Contract No: HK/2011/07

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 2)

 

Environmental Permit no. EP-356/2009,

Further Evironmental permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009, fep-05/356/2009,

 Fep-06/356/2009 and FEP-07/356/2009

 

Quarterly Environmental Monitoring
and Audit Report

 

- June 2013 to August 2013 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

CHECKED by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

27 September 2013


Table of contents

 

EXECUTIVE SUMMARY. 4

1.     Introduction. 13

1.1        Scope of the Report 13

1.2        Structure of the Report 13

2.     Project Background. 14

2.1        Background. 14

2.2        Scope of the Project and Site Description. 14

2.3        Division of the Project Responsibility. 15

2.4        Project Organization and Contact Personnel 16

2.5        Principal Work and Activities. 19

3.     Monitoring Requirements. 25

3.1.       Noise Monitoring. 25

3.2.       Air Monitoring. 26

3.3.       Water Quality Monitoring. 29

4.     Monitoring Results. 35

4.1.       Noise Monitoring Results. 35

4.2.       Real Time Noise Monitoring Results. 36

4.3.       Air Monitoring Results. 37

4.4.       Water Monitoring Results. 39

4.5.       Waste Monitoring Results. 45

5.     Compliance Audit. 50

5.1.       Noise Monitoring. 50

5.2.       Real-time Noise Monitoring. 50

5.3.       Air Monitoring. 50

5.4.       Water Quality Monitoring. 50

5.5.       Site Audit 52

5.6.       Review of the Reasons for and the Implications of Non-compliance. 52

5.7.       Summary of action taken in the event of and follow-up on non-compliance. 52

6.     Complaints, Notification of Summons and Prosecution. 52

7.     Cumulative Construction Impact due to the Concurrent Projects. 54

8.     Conclusion. 54


lIST OF TABLES

 

Table I              Principal Work Activities for Contract no. HK/2009/01

Table II             Principal Work Activities for Contract no. HK/2009/02

Table III            Principal Work Activities for Contract no. HY/2009/15

Table IV           Principal Work Activities for Contract no. HK/2010/06

Table V            Principal Work Activities for Contract no. HY/2009/19

Table VI           Principal Work Activities for Contract no. HK/2012/08

Table 2.1          Schedule 2 Designated Projects under this Project

Table 2.2          Details of Individual Contracts under the Project

Table 2.3          Contact Details of Key Personnel

Table 2.4          Principal Work Activities for Contract no. HK/2009/01

Table 2.5          Principal Work Activities for Contract no. HK/2009/02

Table 2.6          Principal Work Activities for Contract no. HY/2009/15

Table 2.7          Principal Work Activities for Contract no. HK/2010/06

Table 2.8          Principal Work Activities for Contract no. HY/2009/19

Table 2.9I         Principal Work Activities for Contract no. HK/2012/08

Table 3.1          Noise Monitoring Stations

Table 3.2          Real Time Noise Monitoring Station

Table 3.3          Air Monitoring Stations

Table 3.4          Marine Water Quality Stations for Water Quality Monitoring

Table 3.5          Marine Water Quality Monitoring Frequency and Parameters

Table 3.6          Marine Water Quality Stations for Enhanced Water Quality Monitoring

Table 3.7          Marine Water Quality Stations for Additional DO Monitoring

Table 4.1          Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02 and HK/2010/06

Table 4.2          Noise Monitoring Station for Contract nos. HY/2009/15

Table 4.3          Noise Monitoring Stations for Contract no.  HY/2009/19

Table 4.4          Real Time Noise Monitoring Station for Contract no. HY/2009/11 and HY/2009/19

Table 4.6          Air Monitoring Stations for Contract no. HK/2009/01

Table 4.7          Air Monitoring Station for Contract no. HK/2009/02

Table 4.8          Air Monitoring Station for Contract no. HY/2009/15

Table 4.9          Air Monitoring Stations for Contract no. HY/2009/19

Table 4.10        Water Monitoring Stations for Contract no.  HY/2009/11

Table 4.11        Water Monitoring Stations for Contract no. HK/2009/01

Table 4.12        Water Monitoring Stations for Contract no. HK/2009/02

Table 4.13        Water Monitoring Stations for Contract no. HK/2010/06

Table 4.14        Water Monitoring Stations for Contract no. HY/2009/15

Table 4.15        Water Monitoring Stations for Contract no. HY/2009/19

Table 4.15a      Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting period

Table 4.16        Summary of Water Quality Monitoring Exceedances in Reporting period

Table 4.17        Details of Waste Disposal for Contract no. HK/2009/02

Table 4.18        Details of Waste Disposal for Contract no. HK/2009/01

Table 4.19        Details of Waste Disposal for Contract no. HK/2009/02

Table 4.20        Details of Waste Disposal for Contract no. HY/2009/15

Table 4.21        Details of Waste Disposal for Contract no. HK/2010/06

Table 4.22        Details of Waste Disposal for Contract no. HY/2009/19

Table 5.1          Summary of Water Quality Monitoring Exceedances in Reporting period

Table 5.1a        Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting period

Table 6.1          Cumulative Statistics on Complaints

Table 6.2          Cumulative Statistics on Successful Prosecutions

 

 

 

 

 

 

lIST OF FIGUREs

 

Figure 2.1         Project Layout

Figure 2.2         Project Organization Chart

Figure 3.1         Locations of Environmental Monitoring Stations

 

 

 

 

lIST OF APPENDIces

 

Appendix 2.1    Environmental Mitigation Implementation Schedule

Appendix 3.1    Action and Limit Level

Appendix 4.1    Noise Monitoring Graphical Presentations

Appendix 4.2    Air Quality Monitoring Graphical Presentations

Appendix 4.3    Water Quality Monitoring Graphical Presentations

Appenidx 4.3a   Additional Dissolved Oxygen Monitoring Results

Appendix 4.4    Real-time Noise Monitoring Results and Graphical Presentations

Appendix 5.1    Event Action Plans

Appendix 6.1    Complaint Log

Appendix 7.1    Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

  1. This is the Quarterly Environmental Monitoring and Audit (EM&A) Report – June 2013 to August 2013 prepared for the Project of Wan Chai Development Phase II and Central-Wanchai Bypass under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-05/356/2009, FEP-06/356/2009 and FEP-07/356/2009. This report presents the environmental monitoring and audit findings and information during the period from June 2013 to August 2013. The cut-off date of reporting is at 27th of each reporting period.

 

Construction Activities for the Reported Period

  1. During this reporting period, the principal work activities for Contract no. HK/2009/01 are summarized as below:

Table I        Principal Work Activities for Contract no. HK/2009/01

June 2013

July 2013

August 2013

Marine Works (at Wan Chai)

Ÿ Construction of mass concrete coping for new seawall together with the construction of chamber/ manhole for proposed box culvert extension.

Ÿ Installation of ELS for construction of proposed box culvert Bay 8 and Bay 9.

Ÿ Prefabrication of steel bridge on the top of temporary open channel along Convention Avenue.

Ÿ Mitigation measures such as widening the waterway at reclamation area “HKCEC3E”, installation of pumps and water pipe for pumping seawater from Victoria Harbour to temporary water channel were implemented to enhance the seawater circulation for lower the seawater temperature at the temporary water channel.

Ÿ Dumping of ice blocks into temporary water channel to cool down the seawater at the temporary water channel.

 

Cross-Harbour Watermains Installation (CHA & CHB) and Marine Works (at TST)

Ÿ Defect rectification works for submarine pipeline A (removal of silt).

Ÿ Defect rectification works for submarine pipeline B (removal of silt).

Ÿ CCTV / photo inspection to the submarine pipeline B.

Ÿ Testing of ICCP monitoring system for new provided cross harbour watermain.

 

Cooling Watermains, Salt Watermains and Sewer (On Land)

Ÿ Mainlaying works at Zone B6-2A, B6-4, B6-6, A1-5C, A3-3C, C1-2 and X2-1.

Ÿ Mainlaying works in Zone B6-2A and B6-4.

Ÿ Mainlaying works in Zone B6-1B at north of HKCEC area.

Ÿ Mainlaying works in Zone B6-5C & B6-6 at west of HKCEC area.

Ÿ Mainlaying works in Zone A1-5C.

Ÿ Mainlaying works at Zone C1-2.

Ÿ Relocation of fire hydrant in Zone X2-1.

Ÿ Temporary ducting and cabling works at junction between Expo Drive East and Expo Drive Central.

 

E & M

Ÿ Full commissioning test for Cooling Water Pumping Station P5.

Ÿ Trial operation of the new provided cooling system P5.

 

Marine Works (at Wan Chai)

Ÿ Rockfilling at the northern part of HKCEC3E (East of HKCEC) between CH290 and CH385.

Ÿ Structural blinding for construction of proposed box culvert Bay 8 and Bay 9 was poured and dewatering and grouting curtain wall.

Ÿ Pre-drilling work for steel bridge on the top of temporary open channel along Convention Avenue.

Ÿ 4 nos. of drill holes for D-wall and pre-bored H-piles in stage 3.

Ÿ Mitigation measures such as widening the waterway at reclamation area “HKCEC3E”, installation of pumps and water pipe for pumping seawater from Victoria Harbour to temporary water channel to enhance the seawater circulation for lower the seawater temperature at the temporary water channel.

Ÿ Dumping of ice blocks into temporary water channel to cool down the seawater at the temporary water channel.

 

Cross-Harbour Watermains Installation (CHA & CHB) and Marine Works (at TST)

Ÿ Minor defect rectification works for submarine pipeline A and B (removal of silt). WSD accepted the rectification work.

Ÿ Testing of ICCP monitoring system and SCADA for new provided cross harbour watermain was carried out with WSD. Damaged isolation joints would be delivered to HK in mid Aug 2013.

 

XHWM, Cooling Watermains, Salt Watermains and Sewer (On Land)

Ÿ XHWM-Stage 1 connection. Stage 2 and 3 would be connected.

Ÿ Pipework for Additional Washout Chamber at VIP drop-off and the excavation and shoring for the structure.

Ÿ Reinstatement works at B6-2B at Northwest of HKCEC.

Ÿ Planter reinstatement, kerbworks, hard paving at West Foyer of HKCEC.

Ÿ Sewer laying works in Zone B6-2A, B6-4, B6-6 B6-5C & B6-6 at west of HKCEC area.

Ÿ Cooling main works in Zone C1-2.

Ÿ Salt watermain laying works in Zone A1-5C.

Ÿ Salt watermain laying works in Zone A3-5C.

Ÿ Salt watermain laying works in Zone A3-1, A5-2 and A1-5C.

Ÿ Salt watermain laying works in A4-1B, 2B.

Ÿ Temporary ducting and cabling works at junction between Expo Drive East and Expo Drive Central. Another work front at night.

 

Tunnel Works

Ÿ Installation of pre-bored H-pile in CWB Stage 1 underneath Atrium Link (from CH80 to CH120).

Ÿ Installation of pre-bored H-pile in CWB Stage 2 Atrium Link (from CH120 to CH220).

Ÿ Construction of bulkhead wall at CH3129 (18 panels).

Ÿ Filling of the existing open water channel at CH260.

Ÿ Construction of the Common D-wall.

Ÿ Demolition of the Promenade Deck.

Ÿ Installation of dewatering wells, observation wells and piezometers at CWB Stage 1.

 

E & M

Ÿ Operation attendance of 60 day.

Ÿ Switchover for cooling system P5.

Ÿ The old pumping house for EMSD and CP.

Marine Works (at Wan Chai)

Ÿ Rockfilling at the northern part of HKCEC3E (Ease of HKCEC) between CH290 and CH385

Ÿ Dewatering for Bay 8.

Ÿ Pre-drilling work for steel bridge on the top of temporary open channel along Convention Avenue. Installation of casing of the 4th out of 5 nos. pre-bored H-piles. Preparation work for main beam connection.

Ÿ 3 nos. out of 4 nos. drill holes for LSD D-wall in stage 3. 

Ÿ Changed over of P7 and P9 pumping station by others. Placing ice and pumping of water to intake area.

 

Cross-Harbour Watermains Installation (CHA & CHB) and Marine Works (at TST)

Ÿ All defects were rectified and Stage 2 /3 connection.

Ÿ Damaged isolation joints were replaced on 17 Aug. 2013. However, additional anode maybe required since there was still electrical contamination between the new pipe and existing pipeline.

 

XHWM, Cooling Watermains, Salt Watermains and Sewer (On Land)

Ÿ Pipework for Additional Washout Chamber at VIP drop-off. Reinstatement works at B6-2B at Northwest of HKCEC. Reinstatement of roadworks at West Foyer of HKCEC. Planter reinstatement, kerbworks, hard paving.  

Ÿ Cooling main works in Zone C1-2.

