Contract No: HK/2015/01

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 3)

 

Environmental Permit no. EP-356/2009,

Further Evironmental permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009

 Fep-06/356/2009 and FEP-07/356/2009

 

Quarterly Environmental Monitoring
and Audit Report

 

- March 2016 to May 2016 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

CHECKED by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

29 June 2016

 


Table of contents

 

EXECUTIVE SUMMARY. 4

1.     Introduction. 9

1.1        Scope of the Report 9

1.2        Structure of the Report 9

2.     Project Background. 10

2.1        Background. 10

2.2        Scope of the Project and Site Description. 10

2.3        Division of the Project Responsibility. 11

2.4        Project Organization and Contact Personnel 13

2.5        Principal Work and Activities. 14

3.     Monitoring Requirements. 17

3.1.       Noise Monitoring. 17

3.2.       Air Monitoring. 18

3.3        Water Quality Monitoring. 21

4.     Monitoring Results. 27

4.1.       Noise Monitoring Results. 27

4.2.       Air Monitoring Results. 29

4.3        Water Monitoring Results. 32

4.4        Waste Monitoring Results. 39

5.     Compliance Audit. 44

5.1.       Noise Monitoring. 44

5.2.       Air Monitoring. 44

5.3.       Water Quality Monitoring. 44

5.4.       Site Audit 45

5.5.       Review of the Reasons for and the Implications of Non-compliance. 45

5.6.       Summary of action taken in the event of and follow-up on non-compliance. 46

6.     Complaints, Notification of Summons and Prosecution. 47

7.     Cumulative Construction Impact due to the Concurrent Projects. 49

8.     Conclusion. 50


lIST OF TABLES

 

Table I              Principal Work Activities for Contract no. HK/2009/01

Table II             Principal Work Activities for Contract no. HK/2009/02

Table III            Principal Work Activities for Contract no. HY/2009/15

Table IV           Principal Work Activities for Contract no. HY/2009/19

Table V            Principal Work Activities for Contract no. HK/2012/08

Table VI           Principal Work Activities for Contract no. HY/2010/08

Table 2.1          Schedule 2 Designated Projects under this Project

Table 2.2          Details of Individual Contracts under the Project

Table 2.3          Contact Details of Key Personnel

Table 2.4          Principal Work Activities for Contract no. HK/2009/01

Table 2.5          Principal Work Activities for Contract no. HK/2009/02

Table 2.6          Principal Work Activities for Contract no. HY/2009/15

Table 2.7          Principal Work Activities for Contract no. HY/2009/19

Table 2.8          Principal Work Activities for Contract no. HK/2012/08

Table 2.9          Principal Work Activities for Contract no. HY/2010/08

Table 3.1          Noise Monitoring Stations

Table 3.2          Air Monitoring Stations

Table 3.3          Marine Water Quality Stations for Water Quality Monitoring

Table 3.4          Marine Water Quality Monitoring Frequency and Parameters

Table 3.5          Marine Water Quality Stations for Enhanced Water Quality Monitoring

Table 4.1          Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02

Table 4.2          Noise Monitoring Station for Contract nos. HY/2009/15

Table 4.3          Noise Monitoring Stations for Contract no.  HY/2009/19

Table 4.4          Noise Monitoring Stations for Contract no. HY/2010/08

Table 4.5          Air Monitoring Stations for Contract no. HK/2009/01

Table 4.6          Air Monitoring Station for Contract no. HK/2009/02

Table 4.7          Air Monitoring Station for Contract no. HY/2009/15

Table 4.8          Air Monitoring Stations for Contract no. HY/2009/19

Table 4.9          Air Monitoring Station for Contract no. HK/2012/08

Table 4.10        Air Monitoring Stations for Contract no. HY/2010/08

Table 4.11        Water Monitoring Stations for Contract no. HK/2009/01

Table 4.12        Water Monitoring Stations for Contract no. HK/2009/02

Table 4.13        Water Monitoring Stations for Contract no. HK/2012/08

Table 4.14        Water Monitoring Stations for Contract no. HY/2009/15

Table 4.15        Enhance Dissolved Oxygen Monitoring Stations for Contract no. HY/2009/15

Table 4.16        Water quality monitoring Stations for Contract no. HY/2010/08

Table 4.17        Enhance Dissolved Oxygen Monitoring Stations for Contract no. HY/2010/08

Table 4.18        Details of Waste Disposal for Contract no. HK/2009/01

Table 4.19        Details of Waste Disposal for Contract no. HK/2009/02

Table 4.20        Details of Waste Disposal for Contract no. HY/2009/15

Table 4.21        Details of Waste Disposal for Contract no. HY/2009/19

Table 4.22        Details of Waste Disposal for Contract no. HK/2012/08

Table 4.23        Details of Waste Disposal for Contract no. HY/2010/08

Table 6.1          Cumulative Statistics on Complaints

Table 6.2          Cumulative Statistics on Successful Prosecutions

 

 

 

lIST OF FIGUREs

 

Figure 2.1         Project Layout

Figure 2.2         Project Organization Chart

Figure 3.1         Locations of Environmental Monitoring Stations

 

 

 

 

lIST OF APPENDIces

 

Appendix 2.1    Environmental Mitigation Implementation Schedule

Appendix 3.1    Action and Limit Level

Appendix 4.1    Noise Monitoring Graphical Presentations

Appendix 4.2    Air Quality Monitoring Graphical Presentations

Appendix 4.3    Water Quality Monitoring Graphical Presentations

Appendix 5.1    Event Action Plans

Appendix 6.1    Complaint Log

Appendix 7.1    Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

  1. This is the Quarterly Environmental Monitoring and Audit (EM&A) Report – March 2016 to May 2016 prepared for the Project of Wan Chai Development Phase II and Central-Wanchai Bypass under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-06/356/2009 and FEP-07/356/2009. This report presents the environmental monitoring and audit findings and information during the period from 27th February 2015 to 26th May 2016. The cut-off date of reporting is at 26th of each reporting period.

 

Construction Activities for the Reported Period

  1. Contract no HK/2009/01 was commenced on 23 July 2010. During this reporting period, the principal work activities for Contract no. HK/2009/01 are summarized as below:

Table I        Principal Work Activities for Contract no. HK/2009/01

March 2016

April 2016

May 2016

Ÿ   Nil

Ÿ   Nil

Ÿ    Nil

 

  1. Contract no. HK/2009/02 was commenced on 5 July 2010. During this reporting period, the principal work activities for Contract no. HK/2009/02 are summarized as below:

Table II       Principal Work Activities for Contract no. HK/2009/02

March 2016

April 2016

May 2016

Ÿ   Nil

 

Ÿ   Nil

Ÿ   Inspection / Trimming of rockfill profile in front of seawall

Ÿ   Rock armor installation

 

  1. Contract no. HY/2009/15 was commenced on 10 November 2010. During this reporting period, the principal work activities for Contract no. HY/2009/15 are summarized as below:

Table III      Principal Work Activities for Contract no. HY/2009/15

March 2016

April 2016

May 2016

·         Reinstatement of vertical seawall at TPCWAE

·          Reinstatement of vertical seawall at TPCWAE

·          Reinstatement of vertical seawall at TPCWAE

·          Removal of temporary reclamation at TPCWAW

 

  1. Contract no. HY/2009/19 was commenced on 24 March 2011. During this reporting period, the principal work activities for Contract no. HY/2009/19 are summarized as below:

 

Table IV     Principal Work Activities for Contract no. HY/2009/19

March 2016

April 2016

May 2016

Ÿ  Nil

Ÿ  Nil

Ÿ   Nil

 

  1. Contract no. HK/2012/08 was commenced on 5 March 2013. During this reporting period, the principal work activities for Contract no. HK/2012/08 are summarized as below:

Table V      Principal Work Activities for Contract no. HK/2012/08

March 2016

April 2016

May 2016

Ÿ   Construction of culvert

Ÿ   Construction of dry dock

Ÿ   Trimming of rock bedding

Ÿ   Installation of seawall blocks

Ÿ   Filling adjacent to culvert L

Ÿ   Temporary works for culvert L Bay 8

Ÿ   Trimming of rock bedding

Ÿ   Precast unit construction for Box 1 inside Dry dock

Ÿ   Construction of culvert L Bay 8

Ÿ   Pre-bored H-pile installation for culvert L1/FRP-L Bay 12 and Bay 13

Ÿ   Precast unit construction for Box 1 inside Dry dock

Ÿ   Construction of culvert L Bay 8

Ÿ   Pre-bored H-pile installation for culvert L1/FRP-L Bay 12 and Bay 13

 

  1. Contract no. HY/2010/08 was commenced on 21 March 2013. During this reporting period, the principal work activities for Contract no. HY/2010/08 are summarized as below:

Table VI     Principal Work Activities for Contract no. HY/2010/08

March 2016

April 2016

May 2016

Ÿ   Diversion pipe maintenance

Ÿ   Diversion pipe maintenance

Ÿ   Diaphragm Wall Removal Works

Ÿ   Diversion pipe maintenance

Ÿ   Diaphragm Wall Removal Works

 

Noise Monitoring

  1. Noise monitoring during day time and evening time were conducted at the M1a, M2b, M3a, M4b, M5b and M6 on a weekly basis in the reporting period. The Action and Limit level exceedances recorded in the reporting period are listed below. Investigation found that exceedances were not related to the Project. Investigation found that exceedances were not related to the Project.
  2. Three limit level exceedances were recorded at noise monitoring station M1a – Harbour Road Sports Centre on 2, 8, and 15 March 2016 in March reporting month. The exceedances were concluded as non-project related.
  3. Two limit level exceedances were recorded at noise monitoring station M1a – Harbour Road Sports Centre on 29 March 2016 and 12 April 2016 in April reporting month. The exceedances were concluded as non-project related.
  4. Two limit level exceedances were recorded as noise monitoring station M6 – HK Baptist Church Henrietta Secondary School on 11 April 2016 and 19 April 2016 in April reporting month. The exceedances were concluded as non-project related.
  5. Two limit level exceedances were recorded at noise monitoring station M1a – Harbour Road Sports Centre on 04 and 24 May 2016 in May reporting month. The exceedances were concluded as non-project related

 

Air Quality Monitoring

  1. Due to interruption of electricity supply, the 24hr TSP and 1hr TSP was rescheduled as follows:

24hr TSP at CMA6a was rescheduled from 11, 17 and 23 March 2016 to 12, 18 and 24 March 2016 respectively in March reporting month.

24hr TSP at CMA1b was rescheduled from 13 April 2016 to 14 April 2016 in April reporting month.

24hr TSP at CMA3a was rescheduled from 29 March 2016 and 1 April 2016 to 1 April 2016 and 2 April 2016 respectively in April reporting month.

