Contract No: HK/2011/07

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 2)

 

Environmental Permit no. EP-356/2009,

Further Evironmental permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009

 Fep-06/356/2009 and FEP-07/356/2009

 

Quarterly Environmental Monitoring
and Audit Report

 

- June 2015 to August 2015 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

CHECKED by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

22 September 2015

 


Table of contents

 

EXECUTIVE SUMMARY. 4

1.     Introduction. 13

1.1        Scope of the Report 13

1.2        Structure of the Report 13

2.     Project Background. 14

2.1        Background. 14

2.2        Scope of the Project and Site Description. 14

2.3        Division of the Project Responsibility. 15

2.4        Project Organization and Contact Personnel 17

2.5        Principal Work and Activities. 18

3.     Monitoring Requirements. 21

3.1.       Noise Monitoring. 21

3.2.       Air Monitoring. 23

3.3        Water Quality Monitoring. 25

4.     Monitoring Results. 31

4.1.       Noise Monitoring Results. 31

4.2.       Real Time Noise Monitoring Results. 33

4.3.       Air Monitoring Results. 34

4.4        Water Monitoring Results. 36

4.5        Waste Monitoring Results. 42

5.     Compliance Audit. 47

5.1.       Noise Monitoring. 47

5.2.       Real-time Noise Monitoring. 47

5.3.       Air Monitoring. 47

5.4.       Water Quality Monitoring. 48

5.5.       Site Audit 50

5.6.       Review of the Reasons for and the Implications of Non-compliance. 50

5.7.       Summary of action taken in the event of and follow-up on non-compliance. 50

6.     Complaints, Notification of Summons and Prosecution. 51

7.     Cumulative Construction Impact due to the Concurrent Projects. 52

8.     Conclusion. 53


lIST OF TABLES

 

Table I              Principal Work Activities for Contract no. HK/2009/01

Table II             Principal Work Activities for Contract no. HK/2009/02

Table III            Principal Work Activities for Contract no. HY/2009/15

Table IV           Principal Work Activities for Contract no. HY/2009/19

Table V            Principal Work Activities for Contract no. HK/2012/08

Table VI           Principal Work Activities for Contract no. HY/2010/08

Table 2.1          Schedule 2 Designated Projects under this Project

Table 2.2          Details of Individual Contracts under the Project

Table 2.3          Contact Details of Key Personnel

Table 2.4          Principal Work Activities for Contract no. HK/2009/01

Table 2.5          Principal Work Activities for Contract no. HK/2009/02

Table 2.6          Principal Work Activities for Contract no. HY/2009/15

Table 2.7          Principal Work Activities for Contract no. HY/2009/19

Table 2.8          Principal Work Activities for Contract no. HK/2012/08

Table 2.9          Principal Work Activities for Contract no. HY/2010/08

Table 3.1          Noise Monitoring Stations

Table 3.2          Real Time Noise Monitoring Station

Table 3.3          Air Monitoring Stations

Table 3.4          Marine Water Quality Stations for Water Quality Monitoring

Table 3.5          Marine Water Quality Monitoring Frequency and Parameters

Table 3.6          Marine Water Quality Stations for Enhanced Water Quality Monitoring

Table 4.1          Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02

Table 4.2          Noise Monitoring Station for Contract nos. HY/2009/15

Table 4.3          Noise Monitoring Stations for Contract no.  HY/2009/19

Table 4.4          Noise Monitoring Stations for Contract no. HY/2010/08

Table 4.5          Real Time Noise Monitoring Station for Contract no. HY/2009/19

Table 4.6          Air Monitoring Stations for Contract no. HK/2009/01

Table 4.7          Air Monitoring Station for Contract no. HK/2009/02

Table 4.8          Air Monitoring Station for Contract no. HY/2009/15

Table 4.9          Air Monitoring Stations for Contract no. HY/2009/19

Table 4.10        Water Monitoring Stations for Contract no. HK/2009/01

Table 4.11        Water Monitoring Stations for Contract no. HK/2009/02

Table 4.12        Water Monitoring Stations for Contract no. HK/2012/08

Table 4.13        Water Monitoring Stations for Contract no. HY/2009/15

Table 4.14        Summary of Water Quality Monitoring Exceedances in Reporting period

Table 4.15        Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting period

Table 4.16        Details of Waste Disposal for Contract no. HK/2009/01

Table 4.17        Details of Waste Disposal for Contract no. HK/2009/02

Table 4.18        Details of Waste Disposal for Contract no. HY/2009/15

Table 4.19        Details of Waste Disposal for Contract no. HY/2009/19

Table 4.20        Details of Waste Disposal for Contract no. HK/2012/08

Table 4.21        Details of Waste Disposal for Contract no. HY/2010/08

Table 5.1          Summary of Water Quality Monitoring Exceedances in Reporting period

Table 5.2          Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting period

Table 6.1          Cumulative Statistics on Complaints

Table 6.2          Cumulative Statistics on Successful Prosecutions

 

 

 

 

 

 

 

 

lIST OF FIGUREs

 

Figure 2.1         Project Layout

Figure 2.2         Project Organization Chart

Figure 3.1         Locations of Environmental Monitoring Stations

 

 

 

 

lIST OF APPENDIces

 

Appendix 2.1    Environmental Mitigation Implementation Schedule

Appendix 3.1    Action and Limit Level

Appendix 4.1    Noise Monitoring Graphical Presentations

Appendix 4.2    Air Quality Monitoring Graphical Presentations

Appendix 4.3    Water Quality Monitoring Graphical Presentations

Appendix 4.4    Real-time Noise Monitoring Results and Graphical Presentations

Appendix 5.1    Event Action Plans

Appendix 6.1    Complaint Log

Appendix 7.1    Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

  1. This is the Quarterly Environmental Monitoring and Audit (EM&A) Report – June 2015 to August 2015 prepared for the Project of Wan Chai Development Phase II and Central-Wanchai Bypass under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-06/356/2009 and FEP-07/356/2009. This report presents the environmental monitoring and audit findings and information during the period from June 2015 to August 2015. The cut-off date of reporting is at 27th of each reporting period.

 

Construction Activities for the Reported Period

  1. During this reporting period, the principal work activities for Contract no. HK/2009/01 are summarized as below:

Table I        Principal Work Activities for Contract no. HK/2009/01

June 2015

July 2015

August 2015

Ÿ   Nil

Ÿ  Nil

Ÿ    Nil

 

  1. During this reporting period, the principal work activities for Contract no. HK/2009/02 are summarized as below:

Table II       Principal Work Activities for Contract no. HK/2009/02

June 2015

July 2015

August 2015

Ÿ   Nil

Ÿ   Excavation and trimming trenches for caisson seawall at WCR3

Ÿ   Rock filling works at WCR3

Ÿ   Placing levelling stone for construction of seawall at WCR3

Ÿ   Rock filling works at WCR3

 

  1. Contract no. HY/2009/15 was commenced on 10 November 2010. During this reporting period, the principal work activities for Contract no. HY/2009/15 are summarized as below:

Table III      Principal Work Activities for Contract no. HY/2009/15

June 2015

July 2015

August 2015

·         Reinstatement of vertical seawall at TPCWAE

·         Dredging work near Noon Day Gun

·          Reinstatement of vertical seawall at TPCWAE

 

·          Reinstatement of vertical seawall at TPCWAE

 

  1. Contract no. HY/2009/19 was commenced on 24 March 2011. During this reporting period, the principal work activities for Contract no. HY/2009/19 are summarized as below:

 

Table IV     Principal Work Activities for Contract no. HY/2009/19

June 2015

July 2015

August 2015

Ÿ  Nil

Ÿ  Nil

Ÿ   Nil

 

  1. Contract no. HK/2012/08 was commenced on 5 March 2013. During this reporting period, the principal work activities for Contract no. HK/2012/08 are summarized as below:

Table V      Principal Work Activities for Contract no. HK/2012/08

June 2015

July 2015

August 2015

Ÿ   Removal of rock armour

Ÿ   Dry dock construction

Ÿ   Installation of pipe pile wall

Ÿ   Removal of temporary piling platform for culvert diversion

Ÿ   Construction of culvert

Ÿ   Dry dock construction

Ÿ   Installation of pipe pile wall

Ÿ   Removal of temporary piling platform for culvert diversion

Ÿ   Construction of culvert

Ÿ   Dry dock construction

Ÿ   Installation of pipe pile wall

Ÿ   Removal of temporary piling platform for culvert diversion

Ÿ   Construction of culvertl

 

 

  1. Contract no. HY/2010/08 was commenced on 21 March 2013. During this reporting period, the principal work activities for Contract no. HY/2010/08 are summarized as below:

Table VI     Principal Work Activities for Contract no. HY/2010/08

June 2015

July 2015

August 2015

Ÿ   Rock filling works

Ÿ   Pre-treatment works

Ÿ   Bar fixing works

Ÿ   ELS works

Ÿ   Diaphragm Wall, Barrette construction and King Post installation works

Ÿ   Slurry and fill disposal works

Ÿ   Diversion pipe maintenance

Ÿ   Diversion pipe maintenance

 

Noise Monitoring

  1. Noise monitoring during day time and evening time were conducted at the M1a, M2b, M3a, M4b, M5b and M6 on a weekly basis in the reporting period. The Action and Limit level exceedances recorded in the reporting period are listed below. Investigation found that exceedances were not related to the Project. Investigation found that exceedances were not related to the Project.
  2. Three limit level exceedances at M6 – HK Baptist Church Henrietta Secondary School were recorded on 5, 9 and 16 June 2015 in June reporting month. The exceedances were concluded as non-Project works.
  3. No action and limit level exceedance was recorded in July reporting month.
  4. No action and limit level exceedance was recorded in August reporting month.

 

 

Real-time Noise Monitoring

  1. As the land-based piling and filling works- DP3 at Tin Hau had been completed on 3 September 2012 and confirmed by RSS, the real-time noise monitoring results at FEHD Hong Kong Transport Section Whitfield Depot was excluded under EP-356/2009 since 28 November 2012.
  2. Real-time noise monitoring at FEHD Hong Kong Transport Section Whitefield Depot and Oil Street Community Centre have been commenced on 5 October 2010 for the filling works of Contract no. HY/2009/11.
  3. Real-time noise monitoring at FEHD Hong Kong Transport Section Whitefield Depot commenced external wall renovation since 1 June 2012
  4. Oil Street Community Liaison Centre was confirmed to be demolished in mid-October by CWB RSS.  This presented a need for relocation of RTN2 – Oil Street Community Liaison Centre.  After liaison with Hong Kong Electric, permission was granted on 21 Sep 2012 for real time noise monitoring set up at City Garden Electric Centre (RTN2a – Electric Centre), which is a representative of the noise sensitive receiver City Garden.  The real-time noise monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct 2012. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.
  5. No project related exceedance was recorded in June reporting months at RTN2a-Hong Kong Electric Centre.
  6. No limit level exceedance was recorded in July reporting month at RTN2a-Hong Kong Electric Centre.
  7. No limit level exceedance was recorded in August reporting month at RTN2a-Hong Kong Electric Centre.