Ÿ Salt watermain laying works in Zone A1-5C. Salt watermain laying works in Zone A3-5C. Salt watermain laying works in Zone A3-1, A5-2. Salt watermain laying works in A4-1B, 2B.

Ÿ Relocation works of fire hydrant in Zone X2-1.

Ÿ Temporary ducting and cabling works at junction between Expo Drive East and Expo Drive Central.

 

Tunnel Works

Ÿ Installation of pre-bored H-pile in CWB Stage 2 Atrium Link (from CH120 to CH220).  23 nos. pre-bored H-piles had been excavated. 6 nos. pre-bored H-piles.

Ÿ Construction of Common D-wall. Works was slow until BC cutter back on site.

Ÿ Filling of the existing open water channel from CH100 to CH206.

Ÿ Demolition of the Promenade Deck , delayed by MOE matters.

Ÿ ELS at bottom-up area.  Fabrication of steel strutting members ..

 

E & M

Ÿ Operation attendance at Pumping Stations of 60 days.

 

 

  1. During this reporting period, the principal work activities for Contract no. HK/2009/02 are summarized as below:

Table II       Principal Work Activities for Contract no. HK/2009/02

June 2013

July 2013

August 2013

Ÿ Modification work of PTI at Expo Drive East.

Ÿ Modification of existing covered walkway along Expo Drive East.

Ÿ Remedial works for P7 & P8 were in progress at WCR1 area.  All 4 nos. pile cap construction. Mainlaying works for rectifying the subsided intake pipes for SHK cooling water system and the thrust block.  Mainlaying works for GE/HC cooling water system and the thrust block.

Ÿ Concreting of thrust block for the rectifying the P9 cooling watermains and remaining pressure test for rectifying the P9 cooling watermains. Initial Testing/Commissioning & waiting period for switching over.

Ÿ Major E&M works and their T&C in Cooling Water Pumping Stations P7, P8 and P9.

Ÿ Utility diversion for the outstanding DAV Chamber for P9 intake mains at Harbour Road (CHAI425m).

Ÿ Wall and top slab at Bay 2B of Salt Water Intake Culvert.

Ÿ Base slab, wall & top slab of Bay 1B of Salt Water Intake Culvert.

Ÿ Installation of stoplog and preliminary screen at Bay 2A.

Ÿ Water leakage test between Bay 3 and Bay 8.

Ÿ Mainlaying works for DN800 salt watermains (CHS8A) at Ex-Pet Garden except the remaining Y-section near the connection with existing system at Hung Hing Road.  Concreting of thrust block between CH150 – CH160, the temporary discharge point between CH150 – CH160 and backfilling work near Gate No.1.

Ÿ The remaining ABWF works in WSD Salt Water Pumping Station, including maintenance platform and external finishes.

Ÿ Dry tests at WSD Salt Water Pumping Station. Wet test after completion of the proposed intake culvert.

Ÿ Final fitting out for the DSD Pumping Station boundary wall at Hung Hing Road.

Ÿ Sheet pile cutting works at Bay5 / Bay 6 interface for subsequent construction of water plug beneath the installed precast unit (Bay 6)

 

Ÿ Modification work of PTI at Expo Drive East.

Ÿ Modification of existing covered walkway along Expo Drive East.

Ÿ The first and second attempt of full commissioning of P9 cooling water system.

Ÿ Minor remedial works for commissioning for both P7 and P8 cooling water system.-

Ÿ The wall and top slab at Salt Water Intake Culvert Bay 1B.

Ÿ Installation of guide rails for preliminary screens of Salt Water Intake Chamber No.1 at Bay 2A.

Ÿ The leakage test of stoplogs..

Ÿ The base slab of proposed wash out chamber near CHS8A160.

Ÿ The pipe laying work near the proposed connection point.

Ÿ The remaining ABWF works in WSD Salt Water Pumping Station, including maintenance platform and external finishes.

Ÿ Dry tests at WSD Salt Water Pumping Station. Wet test after completion of the proposed intake culvert.

Ÿ Sheet pile cutting works at Bay5 / Bay 6 interface and excavation down to the formation level for subsequent construction of water plug.

Ÿ The diver works between Bay 5 and the installed precast unit (Bay 6).

Ÿ The modification work for both east and west wings of staircase ST-01 landing.

Ÿ Counterweight installation for movable ramp.

Ÿ Installation of landing door for the disabled lift and glass installation.

Ÿ Last panel (BHC12) of Eastern Bulkhead Wall. 

Ÿ Interface coring and shear pin installation for the Eastern Bulkhead Wall.

Ÿ The road modification works along Wan Shing Street for HHR Flyover Diversion (Stage 1).

Ÿ Placing wearing course along in fount of Gammon Entrance No. 1 and road making.

Ÿ Breaking up the existing pavement and disposal for extract sheetpile next to ECO gas filling station.

Ÿ Rockfilling by Grade 400 at WCR4 and Grade 200 rockfilling works..

Ÿ Placing geotextile at TWCR4.

Ÿ Seawall blocks installation at WCR4 & TWCR4.

 

Ÿ Modification of existing covered walkway along Expo Drive East.

Ÿ The full commissioning of P7, P8 and P9 cooling water system.

Ÿ The 60 days for T&C period of P9 cooling water system.

Ÿ Backfilling works for the trench of P7 and P8 cooling water system remedial works area.

Ÿ Fresh water pipeworks had been completely laid to P7, P8 and P9 Cooling Water Pumping Station.

Ÿ Demolish of abandoned P8 Cooling Water Pumping Station.

Ÿ Installation of stoplog and its leakage test in SWIC.

Ÿ Installation of Aeration and Chlorination Pipes at Salt Water Intake Culvert Bay 2 to Bay 5.

Ÿ The lower part of the wall for proposed wash out chamber near CHS8A160.The fabrication works for DN800 temporary discharge pipe on Site.

Ÿ All DN800 watermains at Ex-pet Garden except the Y-section connecting with the existing DN600 watermains at Hung Hing Road. The pipe cleaning and water pressure test for the laid section.

Ÿ The excavation works at the Y-section connecting with the existing DN600 watermains at Hung Hing Road.

Ÿ The remaining ABWF works and boundary wall in WSD Salt Water Pumping Station , including maintenance platform and external finishes.

Ÿ The water plug at Bay5 / Bay 6 interface and the subsequent dewatering.

Ÿ Sheet pile cutting works between Bay 5 and Bay 6.

Ÿ The formwork erection for the base slab at Bay 5 and the rebar fixing .

Ÿ Construction of stoplog chamber extension at Bay 6.

Ÿ The modification work for both east and west wings of staircase ST-01 landing. Installation of glass panels for the disabled lift.

Ÿ Excavation for the 6 nos. Temporary Covered Walkway in the vicinity of Ferry Pier and their blinding layer.

Ÿ The road modification works along Wan Shing Street for HHR Flyover Diversion (Stage 1).

Ÿ Breaking up the existing pavement and disposal for extract sheetpile next to ECO gas filling station.

Ÿ Removing the extract sheetpile between ECO gas fill station and Wan Yan Street .

Ÿ Pavement works at Wan Shing Street near HK Yatch Club.

Ÿ Rockfilling by Grade 400 and Grade 200 at WCR4/TWCR4, all rockfilling works. Leveling stone installation along the temporary seawall.

Ÿ Seawall blocks installation at WCR4/TWCR4.

 

 

  1. Contract no. HY/2009/15 was commenced on 10 November 2010. During this reporting period, the principal work activities for Contract no. HY/2009/15 are summarized as below:

Table III      Principal Work Activities for Contract no. HY/2009/15

June 2013

July 2013

August 2013

Ÿ Removal of eastern breakwater of CBTS

Ÿ Installation of temporary wave protection barrier at eastern breakwater

Ÿ Temporary works for EVA

 

Ÿ Construction of EVA

 

Ÿ Construction of EVA

 

 

  1. Contract no. HK/2010/06 was commenced on 22 March 2011. During this reporting period, the principal work activities for Contract no. HK/2010/06 are summarized as below:

Table IV     Principal Work Activities for Contract no. HK/2010/06

June 2013

July 2013

August 2013

Ÿ Sheet piling works

Ÿ Utility diversion works

Ÿ Road resurfacing works

Ÿ Road opening works

 

Ÿ Sheet piling works

Ÿ Utility diversion works

Ÿ Road resurfacing works

 

Ÿ Pre-cast installation support works

 

 

  1. Contract no. HY/2009/19 was commenced on 24 March 2011. During this reporting period, the principal work activities for Contract no. HY/2009/19 are summarized as below:

Table V      Principal Work Activities for Contract no. HY/2009/19

June 2013

July 2013

August 2013

Ÿ Construction works for Box Culvert T1

Ÿ Construction works for Culvert U1

Ÿ Demolition of parapet at IEC Link

Ÿ Construction of dewatering well for Cut & Cover Tunnel

Ÿ Removal of marine platform

Ÿ Construction of pile cap, column & cross head (Marine)

Ÿ ELS for Cut & Cover Tunnel

Ÿ Laying of 1500f pipe

Ÿ Launching of segments

Ÿ Unloading segments from derrick

Ÿ Extraction of temporary pile from marine section

 

 

Ÿ D-wall and Barrette Construction

Ÿ Construction works for Box Culvert T1

Ÿ Construction works for Culvert U1

Ÿ Demolition of parapet at IEC Link

Ÿ Construction of dewatering well for Cut & Cover Tunnel

Ÿ Removal of marine platform

Ÿ Construction of pile cap, column & cross head (Marine)

Ÿ ELS for Cut & Cover Tunnel

Ÿ Laying of 1500f pipe

Ÿ Launching of segments

Ÿ Unloading segments from derrick

Ÿ Extraction of temporary pile from marine section

 

Ÿ Road works at Watson Road

Ÿ D-wall and Barrette Construction

Ÿ Construction works for Box Culvert T1

Ÿ Construction works for Box Culvert U1

Ÿ Demolition of parapet at IEC Link

Ÿ Removal of marine platform

Ÿ Construction of pile cap, column & cross head (Marine)

Ÿ Installation of dewatering well

Ÿ Laying of 1500f pipe

Ÿ Launching of segments

Ÿ Extraction of temporary pile from marine section

Ÿ Installation of temporary lighting at IEC link commenced

Ÿ Construction of bridge truss TA1 commenced

Ÿ Breaking of barrette piles at Cut & Cover tunnel commenced

Ÿ Demolition of parapet at IEC link

  1. Contract no. HK/2012/08 was commenced on March 2013. During this reporting period, the principal work activities for Contract no. HK/2012/08 are summarized as below:

Table VI     Principal Work Activities for Contract no. HK/2012/08

June 2013

July 2013

August 2013

Ÿ Site preparation works

Ÿ Site survey

Ÿ Marine ground investigation

Ÿ ELS for box culvert La at Lung King Street

Ÿ Dredging

Ÿ Demolition of the existing Expo Drive West Bridge

 

Ÿ Site preparation works

Ÿ Site survey

Ÿ Marine ground investigation

Ÿ ELS for box culvert La at Lung King Street

Ÿ Dredging

Ÿ Demolition of the existing Expo Drive West Bridge

 

Ÿ Site preparation works

Ÿ Site survey

Ÿ ELS for box culvert La at Lung King Street

Ÿ Dredging

Ÿ Demolition of the existing Expo Drive West Bridge

 

 

 

Noise Monitoring

  1. Noise monitoring during day time and evening time were conducted at the M1a, M2b, M3a, M4b, M5b and M6 on a weekly basis in the reporting period. The Action and Limit level exceedances recorded in the reporting period are listed below. Investigation found that exceedances were not related to the Project. Investigation found that exceedances were not related to the Project.
  2. Seven limit level exceedances were recorded at M6 on 3, 13 June, 9, 16 July, 6, 20 and 27 August 2013. The limit level exceedances were considered as non-project related.
  3. Due to adverse weather condition, the noise monitoring at the following stations were rescheduled:

M1a: From 11 June 2013 to 14 June 2013

M2b: From 11 June 2013 to 14 June 2013 and from 13 Aug 2013 to 15 Aug 2013

M3a: From 11 June 2013 to 13 June 2013 and from 13 Aug 2013 to 15 Aug 2013

M4b: From 11 June 2013 to 13 June 2013 and from 13 Aug 2013 to 15 Aug 2013

M5b: From 11 June 2013 to 13 June 2013 and from 13 Aug 2013 to 15 Aug 2013

M6:  From 11 June 2013 to 13 June 2013 and from 13 Aug 2013 to 15 Aug 2013

 

Real-time Noise Monitoring

  1. As the land-based piling and filling works- DP3 at Tin Hau had been completed on 3 September 2012 and confirmed by RSS, the real-time noise monitoring results at FEHD Hong Kong Transport Section Whitfield Depot was excluded under EP-356/2009 since 28 November 2012.
  2. Real-time noise monitoring at FEHD Hong Kong Transport Section Whitefield Depot and Oil Street Community Centre have been commenced on 5 October 2010 for the filling works of Contract no. HY/2009/11.
  3. Real-time noise monitoring at FEHD Hong Kong Transport Section Whitefield Depot commenced external wall renovation since 1 June 2012
  4. Oil Street Community Liaison Centre was confirmed to be demolished in mid-October by CWB RSS.  This presented a need for relocation of RTN2 – Oil Street Community Liaison Centre.  After liaison with Hong Kong Electric, permission was granted on 21 Sep 2012 for real time noise monitoring set up at City Garden Electric Centre (RTN2a – Electric Centre), which is a representative of the noise sensitive receiver City Garden.  The real-time noise monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct 2012. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.
  5. No project related exceedance was recorded in June, July and August reporting month at RTN2a-Hong Kong Electric Centre during this reporting quarter.

