Contract No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and Testing Work
(Stage 2) Environmental
Permit no. EP-356/2009, Further Evironmental permit nos. fep-01/356/2009,
fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 and fep-05/356/2009 Quarterly
Environmental Monitoring
and Audit Report
- June 2012 to August 2012 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai,
H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED
by: |
|
                         Raymond Dai Environmental Team Leader |
|
DATE: |
|
27 September 2012 |
1.1    Scope of the Report
1.2    Structure of the Report
2.   Project Background
2.1    Background
2.2    Scope
of the Project and Site Description
2.3    Division of the Project
Responsibility
2.4    Project Organization and Contact
Personnel
2.5    Principal Work and Activities
3.   Monitoring Requirements
3.1.    Noise Monitoring
3.2.    Air Monitoring
3.3.    Water Quality Monitoring
4.   Monitoring Results
4.1.    Noise Monitoring Results
4.2.    Real Time Noise Monitoring Results
4.3.    Air Monitoring Results
4.4.    Water Monitoring Results
4.5.    Waste Monitoring Results
5.1.    Noise Monitoring
5.2.    Real-time Noise Monitoring
5.3.    Air Monitoring
5.4.    Water Quality Monitoring
5.5.    Site Audit
5.6.    Review
of the Reasons for and the Implications of Non-compliance
5.7.    Summary
of action taken in the event of and follow-up on non-compliance
6.   Complaints, Notification
of Summons and Prosecution
7.   Cumulative Construction
Impact due to the Concurrent Projects.
lIST OF
TABLES
Table I        Principal Work Activities
for Contract no. HY/2009/11
Table II       Principal Work Activities for Contract no. HK/2009/01
Table III       Principal Work Activities for Contract no. HK/2009/02
Table IV      Principal
Work Activities for Contract no. HY/2009/15
Table V       Principal
Work Activities for Contract no. HK/2010/06
Table VI      Principal Work Activities for Contract no. HY/2009/19
Table 2.1      Schedule 2 Designated Projects under this Project
Table 2.2     Details of Individual Contracts under the Project
Table 2.3     Contact Details of Key Personnel
Table 2.4      Principal
Work Activities for Contract no. HY/2009/11
Table 2.5      Principal
Work Activities for Contract no. HK/2009/01
Table 2.6      Principal
Work Activities for Contract no. HK/2009/02
Table 2.7      Principal
Work Activities for Contract no. HY/2009/15
Table 2.8      Principal
Work Activities for Contract no. HK/2010/06
Table 2.9      Principal Work Activities for Contract no. HY/2009/19
Table 3.1     Noise
Monitoring Stations
Table 3.2     Real
Time Noise Monitoring Station
Table 3.3     Air
Monitoring Stations
Table 3.4      Marine
Water Quality Stations for Water Quality Monitoring
Table 3.5     Marine
Water Quality Monitoring Frequency and Parameters
Table 3.6      Marine Water Quality
Stations for Enhanced Water Quality Monitoring
Table 3.7      Marine Water Quality
Stations for Additional DO Monitoring
Table 4.1      Noise
Monitoring Stations for Contract no. 
HY/2009/11
Table 4.2      Noise Monitoring
Station for Contract nos. HK/2009/01 and HK/2009/02
Table 4.3      Noise
Monitoring Station for Contract nos. HY/2009/15
Table 4.4      Noise
Monitoring Station for Contract nos. HY/2009/19
Table 4.5     Real
Time Noise Monitoring Station for Contract no. HY/2009/11
Table 4.6     Real
Time Noise Monitoring Station for Contract no. HY/2009/19
Table 4.7     Air Monitoring
Stations for Contract no. HY/2009/11
Table 4.8      Air Monitoring Stations for Contract no. HK/2009/01
Table 4.9      Air Monitoring
Station for Contract no. HK/2009/02
Table 4.10     Air
Monitoring Station for Contract no. HY/2009/15
Table 4.11     Air
Monitoring Station for Contract no. HY/2009/19
Table 4.12    Water
Monitoring Stations for Contract no. 
HY/2009/11
Table 4.13     Water
Monitoring Stations for Contract no. HK/2009/01
Table 4.14     Water
Monitoring Stations for Contract no. HK/2009/02
Table 4.15     Water
Monitoring Stations for Contract no. HK/2010/06
Table 4.16     Water
Monitoring Stations for Contract no. HY/2009/15
Table
4.17     Water Monitoring Stations for
Contract no. HY/2009/19
Table 4.18     Summary of Water Quality Monitoring Exceedances in
Reporting period
Table 4.19    Details
of Waste Disposal for Contract no. HY/2009/11
Table 4.20    Details
of Waste Disposal for Contract no. HK/2009/01
Table 4.21    Details
of Waste Disposal for Contract no. HK/2009/02
Table 4.22    Details
of Waste Disposal for Contract no. HY/2009/15
Table 4.23    Details
of Waste Disposal for Contract no. HK/2010/06
Table 6.1     Cumulative
Statistics on Complaints
Table 6.2     Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1     Project
Layout
Figure
2.2     Project
Organization Chart
Figure 3.1     Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
2.1  Environmental Mitigation
Implementation Schedule
Appendix 3.1  Action and Limit Level
Appendix
4.1  Noise Monitoring Graphical Presentations
Appendix
4.2  Air Quality Monitoring Graphical Presentations
Appendix
4.3  Water Quality Monitoring Graphical Presentations
Appenidx 4.3a  Additional Dissolved Oxygen
Monitoring Results
Appendix 4.4  Real-time Noise Monitoring Results and Graphical Presentations
Appendix 5.1  Event Action Plans
Appendix 6.1  Complaint Log
Appendix 7.1  Construction Programme of
Individual Contracts
Construction Activities for the
Reported Period
Table I     Principal Work Activities for Contract
no. HY/2009/11
June 2012 |
July 2012 |
August 2012 |
The major
work activities for Contract no. HY/2009/11 was confirmed substantial complete
by RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19 and the FEP-01/356/2009 was under application of surrender in this
reporting period. |
The major
work activities for Contract no. HY/2009/11 was confirmed substantial complete
by RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19 and the FEP-01/356/2009 was under application of surrender in this
reporting period. |
Table II    Principal Work Activities for Contract no.
HK/2009/01
June 2012 |
July 2012 |
August 2012 |
Marine Works (at Wan
Chai) Installation
of sheet pile water channel for cooling water intake at Dome Promenade
between CH170 and Ch220 Rockfilling
for rock bund at HKCEC Water Channel from CH220 to Ch230 Reclamation
of HKECE3W within HKCEC Water Channel Rock Armour
protection to the seawall at Wan Chai Landfall in Zone B1-3 Preparation
works for demolition of existing staircase Cross-Harbour
Watermains Installation (CHA & CHB) and Marine Works (at TST) Rockfilling
and rock protection to cross-harbour watermians Trench
excavation, installation of shoring system and trimming obstructions (mini-piles)
for a 1000 dia. cross harbout watermains (CHB) along the pipe pile wall at
TST seashore Trench
excavation and installation of shoring system for a 1000 dia. cross harbour
watermains (CHA) along the pipe pile wall at TST seashore Removal of
existing seawall at TST seashore for installation of cross harbour watermains
(CHA) and (CHB) Fresh Watermains,
Cooling Watermains and Salt Watermains (On Land) Mainlaying
works at ZoneB1-5A, B2-1, B4-3, B5-1(Switch Room), B5-3(Switch Room), A1-1,
A1-3, A1-3A, A1-3B, A202, A3-3, A3-4B, A3-5B, A3-5B, A4-1 and A4-2A Mainlaying
works and subsequent reinstatement works in Zone b4-4 Mainlaying
works at Zone B4-3 Trench
excavation for cable & G.I. Ducting works at Zone B5-1A, B5-1(Switch
Room) and B5-3(Switch Room) Gate valves connection
works for intake and discharge cooling mains of Shui On Centre at Zone 2-2 Heading No.
H7 and H6A (mainlaying works by trenchless method) Excavation
for jacking pit for pipe laying works by heading method along Mainlaying
and chamber construction works at the traffic island near junction of Cable
ducting works along Trench
excavation, pipe laying works and chamber construction for a 1000dia.
Watermains (CHF) at Trench
excavation, pipe laying works and chamber construction for a 1000 dia.
Waternaubs (CHE) at |
Marine Works (at Wan Chai) Rockfilling
for rock bund across HKCEC Water Channel from Ch220 to Ch230 Reclamation
of HKCEC3W within HKCEC Water Channel Installation
of pipe pile wall for demolition of existing seawall at Cross-Harbour Watermains Installation (CHA & CHB) and Marine Works (at TST) Rockfilling
and rock protection to cross-harbour watermains Removal of
existing seawall at TST seashore for installation of cross harbour watermains
(CHA) and (CHB) Installation
of cross-harbour watermains No. A18 & B18 Fresh Watermains, Cooling Watermains and Salt Watermains (On Land) Mainlaying
works at Zone B1-5A, B2-1, B4-3, B4-1A, B5-1, B5-3, A1-1, A1-2, A1-3A, A1-3B,
A2-2, A3-4B, A3-5B, A4-2A and C1-10 A combined
TTA at Trench
excavation for cable ducting works at Zone B5-1 and B5-3 Pipe laying
works at Heading No. H7 Heading No.
H6a, H6b and H6c Mainlaying
and chamber construction works at the traffic island near junction of Convention
Avenue and Mainlaying
works at Pipe laying
woks and chamber construction for a 1000 dia. Watermains (CHE) at Mainlaying
works including cooling mains and cross harbour watermains across CWB section
within HKCEC Water Channel |
Marine Works (at Wan Chai) Rockfilling
for rock bund across HKCEC Water Channel from Ch220 to Ch230 Reclamation
of HKCEC3W within HKCEC Water Channel Installation
of pipe pile wall for demolition of existing seawall at  /span>Demolition of Wan Chai West Ferry Pier Cross-Harbour Watermains Installation (CHA & CHB) and Marine Works
(at TST) Rockfilling
and rock protection to cross-harbour watermains Installation
of cross-harbour watermains No. A18 & B18 Fresh Watermains, Cooling Watermains and Salt Watermains (On Land) Mainlaying
works at Zone B1-5A, B2-1, B3-1, B4-3, B4-1A, B5-1(Switch Room), B5-3(Switch
Room), A1-1, A1-2, A1-3B, A2-2, A3-2A, A3-4B, A3-5B and A4-2A The
reinstatement of one carriageway at Zone B2-1 Mainlaying Works at Zone B3-1
of Expo Drive Central Breakup of
concrete surround and trimming of 1 no. existing intake and 2 no. existing discharge
pipe at Zone A1-1 and A1-2 Pipe laying
works at Heading No. H7 Heading No.
H6c (Mainlaying works by trenchless method) Mainlaying
and chamber construction works at the traffic island near junction of Mainlaying
works at Zone A3-2A of Mainlaying
works at Mainlaying
Works for a 1000 dia. Watermains (CHE) at Reinstatement
Works at Pipe Laying
works including 9 nos. cooling mains across E/D section within HKCEC Water
Channel Pipe Laying
works including 9 nos. cooling mains across SCL section within HKCEC Water
Channel Pipe Laying
works including 9 nos. cooling mains and 2no. cross harbour watermains at
North Bank of HKCEC Water Channel |
Table III    Principal Work Activities for Contract no.