 

Air Quality Monitoring

  1. Due to electricity interruption, the following 24hr and 1hr TSP monitoring events were rescheduled in this reporting quarter,

24hr TSP monitoring at CMA4a was rescheduled from 18 June 2015 to 19 June 2015

24hr TSP monitoring at CMA1b was rescheduled from 4 and 10 July 2015 to 6 and 11 July 2015 respectively.

24hr TSP monitoring at CMA3a was rescheduled from 29 June 2015 to 30 June 2015.

24hr TSP monitoring at CMA6a was rescheduled from 29 June 2015 to 30 June 2015.

24hr TSP for CMA1b was rescheduled from 28 July 2015 and 26 August 2015 to 29 July 2015 and 27 August 2015 respectively.

24hr TSP for CMA6a was rescheduled from 26 August 2015 to 29 August 2015.

1hr TSP for CMA6a was rescheduled from 27 August 2015 to 28 August 2015.

  1. There were no action level and limit level exceedance of air quality monitoring recorded in June reporting month.
  2. There were no action level and limit level exceedance of air quality monitoring recorded in July reporting month.
  3. One action level exceedance during 24hr TSP monitoring was recorded at monitoring station CMA2a – Causeway Bay Community Centre on 26 August 2015 in August reporting month. Investigation found that the exceedance recorded was not related to the Project.
  4. Two action level exceedances during 1hr TSP monitoring was recorded at monitoring station CMA2a – Causeway Bay Community Centre on 27 August 2015 in August reporting month. Investigation found that the exceedance recorded was not related to the Project.
  5. The odour patrol along the odour route with 7 sniffing locations was conducted by a qualified odour patrol member on 7 and 21 July 2015 at the concerned hours (afternoon for higher daily temperature). No Action and Limit Level was recorded during July reporting month.
  6. The odour patrol along the odour route with 7 sniffing locations was conducted by a qualified odour patrol member on 4 and 18 August 2015 at the concerned hours (afternoon for higher daily temperature). No Action and Limit Level was recorded during August reporting month.
  7. The location ID of air monitoring station CMA1b was updated as Oil Street Site Office in April 2013.
  8. With respect to the area handover, the air quality monitoring station CMA5a at Children Playgrounds opposite to the Pedestrian Plaza was relocated to the Pedestrian Plaza on 3 December 2014. The station reference and location ID of the air quality monitoring station CMA5a was updated as CMA5b and Pedestrian Plaza respectively.
  9. 1hr and 24hr TSP monitoring were conducted at CMA1b, CMA2a, CMA3a, CMA4a, CMA5b and CMA6a in the reporting period.

 

Water Quality Monitoring

  1. Action and Limit level of water quality monitoring was transited from dry season to wet season from 1 April 2015.
  2. With respect to the construction stage and access condition at Ex-PCWAW and the potential DO concern within the area, the suspended Enhance DO monitoring within Ex-PCWAW area at the Enhance DO monitoring station Ex-PCWA-SE was resumed on 10 August 2015 at the finely adjusted monitoring location.
  3. Due to the hoisting of amber rainstorm warning signal, the water quality monitoring on 22 July 2015 during flood tide and ebb tide were cancelled.
  4. With respect to the maintenance works for the diverted seawater supply system to Windsor House Cooling water intake and the suspension of seawater supply to Windsor House from the water storage tank for water quality sampling from 7 July 2015 to 13 July 2015. The respective water quality monitoring at WQM station C7 was cancelled on 8 July 2015 and was temporarily suspended from 9 July 2015 to 13 July 2015. The aforesaid monitoring station was resumed on 15 July 2015 upon completion of the maintenance works.
  5. With respect to the water pipe modification works and the suspension of water supply to Windsor House from the water storage tank for water quality sampling, the water quality monitoring station C7 was cancelled on 10 June 2015 during flood tide.
  6. With respect to the water pipe modification works conducted for the diverted seawater supply system to the Windsor House Cooling water intake and the suspension of water supply to Windsor House from the water storage tank for water quality sampling, the respective water quality monitoring at WQM station C7 was temporarily suspended from 12 June 2015. The water quality monitoring at WQM station C7 has resumed on 17 June 2015 upon completion of the water pipe modification works.
  7. With respect to the construction works undertaken at Ex-PCWAW and the forthcoming wet season DO concern, the suspended Enhance DO monitoring within Ex-PCWAW area at the Enhance DO monitoring station Ex-PCWA-SW was resumed on 30 March 2015 at the finely adjusted monitoring location.
  8. With respect to the commencement of seawall modification works at Ex-PCWAE and the location of the Enhance DO monitoring stations would form an active construction area, the Enhance DO monitoring at monitoring station EX-PCWA SW and SE were temporarily suspended from 2 March 2015 ebb tide and the monitoring at the location is tentatively to be resumed by early April 2015 to cater for the potential DO concern during Wet Season.

xxxvii.        As informed by CWB RSS, the operation of the diverted Windsor House cooling intake was commenced on 20 Dec 2014 and the water quality monitoring at monitoring station C7 for Windsor House Cooling water intake was resumed on 22 Dec 2014.

  1. Water quality monitoring was conducted at 8 monitoring stations namely WSD19, C1, C7, P1, P3, P4, P5 and RW21-P789 during the reporting period.
  2. There were no action level and 1 limit level of turbidity exceedance recorded, and no action and 1 limit level of suspended solid exceedance recorded in June reporting month. Investigation found that the exceedances were not related to Project works.
  3. There was no action and 1 limit level of turbidity exceedance recorded in July reporting month. Investigation found that the exceedance was not related to Project works.
  4. There was no action and no limit level of exceedance recorded in August reporting month.
  5. Enhanced DO monitoring at 4 monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was conducted three days per week during the reporting period.
  6. There were 2 action level and 3 limit level exceedances of enhanced dissolved oxygen recorded in June reporting month. Investigation found that the exceedance was not related to Project works.
  7. There were no action level and 4 limit level exceedances of enhanced dissolved oxygen recorded in July reporting month. Investigation found that the exceedances were not related to Project works.
  8. There were 4 action level and 7 limit level exceedances of enhanced dissolved oxygen recorded in August reporting month. Investigation found that the exceedances were not related to Project works.

xlvi.        With respect to the commencement of temporary reclamation works and seawall construction at Ex-PCWAW zone and diverted culvert extension, the location of the Enhance DO monitoring stations (Ex-PCWASW and Ex-PCWA SE) were finely adjusted to the PCWAE since 7 November 2014.

  1. With respect to the commencement of marine dredging works at WCR3 under contract HK/2009/02. The respective water quality monitoring station C1 were associated with HK/2009/01 and HK/2009/02.
  2. As confirmed by CWB RSS, the operation of the pump station for Windsor House Cooling Water was suspended from 22 Oct 2014 for the Windsor House intake cooling intake scheme and temporary supply of freshwater from WSD water mains was provided to cooling water intake The water quality monitoring for the respective cooling water intake at WQM station C7 was temporarily suspended from 22 Oct 2014.
  3. With respect to the commencement of filling works at TS3 and the formation of TZ3 reclamation zone, the enhance DO monitoring at Enhance monitoring station C7 was temporarily suspended from 22 Oct 2014.
  4. As confirmed by WDII RSS and IEC, the cross harbor dredging works have completed since 16 March 2012 while the dredging works for submarine outfall pipeline has completed since 29 November 2011, considering current construction stage and dredging Scenario, the water quality monitoring at stations WSD9 and WSD17 was temporarily suspended since 8 September 2014 flood tide.
  5. As advised by WDII RSS, the water quality monitoring for WSD21 pump station with respect to HK/2009/02 was switched over to the relocated location since 12 March 2014. According to the EM&A Manual, the water quality monitoring station WSD21 was relocated to station RW21-P789 and the water quality monitoring at station WSD21 was temporarily suspended since 12 March 2014.
  6. With respect to the switching over of cooling water intake location, the water quality monitoring at the relocated intake station RW21-P789 under HK/2009/02 was commenced since 29 July 2013 and monitoring station C5e and C5w were temporarily suspended and switched over to monitoring station RW21-P789 on 29 July 2013 due to suspension of pump house operation.
  7. With respect to the commencement of dredging works under HK/2012/08 and the installation of MTR precast protection unit, the enhanced water quality monitoring for Culvert L was temporarily suspended since 24 July 2013.
  8. With respect to the commencement of marine dredging works under contract HY/2010/08. The respective water quality monitoring station C7 were associated with HY/2009/15 and HY/2010/08.
  9. With respect to the commencement of marine dredging works under contract HK/2012/08/ The respective water quality monitoring station WSD19, P1, P3, P4, and P5 were associated with Contract HK/2012/08 Since September 2013.
  10. WQM events on 22 April 2013 at monitoring stations C2, C3, C4e and C4w were temporarily suspended. Upon confirmation with WDII RSS and the IEC, water quality monitoring at relocated intakes monitoring location P1, P3, P4 and P5 were commenced since 24 April 2013.
  11. Due to the marine piling under Contract no. HY/2009/19 was completed on 4 March 2013, the temporary suspension of impact water quality monitoring at C8 and C9 from 4 March 2013 have been monitored for 4-week period after the completion of marine works to confirm no water deterioration.
  12. As confirmed by CWB RSS, the marine pilling works under contract HY/2009/19 was confirmed completed by 4 March 2013. The water quality monitoring at the respective monitoring stations C8 and C9 were temporarily suspended since 30 March 2013.
  13. RSS confirmed that all Type III Dredging works under HK/2009/01 have been completed since Oct 2012.
  14. Due to the presence of obstacle within the inner silt curtain frame at sampling point, water quality point at C7 was finely adjusted to the outside of the inner silt curtain frame since 29 Dec 2012.
  15. With respect to the trial dredging at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3 , 11, 13, 15, 17, 19, 20 Apr and 3 May 2012, on-going water quality monitoring results at WSD21 during this period was checked and indicated that there was no contribution due to the trial dredging operation.  Enhanced review of water quality around WCR2 was also implemented and no deterioration in the water quality was observed.
  16. Due to the access of water monitoring station at WSD19 was blocked by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the inaccessibility of sampling either land and marine, there is a fine adjustment of the sampling point of WSD 19 since 5 April 2012 to the closest accessible point prior to the completion of the construction activities.
  17. WDII/RSS advised that the dredging works for submarine pipeline at Victoria Harbour had been completed in January 2012. Therefore, the concurrent dredging activities at Sewage Pipeline Zone and reclamation shoreline zone TCBR under the EP-356/2009 scenario 2B no longer exist. As such, with reference to Table 5.39 of the EIA Report for Wan Chai Development Phase II and Central-Wan Chai Bypass, the application of silt screen for cooling water intakes for Queensway Government Offices was suspended and the others remain unchanged.
  18. Due to the dredging works for Cross Harbour Water Mains from Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April 2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for 4-week period after the completion of DP6 to confirm no water deterioration. Water quality monitoring at WSD10 and WSD15 was temporary suspended while water quality monitoring at WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8 Feb 12 onwards;
  19. Based on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no water deterioration with respect to NPR was commenced since 7 Jan 2012 and it was completed on 6 February 2012.
  20. Based on the safety concern when external façade refurbishment was conducted by contractor employed by Provident Centre (C9) between 9 January 2012 to 30 July 2012 which caused to the inaccessibility of sampling either land and marine since 3 Feb 2012, there is a fine adjustment of the sampling location of water quality monitoring at C9 since 10 March 2012 to the closest accessible point prior to the completion of the external façade refurbishment work.
  21. Water quality monitoring at C8 and C9 have been implemented with respect to HY/2009/19 since the marine bore piling work started on 28 Jan 12.
  22. In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be installed to channel water discharge flow from Culvert L to locations outside the embayment area, a proposed replacement of the requirement with additional dissolved oxygen monitoring has been conducted at three monitoring stations, namely A, B and C between the eastern seawall of Central Reclamation Phase III and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level between the eastern seawall of Central Reclamation Phase II and the HKCEC extension could be continuously monitored.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. There was one environmental complaint received in June reporting months.
  2. The public complaint regarding dark smoke and malodour concern referred by EPD was received by ET on 22 June 2015 (EPD Ref.: H05/RS/00015054-15 dated 22 June 2015). The complainant reported that dark smoke and malodour emission was observed from a hopper barge moored near shore and other construction plants under operation from the reclamation construction site with Contract no. HK/2009/02 at location outside Wan Chai Sports Ground caused air pollution. The complainant alleged that the said situation had been observed for a prolonged period.