 

Air Quality Monitoring

  1. Due to extension of site boundary by contractor of HY/2009/19, location of air monitoring station CMA1b – Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.
  2. The location ID of air monitoring station CMA1b was updated as Oil Street Site Office in April 2013.
  3. Due to interruption of electric supply, the 24-hr TSP monitoring at the following stations were rescheduled as below:

MA1e: from 24 August 2013 to 26 August 2013

CMA5a: from 22 June 2013 to 24 and 25 June 2013 and from 3 July 2013 to 4 July 2013

  1. Due to the hoisting of Gale Signal no.8, the 1hr TSP event on 14 Aug 2013 was rescheduled to 15 Aug 2013.
  2. 1hr and 24hr TSP monitoring were conducted at CMA1b, CMA2a, CMA3a, CMA4a, CMA5a and CMA6a in the reporting period.
  3. The odour patrol along the odour route with 7 sniffing locations was conducted by a qualified odour patrol member on 9, 23 July and 6, 20 August 2012 at the concerned hours (afternoon for higher daily temperature).No Action and Limit Level was recorded during this reporting quarter.

 

 

Water Quality Monitoring

  1. Water quality monitoring was conducted at 13 monitoring stations namely WSD9, WSD17, WSD19, WSD 21, C1, C5e, C5w, C7, P1, P3, P4, P5 and RW21-P789 during the reporting period.
  2. Due to the Strong wind signal no.3 was hoisted on 22 June 2013, water quality monitoring at ebb tide were cancelled.
  3. Due to the Amber Rainstorm signal was hoisted on 24 June 2013, water quality monitoring at ebb tide were cancelled.
  4. Due to the Strong wind signal no.3 was hoisted on 2 July 2013, water quality monitoring at flood tide were cancelled.
  5. Due to the Strong wind signal no.3 was hoisted on 1 August and 14 August 2013, water quality monitoring at flood tide were cancelled.
  6. Water quality monitoring station RW21-P789 has been implemented with respect to HK/2009/02 started on 29 July 2013.
  7. Due to improper deployment of silt curtain WQM monitoring at station RW21- P789 was cancelled on 29 July 2013.  
  8. As confirmed by CWB RSS, the marine pilling works under contract HY/2009/19 was confirmed completed by 4 March 2013.  The water quality monitoring at the respective monitoring stations C8 and C9 were temporarily suspended since 30 March 2013.
  9. WQM events on 22 April 2013 at monitoring stations C2, C3, C4e and C4w were temporarily suspended. Upon confirmation with WDII RSS and the IEC, water quality monitoring at relocated intakes monitoring location P1, P3, P4 and P5 were commenced since 24 April 2013.
  10. Due to the blockage of the road access to C5e and C5w on 27 Mar 2013 during mid-flood tide the sample was taken under contingency C5 on 27 Mar 2013 during mid-flood.

xxxii.        Total 4 DO exceedances, 1 turbidity exceedances and 2 SS exceedances were recorded during mid-flood while 10 DO exceedance, 3 turbidity exceedances and 4 SS exceedances were recorded during mid-ebb in the reporting period. All the exceedances were concluded as non-project-related. The details of the recorded exceedances can be referred to the Section 5.4.

  1. Enhanced DO monitoring at 4 monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was conducted three days per week during the reporting period. There were 40 DO exceedance during mid-flood and 12 DO exceedances during mid-ebb recorded in this reporting period.  Investigation found that all exceedances were not project- related.
  2. In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be installed to channel water discharge flow from Culvert L to locations outside the embayment area, a proposed replacement of the requirement with additional dissolved oxygen monitoring has been conducted at three monitoring stations, namely A, B and C between the eastern seawall of Central Reclamation Phase III and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level between the eastern seawall of Central Reclamation Phase II and the HKCEC extension could be continuously monitored.
  3. Based on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no water deterioration with respect to NPR was commenced since 7 Jan 2012 and was completed on 6 Feb 2012 water quality monitoring.
  4. Water quality monitoring at WSD10 and WSD15 will be temporary suspended while water quality monitoring at WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8 Feb 12 onwards;
  5. Water quality monitoring at C8 and C9 have been implemented with respect to HY/2009/19 since the marine bore piling work started on 28 Jan 12.
  6. Due to the marine piling under Contract no. HY/2009/19 was completed on 4 March 2013, the temporary suspension of impact water quality monitoring at C8 and C9 from 4 March 2013 have been monitored for 4-week period after the completion of marine works to confirm no water deterioration.
  7. Based on the safety concern when external façade refurbishment was conducted by contractor employed by Provident Centre (C9) between 9 January 2012 to 30 July 2012 which caused to the inaccessibility of sampling either land and marine since 3 Feb 2012, there is a fine adjustment of the sampling location of water quality monitoring at C9 since 10 March 2012 to the closest accessible point prior to the completion of the external façade refurbishment work.
  8. With respect to the trial dredging at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3 , 11, 13, 15, 17, 19, 20 Apr and 3 May 2012, on-going water quality monitoring results at WSD21 during this period was checked and indicated that there was no contribution due to the trial dredging operation.  Enhanced review of water quality around WCR2 was also implemented and no deterioration in the water quality was observed.
  9. Due to the access of water monitoring station at WSD19 was blocked by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the inaccessibility of sampling either land and marine, there is a fine adjustment of the sampling point of WSD 19 since 5 April 2012 to the closest accessible point prior to the completion of the construction activities.
  10. Due to the dredging works for Cross Harbour Water Mains from Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April 2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for 4-week period after the completion of DP6 to confirm no water deterioration.

 

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. There was no environmental complaint recorded in the reporting period.

 

1.         Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-05/356/2009, FEP-06/356/2009 and FEP-07/356/2009  to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.4 of EM&A Manual and “Environmental Monitoring and Audit Requirements” under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works during the period from June 2013 to August 2013.

1.2          Structure of the Report

 

Section 1          Introduction – details the scope and structure of the report.

 

Section 2          Project Background – summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3          Monitoring Requirements – summarizes all monitoring parameters, monitoring locations, monitoring frequency, duration and action plan.

 

Section 4          Monitoring Results – summarizes the monitoring results obtained in the reporting period.

 

Section 5          Compliance Audit – summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 6          Complaints, Notification of summons and Prosecution – summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 7          Cumulative Construction Impact due to the Concurrent Projects summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8          Conclusion

2.         Project Background

2.1          Background

2.1.1.     “Wan Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2          Scope of the Project and Site Description

2.2.1.     The Project is located mainly in Wan Chai North, Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road Interchange to the east, as shown in Figure 2.1.

2.2.2.     The study area encompasses existing developments along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police Officers' Club, the Causeway Bay Typhoon Shelter (CBTS) and commercial and residential developments.

2.2.3.     The scope of the Project comprises:

·          Land formation for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for connection to the Trunk Road and for through traffic from Central to Wan Chai and Causeway Bay. The land formed for the above transport infrastructure will provide opportunities for the development of an attractive waterfront promenade for the enjoyment of the public

·          Reprovisioning / protection of the existing facilities and structures affected by the land formation works mentioned above

·          Extension, modification, reprovisioning or protection of existing storm water drainage outfalls, sewerage outfalls and watermains affected by the revised land use and land formation works mentioned above

·          Upgrading of hinterland storm water drainage system and sewerage system, which would be rendered insufficient by the land formation works mentioned above

·          Provision of the ground level roads, flyovers, footbridges, necessary transport facilities and the associated utility services

·          Construction of the new waterfront promenade, landscape works and the associated utility services

·          The Trunk Road (i.e. CWB) within the study area and the associated slip roads for connection to the Trunk Road.

 

2.2.4.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

 

2.3          Division of the Project Responsibility

2.3.1.     Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits (FEP) such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.     The details of individual contracts are summarized in Table2.2.

Table 2.2    Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HK/2009/01

Wan Chai Development Phase II – Central –Wanchai Bypass at Hong Kong Convention and Exhibition Centre

DP3, DP6

23 July 2010

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East

DP3, DP5

5 July 2010

DP1

26 April 2011

HY/2009/11

Wan Chai Development Phase II and Central – Wan Chai Bypass – North Point Reclamation

DP3

17 March 2010

(Under applicationof surrender)

HY/2009/15

Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

DP3

10 November 2010

DP1

13 July 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

HY/2009/17

Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works.

DP1

5 October 2010

HY/2009/18

Central - Wan Chai Bypass (CWB) – Central Interchange

DP1

21 April 2011

HY/2009/19

Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

HK/2012/08

Wan Chai Development Phase II Central-

Wan Chai Bypass at Wan Chai

West

DP1,DP2, DP3

March 2013

 

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer’s Representative  for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer’s Representative  for CWB

Principal Resident Engineer

Mr. Peter Poon

3912 3388

3912 3010

Chun Wo – Leader Joint Venture

Contractor under Contract no. HK/2009/01

Joint Venture Board Representative

Mr. PL Yue

2162 9909

2587 1878

Deputy Site Agent

Mr Andy Yu

9648 4896

Construction Manager

Mr Terry Wong

9757 9846

Construction Manager

Mr. Wyman Wong

9627 2467

Construction Manager

Mr. Jack Chu

9775 3008

Environmental Officer (Compliance Manager)

Mr. Andy Mak

9103 2370

Environmental Supervisor

Fan Chun Wai

6487 4488

Chun Wo – CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Project Manager

Mr. David Lau

3658-3022

2827 9996

Quality & Environmental Manager (Environmental Officer)

Mr. C.P. Ho

9191 8856

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

K C Cheung

3557 6399

2566 2192

 

Site Manager

J H Chen

3557 6368

 

 

Contractor’s Representative

Andrew Wong

3557 6358

 

 

Head of Construction Manager

Roger Cheung

3557 6371

 

 

Senior Construction Manager

Gene Cheung

3557 6395

Environmental Officer

Mr. Daniel Sin

3557 6347

Gammon

-Leader JV

 

 

Contractor under Contract no. HK/2010/06

 

 

Project Manager

Mr. Paul Lui

9095 7922

2529 2880

 

 

 

Site Agent

Mr. Eric Yip

2529 2068

Environmental Officer

Clement Pang

9735 9200

Environmental Supervisor

Jacky Cheung

9779 2292

Chun Wo - CRGL - MBEC Joint Venture

 

Contractor under Contract no. HY/2009/19

 

Project Manager

Mr. Rayland Lee

3758 8879

2570 8013

Site Agent

Mr. Paul Yu

9456 9819

Environmental Engineer

Mr. Calvin Leung

9286 9208

Environmental Manager /

Environmental Officer

Mr. M.H. Isa

9884 0810

Construction Manager (Marine)

William Luk

9610 1101

Construction Manager

(Land)

Patrick Cheung

9643 3012

Construction Manager

(Land)

Eric Fong

6191 9337

Operation Manager (Land)

Yung Kwok Wah

9834 1010

China State-

Leader JV

Contractor

under Contract

no. HK/2012/08

Project Director

Andrew Tse

9137 1811

2877 1522

 

 

Project Manager

Victor Wu

9193 8871

 

 

 

Deputy Project Manager

George Cheung

9268 1918

 

 

 

Site Agent

Paul Lui

9095 7922

 

 

 

Environmental Officer

James Ma

9130 9549

 

 

 

Environmental Supervisor

Ching Man, Chan

6050 4919

 

China State

 

Contractor

under Contract

no. HY/2010/08

Project Director

Cheung Kit Cheung

3557 6399

2566 8061

 

 

 

Project Manager

Chan Ying Lun

9812 0592

 

 

 

Deputy Project Manager

Chris Leung

3467 4299

 

 

 

Site Agent

Dave Chan

3467 4277

 

 

 

Environmental Officer

C.M. Wong

3557 6464

 

 

 

Environmental Supervisor

Louis Lam Tsz Kwan

3557 6470

 

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

34652888

34652899

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

2.5          Principal Work and Activities

2.5.1.     During this reporting period, the principal work activities for Contract no. HK/2009/01 are summarized in Table 2.4.