HK/2009/02
June 2012 |
July 2012 |
August 2012 |
The
possession of the new helipad was taken over by GFS The GFS
operation for the private sector business Modification
work of PTI at Self-testing
of the individual systems Install the
motor of the band screen and steel platform at +2.03mPD at wet well of P8 Wet well FRP
platform of P7, P8 & P9 and handed over to E & M for penstock leakage
testing. Combined
chamber for SHK at ex-pet garden Trench excavation
and shoring installation at Removal of
the damaged cooling mains adjacent to new seawall area at WCR1 Trench
excavation and cooling mains installation at WCR1 Cabling
works along The TBM
breaking-out of the WSD 2nd drive The formwork
and scaldfold removal was substantially completed in the WSD pumping station Joint
inspection of the TX room handed over to HEC Preparatory work
of waterproofing at the roof floor for the WSD Salt Water Pumping Station Installation
and welding for 4th layer of walings and struts for construction of intake Opening in
sheetpile cofferdam at Wan Shing Street Bay 24 and dewatering and removal of
loose sand at the bottom ELS of 4th
layer (-5.8mPD) struts & walings of salt water intake landside cofferdam ELS of 3nd
layer (-3.5mPD) struts & walings of salt water intake seadside cofferdam Gridline
9-15 sub-structure and pre-cast slabs to +4.15mPD Approximate
7m DN800 MS pipe installation near Gate 1 at ex-pet garden Temporary
seawall construction works of WCR2 was completed, rockfilling and laying of
geotextile The 1st
layer of waling of the outfall launching shaft Excavation
and breaking up the rock to 2nd layer for strut and waling installation of
the outfall launching shaft Benching
modification at existing DSD chamber Excavation
down to -5.8 mPD of submarine outfall seaside cofferdam E&M
installation at existing DSD treatment plant Excavation
down the Box Culvert N1 seaside cofferdam was commenced on 31 May 2012 and
ELS of 2rd layer (+0.7mPD) struts & walings was in progress. Precast slab
installation at New Ferry Pier Guide line 1-8 / A-F was completed on 24 May
2012, and dismantles formwork for upper beam was in progress. Removal of
formwork for top slab (+4.15mPD) Guide line 1-5 / A-F was completed on 28 May
2012. Dismantle
steel panel for water tank for 2A1, 2A2 was in progress. Formwork
erections for upper beam for 3A2, 3B2, 3C1, 3C2, 3C3,3A1, 3B1 Steel bar
fixing for upper beam & corbel beam for 3A1, 3A2, 3B1, 3B2, 3C1, 3C2, 3C3
was ongoing.          Rock filling
grade 200 at WCR2 reclamation was ongoing. Infill gap
of steel frame “Well A for construction of water diversion channel along the
existing seawall at WCR2 Reinstatement
of permanent bituminous carriageway ELS for Box
culvert "O" diversion |
Modification
work of PTI at Modification
work of bus station at Self-testing
of the individual pumping systems for cooling mains work. Wet well was
handed over to E & M for penstock leakage testing. Installation
work of P7, P8 & P9 Cooling
mains Installation at Discharge
pipe installation for SHK at WCR1 Cooling
mains installation at WCR1 Cabling
works along Waterproofing
slurry to wall at 1/F Surge vessel area for finishing work and remedial work
at R/F for planter area for the WSD Salt Water Pumping Station E&M
works at WSD Salt Water Pumping Station Concreting
of the salt water intake culvert at Base slab
casting of salt water intake culvert at Wan Shing Street Bay 20 Additional
grouting and excavation for pipe cap construction in salt water intake
landside cofferdam Casting of
concrete plug of Bay 7 at WCR12 Concreting
the salt water intake culvert of Bay 3 and Bay 5 at WCR1 Placement of
concrete plug inside salt water intake seaside cofferdam Under water
excavation inside salt water intake seaside cofferdam Approximate Rock filling
and placing bagged concrete at return end of seawall block for WCR2
reclamation Excavation
and breaking up the rock to 2nd layer for strut and waling installation of
the outfall launching shaft Base
concrete plug inside the outfall seaside cofferdam HDPE pipe
butt fusion welding inside the jacking pit ELS for Box
Culvert N1 seaside cofferdam for 3rd layer (-1.5mPD) struts & walings Erecting
formwork for construction of base slab for Box Culvert N1 on UU bridge Final
precast slab installation at New Ferry Pier Guide line 9-15 / A-F and
dismantles formwork for upper beam Erection of
formwork and false work for column at New Ferry Pier Guide line 1-8 level 1
to level 2 Vertical
seawall construction at WCR2 Laying of
geotextile at WCR2                                                                        
Rock filling
grade 200 at WCR2 reclamation Infill gap
of steel frame “Well A and “Well B for construction of water diversion
channel along the existing seawall at WCR2 Flow
Diversion of Box Culvert O Bulkhead
wall Type 3 and Type 2 construction at Box Culvert “O  Bulkhead
wall at Diversion of
LV Cable and 150MS Freshwater pipe |
Modification
work of PTI and bus station at Self-testing
of the individual pumping systems for cooling mains work Wet well was
handed over to E & M for penstock leakage testing Reinstatement
at Cooling
mains installation at west of Gate 1 inside ex-pet garden and the steel
fixing and casting of the damaged
thrust box Cabling
works along Waterproofing
membrane at roof level at WSD Salt Water Pumping Station. E&M
works at WSD Salt Water Pumping Station Wall shaft
and roof slab casting of salt water intake culvert at Wan Shing Street Bay 20
and steel fixing of 19B Removing the
strut & waling for road reinstatement near Bay 24 and backfilling of salt
water intake culvert at Sheetpiling
at Bay 11 and the grouting work Pile cap
steel fixing of Bay Concreting
the salt water intake culvert of Bay 4 and Bay 7 at WCR1 and concreting the
base slab of Bay 8 Concreting
pile cap of IC1 and the construction of pile cap IC2 in salt water intake seaside
cofferdam. Excavation
and breaking up the rock down to 3rd layer of strut and waling installation
of the outfall launching shaft and then the 2nd layer waling Cutting the opening
of sheetpiles and coring of thrust wall between Launching Pit and Jacking Pit
Excavation the
fill material to expose HDPE pipe end by divers inside the outfall seaside
cofferdam Cutting
casing of pre-bored H-pile to cut-off level for pile cap at Bay 4 and Bay 5
of Box Culvert N1 northern cofferdam Excavation
to formation level and making good of blinding layer for pile cap at Bay 4 and
Bay 5 of Box Culvert N1 northern cofferdam Concreting
the base slab of Box Culvert N1 Bay 2 and Bay 3 on UU bridge Dismantling
of steel panel & H-beam of water tank at zone 2B and the dismantling work
of water tank in zone 3B and Concreting
the columns at New Ferry Pier GL 6-7 / B-F level 1 to level 2 and erection
formwork and falsework at GL 8-15 / B-F Steel fixing
the slab at New Ferry Pier GL 1-8 level 1 and GL 9 -15 level 2 Rockfilling
and placing bagged concrete for the seawall block area at WCR2 Reclamation of
WCR2 TDMP for Box
Culvert “O Diversion at Bay 12-13 Bulkhead
wall at Water pressure
test and sterilization test for 150MS freshwater pipe at Box Culvert “O 
prior to the diversion of captioned water pipe. Trial pit
excavation and preparation works for Hung Hing Road Diversion |
Table IV   Principal Work
Activities for Contract no. HY/2009/15
June 2012 |
July 2012 |
August 2012 |
Removal of
temporary reclamation at TS1 Dredging for
seawall foundation at TS2 Seawall
trench works at TS2 |
Removal of
temporary reclamation at TS1 Underwater
cutting of temporary diaphragm walls at TS1 Dredging for
seawall foundation at TS2 Seawall
trench works at TS2 |
Removal of
temporary reclamation at TS1 Underwater
cutting of temporary diaphragm walls at TS1 Dredging for
seawall foundation at TS2 Seawall
trench works at TS2 |
Table V    Principal Work
Activities for Contract no. HK/2010/06
June 2012 |
July 2012 |
August 2012 |
Concrete
Breaking Pre Drill
Works Coring Works Sheet Piling |
Concrete
Breaking Pre Drill
Works Coring Works Platform
Disassembly |
Pile head
breaking Sonic tube
trimming |
Table VI   Principal Work
Activities for Contract no. HY/2009/19
June 2012 |
July 2012 |
August 2012 |
Marine bored piling |
Marine bored piling
Construction works for Box
Culvert T |
Marine bored
piling Construction
works for Box Culvert T |
Noise Monitoring
M1a: From 24 Jul 2012 to 25 Jul 2012
Real-time Noise Monitoring
Air Quality Monitoring
CMA1b: from 6 Jun to 7 Jun 2012
      /span> /span> /span> /span>from 27
Jul and 20 Aug 2012 to 31 Jul and 21 Aug 2012
CMA2a: from 18 Jun to 19 Jun 2012
        /span>from 27 Jul and 8 Aug 2012 to 28 Jul and
10 Aug 2012
CMA3a: from 10 and 16 Jul to 11 and 18 Jul 2012
CMA5a: from 6 Jun to 7 Jun 2012
       
from 4 and 21 Jul to 5 and 24 Jul 2012
       
from 20 Aug to 21 Aug 2012  
CMA6a: from 8 Aug 2012 to 9 Aug 2012
CMA2a: from 9 August 2012 to 11 August 2012
Water Quality Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-356/2009 and Further Environmental
permit nos. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the Environmental Monitoring and
Audit (EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.4 of EM&A Manual and  /span>Environmental
Monitoring and Audit Requirements /span> under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
during the period from June 2012 to August 2012
Section 1     Introduction  details the scope and structure of the
report.
Section 2     Project Background  summarizes
background and scope of the project, site description, project organization and
contact details of key personnel during the reporting period.
Section 3     Monitoring Requirements  summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4     Monitoring Results  summarizes the
monitoring results obtained in the reporting period.
Section 5     Compliance Audit  summarizes the auditing of
monitoring results, all exceedances environmental parameters.
Section 6     Complaints, Notification of summons and
Prosecution  summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 7     Cumulative Construction Impact due to the
Concurrent Projects  summarizes the relevant cumulative
construction impact due to the concurrent activities of the concurrent Projects.
Section 8     Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass and “Central-Wan Chai
Bypass and Island Eastern Corridor Link (hereafter called “the Project  are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
The
Project is located mainly in Wan Chai North,
2.2.2.
The
study area encompasses existing developments along the Wan Chai,
2.2.3.
The scope of the Project comprises:
 -
Land formation for key transport infrastructure and
facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for
connection to the Trunk Road and for through traffic from Central to Wan Chai and
Causeway Bay. The land formed for the above transport infrastructure will provide
opportunities for the development of an attractive waterfront promenade for the
enjoyment of the public
 -
Reprovisioning / protection of the existing
facilities and structures affected by the land formation works mentioned above
 -
Extension, modification, reprovisioning or
protection of existing storm water drainage outfalls, sewerage outfalls and
watermains affected by the revised land use and land formation works mentioned
above
 -
Upgrading of hinterland storm water drainage system
and sewerage system, which would be rendered insufficient by the land formation
works mentioned above
 -
Provision of the ground level roads, flyovers,
footbridges, necessary transport facilities and the associated utility services
 -
Construction of the new waterfront promenade,
landscape works and the associated utility services
 -
The Trunk Road (i.e. CWB) within the study area and
the associated slip roads for connection to the Trunk Road.