24hr TSP at CMA5b was rescheduled from 13 April 2016 to 14 April 2016 in April reporting month.

24hr TSP at CMA6a was rescheduled from 29 March 2016 and 19 April 2016 to 30 March 2016 and 20 April 2016 respectively in April reporting month.

1hr TSP at CMA2a monitoring station was rescheduled from 5 May 2016 to 7 May 2016 in May reporting month.

24hr TSP at CMA5b monitoring station was rescheduled from 20 May 2016 to 21 May 2016 in May reporting month.

  1. No action or limit level exceedance for TSP monitoring was recorded in March reporting month.
  2. One action level exceedance of 1hr TSP monitoring was recorded at CMA5b monitoring station – Pedestrian Plaza on 14 April 2016 in April reporting month. The exceedance was concluded as non-project related.
  3. No action or limit level exceedance for TSP monitoring was recorded in May reporting month.
  4. Due to closure of major road and pedestrian access to monitoring station, 1hr TSP monitoring at CMA5b monitoring station was rescheduled from 17 May 2016 to 20 May 2016.
  5. The location ID of air monitoring station CMA1b was updated as Oil Street Site Office in April 2013.
  6. With respect to the area handover, the air quality monitoring station CMA5a at Children Playgrounds opposite to the Pedestrian Plaza was relocated to the Pedestrian Plaza on 3 December 2014. The station reference and location ID of the air quality monitoring station CMA5a was updated as CMA5b and Pedestrian Plaza respectively.
  7. 1hr and 24hr TSP monitoring were conducted at CMA1b, CMA2a, CMA3a, CMA4a, CMA5b and CMA6a in the reporting period.

 

Water Quality Monitoring

  1. As advised by WDII RSS, the works under Contract HK/2009/01, HK/2009/02 (at WCRIII area) and HK/2012/08 were suspended from 16 May 2016 to 19 May 2016, WQM event at WQM station WSD19, P1, P3, P4, P5 and C1 were temporary suspended on 17 May 2016 and 19 May 2016.
  2. As advised by the Contractor of HK/2009/01, all silt screen remains removal works at P1, P3, P4, P5 and C1 water quality monitoring stations were completed on 8 May 2016.
  3. With respect to the silt screen remains removal works at P1, P3, P4, P5 and C1 water quality monitoring stations conducted by Contractor of HK/2009/01, the water quality monitoring at associated station was temporary suspended as follows:

P1 monitoring station was temporary suspended on 3 May 2016 during flood tide and ebb tide

C1 monitoring station was temporary suspended on 5 May 2016 during ebb tide

  1. P4 and P5 monitoring stations were temporary suspended on 7 May 2016 during flood tide
  2. Due to the hoisting of amber rainstorm warning signal, the WQM was cancelled as follows:

WQM on 13 April 2016 Flood tide

WQM on 22 April 2016 Ebb tide

  1. Action and Limit level of water quality monitoring was transited from dry season to wet season from 1 April 2016.
  2. With respect to the marine works undertaken at WCR3 by Contract HK/2009/02, the respective water quality monitoring station C1 associated with Contract HK/2009/01 was updated as in association with Contract HK/2009/01 and Contract HK/2009/02.
  3. With respect to the marine works undertaken at CBTS by Contract HY/2010/08, the respective water quality monitoring station C7 associated with Contract HY/2009/15 was updated as in association with Contract HY/2009/15 and Contract HY/2010/08.
  4. With respect to the marine works undertaken at HKCEC2 by Contract HK/2012/08, the respective water quality monitoring station WSD19, P1, P3, P4, and P5 were associated with Contract HK/2012/08.
  5. There were 2 action level and 2 limit level of turbidity exceedances recorded in March reporting month. Investigation found that 2 limit level of turbidity exceedances recorded at monitoring station RW21-P789 on 9 March 2016 in March reporting month was concluded as related to Project works. Investigation found that 2 action level of the turbidity exceedances at monitoring station WSD19 recorded in March reporting month were not related to Project works.
  6. There were 1 action level and 1 limit level of turbidity exceedances recorded in April reporting month. Investigation found that the exceedances recorded in April reporting month were not related to Project works.
  7. There were 12 action level and 11 limit level of turbidity exceedances and 1 action level and 1 limit level of suspended solid exceedances recorded in May reporting month. Investigation found that 1 action level and 1 limit level of turbidity exceedances recorded at monitoring station C7 on 29 April 2016 in May reporting month was concluded as related to Project works.

Investigation found that 10 action level and 10 limit level of turbidity exceedances and 1 action level and 1 limit level of suspended solid exceedances recorded in May reporting month were not related to Project works.

  1. Enhanced DO monitoring at 2 monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was conducted three days per week during the reporting period.
  2. There was no action level and 2 limit level exceedances recorded for enhanced dissolved oxygen monitoring in March reporting month. Investigation found that the exceedance was not related to Project works.
  3. There was no action level and 1 limit level exceedances recorded for enhanced dissolved oxygen monitoring in April reporting month. Investigation found that the exceedance was not related to Project works.
  4. There was 2 action level and 4 limit level exceedances recorded for enhanced dissolved oxygen monitoring in May reporting month. Investigation found that the exceedance was not related to Project works.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. No environmental complaint was received in March reporting month.

 

  1. There was one environmental complaint received in April reporting month.

 

  1. The public complaint regarding muddy water discharge referred by EPD was received by ET on 13 April 2016 (EPD Ref.: H05/RS/00008367-16 dated 13 April 2016). The complainant reported that muddy water was discharged from the construction work of Contract HK/2012/08 to the sea outside the Hong Kong Academy for Performing Arts on 13 April 2016 morning.

 

  1. According to the relevant site records provided by RSS, internal transport of soil to the hopper barge for storage via landing barge was conducted by Contractor of HK/2012/08 during 0800 hours to 1000 hours on 13 April 2016 at the sea outside the concerned location and 3 nos. of dump trucks were deployed for the operation. Protection measure including provision of sandbag bunding along the side of the landing barge was implemented by the Contractor of HK/2012/08. In addition, amber rainstorm warning signal was hoisted from 0630 hours to 1200 hours on 13 April 2016 and during the above time period, muddy water was observed from the upstream of culvert L outside the HK/2012/08 site.

 

  1. Follow up inspection was conducted on 19 April 2016, protection measures including provision of sandbag bunding along the side of the landing barge was implemented and no mud or soil deposition was observed along the seawall and no discharge point was located within the temporary water channel connecting the Culvert L outfall location to the Victoria Harbour. In addition, piling works was observed at the north side of Zone A1 on 19 April 2016 and construction effluent collection from piling work via sedimentation tank to wastewater treatment facility was implemented and steel barrier was installed around the piling works area to mitigate against potential surface runoff related impact.

 

  1. Nevertheless, in view of the public concern, the Contractor was reminded to maintain adequate perimeter embankment protection along the seawall boundary and maintain proper construction effluent collection system to avoid potential runoff related impact to nearby waters.

 

  1. No environmental complaint was received in May reporting month.

1.         Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-06/356/2009 and FEP-07/356/2009  to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.4 of EM&A Manual and “Environmental Monitoring and Audit Requirements” under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works during the period from 27th February 2016 to 26th May 2016.

1.2          Structure of the Report

 

Section 1          Introduction – details the scope and structure of the report.

 

Section 2          Project Background – summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3          Monitoring Requirements – summarizes all monitoring parameters, monitoring locations, monitoring frequency, duration and action plan.

 

Section 4          Monitoring Results – summarizes the monitoring results obtained in the reporting period.

 

Section 5          Compliance Audit – summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 6          Complaints, Notification of summons and Prosecution – summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 7          Cumulative Construction Impact due to the Concurrent Projects summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8          Conclusion

2.         Project Background

2.1          Background

2.1.1.     “Wan Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2          Scope of the Project and Site Description

2.2.1.     The Project is located mainly in Wan Chai North, Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road Interchange to the east, as shown in Figure 2.1.

2.2.2.     The study area encompasses existing developments along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police Officers' Club, the Causeway Bay Typhoon Shelter (CBTS) and commercial and residential developments.

2.2.3.     The scope of the Project comprises:

·          Land formation for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for connection to the Trunk Road and for through traffic from Central to Wan Chai and Causeway Bay. The land formed for the above transport infrastructure will provide opportunities for the development of an attractive waterfront promenade for the enjoyment of the public

·          Reprovisioning / protection of the existing facilities and structures affected by the land formation works mentioned above

·          Extension, modification, reprovisioning or protection of existing storm water drainage outfalls, sewerage outfalls and watermains affected by the revised land use and land formation works mentioned above

·          Upgrading of hinterland storm water drainage system and sewerage system, which would be rendered insufficient by the land formation works mentioned above

·          Provision of the ground level roads, flyovers, footbridges, necessary transport facilities and the associated utility services

·          Construction of the new waterfront promenade, landscape works and the associated utility services

·          The Trunk Road (i.e. CWB) within the study area and the associated slip roads for connection to the Trunk Road.

 

2.2.4.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

 

2.3          Division of the Project Responsibility

2.3.1       Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HK/2010/06 – Wan Chai Development Phase II – Central – Wan Chai Bypass over MTR Tsuen Wan Line under FEP-05/356/2009

2.3.2       The construction works were completed and the FEP-05/356/2009 was surrendered by the Contractor on 3 October 2014.

Contract no. HY/2009/11 – Wan Chai Development Phase II – Central – Wan Chai Bypass - North Point Reclamation

2.3.3       The construction works were completed and the FEP-01/356/2009 was surrendered by the Contractor on 22 October 2012.

2.3.4       Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits (FEP) such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.5       The details of individual contracts are summarized in Table2.2.

Table 2.2    Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HK/2009/01

Wan Chai Development Phase II – Central –Wanchai Bypass at Hong Kong Convention and Exhibition Centre

DP3, DP6

23 July 2010

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East

DP3, DP5

5 July 2010

DP1

26 April 2011

HY/2009/11

Wan Chai Development Phase II and Central – Wan Chai Bypass – North Point Reclamation

DP3

17 March 2010

(Completed)

HY/2009/15

Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

DP3

10 November 2010

DP1

13 July 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

(Completed)

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

(Completed)

HY/2009/17

Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works.