Table 2.4    Principal Work Activities for Contract no. HK/2009/01

June 2013

July 2013

August 2013

Marine Works (at Wan Chai)

Ÿ Construction of mass concrete coping for new seawall together with the construction of chamber/ manhole for proposed box culvert extension.

Ÿ Installation of ELS for construction of proposed box culvert Bay 8 and Bay 9.

Ÿ Prefabrication of steel bridge on the top of temporary open channel along Convention Avenue.

Ÿ Mitigation measures such as widening the waterway at reclamation area “HKCEC3E”, installation of pumps and water pipe for pumping seawater from Victoria Harbour to temporary water channel were implemented to enhance the seawater circulation for lower the seawater temperature at the temporary water channel.

Ÿ Dumping of ice blocks into temporary water channel to cool down the seawater at the temporary water channel.

 

Cross-Harbour Watermains Installation (CHA & CHB) and Marine Works (at TST)

Ÿ Defect rectification works for submarine pipeline A (removal of silt).

Ÿ Defect rectification works for submarine pipeline B (removal of silt).

Ÿ CCTV / photo inspection to the submarine pipeline B.

Ÿ Testing of ICCP monitoring system for new provided cross harbour watermain.

 

Cooling Watermains, Salt Watermains and Sewer (On Land)

Ÿ Mainlaying works at Zone B6-2A, B6-4, B6-6, A1-5C, A3-3C, C1-2 and X2-1.

Ÿ Mainlaying works in Zone B6-2A and B6-4.

Ÿ Mainlaying works in Zone B6-1B at north of HKCEC area.

Ÿ Mainlaying works in Zone B6-5C & B6-6 at west of HKCEC area.

Ÿ Mainlaying works in Zone A1-5C.

Ÿ Mainlaying works at Zone C1-2.

Ÿ Relocation of fire hydrant in Zone X2-1.

Ÿ Temporary ducting and cabling works at junction between Expo Drive East and Expo Drive Central.

 

E & M

Ÿ Full commissioning test for Cooling Water Pumping Station P5.

Ÿ Trial operation of the new provided cooling system P5.

 

Marine Works (at Wan Chai)

Ÿ Rockfilling at the northern part of HKCEC3E (East of HKCEC) between CH290 and CH385.

Ÿ Structural blinding for construction of proposed box culvert Bay 8 and Bay 9 was poured and dewatering and grouting curtain wall.

Ÿ Pre-drilling work for steel bridge on the top of temporary open channel along Convention Avenue.

Ÿ 4 nos. of drill holes for D-wall and pre-bored H-piles in stage 3.

Ÿ Mitigation measures such as widening the waterway at reclamation area “HKCEC3E”, installation of pumps and water pipe for pumping seawater from Victoria Harbour to temporary water channel to enhance the seawater circulation for lower the seawater temperature at the temporary water channel.

Ÿ Dumping of ice blocks into temporary water channel to cool down the seawater at the temporary water channel.

 

Cross-Harbour Watermains Installation (CHA & CHB) and Marine Works (at TST)

Ÿ Minor defect rectification works for submarine pipeline A and B (removal of silt). WSD accepted the rectification work.

Ÿ Testing of ICCP monitoring system and SCADA for new provided cross harbour watermain was carried out with WSD. Damaged isolation joints would be delivered to HK in mid Aug 2013.

 

XHWM, Cooling Watermains, Salt Watermains and Sewer (On Land)

Ÿ XHWM-Stage 1 connection. Stage 2 and 3 would be connected.

Ÿ Pipework for Additional Washout Chamber at VIP drop-off and the excavation and shoring for the structure.

Ÿ Reinstatement works at B6-2B at Northwest of HKCEC.

Ÿ Planter reinstatement, kerbworks, hard paving at West Foyer of HKCEC.

Ÿ Sewer laying works in Zone B6-2A, B6-4, B6-6 B6-5C & B6-6 at west of HKCEC area.

Ÿ Cooling main works in Zone C1-2.

Ÿ Salt watermain laying works in Zone A1-5C.

Ÿ Salt watermain laying works in Zone A3-5C.

Ÿ Salt watermain laying works in Zone A3-1, A5-2 and A1-5C.

Ÿ Salt watermain laying works in A4-1B, 2B.

Ÿ Temporary ducting and cabling works at junction between Expo Drive East and Expo Drive Central. Another work front at night.

 

Tunnel Works

Ÿ Installation of pre-bored H-pile in CWB Stage 1 underneath Atrium Link (from CH80 to CH120).

Ÿ Installation of pre-bored H-pile in CWB Stage 2 Atrium Link (from CH120 to CH220).

Ÿ Construction of bulkhead wall at CH3129 (18 panels).

Ÿ Filling of the existing open water channel at CH260.

Ÿ Construction of the Common D-wall.

Ÿ Demolition of the Promenade Deck.

Ÿ Installation of dewatering wells, observation wells and piezometers at CWB Stage 1.

 

E & M

Ÿ Operation attendance of 60 day.

Ÿ Switchover for cooling system P5.

Ÿ The old pumping house for EMSD and CP.

Marine Works (at Wan Chai)

Ÿ Construction of mass concrete coping for new seawall together with the construction of chamber/ manhole for proposed box culvert extension.

Ÿ Installation of ELS for construction of proposed box culvert Bay 8 and Bay 9.

Ÿ Prefabrication of steel bridge on the top of temporary open channel along Convention Avenue.

Ÿ Mitigation measures such as widening the waterway at reclamation area “HKCEC3E”, installation of pumps and water pipe for pumping seawater from Victoria Harbour to temporary water channel were implemented to enhance the seawater circulation for lower the seawater temperature at the temporary water channel.

Ÿ Dumping of ice blocks into temporary water channel to cool down the seawater at the temporary water channel.

 

Cross-Harbour Watermains Installation (CHA & CHB) and Marine Works (at TST)

Ÿ Defect rectification works for submarine pipeline A (removal of silt).

Ÿ Defect rectification works for submarine pipeline B (removal of silt).

Ÿ CCTV / photo inspection to the submarine pipeline B.

Ÿ Testing of ICCP monitoring system for new provided cross harbour watermain.

 

Cooling Watermains, Salt Watermains and Sewer (On Land)

Ÿ Mainlaying works at Zone B6-2A, B6-4, B6-6, A1-5C, A3-3C, C1-2 and X2-1.

Ÿ Mainlaying works in Zone B6-2A and B6-4.

Ÿ Mainlaying works in Zone B6-1B at north of HKCEC area.

Ÿ Mainlaying works in Zone B6-5C & B6-6 at west of HKCEC area.

Ÿ Mainlaying works in Zone A1-5C.

Ÿ Mainlaying works at Zone C1-2.

Ÿ Relocation of fire hydrant in Zone X2-1.

Ÿ Temporary ducting and cabling works at junction between Expo Drive East and Expo Drive Central.

 

E & M

Ÿ Full commissioning test for Cooling Water Pumping Station P5.

Ÿ Trial operation of the new provided cooling system P5.

 

 

2.5.2.     During this reporting period, the principal work activities for Contract no. HK/2009/02 are summarized in Table 2.5.

Table 2.5    Principal Work Activities for Contract no. HK/2009/02

June 2013

July 2013

August 2013

Ÿ Modification work of PTI at Expo Drive East.

Ÿ Modification of existing covered walkway along Expo Drive East.

Ÿ Remedial works for P7 & P8 were in progress at WCR1 area.  All 4 nos. pile cap construction. Mainlaying works for rectifying the subsided intake pipes for SHK cooling water system and the thrust block.  Mainlaying works for GE/HC cooling water system and the thrust block.

Ÿ Concreting of thrust block for the rectifying the P9 cooling watermains and remaining pressure test for rectifying the P9 cooling watermains. Initial Testing/Commissioning & waiting period for switching over.

Ÿ Major E&M works and their T&C in Cooling Water Pumping Stations P7, P8 and P9.

Ÿ Utility diversion for the outstanding DAV Chamber for P9 intake mains at Harbour Road (CHAI425m).

Ÿ Wall and top slab at Bay 2B of Salt Water Intake Culvert.

Ÿ Base slab, wall & top slab of Bay 1B of Salt Water Intake Culvert.

Ÿ Installation of stoplog and preliminary screen at Bay 2A.

Ÿ Water leakage test between Bay 3 and Bay 8.

Ÿ Mainlaying works for DN800 salt watermains (CHS8A) at Ex-Pet Garden except the remaining Y-section near the connection with existing system at Hung Hing Road.  Concreting of thrust block between CH150 – CH160, the temporary discharge point between CH150 – CH160 and backfilling work near Gate No.1.

Ÿ The remaining ABWF works in WSD Salt Water Pumping Station, including maintenance platform and external finishes.

Ÿ Dry tests at WSD Salt Water Pumping Station. Wet test after completion of the proposed intake culvert.

Ÿ Final fitting out for the DSD Pumping Station boundary wall at Hung Hing Road.

Ÿ Sheet pile cutting works at Bay5 / Bay 6 interface for subsequent construction of water plug beneath the installed precast unit (Bay 6)

 

Ÿ Modification work of PTI at Expo Drive East.

Ÿ Modification of existing covered walkway along Expo Drive East.

Ÿ The first and second attempt of full commissioning of P9 cooling water system.

Ÿ Minor remedial works for commissioning for both P7 and P8 cooling water system.-

Ÿ The wall and top slab at Salt Water Intake Culvert Bay 1B.

Ÿ Installation of guide rails for preliminary screens of Salt Water Intake Chamber No.1 at Bay 2A.

Ÿ The leakage test of stoplogs..

Ÿ The base slab of proposed wash out chamber near CHS8A160.

Ÿ The pipe laying work near the proposed connection point.

Ÿ The remaining ABWF works in WSD Salt Water Pumping Station, including maintenance platform and external finishes.

Ÿ Dry tests at WSD Salt Water Pumping Station. Wet test after completion of the proposed intake culvert.

Ÿ Sheet pile cutting works at Bay5 / Bay 6 interface and excavation down to the formation level for subsequent construction of water plug.

Ÿ The diver works between Bay 5 and the installed precast unit (Bay 6).

Ÿ The modification work for both east and west wings of staircase ST-01 landing.

Ÿ Counterweight installation for movable ramp.

Ÿ Installation of landing door for the disabled lift and glass installation.

Ÿ Last panel (BHC12) of Eastern Bulkhead Wall. 

Ÿ Interface coring and shear pin installation for the Eastern Bulkhead Wall.

Ÿ The road modification works along Wan Shing Street for HHR Flyover Diversion (Stage 1).

Ÿ Placing wearing course along in fount of Gammon Entrance No. 1 and road making.

Ÿ Breaking up the existing pavement and disposal for extract sheetpile next to ECO gas filling station.

Ÿ Rockfilling by Grade 400 at WCR4 and Grade 200 rockfilling works..

Ÿ Placing geotextile at TWCR4.

Ÿ Seawall blocks installation at WCR4 & TWCR4.

 

Ÿ Modification of existing covered walkway along Expo Drive East.

Ÿ The full commissioning of P7, P8 and P9 cooling water system.

Ÿ The 60 days for T&C period of P9 cooling water system.

Ÿ Backfilling works for the trench of P7 and P8 cooling water system remedial works area.

Ÿ Fresh water pipeworks had been completely laid to P7, P8 and P9 Cooling Water Pumping Station.

Ÿ Demolish of abandoned P8 Cooling Water Pumping Station.

Ÿ Installation of stoplog and its leakage test in SWIC.

Ÿ Installation of Aeration and Chlorination Pipes at Salt Water Intake Culvert Bay 2 to Bay 5.

Ÿ The lower part of the wall for proposed wash out chamber near CHS8A160.The fabrication works for DN800 temporary discharge pipe on Site.

Ÿ All DN800 watermains at Ex-pet Garden except the Y-section connecting with the existing DN600 watermains at Hung Hing Road. The pipe cleaning and water pressure test for the laid section.

Ÿ The excavation works at the Y-section connecting with the existing DN600 watermains at Hung Hing Road.

Ÿ The remaining ABWF works and boundary wall in WSD Salt Water Pumping Station , including maintenance platform and external finishes.

Ÿ The water plug at Bay5 / Bay 6 interface and the subsequent dewatering.

Ÿ Sheet pile cutting works between Bay 5 and Bay 6.

Ÿ The formwork erection for the base slab at Bay 5 and the rebar fixing .

Ÿ Construction of stoplog chamber extension at Bay 6.

Ÿ The modification work for both east and west wings of staircase ST-01 landing. Installation of glass panels for the disabled lift.

Ÿ Excavation for the 6 nos. Temporary Covered Walkway in the vicinity of Ferry Pier and their blinding layer.

Ÿ The road modification works along Wan Shing Street for HHR Flyover Diversion (Stage 1).

Ÿ Breaking up the existing pavement and disposal for extract sheetpile next to ECO gas filling station.

