Reclamation Phase III were located along the coastline of Central and Admiralty while modification works of bus terminus near Man Yiu Street and Man Kwong Street under CWB and advanced piling works at FEHD Whitfield Depot were undertaken in the reporting period. No significant air, noise impact were anticipated in the reporting period. Besides, no environmental monitoring exceedance was recorded from the Project in the reporting period. Thus, it is evaluated that the cumulative construction impact from the concurrent projects including Wan Chai Development Phase II and Central Reclamation Phase III was insignificant.

8.     Conclusion

8.0.1.        The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

8.0.2.        No exceedance, non-compliances were noted and no prosecutions were received during the reporting quarter.

8.0.3.        The construction programmes of individual contracts are provided in Appendix 8.1.