DP1

5 October 2010

(Completed)

HY/2009/18

Central - Wan Chai Bypass (CWB) – Central Interchange

DP1

10 March 2014

HY/2009/19

Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

HK/2012/08

Wan Chai Development Phase II Central-

Wan Chai Bypass at Wan Chai

West

DP1,DP2, DP3

5 March 2013

HY/2011/08

Central-Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

DP1

8 October 2014

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer’s Representative  for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer’s Representative  for CWB

Principal Resident Engineer

Mr. Peter Poon

3912 3388

3912 3010

Chun Wo – Leader Joint Venture

Contractor under Contract no. HK/2009/01

Project Manager

Mr. Simon Liu

9304 8355

2587 1878

Site Agent

Mr. Andy Yu

9648 4896

Engineer Manager

Mr. Terry Wong

9757 9846

Construction Manager

Mr. Wyman Wong

9627 2467

Construction Manager

Mr. Kenneth Chan

9160 3850

Environmental Officer

Ms. Wendy Ng

9803 0057

Assistant Environmental Engineer

Miss. Connie Chan

6157 7057

Chun Wo – CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Project Manager

Mr. Paul Yu

3658 3085

2827 9996

Quality & Environmental Manager

Mr. C.P. Ho

9191 8856

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Chris Leung

3557 6393

2566 2192

 

Site Manager

Y Huo

 

3557 6368

Contractor’s Representative

Rex Lau

3557 6405

 

 

Contractor’s Representative

Gene Cheung

3557 6395

 

 

Environmental Officer

Andy Mak

3557 6347

Chun Wo - CRGL - MBEC Joint Venture

Contractor under Contract no. HY/2009/19

 

Project Manager

Rayland Lee

3758 6788

2570 8013

Site Agent

David Lau

3758 8879

Environmental Manager /

Environmental Officer

Eric Fong

6191 9337

Construction Manager (Marine)

M.H. Isa

9884 0810

Construction Manager

(Land)

Andy Chan

9879 4325

Construction Manager

(Land)

Bear Ding

6483 6198

Operation Manager (Land)

Yung Kwok Wah

9834 1010

China State-

Leader JV

Contractor

under Contract

no. HK/2012/08

Project Director

C. N. Lai

9106 5806

2877 1522

Project Manager

Eddie Chung

9189 8118

 

 

 

Site Agent

Keith Tse

9037 1839

 

Environmental Officer

James Ma

9130 9549

 

Environmental Supervisor

Y. L. Ho

9856 5669

 

China State

 

Contractor

under Contract

no. HY/2010/08

Project Director

Chris Leung

3467 4299

2566 8061

Project Manager

Chan Ying Lun

3418 3001

 

Site Agent

Dave Chan

3467 4277

 

 

 

Environmental Officer

Gabriel Wong

35576466

 

 

 

Environmental Supervisor

Desmond Ho Tsz Ho

3557 6466

 

Ramboll Environ Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

34652888

34652899

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

2.5          Principal Work and Activities

2.5.1.     During this reporting period, the principal work activities for Contract no. HK/2009/01 are summarized in Table 2.4.

 

 

Table 2.4    Principal Work Activities for Contract no. HK/2009/01

March 2016

April 2016

May 2016

Ÿ   Nil

Ÿ   Nil

Ÿ    Nil

 

2.5.2.     During this reporting period, the principal work activities for Contract no. HK/2009/02 are summarized in Table 2.5.

Table 2.5    Principal Work Activities for Contract no. HK/2009/02

March 2016

April 2016

May 2016

Ÿ   Nil

 

Ÿ   Nil

Ÿ   Inspection / Trimming of rockfill profile in front of seawall

Ÿ   Rock armor installation

 

2.5.3.     Major construction activities for Contract no. HY/2009/15 was commenced on 10 November 2010. During this reporting period, the principal work activities for Contract no. HY/2009/15 are summarized as below:

Table 2.6    Principal Work Activities for Contract no. HY/2009/15

March 2016

April 2016

May 2016

·         Reinstatement of vertical seawall at TPCWAE

·          Reinstatement of vertical seawall at TPCWAE

·          Reinstatement of vertical seawall at TPCWAE

·          Removal of temporary reclamation at TPCWAW

 

2.5.4.     Contract no. HY/2009/19 was commenced on 24 March 2011. During this reporting period, the principal work activities for Contract no. HY/2009/19 are summarized as below:

Table 2.7    Principal Work Activities for Contract no. HY/2009/19

March 2016

April 2016

May 2016

Ÿ  Nil

Ÿ  Nil

Ÿ   Nil

 

2.5.5.     Contract no. HK/2012/08 was commenced on March 2013. During this reporting period, the principal work activities for Contract no. HK/2012/08 are summarized as below:

Table 2.8    Principal Work Activities for Contract no. HK/2012/08

March 2016

April 2016

May 2016

Ÿ   Construction of culvert

Ÿ   Construction of dry dock

Ÿ   Trimming of rock bedding

Ÿ   Installation of seawall blocks

Ÿ   Filling adjacent to culvert L

Ÿ   Temporary works for culvert L Bay 8

Ÿ   Trimming of rock bedding

Ÿ   Precast unit construction for Box 1 inside Dry dock

Ÿ   Construction of culvert L Bay 8

Ÿ   Pre-bored H-pile installation for culvert L1/FRP-L Bay 12 and Bay 13

Ÿ   Precast unit construction for Box 1 inside Dry dock

Ÿ   Construction of culvert L Bay 8

Ÿ   Pre-bored H-pile installation for culvert L1/FRP-L Bay 12 and Bay 13

 

2.5.6.     Contract no. HY/2010/08 was commenced on 21 March 2013. During this reporting period, the principal work activities for Contract no. HY/2010/08 are summarized as below:

Table 2.9    Principal Work Activities for Contract no. HY/2010/08

March 2016

April 2016

May 2016

Ÿ   Diversion pipe maintenance

Ÿ   Diversion pipe maintenance

Ÿ   Diaphragm Wall Removal Works

Ÿ   Diversion pipe maintenance

Ÿ   Diaphragm Wall Removal Works

 

2.5.7.     Implementation status of the recommended mitigation measures during this reporting period is presented in Appendix 2.1.

3.         Monitoring Requirements

3.1.          Noise Monitoring

Noise Monitoring Stations

3.1.1.     The noise monitoring stations for the Project are listed and shown in Table 3.1 and Figure 3.1.  Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.1    Noise Monitoring Stations

Station

Description

M1a

Harbour Road Sports Centre

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

 

 

Noise Monitoring Parameters, Frequency and Duration

3.1.2.     The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

3.1.3.     Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

·          one set of measurements between 0700 and 1900 hours on normal weekdays.

3.1.4.     If construction works are extended to include works during the hours of 1900 – 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

3.1.5.     Real time noise shall be carried out at the designated monitoring stations. The following is an initial guide on the regular monitoring frequency for each station on a 24 hours daily basis when noise generating activities are underway:

·          One set of measurements between 0700 and 1900 hours on normal weekdays.

·          One set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.

·          One set of measurements between 2300 and 0700 hours on next day on everyday.

 

Monitoring Equipment

3.1.6.     As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

3.1.7.     Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

3.2.                Air Monitoring

Air Quality Monitoring Stations

3.2.1.     The air monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.2    Air Monitoring Stations

Station ID

Monitoring Location

Description

CMA1b

Oil Street Site Office**

North Point

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

CWB PRE Site Office *

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5b

Pedestrian Plaza***

Wan Chai

CMA6a

WDII PRE Site Office *

Wan Chai

Remarks*: As per the ENPC meeting in January 2011, the monitoring stations CMA3a - Future CWB site office at Wanchai Waterfront Promenade and CMA6a - Future AECOM site office at Work Area were renamed as remark.

Remarks**: The location ID of monitoring station CMA1b was updated as “Oil Street Site Office” in April 2013.

Remarks***: The station ID and monitoring location was updated in December 2014 with respect to monitoring station relocation.

 

 

Air Monitoring Parameters, Frequency and Duration

3.2.2.     One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

3.2.3.     All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

3.2.4.     For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.

Sampling Procedure and Monitoring Equipment

3.2.5       High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

·          0.6 - 1.7 m3 per minute adjustable flow range;

·          equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

·          installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

·          capable of providing a minimum exposed area of 406 cm2;

·          flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

·          equipped with a shelter to protect the filter and sampler;

·          incorporated with an electronic mass flow rate controller or other equivalent devices;

·          equipped with a flow recorder for continuous monitoring;

·          provided with a peaked roof inlet;

·          incorporated with a manometer;

·          able to hold and seal the filter paper to the sampler housing at horizontal position;

·          easily changeable filter; and

·          capable of operating continuously for a 24-hour period.

3.2.6       Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

Laboratory Measurement / Analysis

3.2.7       A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

3.2.8       An alternative non-HOKLAS accredited laboratory was set-up for carrying out the laboratory analysis, the laboratory equipment was approved by the ER on 8 February 2011 and the measurement procedures were witnessed by the IEC. Any measurement performed by the laboratory was be demonstrated to the satisfaction of the ER and IEC. IEC shall regularly audit to the measurement performed by the laboratory to ensure the accuracy of measurement results.

3.2.9       Filter paper of size 8" x 10" shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

3.2.10    After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

3.2.11    All the collected samples shall be kept in a good condition for 6 months before disposal.

 

impact monitoring for odour patrol

3.2.12    Odour patrols along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai Public Cargo Working Area when there is temporary reclamation in Causeway Bay Typhoon Shelter and/or in the ex-Wan Chai Public Cargo Working Area, or when there is dredging of the odorous sediment and slime at the south-western corner of the Causeway Bay Typhoon Shelter. Odour patrols will be carried out at bi-weekly intervals during July, August and September by a qualified person of the ET who shall:

·        be at least 16 years of age;

·        be free from any respiratory illnesses; and

·        not be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30 min

·        before and during odour patrol

3.2.13    Odour patrol shall be conducted by independent trained personnel / competent persons patrolling and sniffing around the shore as shown in Figure 3.1 to detect any odour at the concerned hours (afternoon is preferred for higher daily temperature).

3.2.14    The qualified person will use the nose (olfactory sensor) to sniff odours at different locations. The main odour emission sources and the areas to be affected by the odour nuisance will be identified.

3.2.15    The perceived odour intensity is to be divided into 5 levels which are ranked in the descending order as follows:

·            0 - Not detected. No odour perceived or an odour so weak that it cannot be easily characterized or described;

·            1 - Slight Identifiable odour, and slight chance to have odour nuisance;

·            2 - Moderate Identifiable odour, and moderate chance to have odour nuisance;

·            3 - Strong Identifiable, likely to have odour nuisance;

·            4 - Extreme Severe odour, and unacceptable odour level.

 

3.2.16    The findings including odour intensity, odour nature and possible odour sources, and also the local wind speed and direction at each location will be recorded. In addition, some relevant meteorological and tidal data such as daily average temperature, and daily average humidity, on that surveyed day will be obtained from the Hong Kong Observatory Station for reference. The Action and Limit levels for odour patrol are shown in Appendix 3.1.

3.3    Water Quality Monitoring

3.3.1.     The EIA Report has identified that the key water quality impact would be associated with the dredging works during the construction phase.  Marine water quality monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is therefore recommended to be carried out at selected WSD flushing water intakes.  The impact monitoring should be carried out during the proposed dredging works to ensure the compliance with the water quality standards.