2.2.4.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project.
Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1   Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits (FEP) such that the impact monitoring stations are sub-divided
accordingly to facilitate the implementation of EM&A programme and to
streamline the EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The
details of individual contracts are summarized in Table2.2.
Table
2.2  Details of Individual Contracts
under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II  Central –Wanchai Bypass at |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central  Wan Chai Bypass  North
Point Reclamation |
DP3 |
17 March 2010 (Under applicationof surrender) |
HY/2009/15 |
Central-Wanchai Bypass  Tunnel ( |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB)  Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For
the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in
Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative  /span>for
WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative  /span>for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
|
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project
Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental
Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo  Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
|
2162 9909 |
2587 1878 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Sub-Agent |
Mr Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 3008 |
|||
Construction
Manager |
Mr. KK Yuen |
9498 1213 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Chun Wo  CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658 3000 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
P J Fan |
3557 6368 |
2566 2192 |
||
|
|
Contractor’s Representative |
Mr. David Lau |
3557 6368 |
2566 2192 |
|
|
Head of Construction Manager |
Roger Cheung |
3557 6371 |
2566 2192 |
|
|
Senior Construction Manager |
Gene Cheung |
3557 6395 |
2566 2192 |
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|
||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee Wai Man |
9481 6024 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental
Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Environmental Manager / Environmental
Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
During
this reporting period, the principal work activities for Contract no.
HY/2009/11 are summarized in Table2.4.
Table
2.4   Principal Work Activities for
Contract no. HY/2009/11
June 2012 |
July 2012 |
Aug 2012 |
The major
work activities for Contract no. HY/2009/11 was confirmed substantial complete
by RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19 and the FEP-01/356/2009 was under application of surrender in this
reporting period. |
The major
work activities for Contract no. HY/2009/11 was confirmed substantial complete
by RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19 and the FEP-01/356/2009 was under application of surrender in this
reporting period. |
The major
work activities for Contract no. HY/2009/11 was confirmed substantial complete
by RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19 and the FEP-01/356/2009 was under application of surrender in this
reporting period. |
2.5.2.
During
this reporting period, the principal work activities for Contract no.
HK/2009/01 are summarized in Table 2.5.
Table
2.5   Principal Work Activities for
Contract no. HK/2009/01
June 2012 |
July 2012 |
Aug 2012 |
Marine Works (at Wan Chai) Installation
of sheet pile water channel for cooling water intake at Dome Promenade
between CH170 and Ch220 Rockfilling
for rock bund at HKCEC Water Channel from CH220 to Ch230 Reclamation
of HKECE3W within HKCEC Water Channel Rock Armour
protection to the seawall at Wan Chai Landfall in Zone B1-3
Preparation works for demolition of existing
staircase Cross-Harbour Watermains Installation (CHA & CHB) and Marine Works
(at TST) Rockfilling
and rock protection to cross-harbour watermians Trench
excavation, installation of shoring system and trimming obstructions
(mini-piles) for a 1000 dia. cross harbout watermains (CHB) along the pipe
pile wall at TST seashore Trench
excavation and installation of shoring system for a 1000 dia. cross harbour
watermains (CHA) along the pipe pile wall at TST seashore Removal of
existing seawall at TST seashore for installation of cross harbour watermains
(CHA) and (CHB) Fresh Watermains, Cooling Watermains and Salt Watermains (On Land) Mainlaying
works at ZoneB1-5A, B2-1, B4-3, B5-1(Switch Room), B5-3(Switch Room), A1-1,
A1-3, A1-3A, A1-3B, A202, A3-3, A3-4B, A3-5B, A3-5B, A4-1 and A4-2A Mainlaying
works and subsequent reinstatement works in Zone b4-4 Mainlaying
works at Zone B4-3 Trench
excavation for cable & G.I. Ducting works at Zone B5-1A, B5-1(Switch
Room) and B5-3(Switch Room) Gate valves connection
works for intake and discharge cooling mains of Shui On Centre at Zone 2-2 Heading No.
H7 and H6A (mainlaying works by trenchless method) Excavation
for jacking pit for pipe laying works by heading method along Mainlaying
and chamber construction works at the traffic island near junction of Cable
ducting works along Trench
excavation, pipe laying works and chamber construction for a 1000dia.
Watermains (CHF) at Trench
excavation, pipe laying works and chamber construction for a 1000 dia.
Waternaubs (CHE) at |
Marine Works (at Wan
Chai) Rockfilling
for rock bund across HKCEC Water Channel from Ch220 to Ch230 Reclamation
of HKCEC3W within HKCEC Water Channel Installation
of pipe pile wall for demolition of existing seawall at Cross-Harbour Watermains
Installation (CHA & CHB) and Marine Works (at TST) Rockfilling
and rock protection to cross-harbour watermains Removal of
existing seawall at TST seashore for installation of cross harbour watermains
(CHA) and (CHB) Installation
of cross-harbour watermains No. A18 & B18 Fresh Watermains,
Cooling Watermains and Salt Watermains (On Land) Mainlaying
works at Zone B1-5A, B2-1, B4-3, B4-1A, B5-1, B5-3, A1-1, A1-2, A1-3A, A1-3B,
A2-2, A3-4B, A3-5B, A4-2A and C1-10 A combined
TTA at Trench
excavation for cable ducting works at Zone B5-1 and B5-3 Pipe laying
works at Heading No. H7 Heading No.
H6a, H6b and H6c Mainlaying
and chamber construction works at the traffic island near junction of Convention
Avenue and Mainlaying
works at Pipe laying
woks and chamber construction for a 1000 dia. Watermains (CHE) at Mainlaying
works including cooling mains and cross harbour watermains across CWB section
within HKCEC Water Channel |
Marine Works (at Wan
Chai) Rockfilling
for rock bund across HKCEC Water Channel from Ch220 to Ch230 Reclamation
of HKCEC3W within HKCEC Water Channel Installation
of pipe pile wall for demolition of existing seawall at  /span>Demolition of Wan Chai West Ferry Pier Cross-Harbour
Watermains Installation (CHA & CHB) and Marine Works (at TST) Rockfilling
and rock protection to cross-harbour watermains Installation
of cross-harbour watermains No. A18 & B18 Fresh Watermains,
Cooling Watermains and Salt Watermains (On Land) Mainlaying
works at Zone B1-5A, B2-1, B3-1, B4-3, B4-1A, B5-1(Switch Room), B5-3(Switch
Room), A1-1, A1-2, A1-3B, A2-2, A3-2A, A3-4B, A3-5B and A4-2A The
reinstatement of one carriageway at Zone B2-1 Mainlaying Works at Zone B3-1
of Expo Drive Central Breakup of
concrete surround and trimming of 1 no. existing intake and 2 no. existing discharge
pipe at Zone A1-1 and A1-2 Pipe laying
works at Heading No. H7 Heading No.
H6c (Mainlaying works by trenchless method) Mainlaying
and chamber construction works at the traffic island near junction of Mainlaying
works at Zone A3-2A of Mainlaying
works at Mainlaying
Works for a 1000 dia. Watermains (CHE) at Reinstatement
Works at Pipe Laying
works including 9 nos. cooling mains across E/D section within HKCEC Water
Channel Pipe Laying
works including 9 nos. cooling mains across SCL section within HKCEC Water
Channel
Pipe Laying works including 9 nos. cooling
mains and 2no. cross harbour watermains at North Bank of HKCEC Water Channel |
2.5.3.
During
this reporting period, the principal work activities for Contract no. HK/2009/02
are summarized in Table 2.6.
Table
2.6   Principal Work Activities for
Contract no. HK/2009/02
June 2012 |
July 2012 |
Aug 2012 |
The
possession of the new helipad was taken over by GFS The GFS
operation for the private sector business Modification
work of PTI at Self-testing
of the individual systems Install the
motor of the band screen and steel platform at +2.03mPD at wet well of P8 Wet well FRP
platform of P7, P8 & P9 and handed over to E & M for penstock leakage
testing. Combined
chamber for SHK at ex-pet garden Trench
excavation and shoring installation at Removal of
the damaged cooling mains adjacent to new seawall area at WCR1 Trench
excavation and cooling mains installation at WCR1 Cabling works
along The TBM
breaking-out of the WSD 2nd drive The formwork
and scaldfold removal was substantially completed in the WSD pumping station Joint
inspection of the TX room handed over to HEC Preparatory work
of waterproofing at the roof floor for the WSD Salt Water Pumping Station Installation
and welding for 4th layer of walings and struts for construction of intake Opening in
sheetpile cofferdam at Wan Shing Street Bay 24 and dewatering and removal of
loose sand at the bottom ELS of 4th
layer (-5.8mPD) struts & walings of salt water intake landside cofferdam ELS of 3nd
layer (-3.5mPD) struts & walings of salt water intake seadside cofferdam Gridline
9-15 sub-structure and pre-cast slabs to +4.15mPD Approximate
7m DN800 MS pipe installation near Gate 1 at ex-pet garden Temporary
seawall construction works of WCR2 was completed, rockfilling and laying of
geotextile The 1st
layer of waling of the outfall launching shaft Excavation
and breaking up the rock to 2nd layer for strut and waling installation of
the outfall launching shaft Benching
modification at existing DSD chamber Excavation
down to -5.8 mPD of submarine outfall seaside cofferdam E&M installation
at existing DSD treatment plant Excavation
down the Box Culvert N1 seaside cofferdam was commenced on 31 May 2012 and
ELS of 2rd layer (+0.7mPD) struts & walings was in progress. Precast slab
installation at New Ferry Pier Guide line 1-8 / A-F was completed on 24 May
2012, and dismantles formwork for upper beam was in progress. Removal of
formwork for top slab (+4.15mPD) Guide line 1-5 / A-F was completed on 28 May
2012. Dismantle
steel panel for water tank for 2A1, 2A2 was in progress. Formwork erections
for upper beam for 3A2, 3B2, 3C1, 3C2, 3C3,3A1, 3B1 Steel bar
fixing for upper beam & corbel beam for 3A1, 3A2, 3B1, 3B2, 3C1, 3C2, 3C3
was ongoing.          Rock filling
grade 200 at WCR2 reclamation was ongoing. Infill gap
of steel frame “Well A for construction of water diversion channel along the
existing seawall at WCR2 Reinstatement
of permanent bituminous carriageway ELS for Box
culvert "O" diversion |
Modification
work of PTI at Modification
work of bus station at Self-testing
of the individual pumping systems for cooling mains work. Wet well was
handed over to E & M for penstock leakage testing. Installation
work of P7, P8 & P9 Cooling
mains Installation at Discharge
pipe installation for SHK at WCR1 Cooling
mains installation at WCR1 Cabling
works along Waterproofing
slurry to wall at 1/F Surge vessel area for finishing work and remedial work
at R/F for planter area for the WSD Salt Water Pumping Station E&M
works at WSD Salt Water Pumping Station Concreting
of the salt water intake culvert at Base slab
casting of salt water intake culvert at Wan Shing Street Bay 20 Additional
grouting and excavation for pipe cap construction in salt water intake
landside cofferdam Casting of
concrete plug of Bay 7 at WCR12 Concreting
the salt water intake culvert of Bay 3 and Bay 5 at WCR1 Placement of
concrete plug inside salt water intake seaside cofferdam Under water
excavation inside salt water intake seaside cofferdam Approximate Rock filling
and placing bagged concrete at return end of seawall block for WCR2
reclamation Excavation
and breaking up the rock to 2nd layer for strut and waling installation of
the outfall launching shaft Base
concrete plug inside the outfall seaside cofferdam HDPE pipe
