Contract No:
HK/2009/05 Wanchai Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing Work
(Stage 1) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEp-06/364/2009/a and FEp-07/364/2009/a Quarterly
Environmental Monitoring
and Audit Report
- december
2010 to february 2011 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai,
H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED
by: |
|
                         Raymond Dai Environmental Team Leader |
|
DATE: |
|
26 March 2011 |
1.1    Scope
of the Report
1.2    Structure
of the Report
2.   Project Background
2.1    Background
2.2    Scope
of the Project and Site Description
2.3    Division
of the Project Responsibility
2.4    Project
Organization and Contact Personnel
2.5    Principal
Work and Activities
3.   Monitoring Requirements
3.1.    Noise
Monitoring
3.2.    Air
Monitoring
4.   Monitoring Results
4.1.    Noise
Monitoring Results
4.2.    Real Time Noise Monitoring Results
4.3.    Air Monitoring Results
4.4.    Waste
Monitoring Results
5.1.    Noise
Monitoring
5.2.    Air
Monitoring
5.3.    Site
Audit
5.4.    Review
of the Reasons for and the Implications of Non-compliance
5.5.    Summary
of action taken in the event of and follow-up on non-compliance
6.   Complaints, Notification of Summons
and Prosecution
7.   Cumulative Construction Impact due to
the Concurrent Projects
lIST OF
TABLES
Table I        Principal Work Activities for Contract no. HY/2009/17
Table II       Principal Work Activities for Contract no. 04/HY/2006
Table III       Principal Work Activities for Contract no. HY/2009/18
Table 2.1      Schedule 2 Designated Projects under this Project
Table 2.2     Details of Individual Contracts under the Project
Table 2.3     Contact Details of Key Personnel
Table 2.4      Principal Work Activities for Contract no. HY/2009/17
Table 2.5      Principal Work Activities for Contract no. 04/HY/2006
Table 2.6      Principal Work Activities for Contract no. HY/2009/18
Table 3.1     Noise Monitoring Station
Table 3.2     Real Time Noise Monitoring Station
Table 3.2     Air Monitoring Stations
Table 4.1      Noise Monitoring Stations for Contract no. HY/2009/17
Table 4.2      Noise Monitoring Station for Contract nos. 04/HY/2006 and HY/2009/18
Table 4.3      Noise Monitoring Stations for Contract nos. HK/2009/01 and HK/2009/02
Table 4.4      Noise Monitoring Station for Contract nos. HY/2009/15
Table 4.5      Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.6     Real Time Noise Monitoring Station for Contract no. HY/2009/17
Table 4.7     Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.8      Air Monitoring Stations for Contract no. HY/2009/17
Table 4.97     Air Monitoring Stations for Contract no. 04/HY/2006 and HY/2009/18
Table 4.10     Air Monitoring Stations for Contract no. HK/2009/01
Table 4.11     Air Monitoring Station for Contract no. HK/2009/02
Table 4.12     Air Monitoring Station for Contract no. HY/2009/15
Table 4.13     Air Monitoring Stations for Contract no. HY/2009/19
Table 4.14    Details of Waste Disposal for Contract no. HY/2009/17
Table 4.15    Details of Waste Disposal for Contract no. 04/HY/2006
Table 4.16    Details of Waste Disposal for Contract no. HK/2009/01
Table 4.17    Details of Waste Disposal for Contract no. HK/2009/02
Table 4.18    Details of Waste Disposal for Contract no. HY/2009/18
Table 4.19    Details of Waste Disposal for Contract no. HY/2009/15
Table 5.20    Details of Waste Disposal for Contract no. HY/2009/19
Table 6.1     Cumulative Statistics on Complaints
Table 6.2     Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1     Project
Layout
Figure
2.2     Project
Organization Chart
Figure 3.1      Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 2.1   Environmental Mitigation Implementation
Schedule
Appendix 3.1   Action and Limit Level
Appendix 4.1   Noise Monitoring Results and Graphical
Presentations
Appendix
4.2   Real-time
Noise Monitoring Results and Graphical Presentations
Appendix 4.3   Air Quality Monitoring Results and
Graphical Presentations
Appendix 5.1   Event Action Plans
Appendix
6.1   Complaint
Log
Appendix 8.1   Construction Programme of Individual
Contracts
EXECUTIVE
SUMMARY
Contract no. HY/2009/17
- Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
Major construction activities for Contract no. HK/2009/17 have been
commenced on 5 October 2010. During this reporting period, the principal work
activities for Contract no. HY/2009/17 are summarized as below:
Table I     Principal
Work Activities for Contract no. HY/2009/17
December
2010 |
January
2011 |
February
2011 |
Piling Works |
Piling Works. |
Piling Works. |
Contract no. 04/HY/2006  /span> Reconstruction of Bus Terminus near Man Yiu Street and
Man Kwong Street under FEP-04/364/2009/A
Major construction activities for Contract no. 04/HY/2006 have been
conducted on September 2010 and were completed and Engineer’s confirmation for completion
of work is under processing in February 2011. During this reporting period, the
preparation works and principal work activities for it are summarized as below:
Table II    Principal
Work Activities for Contract no. 04/HY/2006
December 2010 |
January
2011 |
February
2011 |
Modification of bus bays
at the bus terminus
Modification of traffic
island at Man Yiu Street
Resurfacing Works at Man
Kwong Street |
Modification of bus bays
at the bus terminus
Modification of traffic
island at Man Yiu Street
Resurfacing Works at Man
Kwong Street |
Major construction
activities were completed, and Engineer’s confirmation for completion of work
is under processing |
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) - Central Interchange under
FEP-05/364/2009/A
No major construction activity was undertaken in reporting period. Only
preparation works was commenced. The preparation works for it in
this reporting periods included:
Table III    Principal
Work Activities for Contract no. HY/2009/18
December 2010 |
January
2011 |
February
2011 |
Initial record survey
Condition survey
Tree survey
Cable detection |
Condition survey /
Instrumentation Manholes Survey
Cable detection and
excavation of trial pit
Hoarding erection
Erection of CLC
Tree transplanting
Trial installation of
coupler in CR3 |
Condition survey /
Instrumentation Manholes Survey
Cable detection and
excavation of trial pit
Hoarding erection
Erection of CLC
Tree transplanting
Trial installation of
coupler in CR3 |
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre - Tunnel Works under FEP-02/364/2009
 -
No major construction activity
was undertaken in reporting period.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
 -
No major construction activity
was undertaken in reporting period.
Contract no. HY/2009/15 - Central-Wanchai Bypass  
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
 -
No major construction activity
was undertaken in reporting period.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
 -
No major construction activity
was undertaken in reporting period.
Noise Monitoring
v.24-hour real time noise
monitoring was commenced at FEHD Hong Kong Transport Section Whitefield Depot by
5 October 2010 for the pilling works in FEHD Whitfield Depot. No action and
limit level exceedances were recorded in the reporting period during normal
hour (0700 to 1900 hrs) monitoring. In contrast, exceedances were recorded scrappy
through out in December during restricted hour (1900 to 2300 hrs) and nighttime
(2300 to 0700 hrs on the other day) monitoring and five continuous Limit Level exceedances
were recorded on 4 February 2011 due to the shooting off the Lunar New Year
Fireworks. The details of exceedances can be referred to section 4.1.
Air Quality Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit
nos. FEP-01/364/2009,
FEP-02/364/2009, FEP-03/364/2009,
FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to implement the Environmental
Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual
of the approved Environmental Impact Assessment (EIA) Report for Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
and in the EM&A Manual of the approved EIA Report for Central-Wan Chai
Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring and
auditing work carried out in accordance to the Section
10.3 of EM&A Manual
and  /span>Environmental Monitoring and Audit
Requirements 
under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
during the period from 28th December
2010 to 27th February 2011.
Section 1     Introduction
 details the scope and structure of the report.
Section 2     Project
Background  summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3     Monitoring
Requirements
 summarizes all monitoring parameters, monitoring locations, monitoring
frequency, duration and action
plan.
Section 4     Monitoring
Results  summarizes the monitoring results
obtained in the reporting period.
Section 5     Compliance
Audit  summarizes the auditing of
monitoring results, all exceedances environmental parameters.