3.3.2.     The updated EM&A Manual for EP-356/2009 (Version in March 2011) is approval by EPD on 29 April 2011. As such, the Action Level and Limit Level for the wet season (April – September) will be effected and applied to the water quality monitoring data from 30 April 2011.

Water Quality Monitoring Stations

3.3.3.     Water quality monitoring was undertaken at WSD salt water intakes and cooling water intakes along the seafront of the Victoria Harbour.  The proposed water quality monitoring stations of the Project are shown in Table 3.3 and Figure 3.1.  Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.3    Marine Water Quality Stations for Water Quality Monitoring

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD19

Sheung Wan

833415.0

816771.0

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

C7

Windsor House

837193.7

816150.0

P1

HKCEC Phase I

835774.7

816179.4

P3

The Academy of performing Arts

835824.6

816212.0

P4

Shui on Centre

835865.6

816220.0

P5

Government Buildings

(Wanchai Tower / Revenue Tower / Immigration Tower)

835895.2

816215.2

Cooling Water Intake / WSD Salt Water Intake

RW21-P789

Great Eagle Centre/ Sun Hung Kai Centre/ WSD Wanchai salt water intake

836268.0

816020.0

Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

-   4-week post construction water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012 and the water quality monitoring at WSD 10 and WSD15 were temporary suspended since 8 Feb 2012, and WSD9 and WSD17 was implemented with respect to HK/2009/02 from 8 Feb 2012 onwards.

-   C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.

-   C8 & C9 were temporary suspended since 30 March 2013.

-   WSD7 and WSD20 water quality monitoring were temporarily suspended from 27 Apr 2012.

-   C2, C3 C4e and C4w water quality monitoring station was temporarily suspended since 24 Apr 2013

-   C5e and C5w water quality monitoring station was temporarily suspended since 29 July 2013.

-   WSD21 water quality monitoring station was temporarily suspended since 12 March 2014

-   WSD9 and WSD17 water quality monitoring station was temporarily suspended since 8 September 2014 flood tide.

-    The water quality monitoring station C1 shall be associated with Contract No. HK/2009/02 upon commencement of marine works under DP3 at WCR3 area

 

Water Quality Parameters and frequency

3.3.4.     Monitoring of dissolved oxygen (DO), turbidity and suspended solids (SS) shall be carried out at WSD flushing water intakes and cooling water intakes. DO and Turbidity are measured in-situ while SS is determined in laboratory. 

3.3.5.     In association with the water quality parameters, other relevant data shall also be measured, such as monitoring location/position, time, sampling depth, water temperature, pH, salinity, dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal stage, and any special phenomena and work underway at the construction site etc.

3.3.6.     The interval between two sets of monitoring should not be less than 36 hours except where there are exceedances of Action and/or Limit Levels, in which case the monitoring frequency will be increased.  Table 3.4 shows the proposed monitoring frequency and water quality parameters.  Duplicate in-situ measurements and water sampling should be carried out in each sampling event.  For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5m.

 

Table 3.4    Marine Water Quality Monitoring Frequency and Parameters

Activities

Monitoring Frequency1

Parameters2

During the 4-week baseline monitoring period

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

During marine construction works

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

After completion of marine construction works

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

Notes:

1.     For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5m.

2.     Turbidity should be measured in situ whereas SS should be determined by laboratory.

 

Dissolved Oxygen and Temperature Measuring Equipment

3.3.7.     The instrument should be a portable, weatherproof dissolved oxygen measuring instrument complete with cable, sensor, comprehensive operation manuals, and use a DC power source. It should be capable of measuring:

·          a dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation

·          a temperature of 0-45 degree Celsius

3.3.8.     It should have a membrane electrode with automatic temperature compensation complete with a cable. Sufficient stocks of spare electrodes and cables should be available for replacement where necessary. (e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).

3.3.9.     Should salinity compensation not be build-in in the DO equipment, in-situ salinity shall be measured to calibrate the DO equipment prior to each DO measurement.

Turbidity Measurement Instrument

3.3.10    The instrument should be a portable, weatherproof turbidity-measuring instrument complete with comprehensive operation manual. The equipment should use a DC power source. It should have a photoelectric sensor capable of measuring turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model 2100P or an approved similar instrument).

Sampler

3.3.11     Water sampler comprises a transparent PVC cylinder, with a capacity of not less than 2 litres, and can be effectively sealed with latex cups at both ends. The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (e.g. Kahlsico Water Sampler or an approved similar instrument).

 

 

 

Sample Container and Storage

3.3.12    Water samples for suspended solids measurement should be collected in high-density polythene bottles, packed in ice (cooled to 4°C without being frozen), and delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection for analysis.

Water Depth Detector

3.3.13    A portable, battery-operated echo sounder shall be used for the determination of water depth at each designated monitoring station. This unit can either be handheld or affixed to the bottom of the workboat, if the same vessel is to be used throughout the monitoring programme.

Salinity

3.3.14    A portable salinometer capable of measuring salinity in the range of 0-40 ppt shall be provided for measuring salinity of the water at each of monitoring location.

Monitoring Position Equipment

3.3.15    A hand-held or boat-fixed type digital Global Positioning System (GPS) with waypoint bearing indication or other equivalent instrument of similar accuracy shall be provided and used during monitoring to ensure the monitoring vessel is at the correct location before taking measurements.

Calibration of In-situ Instruments

3.3.16    All in-situ monitoring instrument shall be checked, calibrated and certified by a laboratory accredited under HOKLAS or equivalent before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring. Responses of sensors and electrodes should be checked with certified standard solutions before each use. Wet bulb calibration for a DO meter shall be carried out before measurement at each monitoring location.

3.3.17    For the on site calibration of field equipment by the ET, the BS 127:1993, "Guide to Field and on-site test methods for the analysis of waters" should be observed.

3.3.18    Sufficient stocks of spare parts should be maintained for replacements when necessary. Backup monitoring equipment shall also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, etc.

 

Laboratory Measurement / Analysis

3.3.19    Analysis of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the monitoring stations for carrying out the laboratory SS determination. The SS determination work shall start within 24 hours after collection of the water samples. The SS determination shall follow APHA 19ed or equivalent methods subject to the approval of IEC and EPD.

 

Enhanced Water Quality Monitoring in the ex-Wan Chai Public Cargo

Working Area and the Causeway Bay Typhoon Shelter

3.3.20    The enhanced water quality monitoring and audit programme is to avoid aggravation of odour nuisance from seawater arising from temporary reclamation in the ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.

3.3.21    Dissolved oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when there is temporary reclamation in Causeway Bay Typhoon Shelter and at the south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working Area. The proposed water quality monitoring stations of the Project are shown in Table 3.5 and Figure 3.1.

Table 3.5    Marine Water Quality Stations for Enhanced Water Quality Monitoring

Station

Location

C6

Excelsior Hotel

C7

Windsor House

Ex-WPCWA-SW

South-western of the ex-Wan Chai Public Cargo Working Area

Ex-WPCWA-SE

South-eastern of the ex-Wan Chai Public Cargo Working Area

Remarks:

1.   Enhanced DO monitoring at Windsor House Cooling (Station Ref: C7) was temporarily suspended since 22 October 2014 with respect to the formation of temporary reclamation zone TS3 and to be resumed upon removal of the respective temporary reclamation zone.

2.   Enhanced DO monitoring at Monitoring station at Ex-PCWAE was temporarily suspended from 31 August 2015 with respect to seawall reinstatement works and formation of active works area, to be resumed upon completion of seawall reinstatement works

3.3.22    The monitoring of dissolved oxygen are to be carried out 3 days per week, at mid-flood and mid-ebb tides for 3 water depths (1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth may be omitted. If the water depth be less than 3m, only the mid-depth will be monitored).

 

Daily SS Monitoring and 24 hours Turbidity Monitoring System

3.3.23    During dredging of the sediment at the south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of suspended solids and 24 hour monitoring of turbidity at the cooling water intakes (C6 and C7) shall be conducted.

3.3.24    The 24 hours monitoring of turbidty at the cooling water intakes (C6 and C7) shall be established by setting up a continuous water quality monitoring station in front of the intakes during the dredging activities.  The monitoring system include the turbidity sensor and data logger which is capable of data capturing at every 5 minutes. The data shall be downloaded daily and compared with the Action and Limit level determined during the baseline water qualtiy monitoring at the cooling water intake locations.

Additional Dissovled oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW

3.3.25    In response to the Condition 2.18 of the Environmental Permit no. EP-356/2009 requiring that a silt curtain / impermeable barrier system be installed to channel water discharge flow from Culvert L to locations outside the embayment area, a proposed replacement of the requirement with additional dissolved oxygen monitoring has been conducted at three monitoring stations, namely A, B and C between the eastern seawall of Central Reclamation Phase III and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level between the eastern seawall of Central Reclamation Phase II and the HKCEC extension could be continuously monitored.

3.3.26    With respect to the commencement of dredging works under HK/2012/08 and the installation of MTR precast protection unit, the enhanced water quality monitoring for Culvert L was temporarily suspended since 24 July 2013

3.3.27    The monitoring of dissolved oxygen are to be carried out once per week, at mid-flood and mid-ebb tides for 3 water depths (1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth may be omitted. If the water depth be equal to or less than 3m, only the mid-depth will be monitored).

4.         Monitoring Results

4.0.1.     The environmental monitoring will be implemented based on the division of works areas of each designed project managed under different contracts with separate FEP applied by individual contractors.  Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 3.1. The monitoring results are presented in according to the Individual Contract(s).

4.0.2   According to EP-364/2009/A Part B, “Scale and Scope of Designated Project”, Remarks (c),”The permanent and temporary reclamation and associated dredging works related to the CWB construction are separately covered by environmental permit No. EP-356/2009 issued to Civil Engineering and Development Department”, and marine piling works to be conducted by the Contractor of Contract no. HY/2009/19 from 28 January 2012 was considered to be governed under EP-356/2009. As the construction site area of Contract no. HY/2009/11 had already been handed over to Contract no. HY/2009/19, the designated noise, water and air quality monitoring stations for Contract no. HY/2009/11 would be shared with Contract no. HY/2009/19 from 28 January 2012.

  4.1.       Noise Monitoring Results

Contract no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC and Contract no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East

4.1.1.     The proposed divisions of noise monitoring stations are summarized in Table 4.1 below.

Table 4.1    Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02

Station

Description

M1a

Harbour Road Sports Centre

4.1.2.     Three limit level exceedances were recorded at M1a- Harbour Road Sports Centre on 02, 08 and 15 March 2016 in March reporting month.