Ÿ Removing the extract sheetpile between ECO gas fill station and Wan Yan Street .

Ÿ Pavement works at Wan Shing Street near HK Yatch Club.

Ÿ Rockfilling by Grade 400 and Grade 200 at WCR4/TWCR4, all rockfilling works. Leveling stone installation along the temporary seawall.

Ÿ Seawall blocks installation at WCR4/TWCR4.

 

 

2.5.3.     Major construction activities for Contract no. HY/2009/15 was commenced on 10 November 2010. During this reporting period, the principal work activities for Contract no. HY/2009/15 are summarized as below:

Table 2.6    Principal Work Activities for Contract no. HY/2009/15

June 2013

July 2013

August 2013

Ÿ Removal of eastern breakwater of CBTS

Ÿ Installation of temporary wave protection barrier at eastern breakwater

Ÿ Temporary works for EVA

 

Ÿ Construction of EVA

 

Ÿ Construction of EVA

 

 

2.5.4.     Contract no. HK/2010/06 was commenced on 22 March 2011. During this reporting period, the principal work activities for Contract no. HK/2010/06 are summarized as below:

Table 2.7    Principal Work Activities for Contract no. HK/2010/06

June 2013

July 2013

August 2013

Ÿ Sheet piling works

Ÿ Utility diversion works

Ÿ Road resurfacing works

Ÿ Road opening works

 

Ÿ Sheet piling works

Ÿ Utility diversion works

Ÿ Road resurfacing works

 

Ÿ Pre-cast installation support works

 

 

2.5.5.     Contract no. HY/2009/19 was commenced on 24 March 2011. During this reporting period, the principal work activities for Contract no. HY/2009/19 are summarized as below:

Table 2.8    Principal Work Activities for Contract no. HY/2009/19

June 2013

July 2013

August 2013

Ÿ Construction works for Box Culvert T1

Ÿ Construction works for Culvert U1

Ÿ Demolition of parapet at IEC Link

Ÿ Construction of dewatering well for Cut & Cover Tunnel

Ÿ Removal of marine platform

Ÿ Construction of pile cap, column & cross head (Marine)

Ÿ ELS for Cut & Cover Tunnel

Ÿ Laying of 1500f pipe

Ÿ Launching of segments

Ÿ Unloading segments from derrick

Ÿ Extraction of temporary pile from marine section

 

 

Ÿ D-wall and Barrette Construction

Ÿ Construction works for Box Culvert T1

Ÿ Construction works for Culvert U1

Ÿ Demolition of parapet at IEC Link

Ÿ Construction of dewatering well for Cut & Cover Tunnel

Ÿ Removal of marine platform

Ÿ Construction of pile cap, column & cross head (Marine)

Ÿ ELS for Cut & Cover Tunnel

Ÿ Laying of 1500f pipe

Ÿ Launching of segments

Ÿ Unloading segments from derrick

Ÿ Extraction of temporary pile from marine section

 

Ÿ Road works at Watson Road

Ÿ D-wall and Barrette Construction

Ÿ Construction works for Box Culvert T1

Ÿ Construction works for Box Culvert U1

Ÿ Demolition of parapet at IEC Link

Ÿ Removal of marine platform

Ÿ Construction of pile cap, column & cross head (Marine)

Ÿ Installation of dewatering well

Ÿ Laying of 1500f pipe

Ÿ Launching of segments

Ÿ Extraction of temporary pile from marine section

Ÿ Installation of temporary lighting at IEC link commenced

Ÿ Construction of bridge truss TA1 commenced

Ÿ Breaking of barrette piles at Cut & Cover tunnel commenced

Ÿ Demolition of parapet at IEC link

 

2.5.6.     Contract no. HK/2012/08 was commenced on March 2013. During this reporting period, the principal work activities for Contract no. HK/2012/08 are summarized as below:

Table 2.9I   Principal Work Activities for Contract no. HK/2012/08

June 2013

July 2013

August 2013

Ÿ Site preparation works

Ÿ Site survey

Ÿ Marine ground investigation

Ÿ ELS for box culvert La at Lung King Street

Ÿ Dredging

Ÿ Demolition of the existing Expo Drive West Bridge

 

Ÿ Site preparation works

Ÿ Site survey

Ÿ Marine ground investigation

Ÿ ELS for box culvert La at Lung King Street

Ÿ Dredging

Ÿ Demolition of the existing Expo Drive West Bridge

 

Ÿ Site preparation works

Ÿ Site survey

Ÿ ELS for box culvert La at Lung King Street

Ÿ Dredging

Ÿ Demolition of the existing Expo Drive West Bridge

 

 

2.5.7.     Implementation status of the recommended mitigation measures during this reporting period is presented in Appendix 2.1.

3.         Monitoring Requirements

3.1.          Noise Monitoring

Noise Monitoring Stations

3.1.1.     The noise monitoring stations for the Project are listed and shown in Table 3.1 and Figure 3.1.  Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.1    Noise Monitoring Stations

Station

Description

M1a

Harbour Road Sports Centre

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

 

Real time Noise Monitoring Stations

3.1.1.     The real-noise monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.2    Real Time Noise Monitoring Station

District

Station

Description

Tin Hau

RTN1

FEHD Hong Kong Transport Section Whitefield Depot

North Point

RTN2

Oil Street Community Liaison Centre

North Point

RTN2a

Electric Centre

 

Noise Monitoring Parameters, Frequency and Duration

3.1.2.     The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

3.1.3.     Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

·          one set of measurements between 0700 and 1900 hours on normal weekdays.

3.1.4.     If construction works are extended to include works during the hours of 1900 – 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

3.1.5.     Real time noise shall be carried out at the designated monitoring stations. The following is an initial guide on the regular monitoring frequency for each station on a 24 hours daily basis when noise generating activities are underway:

·          One set of measurements between 0700 and 1900 hours on normal weekdays.

·          One set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.

·          One set of measurements between 2300 and 0700 hours on next day on everyday.

 

Monitoring Equipment

3.1.6.     As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

3.1.7.     Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

3.2.                Air Monitoring

Air Quality Monitoring Stations

3.2.1.     The air monitoring stations for the Project are listed and shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.3    Air Monitoring Stations

Station ID

Monitoring Location

Description

CMA1b

Oil Street Community Liaison Centre

North Point

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

CWB PRE Site Office *

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5a

Children Playgrounds opposite to Pedestrian Plaza

Wan Chai

CMA6a

WDII PRE Site Office *

Wan Chai

* Remarks: As per the ENPC meeting in January 2011, the monitoring stations CMA3a - Future CWB site office at Wanchai Waterfront Promenade and CMA6a - Future AECOM site office at Work Area were renamed as remark.

Air Monitoring Parameters, Frequency and Duration

3.2.2.     One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

3.2.3.     All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

3.2.4.     For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.

Sampling Procedure and Monitoring Equipment

3.2.5       High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

·          0.6 - 1.7 m3 per minute adjustable flow range;

·          equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

·          installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

·          capable of providing a minimum exposed area of 406 cm2;

·          flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

·          equipped with a shelter to protect the filter and sampler;

·          incorporated with an electronic mass flow rate controller or other equivalent devices;

·          equipped with a flow recorder for continuous monitoring;

·          provided with a peaked roof inlet;

·          incorporated with a manometer;

·          able to hold and seal the filter paper to the sampler housing at horizontal position;

·          easily changeable filter; and

·          capable of operating continuously for a 24-hour period.

3.2.6       Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

Laboratory Measurement / Analysis

3.2.7       A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

3.2.8       An alternative non-HOKLAS accredited laboratory was set-up for carrying out the laboratory analysis, the laboratory equipment was approved by the ER on 8 February 2011 and the measurement procedures were witnessed by the IEC. Any measurement performed by the laboratory was be demonstrated to the satisfaction of the ER and IEC. IEC shall regularly audit to the measurement performed by the laboratory to ensure the accuracy of measurement results.

3.2.9       Filter paper of size 8" x 10" shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

3.2.10    After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

3.2.11    All the collected samples shall be kept in a good condition for 6 months before disposal.

impact monitoring for odour patrol

3.2.12    Odour patrols along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai Public Cargo Working Area when there is temporary reclamation in Causeway Bay Typhoon Shelter and/or in the ex-Wan Chai Public Cargo Working Area, or when there is dredging of the odorous sediment and slime at the south-western corner of the Causeway Bay Typhoon Shelter. Odour patrols will be carried out at bi-weekly intervals during July, August and September by a qualified person of the ET who shall:

·        be at least 16 years of age;

·        be free from any respiratory illnesses; and

·        not be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30 min

·        before and during odour patrol

3.2.13    Odour patrol shall be conducted by independent trained personnel / competent persons patrolling and sniffing around the shore as shown in Figure 3.1 to detect any odour at the concerned hours (afternoon is preferred for higher daily temperature).

3.2.14    The qualified person will use the nose (olfactory sensor) to sniff odours at different locations. The main odour emission sources and the areas to be affected by the odour nuisance will be identified.

3.2.15    The perceived odour intensity is to be divided into 5 levels which are ranked in the descending order as follows:

·            0 - Not detected. No odour perceived or an odour so weak that it cannot be easily characterized or described;

·            1 - Slight Identifiable odour, and slight chance to have odour nuisance;

·            2 - Moderate Identifiable odour, and moderate chance to have odour nuisance;

·            3 - Strong Identifiable, likely to have odour nuisance;

·            4 - Extreme Severe odour, and unacceptable odour level.

 

3.2.16    The findings including odour intensity, odour nature and possible odour sources, and also the local wind speed and direction at each location will be recorded. In addition, some relevant meteorological and tidal data such as daily average temperature, and daily average humidity, on that surveyed day will be obtained from the Hong Kong Observatory Station for reference. The Action and Limit levels for odour patrol are shown in Appendix 3.1.

3.3    Water Quality Monitoring

3.3.1.     The EIA Report has identified that the key water quality impact would be associated with the dredging works during the construction phase.  Marine water quality monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is therefore recommended to be carried out at selected WSD flushing water intakes.  The impact monitoring should be carried out during the proposed dredging works to ensure the compliance with the water quality standards.

3.3.2.     The updated EM&A Manual for EP-356/2009 (Version in March 2011) is approval by EPD on 29 April 2011. As such, the Action Level and Limit Level for the wet season (April – September) will be effected and applied to the water quality monitoring data from 30 April 2011.

Water Quality Monitoring Stations

3.3.3.     It is proposed to monitor the water quality at 9 WSD salt water intakes and 14 cooling water intakes along the seafront of the Victoria Harbour. The proposed water quality monitoring stations of the Project are shown in Table 3.4 and Figure 3.1.  Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.4    Marine Water Quality Stations for Water Quality Monitoring

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD7

Kowloon South

834150.0

818300.3

WSD9

Tai Wan

837921.0

818330.0

WSD10

Cha Kwo Ling

841900.9

817700.1

WSD15

Sai Wan Ho

841110.4

816450.1

WSD17

Quarry Bay

839790.3

817032.2

WSD19

Sheung Wan

833415.0

816771.0

WSD20

Kennedy Town

830750.6

816030.3

WSD21

Wan Chai

836220.8

815940.1

RW1

Wan Chai (Reprovision)

836188.8

815911.1

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

C2

Telecom House

835647.9

815864.4

C3

HKCEC Phase I

835836.2

815910.0

C4e

Wan Chai Tower and Great Eagle Centre (Eastern)

835932.8

815888.2

C4w

Wan Chai Tower and Great Eagle Centre (Western)

835629.8

815889.2

C5e

Sun Hung Kai Centre (Eastern)

836250.1

815932.2

C5w

Sun Hung Kai Centre (Western)

836248.1

815933.2

C6

World Trade Centre

837009.6

815999.3

C7

Windsor House

837193.7

816150.0

C8

City Garden

837970.6

816957.3

C9

Provident Garden

838355.0

817116.6

RC1

Proposed HKAPA Extension

835487.7

815987.7

RC5

Sun Hung Kai Centre (Reprovision)

836291.4

816029.7

RC7

Windsor House (Temporary Dilution)

837245.2

816156.6

P1

HKCEC Phase I

835774.7

816179.4

P3

The Academy of performing Arts

835824.6

816212.0

P4

Shui on Centre

835865.6

816220.0

P5

Government Buildings

(Wanchai Tower / Revenue Tower / Immigration Tower)

835895.2

816215.2

RW21-P789

Great Eagle Centre/ Sun Hung Kai Centre/CWB

836268.0

816020.0

Remarks: -    The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

                -   WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.

-   4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.

-   C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.

-   WSD7 and WSD20 water quality monitoring were temporarily suspended from 27 Apr 2012.

 

Water Quality Parameters and frequency

3.3.4.     Monitoring of dissolved oxygen (DO), turbidity and suspended solids (SS) shall be carried out at WSD flushing water intakes and cooling water intakes. DO and Turbidity are measured in-situ while SS is determined in laboratory. 