Section 6     Complaints, Notification of summons and Prosecution
 summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 7     Cumulative Construction Impact due to the
Concurrent Projects  summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section 8     Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan Chai
Bypass and “Central-Wan Chai Bypass and Island Eastern Corridor Link 
(hereafter called “the Project  are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA)
Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register
No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and
11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to
provide relief to the very congested east-west Connaught Road Central/Harcourt
Road / Gloucester Road Corridor (the Corridor) which is currently operating
beyond its capacity. The CWB will provide relief to the existing congestion
along the Corridor and cater for the anticipated growth of traffic on Hong Kong
Island. Without the CWB and its access roads, there will not be sufficient
capacity to serve the heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of
Central  Wan Chai Bypass and Island Eastern Corridor Link under the Project
involves the construction and operation of a trunk road and its road tunnel
more than 800m in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses
existing developments from Central to North Point. The scope
of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
 -
A dual three-lane trunk
road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length
defined from the connection with the existing Rumsey Street Flyover in Central,
through to a connection with the existing Island Eastern Corridor to the east
of the Causeway Bay Typhoon Shelter (CBTS);
 -
The Central Interchange
near the Rumsey Street Flyover to provide road connections to the Central area;
 -
Tunnel control buildings
and ventilation buildings;
 -
Slip roads to connect the
CWB to the local road system in the Wan Chai North and Causeway Bay area;
 -
Associated road lighting,
road signing, traffic control and surveillance system; and
 -
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1 summarises the
five individual DPs under this Project. Figure 2.1 shows the locations of these
Schedule 2 DPs.
Table 2.1   Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. 
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits such that the impact monitoring
stations are sub-divided accordingly to facilitate the implementation of
EM&A programme and to streamline the EM&A reporting for individual FEP
holders correspondingly.
2.3.2.
In the reporting period, Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under Contract no.
04/HY/2006 was commenced on September 2010 and advance piling work at FEHD
Whitfield Depot under Contract no. HY/2009/17 was commenced on 5 October 2010. The details of individual contracts
are summarized in Table2.2.
Table 2.2  Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB)  Central Interchange |
DP1 |
Anticipated to be commenced in February 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre - Tunnel Works |
DP1, DP2 |
Pending |
HK/2009/02 |
Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai
East(CWB Tunnel) (CWB Tunnel) |
DP1 |
Pending |
HY/2009/15 |
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1 |
Pending |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
Pending |
2.4.1.
Civil Engineering and
Development Department and Highways Department are the overall project
controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass
respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Lam
Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
Project Manager |
Mr. K. S. Law |
9090 1378 |
2566 7522 |
Construction Manager / Sub Agent |
Mr. Joe Tsang |
9725-5874 |
|||
Site
Agent |
Mr. Daniel Chan |
9372 0495 |
|||
Environmental Officer |
Mr. Andy Mak |
6461 3065 |
|||
Chiu Hing Construction & Transportation Co. Ltd. |
Contractor under Contract no. 04/HY/2006 |
Contract Manager |
Mr. Frederick Tsui |
2967 6363 |
2967 6366 |
Senior Site Agent |
Mr. Alvin Ma |
2967 6363 |
2967 6366 |
||
Environmental Consultant |
Mr. Jimmy Cheng |
2965 0898 |
2556 9172 |
||
Chun Wo  Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
2634 1626 |
Operation Manager |
Mr. Ho Wing Tai |
9306 1356 |
|||
Construction Manager |
Mr. David Wong |
9653 8635 |
|||
Construction Manager |
Mr. Wilson Lau |
5183 1270 |
|||
Construction Manager |
Mr. Alex Tsang |
9194 9383 |
|||
Environmental Officer
(Compliance Manager) |
Mr.Ho Wing Tai |
9306 1356 |
|||
Environmental Engineer |
Mr. Ken Yang |
9262 6791 |
|||
Chun Wo  CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Eric Lam |
3658-3048 |
|||
Deputy Site Agent |
Mr. Anthony Wu |
3658-3004 |
|||
Environmental Officer (Compliance Manager) |
Mr. Barry Leung |
3658 3031 |
|||
Environmental Engineer |
Ms. Flora Ng |
3658-3064 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
2140 6799 |
Deputy Site Agent |
Mr. Desmond Sze |
2214 7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Supervisor |
Mr. Dennis Yu |
2214 7722 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2566 2192 |
Site Agent |
Mr. Leung Kwok Yiu |
9026 8808 |
|||
Head of construction |
Mr. Simon Tang |
9022 6060 |
|||
Construction Manager |
Mr. C K Kwok |
9779 2162 |
|||
Assistant Construction Manager (East) |
Mr. Gene Cheung |
6105 4880 |
|||
Assistant Construction Manager (West) |
Mr. Tony Chiu |
9090 0606 |
|||
Section Agent (East) |
Mr. Jason Chan |
9254 1635 |
|||
Section Agent (West) |
Mr. Tang Ka Tung |
9473 4771 |
|||
Environmental Manager |
Ms. Anna Yu |
9473 1945 |
|||
Environmental Officer |
Mr Kelven Yip |
9669 5447 |
|||
Chun Wo  CRGL Joint Venture |
Contractor under Contract no. HY/2009/19 |
Pending |
Pending |
Pending |
Pending |
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
Major construction activities
for Contract no. HK/2009/17 have been commenced on 5 October 2010. During this reporting period, the
principal work activities for Contract no. HY/2009/17 are summarized in Table2.4.