4.1.3.     Operation of multiple air compressor at Ex- Wan Chai Swimming Pool (adjacent to Harbour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor was observed as the major noise contribution during monitoring on 02 and 08 March 2016 while operation of multiple air compressor and piling works at Ex- Wan Chai Swimming Pool (adjacent to Harbour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor as major noise contribution during monitoring on 15 March 2016.  As such, the exceedances were considered as non-Project related.

4.1.4.     Two limit level exceedances were recorded at M1a- Harbour Road Sports Centre on 29 March 2016 and 12 April 2016 in April reporting month.

4.1.5.     Operation of multiple air compressor at Ex- Wan Chai Swimming Pool (adjacent to Harbour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor was observed as the major noise contribution during monitoring on 29 March 2016 while breaking works at Ex- Wan Chai Swimming Pool (adjacent to Harbour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor as major noise contribution during monitoring on 12 April 2016.  As such, the exceedances were considered as non-Project related.

4.1.6.     Two limit level exceedances were recorded at M1a- Harbour Road Sports Centre on 04 and 24 May 2016 in May reporting month.

4.1.7.     Breaking works at Ex- Wan Chai Swimming Pool (adjacent to Harbour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor was observed as the major noise contribution during monitoring on 04 May 2016 while operation of Hydromil Trench Cutter at Ex- Wan Chai Swimming Pool (adjacent to Harbour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor as major noise contribution during monitoring on 24 May 2016.  As such, the exceedances were considered as non-Project related.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

4.1.8.     The noise monitoring for HY/2009/15 was commenced on 10 November 2010. The proposed division of noise monitoring stations are summarized in Table 4.2 below.

Table 4.2    Noise Monitoring Station for Contract nos. HY/2009/15

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

 

4.1.9.     No action or limit level exceedance was recorded in this report quarter.

Contract no. HY/2009/19 – Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

4.1.10.   Noise quality monitoring at M4b and M5b have been implemented with respect to HY/2009/19 since the marine bore piling work started on 28 Jan 2012.

4.1.11.   The proposed division of noise monitoring stations for Contract no. HY/2009/19 are summarized in Table 4.3 below:

  Table 4.3  Noise Monitoring Stations for Contract no.  HY/2009/19

Station

Description

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

 

 

 

 

 

 

4.1.12.   No action or limit level exceedance was recorded in March reporting month.

4.1.13.   Two limit level exceedances were recorded at M6 – HK Baptist Church Henrietta Secondary School on 11 and 19 April 2016 in April reporting month.

4.1.14.   Only welding work was conducted at Pier F8C during the time of measurement on 11 and 19 April 2016 and it was observed that traffic noise was a major noise source during monitoring on 11 and 19 April 2016. It is concluded that the exceedances were not due to project but to traffic noise nearby.

4.1.15.   No action or limit level exceedance was recorded in May reporting month.

Contract no. HY/2010/08-Central-Wanchi Bypass Tunnel (Slip Road 8 Section)

4.1.16.   The proposed division of noise monitoring stations are summarized in Table 4.4 below.

Table 4.4     Noise Monitoring Station for Contract no. HY/2010/08

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

 

 

 

4.1.17.   No action or limit level exceedance was recorded in the reporting quarter.

4.1.18.   All Noise monitoring results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and graphical presentation can be referred in Appendix 4.1.

  4.2.       Air Monitoring Results

4.3.1.     1hr and 24hr TSP monitoring were conducted at CMA1b, CMA2a, CMA3a, CMA4a, CMA5b and CMA6a in the reporting period.

 

Contract no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC

4.3.2.     Air monitoring was commenced on 1 April 2011 in response to the commencement of the land-filling work for Contract no. HK/2009/01. The proposed division of air monitoring stations are summarized in Table 4.5 below.

Table 4.5      Air Monitoring Stations for Contract no. HK/2009/01

Station

Description

CMA5b

Pedestrian Plaza

CMA6a

WDII PRE Site Office *

4.3.3.     No action or limit level exceedance was recorded in March reporting month.

4.3.4.     One action level exceedance was recorded at monitoring station CMA5b on 14 April 2016 during 1hr TSP monitoring in April reporting month.

4.3.5.     Only work activities within tunnel section and no construction activities at ground was undertaken on the monitoring date around Pedestrian Plaza under Contract HK/2009/01 and no particular observation regarding air quality impact was observed during sampling. In view of the above, the action level exceedance was considered to be non-project related and contributed by local ambient condition.

4.3.6.     No action or limit level exceedance was recorded in May reporting month.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East

4.3.7.     Air monitoring was commenced in mid-January 2011 for the land-filling work for Contract no. HK/2009/02. The proposed division of air monitoring stations is summarized in Table 4.6 below.

Table 4.6      Air Monitoring Station for Contract no. HK/2009/02

Station

Description

CMA4a

Society for the Prevention of Cruelty to Animals

4.3.8.     No action or limit level exceedance was recorded in March, April and May reporting month.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

4.3.9.     Air monitoring was commenced on 15 March 2011 for the land filling work for Contract no. HY/2009/15.  The proposed division of air monitoring stations are summarized in Table 4.7 below.

Table 4.7      Air Monitoring Station for Contract no. HY/2009/15

Station

Description

CMA3a

CWB PRE Site Office

4.3.10.   No action or limit exceedance was recorded in this reporting quarter.

 

Contract no. HY/2009/19 –Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

4.3.11.   Air monitoring at CMA1b and CMA2a have been implemented with respect to HY/2009/19 since the marine bore piling works started on 28 Jan 2012. No exceedance was recorded in the reporting period.

4.3.12.   The proposed division of air monitoring stations is summarized in Table 4.8 below.

Table 4.8 Air Monitoring Stations for Contract no. HY/2009/19

Station

Description

CMA1b

Oil Street Site Office

CMA2a

Causeway Bay Community Centre

4.3.13.   No action or limit exceedance was recorded in this reporting quarter.

 

Contract no. HK/2012/08- Wan Chai Development Phase II – Central-Wan Chai Bypass at Wan Chai West

4.3.14.   The proposed division of air monitoring stations are summarized in Table 4.9 below.

Table 4.9    Air Monitoring Stations for Contract no. HK/2012/08

Station

Description

CMA5b

Pedestrian Plaza

4.3.15.   No action or limit level exceedance was recorded in March reporting month.

4.3.16.   One action level exceedance was recorded at monitoring station CMA5b on 14 April 2016 during 1hr TSP monitoring in April reporting month.

4.3.17.   After investigation, formwork erection and internal transfer of excavated material were undertaken on the monitoring date at around Pedestrian Plaza under Contractor of HK/2012/08, dust suppression measure including haul road and excavated soil maintained in dampened condition were implemented and no particular observation regarding air quality impact was observed during sampling. In view of the above, the action level exceedance was considered to be non-project related and contributed by local ambient condition.

4.3.18.   No action or limit level exceedance was recorded in May reporting month.

Contract no. HY/2010/08- Central-Wanchai Bypass Tunnel (Slip Road 8 Section)

The proposed division of air monitoring stations are summarized in Table 4.10 below.

Table 4.10 Air Monitoring Stations for Contract no. HY/2010/08

Station

Description

CMA3a

CWB PRE Site Office

4.3.19.   No action or limit level exceedance was recorded in this reporting quarter.

4.4      Water Monitoring Results

Contract no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC

4.4.1.     Water quality monitoring for Contract no. HK/2009/01 was commenced on 23 July 2010. The proposed division of water monitoring stations is summarized in Table 4.11 below.

4.4.2.     Water quality monitoring station RW21-P789 has been implemented with respect to HK/2009/02 started on 29 July 2013.

Table 4.11 Water Monitoring Stations for Contract no. HK/2009/01

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

 

4.4.3.     No action or limit level exceedance was recorded in March reporting month.

4.4.4.     No action or limit level exceedance was recorded April reporting month.

4.4.5.     There were 2 action and 1 limit level turbidity exceedances recorded at C1 on 5, 7 and 9 May 2016 in May reporting month.

4.4.6.     Despite silt screen removal works was conducted on 5 May 2016, removal works including silt screen’s frame cutting and lifting works were observed conducted orderly and contractor clarified the cooling intake water supplies was temporary suspended during removal works. Low SS level was recorded during the monitoring period. In view of the above, the turbidity exceedance was considered not related to project works.

4.4.7.     Despite silt screen removal was conducted at P4 & P5 monitoring stations on 7 May 2016, only wielding works and lifting works was involved and no particular effect on water quality was considered. In addition, only low suspended solid level was recorded during the monitoring period. In view of the above and no turbidity exceedance was recorded on the subsequent monitoring, the turbidity exceedance was considered not related to project works.

4.4.8.     No marine activity was conducted on 9 May 2016. Territory wide water quality variation was observed across Wan Chai East to Sheung Wan at both upstream and downstream locations of works area potentially in related to seasonal tide changes. In view of the above and no exceedance was recorded on the subsequent monitoring, the exceedance was considered not related to project works.

Contract no. HK/2009/02 - Wan Chai Development Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East

4.4.9.     Water quality monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010. The proposed division of water monitoring stations is summarized in Table 4.12 below.

Table 4.12 Water Monitoring Stations for Contract no. HK/2009/02

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

Cooling Water Intake

RW21-P789

Great Eagle Centre/ Sun Hung Kai Centre/WSD Wanchai salt water intake / China Resources Building

836268.0

816020.0

 

4.4.10.   There were 2 limit level turbidity exceedances recorded at RW21-P789 on 9 March 2016 in the reporting month.

4.4.11.   Despite no marine construction activities was conducted under Contract HK/2009/02 during the monitoring period on 9 March 2016, overflow of contaminated surface runoff into nearby waters at WCR2 site area was observed during monitoring and affecting the water quality within and outside the silt screen enclosed waterbody at RW21-P789 WQM station. As such, it was concluded that the exceedance was project related and the Contractor of HK/2009/02 was immediately advised to take immediate action to rectify the defects observed. Relevant mitigation measures including provision of water pump to direct the contaminated surface runoff to the nearby collection point and reinforcement of concrete bunding at the concerned location to prevent further surface runoff were implemented by the Contractor of HK/2009/02 on 9 March 2016. Additional monitoring was conducted on 10 March 2016 and the water quality at the concerned location has returned to normal level during the additional monitoring on 10 March 2016. Nevertheless, the contractor was reminded to maintain regular checking of the installed silt screen at WQM station RW21-P789.

4.4.12.   No action or limit level exceedance was recorded in April reporting month.

4.4.13.   There were 2 action and 1 limit level turbidity exceedances recorded at C1 on 5, 7 and 9 May 2016 in May reporting month.

4.4.14.   No marine activity was conducted on 5 and 9 May 2016. In view of no marine activity was conducted during monitoring period, the exceedances were considered not related to project works.

4.4.15.   Despite seawall trimming works were conducted on 7 May 2016, contractor mitigation measures including the use of silt curtain was in place. In view of the above, it is considered that the exceedance was not related to project works.