butt fusion welding inside the jacking pit ELS for Box
Culvert N1 seaside cofferdam for 3rd layer (-1.5mPD) struts & walings Erecting
formwork for construction of base slab for Box Culvert N1 on UU bridge Final
precast slab installation at New Ferry Pier Guide line 9-15 / A-F and
dismantles formwork for upper beam Erection of
formwork and false work for column at New Ferry Pier Guide line 1-8 level 1
to level 2 Vertical
seawall construction at WCR2 Laying of
geotextile at WCR2                                                         
                /span> Rock filling
grade 200 at WCR2 reclamation Infill gap
of steel frame “Well A and “Well B for construction of water diversion
channel along the existing seawall at WCR2 Flow
Diversion of Box Culvert O Bulkhead
wall Type 3 and Type 2 construction at Box Culvert “O  Bulkhead
wall at Diversion of
LV Cable and 150MS Freshwater pipe |
Modification
work of PTI and bus station at Self-testing
of the individual pumping systems for cooling mains work Wet well was
handed over to E & M for penstock leakage testing Reinstatement
at Cooling
mains installation at west of Gate 1 inside ex-pet garden and the steel
fixing and casting of the damaged
thrust box Cabling
works along Waterproofing
membrane at roof level at WSD Salt Water Pumping Station. E&M
works at WSD Salt Water Pumping Station Wall shaft
and roof slab casting of salt water intake culvert at Wan Shing Street Bay 20
and steel fixing of 19B Removing the
strut & waling for road reinstatement near Bay 24 and backfilling of salt
water intake culvert at Sheetpiling
at Bay 11 and the grouting work Pile cap
steel fixing of Bay Concreting
the salt water intake culvert of Bay 4 and Bay 7 at WCR1 and concreting the
base slab of Bay 8 Concreting
pile cap of IC1 and the construction of pile cap IC2 in salt water intake seaside
cofferdam. Excavation
and breaking up the rock down to 3rd layer of strut and waling installation
of the outfall launching shaft and then the 2nd layer waling Cutting the opening
of sheetpiles and coring of thrust wall between Launching Pit and Jacking Pit
Excavation the
fill material to expose HDPE pipe end by divers inside the outfall seaside
cofferdam Cutting
casing of pre-bored H-pile to cut-off level for pile cap at Bay 4 and Bay 5
of Box Culvert N1 northern cofferdam Excavation
to formation level and making good of blinding layer for pile cap at Bay 4 and
Bay 5 of Box Culvert N1 northern cofferdam Concreting
the base slab of Box Culvert N1 Bay 2 and Bay 3 on UU bridge Dismantling
of steel panel & H-beam of water tank at zone 2B and the dismantling work
of water tank in zone 3B and Concreting
the columns at New Ferry Pier GL 6-7 / B-F level 1 to level 2 and erection
formwork and falsework at GL 8-15 / B-F Steel fixing
the slab at New Ferry Pier GL 1-8 level 1 and GL 9 -15 level 2 Rockfilling
and placing bagged concrete for the seawall block area at WCR2 Reclamation of
WCR2 TDMP for Box
Culvert “O Diversion at Bay 12-13 Bulkhead
wall at Water pressure
test and sterilization test for 150MS freshwater pipe at Box Culvert “O 
prior to the diversion of captioned water pipe. Trial pit
excavation and preparation works for Hung Hing Road Diversion |
2.5.4.
Major construction activities for Contract no.
HY/2009/15 was commenced on 10 November 2010. During this reporting period, the
principal work activities for Contract no. HY/2009/15 are summarized as below:
Table
2.7   Principal Work Activities for Contract no. HY/2009/15
June 2012 |
July 2012 |
Aug 2012 |
Removal of
temporary reclamation at TS1 Dredging for
seawall foundation at TS2 Seawall
trench works at TS2 |
Removal of
temporary reclamation at TS1 Underwater
cutting of temporary diaphragm walls at TS1 Dredging for
seawall foundation at TS2 Seawall
trench works at TS2 |
Removal of
temporary reclamation at TS1 Underwater
cutting of temporary diaphragm walls at TS1 Dredging for
seawall foundation at TS2 Seawall
trench works at TS2 |
2.5.5.
Contract
no. HK/2010/06 was commenced on 22 March 2011. During this reporting period,
the principal work activities for Contract no. HK/2010/06 are summarized as below:
Table
2.8   Principal Work Activities for Contract no. HK/2010/06
June 2012 |
July 2012 |
Aug 2012 |
Concrete
Breaking Pre Drill
Works Coring Works Sheet Piling |
Concrete
Breaking Pre Drill
Works Coring Works Platform
Disassembly |
Pile head
breaking Sonic tube
trimming |
Table 2.9  Principal Work Activities
for Contract no. HY/2009/19
June 2012 |
July 2012 |
Aug 2012 |
Marine bored
piling |
Marine bored
piling Construction
works for Box Culvert T |
Marine bored
piling Construction
works for Box Culvert T |
2.5.7.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in
Appendix 2.1.
Noise Monitoring Stations
3.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
3.1 and
Figure 3.1. Appendix 3.1 shows
the established Action/Limit Levels for the monitoring works.
Table 3.1  Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Real
time Noise Monitoring Stations
3.1.1.
The real-noise monitoring stations for the Project are
listed and shown in Table 3.2 and
Figure 3.1..
Appendix 3.1 shows the established Action/Limit Levels for the
monitoring works.
Table 3.2  Real Time Noise Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring
Parameters, Frequency and Duration
3.1.2.
The construction
noise level shall be measured in terms of the A-weighted equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700
and 1900 hours on normal weekdays. For all other time periods, Leq (5
minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.3.
Noise monitoring
shall be carried out at all the designated monitoring stations. The monitoring
frequency shall depend on the scale of the construction activities. The
following is an initial guide
on the regular monitoring frequency for each station on a weekly basis when
noise generating activities are underway:
 -
one
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.4.
If construction works are extended to
include works during the hours of 1900  0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
3.1.5.
Real
time noise shall be carried out at the designated monitoring stations. The following
is an initial guide on the regular monitoring frequency for each station on a
24 hours daily basis when noise generating activities are underway:
 -
One
set of measurements between 0700 and 1900 hours on normal weekdays.
 -
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
 -
One
set of measurements between 2300 and 0700 hours on next day on everyday.
Monitoring Equipment
3.1.6.
As referred to in the Technical Memorandum  issued
under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise measurement
agree to within 1.0 dB.
3.1.7.
Noise measurements shall not be made in fog, rain,
wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
Air Quality Monitoring
Stations
3.2.1.
The
air monitoring stations for the Project are listed and shown in Table
3.3 and Figure
3.1.
Appendix 3.1 shows the established Action/Limit Levels for the
monitoring works.
Table 3.3  Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
* Remarks: As per the ENPC meeting in January 2011,
the monitoring stations CMA3a - Future CWB site office at Wanchai Waterfront
Promenade and CMA6a - Future AECOM site office at Work Area were renamed as
remark.
Air Monitoring Parameters,
Frequency and Duration
3.2.2.
One-hour
and 24-hour TSP levels should be measured to indicate the impacts of
construction dust on air quality. The 24-hour TSP levels shall be measured by
following the standard high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
3.2.3.
All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and any other local atmospheric factors affecting or
affected by site conditions, etc., shall be recorded down in detail.
3.2.4.
For
regular impact monitoring, the sampling frequency of at least once in every
six-days, shall be strictly observed at all the monitoring stations for 24-hour
TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least
three times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5
High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
 -
0.6
- 1.7 m3 per minute adjustable flow range;
 -
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
 -
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
 -
capable
of providing a minimum exposed area of 406 cm2;
 -
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
 -
equipped
with a shelter to protect the filter and sampler;
 -
incorporated
with an electronic mass flow rate controller or other equivalent devices;
 -
equipped
with a flow recorder for continuous monitoring;
 -
provided
with a peaked roof inlet;
 -
incorporated
with a manometer;
 -
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
 -
easily
changeable filter; and
 -
capable
of operating continuously for a 24-hour period.
3.2.6
Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
Laboratory Measurement /
Analysis
3.2.7
A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
3.2.8
An alternative non-HOKLAS accredited laboratory was set-up for carrying out the laboratory analysis,
the laboratory equipment was
approved by the ER on 8 February 2011 and the
measurement procedures were
witnessed by the IEC. Any measurement performed by the laboratory was be demonstrated to the satisfaction of
the ER and IEC. IEC shall regularly audit to the measurement performed by the
laboratory to ensure the accuracy of measurement results.
3.2.9
Filter paper of size 8" x 10" shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
3.2.10
After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
3.2.11
All the collected samples shall be kept in a good
condition for 6 months before disposal.
impact monitoring for
odour patrol
3.2.12 Odour patrols
along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai Public
Cargo Working Area when there is temporary reclamation in Causeway Bay Typhoon
Shelter and/or in the ex-Wan Chai
Public Cargo Working Area, or when there is dredging of the odorous sediment
and slime at the south-western corner of the Causeway Bay Typhoon Shelter.
Odour patrols will be carried out at bi-weekly intervals during July, August
and September by a qualified person of the ET who shall:
 -
be
at least 16 years of age;
 -
be
free from any respiratory illnesses; and
 -
not
be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30
min
 -
before
and during odour patrol
3.2.13 Odour patrol shall be conducted by
independent trained personnel / competent persons patrolling and sniffing
around the shore as shown in
Figure 3.1 to detect any odour at the
concerned hours (afternoon is preferred for higher daily temperature).
3.2.14 The qualified person will use the nose
(olfactory sensor) to sniff odours at different locations. The main odour
emission sources and the areas to be affected by the odour nuisance will be
identified.
3.2.15 The perceived odour intensity is to be
divided into 5 levels which are ranked in the descending order as follows:
 -
0 -
Not detected. No odour perceived or an odour so weak that it cannot be easily
characterized or described;
 -
1 -
Slight Identifiable odour, and slight chance to have odour nuisance;
 -
2 -
Moderate Identifiable odour, and moderate chance to have odour nuisance;
 -
3 -
Strong Identifiable, likely to have odour nuisance;
 -
4 -
Extreme Severe odour, and unacceptable odour level.
3.2.16 The findings including odour intensity,
odour nature and possible odour sources, and also the local wind speed and
direction at each location will be recorded. In addition, some relevant
meteorological and tidal data such as daily average temperature, and daily
average humidity, on that surveyed day will be obtained from the Hong Kong
Observatory Station for reference. The Action and Limit levels for odour patrol
are shown in
Appendix 3.1.
3.3.1.
The
EIA Report has identified that the key water quality impact would be associated
with the dredging works during the construction phase. Marine water quality monitoring for dissolved
oxygen (DO), suspended solid (SS) and turbidity is therefore recommended to be
carried out at selected WSD flushing water intakes. The impact monitoring should be carried out
during the proposed dredging works to ensure the compliance with the water
quality standards.