 

ET confirmed with the Resident Site Staff that reinforced bar fixing and concreting work (on 17 June 2015 only) were conducted at Portion 2 from 15 June 2015 to 19 June 2015. Total 3 nos. of mobile crane were in operation. On 17 June 2015, one no. of concrete pump truck and two nos. of concrete mixer were in operation. Excavation and Lateral Support was conducted at Portions 3 & 4 from 15 June 2015 to 19 June 2015. Total 4 nos. of excavator, 2 nos. of truck and 2 nos. of crawler crane were in operation. In addition, on 15 June 2015, 17 June 2015 and 19 June 2015, 1 no. of derrick barge was moored near Portions 3 & 4 for transportation of the excavated material away from site.

 

According to the relevant site records under Contract HK/2009/02, from 15 June 2015 to 19 June 2015, reinforced bar fixing and concreting work (on 17 June 2015 only) were conducted at Portion 2 and total 3 nos. of mobile crane, one no. of concrete pump truck (on 17 June 2015 only) and two nos. of concrete mixer (on 17 June 2015 only) were in operation; excavation and lateral support was conducted at Portions 3 & 4 and total 4 nos. of excavator, 2 nos. of truck and 2 nos. of crawler crane were in operation. Based on relevant site record, no hopper barge was moored under Contract HK/2009/02 around the concerned location while 1 no. of derrick barge was moored under Contract HK/2009/02 near Portions 3 & 4 for transportation of the excavated material from Portions 3 & 4 away from site on 15 June 2015, 17 June 2015 and 19 June 2015 respectively.

 

Follow-up inspection was conducted during weekly environmental inspection on 25 June 2015, no dark smoke and malodour emission was observed from the PMEs operating on-site. A derrick barge was observed moored near Portions 3 & 4 and excavated material was transferred to the derrick barge by the excavators on land without barge operation and no particular dark smoke and malodour emission was observed. Nevertheless, the Contractor was reminded to conduct regular checking on the condition of the derrick barge and other PMEs deployed on site to ensure only well maintained PMEs are used to avoid potential dark smoke and maldour emission affecting nearby public

 

  1. There was one environmental complaint received in July reporting month.

 

  1. A public complaint regarding malodour referred by EPD was received by ET on 23 July 2015 (EPD Ref.: H05/RS/00018040-15 dated 23 July 2015).

 

The complainant reported that malodour from marine sediment was scented at ex-Wanchai ferry pier near route 720 & 722 bus stop. (Contract HK/2009/02). ET confirmed with the Resident Site Staff that Rockfill placing works was conducted by one derrick barge at the concerned location (WCR3) under Contract HK/2009/02 on 20 July 2015. No marine sediment was stored or placed on site at the concerned location under Contract HK/2009/02 on 20 July 2015.

 

According to the relevant site records under Contract HK/2009/02, rockfill placing works was conducted by one derrick barge at WCR3 area on 20 July 2015 and no marine sediment was stored or placed on site at the concerned location on the concerned date.

 

Follow-up inspection was conducted during weekly environmental inspection on 29 July 2015. No marine sediment was observed stored or placed at the concerned location while it was noted that a culvert outfall with potential odour concern is located adjacent to the concerned location.

 

Nevertheless, the Contractor was reminded to review the handling procedures in case of any future marine sediment handling at the concerned location and to consider the implementation of mitigation measures as appropriate to minimize potential malodour impact to nearby public.

 

  1. There was no environmental complaint received in August reporting month.

1.         Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-06/356/2009 and FEP-07/356/2009  to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.4 of EM&A Manual and “Environmental Monitoring and Audit Requirements” under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works during the period from June 2015 to August 2015.

1.2          Structure of the Report

 

Section 1          Introduction – details the scope and structure of the report.

 

Section 2          Project Background – summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3          Monitoring Requirements – summarizes all monitoring parameters, monitoring locations, monitoring frequency, duration and action plan.

 

Section 4          Monitoring Results – summarizes the monitoring results obtained in the reporting period.

 

Section 5          Compliance Audit – summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 6          Complaints, Notification of summons and Prosecution – summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 7          Cumulative Construction Impact due to the Concurrent Projects summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8          Conclusion

2.         Project Background

2.1          Background

2.1.1.     “Wan Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2          Scope of the Project and Site Description

2.2.1.     The Project is located mainly in Wan Chai North, Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road Interchange to the east, as shown in Figure 2.1.

2.2.2.     The study area encompasses existing developments along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police Officers' Club, the Causeway Bay Typhoon Shelter (CBTS) and commercial and residential developments.

2.2.3.     The scope of the Project comprises:

·          Land formation for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for connection to the Trunk Road and for through traffic from Central to Wan Chai and Causeway Bay. The land formed for the above transport infrastructure will provide opportunities for the development of an attractive waterfront promenade for the enjoyment of the public

·          Reprovisioning / protection of the existing facilities and structures affected by the land formation works mentioned above

·          Extension, modification, reprovisioning or protection of existing storm water drainage outfalls, sewerage outfalls and watermains affected by the revised land use and land formation works mentioned above

·          Upgrading of hinterland storm water drainage system and sewerage system, which would be rendered insufficient by the land formation works mentioned above

·          Provision of the ground level roads, flyovers, footbridges, necessary transport facilities and the associated utility services

·          Construction of the new waterfront promenade, landscape works and the associated utility services

·          The Trunk Road (i.e. CWB) within the study area and the associated slip roads for connection to the Trunk Road.

 

2.2.4.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

 

2.3          Division of the Project Responsibility

2.3.1       Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HK/2010/06 – Wan Chai Development Phase II – Central – Wan Chai Bypass over MTR Tsuen Wan Line under FEP-05/356/2009

2.3.2       The construction works were completed and the FEP-05/356/2009 was surrendered by the Contractor on 3 October 2014.

Contract no. HY/2009/11 – Wan Chai Development Phase II – Central – Wan Chai Bypass - North Point Reclamation

2.3.3       The construction works were completed and the FEP-01/356/2009 was surrendered by the Contractor on 22 October 2012.

2.3.4       Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits (FEP) such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.5       The details of individual contracts are summarized in Table2.2.

Table 2.2    Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HK/2009/01

Wan Chai Development Phase II – Central –Wanchai Bypass at Hong Kong Convention and Exhibition Centre

DP3, DP6

23 July 2010

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East

DP3, DP5

5 July 2010

DP1

26 April 2011

HY/2009/11

Wan Chai Development Phase II and Central – Wan Chai Bypass – North Point Reclamation

DP3

17 March 2010

(Completed)

HY/2009/15

Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

DP3

10 November 2010

DP1

13 July 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

(Completed)

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

(Completed)

HY/2009/17

Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works.

DP1

5 October 2010

(Completed)

HY/2009/18

Central - Wan Chai Bypass (CWB) – Central Interchange

DP1

10 March 2014

HY/2009/19

Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

HK/2012/08

Wan Chai Development Phase II Central-

Wan Chai Bypass at Wan Chai

West

DP1,DP2, DP3

5 March 2013

HY/2011/08

Central-Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

DP1

8 October 2014

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer’s Representative  for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer’s Representative  for CWB

Principal Resident Engineer

Mr. Peter Poon

3912 3388

3912 3010

Chun Wo – Leader Joint Venture

Contractor under Contract no. HK/2009/01

Project Manager

Mr. Simon Liu

9304 8355

2587 1878

Site Agent

Mr. Andy Yu

9648 4896

Engineer Manager

Mr. Terry Wong

9757 9846

Construction Manager

Mr. Wyman Wong

9627 2467

Construction Manager

Mr. Kenneth Chan

9160 3850

Environmental Officer

Ms. Wendy Ng

9803 0057

Assistant Environmental Engineer

Miss. Connie Chan

6157 7057

Chun Wo – CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Project Manager

Mr. Paul Yu

3658-3085

2827 9996

Quality & Environmental Manager

Mr. C.P. Ho

9191 8856

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Chris Leung

3557 6393

 

2566 2192

 

Site Manager

Y Huo

3557 6368

 

Contractor’s Representative

Andrew Wong

3557 6358

 

 

Contractor’s Representative

Gene Cheung

3557 6395

 

 

Environmental Officer

Andy Mak

3557 6347

Chun Wo - CRGL - MBEC Joint Venture

Contractor under Contract no. HY/2009/19

 

Project Manager

David Lau

3758 8879

2570 8013

Deputy Project Manager

William Luk

3757 8901

Environmental Manager /

Environmental Officer

Eric Fong

6191 9337

Construction Manager (Marine)

M.H. Isa

9884 0810

Construction Manager

(Land)

Andy Chan

9879 4325

Construction Manager

(Land)

Bear Ding

6483 6198

Operation Manager (Land)

Yung Kwok Wah

9834 1010

China State-

Leader JV

Contractor

under Contract

no. HK/2012/08

Project Director

C. N. Lai

9106 5806

2877 1522

Project Manager

Eddie Chung

9189 8118

 

 

 

Site Agent

Keith Tse

9037 1839

 

Environmental Officer

James Ma

9130 9549

 

Environmental Supervisor

Y. L. Ho

9856 5669

 

China State

 

Contractor

under Contract

no. HY/2010/08

Project Director

Chris Leung

3467 4299

2566 8061

Project Manager

Chan Ying Lun

3418 3001

 

Site Agent

Dave Chan

3467 4277

 

 

 

Environmental Officer

Gabriel Wong

35576466

 

 

 

Environmental Supervisor

Desmond Ho Tsz Ho

3557 6466

 

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

34652888

34652899

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

2.5          Principal Work and Activities

2.5.1.     During this reporting period, the principal work activities for Contract no. HK/2009/01 are summarized in Table 2.4.