3.3.5.     In association with the water quality parameters, other relevant data shall also be measured, such as monitoring location/position, time, sampling depth, water temperature, pH, salinity, dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal stage, and any special phenomena and work underway at the construction site etc.

3.3.6.     The interval between two sets of monitoring should not be less than 36 hours except where there are exceedances of Action and/or Limit Levels, in which case the monitoring frequency will be increased.  Table 3.5 shows the proposed monitoring frequency and water quality parameters.  Duplicate in-situ measurements and water sampling should be carried out in each sampling event.  For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5m.

Table 3.5    Marine Water Quality Monitoring Frequency and Parameters

Activities

Monitoring Frequency1

Parameters2

During the 4-week baseline monitoring period

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

During marine construction works

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

After completion of marine construction works

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

Notes:

1.     For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5m.

2.     Turbidity should be measured in situ whereas SS should be determined by laboratory.

 

Dissolved Oxygen and Temperature Measuring Equipment

3.3.7.     The instrument should be a portable, weatherproof dissolved oxygen measuring instrument complete with cable, sensor, comprehensive operation manuals, and use a DC power source. It should be capable of measuring:

·          a dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation

·          a temperature of 0-45 degree Celsius

3.3.8.     It should have a membrane electrode with automatic temperature compensation complete with a cable. Sufficient stocks of spare electrodes and cables should be available for replacement where necessary. (e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).

3.3.9.     Should salinity compensation not be build-in in the DO equipment, in-situ salinity shall be measured to calibrate the DO equipment prior to each DO measurement.

Turbidity Measurement Instrument

3.3.10    The instrument should be a portable, weatherproof turbidity-measuring instrument complete with comprehensive operation manual. The equipment should use a DC power source. It should have a photoelectric sensor capable of measuring turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model 2100P or an approved similar instrument).

Sampler

3.3.11     Water sampler comprises a transparent PVC cylinder, with a capacity of not less than 2 litres, and can be effectively sealed with latex cups at both ends. The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (e.g. Kahlsico Water Sampler or an approved similar instrument).

Sample Container and Storage

3.3.12    Water samples for suspended solids measurement should be collected in high-density polythene bottles, packed in ice (cooled to 4°C without being frozen), and delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection for analysis.

Water Depth Detector

3.3.13    A portable, battery-operated echo sounder shall be used for the determination of water depth at each designated monitoring station. This unit can either be handheld or affixed to the bottom of the workboat, if the same vessel is to be used throughout the monitoring programme.

Salinity

3.3.14    A portable salinometer capable of measuring salinity in the range of 0-40 ppt shall be provided for measuring salinity of the water at each of monitoring location.

Monitoring Position Equipment

3.3.15    A hand-held or boat-fixed type digital Global Positioning System (GPS) with waypoint bearing indication or other equivalent instrument of similar accuracy shall be provided and used during monitoring to ensure the monitoring vessel is at the correct location before taking measurements.

Calibration of In-situ Instruments

3.3.16    All in-situ monitoring instrument shall be checked, calibrated and certified by a laboratory accredited under HOKLAS or equivalent before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring. Responses of sensors and electrodes should be checked with certified standard solutions before each use. Wet bulb calibration for a DO meter shall be carried out before measurement at each monitoring location.

3.3.17    For the on site calibration of field equipment by the ET, the BS 127:1993, "Guide to Field and on-site test methods for the analysis of waters" should be observed.

3.3.18    Sufficient stocks of spare parts should be maintained for replacements when necessary. Backup monitoring equipment shall also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, etc.

Laboratory Measurement / Analysis

3.3.19    Analysis of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the monitoring stations for carrying out the laboratory SS determination. The SS determination work shall start within 24 hours after collection of the water samples. The SS determination shall follow APHA 19ed or equivalent methods subject to the approval of IEC and EPD.

 

Enhanced Water Quality Monitoring in the ex-Wan Chai Public Cargo

Working Area and the Causeway Bay Typhoon Shelter

3.3.10.   The enhanced water quality monitoring and audit programme is to avoid aggravation of odour nuisance from seawater arising from temporary reclamation in the ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.

3.3.11.   Dissolved oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when there is temporary reclamation in Causeway Bay Typhoon Shelter and at the south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working Area. The proposed water quality monitoring stations of the Project are shown in Table 3.6 and Figure 3.1.

Table 3.6    Marine Water Quality Stations for Enhanced Water Quality Monitoring

Station

Location

C6

Excelsior Hotel

C7

Windsor House

Ex-WPCWA-SW

South-western of the ex-Wan Chai Public Cargo Working Area

Ex-WPCWA-SE

South-eastern of the ex-Wan Chai Public Cargo Working Area

3.3.12.   The monitoring of dissolved oxygen are to be carried out 3 days per week, at mid-flood and mid-ebb tides for 3 water depths (1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth may be omitted. If the water depth be less than 3m, only the mid-depth will be monitored).

Daily SS Monitoring and 24 hours Turbidity Monitoring System

3.3.13.   During dredging of the sediment at the south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of suspended solids and 24 hour monitoring of turbidity at the cooling water intakes (C6 and C7) shall be conducted.

3.3.14.   The 24 hours monitoring of turbidty at the cooling water intakes (C6 and C7) shall be established by setting up a continuous water quality monitoring station in front of the intakes during the dredging activities.  The monitoring system include the turbidity sensor and data logger which is capable of data capturing at every 5 minutes. The data shall be downloaded daily and compared with the Action and Limit level determined during the baseline water qualtiy monitoring at the cooling water intake locations.

Additional Dissovled oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW

3.3.15    In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be installed to channel water discharge flow from Culvert L to locations outside the embayment area, a proposed replacement of the requirement with additional dissolved oxygen monitoring has been conducted at three monitoring stations, namely A, B and C between the eastern seawall of Central Reclamation Phase III and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level between the eastern seawall of Central Reclamation Phase II and the HKCEC extension could be continuously monitored.

3.3.16    With respect to the commencement of dredging works under HK/2012/08 and the installation of MTR precast protection unit, the enhanced water quality monitoring for Culvert L was temporarily suspended since 24 July 2013

3.3.17    The proposed DO monitoring stations of the Project are shown in Table 3.7

Table 3.7    Marine Water Quality Stations for Additional DO Monitoring

Station

Easting

Northing

A

835468

815857

B

835572

815961

C

835659

816271

 

3.3.18    The monitoring of dissolved oxygen are to be carried out once per week, at mid-flood and mid-ebb tides for 3 water depths (1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth may be omitted. If the water depth be equal to or less than 3m, only the mid-depth will be monitored).

4.         Monitoring Results

4.0.1.     The environmental monitoring will be implemented based on the division of works areas of each designed project managed under different contracts with separate FEP applied by individual contractors.  Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 3.1. The monitoring results are presented in according to the Individual Contract(s).

 

4.0.2   The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The FEP surrender application was submitted to EPD by contractor on 16 Jan 2012 that they would surrender the permit on 1 Jan 2012. Moreover, the construction site was handed over to contractor HY/2009/19 on 4 January 2012. However, the surrender of the FEP for HY/2009/11 withdrew by contractor on 14 February 2012 due to some outstanding works was confirmed by RSS on 10 Feb 2012. Therefore, the noise, air and water quality monitoring were keeping in view for the commencement of the works under this contract. No construction activity was conducted by HY/2009/11 up to 4 January 2012.

4.0.3  According to EP-364/2009/A Part B, “Scale and Scope of Designated Project”, Remarks (c),”The permanent and temporary reclamation and associated dredging works related to the CWB construction are separately covered by environmental permit No. EP-356/2009 issued to Civil Engineering and Development Department”, and marine piling works to be conducted by the Contractor of Contract no. HY/2009/19 from 28 January 2012 was considered to be governed under EP-356/2009. As the construction site area of Contract no. HY/2009/11 had already been handed over to Contract no. HY/2009/19, the designated noise, water and air quality monitoring stations for Contract no. HY/2009/11 would be shared with Contract no. HY/2009/19 from 28 January 2012.

  4.1.       Noise Monitoring Results

Contract no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC and Contract no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East and Contract no. HK/2010/06 Wan Chai Development Phase II – Central-Wan Chai Bypass over MTR Tsuen Wan Line

4.1.1.     The proposed divisions of noise monitoring stations are summarized in Table 4.1 below.

Table 4.1    Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02 and HK/2010/06

Station

Description

M1a

Harbour Road Sports Centre

4.1.2.     No exceedance was recorded in this reporting period. Details of noise monitoring results and graphical presentation can be referred in Appendix 4.1

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

4.1.3.     The noise monitoring for HY/2009/15 was commenced on 10 November 2010. The proposed division of noise monitoring stations are summarized in Table 4.2 below.

Table 4.2    Noise Monitoring Station for Contract nos. HY/2009/15

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

 

4.1.4.     No exceedance was recorded in this reporting period. Details of noise monitoring results and graphical presentation can be referred in Appendix 4.1

Contract no. HY/2009/19 – Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

4.1.5.     Noise quality monitoring at M4b and M5b have been implemented with respect to HY/2009/19 since the marine bore piling work started on 28 Jan 2012.

4.1.6.     The proposed division of noise monitoring stations for Contract no. HY/2009/19 are summarized in Table 4.3 below:

        Table 4.3  Noise Monitoring Stations for Contract no.  HY/2009/19

Station

Description

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

 

 

 

 

 

 

 

4.1.7.     Seven limit level exceedances were recorded at M6 on 3, 13 June, 9, 16 July, 6, 20 and 27 August 2013. The limit level exceedances were considered as non-project related.

4.1.8.     Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of graphical presentation can be referred in Appendix 4.1. 

  4.2.       Real Time Noise Monitoring Results

4.2.1       As the land-based piling and filling works- DP3 at Tin Hau had been completed on 3 September 2012 and confirmed by RSS, the real-time noise monitoring results at FEHD Hong Kong Transport Section Whitfield Depot was excluded under EP-356/2009 since 28 November 2012.

4.2.2       The real-time noise monitoring results at RTN1  (FEHD Hong Kong Transport Section Whitfield Depot) was excluded under EP-356/2009 since 28 October 2012, as the land-based piling and filling works- DP3 at Tin Hau had been completed on 3 September 2012 and confirmed by RSS

4.2.3       Oil Street Community Liaison Centre was confirmed to be demolished in mid-October by CWB RSS.  This presented a need for relocation of RTN2 – Oil Street Community Liaison Centre.  After liaison with Hong Kong Electric, permission was granted on 21 Sep 2012 for real time noise monitoring set up at City Garden Electric Centre (RTN2a – Electric Centre), which is a representative of the noise sensitive receiver City Garden.  The real-time noise monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct 2012. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.

 

Contract no. HY/2009/19 – Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

4.2.4       The proposed divisions of real time noise monitoring stations are summarized in Table 4.4 below. Real time noise monitoring for the marine bored piling works under contract no. HY/2009/19 was commenced on 28 January 2012.

4.2.5       Real-time noise monitoring at FEHD Hong Kong Transport Section Whitefield Depot commenced external wall renovation since 1 June 2012

4.2.6       The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011 in this reporting period and the FEP-01/356/2009 was surrendered on 22 October 2012. The monitoring was temporary suspended since 5 January 2012.

4.2.7       No project related exceedance was recorded in June, July and August reporting month at RTN2a-Hong Kong Electric Centre during this reporting quarter.

4.2.8       Details of real time noise monitoring results and graphical presentation can be referred to Appendix 4.2

 

Table 4.4    Real Time Noise Monitoring Station for Contract no. HY/2009/11 and HY/2009/19

District

Station

Description

Tin Hau

RTN1

FEHD Hong Kong Transport Section Whitefield Depot

North Point

RTN2

Oil Street Community Liaison Centre

North Point

RTN2a

Electric Centre

l    Real time noise monitoring results and graphical presentation during night time period are for information only.

l   RTN2 had been relocated to RTN2a since 5 Oct 2012

l   RTN1 monitoring had been finished on 28 Nov 2012

  4.3.        Air Monitoring Results

4.3.1.     Due to interruption of electric supply, the 24-hr TSP monitoring at the following stations were rescheduled as below:

MA1e: from 24 August 2013 to 26 August 2013

CMA5a: from 22 June 2013 to 24 and 25 June 2013 and from 3 July 2013 to 4 July 2013

4.3.2.     Due to the hoisting of Gale Signal no.8, the 1hr TSP event on 14 Aug 2013 was rescheduled to 15 Aug 2013.

4.3.3.     1hr and 24hr TSP monitoring were conducted at CMA1b, CMA2a, CMA3a, CMA4a, CMA5a and CMA6a in the reporting period.

4.3.4.     The odour patrol along the odour route with 7 sniffing locations was conducted by a qualified odour patrol member on 9, 23 July and 6, 20 August 2012 at the concerned hours (afternoon for higher daily temperature).No Action and Limit Level was recorded during this reporting quarter.