3.3.2.
The updated EM&A Manual for EP-356/2009
(Version in March 2011) is approval by EPD on 29 April 2011. As such, the
Action Level and Limit Level for the wet season (April  September) will be
effected and applied to the water quality monitoring data from 30 April 2011.
Water Quality Monitoring Stations
3.3.3.
It
is proposed to monitor the water quality at 9 WSD salt water intakes and 14
cooling water intakes along the seafront of the
Table 3.4   Marine Water Quality
Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
|
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW1 |
Wan Chai (Reprovision) |
836188.8 |
815911.1 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Wan |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
C6 |
World Trade Centre |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150.0 |
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
RC1 |
Proposed HKAPA Extension |
835487.7 |
815987.7 |
RC5 |
Sun Hung Kai Centre (Reprovision) |
836291.4 |
816029.7 |
RC7 |
|
837245.2 |
816156.6 |
Remarks: -   The cessation of
seawater intake operation for C6 was confirmed on 17 May 2011, the water
monitoring at C6 was then terminated since 17 May 2011.
        -  WSD9 and WSD17 were implemented with respect
to HK/2009/02 from 8 Feb 2012.
-  4-week water quality monitoring at WSD9,
WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.
-  C8 and C9 were implemented with respect to
HY/2009/19 from 28 Jan 2012.
-  WSD7 and WSD20 water quality monitoring were
temporarily suspended from 27 Apr 2012.
Water Quality Parameters
and frequency
3.3.4.
Monitoring
of dissolved oxygen (DO), turbidity and suspended solids (SS) shall be carried
out at WSD flushing water intakes and cooling water intakes. DO and Turbidity
are measured in-situ while SS is determined in laboratory. 
3.3.5.
In
association with the water quality parameters, other relevant data shall also
be measured, such as monitoring location/position, time, sampling depth, water
temperature, pH, salinity, dissolved oxygen (DO) saturation, weather
conditions, sea conditions, tidal stage, and any special phenomena and work
underway at the construction site etc.
3.3.6.
The
interval between two sets of monitoring should not be less than 36 hours except
where there are exceedances of Action and/or Limit Levels, in which case the
monitoring frequency will be increased. Table
3.5 shows the proposed monitoring frequency and water quality
parameters. Duplicate in-situ
measurements and water sampling should be carried out in each sampling
event. For selection of tides for
in-situ measurement and water sampling, tidal range of individual flood and ebb
tides should be not less than 0.5m.
Table 3.5  Marine Water Quality
Monitoring Frequency and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week
baseline monitoring period |
Three days per week, at
mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine construction works |
Three days per week, at
mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
After completion of marine construction works |
Three days per week, at
mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1. For selection of tides for in-situ measurement and water sampling,
tidal range of individual flood and ebb tides should be not less than 0.5m.
2.
Turbidity should be
measured in situ whereas SS should be determined by laboratory.
Dissolved Oxygen and
Temperature Measuring Equipment
3.3.7.
The
instrument should be a portable, weatherproof dissolved oxygen measuring
instrument complete with cable, sensor, comprehensive operation manuals, and use
a DC power source. It should be capable of measuring:
 -
a
dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation
 -
a
temperature of 0-45 degree Celsius
3.3.8.
It
should have a membrane electrode with automatic temperature compensation
complete with a cable. Sufficient stocks of spare electrodes and cables should
be available for replacement where necessary. (e.g. YSI model 59 meter, YSI
5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved
similar instrument).
3.3.9.
Should
salinity compensation not be build-in in the DO equipment, in-situ salinity
shall be measured to calibrate the DO equipment prior to each DO measurement.
Turbidity Measurement
Instrument
3.3.10
The instrument
should be a portable, weatherproof turbidity-measuring instrument complete with
comprehensive operation manual. The equipment should use a DC power source. It
should have a photoelectric sensor capable of measuring turbidity between 0‑1000
NTU and be complete with a cable (e.g. Hach model 2100P or an approved similar instrument).
Sampler
3.3.11
 /span>Water
sampler comprises a transparent PVC cylinder, with a capacity of not less than
2 litres, and can be effectively sealed with latex cups at both ends. The
sampler should have a positive latching system to keep it open and prevent premature
closure until released by a messenger when the sampler is at the selected water
depth (e.g. Kahlsico Water Sampler or an approved similar instrument).
Sample Container and
Storage
3.3.12
Water samples for suspended solids measurement
should be collected in high-density polythene bottles, packed in ice (cooled to
4°C without being frozen), and delivered to ALS Technichem (HK) Pty Ltd. as
soon as possible after collection for analysis.
Water Depth Detector
3.3.13
A portable, battery-operated echo sounder shall be
used for the determination of water depth at each designated monitoring
station. This unit can either be handheld or affixed to the bottom of the
workboat, if the same vessel is to be used throughout the monitoring programme.
Salinity
3.3.14
A portable salinometer capable of measuring
salinity in the range of 0-40 ppt shall be provided for measuring salinity of
the water at each of monitoring location.
Monitoring Position
Equipment
3.3.15
A hand-held or boat-fixed type digital Global
Positioning System (GPS) with waypoint bearing indication or other equivalent
instrument of similar accuracy shall be provided and used during monitoring to
ensure the monitoring vessel is at the correct location before taking
measurements.
Calibration of In-situ
Instruments
3.3.16
All in-situ monitoring instrument shall be checked,
calibrated and certified by a laboratory accredited under HOKLAS or equivalent
before use, and subsequently re-calibrated at 3 monthly intervals throughout
all stages of the water quality monitoring. Responses of sensors and electrodes
should be checked with certified standard solutions before each use. Wet bulb
calibration for a DO meter shall be carried out before measurement at each
monitoring location.
3.3.17
For the on site calibration of field equipment by
the ET, the BS 127:1993, "Guide to Field and on-site test methods for the
analysis of waters" should be observed.
3.3.18
Sufficient stocks of spare parts should be
maintained for replacements when necessary. Backup monitoring equipment shall
also be made available so that monitoring can proceed uninterrupted even when
some equipment is under maintenance, calibration, etc.
Laboratory Measurement /
Analysis
3.3.19
Analysis of suspended solids has been carried out
in a HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd. Water samples
of about 1L shall be collected at the monitoring stations for carrying out the
laboratory SS determination. The SS determination work shall start within 24
hours after collection of the water samples. The SS determination shall follow
APHA 19ed or equivalent methods subject to the approval of IEC and EPD.
Enhanced Water
Quality Monitoring in the ex-Wan Chai Public Cargo
Working Area
and the
3.3.10. The enhanced water quality monitoring
and audit programme is to avoid aggravation of odour nuisance from seawater
arising from temporary reclamation in the ex-Wan Chai Public Cargo Working Area
and the Causeway Bay Typhoon Shelter.
3.3.11. Dissolved oxygen monitoring at the
intakes C6 and C7 in Causeway Bay Typhoon Shelter when there is temporary
reclamation in Causeway Bay Typhoon Shelter and at the south-western and
south-eastern corners of the ex-Wan Chai Public Cargo Working Area. The
proposed water quality monitoring stations of the Project are shown in Table
3.6 and
Figure 3.1.
Table 3.6   Marine
Water Quality Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior Hotel |
C7 |
|
Ex-WPCWA-SW |
South-western of the ex-Wan Chai Public Cargo
Working Area |
Ex-WPCWA-SE |
South-eastern of the ex-Wan Chai Public Cargo
Working Area |
3.3.12. The monitoring of dissolved oxygen are
to be carried out 3 days per week, at mid-flood and mid-ebb tides for 3 water
depths (1m below water surface, mid-depth and 1m above sea bed, except where
the water depth less than 6m, the mid-depth may be omitted. If the water depth
be less than 3m, only the mid-depth will be monitored).
Daily SS
Monitoring and 24 hours Turbidity Monitoring System
3.3.13. During dredging of the sediment at the
south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of suspended solids and 24 hour
monitoring of turbidity at the cooling water intakes (C6 and C7) shall be conducted.
3.3.14. The 24 hours monitoring of turbidty at the
cooling water intakes (C6 and C7) shall be established
by setting up a continuous water quality monitoring station in front of the
intakes during the dredging activities. 
The monitoring system include the turbidity sensor and data logger which
is capable of data capturing at every 5 minutes.
The data shall
be downloaded daily and compared with the
Action and Limit level determined during the baseline water qualtiy monitoring
at the cooling water intake locations.
Additional Dissovled
oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW
3.3.15
In
response to the Condition 2.18 of the Environmental Permit no. EP-356/2009
requiring that a silt curtain / impermeable barrier system be installed to
channel water discharge flow from Culvert L to locations outside the embayment
area, a proposed replacement of the requirement with additional dissolved
oxygen monitoring has been conducted at three monitoring stations, namely A, B
and C between the eastern seawall of Central Reclamation Phase III and the
HKCEC Extension since November 2011 under EP-356/2009 so that DO level between
the eastern seawall of Central Reclamation Phase II and the HKCEC extension
could be continuously monitored.
3.3.16
The
proposed DO monitoring stations of the Project are shown in Table 3.7
Table 3.7   Marine Water Quality Stations for Additional
DO Monitoring
Station |
Easting |
Northing |
A |
835468 |
815857 |
B |
835572 |
815961 |
C |
835659 |
816271 |
3.3.17
The
monitoring of dissolved oxygen are to be carried out once per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be equal to or less than 3m, only
the mid-depth will be monitored).
4.0.1.
The
environmental monitoring will be implemented based on the division of works
areas of each designed project managed under different contracts with separate
FEP applied by individual contractors. 
Overall layout showing work areas of various contracts, latest status of
work commencement and monitoring stations is shown in Figure 2.1 and
Figure
3.1. The
monitoring results are presented in according to the Individual Contract(s).
4.0.2  The
major work activities for Contract no. HY/2009/11 was confirmed substantial
complete by RSS on 4 January 2012. The FEP surrender application
was submitted to EPD by contractor on 16 Jan 2012 that they would
surrender the permit on 1 Jan 2012. Moreover, the construction site was
handed over to contractor HY/2009/19 on 4 January 2012. However, the surrender
of the FEP for HY/2009/11 withdrew by contractor on 14 February 2012 due to
some outstanding works was confirmed by RSS on 10 Feb 2012.
Therefore, the noise, air and water quality monitoring were keeping in
view for the commencement of the works under this
contract. No construction activity was conducted by HY/2009/11 up to 4 January 2012.
4.0.3  /span>According to
EP-364/2009/A Part B, “Scale and Scope of Designated Project  Remarks (c),”The
permanent and temporary reclamation and associated dredging works related to
the CWB construction are separately covered by environmental permit No.
EP-356/2009 issued to Civil Engineering and Development Department  and
marine piling works to be conducted by the Contractor of Contract no. HY/2009/19
from 28 January 2012 was considered to be governed under EP-356/2009. As the
construction site area of Contract no. HY/2009/11 had already been handed over
to Contract no. HY/2009/19, the designated noise, water and air quality
monitoring stations for Contract no. HY/2009/11 would be shared with Contract
no. HY/2009/19 from 28 January 2012.