 

 

Table 2.4    Principal Work Activities for Contract no. HK/2009/01

June 2015

July 2015

August 2015

Ÿ   Nil

Ÿ  Nil

Ÿ    Nil

 

2.5.2.     During this reporting period, the principal work activities for Contract no. HK/2009/02 are summarized in Table 2.5.

Table 2.5    Principal Work Activities for Contract no. HK/2009/02

June 2015

July 2015

August 2015

Ÿ   Nil

Ÿ   Excavation and trimming trenches for caisson seawall at WCR3

Ÿ   Rock filling works at WCR3

Ÿ   Placing levelling stone for construction of seawall at WCR3

Ÿ   Rock filling works at WCR3

 

2.5.3.     Major construction activities for Contract no. HY/2009/15 was commenced on 10 November 2010. During this reporting period, the principal work activities for Contract no. HY/2009/15 are summarized as below:

Table 2.6    Principal Work Activities for Contract no. HY/2009/15

June 2015

July 2015

August 2015

·         Reinstatement of vertical seawall at TPCWAE

·         Dredging work near Noon Day Gun

·          Reinstatement of vertical seawall at TPCWAE

 

·          Reinstatement of vertical seawall at TPCWAE

 

2.5.4.     Contract no. HY/2009/19 was commenced on 24 March 2011. During this reporting period, the principal work activities for Contract no. HY/2009/19 are summarized as below:

Table 2.7    Principal Work Activities for Contract no. HY/2009/19

June 2015

July 2015

August 2015

Ÿ  Nil

Ÿ  Nil

Ÿ   Nil

 

2.5.5.     Contract no. HK/2012/08 was commenced on March 2013. During this reporting period, the principal work activities for Contract no. HK/2012/08 are summarized as below:

Table 2.8    Principal Work Activities for Contract no. HK/2012/08

June 2015

July 2015

August 2015

Ÿ   Removal of rock armour

Ÿ   Dry dock construction

Ÿ   Installation of pipe pile wall

Ÿ   Removal of temporary piling platform for culvert diversion

Ÿ   Construction of culvert

Ÿ   Dry dock construction

Ÿ   Installation of pipe pile wall

Ÿ   Removal of temporary piling platform for culvert diversion

Ÿ   Construction of culvert

Ÿ   Dry dock construction

Ÿ   Installation of pipe pile wall

Ÿ   Removal of temporary piling platform for culvert diversion

Ÿ   Construction of culvertl

 

 

2.5.6.     Contract no. HY/2010/08 was commenced on 21 March 2013. During this reporting period, the principal work activities for Contract no. HY/2010/08 are summarized as below:

Table 2.9    Principal Work Activities for Contract no. HY/2010/08

June 2015

July 2015

August 2015

Ÿ   Rock filling works

Ÿ   Pre-treatment works

Ÿ   Bar fixing works

Ÿ   ELS works

Ÿ   Diaphragm Wall, Barrette construction and King Post installation works

Ÿ   Slurry and fill disposal works

Ÿ   Diversion pipe maintenance

Ÿ   Diversion pipe maintenance

 

2.5.7.     Implementation status of the recommended mitigation measures during this reporting period is presented in Appendix 2.1.

3.         Monitoring Requirements

3.1.          Noise Monitoring

Noise Monitoring Stations

3.1.1.     The noise monitoring stations for the Project are listed and shown in Table 3.1 and Figure 3.1.  Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.1    Noise Monitoring Stations

Station

Description

M1a

Harbour Road Sports Centre

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

 

Real time Noise Monitoring Stations

3.1.2.     The real-noise monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

3.1.3.     The real-time noise monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct 2012, which is a representative of noise sensitive receiver- City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.

3.1.4.     As the land-based piling and filling works- DP3 at Tin Hau had been completed on 3 September 2012 and confirmed by RSS, the real-time noise monitoring results at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot was excluded under EP-356/2009 since 28 November 2012.

Table 3.2    Real Time Noise Monitoring Station

District

Station

Description

North Point

RTN2

Oil Street Community Liaison Centre

North Point

RTN2a

Electric Centre

l   Real time noise monitoring results and graphical presentation during night time period are for information only.

l   RTN2 had been relocated to RTN2a since 5 Oct 2012

 

 

 

Noise Monitoring Parameters, Frequency and Duration

3.1.5.     The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

3.1.6.     Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

·          one set of measurements between 0700 and 1900 hours on normal weekdays.

3.1.7.     If construction works are extended to include works during the hours of 1900 – 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

3.1.8.     Real time noise shall be carried out at the designated monitoring stations. The following is an initial guide on the regular monitoring frequency for each station on a 24 hours daily basis when noise generating activities are underway:

·          One set of measurements between 0700 and 1900 hours on normal weekdays.

·          One set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.

·          One set of measurements between 2300 and 0700 hours on next day on everyday.

 

Monitoring Equipment

3.1.9.     As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

3.1.10.   Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

 

 

3.2.                Air Monitoring

Air Quality Monitoring Stations

3.2.1.     The air monitoring stations for the Project are listed and shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.3    Air Monitoring Stations

Station ID

Monitoring Location

Description

CMA1b

Oil Street Site Office**

North Point

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

CWB PRE Site Office *

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5b

Pedestrian Plaza***

Wan Chai

CMA6a

WDII PRE Site Office *

Wan Chai

* Remarks: As per the ENPC meeting in January 2011, the monitoring stations CMA3a - Future CWB site office at Wanchai Waterfront Promenade and CMA6a - Future AECOM site office at Work Area were renamed as remark.

Remarks**: The location ID of monitoring station CMA1b was updated as “Oil Street Site Office” in April 2013.

Remarks***: The station ID and monitoring location was updated in December 2014 with respect to monitoring station relocation.

 

Air Monitoring Parameters, Frequency and Duration

3.2.2.     One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

3.2.3.     All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

3.2.4.     For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.

Sampling Procedure and Monitoring Equipment

3.2.5       High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

·          0.6 - 1.7 m3 per minute adjustable flow range;

·          equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

·          installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

·          capable of providing a minimum exposed area of 406 cm2;

·          flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

·          equipped with a shelter to protect the filter and sampler;

·          incorporated with an electronic mass flow rate controller or other equivalent devices;

·          equipped with a flow recorder for continuous monitoring;

·          provided with a peaked roof inlet;

·          incorporated with a manometer;

·          able to hold and seal the filter paper to the sampler housing at horizontal position;

·          easily changeable filter; and

·          capable of operating continuously for a 24-hour period.

3.2.6       Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

Laboratory Measurement / Analysis

3.2.7       A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

3.2.8       An alternative non-HOKLAS accredited laboratory was set-up for carrying out the laboratory analysis, the laboratory equipment was approved by the ER on 8 February 2011 and the measurement procedures were witnessed by the IEC. Any measurement performed by the laboratory was be demonstrated to the satisfaction of the ER and IEC. IEC shall regularly audit to the measurement performed by the laboratory to ensure the accuracy of measurement results.

3.2.9       Filter paper of size 8" x 10" shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

3.2.10    After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

3.2.11    All the collected samples shall be kept in a good condition for 6 months before disposal.

 

impact monitoring for odour patrol

3.2.12    Odour patrols along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai Public Cargo Working Area when there is temporary reclamation in Causeway Bay Typhoon Shelter and/or in the ex-Wan Chai Public Cargo Working Area, or when there is dredging of the odorous sediment and slime at the south-western corner of the Causeway Bay Typhoon Shelter. Odour patrols will be carried out at bi-weekly intervals during July, August and September by a qualified person of the ET who shall:

·        be at least 16 years of age;

·        be free from any respiratory illnesses; and

·        not be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30 min

·        before and during odour patrol

3.2.13    Odour patrol shall be conducted by independent trained personnel / competent persons patrolling and sniffing around the shore as shown in Figure 3.1 to detect any odour at the concerned hours (afternoon is preferred for higher daily temperature).

3.2.14    The qualified person will use the nose (olfactory sensor) to sniff odours at different locations. The main odour emission sources and the areas to be affected by the odour nuisance will be identified.

3.2.15    The perceived odour intensity is to be divided into 5 levels which are ranked in the descending order as follows:

·            0 - Not detected. No odour perceived or an odour so weak that it cannot be easily characterized or described;

·            1 - Slight Identifiable odour, and slight chance to have odour nuisance;

·            2 - Moderate Identifiable odour, and moderate chance to have odour nuisance;

·            3 - Strong Identifiable, likely to have odour nuisance;

·            4 - Extreme Severe odour, and unacceptable odour level.

 

3.2.16    The findings including odour intensity, odour nature and possible odour sources, and also the local wind speed and direction at each location will be recorded. In addition, some relevant meteorological and tidal data such as daily average temperature, and daily average humidity, on that surveyed day will be obtained from the Hong Kong Observatory Station for reference. The Action and Limit levels for odour patrol are shown in Appendix 3.1.

3.3    Water Quality Monitoring

3.3.1.     The EIA Report has identified that the key water quality impact would be associated with the dredging works during the construction phase.  Marine water quality monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is therefore recommended to be carried out at selected WSD flushing water intakes.  The impact monitoring should be carried out during the proposed dredging works to ensure the compliance with the water quality standards.

3.3.2.     The updated EM&A Manual for EP-356/2009 (Version in March 2011) is approval by EPD on 29 April 2011. As such, the Action Level and Limit Level for the wet season (April – September) will be effected and applied to the water quality monitoring data from 30 April 2011.

Water Quality Monitoring Stations

3.3.3.     It is proposed to monitor the water quality at 2 WSD salt water intakes and 7 cooling water intakes along the seafront of the Victoria Harbour. The proposed water quality monitoring stations of the Project are shown in Table 3.4 and Figure 3.1.  Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.4    Marine Water Quality Stations for Water Quality Monitoring

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD19

Sheung Wan

833415.0

816771.0

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

C7

Windsor House

837193.7

816150.0

P1

HKCEC Phase I

835774.7

816179.4

P3

The Academy of performing Arts

835824.6

816212.0

P4

Shui on Centre

835865.6

816220.0

P5

Government Buildings

(Wanchai Tower / Revenue Tower / Immigration Tower)

835895.2

816215.2

Cooling Water Intake / WSD Salt Water Intake

RW21-P789

Great Eagle Centre/ Sun Hung Kai Centre/ WSD Wanchai salt water intake

836268.0

816020.0

Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

-    WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.