 

 

Contract no. HY/2009/11 – Central – Wanchai Bypass, North Point Reclamation

4.3.5.     The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 and the FEP-01/356/2009 was surrendered on 22 October 2012. The monitoring for the contract was temporary suspended on 6 January 2012.

Contract no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC

4.3.6.     Air monitoring was commenced on 1 April 2011 in response to the commencement of the land-filling work for Contract no. HK/2009/01. The proposed division of air monitoring stations are summarized in Table 4.6  below.

4.3.7.     No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized. 

Table 4.6    Air Monitoring Stations for Contract no. HK/2009/01

Station

Description

CMA5a

Children Playgrounds opposite to Pedestrian Plaza

CMA6a

WDII PRE Site Office *

 

Contract no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East

4.3.8.     Air monitoring was commenced in mid-January 2011 for the land-filling work for Contract no. HK/2009/02. The proposed division of air monitoring stations is summarized in Table 4.7 below. No exceedance was recorded in the reporting period.

Table 4.7    Air Monitoring Station for Contract no. HK/2009/02

Station

Description

CMA4a

Society for the Prevention of Cruelty to Animals

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

4.3.9.     Air monitoring was commenced on 15 March 2011 for the land filling work for Contract no. HY/2009/15.  The proposed division of air monitoring stations are summarized in Table 4.8 below.

4.3.10.   No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.

Table 4.8    Air Monitoring Station for Contract no. HY/2009/15

Station

Description

CMA3a

CWB site office at  Wanchai Waterfront Promenade

 

Contract no. HY/2009/19 –Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

4.3.11.   Air monitoring at CMA1b and CMA2a have been implemented with respect to HY/2009/19 since the marine bore piling works started on 28 Jan 2012. No exceedance was recorded in the reporting period.

4.3.12.   No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized. 

4.3.13.   The proposed division of air monitoring stations is summarized in Table 4.9 below.

Table 4.9 Air Monitoring Stations for Contract no. HY/2009/19

Station

Description

CMA1b

Oil Street Community Liaison Centre

CMA2a

Causeway Bay Community Centre

4.4      Water Monitoring Results

Contract no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC

4.4.1.     Water quality monitoring for Contract no. HK/2009/01 was commenced on 23 July 2010. The proposed division of water monitoring stations is summarized in Table 4.10 below.

4.4.2.     Water quality monitoring station RW21-P789 has been implemented with respect to HK/2009/02 started on 29 July 2013.

Table 4.10 Water Monitoring Stations for Contract no. HK/2009/01

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD7

Kowloon South

834150.0

818300.3

WSD19

Sheung Wan

833415.0

816771.0

WSD20

Kennedy Town

830750.6

816030.3

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

C2

Telecom House

835647.9

815864.4

C3

HKCEC Phase I

835836.2

815910.0

C4e

Wan Chai Tower and Great Eagle Centre (Eastern)

835932.8

815888.2

C4w

Wan Chai Tower and Great Eagle Centre (Western)

835629.8

815889.2

P1

HKCEC Phase I

835774.7

816179.4

P3

The Academy of performing Arts

835824.6

816212.0

P4

Shui on Centre

835865.6

816220.0

P5

Government Buildings

(Wanchai Tower / Revenue Tower / Immigration Tower)

835895.2

816215.2

RW21-P789

Great Eagle Centre/ Sun Hung Kai Centre/CWB

836268.0

816020.0

Remarks:

- The water monitoring stations for the dredging works under Contract No. HK/2009/01 should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these locations have not been carried out by others. Similarly, the water monitoring stations for the dredging works under Contract No. HK/2009/02 should also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality monitoring at these locations have not been carried out by others.

         -     WSD7 and WSD20 water quality monitoring were temporarily suspended since 27 Apr 2012.

 

Contract no. HK/2009/02 - Wan Chai Development Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East

4.4.3.     Water quality monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010. The proposed division of water monitoring stations is summarized in Table 4.11 below.

Table 4.11 Water Monitoring Stations for Contract no. HK/2009/02

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD21

Wan Chai

836220.8

815940.1

WSD9

Sheung Wan

833415.0

816771.0

WSD17

Kennedy Town

830750.6

816030.3

Cooling Water Intake

C5e

Sun Hung Kai Centre (Eastern)

836250.1

815932.2

C5w

Sun Hung Kai Centre (Western)

836248.1

815933.2

RW21-P789

Great Eagle Centre/ Sun Hung Kai Centre/CWB

836268.0

816020.0

Remarks:

-       The water monitoring stations for the dredging works under Contract No. HK/2009/01 should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these locations have not been carried out by others. Similarly, the water monitoring stations for the dredging works under Contract No. HK/2009/02 should also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality monitoring at these locations has not been carried out by others.

-       Water quality monitoring at WSD9 and WSD 17 was implemented with respect to HK/2009/02 from 8 Feb 2012.

Contract no. HK/2010/06 - Wan Chai Development Phase II – Central –Wanchai Bypass over MTR Tsuen Wan Line

4.4.4.     Water monitoring for Contract no. HK/2010/06 was commenced on 8 March 2011. The proposed division of water monitoring stations are summarized in Table 4.12 below.

Table 4.12 Water Monitoring Stations for Contract no. HK/2010/06

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C2

Telecom House

835647.9

815864.4

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

4.4.5.     Due to the commencement of the maintenance dredging on 10 November 2010, water quality monitoring for Contract no. HY/2009/15 was commenced on 9 November 2010. The proposed division of water monitoring stations is summarized in Table 4.13 below.

Table 4.13  Water Monitoring Stations for Contract no. HY/2009/15

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C6

Excelsior Hotel

837009.6

815999.3

C7

Windsor House

837193.7

816150

P1

HKCEC Phase I

835774.7

816179.4

Remarks: -      The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

Contract no. HY/2009/19 – Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

4.4.6.     Due to the commencement of the marine bored piling on 28 Jan 2012, water quality monitoring for Contract no. HY/2009/19 was commenced on 28 Jan 2012. The proposed division of water monitoring stations are summarized in Table 4.14 below.

4.4.7.     As confirmed by HY/2009/19 contractor, there was no marine work to be conducted on 26 December 2012, water quality monitoring at C8 and C9 were temporary suspended on 26 December 2012 during mid-ebb and mid-flood.

4.4.8.     As confirmed by CWB RSS, the marine pilling works under contract HY/2009/19 was confirmed completed by 4 March 2013.  The water quality monitoring at the respective monitoring stations C8 and C9 were temporarily suspended since 30 March 2013.

Table 4.14  Water Monitoring Stations for Contract no. HY/2009/19

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C8

City Garden

837970.6

816957.3

C9

Provident Garden

838355.0

817116.6

            Remarks: C8 and C9 water monitoring commenced on 28 Jan 2012.

4.4.9.     Based on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no water deterioration with respect to NPR was commenced since 7 Jan 2012 and it was completed on 6 February 2012.

4.4.10.   Water quality monitoring at WSD10 and WSD15 was temporary suspended while water quality monitoring at WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8 Feb 12 onwards;

4.4.11.   Water quality monitoring at C8 and C9 have been implemented with respect to HY/2009/19 since the marine bore piling work started on 28 Jan 12.

4.4.12.   Based on the safety concern when external façade refurbishment was conducted by contractor employed by Provident Center (C9) between 9 January 2012 to 30 July 2012 which caused to the inaccessibility of sampling either land and marine since 3 Feb 2012, there is a fine adjustment of the sampling location of water quality monitoring at C9 since 10 March 2012 to the closest accessible point prior to the completion of the external façade refurbishment work.

4.4.13.   With respect to the trial dredging at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3 , 11, 13, 15, 17, 19, 20 Apr and 3 May 2012, on-going water quality monitoring results at WSD21 during this period was checked and indicated that there was no contribution due to the trial dredging operation.  Enhanced review of water quality around WCR2 was also implemented and no deterioration in the water quality was observed.

4.4.14.   Due to the access of water monitoring station at WSD19 was blocked by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the inaccessibility of sampling either land and marine, there is a fine adjustment of the sampling point of WSD 19 since 5 April 2012 to the closest accessible point prior to the completion of the construction activities.

4.4.15.   Due to the dredging works for Cross Harbour Water Mains from Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April 2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for 4-week period after the completion of DP6 to confirm no water deterioration.

4.4.16.   As per the meeting with the representative of Excelsior Hotel and World Trade Centre on 17 May 2011, they confirmed that the seawater intake for The Excelsior was no longer in use and replaced by the connected permanent water supply from WSD pipelines since 11 January 2011. Thus, the impact water quality monitoring for the cooling intake - C6 was terminated effective from 26 May 2011. 

4.4.17.   24 hours monitoring of turbidity at the cooling water intakes at C7 was conducted. With respect to the seawall collapsing at TS4 on 17 November 2011, the 24 hours turbidity monitoring and was kept in November 2011. Since the reinstating the seawall was completed on 13 January 2012 and no any water deterioration was performed, 24 hour turbidity monitoring was then suspended on 27 January 2012.

4.4.18.   Investigations were found that 6 turbidity and 5 SS exceedances which were Project-related to Contract no. HK/2009/02 in October 2012. The details of the recorded exceedances can be referred to the Section 5.4.

4.4.19.   The enhanced water quality monitoring at C6, C7, Ex-WPCWA-SW and Ex-WPCWA-SE was commenced on 13 January 2011.  No project-related exceedance was recorded in the daily SS monitoring and 24 hours turbidity monitoring.

4.4.20.   Water monitoring results measured in this reporting period are reviewed and summarized in Table 4.15. Details of water quality monitoring results and graphical presentation can be referred in Appendix 4.3.

Table 4.15 Summary of Water Quality Monitoring Exceedances in Reporting period

 

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HK/2009/01

WSD19

0

0

0

0

1

1

0

0

1

1

0

0

 

C1

0

0

0

0

0

0

0

0

0

0

0

0

 

P1

0

0

0

0

0

0

0

0

0

0

0

0

P3

0

0

0

0

0

0

0

0

0

0

0

0

P4

0

0

0

0

0

0

0

0

0

0

0

0

P5

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/02

C5e

0

0

0

0

0

0

0

0

0

0

0

0

 

C5w

0

0

0

0

0

0

0

0

0

0

0

0

Monitoring started on

8 Feb 2012

WSD21

0

0

0

0

0

0

9

0

0

0

1

2

WSD9

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD17

0

0

0

1

0

0

0

0

0

0

0

1

 

RW21-P789

0

0

0

0

0

0

0

0

0

0

0

0

HY/2009/15

C7

4

0

0

0

0

0

1

0

0

1

0

0

Total

4

0

0

1

1

1

10

0

1

2

1

3

Remarks:  -     The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

                 -    WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.

-   4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.

-     C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.

-   C8 & C9 was temporary suspended on 30 March 2013 due to the marine works for Contract no. HY/2009/19 had been completed on 4 March 2013

-     WSD7 and WSD20 were temporarily suspended from 27 Apr 2012

 

4.4.21.   Enhanced DO monitoring at 4 monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table 4.15a.

 

Table 4.15a     Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting period

 

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

DO

AL

LL

AL

LL

HY/2009/15

C6

0

0

1

0

C7

4

0

3

0

Ex-WPCWA SW

0

14

0

4

Ex-WPCWA SE

8

14

3

1

Total

12

28

7

5

 

4.4.22.   There were 19 action level exceedances and 33 limit level exceedances of enhanced dissolved oxygen recorded in this reporting month. Investigation found that the exceedances are not related to the Project works.  Details of graphical presentation can be referred in Appendix 4.3.

4.4.23.   In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be installed to channel water discharge flow from Culvert L to locations outside the embayment area, a proposed replacement of the requirement with additional dissolved oxygen monitoring has been conducted at three monitoring stations, namely A, B and C between the eastern seawall of Central Reclamation Phase III and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level between the eastern seawall of Central Reclamation Phase II and the HKCEC extension could be continuously monitored. Details of additional DO monitoring results can be referred in Appendix 4.3a.

4.4.24.   With respect to the commencement of dredging works under HK/2012/08 and the installation of MTR precast protection unit, the enhanced water quality monitoring for Culvert L was temporarily suspended since 24 July 2013

4.5     Waste Monitoring Results

Contract no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC

4.5.1.     No Inert C&D waste was recycled and non-inert C&D waste was disposed of for the site works in this reporting period. Details of the waste flow table are summarized in Table 4.16.