4.1.1
Due to adverse weather condition, the noise
monitoring at the following stations were rescheduled:
M1a:
From 24 Jul 2012 to 25 Jul 2012
4.1.2
Due to the equipment repair, the noise monitoring
at M4b and M6 were rescheduled from 23 Aug 2012 to 24 Aug 2012
Contract no. HY/2009/11  Central  
Wanchai Bypass, North Point Reclamation
4.1.1.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December 2011
and the FEP-01/356/2009 was under application of surrender in this reporting
period. The monitoring was temporary suspended since 5 January 2012.
4.1.2.
The
proposed division of noise monitoring stations for Contract no. HY/2009/11 are
summarized in Table 4.1 below:
Table
4.1   Noise Monitoring Stations for Contract no.  /span>HY/2009/11
Station |
Description |
M4b |
Victoria Centre |
M5b |
|
4.1.3.
There
was no exceedance recorded in reporting period. Noise monitoring results
measured in this reporting period are reviewed and summarized. Details of graphical presentation can be
referred in
Appendix 4.1. 
Contract no. HK/2009/01 - Wan Chai
Development Phase II  Central –Wanchai Bypass at HKCEC and Contract no.
HK/2009/02 - Wan Chai Development Phase II  Central  Wan Chai Bypass at
WanChai East and Contract no. HK/2010/06 Wan Chai Development
Phase II  Central-Wan Chai Bypass over MTR Tsuen Wan Line
4.1.4.
The
proposed division of noise monitoring stations are summarized in Table
4.2 below.
Table 4.2   Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02 and HK/2010/06
Station |
Description |
M1a |
Harbour Road Sports Centre |
4.1.5.
There
was no exceedance recorded in reporting period. Details of noise monitoring
results and graphical presentation can be referred in
Appendix 4.1.
Contract no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (
4.1.6.
The
noise monitoring for HY/2009/15 was commenced on 10 November 2010. The proposed division of noise
monitoring stations are summarized in Table 4.3 below.
Table
4.3   Noise Monitoring Station
for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.7.
There was no exceedance recorded
in this reporting period. The
noise complaint was recorded on 5 April 2012. Details of noise monitoring
results and graphical presentation can be referred in
Appendix 4.1
Contract no. HY/2009/19  Central- Wan
Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
4.1.8.
Noise
quality monitoring at M4b and M5b have been implemented with respect to
HY/2009/19 since the marine bore piling work started on 28 Jan 2012.
4.1.9.
The
proposed division of noise monitoring stations for Contract no. HY/2009/19 are
summarized in Table 4.4 below:
    Table 4.4          Noise Monitoring Stations for Contract no.  /span>HY/2009/19
Station |
Description |
M3a |
Tung Lo
Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
|
M6 |
HK |
4.1.10. Three limit level exceedances were
recorded at M6 on 7 and 12 June 2012 and 24 August 2012 during this reporting
quarter. Major traffic jam and no major work activities were observed during
monitoring, the exceedances were considered as non-project related. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of graphical
presentation can be referred in
Appendix 4.1. 
Contract no.
HY/2009/11  Central  Wanchai Bypass, North Point Reclamation and
4.2.1
The major work activities for
Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January
2012. The construction site was handed over to contractor HY/2009/19 on 31
December 2011 and the FEP-01/356/2009 was under application of surrender in
this reporting period. The monitoring was temporary suspended since 5 January
2012.
Table 4.5  Real Time Noise Monitoring
Station for Contract no. HY/2009/11
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section
Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison
Centre |
4.2.2
Real time noise monitoring
results were reviewed and no project-related Action and Limit level exceedance
were recorded in the reporting period. Details of real time
noise monitoring results and graphical presentation can be referred to
Appendix 4.2
Contract no. HY/2009/19  Central- Wan
Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
4.2.3
The
proposed division of real time noise monitoring stations are summarized in Table
4.6 below. Real time noise monitoring for the marine bored piling works
under contract no. HY/2009/19 was commenced on 28 January 2012.
4.2.4
Real-time
noise monitoring at FEHD Hong Kong Transport Section Whitefield Depot commenced
external wall renovation since 1 June 2012
Table 4.6  Real Time Noise Monitoring Station for Contract no. HY/2009/19
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section
Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison
Centre |
4.2.5
Exceedances
were recorded between 0700 and 1900 hours, and 1900 and 2300 hours at RTN1 and
RTN2 throughout July 2012. 
Investigations found that the major noise impacts from 0700 and 1900
hours, and 1900 and 2300 hours were arising from the traffic noise along the
Island Eastern Corridor and demolition works near
4.2.6
Exceedances
were recorded at RTN2 between 0700 and 1900 hours throughout August 2012. Investigations
found that no major noisy activities by the Contractor HY/2009/19 were being
performed. The major noise impact was arising from the demolition works near
 /span>
4.3.1.
Due to extension of site boundary by contractor of
HY/2009/19, location of air monitoring station CMA1b  Oil Street Community
Liaison Centre has been finely adjusted on 21 April 2012.
4.3.2.
Due to lack of electricity supply, the 24-hr TSP
monitoring at the following stations were rescheduled
CMA1b: from 6 Jun to 7 Jun 2012
      
 /span> /span>from 27 Jul and 20 Aug 2012 to 31 Jul and 21
Aug 2012
CMA2a: from 18 Jun to 19 Jun 2012
       
from 27 Jul and 8 Aug 2012 to 28 Jul and 10 Aug 2012
CMA3a: from 10 and 16 Jul to 11 and 18 Jul
2012
CMA5a: from 6 Jun to 7 Jun 2012
        /span>from 4 and 21 Jul to 5 and 24 Jul 2012
       
from 20 Aug to 21 Aug 2012
CMA6a: from 8 Aug 2012 to 9 Aug 2012
4.3.3.
Due to adverse weather condition, the 1-hr TSP
monitoring at the following stations were rescheduled:
CMA2a: from 9 August 2012 to 11 August 2012
Contract no. HY/2009/11  Central  
Wanchai Bypass, North Point Reclamation
4.3.4.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 and the FEP-01/356/2009
was under application of surrender in this reporting period. The monitoring for
the contract was temporary suspended on 6 January 2012.
4.3.5.
The proposed division of air monitoring stations is
summarized in Table 4.7 below.
Table 4.7  Air Monitoring Stations
for Contract no. HY/2009/11
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
|
4.3.6.
No
exceedance was recorded in the reporting period. Details of air monitoring
results and graphical presentation can be referred in
Appendix 4.2.
Contract no. HK/2009/01 - Wan Chai
Development Phase II  Central –Wanchai Bypass at HKCEC
4.3.7.
Air
monitoring was commenced on 1 April 2011 in response to the commencement of the
land-filling work for Contract no. HK/2009/01. The proposed division of air
monitoring stations are summarized in Table 4.8 
below. No exceedance was recorded in the reporting period.
Table 4.8   Air Monitoring Stations for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
CMA6a |
WDII PRE Site Office * |
Contract no. HK/2009/02 - Wan Chai
Development Phase II  Central  Wan Chai Bypass at WanChai East
4.3.8.
Air
monitoring was commenced in mid-January 2011 for the land-filling work for
Contract no. HK/2009/02. The proposed division of air monitoring stations is
summarized in Table 4.9 below. No exceedance was recorded in the
reporting period.
Table 4.9   Air Monitoring Station for
Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (
4.3.9.
Air
monitoring was commenced on 15 March 2011 for the land filling work for
Contract no. HY/2009/15.  /span>The proposed division of
air monitoring stations are summarized in Table 4.10 below. No
exceedance was recorded in the reporting period.
Table
4.10 Air Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB site office at Wanchai
Waterfront Promenade |
Contract no. HY/2009/19 –Central- Wan
Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
4.3.10.
Air monitoring at CMA1b and CMA2a have been
implemented with respect to HY/2009/19 since the marine bore piling works
started on 28 Jan 12. No exceedance was recorded in the
reporting period.
4.3.11.
The proposed division of air monitoring stations is
summarized in Table 4.11 below.
Table 4.11 Air Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
|
4.3.12.
The odour patrol along the odour route with 7
sniffing locations was conducted by a qualified odour patrol member on 9, 27 July
and 13, 23 August 2012 at the concerned hours (afternoon for higher daily
temperature). The odour intensity detected at OP4 was found to be level 2 on 9
and 27 July 2012 which triggered Action Level. After investigation, the
exceedances were likely to be possible in relation to the sewage from outfall
which was considered as not work-related under the Project.
Contract no. HY/2009/11  Central  
Wanchai Bypass, North Point Reclamation
4.4.1.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 on 31 December 2011
and the FEP-01/356/2009 was valid in this reporting period.
4.4.2.
Water quality monitoring for Contract no.
HY/2009/11 was commenced on 19 March 2010. The proposed division of water
monitoring stations for Contract no. HY/2009/11 is summarized in Table
4.12 below:
Table
4.12 Water Monitoring Stations
for Contract no.  /span>HY/2009/11
Station
Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
|
839790.3 |
817032.2 |
Cooling Water Intake |
|||
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
      Remarks:
WSD9, WSD10, WSD15, WSD17. C8 and C9 water monitoring finished on 6 Feb 2012.
Contract no. HK/2009/01 - Wan Chai
Development Phase II  Central –Wanchai Bypass at HKCEC
4.4.3.
Water quality monitoring for Contract no.
HK/2009/01 was commenced on 23 July 2010. The proposed division of water
monitoring stations is summarized in Table 4.13 below.
Table 4.13 Water Monitoring Stations for Contract no. HK/2009/01
Station
Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
Cooling Water Intake |
|||
C1 |
HKCEC
Extension |
835885.6 |
816223.0 |
C2 |
Telecom
House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase
I |
835836.2 |
815910.0 |
C4e |
Wan |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
Remarks:
- The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations have not been carried out by others.
     -  
WSD7 and WSD20 water quality monitoring were temporarily suspended since
27 Apr 2012.
Contract no. HK/2009/02 - Wan Chai
Development Wan Chai Development Phase II  Central  Wan Chai Bypass at WanChai
East
4.4.4.
Water
quality monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010.
The proposed division of water monitoring stations is summarized in Table
4.14 below.
Table 4.14 Water Monitoring Stations for Contract no. HK/2009/02
Station Ref. |
Location |
Easting |
Northing |
|||
WSD Salt Water Intake |
||||||
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
|||
WSD9 |
Sheung Wan |
833415.0 |
816771.0 |
|||
WSD17 |
|
830750.6 |
816030.3 |
|||
Cooling Water Intake |
||||||
C5e |
Sun Hung Kai
Centre (Eastern) |
836250.1 |
815932.2 |
|||
C5w |
Sun Hung Kai
Centre (Western) |
836248.1 |
815933.2 |
|||
Remarks:
-
The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations has not been carried out by others.
-
Water
quality monitoring at WSD9 and WSD 17 was implemented with respect to
HK/2009/02 from 8 Feb 2012.
Contract no. HK/2010/06 - Wan Chai Development
Phase II  Central –Wanchai Bypass over MTR Tsuen Wan Line
4.4.5.
Water
monitoring for Contract no. HK/2010/06 was commenced on 8 March 2011. The
proposed division of water monitoring stations are summarized in Table
4.15 below.
Table
4.15 Water Monitoring Stations
for Contract no. HK/2010/06
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C2 |
Telecom
House |
835647.9 |
815864.4 |
Contract no.