-    4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 were completed on 6 Feb 2012.

-    C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.

-    C8 & C9 was temporary suspended on 30 March 2013 due to the marine works for Contract no. HY/2009/19 had been completed on 4 March 2013

-     WSD7 and WSD20 were temporarily suspended from 27 Apr 2012

-    C2, C3 C4e and C4w water quality monitoring station was temporarily suspended since 24 Apr 2013

-    C5e and C5w water quality monitoring station was temporarily suspended since 29 July 2013

-    WSD21 water quality monitoring station was temporarily suspended since 12 March 2014

-    Maintenance responsibility of silt screen C1, WSD19, P3, P4 and P5 are under Contract HK/2009/01.

-    WSD9 and WSD17 water quality monitoring station was temporarily suspended since 8 September 2014 flood tide.

 

Water Quality Parameters and frequency

3.3.4.     Monitoring of dissolved oxygen (DO), turbidity and suspended solids (SS) shall be carried out at WSD flushing water intakes and cooling water intakes. DO and Turbidity are measured in-situ while SS is determined in laboratory. 

3.3.5.     In association with the water quality parameters, other relevant data shall also be measured, such as monitoring location/position, time, sampling depth, water temperature, pH, salinity, dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal stage, and any special phenomena and work underway at the construction site etc.

3.3.6.     The interval between two sets of monitoring should not be less than 36 hours except where there are exceedances of Action and/or Limit Levels, in which case the monitoring frequency will be increased.  Table 3.5 shows the proposed monitoring frequency and water quality parameters.  Duplicate in-situ measurements and water sampling should be carried out in each sampling event.  For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5m.

Table 3.5    Marine Water Quality Monitoring Frequency and Parameters

Activities

Monitoring Frequency1

Parameters2

During the 4-week baseline monitoring period

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

During marine construction works

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

After completion of marine construction works

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

Notes:

1.     For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5m.

2.     Turbidity should be measured in situ whereas SS should be determined by laboratory.

 

Dissolved Oxygen and Temperature Measuring Equipment

3.3.7.     The instrument should be a portable, weatherproof dissolved oxygen measuring instrument complete with cable, sensor, comprehensive operation manuals, and use a DC power source. It should be capable of measuring:

·          a dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation

·          a temperature of 0-45 degree Celsius

3.3.8.     It should have a membrane electrode with automatic temperature compensation complete with a cable. Sufficient stocks of spare electrodes and cables should be available for replacement where necessary. (e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).

3.3.9.     Should salinity compensation not be build-in in the DO equipment, in-situ salinity shall be measured to calibrate the DO equipment prior to each DO measurement.

Turbidity Measurement Instrument

3.3.10    The instrument should be a portable, weatherproof turbidity-measuring instrument complete with comprehensive operation manual. The equipment should use a DC power source. It should have a photoelectric sensor capable of measuring turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model 2100P or an approved similar instrument).

Sampler

3.3.11     Water sampler comprises a transparent PVC cylinder, with a capacity of not less than 2 litres, and can be effectively sealed with latex cups at both ends. The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (e.g. Kahlsico Water Sampler or an approved similar instrument).

Sample Container and Storage

3.3.12    Water samples for suspended solids measurement should be collected in high-density polythene bottles, packed in ice (cooled to 4°C without being frozen), and delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection for analysis.

Water Depth Detector

3.3.13    A portable, battery-operated echo sounder shall be used for the determination of water depth at each designated monitoring station. This unit can either be handheld or affixed to the bottom of the workboat, if the same vessel is to be used throughout the monitoring programme.

Salinity

3.3.14    A portable salinometer capable of measuring salinity in the range of 0-40 ppt shall be provided for measuring salinity of the water at each of monitoring location.

Monitoring Position Equipment

3.3.15    A hand-held or boat-fixed type digital Global Positioning System (GPS) with waypoint bearing indication or other equivalent instrument of similar accuracy shall be provided and used during monitoring to ensure the monitoring vessel is at the correct location before taking measurements.

Calibration of In-situ Instruments

3.3.16    All in-situ monitoring instrument shall be checked, calibrated and certified by a laboratory accredited under HOKLAS or equivalent before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring. Responses of sensors and electrodes should be checked with certified standard solutions before each use. Wet bulb calibration for a DO meter shall be carried out before measurement at each monitoring location.

3.3.17    For the on site calibration of field equipment by the ET, the BS 127:1993, "Guide to Field and on-site test methods for the analysis of waters" should be observed.

3.3.18    Sufficient stocks of spare parts should be maintained for replacements when necessary. Backup monitoring equipment shall also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, etc.

 

Laboratory Measurement / Analysis

3.3.19    Analysis of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the monitoring stations for carrying out the laboratory SS determination. The SS determination work shall start within 24 hours after collection of the water samples. The SS determination shall follow APHA 19ed or equivalent methods subject to the approval of IEC and EPD.

 

Enhanced Water Quality Monitoring in the ex-Wan Chai Public Cargo

Working Area and the Causeway Bay Typhoon Shelter

3.3.20    The enhanced water quality monitoring and audit programme is to avoid aggravation of odour nuisance from seawater arising from temporary reclamation in the ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.

3.3.21    Dissolved oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when there is temporary reclamation in Causeway Bay Typhoon Shelter and at the south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working Area. The proposed water quality monitoring stations of the Project are shown in Table 3.6 and Figure 3.1.

Table 3.6    Marine Water Quality Stations for Enhanced Water Quality Monitoring

Station

Location

C6

Excelsior Hotel

C7

Windsor House

Ex-WPCWA-SW

South-western of the ex-Wan Chai Public Cargo Working Area

Ex-WPCWA-SE

South-eastern of the ex-Wan Chai Public Cargo Working Area

3.3.22    The monitoring of dissolved oxygen are to be carried out 3 days per week, at mid-flood and mid-ebb tides for 3 water depths (1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth may be omitted. If the water depth be less than 3m, only the mid-depth will be monitored).

 

 

 

 

Daily SS Monitoring and 24 hours Turbidity Monitoring System

3.3.23    During dredging of the sediment at the south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of suspended solids and 24 hour monitoring of turbidity at the cooling water intakes (C6 and C7) shall be conducted.

3.3.24    The 24 hours monitoring of turbidty at the cooling water intakes (C6 and C7) shall be established by setting up a continuous water quality monitoring station in front of the intakes during the dredging activities.  The monitoring system include the turbidity sensor and data logger which is capable of data capturing at every 5 minutes. The data shall be downloaded daily and compared with the Action and Limit level determined during the baseline water qualtiy monitoring at the cooling water intake locations.

Additional Dissovled oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW

3.3.25    In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be installed to channel water discharge flow from Culvert L to locations outside the embayment area, a proposed replacement of the requirement with additional dissolved oxygen monitoring has been conducted at three monitoring stations, namely A, B and C between the eastern seawall of Central Reclamation Phase III and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level between the eastern seawall of Central Reclamation Phase II and the HKCEC extension could be continuously monitored.

3.3.26    With respect to the commencement of dredging works under HK/2012/08 and the installation of MTR precast protection unit, the enhanced water quality monitoring for Culvert L was temporarily suspended since 24 July 2013

3.3.27    The monitoring of dissolved oxygen are to be carried out once per week, at mid-flood and mid-ebb tides for 3 water depths (1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth may be omitted. If the water depth be equal to or less than 3m, only the mid-depth will be monitored).

4.         Monitoring Results

4.0.1.     The environmental monitoring will be implemented based on the division of works areas of each designed project managed under different contracts with separate FEP applied by individual contractors.  Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 3.1. The monitoring results are presented in according to the Individual Contract(s).

4.0.2   According to EP-364/2009/A Part B, “Scale and Scope of Designated Project”, Remarks (c),”The permanent and temporary reclamation and associated dredging works related to the CWB construction are separately covered by environmental permit No. EP-356/2009 issued to Civil Engineering and Development Department”, and marine piling works to be conducted by the Contractor of Contract no. HY/2009/19 from 28 January 2012 was considered to be governed under EP-356/2009. As the construction site area of Contract no. HY/2009/11 had already been handed over to Contract no. HY/2009/19, the designated noise, water and air quality monitoring stations for Contract no. HY/2009/11 would be shared with Contract no. HY/2009/19 from 28 January 2012.

  4.1.       Noise Monitoring Results

Contract no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC and Contract no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East

4.1.1.     The proposed divisions of noise monitoring stations are summarized in Table 4.1 below.

Table 4.1    Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02

Station

Description

M1a

Harbour Road Sports Centre

4.1.2.     No action or limit level exceedance was recorded in this reporting quarter.

Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of graphical presentation can be referred in Appendix 4.1.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

4.1.3.     The noise monitoring for HY/2009/15 was commenced on 10 November 2010. The proposed division of noise monitoring stations are summarized in Table 4.2 below.

Table 4.2    Noise Monitoring Station for Contract nos. HY/2009/15

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

 

4.1.4.     No action or limit level exceedance was recorded in this report quarter.

Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of graphical presentation can be referred in Appendix 4.1.

 

Contract no. HY/2009/19 – Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

4.1.5.     Noise quality monitoring at M4b and M5b have been implemented with respect to HY/2009/19 since the marine bore piling work started on 28 Jan 2012.

4.1.6.     The proposed division of noise monitoring stations for Contract no. HY/2009/19 are summarized in Table 4.3 below:

        Table 4.3  Noise Monitoring Stations for Contract no.  HY/2009/19

Station

Description

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

 

 

 

 

 

 

4.1.7.     Three limit level exceedances were recorded at M6 monitoring station on 5, 9 and 16 June 2015 in June reporting month.

4.1.8.     Traffic noise was observed during monitoring on 5, 9 and 16 June 2015 and it was considered as the major noise contribution. As such, the limit level exceedances were concluded as non-project related.

4.1.9.     No action or limit level exceedance was recorded in July reporting month.

4.1.10.   No action or limit level exceedance was recorded in August reporting month.

4.1.11.   Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of graphical presentation can be referred in Appendix 4.1.     

Contract no. HY/2010/08-Central-Wanchi Bypass Tunnel (Slip Road 8 Section)

4.1.12.   The proposed division of noise monitoring stations are summarized in Table 4.4 below.

Table 4.4     Noise Monitoring Station for Contract no. HY/2010/08

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

 

 

 

4.1.13.   No action or limit level exceedance was recorded in the reporting quarter.

4.1.14.   Noise monitoring results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and graphical presentation can be referred in Appendix 4.1.

  4.2.       Real Time Noise Monitoring Results

 

Contract no. HY/2009/19 – Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

4.2.1       As the land-based piling and filling works- DP3 at Tin Hau had been completed on 3 September 2012 and confirmed by RSS, the real-time noise monitoring results at FEHD Hong Kong Transport Section Whitfield Depot was excluded under EP-356/2009 since 28 November 2012.