Table
2.4   Principal Work Activities for Contract no.
HY/2009/17
December 2010 |
January 2011 |
February 2011 |
Piling Works. |
Piling Works. |
Piling Works. |
2.5.2.
Major construction
activities for Contract no. 04/HY/2006 have been conducted on September 2010
and were completed and Engineer’s confirmation for completion of work is under
processing in February 2011. The major construction works in the reporting
quarter are summarized in Table 2.5.
Table
2.5   Principal Work Activities for Contract no. 04/HY/2006
December 2010 |
January 2011 |
February 2011 |
Modification of bus bays
at the bus terminus
Modification of traffic
island at Man Yiu Street
Resurfacing Works at Man
Kwong Street |
Modification of bus bays
at the bus terminus
Modification of traffic
island at Man Yiu Street
Resurfacing Works at Man
Kwong Street |
All major construction
activities were completed, and Engineer’s confirmation for completion of work
is under processing |
2.5.3.
No major construction activity
was undertaken in reporting period. Only preparation works was commenced. The
preparation works in the reporting quarter are summarized in Table 2.6.
Table
2.6   Principal Work Activities for Contract no. HY/2009/18
December 2010 |
January 2011 |
February 2011 |
Initial record survey
Condition survey
Tree survey
Cable detection |
Condition survey /
Instrumentation Manholes Survey
Cable detection and
excavation of trial pit
Hoarding erection
Erection of CLC
Tree transplanting
Trial installation of
coupler in CR3 |
Condition survey / Instrumentation
Manholes Survey
Cable detection and
excavation of trial pit
Hoarding erection
Erection of CLC
Tree transplanting
Trial installation of
coupler in CR3 |
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under
FEP-02/364/2009
 -
No major construction activity
was undertaken in reporting period.
2.5.4.
Contract no. HK/2009/02 -
Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
 -
No major construction activity
was undertaken in reporting period.
2.5.5.
Contract no. HY/2009/15 - Central-Wanchai
Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
 -
No major construction activity
was undertaken in reporting period.
2.5.6.
Contract no. HY/2009/19 - Central
- Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
 -
No major construction activity
was undertaken in reporting period.
2.5.7.
Implementation status of the recommended mitigation
measures during this reporting period is presented in Appendix 2.1.
3.1.1.
The noise monitoring stations for the Project are
listed and shown in Table 3.1
and Figure 3.1.  /span>Appendix 3.1 shows the established Action/Limit
Levels for the monitoring works.
Table 3.1  Noise
Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church
Henrietta Secondary School |
M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
Real time Noise Monitoring Stations
3.1.2.
The noise monitoring stations for the Project are
listed and shown in Table 3.2 and
Figure 3.1..
Appendix 3.1
shows the established Action/Limit Levels for the monitoring works.
Table
3.2  Real
Time Noise
Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring Parameters, Frequency and Duration
3.1.3.
The construction noise level
shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes)
shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for comparison
with the Noise Control Ordinance (NCO) criteria. Supplementary information for
data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
3.1.4.
Noise monitoring shall be carried out at all
the designated monitoring stations. The monitoring frequency shall depend on
the scale of the construction activities. The following is an initial guide on
the regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
 -
One set of measurements between 0700 and 1900
hours on normal weekdays.