4.4.16.   There were 1 action and 2 limit level turbidity exceedances recorded at RW21-P789 on 29 April 2016, 5 and 9 May 2016 in May reporting month.

4.4.17.   Despite rock armour placing works at seawall near Expo Drive East was conducted on 29 April 2016, contractor mitigation measures include the use of silt curtain was in place, and installed silt screen was generally in order. Location of the construction area was downstream of RW21-P789 monitoring station during monitoring period. In view of the above and no exceedance was recorded on the subsequent monitoring, it was considered that the exceedance was not project related.

4.4.18.   No marine activity was conducted on 5 and 9 May 2016. In view of no marine activity was conducted and no exceedance was recorded on the subsequent monitoring, it is considered that the exceedances were not project related.

Contract no. HK/2012/08 - Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West

 

4.4.19.   Water monitoring for Contract no. HK/2012/08 was commenced on 5 March 2013. The proposed division of water monitoring stations are summarized in Table 4.13 below.

Table 4.13 Water Monitoring Stations for Contract no. HK/2012/08

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD19

Sheung Wan

833415.0

816771.0

Cooling Water Intake

P1

HKCEC Phase I

835774.7

816179.4

P3

The Academy of performing Arts

835824.6

816212.0

P4

Shui on Centre

835865.6

816220.0

P5

Government Buildings

(Wanchai Tower / Revenue Tower / Immigration Tower)

835895.2

816215.2

4.4.20.   There was 2 action level turbidity exceedances recorded at WSD19 on 21 and 23 March 2016 in March reporting month.

4.4.21.   After checking with contractor, despite trimming of grade 400 rock mound profile was conducted under Contract HK/2012/08 at Zone D on 21 and 23 March 2016, contractor mitigation measures including the use of localized silt curtain was generally in place. The construction area was located at downstream of WSD19 monitoring station during the monitoring period. In view of the above and no exceedance was recorded on the subsequent monitoring, it was considered that the exceedance was not project related.

4.4.22.   There were 1 action level and 1 limit level turbidity exceedances recorded at WSD19 on 29 March 2016 and 20 April 2016 in April reporting month.

4.4.23.   After checking with contractor, despite installation of concrete blocks was conducted near Zone D on 29 March 2016, contractor mitigation measures including the use of localized silt curtain was generally in place. The construction area was located at downstream of WSD19 monitoring station during the monitoring period. In view of the above and no exceedance was recorded on the subsequent monitoring, it was considered that the exceedance was not project related.

4.4.24.   Despite trimming of rock mound profile was conducted near Zone D on 20 April 2016, contractor mitigation measures including the use of localized silt curtain was generally in place. The location of the construction area was located at downstream of WDS19 monitoring station during the monitoring period. In view of the above and no exceedance was recorded on the subsequent monitoring, it was considered that the exceedance was not project related.

4.4.25.   There were 2 action level and 4 limit level turbidity exceedances at WSD19 recorded on 29 April 2016, 3, 5, 7 and 9 May 2016 in May reporting month.

4.4.26.   No marine activity was conducted on 29 April 2016, 3, 5, 7 and 9 May 2016. In view of no marine activity was conducted, it is considered that the exceedances were not project related.

4.4.27.   There was 1 action level turbidity exceedance at P1 recorded on 9 May 2016 in May reporting month.

4.4.28.   No marine activity was conducted on 9 May 2016. The location of the construction area was downstream of P1 monitoring station during the monitoring period. Territory wide water quality variation was observed across Wan Chai East to Sheung Wan at both upstream and downstream locations of works area potential in related to seasonal tide changes. In view of the above and no exceedance was recorded on the subsequent monitoring, the exceedance was considered not related to Project works.

4.4.29.   There were 2 action and 1 limit level turbidity exceedances at P3 recorded on 7 and 9 May 2016 in May reporting month.

4.4.30.   No marine activity was conducted on 7 May 2016. In view of no marine activity conducted, it is considered that the exceedance was not related to project works. Despite silt screen removal was conducted by Contract HK/2009/01 on 7 May 2016, only welding works and lifting works was involved and no particular effect on water quality was considered. In addition, only low suspended solid level was recorded during monitoring period. In view of the above, the turbidity exceedances were not related to project works.

4.4.31.   No marine activity was conducted on 9 May 2016. Territory wide water quality variation was observed across Wan Chai East to Sheung Wan at both upstream and downstream locations of works area potential in related to seasonal tide changes. In view of the above and no exceedance was recorded on the subsequent monitoring, the exceedance was considered not related to Project works.

4.4.32.   There were 1 action level and 2 limit level turbidity exceedance recorded at P4 on 5, 7 and 9 May 2016 in May reporting month.

4.4.33.   No marine activity was conducted on 5 and 7 May 2016. In view of no marine activity conducted, it is considered that the exceedances were not related to project works. Despite silt screen removal was conducted by Contract HK/2009/01 on 5 and 7 May 2016, only welding works and lifting works was involved and no particular effect on water quality was considered. In addition, only low suspended solid level were recorded on 5 and 7 May 2016. In view of the above, the turbidity exceedances were not related to project works.

4.4.34.   No marine activity was conducted on 9 May 2016. Territory wide water quality variation was observed across Wan Chai East to Sheung Wan at both upstream and downstream locations of works area potential in related to seasonal tide changes. In view of the above and no exceedance was recorded on the subsequent monitoring, the exceedance was considered not related to Project works.

4.4.35.   There were 2 action level turbidity exceedances recorded at P5 on 5 and 9 May 2016 in May reporting month.

4.4.36.   No marine activity was conducted on 5 May 2016. In view of no marine activity conducted, it is considered that the exceedance was not related to project works. Despite silt screen removal was conducted by Contract HK/2009/01 on 5 May 2016, only welding works and lifting works was involved and no particular effect on water quality was considered. In addition, only low suspended solid level was recorded during monitoring period. In view of the above, the turbidity exceedance was not related to project works.

4.4.37.   No marine activity was conducted on 9 May 2016. Territory wide water quality variation was observed across Wan Chai East to Sheung Wan at both upstream and downstream locations of works area potential in related to seasonal tide changes. In view of the above and no exceedance was recorded on the subsequent monitoring, the exceedance was considered not related to Project works.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

4.4.38.   Due to the commencement of the maintenance dredging on 10 November 2010, water quality monitoring for Contract no. HY/2009/15 was commenced on 9 November 2010. The proposed division of water monitoring stations is summarized in Table 4.14 and Table 4.15 below.

 

Table 4.14   Water Monitoring Stations for Contract no. HY/2009/15

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C7

Windsor House

837193.7

816150.0

Remarks: -      The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

 

Table 4.15 Enhance Dissolved Oxygen Monitoring Stations for Contract no. HY/2009/15

Station Ref.

Location

C6

Excelsior Hotel

Ex-WPCWA SW

South-western of the ex-Wan Chai Public Cargo Working Area

Remarks:

1.   Enhanced DO monitoring at Windsor House Cooling (Station Ref: C7) was temporarily suspended since 22 October 2014 with respect to the formation of temporary reclamation zone TS3 and to be resumed upon removal of the respective temporary reclamation zone.

2.   Enhanced DO monitoring at Monitoring station at Ex-PCWAE was temporarily suspended from 31 August 2015 with respect to seawall reinstatement works and formation of active works area, to be resumed upon completion of seawall reinstatement works

4.4.39.   There were 2 limit level DO exceedances recorded at Ex-WPCWA SW on 9 and 11 March 2016 in March reporting month.

4.4.40.   After checking with contractor, no marine activity was conducted at TPCWAE on 9 and 11 March 2016, while upstream discharge from nearby culvert was noted. In view of no marine activity was conducted and no exceedance was recorded on the subsequent monitoring, the exceedances were considered not related to Project works.

4.4.41.   There was 1 limit level DO exceedances recorded at Ex-WPCWA SW on 11 April 2016 in April reporting month.

4.4.42.   After checking with contractor, despite backfilling works was conducted at TPCWAW on 11 April 2016, contractor mitigation measures include the use of tarpaulin sheet between barge and land and provision of bunding for site runoff control was generally in place. Meanwhile, upstream discharge from nearby culvert was noted. In view of the above and no exceedance was recorded on the subsequent monitoring, the exceedance was considered not related to the Project works.

4.4.43.   There were 4 limit level DO exceedances recorded at Ex-WPCWA SW on 3, 7, 9 and 25 May 2016 in May reporting month.

4.4.44.   After checking with contractor, despite backfilling works was conducted at TPCWAW on 3 and 9 May 2016, contractor mitigation measures include the use of tarpaulin sheet between barge and land and provision of bunding for site runoff control was generally in place. Meanwhile, upstream discharge from nearby culvert was noted. In view of the above and no exceedance was recorded on the subsequent monitoring, the exceedance was considered not related to the Project works.

4.4.45.   No marine activity was conducted on 7 and 25 May 2016. Upstream discharge nearby culvert was noted. In view of no marine activity and no exceedance was recorded on the subsequent monitoring, the exceedances were considered not related to the Project works.

4.4.46.   There were 2 action level DO exceedances recorded at Ex-WPCWA SE on 23 and 25 May 2016 in May reporting month.

4.4.47.   No marine activity was conducted on 23 and 25 May 2016. Upstream discharge nearby culvert was noted. In view of no marine activity and no exceedance was recorded on the subsequent monitoring, the exceedances were considered not related to the Project works.

4.4.48.   There were 2 action level of suspended solids exceedances recorded at C7 on 27 April 2016 in May reporting month.

4.4.49.   No marine activity was conducted at Causeway Bay Typhoon Shelter on 27 April 2016. In view of no marine activity conducted, it is considered that the exceedances were not related to Project works.

4.4.50.   There were 1 action level and 1 limit level of turbidity exceedances recorded at C7 on 29 April 2016 in May reporting month.

4.4.51.   No marine activity was conducted at Causeway Bay Typhoon Shelter on 29 April 2016. In view of no marine activity conducted, it is considered that the exceedances were not related to Project works.

Contract no. HY/2010/08- Central-Wanchai Bypass Tunnel (Slip Road 8 Section)

4.4.52.   The proposed division of water quality monitoring stations are summarized in Table 4.16 and Table 4.17 below:

Table 4.16 Water quality monitoring Stations for Contract no. HY/2010/08

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C7

Windsor House

837193.7

816150.0

 

Table 4.17 Enhance Dissolved Oxygen Monitoring Stations for Contract no. HY/2010/08

Station Ref.

Location

C6

Excelsior Hotel

Remarks:

1.   Enhanced DO monitoring at Windsor House Cooling (Station Ref: C7) was temporarily suspended since 22 October 2014 with respect to the formation of temporary reclamation zone TS3 and to be resumed upon removal of the respective temporary reclamation zone.