 

4.2.2       The real-time noise monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct 2012, which is a representative of noise sensitive receiver- City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.

 

4.2.3       The major work activities for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The construction site was handed over to contractor HY/2009/19 on 31 December 2011 and the FEP-01/356/2009 was surrendered on 22 Oct 2012.

 

4.2.4       Real-time noise monitoring at FEHD Hong Kong Transport Section Whitfield Depot commenced external wall renovation since 1 June 2012

Table 4.5   Real Time Noise Monitoring Station for Contract no. HY/2009/19

District

Station

Description

North Point

RTN2a

Electric Centre

l   Real time noise monitoring results and graphical presentation during night time period are for information only.

l   RTN2 had been relocated to RTN2a since 5 Oct 2012

l   RTN1 monitoring had been finished on 28 Nov 2012

4.2.5       Limit level exceedances were recorded at RTN2a-Electric Centre during daytime on 23, 24 and 25 June 2015 during day time in June reporting month. After checking with Contractor of HY/2009/19, pile cap breaking works was conducted on 23 and 24 June 2015 and pile cap excavation works was conducted on 25 June 2015. Noise mitigation measures including temporary noise barrier was implemented by the Contractor while breaking works and excavation works was noted on-going at the construction site located next to the monitoring station. In view of the above, the exceedances were considered to be non-Project related and contributed by nearby non-CWB construction site works. Nevertheless, the Contractor was reminded to strengthen the noise mitigation measures implemented for the pile cap demolition works to avoid potential cumulative impact to nearby sensitive receivers.

4.2.6       No limit level exceedance was recorded in July reporting month.

4.2.7       No limit level exceedance was recorded in August reporting month.

  4.3.       Air Monitoring Results

4.3.1.     1hr and 24hr TSP monitoring were conducted at CMA1b, CMA2a, CMA3a, CMA4a, CMA5b and CMA6a in the reporting period.

 

Contract no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC

4.3.2.     Air monitoring was commenced on 1 April 2011 in response to the commencement of the land-filling work for Contract no. HK/2009/01. The proposed division of air monitoring stations are summarized in Table 4.6 below.

 

Table 4.6      Air Monitoring Stations for Contract no. HK/2009/01

Station

Description

CMA5b

Pedestrian Plaza

CMA6a

WDII PRE Site Office *

4.3.3.     No action or limit exceedance was recorded in this reporting quarter.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East

4.3.4.     Air monitoring was commenced in mid-January 2011 for the land-filling work for Contract no. HK/2009/02. The proposed division of air monitoring stations is summarized in Table 4.7 below.

Table 4.7      Air Monitoring Station for Contract no. HK/2009/02

Station

Description

CMA4a

Society for the Prevention of Cruelty to Animals

4.3.5.     No action or limit level exceedance was recorded in March, April and May reporting month.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

4.3.6.     Air monitoring was commenced on 15 March 2011 for the land filling work for Contract no. HY/2009/15.  The proposed division of air monitoring stations are summarized in Table 4.8 below.

 

Table 4.8      Air Monitoring Station for Contract no. HY/2009/15

Station

Description

CMA3a

CWB PRE Site Office

4.3.7.     No action or limit exceedance was recorded in this reporting quarter.

4.3.8.     The odour patrol along the odour route with 7 sniffing locations was conducted by a qualified odour patrol member on 7 and 21 July 2015 at the concerned hours (afternoon for higher daily temperature). No Action and Limit Level was recorded during July reporting month.

4.3.9.     The odour patrol along the odour route with 7 sniffing locations was conducted by a qualified odour patrol member on 4 and 18 August 2015 at the concerned hours (afternoon for higher daily temperature). No Action and Limit Level was recorded during August reporting month.

 

Contract no. HY/2009/19 –Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

4.3.10.   Air monitoring at CMA1b and CMA2a have been implemented with respect to HY/2009/19 since the marine bore piling works started on 28 Jan 2012. No exceedance was recorded in the reporting period.

4.3.11.   The proposed division of air monitoring stations is summarized in Table 4.9 below.

Table 4.9 Air Monitoring Stations for Contract no. HY/2009/19

Station

Description

CMA1b

Oil Street Site Office

CMA2a

Causeway Bay Community Centre

4.3.12.   No action or limit exceedance was recorded in June reporting month.

4.3.13.   No action or limit exceedance was recorded in July reporting month.

4.3.14.   One action level exceedance was recorded at monitoring station CMA2a on 26 August 2015 during 24hr TSP monitoring in August reporting month.

4.3.15.   After investigation, it was found that external renovation at Causeway Bay Community Centre by non-CWB Contractor was the major contribution to air quality impact and no construction works with considerable dust impact was undertaken by the Contractor on the monitoring date. As such, the exceedance was considered as non-Project related.

4.3.16.   Two action level exceedances were recorded at monitoring station CMA1a on 27 August 2015 during 1hr TSP monitoring in August reporting month.

4.3.17.   After investigation, it was found that external renovation at Causeway Bay Community Centre by non-CWB Contractor was the major contribution to air quality impact and no construction works with considerable dust impact was undertaken by the Contractor on the monitoring date. As such, the exceedance was considered as non-Project related.

4.4      Water Monitoring Results

Contract no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC

4.4.1.     Water quality monitoring for Contract no. HK/2009/01 was commenced on 23 July 2010. The proposed division of water monitoring stations is summarized in Table 4.10 below.

4.4.2.     Water quality monitoring station RW21-P789 has been implemented with respect to HK/2009/02 started on 29 July 2013.

Table 4.10 Water Monitoring Stations for Contract no. HK/2009/01

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

Remarks:

-       The water monitoring stations for the dredging works under Contract No. HK/2009/01 should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these locations have not been carried out by others. Similarly, the water monitoring stations for the dredging works under Contract No. HK/2009/02 should also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality monitoring at these locations have not been carried out by others.

-       WSD7 and WSD20 water quality monitoring were temporarily suspended since 27 Apr 2012.

-       C2, C3 C4e and C4w water quality monitoring station was temporarily suspended since 24 Apr 2013

 

Contract no. HK/2009/02 - Wan Chai Development Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East

4.4.3.     Water quality monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010. The proposed division of water monitoring stations is summarized in Table 4.11 below.

Table 4.11 Water Monitoring Stations for Contract no. HK/2009/02

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD9

Tai Wan

837921.0

818330.0

WSD17

Quarry Bay

839790.3

817032.2

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

Cooling Water Intake

RW21-P789

Great Eagle Centre/ Sun Hung Kai Centre/CWB

836268.0

816020.0

Remarks:

-       The water monitoring stations for the dredging works under Contract No. HK/2009/01 should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these locations have not been carried out by others. Similarly, the water monitoring stations for the dredging works under Contract No. HK/2009/02 should also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality monitoring at these locations has not been carried out by others.

-       Water quality monitoring at WSD9 and WSD 17 was implemented with respect to HK/2009/02 from 8 Feb 2012.

-       C5e and C5w water quality monitoring station was temporarily suspended since 29 July 2013

-       WSD21 water quality monitoring station was temporarily suspended since 12 March 2014

-       WSD9 and WSD17 water quality monitoring station was temporarily suspended since 8 September 2014 flood tide.

-       The water monitoring station C1 shall be associated with Contract No. HK/2009/02 upon commencement of marine works under DP3 at WCR3 area.

 

 

Contract no. HK/2012/08 - Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West

 

4.4.4.     Water monitoring for Contract no. HK/2012/08 was commenced on 5 March 2013. The proposed division of water monitoring stations are summarized in Table 4.12 below.

Table 4.12 Water Monitoring Stations for Contract no. HK/2012/08

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD19

Sheung Wan

833415.0

816771.0

Cooling Water Intake

P1

HKCEC Phase I

835774.7

816179.4

P3

The Academy of performing Arts

835824.6

816212.0

P4

Shui on Centre

835865.6

816220.0

P5

Government Buildings

(Wanchai Tower / Revenue Tower / Immigration Tower)

835895.2

816215.2

 

 

 

 

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

4.4.5.     As the removal of reclamation work of TS1 at CBTS has been completed, all procedures have been rectified and complied with the conditions set in EP-356/2009 and FEP-04/356/2009.

4.4.6.     Due to the presence of obstacle within the inner silt curtain frame at sampling point, water quality point at C7 was finely adjusted to the outside of the inner silt curtain frame since 29 Dec 2012.

4.4.7.     Due to the commencement of the maintenance dredging on 10 November 2010, water quality monitoring for Contract no. HY/2009/15 was commenced on 9 November 2010. The proposed division of water monitoring stations is summarized in Table 4.13 below.

 

Table 4.13  Water Monitoring Stations for Contract no. HY/2009/15

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C7

Windsor House

837193.7

816150.0

Remarks: -      The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

 

Contract no. HY/2009/19 – Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

4.4.8.     Due to the commencement of the marine bored piling on 28 Jan 2012, water quality monitoring for Contract no. HY/2009/19 was commenced on 28 Jan 2012.

4.4.9.     Due to the marine piling under Contract no. HY/2009/19 was completed on 4 March 2013, the temporary suspension of impact water quality monitoring at C8 and C9 from 4 March 2013 have been monitored for 4-week period after the completion of marine works to confirm no water deterioration.

4.4.10.   As confirmed by CWB RSS, the marine pilling works under contract HY/2009/19 was confirmed completed by 4 March 2013.  The water quality monitoring at the respective monitoring stations C8 and C9 were temporarily suspended since 30 March 2013.

4.4.11.   Based on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no water deterioration with respect to NPR was commenced since 7 Jan 2012 and it was completed on 6 February 2012.

4.4.12.   Water quality monitoring at WSD10 and WSD15 was temporary suspended while water quality monitoring at WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8 Feb 12 onwards;

4.4.13.   Water quality monitoring at C8 and C9 have been implemented with respect to HY/2009/19 since the marine bore piling work started on 28 Jan 12.

4.4.14.   Based on the safety concern when external façade refurbishment was conducted by contractor employed by Provident Center (C9) between 9 January 2012 to 30 July 2012 which caused to the inaccessibility of sampling either land and marine since 3 Feb 2012, there is a fine adjustment of the sampling location of water quality monitoring at C9 since 10 March 2012 to the closest accessible point prior to the completion of the external façade refurbishment work.

4.4.15.   With respect to the trial dredging at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3 , 11, 13, 15, 17, 19, 20 Apr and 3 May 2012, on-going water quality monitoring results at WSD21 during this period was checked and indicated that there was no contribution due to the trial dredging operation.  Enhanced review of water quality around WCR2 was also implemented and no deterioration in the water quality was observed.

4.4.16.   Due to the access of water monitoring station at WSD19 was blocked by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the inaccessibility of sampling either land and marine, there is a fine adjustment of the sampling point of WSD 19 since 5 April 2012 to the closest accessible point prior to the completion of the construction activities.