3.1.5.
Real time noise shall be carried out at the designated
monitoring stations. The following is an initial guide on the regular
monitoring frequency for each station on a 24 hours daily basis when noise
generating activities are underway:
 -
One set of measurements between 0700 and 1900
hours on normal weekdays.
 -
One set of measurements between 1900 and 2300
hours on normal weekdays and 0700 and 2300 hours on public holidays.
 -
One set of measurements between 2300 and 0700
hours on next day on everyday.
3.1.6.
If construction works are extended to include
works during the hours of 1900  0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
3.1.7.
As referred to in the Technical Memorandum  
issued under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring. Immediately
prior to and following each noise measurement the accuracy of the sound level
meter shall be checked using an acoustic calibrator generating a known sound
pressure level at a known frequency. Measurements may be accepted as valid only
if the calibration level from before and after the noise measurement agree to
within 1.0 dB.
3.1.8.
Noise measurements shall not be made in fog,
rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10
m/s. The wind speed shall be checked with a portable wind speed meter capable
of measuring the wind speed in m/s.
3.1.9.
The sound level meter shall be checked using
an acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit. Measurements
may be accepted as valid only if the calibration level from before and after
the noise measurement agree to within 1.0 dB.
Air Quality Monitoring Stations
3.2.1.
The air monitoring stations for the Project
are listed and shown in Table 3.2 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table 3.2  Air
Monitoring Stations
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North
Point |
CMA2a |
Causeway Bay Community Centre |
Causeway
Bay |
CMA3a |
Future CWB site office at Wanchai
Waterfront Promenade |
Causeway
Bay |
CMA4a |
Society for the Prevention of
Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds opposite to
Pedestrian Plaza |
Wan Chai |
CMA6a |
Future AECOM site office at Work
Area |
Wan Chai |
MA1e |
International
Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International
Finance Centre (Western End of Podium) |
Central |
Air Monitoring Parameters, Frequency and
Duration
3.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
3.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
3.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring
Equipment
3.2.5.
High volume samplers (HVSs) in compliance
with the following specifications shall be used for carrying out the 1-hour and
24-hour TSP monitoring:
 -
0.6 - 1.7 m3 per minute adjustable flow
range;
 -
Equipped with a timing / control device with
+/- 5 minutes accuracy for 24 hours operation;
 -
Installed with elapsed-time meter with +/- 2
minutes accuracy for 24 hours operation;
 -
Capable of providing a minimum exposed area
of 406 cm2;
 -
Flow control accuracy: +/- 2.5% deviation
over 24-hour sampling period;
 -
Equipped with a shelter to protect the filter
and sampler;
 -
Incorporated with an electronic mass flow
rate controller or other equivalent devices;
 -
Equipped with a flow recorder for continuous
monitoring;
 -
Provided with a peaked roof inlet;
 -
Incorporated with a manometer;
 -
Able to hold and seal the filter paper to the
sampler housing at horizontal position;
 -
Easily changeable filter; and
 -
Capable of operating continuously for a
24-hour period.
3.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
3.2.7.
Laboratory Measurement / Analysis
3.2.8.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
3.2.9.
Filter paper of size 8" x 10" shall
be labeled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
3.2.10. After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
3.2.11. All
the collected samples shall be kept in a good condition for 6 months before
disposal.
4.0.1.
The environmental monitoring will be
implemented based on the division of works areas of each designed project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and monitoring
stations is shown in Figure
2.1 and Figure 3.1. The monitoring results
are presented in according to the Individual Contract(s).
4.0.2.
In the reporting period, the concurrent
contracts are as follows:
Contract no. 04/HY/2006 –Reconstruction of
Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A.
Contract no. HY/2009/17 - Central - Wan Chai
Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under
FEP-03/364/2009
Contract
no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
4.1.1.
The proposed division of noise monitoring
stations for Contract no. HY/2009/17 is summarized in Table 4.1 below:
Table
4.1   Noise
Monitoring Stations for
Contract no.  /span>HY/2009/17
Station |
Description |
M4b |
Victoria Centre |
4.1.2.