4.4.53.   No action or limit level exceedance was recorded in March reporting month.

4.4.54.   No action or limit level exceedance was recorded in April reporting month.

4.4.55.   There were 2 action level suspended solids exceedance recorded at C7 on 27 April 2016 in May reporting month.

4.4.56.   After checking with the Contractor, despite temporary reclamation removal works were conducted on 27 April 2016, contractor mitigation measures including the use of impermeable barrier and silt curtain was in place. In view of the above, it was considered that the exceedances were not related to project works. Nevertheless, contractor was reminded to maintain the deployed impermeable barrier to safeguard the water quality to nearby water intake.

4.4.57.   There were 1 action level and 1 limit level turbidity exceedances recorded at C7 on 29 April 2016 in May reporting month.

4.4.58.   Underwater excavation works for TS3(E) temporary reclamation removal works was conducted on 29 April 2016 during both flood tide and ebb tide and muddy dispersion was observed around a portion TS3(E ) works area during monitoring sampling at flood tide, and it was observed that the impermeable barrier deployed around the temporary reclamation removal area was not fully extended to seabed level and not fully unclosing the underwater excavation area during monitoring sampling at both ebb and flood tides. In addition, it was observed that the outer layer of silt curtain deployed was incomplete at the concerned location. As such, it was considered that the turbidity exceedance was related to Project works and the contractor was immediately advised to take immediate action to rectify the defects observed. Rectification measures including deployment of impermeable barriers and silt curtain to enclose the concerned works area by contractor was implemented on 30 April 2016 and no further turbidity exceedance was recorded during additional monitoring conducted on 30 April 2016. Nevertheless, the contractor was reminded to maintain regular checking of the installed silt screen at WQM station C7 for safeguarding the water quality to nearby intake.

4.5     Waste Monitoring Results

Contract no. HK/2009/01 - Wan Chai Development Phase II – Central –Wanchai Bypass at HKCEC

4.5.1.     No Inert C&D waste and non-inert C&D waste was disposed of for the site works in this reporting period. Details of the waste flow table are summarized in Table 4.18.

Table 4.18  Details of Waste Disposal for Contract no. HK/2009/01

Waste Type

Quantity this quarter

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

NIL

62116.405

TKO137, TM38

Inert C&D materials recycled, m3

NIL

5856.5

N/A

Non-inert C&D materials disposed, m3

NIL

1673.69

SENT Landfill

Non-inert C&D materials recycled, kg

NIL

203993

N/A

Chemical waste disposed, kg

NIL

10250

N/A

Marine Sediment (Type 1 – Open Sea Disposal) , m3

NIL

(Bulk Volume)

97428.2

(Bulk Volume)

South of Cheung Chau

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3

NIL

(Bulk Volume)

52250

(Bulk Volume)

East of Cha Chau

Dredged Sediment Requiring Type 3 – Special Treatment / Disposal contained in Geosynthetic Containers

NIL

(Bulk Volume)

6773

(Bulk Volume)

East of Cha Chau

4.5.2.     There were no Marine Sediment (Type 1 – Open Sea Disposal) and no Marine Sediment (Type 1- Open Sea Disposal (Dedicate Sites) & Type 2- Confined Marine Disposal) disposed of in this reporting quarter.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai East

4.5.3.     No Inert and non-inert C&D waste were disposed of for the site works in this reporting period. Details of the waste flow table are summarized in Table 4.19.

Table 4.19  Details of Waste Disposal for Contract no. HK/2009/02

Waste Type

Quantity this quarter

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

NIL

276075.1

TKO137/ TM 38

Inert C&D materials recycled, m3

NIL

18161

N/A

Non-inert C&D materials disposed, m3

NIL

1515.103

SENT Landfill

Non-inert C&D materials recycled, m3

N/A

N/A

N/A

Chemical waste disposed, kg

NIL

13860

SENT Landfill

Marine Sediment (Type 1 – Open Sea Disposal), m3

NIL

240222

(Bulk volume)

South of Cheung Chau

 

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal), m3 *

NIL

146445

(Bulk volume)

East of Sha Chau

4.5.4.     There was no Marine Sediment (Type 1 – Open Sea Disposal) and no Marine Sediment (Type 1- Open Sea Disposal (Dedicate Sites) & Type 2- Confined Marine Disposal) disposed of in this reporting quarter.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

4.5.5.     No inert and non-inert C&D waste were disposed of for the site works in this reporting period. Details of the waste flow table are summarized in Table 4.20.

Table 4.20  Details of Waste Disposal for Contract no. HY/2009/15

Waste Type

Quantity this quarter

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Remarks

Inert C&D materials disposed, m3

NIL

141579.2

Tuen Mun Area 38

NIL

NIL

65216

TKO137 FB

NIL

Inert C&D materials recycled, m3

NIL

304

Ex-PCWA

NIL

NIL

111.9

TS4

NIL

Non-inert C&D materials disposed, m3

NIL

252.2

SENT Landfill

 

NIL

Non-inert C&D materials recycled, kg

NIL

299361.5

N/A

NIL

Chemical waste disposed, kg

NIL

8,200

N/A

NIL

Marine Sediment (Type 1 – Open Sea Disposal) , m3

NIL

156909

 (Bulk Volume)

South of Cheung Chau

Dredging from TCBR1E / TCBR1W / TCBR2/ TCBR3 / TCBR4 / Maintenance dredging

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3

NIL

322796

 (Bulk Volume)

 

East of Sha Chau

Dredging from TCBR1E / TCBR1W / TCBR2/ TCBR3 / TCBR4 / Maintenance dredging

Marine Sediment (Type 3 – Special Treatment / Disposal contained in Geosynthetic Containers)

NIL

12640

(Bulk Volume)

 

East of Sha Chau

Dredging from TCBR1W / Maintenance dredging

Marine Sediment (Type 2 – Confined Marine Disposal), m3

NIL

(Bulk Volume)

9350

(Bulk Volume)

East of Sha Chau

Dredging from Eastern Breakwater of CBTS

Marine Sediment (Type 1 – Open Sea Disposal) , m3

NIL

(Bulk Volume)

600

(Bulk Volume)

East Sha Chau / South of The Brothers

Dredging from Phase 3 Mooring Re-arrangement

Marine Sediment (Type 2– Confined Marine Disposal) , m3

NIL

(Bulk Volume)

14,780

(Bulk Volume)

South of The Brothers

Dredging from Phase 3 Mooring Re-arrangement

Marine Sediment (Type 3 – Special Treatment / Disposal contained in Geosynehetic Containers) , m3

NIL

(Bulk Volume)

2,760

(Bulk Volume)

South of The Brothers

Dredging from Phase 3 Mooring Re-arrangement

4.5.6.     There was no Marine Sediment (Type 1 – Open Sea Disposal) and no Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sties) & Type 2 – Confined Marine Disposal) disposed in this reporting quarter.

Contract no. HY/2009/19 – Central- WanChai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

4.5.7.     No Inert and non-inert C&D waste were disposed of in this reporting quarter. Details of the waste flow table are summarized in Table 4.21.

Table 4.21 Details of Waste Disposal for Contract no. HY/2009/19

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

NIL

355921.04

TM38

Inert C&D materials recycled, m3

NIL

59367

N/A

Non-inert C&D materials disposed, m3

NIL

1068.6

N/A

Non-inert C&D materials recycled, kg

NIL

333.14

N/A

Chemical waste disposed, L

NIL

2.12

N/A

Marine Sediment (Type 1 – Open Sea Disposal), m3

NIL

162

South Cheung Chau

Marine Sediment (Type 2 – Confined Marine Disposal) , m3

NIL

681

East Sha Chau

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3

NIL

4976.00

N/A

 

4.5.8.     There were no marine sediments Type1- Open Sea Disposal and there were no Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal in this reporting quarter.

Contract no. HK/2012/08 –Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West

4.5.9.     No Inert and non-inert C&D waste was disposed of in this reporting quarter. Details of the waste flow table are summarized in Table 4.22.

 

Table 4.22 Details of Waste Disposal for Contract no. HK/2012/08

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

NIL

4131

TM38

Inert C&D materials recycled, m3

NIL

NIL

N/A

Non-inert C&D materials disposed, m3 *

NIL

315

N/A

Non-inert C&D materials recycled, kg

NIL

NIL

N/A

Chemical waste disposed, L

NIL

NIL

N/A

Marine Sediment (Type 1 – Open Sea Disposal), m3 *

NIL

(Bulk volume)

31759

(Bulk volume)

South of Cheung Chau

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 *

57

(Bulk volume)

108542

(Bulk volume)

South of The Brothers (from 27 Aug 2013 onwards)

4.5.10.   No Marine Sediment (Type 1 – Open Sea Disposal) disposed in this reporting quarter. There was marine sediment Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal generated disposed in this reporting quarter.

Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)

4.5.11.   There was Inert C&D waste disposed in this reporting period. No non-inert C&D waste was disposed in this reporting period. Details of the waste flow table are summarized in Table 4.23

Table 4.23 Details of Waste Disposal for Contract no. HY/2010/08

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

9336.4

 

8210.3

18528.7

 

12179.2

TM38

 

TKO137

Inert C&D materials recycled, m3

NIL

NIL

N/A

Non-inert C&D materials disposed, m3

NIL

NIL

N/A

Non-inert C&D materials recycled, kg

NIL

NIL

N/A

Chemical waste disposed, L

NIL

NIL

N/A

Marine Sediment (Type 1 – Open Sea Disposal)

NIL

55290

South Cheung Chau

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine disposal)

NIL

27760

Brothers Island

Marine Sediment (Type 3 – Special Treatment)

NIL

7780

Brothers Island

Remarks: Contractor has clarified and updated the cumulative quantity of the Inert C&D materials disposed in this reporting quarter. Contractor has clarified and updated that no marine sediment disposal recorded in this reporting quarter.

4.5.12.   There was no Marine Sediment (Type 1 – Open Sea Disposal), Marine Sediment (Type 3 – Special Treatment) and marine sediment Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal disposed in this reporting quarter.

5.         Compliance Audit

5.0.1.     The Event Action Plan for construction noise, air quality and water quality are presented in Appendix 5.1.

5.1.          Noise Monitoring

5.1.1       Three limit level exceedances were recorded at noise monitoring station M1a – Harbour Road Sports Centre on 2, 8, and 15 March 2016 in March reporting month. The exceedances were concluded as non-project related.

5.1.2       Two limit level exceedances were recorded at noise monitoring station M1a – Harbour Road Sports Centre on 29 March 2016 and 12 April 2016 in April reporting month. The exceedances were concluded as non-project related.

5.1.3       Two limit level exceedances were recorded as noise monitoring station M6 – HK Baptist Church Henrietta Secondary School on 11 April 2016 and 19 April 2016 in April reporting month. The exceedances were concluded as non-project related.