4.4.17.   Due to the dredging works for Cross Harbour Water Mains from Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April 2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for 4-week period after the completion of DP6 to confirm no water deterioration.

4.4.18.   As per the meeting with the representative of Excelsior Hotel and World Trade Centre on 17 May 2011, they confirmed that the seawater intake for The Excelsior was no longer in use and replaced by the connected permanent water supply from WSD pipelines since 11 January 2011. Thus, the impact water quality monitoring for the cooling intake - C6 was terminated effective from 26 May 2011. 

4.4.19.   24 hours monitoring of turbidity at the cooling water intakes at C7 was conducted. With respect to the seawall collapsing at TS4 on 17 November 2011, the 24 hours turbidity monitoring and was kept in November 2011. Since the reinstating the seawall was completed on 13 January 2012 and no any water deterioration was performed, 24 hour turbidity monitoring was then suspended on 27 January 2012.

4.4.20.   The enhanced water quality monitoring at C6, C7, Ex-WPCWA-SW and Ex-WPCWA-SE was commenced on 13 January 2011.  

4.4.21.   Water monitoring results measured in this reporting period are reviewed and summarized in Table 4.14. Details of water quality monitoring results and graphical presentation can be referred in Appendix 4.3.

 

Table 4.14 Summary of Water Quality Monitoring Exceedances in Reporting period

 

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HK/2009/01 & HK/2009/02

C1

0

0

0

0

0

0

0

0

0

0

0

0

HK/2012/08

WSD19

0

0

0

0

0

0

0

0

0

0

0

0

P1

0

0

0

0

0

0

0

0

0

0

0

0

P3

0

0

0

0

0

0

0

0

0

0

0

0

P4

0

0

0

0

0

0

0

0

0

0

0

0

P5

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/02

RW21-P789

0

0

0

0

0

0

0

0

0

0

0

0

HY/2009/15 & HY/2010/08

C7

0

0

0

1

0

0

0

0

0

1

0

1

Total

0

0

0

1

0

0

0

0

0

1

0

1

Remarks:  

-       The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

-       WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.

-       4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.

-       C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.

-       C8 & C9 was temporary suspended on 30 March 2013 due to the marine works for Contract no. HY/2009/19 had been completed on 4 March 2013

-       WSD7 and WSD20 were temporarily suspended from 27 Apr 2012

-       C2, C3 C4e and C4w water quality monitoring station was temporarily suspended since 24 Apr 2013

-       C5e and C5w water quality monitoring station was temporarily suspended since 29 July 2013

-       WSD21 water quality monitoring station was temporarily suspended since 12 March 2014

-       Maintenance responsibility of silt screen C1, WSD19, P3, P4 and P5 are under Contract HK/2009/01.

-       WSD9 and WSD17 water quality monitoring station was temporarily suspended since 8 September 2014 flood tide.

-       Water quality monitoring for Windsor House Cooling (Station Ref: C7) was temporarily suspended since 22 October 2014 with respect to the diversion scheme and was resumed since 22 December 2014.

-       The water monitoring station C1 shall be associated with Contract No. HK/2009/02 upon commencement of marine works under DP3 at WCR3 area.

 

4.4.22.   There was no action and 1 limit level of turbidity exceedance, and no action and 1 limit level of suspended solid exceedance recorded in June reporting month. Investigation found that the exceedance was not related to Project works.

4.4.23.   There was no action and 1 limit level of turbidity exceedance recorded in July reporting month. Investigation found that the exceedance was not related to Project works.

4.4.24.   There was no action and no limit level exceedance recorded in August reporting month.

 

4.4.25.   Enhanced DO monitoring at 4 monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table 4.15.

 

 

 

 

 

 

 

Table 4.15      Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting period

 

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

DO

AL

LL

AL

LL

HY/2009/15

C6

0

0

0

0

C7

0

0

0

0

Ex-WPCWA SW

1

4

1

9

Ex-WPCWA SE

2

0

2

1

Total

3

4

3

10

 

4.4.26.   There were 2 action level and 3 limit level exceedance of enhanced dissolved oxygen recorded in June reporting month. Investigation found that the exceedance was not related to Project works.

4.4.27.   There were no action level and 4 limit level exceedances of enhanced dissolved oxygen recorded in July reporting month. Investigation found that the exceedances were not related to Project works.

4.4.28.   There were 4 action level and 7 limit level exceedances of enhanced dissolved oxygen recorded in August reporting month. Investigation found that the exceedances were not related to Project works.

4.4.29.   Investigation found that the exceedances are not related to the Project works.  Details of graphical presentation can be referred in Appendix 4.3.

4.4.30.   In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be installed to channel water discharge flow from Culvert L to locations outside the embayment area, a proposed replacement of the requirement with additional dissolved oxygen monitoring has been conducted at three monitoring stations, namely A, B and C between the eastern seawall of Central Reclamation Phase III and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level between the eastern seawall of Central Reclamation Phase II and the HKCEC extension could be continuously monitored.

4.4.31.   With respect to the commencement of dredging works under HK/2012/08 and the installation of MTR precast protection unit, the enhanced water quality monitoring for Culvert L was temporarily suspended since 24 July 2013

4.4.32.   With respect to the commencement of temporary reclamation works and seawall construction at Ex-PCWAW zone and diverted culvert extension, the location of the Enhance DO monitoring stations (Ex-PCWASW and Ex-PCWA SE) were finely adjusted to the PCWAE since 7 November 2014.

4.5     Waste Monitoring Results

Contract no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC

4.5.1.     No Inert C&D waste and non-inert C&D waste was disposed of for the site works in this reporting period. Details of the waste flow table are summarized in Table 4.16.

Table 4.16  Details of Waste Disposal for Contract no. HK/2009/01

Waste Type

Quantity this quarter

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

NIL

62116.405

TKO137, TM38

Inert C&D materials recycled, m3

NIL

5856.5

N/A

Non-inert C&D materials disposed, m3

NIL

1673.69

SENT Landfill

Non-inert C&D materials recycled, kg

NIL

203993

N/A

Chemical waste disposed, kg

NIL

10250

N/A

Marine Sediment (Type 1 – Open Sea Disposal) , m3

NIL

(Bulk Volume)

97428.2

(Bulk Volume)

South of Cheung Chau

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3

NIL

(Bulk Volume)

52250

(Bulk Volume)

East of Cha Chau

Dredged Sediment Requiring Type 3 – Special Treatment / Disposal contained in Geosynthetic Containers

NIL

(Bulk Volume)

6773

(Bulk Volume)

East of Cha Chau

4.5.2.     There were no Marine Sediment (Type 1 – Open Sea Disposal) and no Marine Sediment (Type 1- Open Sea Disposal (Dedicate Sites) & Type 2- Confined Marine Disposal) disposed of in this reporting quarter.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East

4.5.3.     No Inert and non-inert C&D waste were disposed of for the site works in this reporting period. Details of the waste flow table are summarized in Table 4.17.

 

 

 

Table 4.17  Details of Waste Disposal for Contract no. HK/2009/02

Waste Type

Quantity this quarter

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

NIL

276075.1

TKO137/ TM 38

Inert C&D materials recycled, m3

NIL

18161

N/A

Non-inert C&D materials disposed, m3

NIL

1515.103

SENT Landfill

Non-inert C&D materials recycled, m3

N/A

N/A

N/A

Chemical waste disposed, kg

NIL

13860

SENT Landfill

Marine Sediment (Type 1 – Open Sea Disposal), m3

434

244249

(Bulk volume)

South of Cheung Chau

 

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal), m3 *

0

146445*

(Bulk volume)

East of Sha Chau

Remarks: The cumulative quantity of Type 1 – Open Sea Disposal (Delicate Sites) & Type 2 – Confined Marine Disposal has been updated in July reporting month.

4.5.4.     There was Marine Sediment (Type 1 – Open Sea Disposal) and no Marine Sediment (Type 1- Open Sea Disposal (Dedicate Sites) & Type 2- Confined Marine Disposal) disposed of in this reporting quarter.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

4.5.5.     No inert and non-inert C&D waste were disposed of for the site works in this reporting period. Details of the waste flow table are summarized in Table 4.18.

Table 4.18  Details of Waste Disposal for Contract no. HY/2009/15

Waste Type

Quantity this quarter

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Remarks

Inert C&D materials disposed, m3

NIL

141579.2

Tuen Mun Area 38

NIL

NIL

65216

TKO137 FB

NIL

Inert C&D materials recycled, m3

NIL

304

Ex-PCWA

NIL

NIL

111.9

TS4

NIL

Non-inert C&D materials disposed, m3

NIL

252.2

SENT Landfill

 

NIL

Non-inert C&D materials recycled, kg

NIL

299361.5

N/A

NIL

Chemical waste disposed, kg

NIL

8,200

N/A

NIL

Marine Sediment (Type 1 – Open Sea Disposal) , m3

10774

 

126298

 (Bulk Volume)

South of Cheung Chau

Dredging from TCBR1E / TCBR1W / TCBR2/ TCBR3 / TCBR4 / Maintenance dredging

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3

18560

307175

 (Bulk Volume)

 

East of Sha Chau

Dredging from TCBR1E / TCBR1W / TCBR2/ TCBR3 / TCBR4 / Maintenance dredging

Marine Sediment (Type 3 – Special Treatment / Disposal contained in Geosynthetic Containers)

NIL

12640

(Bulk Volume)

 

East of Sha Chau

Dredging from TCBR1W / Maintenance dredging

Marine Sediment (Type 2 – Confined Marine Disposal), m3

NIL

(Bulk Volume)

9350

(Bulk Volume)

East of Sha Chau

Dredging from Eastern Breakwater of CBTS

Marine Sediment (Type 1 – Open Sea Disposal) , m3

NIL

(Bulk Volume)

600

(Bulk Volume)

East Sha Chau / South of The Brothers

Dredging from Phase 3 Mooring Re-arrangement

Marine Sediment (Type 2– Confined Marine Disposal) , m3

NIL

(Bulk Volume)

14,780

(Bulk Volume)

South of The Brothers

Dredging from Phase 3 Mooring Re-arrangement

Marine Sediment (Type 3 – Special Treatment / Disposal contained in Geosynehetic Containers) , m3

NIL

(Bulk Volume)

2,760

(Bulk Volume)

South of The Brothers

Dredging from Phase 3 Mooring Re-arrangement

4.5.6.     There was Marine Sediment (Type 1 – Open Sea Disposal) and Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sties) & Type 2 – Confined Marine Disposal) disposed in this reporting quarter.