HY/2009/15 - Central-Wanchai Bypass  Tunnel (
4.4.6.
Due to the commencement of the
maintenance dredging on 10 November 2010, water quality monitoring for Contract
no. HY/2009/15 was commenced on 9 November 2010. The proposed division of water
monitoring stations is summarized in Table 4.16 below.
Table
4.16 Water Monitoring Stations for Contract no.
HY/2009/15
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C6 |
Excelsior Hotel |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150 |
Remarks: -    The cessation of seawater intake operation for C6
was confirmed on 17 May 2011, the water monitoring at C6 was then terminated
since 17 May 2011.
Contract no. HY/2009/19  Central- Wan
Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
4.4.7.
Due to the commencement of the marine bored piling
on 28 Jan 2012, water quality monitoring for Contract no. HY/2009/19 was
commenced on 28 Jan 2012. The proposed division of water monitoring stations
are summarized in Table 4.17 below.
Table 4.17  Water
Monitoring Stations for Contract no. HY/2009/19
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident
Garden |
838355.0 |
817116.6 |
      Remarks: C8 and C9 water monitoring
commenced on 28 Jan 2012.
4.4.8.
During the weekly site inspection for HY/2009/15 on
10 July 2012 and further inspection on 11 July 2012, it was found that the
seawall blocks on the south side of TCBR1E (TS1) have been removed before all
dredging works have been completed. The
contractor has immediately surrounded the seawall gap with silt curtains and
stopped the relevant dredging works on 12 July 2012. No action or limit level exceedance was found
during the water quality monitoring on 9 or 11 July 2012. The contractor has promised to provide double
layer silt curtains and geotextile to act as temporary seawall and covered the
sloping seawall with geotextile, and would provide a full incident report. A self water quality monitoring was conducted
on 15 July 2012 to indicate the effectiveness of the double silt curtain layers
and would perform each time during dredging operations. The results from the self water quality
monitoring showed that the suspended solids, turbidity and dissolved oxygen
level outside the double silt curtain layers were not affected by the dredging
activities inside the silt curtain layers.
4.4.9.
Due to a series of celebratory activities relating
to the Anniversary of the Establishment of HKSAR to be held at the HKCEC and
security search conducted at work sites of the HKCEC, the water quality
monitoring at C1, C2, C4e and C4w WQM stations in ebb and flood tides were temporary
suspended on 30 June 2012.
4.4.10.
Due to the adverse weather condition (e.g. Amber
Rainstorm signal or Strong wind signal No.3 or above) were hoisted on 30 June
2012, 5 and 25 July 2012 and 11 and 17 August 2012 , water quality monitoring
at ebb tide were cancelled.
4.4.11.
Due to the adverse weather condition (e.g. Amber Rainstorm
signal or Strong wind signal No.3 or above) was hoisted on 23 July 2012, water
quality monitoring at flood and ebb tide were cancelled.
4.4.12. Based on the joint inspection on 4
Jan 2012 for the NPR area, the 4-week water quality monitoring at WSD9, WSD10,
WSD15, WSD17, C8, C9 to confirm no water deterioration with respect to NPR was
commenced since 7 Jan 2012 and it was completed on 6 February 2012.
4.4.13. Water quality monitoring at WSD10
and WSD15 was temporary suspended while water quality monitoring at WSD9 and
WSD17 was implemented with respect to HK/2009/02 from 8 Feb 12 onwards;
4.4.14. Water quality monitoring at C8 and
C9 have been implemented with respect to HY/2009/19 since the marine bore
piling work started on 28 Jan 12.
4.4.15. Based on the safety concern when
external façade refurbishment was conducted by contractor employed by Provident
Center (C9) between 9 January 2012 to 30 July 2012 which caused to the
inaccessibility of sampling either land and marine since 3 Feb 2012, there is a
fine adjustment of the sampling location of water quality monitoring at C9
since 10 March 2012 to the closest accessible point prior to the completion of
the external façade refurbishment work.
4.4.16. With respect to the trial dredging
at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3 , 11, 13, 15, 17, 19, 20
Apr and 3 May 2012, on-going water quality monitoring results at WSD21 during
this period was checked and indicated that there was no contribution due to the
trial dredging operation. Enhanced review of water quality around WCR2 was
also implemented and no deterioration in the water quality was observed.
4.4.17. Due to the access of water monitoring station at WSD19 was blocked
by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the
inaccessibility of sampling either land and marine, there is a fine adjustment
of the sampling point of WSD 19 since 5 April 2012 to the closest accessible
point prior to the completion of the construction activities.
4.4.18. Due to the dredging works for Cross Harbour Water Mains from
Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary
suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April
2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for
4-week period after the completion of DP6 to confirm no water deterioration.
4.4.19.
As
per the meeting with the representative of Excelsior Hotel and World Trade
Centre on 17 May 2011, they confirmed that the seawater intake for The
Excelsior was no longer in use and replaced by the connected permanent water
supply from WSD pipelines since 11 January 2011. Thus, the impact water quality
monitoring for the cooling intake - C6 was terminated effective from 26 May
2011. 
4.4.20. 24 hours monitoring of turbidity at the cooling water intakes at
C7 was conducted. With respect to the seawall collapsing
at TS4 on 17 November 2011, the 24 hours turbidity monitoring and was kept in
November 2011. Since the reinstating the seawall was completed on 13 January
2012 and no any water deterioration was performed, 24 hour turbidity monitoring
was then suspended on 27 January 2012.
4.4.21.
The
enhanced water quality monitoring at C6, C7, Ex-WPCWA-SW and Ex-WPCWA-SE was
commenced on 13 January 2011.  /span>No
project-related exceedances was recorded in the daily SS monitoring and 24 hours
turbidity monitoring.
4.4.22.
Water
monitoring results measured in this reporting period are reviewed and
summarized in Table 4.18. Details of water quality
monitoring results and graphical presentation can be referred in
Appendix 4.3.
Table 4.18 Summary of Water Quality Monitoring Exceedances in Reporting period
Contract no. |
Water Monitoring
Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished on 6 Feb 2012 |
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
1 |
1 |
0 |
1 |
0 |
0 |
1 |
1 |
0 |
|
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4e |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
0 |
0 |
1 |
0 |
|
|
C4w |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
|
Monitoring finished on 27 April 2012 |
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C5w |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
|
Monitoring started on 8 Feb 2012 |
WSD21 |
0 |
0 |
0 |
1 |
2 |
3 |
2 |
0 |
0 |
0 |
0 |
0 |
|
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
||
|
WSD17
|
0 |
0 |
0 |
0 |
1 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
|
HY/2009/15 |
C7 |
1 |
0 |
0 |
0 |
0 |
0 |
3 |
1 |
0 |
0 |
1 |
0 |
|
HY/2009/19 Monitoring started on 28 Jan 2012 |
C8 |
0 |
0 |
0 |
1 |
0 |
0 |
1 |
0 |
0 |
3 |
1 |
1 |
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
||
Total |
3 |
0 |
0 |
3 |
8 |
3 |
10 |
5 |
0 |
5 |
5 |
2 |
||
Remarks: -    The cessation of seawater intake operation for
C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated
since 17 May 2011.
         /span>-  WSD9 and WSD17 were
implemented with respect to HK/2009/02 from 8 Feb 2012.
-  /span>4-week water quality monitoring at WSD9,
WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.
-   C8 and C9 were implemented with respect to
HY/2009/19 from 28 Jan 2012.
-  
WSD7 and WSD20 were temporarily suspended from 27 Apr 2012
-  
The total number of water exceedances in August had been revised.
4.4.23.
Enhanced
DO monitoring at 4 monitoring stations in Causeway Bay Typhoon Shelter and
Ex-Public Cargo Works Area was conducted three days per week during the
reporting period. The action and limit level exceedances of water quality
monitoring are summarized in Table 4.18a.
4.4.24.
Due
to the enforcement of Amber Rainstorm Warning Signal on 16, 20 and 27 April
2012, the ebb tide Enhanced DO water monitoring on 16, 20 and 27 April 2012
were cancelled. 
Table 4.18a   Summary of Enhanced
Dissolved Oxygen Monitoring Exceedances in Reporting period
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
2 |
0 |
C7 |
3 |
0 |
3 |
2 |
|
Ex-WPCWA SW |
1 |
0 |
0 |
5 |
|
Ex-WPCWA SE |
7 |
2 |
5 |
10 |
|
Total |
11 |
2 |
10 |
17 |
4.4.25.
There
was no exceedance in this reporting period are reviewed and summarized. Details of graphical presentation can be
referred in Appendix 4.3.
Contract no. HY/2009/11  Central  
Wanchai Bypass, North Point Reclamation
4.5.1.
The
major work activities for Contract no. HY/2009/11 was confirmed substantial complete
by RSS on 4 January 2012. Therefore, no C&D waste was generated.
Table 4.19 Details of Waste Disposal for Contract no. HY/2009/11
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
692.255 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Chemical waste disposed, kg |
N/A |
N/A |
N/A |
Marine Sediment (Type 1  Open Sea
Disposal), m3 |
0 (Bulk Volume) |
89,500 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal), m3 |
0  /span>(Bulk
Volume) |
129,200  /span>(Bulk
Volume) |
East of Sha Chau |
4.5.2.
There
was no marine sediment disposed and no dredging work undertaken in the
reporting period. Contractor submitted a letter dated 20 July 2011 to confirm
that the dredging works and dumping operation were completed.
Contract no. HK/2009/01 - Wan Chai Development
Phase II  Central –Wanchai Bypass at HKCEC
4.5.3.
Inert and non-inert C&D waste was disposed of for the site
preparation works in this reporting period. Details of the waste flow table are
summarized in Table 4.20.
Table 4.20 Details of Waste Disposal for Contract no. HK/2009/01
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
175.775 |
22245.42 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
4589.54 |
4979.5 |
N/A |
Non-inert C&D materials disposed, m3 |
190.48 |
942.88 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
11259 |
151143 |
N/A |
Chemical waste disposed, kg |
870 |
7200 |
N/A |
Marine Sediment (Type 1  Open Sea Disposal)
, m3 |
0 |
91164.2 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) , m3 |
0 |
43018 (Bulk Volume) |
East of Cha Chau |
Dredged Sediment Requiring Type 3  Special Treatment / Disposal contained in
Geosynthetic Containers |
0 |
5613 (Bulk Volume) |
East of Cha Chau |
Remarks: Contractor clarified and updated waste flow table for the
reporting month of July
4.5.4.
There
was no marine sediment disposed in the reporting period.
Contract no. HK/2009/02 - Wan Chai Development
Phase II  Central  Wan Chai Bypass at WanChai East
4.5.5.
Inert and non-inert C&D waste was disposed of for the site
preparation works in this reporting period. Details of the waste flow table are
summarized in Table 4.21.
Table 4.21 Details of Waste Disposal for Contract no. HK/2009/02
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
34,168 |
174,298 |
TKO137/ TM 38 |
Inert C&D materials recycled, m3 |
18,161 |
18,161 |
N/A |
Non-inert C&D materials disposed, m3 |
134 |
586 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Chemical waste disposed, kg |
535 |
4,186 |
N/A |
Marine Sediment (Type 1  Open Sea
Disposal), m3 |
NIL |
154,827 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal), m3 |
NIL |
114,464 (Bulk Volume) |
East of Sha Chau |
4.5.6.