No action and limit exceedance was recorded
during day time and restricted hour period in the reporting period. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Noise monitoring results measured in this reporting period are
reviewed and summarized. Details of
graphical presentation can be referred in Appendix 4.1. 
Contract no. 04/HY/2006  /span>
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and Contract no. HY/2009/18 - Central - Wan Chai
Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
4.1.3.
The commencement of major construction works
for Contract no. 04/HY/2006 by September 2010 and no major construction work
was commenced by Contract no. HY/2009/18 in the reporting period. The proposed
division of noise monitoring stations are summarized in Table 4.2 below.
Table 4.2   Noise
Monitoring Station for Contract
nos. 04/HY/2006 and HY/2009/18
Station |
Description |
M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
4.1.4.
No exceedance was recorded in the reporting
period. Noise monitoring results measured in this reporting period are reviewed and summarized. Details
of noise monitoring results and graphical presentation can be referred in Appendix 4.1. 
4.1.5.
The commencement of major construction works
for Contract no. HY/2009/18 under FEP-05/364/2009A is pending. Only
preparation works was commenced in the reporting period.
4.1.6.
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009 and Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
4.1.7.
The commencement of construction works for
Contract no. HK/2009/01 and HK/2009/02 under FEP-02/364/2009 and
FEP-01/364/2009 respectively are pending. The proposed division of air
monitoring stations are summarized in Table 4.3 below.
Table 4.3   Noise Monitoring Stations for
Contract
nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
Contract no. HY/2009/15 - Central-Wanchai Bypass  
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
4.1.8.
The commencement of construction works for Contract
no. under FEP-06/364/2009/A is pending. The proposed division of noise
monitoring stations are summarized in in Table 4.4 below.
Table 4.4   Noise
Monitoring Station for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.9.
The commencement of construction works for Contract
no. HY/2009/19 under FEP-07/364/2009/A is pending. The proposed division of
noise monitoring stations are summarized in Table 4.5 below.
Table
4.5   Noise
Monitoring Stations for Contract
no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
Contract no. HY/2009/17 –Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
and Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link 
under FEP-07/364/2009/A
4.2.1.
The proposed division of real time noise
monitoring stations are summarized in Table 4.6 below. Real time
noise monitoring for the piling works under contract no. HY/2009/17 was
commenced on 5 October 2010.
Table
4.6  Real
Time Noise Monitoring Station for Contract
no. HY/2009/17
District |
Description |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
4.2.2.
No action and limit level
exceedances were recorded in the reporting period during normal hour (0700 to
1900 hrs) monitoring. In contrast, exceedances were recorded scrappy through out
in December during restricted hour (1900 to 2300 hrs) and nighttime (2300 to
0700 hrs on the other day) monitoring and five continuous Limit Level exceedances
were recorded on 4 February 2011 due to the shooting off the Lunar New Year
Fireworks. Details
of real time noise monitoring results and graphical presentation can be
referred to Appendix 4.2
4.2.3.
The proposed division of noise monitoring
stations are summarized in Table 4.7 below. Real time noise
monitoring for major construction works under contract no. HY/2009/19 is
pending.
Table
4.7  Real
Time Noise Monitoring Stations for Contract
no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
RTN2 |
North
Point |
Oil Street Community Liaison Center |
Contract no. HY/2009/17 –Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under
FEP-03/364/2009
4.3.1.
The proposed division of air monitoring
stations are summarized in Table 4.8 below. Air monitoring for
the piling works under contract no. HY/2009/17 was commenced on 8 October 2010.
Table
4.8   Air Monitoring Stations for Contract
no. HY/2009/17
Station |
Description |
CMA2a |
Causeway Bay Community Centre |
4.3.2.
No exceedance was recorded in the reporting
period. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air
monitoring results and graphical presentation can be referred in
Appendix
4.3. 
Contract
no. 04/HY/2006  /span>
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB)  Central Interchange under
FEP-05/364/2009/A
4.3.3.
The proposed division of air monitoring
stations are summarized in Table 4.9 below.
Table
4.97 Air Monitoring Stations for Contract
no. 04/HY/2006
and HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
4.3.4.
No exceedance was recorded in the reporting
period. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air
monitoring results and graphical presentation can be referred in
Appendix 4.3. 
4.3.5.
The commencement of major construction works
for Contract no. HY/2009/18 under FEP-05/364/2009A is pending. Only
preparation works was commenced in the reporting period.