Contract no. HY/2009/19 – Central- WanChai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

4.5.7.     No Inert and non-inert C&D waste were disposed of in this reporting quarter

Table 4.19  Details of Waste Disposal for Contract no. HY/2009/19

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

NIL

355921.04

TM38

Inert C&D materials recycled, m3

NIL

59367

N/A

Non-inert C&D materials disposed, m3

NIL

1068.6

N/A

Non-inert C&D materials recycled, kg

NIL

333.14

N/A

Chemical waste disposed, L

NIL

2.12

N/A

Marine Sediment (Type 1 – Open Sea Disposal), m3

NIL

162

South Cheung Chau

Marine Sediment (Type 2 – Confined Marine Disposal) , m3

NIL

681

East Sha Chau

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3

NIL

4976.00

N/A

 

4.5.8.     There were no marine sediments Type1- Open Sea Disposal and there were no Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal in this reporting quarter.

Contract no. HK/2012/08 –Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West

4.5.9.     Inert C&D waste were disposed of in this reporting quarter. Details of the waste flow table are summarized in Table 4.20.

Table 4.20 Details of Waste Disposal for Contract no. HK/2012/08

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

245

4131

TM38

Inert C&D materials recycled, m3

NIL

NIL

N/A

Non-inert C&D materials disposed, m3 *

NIL

315

N/A

Non-inert C&D materials recycled, kg

NIL

NIL

N/A

Chemical waste disposed, L

NIL

NIL

N/A

Marine Sediment (Type 1 – Open Sea Disposal), m3 *

NIL

(Bulk volume)

31759

(Bulk volume)

South of Cheung Chau

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 *

NIL

(Bulk volume)

108485

(Bulk volume)

South of The Brothers (from 27 Aug 2013 onwards)

4.5.10.   No Marine Sediment (Type 1 – Open Sea Disposal) and no marine sediment Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal generated disposed in this reporting quarter.

Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)

4.5.11.   No Inert C&D waste and non-inert C&D waste were disposed in this reporting period. Details of the waste flow table are summarized in Table 4.21

Table 4.21 Details of Waste Disposal for Contract no. HY/2010/08

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

1119711.3

119711.3

N/A

Inert C&D materials recycled, m3

NIL

NIL

N/A

Non-inert C&D materials disposed, m3

NIL

NIL

N/A

Non-inert C&D materials recycled, kg

NIL

NIL

N/A

Chemical waste disposed, L

NIL

NIL

N/A

Marine Sediment (Type 1 – Open Sea Disposal)

NIL

55290

South Cheung Chau

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine disposal)

NIL

27760

Brothers Island

Marine Sediment (Type 3 – Special Treatment)

NIL

7780

Brothers Island

4.5.12.   There were no Marine Sediment (Type 1 – Open Sea Disposal), Marine Sediment (Type 3 – Special Treatment) and marine sediment Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal disposed in this reporting quarter.

 

 

5.         Compliance Audit

5.0.1.     The Event Action Plan for construction noise, air quality and water quality are presented in Appendix 5.1.

5.1.          Noise Monitoring

5.1.1       Three limit level exceedances were recorded on 5, 9 and 16 June 2015 at M6 – HK Baptist Church Henrietta Secondary School in June reporting month. Investigations found that on 5, 9 and 16 June 2015, traffic noise was the major contribution in the noise monitoring and exceedance was not related to the Project.

5.1.2       No action and limit level exceedance was recorded in July reporting month.

5.1.3       No action and limit leve exceedance was recorded in August reporting month.

5.1.4       Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of graphical presentation can be referred in Appendix 4.1.   

 

5.2.          Real-time Noise Monitoring

5.2.1       Limit level exceedances were recorded at RTN2a-Electric Centre during daytime on 23, 24 and 25 June 2015 during day time in June reporting month. After checking with Contractor of HY/2009/19, pile cap breaking works was conducted on 23 and 24 June 2015 and pile cap excavation works was conducted on 25 June 2015. Noise mitigation measures including temporary noise barrier was implemented by the Contractor while breaking works and excavation works was noted on-going at the construction site located next to the monitoring station. In view of the above, the exceedances were considered to be non-Project related and contributed by nearby non-CWB construction site works. Nevertheless, the Contractor was reminded to strengthen the noise mitigation measures implemented for the pile cap demolition works to avoid potential cumulative impact to nearby sensitive receivers

5.2.2       No project related exceedances were recorded in July and August reporting month at RTN2a-Hong Kong Electric Centre.

5.2.3       Details of real time noise monitoring results and graphical presentation can be referred to Appendix 4.2 

 

5.3.          Air Monitoring

5.3.1       No action or limit exceedance was recorded in 1-hr TSP and 24-hrs TSP monitoring in June and July reporting months

5.3.2       One action level exceedance during 24hr TSP monitoring was recorded at monitoring station CMA2a – Causeway Bay Community Centre on 26 August 2015 and two action level exceedances during 1hr TSP monitoring exceedances were recorded at monitoring station CMA2a – Causeway Bay Community Centre on 27 August 2015 in August reporting month.

5.3.3       External renovation undertaken at Causeway Bay Community Centre on 26, 27 August 2015 by non-CWB Contractor was considered as the major contribution to the air quality impact and the exceedances were considered as non-Project related.

5.3.4       No action and limit level was recorded for odour patrol during July and August reporting months.

 

5.4.          Water Quality Monitoring

5.4.1.     The summary of water quality exceedances recorded in reporting period is presented in the Table 5.1 and Table 5.2.

Table 5.1    Summary of Water Quality Monitoring Exceedances in Reporting period

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HK/2009/01 & HK/2009/02

C1

0

0

0

1

0

0

0

0

0

0

0

0

HK/2012/08

WSD19

0

0

0

1

0

0

0

0

0

0

0

0

P1

0

0

0

0

0

0

0

0

0

0

0

0

P3

0

0

0

0

0

0

0

0

0

0

0

0

P4

0

0

0

0

0

0

0

0

0

0

0

0

P5

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/02

RW21-P789

0

0

0

0

0

0

0

0

0

0

0

0

HY/2009/15 & HY/2010/08

C7

0

0

0

1

0

0

0

0

0

1

0

1

Total

0

0

0

1

0

0

0

0

0

1

0

1

 

Remarks:

-        The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

-       WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.

-       4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.

-       C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.

-       C8 & C9 was temporary suspended on 30 March 2013 due to the marine works for Contract no. HY/2009/19 had been completed on 4 March 2013

-       WSD7 and WSD20 were temporary suspended since 27 April 2012

-       C2, C3 C4e and C4w water quality monitoring station was temporarily suspended since 24 Apr 2013

-       C5e and C5w water quality monitoring station was temporarily suspended since 29 July 2013

-       WSD21 water quality monitoring station was temporarily suspended since 12 March 2014

-       Maintenance responsibility of silt screen C1, WSD19, P3, P4 and P5 are under Contract HK/2009/01.

-       WSD9 and WSD17 water quality monitoring station was temporarily suspended since 8 September 2014 flood tide.

-       Water quality monitoring for Windsor House Cooling (Station Ref: C7) was temporarily suspended since 22 October 2014 with respect to the diversion scheme and was resumed since 22 December 2014

-       The water monitoring station C1 shall be associated with Contract No. HK/2009/02 upon commencement of marine works under DP3 at WCR3 area.

 

4.4.33.   There was no action and 1 limit level of turbidity exceedance, and no action and 1 limit level of suspended solid exceedance recorded in June reporting month. Investigation found that the exceedance was not related to Project works.

4.4.34.   There was no action and 1 limit level of turbidity exceedance recorded in July reporting month. Investigation found that the exceedance was not related to Project works.

4.4.35.   There was no action and no limit level exceedance recorded in August reporting month.

 

 

Table 5.2        Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting period

 

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

DO

AL

LL

AL

LL

HY/2009/15

C6

0

0

0

0

C7

0

0

0

0

Ex-WPCWA SW

1

4

1

9

Ex-WPCWA SE

2

0

2

1

Total

3

4

3

10

 

5.4.2.     There were 2 action level and 3 limit level exceedance of enhanced dissolved oxygen recorded in June reporting month. Investigation found that the exceedance was not related to Project works.

5.4.3.     There were no action level and 4 limit level exceedances of enhanced dissolved oxygen recorded in July reporting month. Investigation found that the exceedances were not related to Project works.

5.4.4.     There were 4 action level and 7 limit level exceedances of enhanced dissolved oxygen recorded in August reporting month. Investigation found that the exceedances were not related to Project works.

5.5.          Site Audit

5.5.1.     There was no non-compliance from the site audits in the reporting period. During environmental site inspections conducted during the reporting period, minor deficiencies were noted.

5.6.          Review of the Reasons for and the Implications of Non-compliance

5.6.1       There was no non-compliance from the site audits in the reporting period.

5.7.          Summary of action taken in the event of and follow-up on non-compliance

5.7.1       There was no particular action taken since no project-related non-compliance was recorded from the site audits in this reporting quarter.

6.         Complaints, Notification of Summons and Prosecution

6.0.1.     No environmental complaint received in March, April and May reporting months.

6.0.2.     The details of cumulative complaint log and summary of complaints are presented in Appendix 6.1.

6.0.3.     Cumulative statistic on complaints and successful prosecutions are summarized in Table 6.1 and Table 6.2 respectively.

 

Table 6.1    Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

Commencement works (Mar 2010) to last reporting period

35

June 2015 - August 2015

2

Project-to-Date

37

 

 

Table 6.2    Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this quarter (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Water

-

0

0

Waste

-

0

0

Total

-

0

0

 

 

 

7.      Cumulative Construction Impact due to the Concurrent Projects

7.0.1.     According to Condition 3.4 of the EP-356/2009, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III, Central-Wanchai Bypass and Island Eastern Corridor Link projects.

7.0.2.     According to the Final EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK 12/02, the major construction activities were completed by end of January 2014 and no construction activities were undertaken thereafter and the water quality monitoring was completed in October 2011 and no Project-related exceedance was recorded for air and noise monitoring.  It can be concluded that cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) was insignificant.

7.0.3.     According to the construction programme of Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III area, removal of L-shape wall and installation of caisson seawall were performed in this reporting quarter. As no project related exceedance were recorded during the reporting period, cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) was considered as insignificant.

7.0.4.     According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activities under Wan Chai Development Phase II were tunnel works, ELS works and culvert construction at Wan Chai East and removal of L-shape wall, D-wall construction and ELS works at Wan Chai West. The major construction activities under Central-Wan Chai Bypass and Island Eastern Corridor Link Projects were bridge construction and road works at Central Interchange, ELS works at Ex-PCWAW, ELS works and retaining wall construction at Victoria Park, D- wall construction and ELS works at TS3, IEC demolition and tunnel works at North Point area in the reporting quarter.

7.0.5.     No significant air impact from construction activities was anticipated in the reporting month. Besides, no project related exceedance was recorded during the air and noise environmental monitoring events in the reporting month. Thus, it is evaluated that the cumulative construction impact from the concurrent projects including Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) was insignificant.

8.         Conclusion

8.0.1.     The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

8.0.2.     No non-compliance was noted and no prosecution was received during the reporting quarter.

8.0.3.     The construction programmes of individual contracts are provided in Appendix 8.1.