There
was no marine sediment disposed in this reporting period.
Contract no. HY/2009/15 -
Central-Wanchai Bypass  Tunnel (
4.5.7.
Inert and non-inert C&D waste was disposed of for the site
preparation works in this reporting period. Details of the waste flow table are
summarized in Table 4.22.
Table 4.22 Details of Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
141579.2 |
Tuen Mun Area 38 |
NIL |
65216 |
TKO137 FB |
|
Inert C&D materials recycled, m3 |
NIL |
184.0 |
To Contract HY/2009/11 |
NIL |
304 |
Ex-PCWA |
|
|
NIL |
111.9 |
TS4 |
Non-inert C&D materials disposed, m3 |
NIL |
252.2 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
NIL |
299361.5 |
N/A |
Chemical waste disposed, kg |
NIL |
8,200 |
N/A |
Marine Sediment (Type 1  Open Sea Disposal)
, m3 |
38,429 |
96,877  /span>(Bulk
Volume) |
South of Cheung Chau |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) , m3 |
20,943 |
207,285  /span>(Bulk
Volume) |
East of Sha Chau |
Marine Sediment (Type 3  Special Treatment
/ Disposal contained in Geosynthetic Containers) |
0 |
7,050 (Bulk Volume) |
East of Sha Chau |
4.5.8.
There
were marine sediments Type 1- Open Sea Disposal, Type 1- Open Sea Disposal
(Dedicate Sites) & Type 2-Confined Marine Disposal dredging from
bore-piling casing in the reporting month.
Contract no.
HK/2010/06 - Wan Chai Development Phase II  Central –Wanchai Bypass over MTR
Tsuen Wan Line
4.5.9.
Inert C&D waste was disposed of for the site preparation works in this
reporting period. Details of the waste flow table are summarized in Table
4.23.
Table 4.23 Details of Waste Disposal for Contract no. HK/2010/06
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
11027.83 |
Tuen Mun Area 38 |
Inert C&D materials recycled, m3 |
266.8 |
266.8 |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled, kg |
366 |
1374.5 |
N/A |
Chemical waste disposed, L |
0 |
600 |
N/A |
Marine Sediment (Type 1  Open Sea Disposal), m3 |
0  /span>(Bulk
Volume) |
3,694 (Bulk Volume) |
South Cheung Chau |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) , m3 |
0 (Bulk Volume) |
12,297 (Bulk Volume) |
|
4.5.10. There was no marine sediment disposed in
the reporting period.
Contract no. HY/2009/19
 Central- WanChai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
4.5.11. There was no project-related waste
disposal in the reporting period.
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
36585.7 |
36585.7 |
Tuen Mun Area 38 |
Inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed, m3 |
55.97 |
55.97 |
N/A |
Non-inert C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical waste disposed, L |
0.29 |
0.29 |
N/A |
Marine Sediment (Type 1  Open Sea Disposal), m3 |
NIL |
NIL |
South Cheung Chau |
Marine Sediment (Type 1  Open Sea Disposal
(Dedicate Sites) & Type 2  Confined Marine Disposal) , m3 |
105 |
105 |
|
5.0.1.
The
Event Action Plan for construction noise, air quality and water quality are
presented in Appendix
5.1.
5.1.1
Three
limit level exceedances were recorded at M6 on 7 and 12 June 2012 and 24 August
2012 during this reporting quarter. Major traffic jam and no major work
activities were observed during monitoring, the exceedances were considered as
non-project related. Noise monitoring results measured in this reporting period
are reviewed and summarized. Details of
graphical presentation can be referred in
Appendix 4.1. 
5.2.1
Exceedances
were recorded at RTN1 and RTN2 between 0700 and 1900 hours, and 1900 and 2300
hours throughout the July reporting month. 
Investigations found that the major noise impacts from 0700 and 1900
hours, and 1900 and 2300 hours were arising from the traffic noise along the
Island Eastern Corridor and demolition works near
5.2.2
Exceedances
were recorded at RTN2, between 0700 and 1900 hours throughout the August reporting
month. Investigations found that no
major noisy activities by the Contractor HY/2009/19 were being performed. The
major noise impact was arising from the demolition works near
5.3.1.
No
exceedance was recorded in the reporting period.
5.4.1.
The
summary of water quality exceedances recorded in reporting period is presented
in the Table 5.1 and Table 5.1a.
Table 5.1  Summary of Water Quality Monitoring
Exceedances in Reporting period
Contract no. |
Water Monitoring
Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring
finished on 6 Feb
2012 |
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
1 |
1 |
0 |
1 |
0 |
0 |
1 |
1 |
0 |
|
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4e |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
0 |
0 |
1 |
0 |
|
|
C4w |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
|
Monitoring
finished on 27 April 2012 |
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C5w |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
|
Monitoring
started on 8 Feb
2012 |
WSD21 |
0 |
0 |
0 |
1 |
2 |
3 |
2 |
0 |
0 |
0 |
0 |
0 |
|
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
||
|
WSD17 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
|
HY/2009/15 |
C7 |
1 |
0 |
0 |
0 |
0 |
0 |
3 |
1 |
0 |
0 |
1 |
0 |
|
HY/2009/19 Monitoring started on 28 Jan 2012 |
C8 |
0 |
0 |
0 |
1 |
0 |
0 |
1 |
0 |
0 |
3 |
1 |
1 |
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
||
Total |
3 |
0 |
0 |
3 |
8 |
3 |
10 |
5 |
0 |
5 |
5 |
2 |
||
Remarks: -    The cessation of seawater intake operation
for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then
terminated since 17 May 2011.
         /span>-   /span>WSD9 and WSD17 were implemented with respect
to HK/2009/02 from 8 Feb 2012.
-  4-week
water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed
on 6 Feb 2012.
-   C8 and C9 were implemented with respect to
HY/2009/19 from 28 Jan 2012.
-   WSD7
and WSD20 were temporary suspended since 27 April 2012
-   The
total number of water exceedance in August had been reviewed.
5.4.2.
All
exceedances in Table 5.1 have been investigated and there was no
project-related exceedance.
Table 5.1a    Summary of Enhanced Dissolved Oxygen
Monitoring Exceedances in Reporting period
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
2 |
0 |
C7 |
3 |
0 |
3 |
2 |
|
Ex-WPCWA SW |
1 |
0 |
0 |
5 |
|
Ex-WPCWA SE |
7 |
2 |
5 |
10 |
|
Total |
11 |
2 |
10 |
17 |
5.5.1.
There
was non-compliance from the site audits in the reporting month of August 2012 in
Contract HY/2009/15. During environmental site inspections conducted during the
reporting period, minor deficiencies were noted.
5.6.1
During the reporting month of August 2012,
contractor of HY/2009/15 has failed to demonstrate compliance with the conditions
set in FEP-04/356/2009 and relevant conditions  /span>in EP-356/2009 for the temporary reclamation
removal operations at TCBR1E (TS1).  /span>Contractor
was unable to provide a proper method statement with respect to the change in
works circumstance, and the Contractor was unable to effectively mitigate the
impact due to non-compliance such that muddy boom recurrence occurred and dispersed into
5.7.2
As removal dredging and barge mooring operations
were anticipated to be performed at the southern side of TS1, ETL requested
that daily self water quality tests during removal dredging operations, also
pilot test for mooring operations, to demonstrate the effectiveness of the
mitigation measures during the operation and to demonstrate the operation
itself would not cause substantial water quality impact, should be performed
before the mooring operations. These
tests were requested to prove whether conditions set in FEP-04/356/2009 and
relevant conditions EP-356/2009 are fully complied.
5.7.3
Water samplings for self water quality tests were
collected at locations inside and outside the silt curtains during removal
dredging operations. This was to
demonstrate whether the double silt curtains could
effectively hold back silty water during removal dredging operations.
5.7.4
Water samplings for pilot test were collected
inside and outside the double silt curtains before and after the mooring
operations. This was to demonstrate
whether the double silt curtains could effectively hold back silty water during
removal mooring operations, and if high turbid would be generated during the
mooring operations.
5.7.5
On 15 July 2012, a successful self water quality
test was performed by the contractor.
5.7.6
Pilot tests were carried out on 27 July, 2, 7 and
20 Aug 2012 to demonstrate the compliance of barge mooring operations with the
conditions set in FEP-04/356/2009 and EP-356/2009, but none of the pilot test
was successful. 
5.7.7
It is concluded that the self water quality tests
proved the effectiveness of the mitigation measures, but the pilot tests were a
failure and the contractor cannot demonstrate their ability to comply with the
conditions set in FEP-04/356/2009 and EP-356/2009.
5.7.8
ETL then strongly recommended the Contractor to
follow the following points for future activities. First, the Contractor should request for RSS
inspections for confirmation of implementation of mitigation measures before
any commencement of work activities that are governed by the EP. Second, if there is any site mitigation measure
not confirmed by RSS for fulfilling the agreed method statements, contractor
shall not commence any environmentally sensitive construction activities (e.g.
dredging, filling, mooring or any works related to temporary reclamation)
unless such site mitigation measures have been properly reviewed by both ET and
IEC. Third, the revised site mitigation
measures should be reviewed and consented by both ET and IEC before
implementation.
5.7.9
The Contractor and RSS agreed on the above points
and the Contractor submitted Investigation Report regarding the incident at
TS1, Rectification Plan, Preventive Action Plan and revised Method Statement on
7 September 2012.
.
6.0.1.
There
was one water impact complaint received in this reporting period.
6.0.2.
The details of cumulative complaint log and summary
of complaints are presented in
Appendix 6.1.
6.0.3.
No notification of summons
or prosecution was received in the reporting period. Cumulative statistic on complaints and successful
prosecutions are summarized in Table 6.1 and Table 6.2 respectively.
Table 6.1  Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works
(Mar 2010) to last reporting period |
26 |
June
2012- August 2012 |
1 |
Project-to-Date |
27 |
Table 6.2  Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1.
According to Condition 3.4 of the EP-356/2009, this
section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation
Phase III, Central-Wanchai Bypass and Island Eastern Corridor Link projects.
7.0.2.
According to the Monthly EM&A report (July 2012) of
Central Reclamation Phase III (CRIII), drainage work, building construction
works and pipe works were performed in the reporting period. The water
quality monitoring was completed in October 2011 and no exceedance was recorded
for air and noise monitoring. It can be concluded that cumulative construction
impact due to the concurrent activities of the current projects with the
Central Reclamation Phase III (CRIII) was insignificant.
7.0.3.
According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activities at Reclamation Shoreline Sub-zones
under Wan Chai Development Phase II were the dredging and filling at HKCEC3w,
dredging at submarine sewage pipelines, reinstatement of seawall block
construction at TCBR1W and marine bored piling at MTR Tunnel Crossing in the
reporting month. The major environmental impact was water quality impact at
North Point,
7.0.4.
The major environmental impacts generated from the reclamation
work at Central Reclamation Phase III were only located along the coastline of
Central and Admiralty. As no project related exceedance was recorded in the
Project, it was considered no adverse environmental impact caused by the
Project works. Thus, it is evaluated the cumulative construction impact was
insignificant.
8.0.1.
The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
8.0.2.
One non-compliance
was noted and no prosecution was received during the reporting period.
8.0.3.
The
construction programmes of individual contracts are provided in
Appendix 7.1.