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre - Tunnel Works under FEP-02/364/2009
4.3.6.
Air quality
monitoring will be
commenced depending on the commencement of work for Contract no. HK/2009/01
under FEP-02/364/2009. The proposed division of air monitoring stations
are summarized in Table 4.10 below.
Table
4.10 Air Monitoring Stations for Contract
no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
4.3.7.
Air quality
monitoring will be
commenced depending on the commencement of work for Contract no. HK/2009/02
under FEP-01/364/2009. The proposed division of air monitoring stations
are summarized in Table 4.11 below.
Table
4.11 Air Monitoring Station for Contract
no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract
no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
4.3.8.
Air
quality monitoring will be commenced depending on
the commencement of work for Contract no. HY/2009/15 under FEP-06/364/2009/A. The proposed division of air monitoring stations are
summarized in Table 4.12 below.
Table 4.12
Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB site office at Wanchai
Waterfront Promenade |
4.3.9.
Air
quality monitoring will be commenced depending on
the commencement of work for Contract no. HY/2009/19 under FEP-07/364/2009/A. The proposed division of air monitoring stations are
summarized in Table 4.13 below.
Table
4.13 Air
Monitoring Stations for Contract
no. HY/2009/19
Station |
Description |
CMA1b |
Oil St Community Liaison Centre |
CMA2a |
Causeway Bay Community Centre |
Contract
no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
4.4.1.
Inert C&D waste was recycled in the
reporting period. Details of the waste flow table are summarized in Table
4.14
Table
4.14 Details
of Waste Disposal for
Contract no.
HY/2009/17
Waste Type |
Quantity this quarter, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping
Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
621.58 |
N/A |
|
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Contract no. 04/HY/2006  /span>
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
4.4.2.
Inert C&D waste was disposed of in this
reporting period. Details of the waste flow table are summarized in Table
4.15.
Table
4.15 Details
of Waste Disposal for Contract
no. 04/HY/2006
Inert C&D materials disposed |
152.6 |
1288.5 |
Chai
Wan and T.K.O.
137 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract
nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
4.4.3.
No inert and non-inert C&D waste was disposed
of in this reporting period. Details of the waste flow table are summarized in Table
4.16.
Table 4.16 Details of Waste Disposal for Contract no. HK/2009/01
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract
no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
4.4.4.
No inert and no-inert C&D waste was
disposed of in this reporting period. Details of the waste flow table are
summarized in Table 4.17.
Table 4.17 Details of Waste Disposal for Contract no.
HK/2009/02
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract no. HY/2009/18 -
Central - Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
4.4.5.
Non-Inert C&D waste was disposed of in
this reporting period. Details of the waste flow table are summarized in Table
4.18.
Table
4.18 Details
of Waste Disposal for Contract no. HY/2009/18
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
41.0 |
41.0 |
SENT
Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract no. HY/2009/15 - Central-Wanchai
Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
4.4.6.
No inert and no-inert C&D waste was
disposed of in this reporting period. Details of the waste flow table are
summarized in Table 4.19.
Table 4.19 Details
of Waste Disposal for Contract no. HY/2009/15
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
4.4.7.
No inert and no-inert C&D waste was
disposed of in this reporting period. Details of the waste flow table are
summarized in Table 5.20.
Table
5.20 Details
of Waste Disposal for Contract no. HY/2009/19
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
5.0.1.
The Event Action Plan for construction noise
and air quality are presented in Appendix 5.1.
Contract
no. HY/2009/17  Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
5.1.1.
No exceedance was recorded
in the reporting period.
Contract
no. 04/HY/2006  /span>
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
5.1.2.
No exceedance was recorded in the reporting
period.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  Central Interchange under
FEP-05/364/2009/A
5.1.3.
No noise monitoring was
undertaken in the reporting period.
Contract
nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre - Tunnel Works and HK/2009/02 - Wan Chai Development Phase II -
Central - Wan Chai Bypass at Wan Chai East(CWB Tunnel)
5.1.4.
No noise monitoring was
undertaken in the reporting period.
Contract no. HY/2009/15 - Central-Wanchai Bypass  
Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A
5.1.5.
No noise monitoring was
undertaken in the reporting period.