5.1.4       Two limit level exceedances were recorded at noise monitoring station M1a – Harbour Road Sports Centre on 04 and 24 May 2016 in May reporting month. The exceedances were concluded as non-project related.

5.1.5       Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of graphical presentation can be referred in Appendix 4.1.   

 

5.2.          Air Monitoring

5.2.1       No action or limit level exceedance for TSP monitoring was recorded in March reporting month.

5.2.2       One action level exceedance of 1hr TSP monitoring was recorded at CMA5b monitoring station – Pedestrian Plaza on 14 April 2016 in April reporting month. The exceedance was concluded as non-project related.

5.2.3       No action or limit level exceedance for TSP monitoring was recorded in May reporting month.

5.3.          Water Quality Monitoring

5.3.1       There were 2 action level and 2 limit level of turbidity exceedances recorded in March reporting month. Investigation found that 2 limit level of turbidity exceedances recorded at monitoring station RW21-P789 on 9 March 2016 in March reporting month was concluded as related to Project works. Investigation found that 2 action level of the turbidity exceedances at monitoring station WSD19 recorded in March reporting month were not related to Project works.

5.3.2       There were 1 action level and 1 limit level of turbidity exceedances recorded in April reporting month. Investigation found that the exceedances recorded in April reporting month were not related to Project works.

5.3.3       There were 12 action level and 11 limit level of turbidity exceedances and 1 action level and 1 limit level of suspended solid exceedances recorded in May reporting month. Investigation found that 1 action level and 1 limit level of turbidity exceedances recorded at monitoring station C7 on 29 April 2016 in May reporting month was concluded as related to Project works.

5.3.4       Investigation found that 10 action level and 10 limit level of turbidity exceedances and 1 action level and 1 limit level of suspended solid exceedances recorded in May reporting month were not related to Project works.

5.3.5       There was no action level and 2 limit level exceedances recorded for enhanced dissolved oxygen monitoring in March reporting month. Investigation found that the exceedance was not related to Project works.

5.3.6       There was no action level and 1 limit level exceedances recorded for enhanced dissolved oxygen monitoring in April reporting month. Investigation found that the exceedance was not related to Project works.

5.3.7       There was 2 action level and 4 limit level exceedances recorded for enhanced dissolved oxygen monitoring in May reporting month. Investigation found that the exceedance was not related to Project works.

5.4.          Site Audit

5.5.1.     There was no non-compliance from the site audits in the reporting period. During environmental site inspections conducted during the reporting period, minor deficiencies were noted.

5.5.          Review of the Reasons for and the Implications of Non-compliance

5.5.1       There were 2 limit level turbidity exceedances recorded at RW21-P789 on 9 March 2016 in March reporting month. Despite no marine construction activities was conducted under Contract HK/2009/02 during the monitoring period on 9 March 2016, overflow of contaminated surface runoff into nearby waters at WCR2 site area was observed during monitoring and affecting the water quality within and outside the silt screen enclosed waterbody at RW21-P789 WQM station. As such, it was concluded that the exceedance was project related and the Contractor of HK/2009/02 was immediately advised to take immediate action to rectify the defects observed.

5.5.2       There was no non-compliances from monitoring was recorded in April reporting month.

5.5.3       There were 1 action level and 1 limit level turbidity exceedances recorded at C7 on 29 April 2016 in May reporting month. Underwater excavation works for TS3(E) temporary reclamation removal works was conducted under Contract HY/2010/08 during the monitoring period on 29 April 2016 during both flood and ebb tide and muddy dispersion was observed around at portion TS3(E ) works area during monitoring sampling at flood tide, and it was observed that the impermeable barrier deployed under Contract HY/2010/08 around the temporary reclamation removal area was not fully extended to seabed level and not fully enclosing the underwater excavation area during monitoring at both ebb and flood tides. In addition, it was observed that the outer layer of silt curtain deployed by Contract HY/2010/08 was incomplete at the concerned location. As such, it was considered that the turbidity exceedance was related to HY/2010/08 Project works and the Contractor of HY/2010/08 was immediately advised to take immediate action to rectify the defects observed.

5.6.          Summary of action taken in the event of and follow-up on non-compliance

5.6.1       Immediate repeat in-site measurement has confirmed the 2 limit level exceedances recorded at RW21-P789 on 9 March 2016 in March reporting month. The Contractor of HK/2009/02 was immediately advised to take remedial action to rectify the defects observed. Rectification measures including provision of water pump to direct the contaminated surface runoff to the nearby collection point and reinforcement of concrete bunding at the concerned location to prevent further surface runoff were implemented by the Contractor of HK/2009/02 on 9 March 2016. Additional monitoring in accordance with the Event and Action Plan was conducted on 10 March 2016. No further turbidity exceedance was recorded during the additional monitoring on 10 March 2016. Nevertheless, the contractor was reminded to maintain regular checking of the installed silt screen at WQM station RW21-P789.

5.6.2       There was no particular action taken since no project-related non-compliance was recorded in April reporting month.

5.6.3       Immediate repeat in-site measurement has confirmed the 1 action level and 1 limit level turbidity exceedances recorded at C7 on 29 April 2016 in May reporting month. The Contractor of HY/2010/08 was immediately advised to take remedial action to rectify the defects observed. Rectification measures including deployment of impermeable barriers and silt curtain to enclose the concerned works area by Contractor of HY/2010/08 was implemented on 30 April 2016 and no further turbidity exceedance was recorded during additional monitoring conducted on 30 April 2016. Nevertheless, the Contractor of HY/2010/08 was reminded to maintain regular checking of the installed silt screen at WQM station C7 for safeguarding the water quality to nearby intake.

6.         Complaints, Notification of Summons and Prosecution

6.0.1.     No environmental complaint was received in March reporting month.

6.0.2.     There was one environmental complaint received in April reporting month.

6.0.3.     The public complaint regarding muddy water discharge referred by EPD was received by ET on 13 April 2016 (EPD Ref.: H05/RS/00008367-16 dated 13 April 2016). The complainant reported that muddy water was discharged from the construction work of Contract HK/2012/08 to the sea outside the Hong Kong Academy for Performing Arts on 13 April 2016 morning.

6.0.4.     ET confirmed with the Resident Site Staff that internal transport of soil to the hopper barge for storage via landing barge was conducted by Contractor of HK/2012/08 during 0800 hours to 1000 hours on 13 April 2016 at the sea outside the concerned location and 3 nos. of dump trucks were deployed for the operation.

6.0.5.     Protection measure including provision of sandbag bunding along the side of the landing barge was implemented by the Contractor of HK/2012/08.

6.0.6.     According to the relevant site records provided by RSS, internal transport of soil to the hopper barge for storage via landing barge was conducted by Contractor of HK/2012/08 during 0800 hours to 1000 hours on 13 April 2016 at the sea outside the concerned location and 3 nos. of dump trucks were deployed for the operation. Protection measure including provision of sandbag bunding along the side of the landing barge was implemented by the Contractor of HK/2012/08. In addition, amber rainstorm warning signal was hoisted from 0630 hours to 1200 hours on 13 April 2016 and during the above time period, muddy water was observed from the upstream of culvert L outside the HK/2012/08 site.

6.0.7.     Follow up inspection was conducted on 19 April 2016, protection measures including provision of sandbag bunding along the side of the landing barge was implemented and no mud or soil deposition was observed along the seawall and no discharge point was located within the temporary water channel connecting the Culvert L outfall location to the Victoria Harbour. In addition, piling works was observed at the north side of Zone A1 on 19 April 2016 and construction effluent collection from piling work via sedimentation tank to wastewater treatment facility was implemented and steel barrier was installed around the piling works area to mitigate against potential surface runoff related impact.

6.0.8.     Nevertheless, in view of the public concern, the Contractor was reminded to maintain adequate perimeter embankment protection along the seawall boundary and maintain proper construction effluent collection system to avoid potential runoff related impact to nearby waters.

6.0.9.     No environmental complaint was received in May reporting month.

6.0.10.   The details of cumulative complaint log and summary of complaints are presented in Appendix 6.1.

6.0.11.   Cumulative statistic on complaints and successful prosecutions are summarized in Table 6.1 and Table 6.2 respectively.

Table 6.1    Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

Commencement works (Mar 2010) to last reporting quarter

44

March 2016 – May 2016

1

Project-to-Date

45

 

 

Table 6.2    Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this quarter (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Water

-

0

0

Waste

-

0

0

Total

-

0

0

 

 

 

7.      Cumulative Construction Impact due to the Concurrent Projects

7.0.1.     According to Condition 3.4 of the EP-356/2009, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III, Central-Wanchai Bypass and Island Eastern Corridor Link projects.

7.0.2.     According to the Final EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK 12/02, the major construction activities were completed by end of January 2014 and no construction activities were undertaken thereafter and the water quality monitoring was completed in October 2011 and no Project-related exceedance was recorded for air and noise monitoring.  It can be concluded that cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) was insignificant.

7.0.3.     According to the construction programme of Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III area include structural works for tunnel construction, road works and drainage works, removal of bulkhead wall and seawall modification were performed in May 2016 reporting month. As no project related exceedance were recorded during the reporting period, cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) was considered as insignificant. 

7.0.4.     According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activities under Wan Chai Development Phase II were tunnel works, D-wall construction at Wan Chai East and culvert construction, tunnel construction and ELS works at Wan Chai West. The major construction activities under Central-Wan Chai Bypass and Island Eastern Corridor Link Projects were road works at Central Interchange, backfilling works at Ex-PCWAW, ELS works and retaining wall construction at Victoria Park, ELS works and tunnel works at TS3; bridge construction, piling and tunnel works at North Point area in the reporting month. In addition, other non-Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects was observed undertaken at Wan Chai North area

7.0.5.     No significant air impact from construction activities was anticipated in the reporting month. Besides, no project related exceedance was recorded during the air and noise environmental monitoring events in the reporting month. Thus, it is evaluated that the cumulative construction impact from the concurrent projects including Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) was insignificant.

8.         Conclusion

8.0.1.     The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

8.0.2.     Two limit level of turbidity exceedances recorded at RW21-P789 on 9 March 2016 in March reporting month were concluded as related to Project works. Rectification measure was implemented by the Contractor and no further exceedance was recorded during the additional monitoring on 10 March 2016.

8.0.3.     No non-compliance was noted and no prosecution was received in April reporting month.

8.0.4.     One action level and one limit level turbidity exceedances recorded at C7 on 29 April 2016 in May reporting month were concluded as related to Project works. Rectification measure was implemented by the Contractor and no further exceedance was recorded during the additional monitoring on 30 April 2016.

8.0.5.     The construction programmes of individual contracts are provided in Appendix 8.1.