Table 4.16  Details of Waste Disposal for Contract no. HK/2009/01

Waste Type

Quantity this quarter

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

2045.27

29852.185

TKO137, TM38

Inert C&D materials recycled, m3

0

5104.5

N/A

Non-inert C&D materials disposed, m3

96.88

1411.86

SENT Landfill

Non-inert C&D materials recycled, kg

0

151143

N/A

Chemical waste disposed, kg

500

9950

N/A

Marine Sediment (Type 1 – Open Sea Disposal) , m3

0

(Bulk Volume)

97428.2

(Bulk Volume)

South of Cheung Chau

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3

0

(Bulk Volume)

52250

(Bulk Volume)

East of Cha Chau

 

Dredged Sediment Requiring Type 3 – Special Treatment / Disposal contained in Geosynthetic Containers

0

 (Bulk Volume)

6773

(Bulk Volume)

East of Cha Chau

4.5.2.     There were no Marine Sediment (Type 1 – Open Sea Disposal) and no Marine Sediment (Type 1- Open Sea Disposal (Dedicate Sites) & Type 2- Confined Marine Disposal) disposed of in this reporting quarter.

Contract no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East

4.5.3.     Inert and non-inert C&D waste were disposed of for the site works in this reporting period. Details of the waste flow table are summarized in Table 4.17.

Table 4.17  Details of Waste Disposal for Contract no. HK/2009/02

Waste Type

Quantity this quarter

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

2948.985

236181.765

TKO137/ TM 38

Inert C&D materials recycled, m3

NIL

18161

N/A

Non-inert C&D materials disposed, m3

131.63

1030.20

SENT Landfill

Non-inert C&D materials recycled, m3

NIL

NIL

N/A

Chemical waste disposed, kg

1400

8836

SENT Landfill

Marine Sediment (Type 1 – Open Sea Disposal), m3

0

184167

(Bulk volume)

South of Cheung Chau

 

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal), m3

0

129320

(Bulk volume)

East of Sha Chau

 

4.5.4.     There were no Marine Sediment (Type 1 – Open Sea Disposal) and no Marine Sediment (Type 1- Open Sea Disposal (Dedicate Sites) & Type 2- Confined Marine Disposal) disposed of in this reporting quarter.

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

4.5.5.     No inert and non-inert C&D waste were disposed of for the site works in this reporting period. Details of the waste flow table are summarized in Table 4.18.

Table 4.18  Details of Waste Disposal for Contract no. HY/2009/15

Waste Type

Quantity this quarter

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

NIL

141579.2

Tuen Mun Area 38

NIL

65216

TKO137 FB

Inert C&D materials recycled, m3

NIL

304

Ex-PCWA

NIL

111.9

TS4

Non-inert C&D materials disposed, m3

NIL

252.2

SENT Landfill

 

Non-inert C&D materials recycled, kg

NIL

299361.5

N/A

Chemical waste disposed, kg

NIL

8,200

N/A

Marine Sediment (Type 1 – Open Sea Disposal) , m3

NIL

 

100,208

 (Bulk Volume)

South of Cheung Chau

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3

NIL

 

218,665

 (Bulk Volume)

 

East of Sha Chau

Marine Sediment (Type 3 – Special Treatment / Disposal contained in Geosynthetic Containers)

0

 

7,050

(Bulk Volume)

 

East of Sha Chau

Marine Sediment (Type 2 – Confined Marine Disposal), m3

1500

(Bulk Volume)

9350

(Bulk Volume)

East of Sha Chau

 

4.5.6.     There was Marine Sediment (Type 2 – Confined Marine Disposal) were disposed in this reporting quarter.

Contract no. HK/2010/06 - Wan Chai Development Phase II – Central –Wanchai Bypass over MTR Tsuen Wan Line

4.5.7.     Non-inert C&D and Inert C&D waste were disposed of for the site works in this reporting period. Details of the waste flow table are summarized in Table 4.19.

Table 4.19  Details of Waste Disposal for Contract no. HK/2010/06

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

480.08

12567.88

TM38

Inert C&D materials recycled, m3

0

267

HK/2009/01

Non-inert C&D materials disposed, m3

185

319.48

SENT/TKO137SF

Non-inert C&D materials recycled, m3

0

60.58

Recyclers

Chemical waste disposed, L

400

2600

N/A

Marine Sediment (Type 1 – Open Sea Disposal), m3

0

(Bulk Volume)

3,891

(Bulk Volume)

South Cheung Chau

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3

0

 (Bulk Volume)

12,586

(Bulk Volume)

East Sha Chau

4.5.8.     There was no Marine Sediment (Type 1- Open Sea Disposal) and no Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) were disposed in this reporting quarter.

Contract no. HY/2009/19 – Central- WanChai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

4.5.9.     Inert and non-inert C&D waste were disposed of in this reporting quarter

Table 4.20  Details of Waste Disposal for Contract no. HY/2009/19

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

49677.92

233001.09

TM38

Inert C&D materials recycled, m3

6675.62

47543.34

N/A

Non-inert C&D materials disposed, m3

68.91

412.45

N/A

Non-inert C&D materials recycled, kg

41.2

280.42

N/A

Chemical waste disposed, L

0

0.46

N/A

Marine Sediment (Type 1 – Open Sea Disposal), m3

0

162

South Cheung Chau

Marine Sediment (Type 2 – Confined Marine Disposal) , m3

0

681

East Sha Chau

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3

4976.00

4976.00

N/A

 

4.5.10.   There were no marine sediments Type1- Open Sea Disposal and there were Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal in the reporting period.

Contract no. HK/2012/08 –Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West

4.5.11.   Inert and non-inert C&D waste were disposed of in this reporting quarter. Details of the waste flow table are summarized in Table 4.21.

Table 4.21 Details of Waste Disposal for Contract no. HK/2012/08

Waste Type

Quantity this period

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

330

330

TM38

Inert C&D materials recycled, m3

NIL

NIL

N/A

Non-inert C&D materials disposed, m3

20

20

N/A

Non-inert C&D materials recycled, kg

NIL

NIL

N/A

Chemical waste disposed, L

NIL

NIL

N/A

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3

10890

12048

East of Sha Chau

4.5.12.   There was marine sediment Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal generated were disposed in this reporting period.

Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)

4.5.13.   No Inert C&D waste and non-inert C&D waste were disposed in this reporting period. Details of the waste flow table are summarized in Table 4.22

       Table 4.22 Details of Waste Disposal for Contract no. HY/2010/08

Waste Type

Quantity this period

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

NIL

NIL

N/A

Inert C&D materials recycled, m3

NIL

NIL

N/A

Non-inert C&D materials disposed, m3

NIL

NIL

N/A

Non-inert C&D materials recycled, kg

NIL

NIL

N/A

Chemical waste disposed, L

NIL

NIL

N/A

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3

NIL

NIL

N/A

 

 

5.         Compliance Audit

5.0.1.     The Event Action Plan for construction noise, air quality and water quality are presented in Appendix 5.1.

5.1.          Noise Monitoring

5.1.1       Seven limit level exceedances were recorded at M6 on 3, 13 June, 9, 16 July, 6, 20 and 27 August 2013. The limit level exceedances were considered as non-project related.

5.1.2       Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of graphical presentation can be referred in Appendix 4.1. 

5.2.          Real-time Noise Monitoring

5.2.1       No project related exceedance was recorded in June, July and August reporting month at RTN2a-Hong Kong Electric Centre during this reporting quarter.

5.2.2       Details of real time noise monitoring results and graphical presentation can be referred to Appendix 4.2

5.3.          Air Monitoring

5.3.1       No exceedance was recorded in 1-hr TSP and 24-hrs TSP monitoring in the reporting period.

5.4.          Water Quality Monitoring

5.4.1.     The summary of water quality exceedances recorded in reporting period is presented in the Table 5.1 and Table 5.1a.

 

 

 

 

 

 

 

 

 

 

Table 5.1    Summary of Water Quality Monitoring Exceedances in Reporting period

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HK/2009/01

WSD19

0

0

0

0

1

1

0

0

1

1

0

0

 

C1

0

0

0

0

0

0

0

0

0

0

0

0

 

P1

0

0

0

0

0

0

0

0

0

0

0

0

P3

0

0

0

0

0

0

0

0

0

0

0

0

P4

0

0

0

0

0

0

0

0

0

0

0

0

P5

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/02

C5e

0

0

0

0

0

0

0

0

0

0

0

0

 

C5w

0

0

0

0

0

0

0

0

0

0

0

0

Monitoring started on

8 Feb 2012

WSD21

0

0

0

0

0

0

9

0

0

0

1

2

WSD9

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD17

0

0

0

1

0

0

0

0

0

0

0

1

 

RW21-P789

0

0

0

0

0

0

0

0

0

0

0

0

HY/2009/15

C7

4

0

0

0

0

0

1

0

0

1

0

0

Total

4

0

0

1

1

1

10

0

1

2

1

3

Remarks: -      The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

                -     WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.

-    4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.

-     C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.

-   C8 & C9 was temporary suspended on 30 March 2013 due to the marine works for Contract no. HY/2009/19 had been completed on 4 March 2013

-     WSD7 and WSD20 were temporary suspended since 27 April 2012

 

 

5.4.2.     All exceedances in Table 5.1 have been investigated. Total 4 DO exceedances, 1 turbidity exceedances and 2 SS exceedances were recorded during mid-flood while 10 DO exceedance, 3 turbidity exceedances and 4 SS exceedances were recorded during mid-ebb in the reporting period. All the exceedances were concluded as non-project-related.

Table 5.1a      Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting period

 

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

DO

AL

LL

AL

LL

HY/2009/15

C6

0

0

1

0

C7

4

0

3

0

Ex-WPCWA SW

0

14

0

4

Ex-WPCWA SE

8

14

3

1

Total

12

28

7

5

 

5.4.3.     All exceedances in Table 5.1a have been investigated and were considered unlikely to be related to project works. The low DO levels were possible in relation to the low flow and recorded low water depth. In view that no odour nuisance was detected during monitoring, the DO exceedances were considered not related to the Project. These DO exceedances were considered as the natural variation and not related to the Project works.

5.5.          Site Audit

5.5.1.     There was no non-compliance from the site audits in the reporting period. During environmental site inspections conducted during the reporting period, minor deficiencies were noted.

5.6.          Review of the Reasons for and the Implications of Non-compliance

5.6.1       There was no non-compliance from the site audits in the reporting period.

5.7.          Summary of action taken in the event of and follow-up on non-compliance

5.7.1       There was no particular action taken since no project-related non-compliance was recorded from the site audits and environmental monitoring in the reporting period.

6.         Complaints, Notification of Summons and Prosecution

6.0.1.     There was no complaint received in this reporting period.

6.0.2.     The details of cumulative complaint log and summary of complaints are presented in Appendix 6.1.

6.0.3.     No notification of summons or prosecution was received in the reporting period. Cumulative statistic on complaints and successful prosecutions are summarized in Table 6.1 and Table 6.2 respectively.

 

Table 6.1    Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

Commencement works (Mar 2010) to last reporting period

28

March 2013- May 2013

0

Project-to-Date

28

 

Table 6.2    Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this quarter (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Water

-

0

0

Waste

-

0

0

Total

-

0

0

 

 

 

7.      Cumulative Construction Impact due to the Concurrent Projects

7.0.1.     According to Condition 3.4 of the EP-356/2009, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III, Central-Wanchai Bypass and Island Eastern Corridor Link projects.

7.0.2.     According to the Monthly EM&A report (July 2013) of Central Reclamation Phase III (CRIII), surface drainage and footpath construction adjacent to GPO, modification to the junction of Road D8 and Road P2 and modification of timber decks at advance promenade were performed in the August 2013 reporting month. The water quality monitoring was completed in October 2011 and no Project-related exceedance was recorded for air and noise monitoring.  It can be concluded that cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) was insignificant

7.0.3.     According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activity under Wan Chai Development Phase II were marine works at HKCEC areas, cross-harbour Watermains, Fresh Watermains and Cooling Watermains Installations, tunnel works at Wan Chai East, ELS work and pipe roofing works at TS4 and cut and cover tunnel construction at TPCWAE. Excavation and tunnel works at Central Interchange, ELS and box culvert construction at North Point area. The major environmental impact was water quality impact at Causeway Bay and Wan Chai. Land-based construction activities were diaphragm wall construction at TS2, ELS work and pipe roofing works at TS4, cut and cover tunnel construction at TPCWAE, tunnel works at Central and ELS work at North Point and tunnel works at Wan Chai East in the reporting month.

7.0.4.     The major environmental impacts generated from tunnel works at Central and tunnel works at Wan Chai East, IECL and Causeway Bay Typhoon Shelter were undertaken in the reporting month. No significant air impact from construction activities was anticipated in the reporting month. Besides, there was works-related limit level exceedance during water quality monitoring event in the reporting month and rectification measures have been implemented by contractor. Thus, it is evaluated that the cumulative construction impact from the concurrent projects including Wan Chai Development Phase II was insignificant.

8.         Conclusion

8.0.1.     The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

8.0.2.     No non-compliance was noted and no prosecution was received during the reporting period.

8.0.3.     The construction programmes of individual contracts are provided in Appendix 8.1.