5.1.6.
No noise monitoring was
undertaken in the reporting period.
Contract
no. HY/2009/17  Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works under FEP-03/364/2009
5.2.1.
No exceedance was recorded
in the reporting period.
Contract
no. 04/HY/2006  /span>
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
5.2.2.
No exceedance was recorded in the reporting
period.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  Central Interchange under
FEP-05/364/2009/A
5.2.3.
No air quality monitoring
was undertaken in the reporting period.
Contract
nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre - Tunnel Works and HK/2009/02 - Wan Chai Development Phase II -
Central - Wan Chai Bypass at Wan Chai East(CWB Tunnel)
5.2.4.
No air quality monitoring
was undertaken in the reporting period.
Contract no. HY/2009/15 - Central-Wanchai Bypass  
Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A
5.2.5.
No air quality monitoring
was undertaken in the reporting period.
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
5.2.6.
No air quality monitoring
was undertaken in the reporting period.
Contract
no. HY/2009/17  Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under
FEP-03/364/2009
No action and limit level exceedances were recorded
in the reporting period during normal hour (0700 to 1900 hrs) monitoring. In
contrast, exceedances were recorded scrappy through out in December during
restricted hour (1900 to 2300 hrs) and nighttime (2300 to 0700 hrs on the other
day) monitoring and five continuous Limit Level exceedances were recorded on 4
February 2011 due to the shooting off the Lunar New Year Fireworks. The
exceedances were considered non-projected related.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
5.3.1.
No real time noise
monitoring was undertaken in the reporting period.
5.4.1.
There was no non-compliance from the site
audits in the reporting period. During environmental site inspections conducted
during the reporting quarter, minor deficiencies were noted. However, the Contractor rectified all
deficiencies after receipt of notification.
5.5.1.
No project-related non-compliance from
monitoring was recorded in the reporting period.
5.6.1.
There was no particular action taken since no project-related
non-compliance was recorded from the site audits and environmental monitoring
in the reporting period.
6.0.1.
No complaint was recorded in
the reporting period. 
The details of cumulative complaint log and summary of complaints are
presented in Appendix 6.1.
6.0.2.
No notification
of summons or prosecution was received in the reporting period. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
6.1 and Table 6.2 respectively.
Table 6.1  Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement
Works (Sep  Nov 2010) up to last reporting quarter |
0 |
Dec  /span>2010  Feb 2011 |
0 |
Project-to-Date |
0 |
Table 6.2  Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1.
According to Condition 3.4 of the EP-364/2009/A,
this section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation
Phase III (CRIII), Wan Chai Development Phase II (WWDII), Central-WanChai
Bypass (CWB) and Island Eastern Corridor Link projects (IECL).
7.0.2.
According to the construction programme of Wan
Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor
Link projects, the major construction activity under Wan Chai Development Phase
II was the filling works at North Point Reclamation Stage 1(NPR1), dredging
works at Wan Chai Reclamation Stage 1(WCR1), Advanced piling works at FEHD Whitfield
Depot and cross-harbour
water mains in the reporting period. The major environmental impact was water
quality impact at North Point and Wan Chai. Land-based construction activity
was only the modification works of bus terminus near Man Yiu Street and Man
Kwong Street under CWB and advance piling works at FEHD Whitfield Depot in the
reporting period.
7.0.3.
The major environmental impacts generated from
the Central Reclamation Phase III were located along the coastline of Central
and Admiralty while modification works of bus terminus near Man
Yiu Street and Man Kwong Street
under CWB and advanced piling works at FEHD Whitfield Depot were undertaken in the reporting period. No significant
air, noise impact were anticipated in the reporting period. Besides, no
environmental monitoring exceedance was recorded from the Project in the
reporting period. Thus, it is evaluated
that the cumulative construction impact from the concurrent projects including
Wan Chai Development Phase II and Central Reclamation Phase III was insignificant.
8.0.1.
The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
8.0.2.
No exceedance, non-compliances were noted and
no prosecutions were received during the reporting quarter.
8.0.3.
Major construction works for Contract no.
04/HY/2006 were completed in February 2011 and Engineer’s confirmation
for completion of work is under processing in this reporting period.
8.0.4.
The construction programmes of individual contracts
are provided in
Appendix 8.1.